Professional Documents
Culture Documents
2009
PART 4
The procedure is based upon the AASHTO Design Guide (1993) which uses the concept of
Structural Number (SN) to establish the thickness of the overlay. The procedure uses a
correlation between Falling Weight Deflectometer (FWD) deflection measurements and the
Adjusted Structural Number (SNP) of the existing pavement. This correlation must be
calibrated for Kenya conditions.
Where:
SNPDesign = Structural Number for future traffic
SNPExisting = Structural Number of the existing road
a1 = Layer coefficient of asphalt overlay
25.4 = conversion mm to inches
The use of the FWD allows designs to be completed quickly and at relatively low cost. In
common with all overlay design procedures the method described in this must be critically
reviewed and adjusted according to local experience.
The Manual also provides guidance on a method of designing overlays using the Dynamic
Cone Penetrometer (DCP), when FWD results are not available.
Falling Weight Deflectometer A road testing device that generates a pulse load on the road
surface and measures the peak vertical deflection at the
centre of the loading plate and at several radial positions by a
series of sensors.
FWD Falling Weight Deflectometer
Layer coefficient A number (a1 value) to indicate the strength of asphalt, base
course or unbound sub-base layers when calculating the
structural number of a road pavement.
Maintenance measures undertaken to preserve the pavement, consisting
of:
routine: eg grass cutting, ditch & culvert cleaning
recurrent: eg patching, pothole-filling, crack-sealing
periodic: eg re-sealing road, re-gravelling shoulders
The present overlay practice is either to mill the existing surface and overlay with 40-50mm
(periodic maintenance) of asphalt, or to apply a new surface dressing, or to engage
consultants to carry out the overlay design for major projects. The overlay designs
submitted by Consultants are generally based on the methods described in ‘Design of
Pavement Structures’ (AASHTO, 1993).
The proposed empirical overlay design method, described in this , is also based upon the
AASHTO recommendations (1993) and uses the concept of Structural Number (SN) to
establish the thickness of the overlay. The design process is illustrated in Fig 3.1.
The procedure uses a relationship to convert FWD deflection measurements to the
Adjusted Structural Number (SNP) of the existing pavement, allowing designs to be
completed quickly and at relatively low cost.
In common with all overlay design procedures the method described in this recommends a
method to formulate designs which must be reviewed by the Engineer and adjusted based
on his/her own local experience.
• Network level surveys, consisting of roughness and visual condition, carried out to
demarcate road sections of equivalent condition, followed by:
• Project level surveys, more detailed in scope, consisting of visual condition, FWD,
DCP and Test Pit investigations, carried out to determine the level of maintenance
required.
Establish BoQ of
remedial works from Results from Network VCS and Roughness Survey
VCS. identifies sections of road for rehabilitation
-
Carry out nondestructive tests
Project Level VCS
FWD deflections
Traffic count (where necessary)
Axle load survey (where necessary)
Calculate Costs
The inspection is implemented by examining the condition of road cross sections at discreet
intervals, or samples. The condition is evaluated at each sample and combined with a
qualitative assessment of the interval between each sample.
The inspection should be undertaken by a trained engineer who also has knowledge of the
software system that he will use to process the data recorded.
Each sample is subdivided into a number of sub-samples and the distress in each sub-
sample is recorded. The severity of the distress is estimated as the proportion of the total
number of sub-samples affected.
The total number of sub-samples influences the survey precision. The number of samples
influences the reliability of the survey. The level of detail required is governed by the
purpose for the data and the resources available to do the work. For network surveys,
sample points could be spaced at up to 1km spacings, each with 2 sub-sample points. For
project surveys, sample points would be more frequent (from 0.01km to 0.1km spacings),
each sample point having 4 sub-sample points.
Table 4.1 gives details of the assessment criteria, Table 4.2 the roughness values to be
expected, Table 4.3 the recommended threshold values for all the assessment criteria and
Table 4.4 lists the risks associated with these partial surveys and recommended follow-up
work. Table 4.5 is a recommended field form.
