Five-Year Annual Transmission Capability Statement (2016 - 2020)

Table1: Summary of Planned Developments on OETC Transmission System (2016 - 2020)


Expected
S.N

Project

Completion
Date

Status

Main Equipment

Purpose

Peak 2016
35 km 132kV OHL from Sur grid
station
1

Al Ayjah 132/33kV grid station

Q3 2015

Energized

To cater for the new load growth at Ras Al Had area

2x125MVA transformers

Solve the issue of voltage drop of 33kV lines. Currently


this area is fed by 33kV feeders from Sur grid station

6 no. 132kV GIS

Load transfer from existing Sur grid

2 x 125 MVA transformers


2

Madinat Nizwa 132/33kV grid


station

Q3 2015

Energized

6 no. 132kV GIS

Load transfer from Nizwa grid station

12 km 132kV double circuit OHL


from Nizwa grid station

To meet load growth requirements in the area

12 no. 132kV GIS


3

Rusail Industrial 132/33kV


grid station

Q3 2015

Energized

4 x 125MVA transformers

Replacement of old 132kV and 33kV switch gears due to


132kV and 33kV short circuit effects
Replacement of old 75MVA transformers with 125MVA
To cater for the new load growth at Rusail area

2 x 125 MVA transformers


4

Amerat 132/33kV grid station


(TX1 & TX2)

Q3 2015

Energized

8 no. 132kV GIS


5km LILO of 132kV OHL between
MSQ and Jahloot

Load transfer from Jahloot and Wadi Adai grid stations


To meet the high load growth at Amrat area
To resolve 33kV voltage issues

Page | 12

Five-Year Annual Transmission Capability Statement (2016 - 2020)

Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)

S.N

Project

Expected
Completion
Date

Status

Main Equipment

Purpose

Peak 2016
2x 125MVA transformers

A'salam 132/33kV grid station


(TX1 & TX2)

8.4km 132kV 2500mm2 UGC from


Mobella to A'salam
Q3 2015

Energized
7.4km132kV 2500mm2 UGC from
Seeb Main to A'salam

To cater for the load growth at Mobella


Load transfer from grids in this area (Mawalleh , Seeb
Main , Barka Main and Mobella)

10 no. 132kV GIS

Ghala 132/33kV grid station


(TX1 & TX2)

Q3 2015

Energized

2 x 125 MVA transformers

To cater for the expected load growth in Ghala area

12 no. 132kV GIS

Load transfer from Bousher and Airport Heights grid


stations

4km UGC 2500mm from Airport


Heights grid station
2 x 125MVA transformers

Khadhra 132/33kV grid station


(TX1 & TX2)

Q4 2015

Energized

10. no. 132kV GIS

To supply the new Al Arfan area load


To cater for the new demand within the area
Load transfer from Khaborah & MIS grid stations

0.135 km LILO of 132kV between


MIS Khabourah

Page | 13

Five-Year Annual Transmission Capability Statement (2016 - 2020)

Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)

S.N

Project

Expected
Completion
Date

Status

Main Equipment

Purpose

Peak 2016
223 km 400kV lines route length
between Sur Qalat Al Awamer

New 400kV OHL between Sur


8

Power Plant and Qalat Al


Awamer 400 kV grid stations

Q4 2015

Completed

10

Al Hamriyah 220/132kV grid


station

To support the voltage and power flow to Al Dakhliah


area
To comply with Transmission Security Standards
requirements

2x 125MVA transformers
Madinat Barka 132/33kV grid
station (TX1 & TX2)

To evacuate the power from Sur Generation

Q4 2015

Q1 2016

Under
Construction

Energized
(Grid
Station)
Under
Construction
(220kV
OHL)

10 no. 132kV GIS

To cater for the load growth at Barka area


To meet Transmission Security Standard

0.13 km LILO of 132kV OHL from


Filaj to Mualdah

Load transfer from Barka Main

2 x 500MVA transformers 220/132kV

To supply the load of the area

8 no. 220kV GIS

To support the voltage at Muscat area Grids

14 no. 132kV GIS

( Wadi Adai, Wadi Kabir, Muttrah , Qurum and AlFalaj)

