You are on page 1of 4

APPENDIX - IV

Cost analysis of a sewage treatment plant based on ASP

FLOW 100 MLD


DESIGN 30 YERS FOR RCC & 15 YEARS
PERIOD FOR MECHANICAL AND
OPERATION ELECTRICAL WORK
24 HRS/DAY
HOURS

PRILIMINARY
TREATMENT(SCREENING + CC = 674Q.611 3 CR 45 LACS
1 GRIT REMOVAL)

O & M = .96Q+25038 55 LACS


MAIN UNITS THAT ARE INCLUDED
1 FLOW CHANNELS
2 SUPER STRUCTURES
3 MECHANICAL BAR SCREENS
4 GRINDERS FOR SCREENING
5 GRAVITY GRIT CHAMBER WITH MECHANICAL GRIT HANDELING EQUIPMENT
6 PARSHALL FLUME
7 ELECTRICAL COST
8 FLOW RECORDING EQUIPMENT

PRILIMINARY
SEDIMENTATION WITH CC = -0.00002Q 2 + 19.29Q + 220389 9 CR
2 SLUDGE PUMPS
O & M = 1.69 Q + 11376 80 LACS
MAIN UNITS THAT ARE INCLUDED
1 THE COST INCLUDES THE SLUDGE PUMPS (HEAD 3.05 M)
2 SUPER STRUCTURES
3 MECHANICAL SLUDGE REMOVAL UNITS
4 ELECTRICAL COST

PRIMARY CLARIFIER CC = 2941 Q0.609 14 CR 70 LACS


3
O & M = 3.32 Q + 5842 1 CR 55 LACS
MAIN UNITS THAT ARE INCLUDED
1 CLARIFIER CONSTRUCTION COST
2 SLUDGE RETURN AND WASTE SLUDGE PUMPS
3 ELECTRICAL AND MECHANICAL COST

CONVENTIONAL ACTIVATED
SLUDGE WITH
CC = 72 Q + 368043 34 CR 6 LACS
DIFFUSER(AERATION
4
TANK+BLOWERS)
NOTE: CLARIFIERS & RETURN
O & M = 4.58 Q + 36295 2 CR 23 LACS
SLUDGE PUMPS ARE NOT
MAIN UNITS THAT ARE INCLUDED
1 FLOW CHANNELS
2 PIPING
3 CIVIL WORK FOR TANKS
4 BLOWERS FOR AIR SUPPLY
5 FLOW RECORDING EQUIPMENT
6 ELECTRICAL AND MECHANICAL COST
SECONDARY CLARIFIER CC = 2941 Q0.609 14 CR 70 LACS
5
O & M = 3.32 Q + 5842 1 CR 55 LACS
MAIN UNITS THAT ARE INCLUDED
1 CLARIFIER CONSTRUCTION COST
2 SLUDGE RETURN AND WASTE SLUDGE PUMPS (HEAD 3.05 M)
3 ELECTRICAL AND MECHANICAL COST

CHLORINATION CC = 795 Q 0.598 2 CR


6
O & M = -0.000001 Q 2 + 2.36 Q + 24813 1 CR 15 LACS
MAIN UNITS THAT ARE INCLUDED
1 CHLORINE BUILDING
2 CHLORINE STORAGE & HANDLING FACILITIES
3 CHLORINATORS
4 INJECTORS

GRAVITY THICKENER CC = 177 Q0.68 2 CR 10 LACS


7
O & M = -0.0000003 Q 2 + 0.18 Q + 4136 9 LACS
MAIN UNITS THAT ARE INCLUDED
1 THICKENER
2 MECHANICAL EQUIPMENT

SLUDGE DRYING BEDS CC = 89 Q0.854 7 CR 46 LACS


8
O & M = -0.00002 Q2 + 2.57 Q + 8003 35 LACS
MAIN UNITS THAT ARE INCLUDED
1 THICKENER
2 MECHANICAL EQUIPMENT

MISCELLANOUS STRUCTURES CC = 1438 Q0.567 4 CR 50 LACS


9
O & M = -0.000003 Q 2 + 1.97 Q + 57349 1 CR 2 LACS
MAIN UNITS THAT ARE INCLUDED
1 ADMINISTRATIVE OFFICE
2 LABORATORY
3 MACHINE SHOPES
4 PARKINGS

Total capital cost = 92 crs.