For 2-lane roads ( ≥ 5.5m), the defects will be assessed in 4 transverse strips
corresponding to each wheel path, covering the full width of the pavement. For road widths
< 5.5 m wide, such that the inner wheel paths overlap leading to 3 rather than 4 wheelpaths,
the assessment shall be carried out over three strips corresponding to the wheelpaths. The
centre wheel path ratings shall be allocated to both strips 2 and 3.
4 Reconstruction: Broken up
pavement areas, deep potholes,
depressions with cracks and
substantial rutting.
The results of the survey can be evaluated according to Table 4.3 and this will enable the
road sections to be categorised.
Table 4.4: Risks involved and action required on completion of Network Surveys
Class 1 2 3 4
………………
Start of Survey: 1 2 3 4 5 6 7 8 9 10
General Condition 1 2 3 4
Neither the condition of the road shoulders, nor of the drainage are covered in this type of
survey, which refers to bituminous-surfaced roads only.
Any one defect should only be counted once: for example, ‘rutting with cracks should be
counted as “Depressions with cracks” only and not also recorded as “Rutting”. The data
from the VCS is transferred to a spreadsheet that automatically calculates the Bill of
Quantities for the remedial work prior to overlay. Quantities for crack sealing should be
adjusted to an area not affected by previous deep or surface patching.
Prior to overlay a number of these defects will need remedial work. The survey enables the
quantity of materials required to be estimated.
BILL OF QUANTITIES
Start of Survey:
Mean
Sta 0+000 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Unit Sum Quantity
Width
CRACK SEALING
Wide Connected
l.m 0 0
cracks
Alligator Cracks
sq.m 0 0
without Depression
Alligator Cracks with
sq.m 0 0
FULL DEPTH PATCHING
Depression
On Class A, B and C roads, the tests should be carried out at 50 metre intervals. On 2 lane
single carriageway roads the location of the tests should be ‘staggered’ by 25 metres so as to
result in an FWD test every 25 metres along the road.
On Class D and E roads, the tests should be carried out at 100 metre intervals. On 2 lane
single carriageway roads the location of the tests should be ‘staggered’ by 50 metres so as to
result in an FWD test every 50 metres along the road.
Figure 5.2: Steps for carrying out Traffic and Axle Load Surveys
Determine Cumulative
Traffic Volumes over the
Design Period
Estimate Cumulative
Republic of Kenya - Ministry of Roads 15 ESAs
over the Design Period (in
Draft Document – September 2009
one direction)
DESIGN for ROADS and BRIDGES
PART 4 – Overlay Design
2009
The individual weights of each axle of a particular vehicle class are converted to ESA, which
are added to produce a total for the vehicle. It is usual to determine the average ESA for each
vehicle class based on the results of an axle load survey, allowing for the proportions of loaded
and unloaded vehicles in each class. (These may vary in each direction and between routes.)
It is essential that the individual axle weights are converted to ESA before any aggregation or
averaging of data is carried out for either the individual vehicle or for all the weighed vehicles of
a single class.
After the total ESA for each vehicle have been calculated, the average value of ESA is
calculated for the whole vehicle class. These average values of ESA are sometimes termed
“vehicle wear factors” or “vehicle damage factors”.
The total contribution to pavement loading of a vehicle class is the product of the vehicle
damage factor of the vehicle class and the number of such vehicles recorded on the road either
on a daily or annual basis. The process is repeated for the other classes and the total loading
per unit of time is determined by summation.
The Design Traffic Loading in the performance period is calculated from Equation 1:
<5
No 0
> 10 Patch, Seal Cracks, Grinding
< 10
IRI ≤ Min 0 to .3 Patch, Seal Cracks, Surface Dressing [SD]
< 15
<2 < .5 Patch, Seal Cracks, Inlay, Double SD
< 20
.5 to 1 Patch, Seal Cracks, Mill & Replace
All roads vary in pavement thickness and strength along their length. For instance, the strength
of the underlying subgrade will vary along the road alignment as the road passes from areas of
cut to fill. Rehabilitation measures cannot be tailored to each and every variation in road
characteristic, so to produce cost-effective designs the road should be divided into lengths
This procedure is best carried out by using the Cumulative Sum Method (CUSUM) on FWD
central deflection measurements (do). The method involves plotting the cumulative sum of the
differences of the FWD deflection from the mean FWD value calculated from all the results.
