Professional Documents
Culture Documents
Maracaibo. A sixth series capacitor is planned for future extension of the grid in the same area. The main purpose of the
transmission corridor is to transmit low cost hydroelectric
power to western Venezuela. Before, the system lacked the
capability to transmit all the power needed, therefore the use of
expensive fuel was required for local generation. By series
compensating the three 400 kV lines between Yaracuy substation and El Tablazo substation, plus the lines between Yaracuy
- Planta Centro and Yaracuy - Arenosa, the total power transmission capacity was increased from 1,800 to 2,125 MW.
Three series capacitors are located at El Tablazo and two at
Yaracuy.
I. INTRODUCTION
ENELVEN, a regional electricity utility in Venezuela, has
installed a total of five series capacitors in their grid to increase the capacity of existing overhead transmission lines
serving the residential, petroleum and petrochemicals center of
Nelson Sandoval is with ENELDIS, Centro de Control Caujarito Via
Aeropuerto, PO Box 146 Maracaibo 4001, Venezuela (e-mail:
nelson.sandoval@cantv.net)
Alex Molina is with CADAFE, Termoelectrica Planta Centro, Venezuela
(e-mail: amolina@plantacentro.com.ve)
ke Petersson is with ABB Power Systems, 721 64 Vsters, Sweden (email: ake.petersson@se.abb.com)
Gran Strmberg is with ABB Power Systems, 721 64 Vsters, Sweden
(e-mail: goran.stromberg@se.abb.com)
Jan Samuelsson is with ABB Power Systems, 721 64 Vsters, Sweden (email: jan.samuelsson@se.abb.com)
The project is making additionally 325 MW of power available to help meet growing demand for power in the Maracaibo
region, and enables ENELVEN to defer major investment in
additional transmission lines or new generating capacity to a
later stage.
The relation between the benefit of the project to the cost of
the installation is calculated as follows: 325 MW has a
monthly thermal energy cost of $6.5 million; the same amount
of hydroelectric power costs $1.6 million per month, which
corresponds to a monthly savings of $4.9 million. The total
monthly cost, including installation of five series capacitors is
$0.29 million. Therefore the benefit/cost relation is an amazing
17 times and a pay back period of less than a year.
Thus, conventional solutions to ENELVENs anticipated
shortfall in power would have been to build additional trans-
800
600
400
200
0
1
10
19
28
37
46
55
64
73
82
91
100
73
82
91
100
73
82
91
100
No. of simulations
800
600
400
200
0
1
10
19
28
37
46
55
64
No. of simulations
Series capacitors in a transmission line can have a significant effect on the transient voltage that appears across the contacts of a line circuit breaker when opening to clear a fault.
This voltage is referred to as the transient recovery voltage
(TRV). Circuit breakers have limited TRV capability. Another
limitation in the circuit breaker is the rate of rise of restriking
voltage (RRRV) [1].
The stress on existing line breakers on transmission lines
connected to either El Tablazo or Yaracuy substations was
determined. The study was performed using a deterministic
method, by varying the fault instant in steps of 1ms, to find the
worst fault type and location for each circuit breaker. Then the
worst fault case for each line circuit breaker i.e. the fault that
results in maximum TRV was repeated with 100 random
switching. Each simulation considers the randomness of fault
application, SC bypass (indirectly as it follows the fault inception) and LCB opening. The worst fault cases have been performed with the SC bypassed and not bypassed.
The result of random switching for one breaker in Planta
Centro (line Yaracuy - Planta Centro) is showed in Fig. 2. The
maximum calculated TRV for this breaker is 1292 kV, which
was more than this breaker could withstand. The study showed
also other line circuit breakers that could not withstand the
maximum TRV. All in all twenty line circuit breakers in the
substations El Tablazo, La Arenosa and Planta Centro had to
be replaced.