33.8 km 220kV OHL from Jahloot to


Al Hamriyah

To evacuate the power coming from Sur via Jahloot grid


station

LILO the 132kV Wadi Adai- Wadi


Kabir lines grids station

To increase the system reliability within Muscat area grid


stations

LILO the 132kV Qurum-Muttrah lines


to Al Hamriyah grids station

To increase and maintain the system security of 132kV


lines within the area

Page | 14

Five-Year Annual Transmission Capability Statement (2016 - 2020)

Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)

S.N

Project

Expected
Completion
Date

Status

Main Equipment

Purpose

Peak 2016
6 no. 132kV GIS
11

Ibra 132/33kV grid station

Q1 2016

Under
Construction

28 km OHL 132kV route length


between Mudhairib and Ibra grid
stations

To meet load growth requirements


To meet Transmission Security Standard
Load transfer from Mudhairib

2x 125MVA transformers
12

13

New 132kV Line Ashoor Awqad (Part-1)

Q1 2016

New 132kV Line Ashoor Awqad (Part-2)

Q1 2016

Under
Construction
Under
Construction

8.5 km 132kV OHL

To complete the ring of 132kV system

1.2 km 132kV UGC

To meet Transmission Security Standard

48.3 km 132kV OHL

To complete the ring of 132kV system


To meet Transmission Security Standard

At Jahloot:
4 x500MVA, 400/220kV transformers
10 no. 400kV GIS

14

Sur IPP 400/220kV Grid Station


& Jahloot 400/220kV Grid
Station

Q2 2016

Under
Construction

2 no. 220kV GIS


At Sur Power Plant:

To evacuate the power from Sur Generation

5 x 750MVA 400/220kV
transformers
13 no. 400kV
1 no. 220kV GIS
Page | 15

Five-Year Annual Transmission Capability Statement (2016 - 2020)

Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)

S.N

Project

Expected
Completion
Date

Status

Main Equipment

Purpose

Peak 2016
2 x 125 MVA transformers

15

JBB Hassan 132/33kV grid


station

Q2 2016

Under
Construction

8 no. 132kV GIS

Load transfer from existing JBB Ali grid station

2x16 km LILO Al kamil-Sur 132kV


OHL

To meet load growth requirements in the area


To meet Transmission Security Standard

6x132kV AIS at JBB Ali grid station


2 x 125 MVA transformers
16

Qalat Al Awamer 132/33kV


grid station

Q2 2016

Under
Construction

8 no. 132kV GIS

To cater for the new demand in the area

2x0.62 km LILO of Izki Mudhaibi


132kV UGC

Load Transfer from Izki grid station

To evacuate the power from Sur Generation

17

Qalat Al Awamer 220kV grid


station

Q2 2016

Under
Construction

2x 500 MVA transformers(220/132kV)

To support the voltage and power flow to Al Dakhliah


area

7 no. 220kV GIS


To comply with Transmission Security Standards
requirements

Page | 16

Five-Year Annual Transmission Capability Statement (2016 - 2020)

Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)

S.N

Project

Expected
Completion
Date

Status

Main Equipment

Purpose

Peak 2016

18

Qalat Al Awamer 400/220 kV


grid station

Q2 2016

Under
Construction

2x 500 MVA transformers


(400/220kV)
10 no. 400kV GIS

To evacuate the power from Sur Generation


To support the voltage and power flow to Al Dakhliah
area
To comply with Transmission Security Standards
requirements

Peak 2017

19

20

Dreez 132/33kV grid station

Sohar Free Zone 220/132/33kV


grid station

Q4 2016

Q4 2016

Under
Construction

Under
Construction

2 x 125 MVA

To cater for the new demand within the area

30 km 132kV OHL from Ibri

Load transfer from Ibri and Al Hayl grid stations

8 no. 132kV GIS


2x 0.17 km LILO Wadi Al Jizzi
Liwa 132kV OHL

To cope with the load growth.