The calculations are based on Equation 2 and a worked example is shown in Table 6.1:
S = FWD − FWD +S
i i mean i −1
Where:
The FWD d0 deflection values and CUSUM plot are given in Fig 6.2 and Fig 6.3 respectively.
Error: Reference source not foundA change in slope of the graph indicates a change in
strength along the road. In Fig 6.3 five distinct homogeneous sections can be identified. These
sections should be treated as separate overlay designs.
1.200
1.000
0.800
FWD (D0) @ 50KN
0.000
0.600 0 500
-0.500
0.400
-1.000
0.200
5.4.1 DCP AND TEST PIT INVESTIGATIONS
Cumulative Sum
Destructive testing may be needed after the non-destructive testing is completed to establish
the thickness and strength of the existing pavement layers and relate these to the road failure.
Two methods are available, either the Dynamic Cone Penetrometer (DCP) or Test Pits. Details
of these field methods are presented in Appendices respectively
0.000
-1.500
DCP tests are relatively quick and therefore should be used where there is no risk of damaging
0
0
0
any utilities in the road pavement. The results from DCP tests are particularly useful in
10
20
50
60
70
30
40
80
90
identifying areas of weak base course and sub-base layers which will need deep patching
1
Test pits are best used when the road is to be partially or fully reconstructed. In this case
-2.000
laboratory tests are carried out on the samples collected from the various granular layers in the
road to establish whether they can be used in the reconstruction process.
-3.000
DESIGN for ROADS and BRIDGES
PART 4 – Overlay Design
2009
wheelpath at these chainages to establish the cause of the weakness. Prior to testing a
detector should be used to ensure there are no utilities beneath the test location.
1.200
1.000
DCP Test
0.800
FWD (D0) @ 50KN
The DCP is driven through the road pavement under a standard force to a maximum depth of
approximately 800mm. The strength of the layers is related to their resistance to penetration,
measured as mm per blow, and there are correlations to convert the DCP values to in-situ
values of CBR. The thickness of the road layers are identified by the changes in mm/blow as
the apparatus penetrates the pavement layers.
0.600
Where the in-situ CBR of the granular base course and sub-base are below 80% and 30%
respectively (as measured from the DCP), the base course and sub-base (if necessary) shall
be deep patched. Sometimes it is difficult to differentiate between the base and subbase and
test pits may be necessary as a last resort to determine the layer interval.
0.400
5.5.1 TEST PITS
Where the FWD results indicate that the road should have a thick overlay or be either partially
or fully reconstructed then test pits will be needed. If the road is to be overlaid then the pits
should be dug in areas where the FWD shows the road to be weak.
If the road is to be partially or fully reconstructed the Test Pits should be dug at regular intervals
0.200
where the road is weak. Two test pits would normally be dug in every one kilometre of road.
The test pit data are used to determine the reasons for the weaknesses identified from the
FWD investigation, which could include:
whether the existing granular base course and sub-base meet normally acceptable
0.000
material standards for partial or full reconstruction.
whether the existing granular base course and sub-base meet normally acceptable
0
0
0
20
50
60
70
30
40
80
90
Test Pits will be dug at points in the road where the Detailed VCS and FWD deflection profile
show the road to abnormally weak. The measurements and tests required are listed in Table
6.2.
