Professional Documents
Culture Documents
Keywords:
This document is the property of Petroleum Development Oman, LLC. Neither the
whole nor any part of this document may be disclosed to others or reproduced, stored in
a retrieval system, or transmitted in any form by any means (electronic, mechanical,
reprographic recording or otherwise) without prior written consent of the owner.
Pipeline Construction Specification Version 2.0
Signed :
CFDH Pipelines
The following is a brief summary of the 4 most recent revisions to this document. Details
of all revisions prior to these are held on file by the issuing department.
TABLE OF CONTENTS
1.1 Purpose............................................................................................................................1
1.2 Changes to the Specification............................................................................................1
1.3 Conflicting Requirements.................................................................................................1
1.4 Exceptions........................................................................................................................1
1.5 Health, Safety and Environment (HSE)............................................................................2
1.6 Quality Assurance............................................................................................................3
1.7 Materials Handling and Control........................................................................................6
1.8 R.O.W. and Trenching....................................................................................................11
1.9 Stringing and Bending....................................................................................................18
1.10 Welding and NDT.........................................................................................................20
1.11 Anti-Corrosion Field Joint Coating................................................................................21
1.12 Lowering-In, Backfilling and Reinstatement .................................................................29
1.13 Road and Wadi Crossings............................................................................................34
1.14 Concrete Coating for Wadi Crossings..........................................................................37
1.15 Permanent Markers and Barriers.................................................................................44
1.16 Station Works...............................................................................................................46
1.17 Cathodic Protection......................................................................................................49
1.18 Quality and Treatment of Hydrotesting Water..............................................................51
1.19 Hydrostatic Testing.......................................................................................................51
1.20 Precommissioning Of Pipelines....................................................................................52
1.21 Work on Live Pipe Systems.........................................................................................53
1.22 As-Built Records and Hand-Over Documentation........................................................53
1.23 Effective Period............................................................................................................55
1.24 Review and Improvement.............................................................................................55
Appendix A Glossary of Definitions, Terms and Abbreviations...........................................56
Appendix B Reference Documents.....................................................................................57
Appendix C: Facilities For Company Personnel..................................................................61
Appendix D: List of Handover and As-built Documentation.................................................64
Appendix E List of Typical Drawings for Pipeline Construction...........................................69
Appendix F CONSTRUCTION REQUIREMENTS FOR GRE PIPELINES.........................95
User Comment Form.........................................................................................................105
1.1 Purpose............................................................................................................................1
1.2 Changes to the Specification............................................................................................1
1.3 Conflicting Requirements.................................................................................................1
1.4 Exceptions........................................................................................................................1
1.5 Health, Safety and Environment (HSE)............................................................................2
1.5.1 Scope 2
1.5.2 General...................................................................................................................................2
1.5.3 HSE Advisor............................................................................................................................2
1.5.4 Specific Pipeline Activities.......................................................................................................3
1.6 Quality Assurance............................................................................................................3
1.6.1 Scope 3
1.6.2 General...................................................................................................................................3
1.6.3 Quality Assurance Team........................................................................................................3
1.6.3.1 Personnel....................................................................................................................4
1.6.3.2 Organisation...............................................................................................................5
1.6.4 Company Inspection...............................................................................................................5
1.7 Materials Handling and Control........................................................................................6
1.7.1 Scope 6
1.7.2 General...................................................................................................................................6
1.7.2.1 Handling, including but not necessarily limited to receipt, checking, lifting, loading,
transport, unloading, stacking, and storage of materials shall be carried out by the
Contractor in such a manner as to avoid any damage and loss of materials. Method
and means of transport and handling (including documentation) shall be subject to
approval by the Company..........................................................................................6
1.7.2.2 Contractor’s material control and storage procedure shall be submitted to the
Company within two weeks of the start of mobilisation on site, for approval.............6
1.7.2.3 Contractor shall give the Company at least 2 Company working days notice in
writing on each occasion when he intends to start transporting Company supplied
materials. A lapse greater than 2 working days shall require re-notification. Pipe can
be removed from Company’s yard 7 days per week during daylight hours, unless
otherwise specified by the Company. Contractor shall provide the Company with a
written confirmation of receipt of all materials (identified by type and quantity) and a
written reconciliation of all materials (identified by type and quality) transported by
them from Company’s storage yard on a weekly basis..............................................6