2x 500 MVA transformers

To meet Transmission Security Standard

8 no. 220kV GIS

To supply the free zone area industrial loads

2x 0.48 km UGC as LILO of 220kV


OHL Sohar 2 PS -SIS
2x125MVA transformers
16 no.132kV GIS

Page | 17

Five-Year Annual Transmission Capability Statement (2016 - 2020)

Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)
S.N

Project

Expected
Completion
Date

Status

Main Equipment

Purpose

Peak 2017
To replace the existing AIS to GIS due to:
Lightening
21

Replacement of Mahadha
132kV AIS to GIS

Q4 2016

Under
Construction

14 no. 132kV GIS

Maintenance Issus
Old Assets
System reliability
System security

22

Upgrading Misfah grid station


to 400kV

Q4 2016

Under
Construction

3 x 500MVA transformers
(400/220kV)

To support the evacuation of Sur power plant

11 no. 400kV GIS

To maintain the security requirement

3 no. 220kV GIS

23

24

Adding third & fourth


transformers 132/33kV at
Muladah grid station

Adding third & fourth


transformers 132/33kV at Liwa
grid station

2 x 125 MVA transformers


Q1 2017

Under
Construction

2 no. 132kV GIS

To meet load growth requirements


To meet Transmission Security Standard

4 no. 33kV Interlink


2 x 125 MVA transformers
Q1 2017

Under
Construction

2 no. 132kV GIS

To cater for the new demand in the area


To meet Transmission Security Standard

4 no. 33kV Interlink

Page | 18

Five-Year Annual Transmission Capability Statement (2016 - 2020)

Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)
Expected
S.N

Project

Completion
Date

Status

Main Equipment

Purpose

Peak 2017

25

400 kV OHL between Qalat Al


Awamer and Misfah

26

33kV busbars Interlinking at


Bousher & Mawalleh South
grid stations

Q2 2017

Q2 2017

Under
Construction

Design

100 km OHL 400kV

8 no. of 33kV at Bousher & Mawalleh


South
4x125MVA Transformers

27

Saadah 132/33kV grid station

Q2 2017

Under
Construction

10 no. of 132kV GIS.


4 no. 33kV Interlink
13km LILO from AshoorAwqad132kV UGC

To support the evacuation of Sur power plant


To meet Transmission Security Standard
To meet Transmission Security Standard

To meet load growth requirements


To meet Transmission Security Standard
Load Transfer from Al Qarm, Ittin and Awqad grid
stations

3x 50 MVA (shifted from the


Mawalleh North grid station)
28

Daghmar 132/11kV grid


station

Q2 2017

Under
Construction

4km OHL from Quriyat grid station

To supply the new IWP at Quriyat

2 no. 132kV GIS at existing Quriyat


grid station
7 no. 132kV GIS at Daghmar

Page | 19

Five-Year Annual Transmission Capability Statement (2016 - 2020)

Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)
Expected
S.N

Project

Completion
Date

Status

Main Equipment

Purpose

Peak 2017

29

Connection of Salalah-2 IPP &


Adding third & fourth
transformers to Salalah Free
Zone grid station

Q2 2017

Under
Construction

16 no. of 132kV GIS

To connected the new Salalah-2 IPP Power Plant

2x125MVA transformers

To meet load growth requirements


To meet Transmission Security Standard

3km 132kV 2500mm2 cables between


Muttrah-Al Falaj grid stations

30

132kV Linking System between


Al Falaj, Muttrah and Wadi
Kabir Grid stations & Adding
Fourth 125MVA transformer at
Wadi Kabir grid station

Q2 2017

Under
Construction

One circuit Twin YEW 1.5 km OHL and 2


km UGC 132kV between Muttrah-Wadi
Kabair grid stations

To secure the loads and meet Transmission


Security Standard.
Safety clearance and environment issues
To cater for the new demand in the area

10 no. 132kV GIS at Wadi Kabair grid


station
8 no. 132 GIS at Al Falaj
1 x 125MVA transformer at Wadi Kabir
Peak 2018
2x35 MVAr reactors at end of 400kV line
between Sur-Jahloot