Table 5.8
Field/Lab Pavement material Test Description Test
Test
Field Asphalt surfacing Thickness
Road base Description
Sub base/Selected Subgrade Moisture Content KS 999 Part 2 2001
Subgrade
Road base Layer density KS 999 Part 9 2001
Sub base/Selected Subgrade
Subgrade
Laboratory Road base Atterberg Limits KS 999 Part 2 2001
Sub base/Selected Subgrade
Subgrade Grading KS 999 Part 2 2001
Sub base/Selected Subgrade Compaction KS 999 Part 4 2001
Subgrade CBR KS 999 Part 2 2001
SN = 0.0394 ∑i a i hi
Where:
ai = Layer coefficient of layer i
hi= Thickness of layer i (mm)
The calculation of layer coefficients for existing pavement layers is based on the stiffness of
bituminous materials and the CBR of granular materials. They are indicated in Tables 6.1 and
6.2.
Table 6.9: Layer Coefficients for Existing Asphaltic Concrete and Granular Materials
MATERIAL SURFACE CONDITION COEFFICIENT, ai
The Structural Number was developed during the AASHO Road Test, which considered the
performance of trial sections constructed over a uniform subgrade having a particular strength.
A further parameter, the Modified Structural Number (SNC) (Hodges et al, 1975), was later
developed to take into account different subgrade strengths. This relationship is defined in
Equation 4:
SNC = SNSG + SN
Where:
SNSG = Structural Number contribution from the subgrade= 3.51 Log10 (CBR) – 0.85 (Log10
(CBR))2 – 1.43
SNC = Modified Structural Number
CBR = In situ CBR of the subgrade.
The AASHO Road Test was carried out in Illinois, USA. The layer coefficient taken for a new
asphalt concrete surfacing during the Road Test was 0.44. This was for asphalt concrete
having an elastic modulus of 3100 MPa at a temperature of 20oC. It is therefore necessary to
derive a strength coefficient suitable for Kenya, where the ambient temperatures, and hence
road temperatures, are different to those in Illinois. This is obtained by calculating the effective
elastic modulus of asphalt concrete using the Shell Method of Weighted Monthly Average
Annual Temperature (WMAAT) (Shell, 1978), shown below. The analysis shows that the layer
coefficient of asphalt concrete used in Kenya should be:
Step 1
Calculate equivalent modulus at the AASHO Road Test site (WMAAT = 15oC) of asphalt
concrete having an elastic modulus of 3100MPa at 20oC tested in laboratory, using the
equation 5:
Step 2
Calculate the elastic modulus of similar material, for instance, in the Coastal Region (WMAAT =
22.5oC) to that in Illinois (WMAAT = 15oC):
Step 3
Calculate layer coefficient of asphalt concrete in the Coastal Region having an elastic modulus
of 2700MPa:
• aT1/aT2 = (ET1/ET2)0.333
Where:
aT1 and ET1 are the layer coefficient and elastic modulus respectively at temperature T1.
Therefore to calculate the thickness of required overlay, the Structural Number of the existing
road (SNExisting) has to be measured. There are a number of ways of doing this, all of which have
various advantages and disadvantages, as enumerated in Table 6.3.
The Structural Number and Modified Structural Number concept, whilst simple in principle,
gives rise to a number of practical difficulties, especially on roads that have been in existence
for many years. When DCP tests and Test Pits are carried out, the boundaries between the
different materials are sometimes indistinct and differentiating base courses from sub-bases,
and sub-bases from the subgrade can be difficult. Changes of strength are expected to occur
when passing from one layer to another but significant changes of strength also occur within
reasonably well-defined layers. When the same pavement is tested with a DCP a more
complex, many-layered structure is often revealed.
This can cause a problem in defining the layers in Test Pits for calculating the Modified
Structural Number. The same difficulty also applies when trying to define the appropriate layer
thickness for back-analysis of FWD data and often makes this form of analysis somewhat
unreliable.
A procedure is therefore required which takes account of the contribution to Structural Number
of a pavement from all the pavement layers and the contribution of the subgrade, which is
independent of where the subgrade boundary is defined. This value is called the Adjusted
Structural Number (SNP) (Rolt and Parkman, 2000).
• it may not be practicable to take sufficient DCP measurements along each road to cope
with the possible high variability found in Kenya, and
• the coarse granular road base in the Kenya roads prevent the instrument’s penetration.
An overlay procedure based on DCP results is described in Section 6.6 for Secondary and
Local roads where FWD results are not available.
