Professional Documents
Culture Documents
Project
Completion
Date
Status
Main Equipment
Purpose
Peak 2016
35 km 132kV OHL from Sur grid
station
1
Q3 2015
Energized
2x125MVA transformers
Q3 2015
Energized
Q3 2015
Energized
4 x 125MVA transformers
Q3 2015
Energized
Page | 12
Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)
S.N
Project
Expected
Completion
Date
Status
Main Equipment
Purpose
Peak 2016
2x 125MVA transformers
Energized
7.4km132kV 2500mm2 UGC from
Seeb Main to A'salam
Q3 2015
Energized
Q4 2015
Energized
Page | 13
Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)
S.N
Project
Expected
Completion
Date
Status
Main Equipment
Purpose
Peak 2016
223 km 400kV lines route length
between Sur Qalat Al Awamer
Q4 2015
Completed
10
2x 125MVA transformers
Madinat Barka 132/33kV grid
station (TX1 & TX2)
Q4 2015
Q1 2016
Under
Construction
Energized
(Grid
Station)
Under
Construction
(220kV
OHL)
Page | 14
Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)
S.N
Project
Expected
Completion
Date
Status
Main Equipment
Purpose
Peak 2016
6 no. 132kV GIS
11
Q1 2016
Under
Construction
2x 125MVA transformers
12
13
Q1 2016
Q1 2016
Under
Construction
Under
Construction
At Jahloot:
4 x500MVA, 400/220kV transformers
10 no. 400kV GIS
14
Q2 2016
Under
Construction
5 x 750MVA 400/220kV
transformers
13 no. 400kV
1 no. 220kV GIS
Page | 15
Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)
S.N
Project
Expected
Completion
Date
Status
Main Equipment
Purpose
Peak 2016
2 x 125 MVA transformers
15
Q2 2016
Under
Construction
Q2 2016
Under
Construction
17
Q2 2016
Under
Construction
Page | 16
Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)
S.N
Project
Expected
Completion
Date
Status
Main Equipment
Purpose
Peak 2016
18
Q2 2016
Under
Construction
Peak 2017
19
20
Q4 2016
Q4 2016
Under
Construction
Under
Construction
2 x 125 MVA
Page | 17
Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)
S.N
Project
Expected
Completion
Date
Status
Main Equipment
Purpose
Peak 2017
To replace the existing AIS to GIS due to:
Lightening
21
Replacement of Mahadha
132kV AIS to GIS
Q4 2016
Under
Construction
Maintenance Issus
Old Assets
System reliability
System security
22
Q4 2016
Under
Construction
3 x 500MVA transformers
(400/220kV)
23
24
Under
Construction
Under
Construction
Page | 18
Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)
Expected
S.N
Project
Completion
Date
Status
Main Equipment
Purpose
Peak 2017
25
26
Q2 2017
Q2 2017
Under
Construction
Design
27
Q2 2017
Under
Construction
Q2 2017
Under
Construction
Page | 19
Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)
Expected
S.N
Project
Completion
Date
Status
Main Equipment
Purpose
Peak 2017
29
Q2 2017
Under
Construction
2x125MVA transformers
30
Q2 2017
Under
Construction
31
Q3 2017
Design
Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)
Expected
S.N
Project
Completion
Date
Status
Main Equipment
Purpose
Peak 2018
2 x 125 MVA transformers
32
Q3 2017
Design
33
34
Q3 2017
Q3 2017
Design
Design
35
Q3 2017
Design
Page | 21
Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)
S.N
Project
Expected
Completion
Date
Status
Main Equipment
Purpose
Peak 2018
2 x 125 MVA transformers
36
Q3 2017
Design
37
Q3 2017
Design
38
Design
Q3 2017
Design
Page | 22
Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)
Expected
S.N
Project
Completion
Date
Status
Main Equipment
Purpose
Peak 2018
3 x 500 MVA transformers (400/220kV)
40
41
42
Adding 2x125MVA
transformers 220/33kV at
Barka-3 PS grid station
Construction of a new 132 kV
OHL from Sohar Free Zoon to
Shinas
Q3 2017
Q4 2017
Under
Construction
Design
Design
Design
6 no. 132kV GIS
1 no 132kV GIS
2 no. of 220kV GIS
44
Q2 2018
Design
1x500MVA transformer
Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)
S.N
Project
Expected
Completion
Date
Status
Main Equipment
Purpose
Peak 2018
2 no 132kV GIS at Nakhal
New 132kV double circuits
45
Design
46
Q2 2018
Design
Design
10 no. 132kV GIS
48
Design
Adding 8 x 50 MVAr reactors at 400kV
line ends
Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)
Expected
S.N
Project
Completion
Date
Status
Main Equipment
Purpose
Peak 2018
42 km 400kV OHL between Sohar Free
Zone to SIS
49
Design
50
51
Q2 2018
Design
1 x 125MVA transformer
Q2 2018
Under
Construction
Page | 25
Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)
Expected
S.N
Project
Completion
Date
Status
Main Equipment
Purpose
Peak 2018
6 km OHL from Terminal Tower to Sohar Free
Zone
3.3 km 400kV cable from Sohar III IPP to
Terminal Tower
52
Q2 2018
Design
Q2 2018
Under
Construction
2 no 132kV GIS
Peak 2019
4 x 125 MVA transformers
54
Design
Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)
S.N
Project
Expected
Completion
Date
Status
Main Equipment
Purpose
Peak 2019
2 x 63 MVA transformers (shifted from
55
Q2 2019
Design
transformers 132/33kV at
Design
Reactive Power
57
Compensation Requirements
Q2 2019
Q2 2019
Design
transformers 132/33kV at
Airport Heights grid station
SVC at Hamriyah
Planning
(SVC)
58
Q2 2019
Design
Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)
Expected
S.N
Project
Completion
Date
Status
Main Equipment
Purpose
Peak 2019
60
Design
61
Q2 2019
Design
Q2 2019
Design
Q2 2019
Design
Page | 28
Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)
S.N
Project
Expected
Completion
Date
Status
Main Equipment
Purpose
Peak 2019
64
Design
65
Q2 2019
Design
66
Design
Page | 29
Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)
Expected
S.N
Project
Completion
Date
Status
Main Equipment
Purpose
Peak 2019
67
Q2 2019
Design
Q2 2019
Design
2 no 132kV GIS
69
Planning
70
Q2 2019
Design
Page | 30
Table1 (Continued): Summary of Planned Developments on OETC Transmission System (2016 - 2020)
S.N
Project
Expected
Completion
Date
Status
Main Equipment
Purpose
Peak 2020
71
72
Q2 2020
Q2 2020
Design
Planning
73
Q2 2020
Planning
Q2 2020
Planning
Page | 31