You are on page 1of 6

ATTACHMENT: I-A: TERMINAL POINTS FOR MAIN PLANT EQUIPMENT SUPPLIER

10 x 660 MW- JSPL (Jindal Power), Date 05-03-2012


Equipment/ System

Terminal points

Resolutions
TBWES)

(Toshiba

Inlet of Bunker

TBWES noted & confirmed.

&

MECHANICAL
Steam Generator
1

Coal

Ash
(a) Bottom ash

Outlet of
assembly

boiler

seal

plate

TBWES noted & confirmed.

(b) Fly ash

Outlet flanges of knife edge gate


valve of
air preheater,
economizer, ESP , hoppers

TBWES noted & confirmed.

Flue gas

Approx
1
meter
outside
chimney.
Note - Expansion compensator
in boiler scope.

TBWES noted & confirmed.

Fuel oil

One meter away from boiler for


supply and return line(in
the pipe rack)

TBWES noted & confirmed.

Boiler filling lines/


deaerator emergency /
initial filling line

Inlet of CST

Boiler filling system including


associated piping (between CST
and Economiser) by TBWES.
Terminal point shall be the inlet
nozzle on CST.

One point at first column of


boiler for each boiler

Terminal point for ACW system


shall be 1.0 m from boiler 1 st
row column. However, DMCW
pumps and PHEs shall be
separate of boiler cooling water
requirement and supplied by
boiler.

6
(a) CCW/SW

Also, for owners BOPs cooling


water requirement (DMCW),
terminal
point
shall
be

discussed with owner.

(b) AH Washing

One point at last column of


boiler for each boiler

TBWES noted & confirmed.

(c) Fire fighting for


APH

One point at last column of


boiler for each boiler

TBWES noted & confirmed.

One point at first column of


boiler for each boiler

TBWES noted & confirmed for


their scope.

Instrument Air /Service


Air

Service Air and Instrument Air


Supply shall be made
available by the Owner at two
points (one at Boiler and
other at Turbine area) with
isolation valve.
8

Equipments and Piping


Drains

Terminal
at
nearest
tundish/station drains at zero
elevation

TBWES noted & confirmed.

Blow Down

IBD Boiler blow down up to


nearest effluent pit. Cooling of
hot blow down prior to disposal
in boiler scope.

TBWES noted & confirmed.

10

Mill reject system

Outlet of mill pyrite hopper.

TBWES noted & confirmed.

11

Steam vent

1m above boiler roof including


silencer.(Note: Each vent is to be
provided
with
individual
silencer)

TBWES noted & confirmed.

12

Counter flanges

All flange interface terminals


should be provided with counter
flanges, nuts, bolts, gaskets etc.
by bidder.

TBWES noted & confirmed.

13

Feed Water

From the inlet of Feed Control


Station (FCS) (FCS to be
supplied by Boiler Vendor)

14

Steam Output

15

CRH , HRH and Auxiliary


Steam line( as applicable)
-

At the outlet of the main steam


valve of the boiler.
1 meter away from the
connecting
point
of
the
respective Equipments of the
Boiler.

Terminal point shall be inlet of


check valve near economizer
inlet header. Flow element shall
be issued as Free-Issue-Item
(FIM)
to
Toshiba
for
installation in upstream feed
water piping.
For MS piping terminal point
shall be the ESV inlet.
For CRH,TP shall be Turbine
Exhaust (QCNRV shall be
supplied by Toshiba as free
issue item)

For HRH, TP shall be inlet of


IV.
For Auxiliary steam, TP shall
be at 1.0 meter from Boiler first
row column.
For HP Bypass, the piping shall
be by TBWES.HP Bypass
valves shall be free issue item
by TBWES to Toshiba.

16

Steam input ( as
applicable) Steam Turbine:
1

Condenser Cooling Water

(a) Closed loop DM


Cooling Water for
equipments (Primary
Circuit)
(b) ACW (Secondary
Circuit)

Condenser Make-up water

Instrument Air / Service


Air

Equipment and Piping


Drains

At the outlet of the main steam


valve of the boiler.

For LP Bypass, Upstream


piping of LP Bypass valve by
TBWES.
Refer Sl. N-14 above.

Upto the Condenser side flange


of the Butterfly valve ( scope of
Owner) including counter flange
At 1 meter away from TG
building column. (TG Vendor to
consider the requirement of DM
cooling water of the Boiler area
while sizing their PHE and
Pumps.) for Closed loop DM
Cooling Water for equipments
(Primary Circuit)
At Condenser Hot well Nozzle

Not Applicable to Boiler

Piping with isolation valve will


be provided at single point near
TG building. Further distribution
by vendor
Terminal at nearest tundish /
station drains at zero elevation.

Not Applicable to Boiler

Steam Vent

At suitable location, 1 m above


Turbine building roof including
silencer as required.

Not Applicable to Boiler

Carbon-di-oxide and
Hydrogen

Outlet manifold and subsequent


distribution under
bidders scope.