As FWD deflection data can be measured very quickly and accurately, the proposed overlay
procedure uses the data to estimate the SNPExisting of the existing road, rather than the DCP.
Previous work (Rolt, 2000) showed that the most effective form of the correlation between FWD
measurements and SNP takes the form below:
12.00
10.00
8.00
The equation above has been used to convert FWD measurements taken from hypothetical
Trial Sites. The predicted values of SNP are shown plotted against the central deflection d0 in
Fig 6.1. The limited scatter around the ‘line of best fit’ (R2 = 0.96) shows the suitability of this
form of general relationship for the analysis of FWD results.
SNP(Existing)
2
R = 0.96
However, to enable the equation above to be used in for Kenya a series of comparative tests
between the FWD and the DCP must be carried out on a selection of Category A and B roads.
6.00
6.4 Overlay Design Procedure using the FWD
The required overlay thickness is calculated based on a comparison of the strength of the road
required for the future traffic and the existing strength of the road, as assessed by FWD
measurements.
4.00
6.4.1 SNP FOR FUTURE TRAFFIC (SNPD )
ESIGN
The first step in the process is to establish the value of Structural Number (SNPDesign) that is
required for each homogeneous section of road for future traffic loading. This is achieved by
using the AASHTO (1993) equation for flexible pavements, shown below:
Table 6.12: AASHTO Design Criteria: Reliability factors and Servicability Indices
Road Class Reliability Standard Terminal Decrease
Deviation PSI in PSI
To use the AASHTO design equation when the Adjusted Structural Number (SNP) is used
rather than SN and subgrade strength separately, the subgrade resilient modulus value must
be assumed at 4325 psi in the equation. This was the subgrade resilient modulus used in the
Road Test and therefore at this value the subgrade contribution is zero. Thus SN is then the
same as SNP. In using either method, the difference between SN and SNP needs to be
understood. In the normal AASHTO design method SN is used rather than SNP. The overlay
procedure described in this Manual uses SNP.
This results in the principle that if any two pavements have the same value of Adjusted
Structural Number (SNP) then they should carry the same level of traffic.
In the following paragraphs that describe the overlay procedure it has been assumed that the
road under investigation is a Category A road with a design traffic loading of between 5-10
million ESA. Therefore, from Table 6.5, the SNPDesign is 5.76.
It is necessary to plot the ‘Structural Deficiency’, that is the difference between the required
design Structural Number of the road (SNPDesign) and the existing Structural Number at each
FWD test (SNPExisting), for each FWD test. This is simply :
After calculation the Structural Deficiency is plotted as a bar chart, which allows the engineer to
identify the following actions for the homogeneous sections based on the criteria given in Table
6.6:
Fig 6.2, the results of an actual FWD survey, illustrates these principles:
Figure 6.8: Structural Deficiency
4.00
No strengthening overlay Patching
2.00
Structural Deficiency
0
0
10
20
30
40
50
60
70
80
If the mean structural deficiency lies in the range ranges from 0 to 0.6 a thin overlay should
be constructed. Points with high structural deficiency should be investigated and deep
-1.00
patched where necessary.
If the mean structural deficiency ranges from 0.6 to 1.5 then a thick overlay is necessary.
The need for some deep patching is also very likely to be required. The thickness design
procedure is described in Section 6.4.3.
-2.00
The need for partial or full reconstruction is less easy to define, but becomes probable if the
structural deficiency is greater than 1.5. Under such circumstances the visual condition
data, DCP and test pit data needs to be re-assessed.
-3.00
The design of roads that require reconstruction should be done in accordance with design
recommendations set out in the Design of New Bituminous, Gravel and Concrete Roads. In
general, roads with good foundations can be partially reconstructed by making use of much
of the existing material in the form of enhanced sub-base or even lower base course layers.
Roads which have a very weak or non uniform pavement structure and or sub-grade
require more-4.00
elaborate remedial works and full reconstruction is possibly required.
The overlay thickness for each homogeneous section is then calculated as follows:
Where:
SD = Standard deviation of the overlay thickness in the homogeneous section
CF = Probability of achieving design life.
