PROPOSED

CABLE STACKING
FOR EXPRESSWAY PROJECTS

20 August 2015

PROPOSED CABLE STACKING


FOR
EXPRESSWAY PROGRAMME

CONTENTS

1. INTRODUCTION
2. UNDERGROUND INSTALLATION METHODS
3. CABLE STACKING
4. MAINTENANCE
5. CONSTRUCTION
6. FUTURE SUBSTATION
7. CURRENT CARRYING CAPACITY
8. CABLE PULLING
9. COST AND TIME
10.INSTALLATION REFERENCES
2

PROPOSED CABLE STACKING


FOR
EXPRESSWAY PROGRAMME

PROPOSED CABLE STACKING


FOR
EXPRESSWAY PROGRAMME

CORRIDOR ISSUES: BASIS FOR


CABLE STACKING
.
.
.

LIMITED CORRIDOR SPACE AVAILABLE


LARGE NUMBER OF CIRCUITS TO DIVERT /
ROUTE WITHIN THE AVAILABLE CORRIDOR
MMUP ADVISED THAT NO FURTHER
LANDTAKE WILL BE APPROVED

PROPOSED CABLE STACKING


FOR
EXPRESSWAY PROGRAMME
RAS ABU ABOUD STREET
REQUIRED CORRIDOR = 13.5 m
AVAILABLE CORRIDOR = 2.7 m
K
AL

D
U ABOU
RAS AB ET
STRE
L= 225 m

S
EJ
LE
HA

L= 210 m

E
TR

A RING ROAD

ET
AL

L= 2900 m

AL M
UNT
AZA
H

A
LW
A
S

AD
RO

S TR
EET

L= 2850 m

B RING ROAD

M
AT
AR

B RING ROAD
REQUIRED CORRIDOR = 12.5 m
AVAILABLE CORRIDOR = 2.5 m

ST
RE

ET

CORRIDOR CONSTRAINS
5

PROPOSED CABLE STACKING


FOR
EXPRESSWAY PROGRAMME

2.1 OPTIONS AT CONSTRAINT AREAS

CABLE STACKING

CABLE TUNNEL via CUT & COVER

CABLE TUNNEL via TBM


6

PROPOSED CABLE STACKING


FOR
EXPRESSWAY PROGRAMME

.2 UNDERGROUND INSTALLATION METHO


METHOD

CAUSE

1. DIRECT BURIED

INADEQUATE UTILITY CORRIDOR AT FEW


AREAS

2. CABLE STACKING

SIMPLE CONSTRUCTION
LESS EXPENSIVE
NO RUNNING COST
MINIMUM MAINTENANCE REQUIRED

REQUIRED REGULAR MAINTENANCE


3. CABLE TUNNEL
- CUT AND COVER REQUIRES ADDITIONAL LAND TAKE FOR
UTILITY BUILDINGS AND VENTILLATION SHAFTS
EXPENSIVE
4. CABLE TUNNEL
- TBM