Cost analysis of a sewage treatment plant based on UASBR

FLOW 100 MLD


30 YERS FOR RCC & 15 YEARS
DESIGN
FOR MECHANICAL AND
PERIOD
ELECTRICAL WORK
OPERATION
24 HRS/DAY
HOURS

PRILIMINARY
TREATMENT(SCREENING + CC = 674Q.611 3 CR 45 LACS
1 GRIT REMOVAL)
PRILIMINARY
TREATMENT(SCREENING + CC = 674Q.611 3 CR 45 LACS
1 GRIT REMOVAL)

O & M = .96Q+25038 55 LACS


MAIN UNITS THAT ARE INCLUDED
1 FLOW CHANNELS
2 SUPER STRUCTURES
3 MECHANICAL BAR SCREENS
4 GRINDERS FOR SCREENING
5 GRAVITY GRIT CHAMBER WITH MECHANICAL GRIT HANDELING EQUIPMENT
6 PARSHALL FLUME
7 ELECTRICAL COST
8 FLOW RECORDING EQUIPMENT

PRILIMINARY
SEDIMENTATION WITH CC = -0.00002Q 2 + 19.29Q + 220389 9 CR
2 SLUDGE PUMPS
O & M = 1.69 Q + 11376 80 LACS
MAIN UNITS THAT ARE INCLUDED
1 THE COST INCLUDES THE SLUDGE PUMPS (HEAD 3.05 M)
2 SUPER STRUCTURES
3 MECHANICAL SLUDGE REMOVAL UNITS
4 ELECTRICAL COST

UASBR CC = -0.00004Q2 + 45Q + 3,98,838 22 CR 5 LACS


3
O & M = 14.5 Q + 61,827 90 LACS
MAIN UNITS THAT ARE INCLUDED
1 FLOW CHANNELS
2 SUPER STRUCTURES
3 PIPING
4 VALVING
5 GATES
6 MECHANICAL WORK
7 ELECTRICAL COST
8 FLOW RECORDING EQUIPMENT

CASCADE AERATOR CC = 1 LAC / MLD (Appx.) 1 CR


4
O & M = (.45 LAC / MLD) (Appx.) 45 LACS
MAIN UNITS THAT ARE INCLUDED
1 PIPING
2 SUPER STRUCTURES
3 MECHANICAL WORK
4 ELECTRICAL COST

CHLORINATION CC = 795 Q 0.598 2 CR


5
O & M = -0.000001 Q 2 + 2.36 Q + 24813 1 CR 15 LACS
MAIN UNITS THAT ARE INCLUDED
1 CHLORINE BUILDING
2 CHLORINE STORAGE & HANDLING FACILITIES
3 CHLORINATORS
4 INJECTORS
GRAVITY THICKENER CC = 177 Q0.68 2 CR 10 LACS
6
6
O & M = -0.0000003 Q 2 + 0.18 Q + 4136 9 LACS
MAIN UNITS THAT ARE INCLUDED
1 THICKENER
2 MECHANICAL EQUIPMENT

SLUDGE DRYING BEDS CC = 89 Q0.854 7 CR 46 LACS


7
O & M = -0.00002 Q2 + 2.57 Q + 8003 35 LACS
MAIN UNITS THAT ARE INCLUDED
1 THICKENER
2 MECHANICAL EQUIPMENT

MISCELLANOUS STRUCTURES CC = 1438 Q0.567 4 CR 50 LACS


8
O & M = -0.000003 Q 2 + 1.97 Q + 57349 1 CR 2 LACS
MAIN UNITS THAT ARE INCLUDED
1 ADMINISTRATIVE OFFICE
2 LABORATORY
3 MACHINE SHOPES
4 PARKINGS

Total capital cost = 52 crs.

You might also like