Values of CF that should be used for different levels of probability are given below:
A value of 85% is usually recommended. The use of a higher level of probability can result in
overlays being too thick if the road construction is highly variable. In Fig 6.3 a value of 1.037
has been used:
180
160
140
Deep pa
120
thickness (mm)
100
Republic of Kenya - Ministry of Roads 31
Draft Document – September 2009
80
DESIGN for ROADS and BRIDGES
PART 4 – Overlay Design
2009
This procedure should only be used on Secondary and Local roads where FWD data is
unavailable and where the road structure allows the DCP to penetrate the road structure to
a depth of 800mm. The required overlay thickness is calculated based on a comparison of
the strength of the road required for the future traffic and the existing strength of the road,
as assessed by DCP measurements. The following steps should be followed:
1. Establish the value of Structural Number (SNPDesign) that is required for each
homogeneous section of road for future traffic loading. This is done using the AASHTO
(1993) equation in the same way as described in Sections 6.4.2 and 6.4.3. The
resultant values of SNPDesign are given in Table 6.5 for different levels of traffic for
Category B roads and Local roads.
2. Calculate the adjusted Structural Number of the existing road (SNPExisting) from DCP
tests. On Secondary and Local roads, the DCP tests should be carried out at 100 metre
intervals. The location of the tests should be ‘staggered’ by 50 metres to result in a DCP
test every 50 metres along the road. The DCP data shall be analysed in purpose
designed software called UKDCP. This software enables the user to analyse each DCP
test and then calculate the SNPExisting for each test.
4. Calculate the ‘Structural Deficiency’ for each DCP test. The value of Structural
Deficiency is simply the difference between the required design Structural Number of
the road (SNPDesign) and the existing Adjusted Structural Number at each DCP test
(SNPExisting). After calculation the Structural Deficiency should be plotted as a bar chart
and the required actions are described above.
5. Calculate the thickness of overlay for those homogeneous section where a thick
strengthening overlay (>40/50mm) is required. The overlay at each DCP test is
calculated using the equation below. Where no overlay is required at a DCP test, a
value of zero is assigned.
Where a1 = layer coefficient for the asphalt overlay (See Section 6.1.1).
The overlay thickness for each homogeneous section is then calculated using the
following.
Values of CF that should be used for different levels of probability are given in Table 6.7.
Under most circumstances a value of 80% is recommended for Secondary roads and 75%
for Local roads. The use of a higher level of probability can result in overlays being too thick
if the road construction is highly variable.
The type of remedial work will depend on the type of road defect and these are recorded during
the Detailed Visual Condition Survey. The remedial works are summarised in Table 7.1.
2. Wide cracks should be sealed prior to overlay to prevent water entering the granular base
course if reflection cracking occurs.
When deep patching is needed the required minimum thickness of base course and sub-base
materials are given in Table 11. For low levels of traffic, granular base course materials should
be used. However, for higher levels of traffic on Category A and Category B roads a bituminous
base course material can also be used.
Where the high deflections are related to lengths of road with poor or poorly maintained
drainage then these shortcomings should be rectified prior to overlay construction. Details on
the construction and maintenance of road drainage are described in Design for New
Bituminous, Gravel and Concrete Roads.
8 REFERENCES
AASHTO (1993). Guide for the design of pavement structures. AASHTO, Washington DC, USA
HODGES J W, J ROLT and T E JONES (1975). The Kenya road transport cost study: research
on road deterioration. TRL Report 673, TRL, UK.
ROLT J and C PARKMAN (2000). The characterisation of pavement strength in HDM-III and
improvements adopted for HDM-4. 10th REAAA Conference, Tokyo, 2000.
ROLT J (2000). Pavement structural number from FWD measurements for network analysis.
TRL Unpublished Report PR\INT\664\00
9.1.1 DESCRIPTION
The DCP uses an 8 Kg hammer dropping through a height of 575mm and a 60° cone having a
maximum diameter of 20mm. The instrument is assembled as shown in Figure 3.1. The
instrument is usually split at the joint between the standard shaft and the coupling for carriage
and storage and it is important that when in operation the joints do not become loose.
