IT PROJECT MANAGEMENT

Resource Plan and Cost Estimation


Institute of Information and Communication Technology
University of Sindh, Jamshoro

Dr. Zeeshan Bhatti


MPhil (IT)
Chapter 4
BY: DR. ZEESHAN BHATTI

Roadmap to Project Management Success


Statement
of Work
Form
Project
Team

Purpose

Work
Breakdown
Structure

Responsibility
Matrix
R

Project Background

A
S

Resource
Plan

Budget

Resource
Plan

A
Project Deliverables

Gantt

Network

TIME

PROJE
CT

Perform
Tasks

LEADERSHIP

AR
NED

S
RE

EN

LE

PO
RT

Track
Progress

SO

LES
EOS
CL

COMMUNICATION

O
UT

Evaluate
Success

ME

S
I NG

Conduct
Close-Out
Meeting

Share
Lessons
Learned

BOOK
E
T

ET

PLAN

E
L
IM P

Update
Plan

Resolve
Issues

BY: DR. ZEESHAN BHATTI

Manage
Change

ASSIGNING RESOURCES
A schedule is not complete until all the resources necessary to complete
the project have been committed or assigned.

BY: DR. ZEESHAN BHATTI

NON-LABOR RESOURCES
Lab time
Facilities

Prototype parts/systems
Equipment
Materials
Roadmap to Project Management Success
Statement
of Work
Form
Project
Team

Purpose

Work
Breakdown
Structure

Responsibility
Matrix
R

Project Background

Resource
Plan

Resource
Plan

Gantt

Network

A
A

Project Deliverables
R

Budget

TIME

Track
Progress

P
OR
T

RE

EN

LE
IM P

SO

E
OS
CL

COMMUNICATION

O EARNED
UT

Evaluate
Success

Perform
Tasks

LEADERSHIP

LES

Share
Lessons
Learned

ME

GS

Conduct
Close-Out
Meeting

OK
EB O

IN

PROJE
CT

OT

ET

PLAN

Update
Plan

Resolve
Issues

Manage
Change

BY: DR. ZEESHAN BHATTI

WHERE WE ARE NOW

85

BY: DR. ZEESHAN BHATTI

THE RESOURCE PROBLEM

Resources and Priorities

Project network times are not a schedule


until resources have been assigned.
The implicit assumption is that resources will be available in the required amounts when needed.
Adding new projects requires making realistic judgments of resource availability and project durations.

Cost estimates are not a budget


until they have been time-phased.

86

BY: DR. ZEESHAN BHATTI

THE RESOURCE PROBLEM (CONTD)


Resource Smoothing (or Leveling)
Involves attempting to even out varying demands
on resources by using slack (delaying noncritical activities) to manage resource
utilization when resources are adequate over the life of the project.

Resource-Constrained Scheduling
The duration of a project may be increased by delaying the late start of some of its
activities if resources are not adequate to meet peak demands.

87

BY: DR. ZEESHAN BHATTI

TYPES OF PROJECT CONSTRAINTS

Technical or Logic Constraints

Constraints related to the networked sequence


in which project activities must occur.

Physical Constraints
Activities that cannot occur in parallel or are affected by contractual or
environmental conditions.

Resource Constraints
The absence, shortage, or unique interrelationship and interaction
characteristics of resources that require a particular sequencing of project
activities

Kinds of Resource Constraints


People, materials, equipment

88

BY: DR. ZEESHAN BHATTI

CONSTRAINT EXAMPLES

FIGURE 8.2
89

BY: DR. ZEESHAN BHATTI

CLASSIFICATION OF A SCHEDULING
PROBLEM
Classification of Problem
Using a priority matrix will help determine if
the project is time or resource constrained.

Time-Constrained Project
Must be completed by an imposed date.
Time is fixed, resources are flexible: additional resources are required to ensure project meets schedule.