31

Adding 400kV reactors

Q3 2017

Design

4x40 MVAr reactors at end of 400kV line


between Sur-Qalat Al Awamer

To maintain the voltage within the range during


the winter time

2x30 MVAr reactors at end of 400kV line


between Qalat Al Awamer-Misfah
Page | 20

Five-Year Annual Transmission Capability Statement (2016 - 2020)

Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)
Expected
S.N

Project

Completion
Date

Status

Main Equipment

Purpose

Peak 2018
2 x 125 MVA transformers
32

Dil Abdusalam 132/33kV grid


station

Q3 2017

Design

2x8 km LILO of SahamKhaborah132kV OHL


8 no. 132kV GIS

33

34

Adding third & fourth


transformers 132/33kV at
Khadhra grid station

Q3 2017

Adding third & fourth


transformers 132/33kV at
Madinat Barka grid station

Q3 2017

To cater for the new demand in the area


Load Transfer from Saham & Khaborah grid stations
To meet Transmission Security Standard

2 x 125 MVA transformers

To meet Transmission Security Standard

4 no. 33kV Interlink

To cater for the load growth in the area

2 x 125 MVA transformers

To meet Transmission Security Standard

4 no. 33kV Interlink

To cater for the load growth in the area

Design

Design

2 x 125 MVA transformers

35

Madinat Shinas 132/33kV


grid station

Q3 2017

Design

24.06 km 132kV OHL from Shinas to


Madinat Shinas

To cater for the new demand in the area

2 no. 132kV GIS at Shinas

To meet Transmission Security Standard

Load Transfer from Shinas grid station

6 no. 132kV GIS at Madinat Shinas

Page | 21

Five-Year Annual Transmission Capability Statement (2016 - 2020)

Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)

S.N

Project

Expected
Completion
Date

Status

Main Equipment

Purpose

Peak 2018
2 x 125 MVA transformers
36

Suwaiq 132/33kV grid station

Q3 2017

Design

2x0.2 km LILO of MIS-Khadhra


132kV OHL
8 no. 132kV GIS
2 x 125 MVA transformers

37

Sinaw 132/33kV grid station

Q3 2017

Design

2x15 km LILO of Qalat Al Awamer Mudhaibi 132kV OHL


8 no. 132kV GIS

To cater for the new demand in the area


To meet Transmission Security Standard
Load Transfer from MIS grid station

To cater for the new demand in the area


Load transfer from Mudhaibi
Solve the issue of voltage drop of 33kV lines
To meet Transmission Security Standard

38

Upgrading of Mawalleh North


grid station from 3x50MVA
(132/11kV) to 2 x 125 MVA
(132/33kV) transformers

To cater for the new demand in the area


Q3 2017

Design

2 x 125 MVA transformers

2 x 125 MVA transformers


39

Jebreen 132/33kV grid station

Q3 2017

Design

2x0.5 km LILO of Nizwa - Ibri


132kV OHL
8 no. 132kV GIS

To support the 33kV network in the Seeb area and


enable to transfer more load from neighbouring grid
stations (Seeb & Mawalleh)
To cater for the new demand in the area
Load Transfer from Bahla grid station
To meet Transmission Security Standard

Page | 22

Five-Year Annual Transmission Capability Statement (2016 - 2020)

Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)
Expected
S.N

Project

Completion
Date

Status

Main Equipment

Purpose

Peak 2018
3 x 500 MVA transformers (400/220kV)
40

41

42

Ibri 400kV grid station

Adding 2x125MVA
transformers 220/33kV at
Barka-3 PS grid station
Construction of a new 132 kV
OHL from Sohar Free Zoon to
Shinas