Operating the DCP with any loose joints will significantly reduce the life of the instrument.
1
Key:-
1 Handle
2 Hammer (8kg)
3 Hammer shaft 2
4 Coupling
5 Handguard
6 Clamp ring
7 Standard shaft
8 1 metre rule 3
9 60° cone
Ø 20mm
7
9
9
· 60° INC
9.1.2 OPERATION
After assembly, the first task is to record the zero reading of the instrument. This is done by
standing the DCP on a hard flat surface, such as concrete, checking that it is vertical and then
entering the zero reading in the appropriate place on DCP Test Data Sheet shown in Figure
3.2.
The DCP needs three operators, one to hold the instrument, one to raise and drop the weight
and a technician to record the readings. The instrument is held vertical and the weight raised to
the handle. Care should be taken to ensure that the weight is touching the handle, but not lifting
the instrument, before it is allowed to drop. The operator must let it fall freely and not partially
lower it with his hands.
After completing the test the DCP is removed by tapping the weight upwards against the
handle. Care should be taken when doing this; if it is done too vigorously the life of the
instrument will be reduced.
The DCP can be driven through surface dressings but it is recommended that thick bituminous
surfacings are cored prior to testing the lower layers. Little difficulty is normally experienced
with the penetration of most types of granular or lightly stabilised materials. It is more difficult to
penetrate strongly stabilised layers, granular materials with large particles and very dense, high
quality crushed stone. Penetration rates as low as 0.5mm/blow are acceptable but if there is no
measurable penetration after 20 consecutive blows it can be assumed that the DCP will not
penetrate the material. Under these circumstances a hole can be drilled through the layer using
an electric or pneumatic drill, or by coring. The lower pavement layers can then be tested in the
normal way. If only occasional difficulties are experienced in penetrating granular materials, it is
worthwhile repeating any failed tests a short distance away from the original test point.
If, during the test, the DCP leans away from the vertical no attempt should be made to correct it
because contact between the shaft and the sides of the hole can give rise to erroneous results.
If the lean becomes too severe and the weight slides down the hammer shaft, rather than
dropping freely, the test should be abandoned and the tests repeated approximately one metre
away from the first test. DCP is used extensively for hard materials, wear on the cone itself will
be accelerated. The cone is a replaceable part and it is recommended that it should be
replaced when its diameter is reduced by 10 per cent. However, other causes of wear can also
occur hence the cone should be inspected before every test.
The correlation between DCP readings and CBR value has been determined by a number of
authorities and a selection of these are given in Figure 3.3. Agreement is generally good over
most of the range but differences are apparent at low values of CBR in fine grained materials. It
is expected that for such materials the relationship between DCP and CBR will depend on
material state and therefore, if more precise values are needed it is advisable to calibrate the
DCP for the material being evaluated.
The results can be either be plotted by hand, as shown in Figure 3.3, or processed in a
spreadsheet.
If required the Structural Number of the pavement can then be calculated from the DCP results
using the following general equation.
SN = 0.0394 Σ I aI dI
No of Σ mm No of Σ mm No of Σ mm
Blows Blows Blows Blows Blows Blows
The purpose of carrying out a test pit investigation is to confirm the information obtained from
surface condition survey, and FWD and DCP surveys. Pit digging is a time consuming and
expensive operation and for this reason the location of each test pit should be carefully
selected to maximise the benefit of any data collected.
The responsible engineer will select the number and position of the test pits to establish:
• the thickness and material properties of the road pavement in each homogeneous section
• the thickness and material properties of any lengths of road pavement, within any
homogeneous length, which have been shown to be significantly weaker by either FWD or
DCP testing.
The minimum number of test pits dug in any one homogeneous length of road should not be
less than one every 2 kms. In general the test pits will be dug in the near-side wheelpath. ie the
wheelpath adjacent to the shoulder of the road.