MOST EXPENSIVE AMONG OPTIONS


REQUIRED REGULAR MAINTENANCE
REQUIRES ADDITIONAL LAND TAKE FOR
UTILITY BUILDINGS AND VENTILLATION SHAFTS
7

PROPOSED CABLE STACKING


FOR
EXPRESSWAY PROGRAMME

3) CABLE STACKING

CABLE ARRANGEMENTS IN DUCT BAN


3150

PROPOSED CABLE STACKING


FOR
EXPRESSWAY PROGRAMME
3.1) CABLE STACKING

YPICAL DUCT ARRANGEMENT

SEPARATE UPVC DUCTS FOR EVERY CABLE


SPACING BETWEEN DUCTS HAVE BEEN
DERIVED UPON THE SIMULATION RESULTS
3150

PROPOSED CABLE STACKING


FOR
EXPRESSWAY PROGRAMME

3.2) SAFETY AND RELIABILITY

DEDICATED ACCESS
FOR EVERY SYSTEM VOLTAGES
LV ACCESS CHAMBER
MV ACCESS CHAMBER
HV ACCESS CHAMBER
EHV ACCESS CHAMBER

10

PROPOSED CABLE STACKING


FOR
EXPRESSWAY PROGRAMME
3.3) SAFETY AND RELIABILITY

LV ACCESS CHAMBER
- MAINTENANCE AND MATERIAL ACCESS

11

PROPOSED CABLE STACKING


FOR
EXPRESSWAY PROGRAMME
3.3) SAFETY AND RELIABILITY

LV CHAMBER
2.3m

12

PROPOSED CABLE STACKING


FOR
EXPRESSWAY PROGRAMME
3.4) SAFETY AND RELIABILITY

MV ACCESS CHAMBER
- MAINTENANCE AND MATERIAL ACCESS

13

PROPOSED CABLE STACKING


FOR
EXPRESSWAY PROGRAMME
3.4) SAFETY AND RELIABILITY

MV CHAMBER

14

PROPOSED CABLE STACKING


FOR
EXPRESSWAY PROGRAMME
3.5) SAFETY AND RELIABILITY

HV ACCESS CHAMBER

UPPER CONFIGURATI

MAINTENANCE AND MATERIAL ACCESS

15

PROPOSED CABLE STACKING


FOR
EXPRESSWAY PROGRAMME
3.5) SAFETY AND RELIABILITY

EHV CHAMBER
- UPPER CONFIGURATION

16

PROPOSED CABLE STACKING


FOR
EXPRESSWAY PROGRAMME
3.6) SAFETY AND RELIABILITY

EHV ACCESS CHAMBER

DOWN CONFIGURATIO

MAINTENANCE AND MATERIAL ACCESS

17

PROPOSED CABLE STACKING


FOR
EXPRESSWAY PROGRAMME
3.6) SAFETY AND RELIABILITY

EHV CHAMBER
- DOWN CONFIGURATION

18

PROPOSED CABLE STACKING


FOR
EXPRESSWAY PROGRAMME

3.7) SUSTAINABLE DESIGN

80 YEARS OF RESOLUTION
40 YEARS OF LIFE SPAN
FOR THE INSTALLED CABLES
SPARE FOR 41 TO 80 YEARS

ECO FRIENDLY
REDUCED CARBON FOOTAGES
- NO MEP EQUIPMENTS
DIESEL GENERATOR, MOTORS,..
19

PROPOSED CABLE STACKING


FOR
EXPRESSWAY PROGRAMME
3.7) SUSTAINABLE DESIGN

ECO FRIENDLY

SOFT LANDSCAPING POSIBILITY


- TO REDUCE URBAN HEAT RADIATIONS
- IMPROVED AIR QUALITY
AND LOWER GREENHOUSE EMISSIONS

20

PROPOSED CABLE STACKING


FOR
EXPRESSWAY PROGRAMME
3.8) SAFETY AND RELIABILITY

NO MECHANICAL EQUIPMENTS

JUMBO JET FAN, SMOKE EXTRACT FAN


FIRE PUMP
CHILLER
DIESEL GENERATOR
MOTOR

21

PROPOSED CABLE STACKING


FOR
EXPRESSWAY PROGRAMME
3.8) SUSTAINABLE DESIGN

SAVE EARTH - ENERGY SAVINGS

SAVE LIGHTING ENERGY


WATER (e.g., FIRE WATER, PIPING)
FUEL (e.g., STANDBY DIESEL GENERATO
KEEP THE ENVIRONMENT COOL (HEAT F
FANS)
POWER CONSUMPTION