Q3 2017

Q4 2017

Under
Construction

station from 2x40MVA to


2x125MVA transformers

10 No. 220kV GIS at Ibri IPP


2x4.3 km LILO of 220kV OHL Ibri Mahadha

To maintain Transmission Security


Standard

2 x 125 MVA transformers

To Supply the Barka IWP

2 no. 220kV GIS

Load Transfer from Barka Main grid station

Design

2 no. 132kV GIS at Shinas


Q4 2017

Design

2 no. 132kV GIS at Sohar Free Zone

To meet Transmission Security Standard

20km 132kV OHL from Sohar Free Zone to Shinas

Upgrading of Adam grid


43

19 No. 400kV GIS at Ibri IPP

To evacuate power coming from Ibri IPP


Power Plant and supply Ibri area

2 x 125 MVA transformers


Q2 2018

Design
6 no. 132kV GIS

To maintain Transmission Security


Standard
To cater for the new demand in the area

1 no 132kV GIS
2 no. of 220kV GIS
44

Security of SIA grid station

Q2 2018

Design
1x500MVA transformer

To meet Transmission Security Standard at


SIA during maintenance period

3.2 km UGC of 220kV SPS 1 SIA


Page | 23

Five-Year Annual Transmission Capability Statement (2016 - 2020)

Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)

S.N

Project

Expected
Completion
Date

Status

Main Equipment

Purpose

Peak 2018
2 no 132kV GIS at Nakhal
New 132kV double circuits
45

lines from Rustaq-Wadi bani


Auwf-Nakhal with a new
Wadi bani Auwf 132/33 kV
grid station

2 no 132kV AIS at Rustaq


Q2 2018

Design

88km 132kV OHL

To meet Transmission Security Standard at Rustaq


during maintenance period

2x125 MVA at Wadi bani Auwf

Load Transfer from Rustaq grid station

8 no. of 132kV GIS at Wadi bani Auwf

46

Upgrading of Seeb Main grid


station from 2 x 63 MVA to 2 x
125 MVA transformers and
installing 33kV busbars
Interlinking

Q2 2018

2 x 125 MVA transformers

To maintain Transmission Security Standard

4 no. 33kV Interlink

To cater for the new demand in the area

Design

4 x 125 MVA transformers


47

Uwaynat 132/33kV grid


station

2x5 km LILO of Sohar-SIS 132kV OHL


Q2 2018

Design
10 no. 132kV GIS

To cater for the new demand in the area


Load Transfer from the existing Saham and Sohar grid
stations

4 no. 33kV Interlink

48

400kV connection line to Ibri


IPP Power Plant

250 km 400kV OHL between Ibri to


Qalat Al Awamer
Q2 2018

Design
Adding 8 x 50 MVAr reactors at 400kV
line ends

To evacuate power coming from Ibri IPP Power Plant


and supply Ibri area
To maintain Transmission Security Standard
Page | 24

Five-Year Annual Transmission Capability Statement (2016 - 2020)

Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)
Expected
S.N

Project

Completion
Date

Status

Main Equipment

Purpose

Peak 2018
42 km 400kV OHL between Sohar Free
Zone to SIS

49

400kV line connection between


Sohar Free Zone & SIS

3 x 500 MVA transformers (400/220kV)


at SIS
Q2 2018

Design

9 no. 400kV GIS at SIS


3 no. 220kV GIS at SIS

To develop 400kV network


To evacuate full power from Sohar III IPP
To maintain Transmission Security Standard

Adding 2 x 50 MVAr reactor at Sohar


Free Zone

50

51

400kV line connection between


Sohar Free Zone & Mahadha

Installing 220kV GIS and


adding fourth 125MVA
transformer at MSQ grid
station

Q2 2018

Design

63 km 400kV OHL between Sohar Free


Zone to Mahadhah

To develop 400kV network

2 no. 400kV GIS at Mahadhah

To evacuate full power from Sohar III IPP

Adding 4 x 50 MVAr reactor at 400kV


line

To maintain Transmission Security Standard

1 x 125MVA transformer
Q2 2018

Under
Construction

6 no. of 220kV GIS


8 no. of 132kV GIS
4 no. 33kV Interlink

To meet load growth requirements


To meet Transmission Security Standard
To cater for the new demand in the area

Page | 25

Five-Year Annual Transmission Capability Statement (2016 - 2020)

Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)
Expected
S.N

Project

Completion
Date

Status

Main Equipment

Purpose

Peak 2018
6 km OHL from Terminal Tower to Sohar Free
Zone
3.3 km 400kV cable from Sohar III IPP to
Terminal Tower
52

