IN HOUSE ESTIMATE
Building Administration Department
RENOVATION OF APARTELLE 18
OPTION 1- Includes total re-tiling from ground to 3rd floor(job out) OPTION 2 -Retained existing flooring at 2nd and 3rd floor(in-house)
GROUND FLOOR
Preparation and Chipping works for tiles installation (ground
1 floor) 45 800.00 36,000.00 45 650.00 29,250.00
2 Painting works for ceiling , walls and column (grd floor) 18 800.00 14,400.00 18 550.00 9,900.00
SECOND FLOOR
Preparation and Chipping works for tiles installation (2nd
1 floor) 73 800.00 58,400.00 73 160.00 11,680.00 USING RUBBERIZED PAINT
.40 x .40 Homogenous tiles 73 73
Painting works for ceiling, walls, column , doors and cabinets
2 (2nd floor) 20 800.00 16,000.00 20 550.00 11,000.00
THIRD FLOOR
1 Preparation and Chipping works for tiles (ground floor) 85 800.00 68,000.00 85 160.00 13,600.00 USING RUBBERIZED PAINT
.40 x .40 Homogenous tiles 85 85
Painting works for ceiling ,walls,column and cabinets(3rd
2 floor) 24 800.00 19,200.00 24 550.00 13,200.00
OTHERS
NOTES/OPTIONS:
- AIRCON IS NOT INCLUDED
OPTIONS:
- REPAINTING OF 2ND &3RD FLOORING IS ALSO AN ALTERNATIVE