22

PROPOSED CABLE STACKING


FOR
EXPRESSWAY PROGRAMME
3.9) SAFETY AND RELIABILITY

AZARDOUS

IN CASE OF FIRE IN A DUCT, THERE WILL


BE NO CHANCE TO SPREAD OR DAMAGE
THE OTHER CABLES

CONCRETE ENCASEMENT EFFECTIVELY


PROTECTS THE CABLE DURING THE
GROUND MOVEMENT
23

PROPOSED CABLE STACKING


FOR
EXPRESSWAY PROGRAMME

4) MAINTENANCE

AINTAINABILITY
LIGHT MAINTENANCE FOR CHAMBERS
NO MAINTENANCE FOR DUCT BANKS

O PERIODIC MAINTENANCE
SAVE REQULAR / ANNUAL MAINT. CONTRAC

UTURE CABLE INSTALLATION


NO EXCAVATION IS REQUIRED

24

PROPOSED CABLE STACKING


FOR
EXPRESSWAY PROGRAMME

5) CONSTRUCTION
CONSTRUCTABILITY
NO SPECIALIZED CONTRACTOR FOR
CIVIL WORKS CONSTRUCTION

NO MOBILIZATION PERIOD
(APPROX. 12 MONTHS) FOR SPECIA
MACHINERY IS REQUIRED

25

PROPOSED CABLE STACKING


FOR
EXPRESSWAY PROGRAMME

6) FUTURE SUBSTATION

DIRECTLY BURIED CABLING POSSIBI


FUTURE
SUBSTATION

FUTURE
SUBSTATION
26

PROPOSED CABLE STACKING


FOR
EXPRESSWAY PROGRAMME

6) FUTURE SUBSTATION

ROAD CROSSINGS AND FUTURE POSSIBI

27

PROPOSED CABLE STACKING


FOR
EXPRESSWAY PROGRAMME

6) FUTURE SUBSTATION

UTURE MV CONNECTION FROM EXISTING

28

PROPOSED CABLE STACKING


FOR
EXPRESSWAY PROGRAMME

6) FUTURE SUBSTATION

DIRECTLY BURIED CABLING POSSIBI

29

PROPOSED CABLE STACKING


FOR
EXPRESSWAY PROGRAMME

7) AMPACITY CALCULATIONS
RESULTS OF CALCULATION
FROM AN APPROVED
KAHRAMAA CONTRACTOR
CABLE DETAILS

AMPACITY REQUIRED

AMPACITY OFFERED

220 KV 2500 SQ.MM

515 MVA

531 MVA

220 KV 1600 SQ.MM

315 MVA

315 MVA

66 KV 400 SQ.MM

40 MVA

40 MVA

11 KV 240 SQ.MM

6.5 MVA

6.5 MVA

MAXIMUM CONDUCTOR TEMPERATURE 86.76 C


WHEN 4 CIRCUITS OPERATING AT 100% LOAD, OUTSIDE TEMP. AT SHAFT IS 58C
30

PROPOSED CABLE STACKING


FOR
EXPRESSWAY PROGRAMME

8) CABLE PULLING CALCULATION

RESULTS OF CALCULATION FROM AN


APPROVED KAHRAMAA CONTRACTOR

LENGTH OF 650 M

31

PROPOSED CABLE STACKING


FOR
EXPRESSWAY PROGRAMME

9) COST AND TIME

TYPE
CABLE STACKING

CABLE TUNNEL
- CUT AND COVER

CABLE TUNNEL
- TBM

INITIAL COST
370,000,000.00 QR
- THREE HUNDRED
AND SEVENTY
MILLION
740,000,000.00 QR
- SEVEN HUNDRED
AND FORTY
MILLION
1,200,000,000.00 QR
- 1.2 BILLION

CONST. TIME
24 MONTHS

LCC
NO RUNNING
COST

36 MONTHS

RUNNING
COST TO BE
ADDED

48 MONTHS

RUNNING
COST TO BE
ADDED

TOTAL LENGTH = 6 KM
32

PROPOSED CABLE STACKING


FOR
EXPRESSWAY PROGRAMME

10) INSTALLATION REFERENCES

@ KOREA

33

PROPOSED CABLE STACKING


FOR
EXPRESSWAY PROGRAMME

10) INSTALLATION REFERENCES

@ KOREA

34

PROPOSED CABLE STACKING


FOR
EXPRESSWAY PROGRAMME

10) INSTALLATION SAMPLES

EXAMPLE OF CABLE ARRANGEMENT IN EHV / HV ACCESS CHAMBERS


35

PROPOSED CABLE STACKING


FOR
EXPRESSWAY PROGRAMME

10) INSTALLATION SAMPLES

TRENCHING

DUCTS

36

PROPOSED CABLE STACKING


FOR
EXPRESSWAY PROGRAMME

10) INSTALLATION SAMPLES

PRECAST ACCESS CHAMBER

37

PROPOSED CABLE STACKING


FOR
EXPRESSWAY PROGRAMME

10) INSTALLATION SAMPLES

38

PROPOSED CABLE STACKING


FOR
EXPRESSWAY PROGRAMME

10) INSTALLATION SAMPLES

PRECAST DUCT BANK

PRECAST ACCESS SHAFTS


39

PROPOSED CABLE STACKING


FOR
EXPRESSWAY PROGRAMME

10) INSTALLATION SAMPLES

DUCTILE IRON HEAVY DUTY COVER


AND FRAME - WATER TIGHT

CONCRETE COVER SLAB

40

PROPOSED CABLE STACKING


FOR
EXPRESSWAY PROGRAMME

10) INSTALLATION REFERENCES

CABLE ENTRIES IN ACCESS CHAMBERS

41

PROPOSED CABLE STACKING


FOR
EXPRESSWAY PROGRAMME

42

43