Sohar Free Zone 400kV grid


station

Q2 2018

Design

0.9 km 400kV cable from Terminal Tower to


Sohar Free Zone

To evacuate power coming from Sohar III IPP


Power Plant and to supply area

3 x 500 MVA transformers (400/220kV) at


Sohar Free Zone

To maintain Transmission Security Standard

20 no. 400kV GIS at Sohar III IPP


17 no. 400kV GIS at Sohar Free Zone
3 no. 220kV GIS at Sohar Free Zone
2 x 500MVA transformers
53

Upgrading Mobella grid station


to 220kV

Q2 2018

Under
Construction

2x0.5 km LILO of Al Filaj-Airport Heights


220kV OHL
8 no. 220kV GIS

Supporting Mobella demand


Securing of the supply within the area

2 no 132kV GIS
Peak 2019
4 x 125 MVA transformers
54

Ghala Heights 132/33kV grid


station

14 no. of 132kV GIS


Q3 2018

Design

New 132kV cable of 7km from Ghala to Ghala


Heights and 7km from Ghala Heights to Bousher
4 no. 33kV Interlink

To cater for the new demand in the area


Load transfer from Bousher
To meet Transmission Security Standard
Page | 26

Five-Year Annual Transmission Capability Statement (2016 - 2020)

Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)

S.N

Project

Expected
Completion
Date

Status

Main Equipment

Purpose

Peak 2019
2 x 63 MVA transformers (shifted from
55

Samad 132/33kV grid station

Q2 2019

Design

Mudhaibi grid station)

To cater for the new demand in the area

38.5 km 132kV OHL from Mudhaibi

Load transfer from Mudhaibi grid station

6 no. 132kV GIS


2 x 125 MVA transformers

Adding third & fourth


56

transformers 132/33kV at

To meet Transmission Security Standard


Q2 2019

Design

To meet load growth in the area

Ghala grid station

4 no. 33kV Interlink

Reactive Power
57

Compensation Requirements

Q2 2019

Q2 2019

Design

Amerat grid station

transformers 132/33kV at
Airport Heights grid station

SVC at Airport Heights

transient at the winter time

2 no. 132kV GIS

To meet Transmission Security Standard


To meet load growth in the area

4 no. 33kV Interlink


2 x 125 MVA transformers

Adding third & fourth


59

To maintain the voltage within the range during the

2 x 125 MVA transformers

Adding third & fourth


transformers 132/33kV at

SVC at Hamriyah
Planning

(SVC)

58

2 no. 132kV GIS

Q2 2019

Design

To meet Transmission Security Standard


2 no. 132kV GIS
To meet load growth in the area
4 no. 33kV Interlink
Page | 27

Five-Year Annual Transmission Capability Statement (2016 - 2020)

Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)
Expected
S.N

Project

Completion
Date

Status

Main Equipment

Purpose

Peak 2019

60

Adding third & fourth


transformers 132/33kV at
A'salam grid station

2 x 125 MVA transformers


To meet Transmission Security Standard
Q2 2019

Design

2 no. 132kV GIS


To meet load growth in the area
4 no. 33kV Interlink
4x 125 MVA transformers
To cater for the new demand in the area
10 no. 132kV GIS

61

Halban 132/33kV grid station

Q2 2019

Design

4 no. 33kV Interlink

Load transfer from Mobella & Barka Main grid


stations

2x0.4 km LILO 132kV UGC Barka


Main Mobella
2 x 125 MVA transformers
62

Sumail Industrial 132/33kV


grid station

Q2 2019

Design

12km LILO of Rusail-Sumail 132kV


OHL

To cater for the new demand in the area


Load transfer from Sumail grid station

8 no. 132kV GIS


2 x 125 MVA transformers
63

Bedyah 132/33kV grid station

Q2 2019

Design

0.6 km LILO of Mudhairib Al Kamil


132 kV OHL

To cater for the new demand in the area


Load transfer from Mudhairib

8 no. 132kV GIS

Page | 28

Five-Year Annual Transmission Capability Statement (2016 - 2020)

Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)