Not Applicable to Boiler

Steam Input

Refer Sl. N-14 above.

CRH, HRH and Auxiliary


Steam
Line (as applicable)

At the outlet of Main steam


valve of the Boiler
1 meter away from the
connecting point of the

Refer Sl. N-6a above for Boiler


scope.

Not Applicable to Boiler

Not Applicable to Boiler

Refer Sl. N-15 above.

respective Equipments of the


Boiler
10

Feed water

Up to the Inlet of Feed Control


Station (FCS). FCS
Supplied by the Boiler Vendor.

Refer Sl. N-13 above.

Electrical & Instrumentation:


1

Generator

Both phase and neutral side


flanges for connection with
IPBD. Generator Line and
Neutral side seal off bushing
terminals
suitable
for
termination
of
Purchaser's
Isolated
Phase
Generator
Busduct.

Not Applicable to Boiler

Neutral Grounding
Transformer & Resistor
(NGTR)

At the panel flange for


connection with IPBD. Seal off
bushing terminal of the Neutral
Grounding Equipment Cubicle
suitable for termination of
Purchaser's
Isolated
Phase
Generator Busduct.

Not Applicable to Boiler

Surge Protection and


Voltage Transformer
Cubicle

Seal off bushing terminals of the


Surge Protection and Voltage
Transformer Cubicle suitable for
termination
of
Purchaser's
Isolated
Phase
Generator
Busduct's tap-offs.

Not Applicable to Boiler

Lightening arrester
potential transformer
(LAPT) Cubicle

At the panel flange


connection with IPBD. .

Emergency DC Drives

At the incoming power supply


terminals of DC starters to be
located locally near the drives.
Power Cable interconnection
between DC starter and Motor
by Purchaser.

for

At the incoming power supply


terminals of DC starters
to be located locally near the
drives. Power Cable
interconnection between DC
starter and Motor is BTG
package scope
6

Cable & Cabling for

(1)

At

the

terminals

of

For TBWES scope.


For DC scanner air fan, TP
shall be motor terminal box.
For Local DC junction box ,TP
shall be local incoming
terminal.

For TBWES scope

BTG, except for ESP and


Soot Blower.

Instrument rack /JB mounted


locally near the equipment.
(2) At motor terminals

1.TBWES Noted & confirmed


2. TBWES Noted & confirmed

ESP

Power supply at 415 V level at


the incoming flange of ESP
PMCC for Busduct connection.

TBWES Noted & confirmed

Soot Blower MCC

Power supply at 415 V level at


the incoming terminals of Soot
Blower
MCC
for
cable
connection.

TBWES Noted & confirmed

UPS Supply (230 V AC, 1


phase, 50 Hz)

At the incoming power supply


terminals of Panels.

TBWES Noted & confirmed for


their scope as applicable.

10

Non UPS AC Supply

At the incoming power supply


terminals of Panels.

TBWES Noted & confirmed for


their scope as applicable.

11

DC Supply (220 V DC)

Redundant supply at each panel.

TBWES Noted & confirmed for


their scope as applicable.

12

Earthing

At the earth pad of MP


Equipment / Earth bus of Panels.

TBWES Noted & confirmed for


their scope.

At the earth riser 300 mm above


ground level
13

DCS ( including other PLC, Turbine Governor & BMS


systems)

TBWES confirmed
input for BMS.

for

the

13.1

UPS Supply

Redundant supply at DCS UPS


distribution board ( in MP
Vendor's scope)

Refer Sl. N-9 above.

13.2

Non UPS AC Supply

Supply at DCS ACDB ( in MP


Vendor's scope)

Refer Sl. N-10 above.

13.3

DC Supply

Redundant supply at DCS


DCDB ( in MP Vendor's scope)

Refer Sl. N-11 above.

13.4

Gateway cables

At the terminal point of gateway


module/marshalling.

TBWES Noted & confirmed for


their scope as applicable.

13.5

Electronic Earthing

At the Copper busbar of each


panel.

TBWES Noted & confirmed for


their scope as applicable.

14

VFD Drive

At the incoming power supply


terminals.

TBWES Noted & confirmed for


their scope as applicable.

15

Cable Tray & Support

Branch cable tray from Owners

TBWES Noted & confirmed for

16

AC Motor & Actuator

main cable trays/rack

their scope as applicable.

Motor Actuator Terminal Box

TBWES Noted & confirmed for


their scope.

CIVIL:
Base plate/sole plate, special and additional packers for all equipment
in BTG vendor scope. Supply of all foundation bolt for all equipment
in BTG scope shall be in scope of BTG vendor. Templates/ anchor
frames, if required, shall also be in Contractors scope.

TBWES Noted & confirmed for


their scope.

GENERAL:
All overflow drain connection, equipment drains, piping drains and
effluent discharge connections up to nearest effluent pit.

TBWES Noted & confirmed for


their scope.

Note: For the total BTG Package Vendor, the T.P for M.S., CRH, HRH, Feed water and
Auxiliary Steam Lines are not applicable

You might also like