You are on page 1of 1

ESTIMATED TOTAL ALLOCATIONS RECEIVED DURING THE TIME-PERIOD (Figures to be checked and

verified with relevant authorities)

DESCRIPTION OF SOURCES & APPLICATIONS OF FUNDS TENDERED/QUOTE

NO SOURCE OF FUNDING AMOUNT PROJECT UNDERTAKEN CONTRACTORS/SUPPLIERS

1 JPPS RM60,000.00 Balai Raya, Kibabaig ? (all decided by 1 person)

2 MP’s Allocation RM50,000.00 Balai Raya, Kibabaig ? (all decided by 1 person)

3 MP’s Allocation RM10,000.00 Kg. Pogun, Electric Posts ? (all decided by 1 person)

4 MP’s Allocation RM4,000.00 Kg. Pogun – Bus stop ? (all decided by 1 person)

5 MP’s Allocation RM7,000.00 Jambatan - Kibabaig ? (all decided by 1 person)

6 MP’s Allocation RM7,000.00 Balai Raya - reclamation ? (all decided by 1 person)

7 JPPS ? RM15,000.00 + Supply of 2 units of Boats ? (all decided by 1 person)

    RM153,000.00+    

The above figures are based on estimates only, waiting to be verified, audited and certified by the JKKK’s
auditors and appropriate authorities, and should be used as a guideline. The JKKK has yet to meet to
appoint a qualified auditors and examiners.

Queries and request for more information should be directed to the following:

The Administration,

Box 35,

89507 Penampang

e-mail address: tab.jkkk@yahoo.com