Resource-Constrained Project
Is one in which the level of resources available cannot be exceeded.
Resources are fixed, time is flexible: inadequate resources
will delay the project.

810

BY: DR. ZEESHAN BHATTI

RESOURCE ALLOCATION METHODS

Limiting Assumptions

Splitting activities is not allowedonce an activity is start, it is carried to completion.


Level of resources used for an activity cannot be changed.

Risk Assumptions
Activities with the most slack pose the least risk.
Reduction of flexibility does not increase risk.
The nature of an activity (easy, complex) doesnt increase risk.

811

BY: DR. ZEESHAN BHATTI

RESOURCE ALLOCATION METHODS (CONTD)


Time-Constrained Projects
Must be completed by an imposed date.
Require use of leveling techniques that focus
on balancing or smoothing resource demands.
Use positive slack (delaying noncritical activities) to manage resource utilization over the
duration
of the project.
Peak resource demands are reduced.
Resources over the life of the project are reduced.
Fluctuation in resource demand is minimized.

812

BY: DR. ZEESHAN BHATTI

RESOURCE ALLOCATION METHODS (CONTD)


Resource Demand Leveling Techniques
for Time-Constrained Projects
Advantages

Peak resource demands are reduced.


Resources over the life of the project are reduced.
Fluctuation in resource demand is minimized.
Disadvantages

Loss of flexibility that occurs from reducing slack.


Increases in the criticality of all activities.

813

BY: DR. ZEESHAN BHATTI

RESOURCE ALLOCATION METHODS (CONTD)


Resource-Constrained Projects

Resources are limited in quantity or availability.

Activities are scheduled using heuristics


(rules-of-thumb) that focus on:

1.

Minimum slack

2.

Smallest (least) duration

3.

Lowest activity identification number

The parallel method is used to apply heuristics

814

An iterative process starting at the first time period


of the project and scheduling period-by-period the start of any activities using the three priority rules.

BY: DR. ZEESHAN BHATTI

Roadmap to Project Management Success


Statement
of Work
Form
Project
Team

Purpose

Work
Breakdown
Structure

Responsibility
Matrix
R

Project Background

Resource
Plan

Gantt

Network

Budget

A
A

Project Deliverables

Budget

TIME

PROJE
CT

Perform
Tasks

LEADERSHIP

AR
NED

S
RE

EN

LE

PO
RT

Track
Progress

TIME

SO

LES
EOS
CL

COMMUNICATION

O
UT

Evaluate
Success

ME

S
I NG

Conduct
Close-Out
Meeting

Share
Lessons
Learned

BOOK
E
T

ET

PLAN

E
L
IM P

Update
Plan

Resolve
Issues

BY: DR. ZEESHAN BHATTI

Manage
Change

15

WHERE WE ARE NOW

BY: DR. ZEESHAN BHATTI

516

COST BUDGETING
Cost Budgeting involves allocating overall cost
estimates to individual work items in order to
establish a cost baseline for measuring project
performance. Using cost estimates, the WBS, the
project schedule, and cost estimating tools, the
project team develops a time-phased budget.
This budget will be used to measure and monitor
cost performance on the project.
Source: PMI
BY: DR. ZEESHAN BHATTI

17

ESTIMATING PROJECTS
Estimating
The process of forecasting or approximating the time and cost of completing project
deliverables.
The task of balancing expectations of stakeholders and need for control while the
project is implemented.

Types of Estimates
Top-down (macro) estimates: analogy, group consensus, or mathematical relationships
Bottom-up (micro) estimates: estimates of elements
of the work breakdown structure

BY: DR. ZEESHAN BHATTI

518

WHY ESTIMATING TIME AND COST ARE IMPORTANT


To support good decisions.
To schedule work.
To determine how long the project should take
and its cost.

To determine whether the project is worth doing.


