POWER PLANT
SURVEY REPORT
Al-Falah University
Ref: SEI/SPV/50/01/180516
Dear Sir,
Sub: Survey report for 50KWp Roof Top Solar Power Plant
We enclose the following documents for your kind consideration and reference.
1. Executive summary
2. Benefits of the projects
3. Details of the Projects
4. Expected Annual Energy Generation
5. Technical specification and bill of materials
6. Block diagram of the power plant
7. Scope of work
a. Design work
b. Installation work
8. Clint Scope
Email: soralitepower@gmail.com
1. Executive Summary
Al-Falah University is an endeavour of Al-Falah Charitable Trust, in keeping up with its
tradition of fostering professional education, training and guidance. Spread over 56 acres of
lush greenery, Al-Falah University offers world-class education to students from India and other
countries by providing a learning experience designed to develop intellectual abilities as well as
good social, moral and ethical values. The university is committed to providing a rigorous
academic environment to equip students with knowledge, skills, insights, attitudes and practical
experience in order to enable them to become discerning citizens.
The emphasis by the university is placed on nurturing talent by providing need-based
education to create a resource pool for developing cutting edge technologies for the benefit of
the country. We believe that this pool of immense talent would enrich the national fabric and
shall act as a driving force for transforming India into a great nation. Our curricula and teaching
methods are rigorous, innovative and distinctly oriented towards competitiveness, keeping an
eye on global environment of business, industry and academia. A distinct feature of our
academic programme is the focus on the industrial needs of the country.
India is endowed with vast solar energy potential. About 5,000 trillion kWh per year
energy is incident over Indias land area with most parts receiving 4-7 kWh per sq. m per day.
Hence both technology routes for conversion of solar radiation into heat and electricity, namely,
solar thermal and solar photovoltaics, can effectively be harnessed providing huge scalability
for solar in India.
Email: soralitepower@gmail.com
The Project will provide green solar power to the university and will share the load
requirements in synchronization with the Grid.
Directly, the project is expected to generate around 67,110 Units and reduce the Electricity
Charges incurred by the Beneficiary Organization and also the diesel consumption.
We can avoid the 40.06 tons1 of the CO2 by using of this power plant in a year.
Email: soralitepower@gmail.com
Months
Units Generated
January
5250
February
5400
March
5550
April
6000
May
6000
June
6000
July
5940
August
5925
September
5745
October
5400
November
5100
December
4800
Yearly
67,110
Note: Energy production projections are reasonably accurate estimates based on sites solar
data and our experience with similar systems. No guarantees as to actual production output
from this system.
Grid/Load Interfacing
Solar system output shall be connected to a suitable load bus capable of taking the input. This
input point shall be selected in field in consultation with clients Executive Engineer.
Email: soralitepower@gmail.com
Description
a
Solar Panels
System Components
Details
b
Quantity: 200
Wattage: 250Wp / 260Wp
No. of Cells: 60
Voc: 37.1 V
Isc: 8.28 A
Vmp: 29.6 V
Imp: 7.6 A
Dimensions: 1660X990X42 (mm)
Weight: 20 kg
Operating Conditions: -40 to +90 C
Maximum System Voltage: 1000 Vdc
Inverter
Quantity: 1 or 2
AC maximum output: 50 KWp
MPP voltage range : 360 800 V
Maximum current input DC/String : 15A
Maximum efficiency : >98.1%
Power connection : 3-phase
Remark
c
As per Clint
requirement
Accurate degree of
inclined of the solar
module will be
design after survey
of site and collected
the cordinated of the
site.
Email: soralitepower@gmail.com
Foundation Base
Electrical Accessories
Battery
None
Energy Meter
Remote Monitoring
System
The
remote
monitoring
system Optional
continuously records and stores all
available data of number of inverters in
real time.
Email: soralitepower@gmail.com
DESCRIPTION OF ITEM
Unit
Nos
2.0
Nos.
2.1
Nos.
2.2
Weather sensor
Nos.
2.3
Irradiation sensor
Nos.
AJB
Nos
3
4
5
6
7
QTY.
Remark
200.00
1.00
1.00
1.00
1.00
Optional
Optional
2.00
mtr.
As per design
Set
As per design
Mtr
As per design
set
Connectors
Nos.
ACDB
Nos.
10
Lot
11
Mtr.
12
Cable tray
Mtr.
13
Lightning arrester
set
7.00
As per design
1.00
As per design
As per structure
design
10.00
1.00
Note:
a. Sensors are the optional we can avoid to be use these devise.
b. Lightning arrester can also be avoided in case of already having lightning arrester on the
building and cover the entire area of roof where we plan to install the solar modules.
Email: soralitepower@gmail.com
Email: soralitepower@gmail.com
7. Scope of wok
1. Design Work
10
Email: soralitepower@gmail.com
11
Email: soralitepower@gmail.com
c. Electrical Design: i.
ii.
iii.
iv.
12
Email: soralitepower@gmail.com
13
Email: soralitepower@gmail.com
Note: Fig 4, 5, 6 &7 are the PVsyst Software Reports only for your
references.
14
Email: soralitepower@gmail.com
2. Installation Work
a. Area required: The total area required for the system installation shall be
apx 500 600 Sq meter, without any shades, true south facing.
b. Structure Anchoring: Panels shall be mounted on galvanized frames
inclined at 28 degrees to the south. The structure is designed in such a
manner that module can be replaced easily and in line with site requirements
and it is easy to install and service in future. The frames will be supported by
angle legs of suitable lengths to provide the pre-determined inclination. All
fasteners, nut and bolts are made of Stainless steel - SS 304.
c. Foundation Base: The legs of the structures made with GI square pipe and
nut bolted on the foundation bolts in the RCC foundation columns made with
1:2:4 cement concrete. Actual frame and other structural dimensions will be
determined during a more detailed site visit by specialists during full design
phase.
d. Inverter installation: Based on the initial site visit, the inverters could
possibly be installed on the terrace. This space provides ample accessibility
and good air circulation. The inverter is available in IP54 housing; however,
an enclosed space has to be provided for the same. Actual installation
location and methods will be determined during full design phase.
e. Electrical: Proposed fire hose shaft will be used for running electrical cables
down to the electrical panel room. A detailed electrical design with single-line
diagram and specifications will be prepared during full design phase after
receiving the PO, for the clients approval.
15
Email: soralitepower@gmail.com
8. Clint Scope :-
*************************************************************************************************************
*************************************************************************************************************
*
16
Email: soralitepower@gmail.com