1000
800
600
400
200
0
1
10
19
28
37
46
55
64
No. of simulations
Fig. 2. TRV for breaker in Planta Centro (line Yaracuy-Planta Centro) random switching method.
04yt1-ys1-bdetrT>YT1YC (Type 4)
1000000
Voltage (V)
500000
-500000
-1000000
0
50
100
Time (ms)
150
200
Fig. 3 Fault clearing and reclosing simulation for line Yaracuy Tablazo I.
After completing the 400 simulations, the maximum overvoltage levels among the three phases were sorted in 0,05 p.u.
bins, ranging from 1,5 to 2,5 p.u.. Finally, the 2% overvoltage
level was determined from the cumulative distribution. The
overvoltage levels for series compensated lines have been determined before and after installation of the series capacitors.
The result is shown in Table I.
TABLE I
STATISTICAL 2% SWITCHING OVERVOLTAGE LEVELS AT OPEN END OF SERIES
COMPENSATED LINES
Line
Fault
Reclosed
No SC
SC
Position
From
Installed
Installed
Tablazo
2,11 pu
2,14 pu
Yaracuy
1,75 pu
1,77 pu
Planta Centro
1,81 pu
1,80 pu
Yaracuy
1,76 pu
1,78 pu
Arenosa
1,84 pu
1,79 pu
Yaracuy
1,83 pu
1,81 pu
Yar-Tabl
Line end
I, II, III
Yaracuy
Yar-Tabl
Line end
I, II, III
Tablazo
YaracuyPl.Centro
YaracuyPl.Centro
YaracuyArenosa
YaracuyArenosa
Line end
Yaracuy
Line end
Pl.Centro
Line end
Yaracuy
Line end
Arenosa
lines show that the influence of the SCs on the switching overvoltage level is small, the difference are less than 0,1 p.u. The
risk of insulation failure due to switching over voltages can be
estimated by a comparison with the insulation levels of the
line. The switching impulse withstand level (SIWL) is 1175
kV, corresponding to about 3,4 p.u., which gives a good margin, well above international standards, between the highest
calculated switching over voltage level and the SIWL of the
lines. Accordingly, it can be concluded that the risk of insulation failure due to switching overvoltages is low and practically unaffected by the installation of the series capacitors.
IV. SHORT CIRCUIT CALCULATIONS
The fault current levels and the through-fault currents with
the series compensated lines have been determine in a study.
The faults (three-phase-to-ground, two-phase-to-ground, twophase and single-phase-to-ground) were applied on 765 kV,
400 kV, 230 kV and 138 kV-buses. For the series compensated lines, also internal faults were applied on the line side of
the series capacitor (SC). The SC was modeled as a capacitor
with MOV protection according to Goldsworthy linearized
MOV model [3], as an ideal capacitor and as a bypassed capacitor.
The conclusion is that the SC with linearized model of the
MOV gives a good approximation of the SC through-fault currents for all types of faults. The SC modeled as an ideal capacitor can be used for external faults and for internal faults,
the SC bypassed gives a close approximation compared to the
linearized model.
For distance faults the through-faults currents through the
series capacitors have been found within the protective limit.
The maximum through-fault currents have been found to be
within limits of the existing equipment.
V. LINE PROTECTION COORDINATION
With line protection we here refer to the power system
aspect of selectively detecting a fault on a transmission line,
and subsequently clear the fault by tripping the line. In line
with state-of-art praxis, such protection is designed in a redundant configuration, with two different detection principles. The
two common principles are (i) Differential current measurement, and (ii) Distance (to fault) calculation. Whereas the differential current measurement is based on comparing the line
end currents (hence relying on high-speed line transfer communication), detecting any current deviation between into and
out of the transmission line, the distance protection scheme
functions primarily out of measured parameters at the line end
where the protection is located. Out of these two protection
schemes, only the distance protection is affected by the introduction of Series Capacitors. This comes out of the fact that
the series capacitors have a large impact on the electrical
length of the transmission line, they actually make it a lot
shorter and consequently they can lure distance protections
into false tripping. But there are modern computerized distance protections, in this case REL531, that are built for use
Resistance [Ohm]
100
50
0
50
10
20
30
Electrical frequency [Hz]
40
50
10
20
30
Electrical frequency [Hz]
40
50
60
Reactance [Ohm]
100
50
0
TI Undamping [1/s]
50
Short circuit studies with the purpose to identify prospective voltage reversal for various fault locations were performed
as part of the project. These studies identified that voltage reversal could happen at the line terminals of the series compensated lines, but also in the line terminals one bus away from
the series compensated lines. All in all twenty-two line protection terminals had to be replaced in the substation El Tablazo,
Yaracuy, Cuatrocentenario, La Arenosa and Planta Centro.
