You are on page 1of 1

WATER TRANSMISSION SYSTEM

Contractor
PROJECT NUMBER :

CATHODIC PROTECTION DAILY PROGRESS REPORT Client Engineer


Subcontractor

3
Steel Tanks (2 x 140,000 m )

Month Aug. 2010 PRODUCTION

UNIT
Project Total
Works Total
Working Days 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 Total Production
Done Monthly
Quantity Percentage

MMO anodes Installation m #DIV/0!

Titanium conductor m #DIV/0!

Power feeder cable pcs #DIV/0!

Monitoring tube pc #DIV/0!

Perm. Ref. Elec. For External pc #DIV/0!


EXECUTION

Positive cable laying m #DIV/0!

Negative cable laying m #DIV/0!

Junction box installation pcs #DIV/0!

String anodes installation pcs #DIV/0!

internal CPS equipments % #DIV/0!

Perm. Ref. Elec. For Internal pcs #DIV/0!


Transformer Rec. Unit
pc #DIV/0!
installation

DRAWINGS MATERIALS EQUIPMENT LIST PERSONNEL LIST PERSONNEL LIST

TITLE DOC. # / Status DESCRIPTION on site DESCRIPTION TOTAL MANPOWER OF ESMAS TOTAL Subcon Total

External-MMO anode Transformer rectifier unit 1 Generator 1 Electrical Engineer 1


External-monitoring pipe AC disconnect switch 2 Welding Machine for CP anode 2 Foreman 2
External-power feeder cable Multipurpose junction box 3 Holiday Detector 3 Electrician 3
External-Design doc. 12 Terminal anode JB 4 Helper 4
AC disconnect switch MMO coated titanium ribbon
Multi purpose junction box Titanium conductor bar
20 terminal junction box Permanent Ref. Elec. For Internal Total
Contractor
12 terminal junction box Permanent Ref. Elec. For External
Internal-Design doc. slotted pipe 1

Internal-String anode layout & interanal power feeder cable 2


equipment installations 1cx50mm.sq HMWPE cable 3
direct buried cable installation details 1cx35mm.sq HMWPE cable

transformer rec. enclosure assmebly & 1cx25mm.sq HMWPE cable


foundation details 1cx6mm.sq HMWPE cable Total
Consultant
Cable ties
nylon rope 1
string anode 2
internal CPS equipment 3

Prepared by: DEL Patacsil - Qa/Qc Engr., 8/19/2010, 11:03 AM Page 1 of 1

You might also like