Test pits can be excavated by hand or by machine, depending on the availability of plant and
the test pit programme required. Machine operations are usually more productive but more
costly than methods.
• traffic controllers - a minimum of one at each end of the site (but see above);
• 2 (if machine excavation) or 3 (if excavation) labourers;
• 1 machine operator if applicable;
• 1 driver for vehicle; and
• 1 supervising technician.
A safe working environment should be maintained at all times. Reference should be made to
the appropriate regulations in this regard.
Once it has been decided what testing is to be carried out and the location of the trial pits has
been confirmed, the following procedure should be adopted:
2. Accurately locate position of test pit and record this on the Pavement Test Pit Log (see
Figure G1). Usually, the position of a pit will be apparent after completion due to the
patched surface. However, if long term monitoring is required, a permanent location marker
should be placed at the roadside. Record any relevant details such as surrounding
drainage features, road condition and weather.
3. Define the edge of the test pit and remove surfacing. The required size of pit will depend on
the sample sizes necessary for the selected tests, but it can be increased later if found to
be too small. Usually an area of about 0.8m by 0.8m will be sufficient for excavation, and
the minimum working area required for a backhoe operation will be sufficient for machine
excavations. The edge of the pit can be cut with a jack hammer or pick and the surfacing
‘peeled’ off, taking care not to disturb the surface of the aggregate roadbase. The average
thickness of surfacing should be recorded.
4. If density tests are to be performed, a smooth, clean and even surface is required. It is
important for the accuracy of the test that the layer is homogeneous. For the sand
replacement method, no prior knowledge is required of the layer thickness since this
becomes obvious as the hole is excavated. If a nuclear density meter is used, the thickness
of the layer can either be estimated from previous DCP results or construction details to
determine the depth of testing.
5. On completion of any required density testing, the layer can be removed over the extent of
the trial pit, a visual assessment made of the material and samples taken for laboratory
testing. Care should be taken not to disturb the adjacent lower layer. The thickness of the
layer and the depth at which samples are taken should be measured. All information should
be recorded on the Pavement Test Pit Log.
6. Continue to sample, test and excavate each pavement layer following the procedure above.
Once it has been decided that there is no need to excavate further, the total depth of pit
should be recorded along with any other information such as appearance of water in any of
the layers.
7. All samples should be clearly labelled and proposed tests for the pit materials should be
logged in a sample log book to avoid later confusion in the laboratory.
8. The pit should be backfilled in layers with suitable material which should be properly
compacted. It is often good practice to stabilise the upper layer with cement accepting that
9. The site should be cleared and left in a tidy and safe condition for traffic.
In some cases, the possible tests listed for a given property are alternatives. In other cases all
the tests listed for a given property might be required. The engineer must decide for which
properties information is required and then design a suitable testing programme.
Field tests require testing at the site and possibly further analysis in the laboratory. Laboratory
tests require only sampling in the field. All sampling should be carried out in accordance with
the general guidance of KS 999 or KS 1238, whichever is applicable, as well as any specific
requirements for each test.
Kenya Standards (KS) are quoted where available. Where no Kenya Standard is available, an
alternative is quoted.
These tests will only be required where a slope stability or settlement problem is being
evaluated and will only apply to subgrade materials.
For moisture content determination, the oven-drying method is recommended since it provides
a fundamental measure of the moisture content. Both the `Speedy' and the Nuclear Density
Meter methods require accurate calibration and validation, since they derive the moisture
content by indirect analysis, but they have the advantage of providing instant results. Validation
should always be made with reference to the oven-dry method.
P urpose of Investigation:
500
1000
1500
Layer Functio n: S -Surfacing, R -Roadbase , SB -Sub -b ase, SF -Select Fil l, SGR -Subgrade
Material Description: Subjective assessment of material type and p roperti es
Sa mp le Depth: Depth (range) at which any samples t aken
Tests Requ ired: Note any laborat ory tests required
Remarks: Note any particula r points o f i nterest such as pavement or drain age condition, on si te
t est s (m oisture, de nsit y), evidence of groundwater e tc.