To develop cash flow needs.
To determine how well the project is progressing.
To develop time-phased budgets and establish the
project baseline.
EXHIBIT 5.1
BY: DR. ZEESHAN BHATTI

519

FACTORS INFLUENCING THE QUALITY OF


ESTIMATES
Planning Horizon

Other
(Nonproject)
Factors

Organization
Culture

Padding
Estimates

Project
Duration

Quality of
Estimates

People

Project Structure
and Organization

BY: DR. ZEESHAN BHATTI

520

ESTIMATING GUIDELINES FOR TIMES,


COSTS, AND RESOURCES
1. Have people familiar with the tasks make the estimate.
2. Use several people to make estimates.
3. Base estimates on normal conditions, efficient methods, and a
normal level of resources.
4. Use consistent time units in estimating task times.
5. Treat each task as independent, dont aggregate.
6. Dont make allowances for contingencies.
7. Adding a risk assessment helps avoid surprises
to stakeholders.
BY: DR. ZEESHAN BHATTI

521

TOP-DOWN VERSUS BOTTOM-UP ESTIMATING

Top-Down Estimates
Are usually are derived from someone who uses experience and/or information to
determine the project duration and total cost.

Are made by top managers who have little knowledge of the processes used to
complete the project.

Bottom-Up Approach
Can serve as a check on cost elements in the WBS
by rolling up the work packages and associated cost accounts to major deliverables
at the work package level.

BY: DR. ZEESHAN BHATTI

522

TOP-DOWN VERSUS BOTTOM-UP


Conditions
for Preferring Top-Down or Bottom-up Time and
ESTIMATING
Cost Estimates

Condition
Strategic decision making

Macro Estimates

Micro Estimates

Cost and time important

High uncertainty

Internal, small project

Fixed-price contract

Customer wants details

Unstable scope

TABLE 5.1
BY: DR. ZEESHAN BHATTI

523

ESTIMATING PROJECTS: PREFERRED


APPROACH
Make
rough top-down estimates.
Develop the WBS/OBS.
Make bottom-up estimates.
Develop schedules and budgets.
Reconcile differences between top-down
and bottom-up estimates

BY: DR. ZEESHAN BHATTI

524

TOP-DOWN APPROACHES FOR ESTIMATING


PROJECT TIMES AND COSTS
Consensus methods
Ratio methods
Apportion method

Function point methods for software and system


projects
Learning curves

Project Estimate
Times
Costs

BY: DR. ZEESHAN BHATTI

525

APPORTION METHOD OF ALLOCATING PROJECT COSTS USING THE


WORK BREAKDOWN STRUCTURE

FIGURE 5.1
BY: DR. ZEESHAN BHATTI

526

SIMPLIFIED BASIC FUNCTION POINT COUNT PROCESS


FOR A PROSPECTIVE PROJECT OR DELIVERABLE

TABLE 5.2
BY: DR. ZEESHAN BHATTI

527

EXAMPLE: FUNCTION POINT COUNT METHOD

TABLE 5.3
BY: DR. ZEESHAN BHATTI

528

BOTTOM-UP APPROACHES FOR ESTIMATING


PROJECT TIMES AND COSTS
Template methods
Parametric procedures applied to specific
tasks

Range estimates for


the WBS work packages
Phase estimating: A hybrid

BY: DR. ZEESHAN BHATTI

529

SUPPORT COST ESTIMATE WORKSHEET

FIGURE 5.2
BY: DR. ZEESHAN BHATTI

530

PHASE ESTIMATING OVER PRODUCT LIFE CYCLE

FIGURE 5.3
BY: DR. ZEESHAN BHATTI

531

TOP-DOWN AND BOTTOM-UP ESTIMATES

FIGURE 5.4
BY: DR. ZEESHAN BHATTI

532

LEVEL OF DETAIL
Level of detail is different for
different levels of management.
Level of detail in the WBS varies
with the complexity of the project.
Excessive detail is costly.
Fosters a focus on departmental outcomes

Creates unproductive paperwork

Insufficient detail is costly.