S.N

Project

Expected
Completion
Date

Status

Main Equipment

Purpose

Peak 2019

64

Adding third & fourth


transformers 132/33kV at
Sohar Free Zone grid station

2 x 125 MVA transformers


Q2 2019

Design

2 no. 132kV GIS


4 no. 33kV Interlink

To meet Transmission Security Standard


To meet load growth in the area

2 x 500 MVA transformers (400/132kV)

65

Qabel 400/132kV grid station

Q2 2019

Design

2x0.2 km LILO of 400kV OHL Sur


Qalat Al Awamer

To increase the system reliability within Sharqia area


when Al Kamil IPP is retired

2x0.2 km LILO of 132kV OHL


Mudhairib Ibra

To increase and maintain the system security of 132kV


lines within the area

8 no. of 400kV GIS at Qabel grid station


8 no. 132kV GIS at Qabel grid station

66

Upgrading Bureimi Industrial


grid station to 220kV

2 no. 132kV AIS at Mudhairib 132 kV


grid station

To evacuate power coming from Sur Power Plant

2 x 500 MVA transformers

To maintain Transmission Security Standard


requirements

8 no. of 220kV GIS


Q2 2019

Design

2x6 km LILO of 220kV OHL Mahdhah


UAE
2 no 132kV GIS

To meet load growth requirements


To increase the system reliability within Al Bureimi
area

Page | 29

Five-Year Annual Transmission Capability Statement (2016 - 2020)

Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)
Expected
S.N

Project

Completion
Date

Status

Main Equipment

Purpose

Peak 2019

67

Birkat Al Mouz 132/33kV grid


station

Q2 2019

Design

2 x 125 MVA transformers

To cater for the new demand in the area

8 no. 132kV GIS

Load transfer from Nizwa & Madinat Nizwa


grid stations

2x0.35 km LILO of Izki- Nizwa 132 kV OHL


2 x 500 MVA transformers
68

Upgrading Khaborah grid


station to 220kV

Q2 2019

Design

8 no. of 220kV GIS


2x16km LILO of 220kV OHL SIS MIS

To cater for the new demand in the area


To increase the system reliability within Al
Batinah South North

2 no 132kV GIS

69

Construction of a new 132 kV


OHL from Jahloot to Quriyat

132 kV OHL from Jahloot to Quriyat (50


km).
Q2 2019

Planning

2 no. 132kV GIS at Quriyat

To meet Transmission Security Standard

2 no. 132kV AIS at Jahloot

70

Adding third & fourth


transformers 132/33kV at
Bureimi Industrial grid station

Q2 2019

Design

2 x 125 MVA transformers

To meet Transmission Security Standard

2 no. 132kV GIS

To meet load growth in the area

4 no. 33kV Interlink

Load transfer from Bureimi grid station

Page | 30

Five-Year Annual Transmission Capability Statement (2016 - 2020)

Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)

S.N

Project

Expected
Completion
Date

Status

Main Equipment

Purpose

Peak 2020

71

72

Yanqul 132/33kV grid station

Adding third & fourth


transformers 132/33kV at
Ghubrah grid station

Q2 2020

Q2 2020

Design

Planning

2 x 125 MVA transformers

To cater for the new demand in the area

8 no. 132kV GIS

Load transfer from Al Hayl grid station

2x4 km LILO 132kV OHL Dank - Al Hayl

To maintain the 33kV OHL losses

2 x 125 MVA transformers

To meet Transmission Security Standard

2 no. 132kV GIS

To meet load growth in the area

4 no. 33kV Interlink


4 x 125 MVA transformers
10 no. 132kV GIS

73

Khoudh 132/33kV grid station

Q2 2020

Planning

LILO 132kV Mawalleh South Rusail


Industrial

To cater for the new demand in the area


Load transfer from Mawalleh South grid station

4 no. 33kV Interlink


2 x 125 MVA transformers
74

Khuwair 132/33kV grid station

Q2 2020

Planning

10 no. 132kV GIS


LILO 132kV MSQ Ghubrah

To cater for the new demand in the area


Load transfer from MSQ grid station

Page | 31