You are on page 1of 3

PARK ONE

COMMERCIAL & LUXURY APARTMENTS

Daily Construction Report


WEATHER
TEMPERATURE: 21oC

CONDITIONS:
Snow

sunny

Partly Cloudy

Cloudy

Windy

WORKMEN/EQUIPMENT
WORKERS
Contract #01
Bukhari (piling
sub-contractor)

Mgt staff: 1

TESTS/INSPECTIONS
Contract #02
Zafar shah
(pile head
cutting)

Contract #03
Ishaq butt
(steel fixer)

Mgt staff: 1

Labors:

Labors :

TOTAL

TOTAL

TOTAL

Haji
mahmood
(Excavator)

Mgt staff: 1

Contract #06

TOTAL

TOTAL

TOTAL

Contract #10

TOTAL

10

Deepwell (piling
sub-contractor)

Mgt staff: 1
2

Contract #11

Al-wahab
(mobile crane)

Afzal and
brother
( plastering
contactor)

Mgt staff:1

Mgt staff: 1

Labors: 3

Contract #08

Mgt staff: 1
Labors:

Labors:

Labors :

Mgt staff: 1
3

Mgt staff: 1

Nazar(rental
excavator)

Labors:

Dilawar khan
(excavator)

Mgt staff: 1

Azam (concrete
mobile pump)

Contract #09

Contract #07

Labors:

1. Concrete compressive strength test


2. Pile load test (in process)

Royal
geotech(piling
sub -contractor)

Mgt staff:

Labors:

Contract #05

Contract #04

Labors: 20

Labors:
TOTAL

21
22

Rain

TOTAL

TOTAL

TOTAL

21

This legend shows the contractors working on a particular day.

EQUIPMENTS AVAILABLE AT SITE

REMARKS

REMARKS

EQUIPMENT AVAILABLE AT SITE

1. Auger machine

8.concrete mobile pump


9. Tractor

2. Excavator
3. Dewatering pumps

10. Mobile crane


11.Batching plant
12. Compressive testing machine
13.Plate compactor

4.Air compressor

01m

5. Welding plant
6. Dumper
7. Concrete mixer

SAFETY NOTE
Nil

KEY ACTIVITIES
Activity
1.steel cage fabrication

Qty
9

Unit
#

Total
-

2.spacer formed

3.de watering

Occurring (Quantity not available)

4.pile concreting

948

6.levelling and spreading

7.pile boring/drilling

8.Slush removal

Occurring (Quantity not available)

Activity detail
1.Pile concreting
Zone
1
2
3

Pile concreted
(particular day )
-

Pile concreted
to date
186

5
443
4
319
Total pile concreted=948

Total piles

Pile No

186

466
405

679,630,679,1056,620
1041,780,799,83

Remarks

2.Concrete compressive strength test for piles


Sample
No of
Concrete
#
days
Purchased from
1
28
Sarwar
2

Pile No

Remarks

Strength achieved
(psi)
3700

3.Pile cutting and excavation:


Pile cap

Grid

Zone

Excavation

PC 17

C~5

Completed

PC 8

C~5

Completed

PC 156

F~8

In process

4.Steel fixing :
Pile cap
PC5
PC4

Grid
E~4
C~4

Pile head cutting


Previous
This day
To date
17
-

25

Remarks
Completed
Completed

32

Status
Completed
Completed

Remarks

5.Concrete compressive strength test for pile caps


6.Pile load test result:
Pile no 554 grid H~14
7. Dewatering was occurring.
8. Slush removal occurring.
9.PC12B steel placement (bottom main and distribution bars)
10. Pile head cutting of PC156 occurring.
11. PC8 SOG steel placed (partially completed )
12. Plastering completed up to grid 5 onwards (Main office side)
13.plastering occurring on grid 1~2 onward on Mustafa tower side (80% completed)
14.Pile load test platform formation.

MATERIAL DELIVERIES
Items

DATE

25-04-2016

SOURCE/VENDOR

Signature

QTY

UNIT

REMARKS

You might also like