Lack of focus on goals
Wasted effort on nonessential activities

BY: DR. ZEESHAN BHATTI

533

TYPES OF COSTS
Direct Costs
Costs that are clearly chargeable
to a specific work package.
Labor, materials, equipment, and other

Direct (Project) Overhead Costs


Costs incurred that are directly tied to an identifiable project deliverable or work
package.
Salary, rents, supplies, specialized machinery

General and Administrative Overhead Costs


Organization costs indirectly linked to a specific package that are apportioned to the
project

BY: DR. ZEESHAN BHATTI

534

CONTRACT BID SUMMARY COSTS

Direct costs
Direct overhead
Total direct costs
G&A overhead (20%)
Total costs
Profit (20%)
Total bid

$80,000
$20,000
$100,000
$20,000
$120,000
$24,000
$144,000

FIGURE 5.5
BY: DR. ZEESHAN BHATTI

535

THREE VIEWS OF COST

FIGURE 5.6
BY: DR. ZEESHAN BHATTI

536

REFINING ESTIMATES
Reasons for Adjusting Estimates
Interaction costs are hidden in estimates.
Normal conditions do not apply.
Things go wrong on projects.
Changes in project scope and plans.

Adjusting Estimates
Time and cost estimates of specific activities are adjusted as the risks, resources, and
situation particulars become more clearly defined.

BY: DR. ZEESHAN BHATTI

537

CREATING A DATABASE FOR ESTIMATING

FIGURE 5.7
BY: DR. ZEESHAN BHATTI

538

KEY TERMS

Apportionment methods
Bottom-up estimates
Contingency funds
Delphi method
Direct costs
Function points
Learning curves

Overhead costs
Padding estimates
Phase estimating
Range estimating
Ratio methods
Template method
Time and cost databases

BY: DR. ZEESHAN BHATTI

539

WBS FIGURE

TABLE 5.4
BY: DR. ZEESHAN BHATTI

540

Roadmap to Project Management Success


Statement
of Work
Form
Project
Team

Purpose

Work
Breakdown
Structure

Responsibility
Matrix
R

Project Background

Gantt

Network

Resource
Plan

Budget

A
A

Project Deliverables

S
R

TIME

PROJE
CT

Perform
Tasks

LEADERSHIP

AR
NED

S
RE

EN

LE

PO
RT

Track
Progress

SO

LES
EOS
CL

COMMUNICATION

O
UT

Evaluate
Success

ME

S
I NG

Conduct
Close-Out
Meeting

Share
Lessons
Learned

BOOK
E
T

ET

PLAN

E
L
IM P

Update
Plan

Resolve
Issues

BY: DR. ZEESHAN BHATTI

Manage
Change

41

Roadmap to Project Management Success


Statement
of Work
Form
Project
Team

Purpose

Work
Breakdown
Structure

Responsibility
Matrix
R

Project Background

Gantt

Network

Resource
Plan

Budget

A
A

Project Deliverables

S
R

TIME

PROJE
CT

Perform
Tasks

LEADERSHIP

AR
NED

S
RE

EN

LE

PO
RT

Track
Progress

SO

LES
EOS
CL

COMMUNICATION

O
UT

Evaluate
Success

ME

S
I NG

Conduct
Close-Out
Meeting

Share
Lessons
Learned

BOOK
E
T

ET

PLAN

E
L
IM P

Update
Plan

Resolve
Issues

BY: DR. ZEESHAN BHATTI

Manage
Change

42

REFERRED NOTES

REFERRED BOOK

A Short Course in Project


Management, by Nayda G.
Santiago

BY: DR. ZEESHAN BHATTI

43

THANKYOU

Q&A
For Course Slides and Handouts
Blog:

http://zeeshanacademy.blogspot.com/
Facebook:

https://www.facebook.com/drzeeshanacademy

BY: DR. ZEESHAN BHATTI