fm Hz
+1 Hz
1 Hz
0.1
0.05
0
0.05
60
0.15
10
20
30
Electrical frequency [Hz]
40
50
60
Fig. 5. Showing electrical resonance near Planta Centro unit #3-5 torsional
mode. Torsional modes are indicated with colored vertical lines.
Initially the SSR risk, or more correctly the risk for selfexcited sub-synchronous torsional interaction (SSTI), was
studied using frequency scanning technique. This is an effective screening tool as numerous grid configurations can be
analyzed quickly with a minimum of computer effort. The results of the frequency scanning analysis indicated that SSTI
could appear with both types of machines in Planta Centro.
Specifically the Planta Centro units #3-5, these having a natural torsional mode near 30Hz, could interact with the series
compensated grid as the electrical resonance could show up at
the complementary frequency 30Hz. This resonance also ap-
VII. CONCLUSIONS
ENELVEN, a regional electricity utility in Venezuela, has
installed a total of five series capacitors in their grid to increase the capacity of existing overhead transmission lines
serving the residential, petroleum and petrochemicals center of
Maracaibo. The project is making additionally 325 MW of low
cost hydroelectric power available. The pay back period for
the installation is less than one year.
In order to assure that grid code criteria was met and that
stresses on new and existing equipment was still acceptable, a
number of engineering studies were performed. The following
subtasks were given the utmost focus in this process: transient
stability validation, insulation coordination and switching over
voltage studies, short circuit calculations, line circuit-breaker
transient recovery voltage (TRV) determination, line protection coordination and sub synchronous resonance (SSR) studies.
The series capacitors impact on insulation levels of the existing equipment has been found very low. But the installation
of SCs has required replacement of twenty line breakers, due
to TRV stresses, and replacement of twenty-two line distance
protections, specially designed for series compensated lines.
The issue of SSR was apparent in this case, but studies and
measurements concluded that the there is sufficient damping in
the electromechanical system of the generators in Planta
Centro, i.e. low SSR risk. Nevertheless, a protection logic was
implemented. This logic is bypassing the serie capacitor in the
Yaracuy Planta Centro line, when two or more lines between
Planta Centro and Arenosa have been opened.
The conclusion is that power system engineering studies are
required to minimize failure in existing equipment and unwanted line trips, when installing series capacitors.
VIII. REFERENCES
[1]
[2]
[3]
[4]
IX. BIOGRAPHIES
Nelson Sandoval was born in Caracas, Venezuela on December, 4 1947. He
received his M. Sc. Degree in Electrical Power Engineering from Rensselaer
Polytechnic Institute, New York, USA in 1977. Since then he has been working for ENELVEN in several areas, but his main experience is in transmission
and distribution planning.
Alex Molina was born in Barinas, Venezuela on March 12, 1970. He graduated as Electrical Engineer at I.U.P. Santiago Marino, Valencia, Venezuela in
1998. He is now studying for a M. SC. Degree in Electrical Engineering at
University Simn Bolvar, Venezuela. Since 1992 he has been working for
CADAFE in Planta Centro generating station in several areas. He is presently
responsible for the department of Protections and Substations.