1.7.2.4 Contractor is required to supply lifting equipment for lifting materials at all locations.
Lifting equipment and operations shall be in accordance with SP-1239....................6
1.7.2.5 Contractor shall appoint a dedicated site-based materials Controller whose sole
function shall be to control and report on the receipt, issue, and stock status of the
Contractor and Company supplied materials.............................................................6
1.7.2.6 Contractor shall not be held responsible for manufacturing defects in Company
supplied materials, but shall be held responsible for any delays to the Work caused
by Contractors failure to report defects discovered during inspection by the
Contractor within 24 hours of such inspection...........................................................6
1.7.2.7 Contractor’s procedures for material receipt and return of surplus materials shall
conform to Company’s materials procurement/administration procedures................6
1.7.3 Pipe Inspection.......................................................................................................................6
1.7.3.1 The Contractor shall visually inspect at the Company storage yards, all pipes
internally and externally for damages, surface defects and defective bevels. The
Contractor shall satisfy himself at this stage of the suitability of each pipe for
welding and shall accept all responsibility thereafter for all damages however
caused.......................................................................................................................6
1.7.3.2 Prior to haulage of pipe from Company’s storage yard, Company and Contractor
shall carry out a joint survey of pipe coating damage and bevel damages. On the
basis of this survey, Company will pay the Contractor a lump sum for repair of all
bevel and coating damage, based on the submitted unit rates in the Schedule of
Rates, in accordance with this specification. For bevel damages between 1 and 3
mm deep, the repair shall be by grinding. For bevel damage depth greater than 3
mm, the repair shall be by re-bevelling......................................................................6
1.7.4 Pipe Handling..........................................................................................................................8
1.7.4.1 Pipe shall not be allowed to drop or strike objects which may damage the pipe
and/or coating but shall be lifted, moved and lowered from one position to another
by suitable equipment. When lifting pipe, non-abrasive wide nylon pipe slings or
special lifting hooks equipped with a non-metallic bevel protectors curved to fit the
curvature of the inside of the pipe shall be used. Temporary attachments for
handling or lifting shall not be welded to any pipe. A spreader bar shall be used for
all bulk pipe lifting/handling (excluding welding operations).......................................8
1.7.4.2 Trucks used to transport coated or bare pipes shall be free of any materials that
might damage or contribute to movement of the pipe during transport. Pipes shall
be protected against truck beds and side metallic posts by means of non-metallic
soft materials. Pipes shall be loaded and stacked on trucks in such a manner that
flexing and shifting of the pipe during transport is avoided. After loading, suitable
non-metallic slings shall be used to tie the pipes securely to the truck. During
transport the tension of these slings shall be regularly checked. Pipe ends shall be
protected from contact with other metallic materials. Contractor shall ensure that no
bevel protectors are lost during transport. Pipes shall only be transported on trucks
(lifting equipment shall not be used to transport pipe)...............................................8
1.7.4.3 Trucks used for loading of pipes will be checked by the Company prior to lifting the
pipes to ensure that the trucks and loading/load securing arrangements comply with
the requirements of PDO’s Transport Manual TOM/04/001, SP-2000 ‘Road
Transport’ and government regulations.....................................................................8
1.7.5 Pipe Stacking..........................................................................................................................8
1.7.5.1 Ground surfaces to be used for stacking of pipe shall be reasonably flat. Stacked
pipes shall be raised above ground surfaces and prevented from movement by
berms of screened sand covered by polyethylene sheeting or by using timber
covered with non-metallic soft materials. When stacked, the bottom layer of pipes
shall be wedged or clipped. Pipes of different diameter, wall thickness, grade or
manufacturer shall be stacked separately. Each stack shall be properly marked to
the satisfaction of the Company................................................................................8
1.7.5.2 Epoxy-coated pipes shall be stacked during transport and storage using rubber or
other suitable separator strips....................................................................................8
1.7.5.3 Pipes shall not be stacked higher than 3.5 metres. Pipes shall be stacked in such a
way that no water is retained inside the pipe during storage.....................................8
1.7.6 Linepipe Specifications...........................................................................................................8
1.7.6.1 Line-pipe shall be manufactured in accordance to DEP 31.40.20.35 and DEP
31.40.20.37 for non critical and critical services respectively. These specify
amendments/supplements to ISO 3183 Specification...............................................8
1.7.6.2 Minimum average pipe length shall be 11.50m as per above DEP. The minimum and
maximum length of pipe shall be between 9m and 13.7m long.................................8
1.7.6.3 Linepipes if required, shall be provided with a factory-applied polyethylene /
polypropylene coating or a factory applied fusion bonded epoxy powder coating.
Each polyethylene / polypropylene coated pipe shall be left bare for a distance of
150 ± 20 mm from each end. Each fusion-bonded epoxy powder coated pipe shall
be left bare for a distance of 80 ± 15mm. Where concrete coating of linepipe is
envisaged, the concrete coating cut back shall be increased by 100mm over and
above the cut back left in the mill coated pipe...........................................................8
1.7.7 Inspection of Materials other than Pipe................................................................................10
1.7.7.1 Upon receipt of any materials, the Contractor shall ensure that they conform to the
required specification and are suitable for their intended application. Any
damage/defects shall be reported to the Company within 24 hours of receipt of
these materials and prior to transportation to the Contractor’s own storage yard.
Visual inspection shall be adequate for this purpose...............................................10
1.7.7.2 In the case of materials delivered in their original sealed crates, Contractor shall only
open the crates to examine the materials upon arrival at his own storage yard,
except in the case of damaged crates which shall be noted and the contents
examined when Contractor takes receipt at Company’s storage yard.....................10
1.7.7.3 If no report is issued for damaged materials 24 hours after receipt (or in the case of
2.3.7.2 above, 24 hours after arrival of materials at the Contractors storage yard),
then the materials shall be considered free from damage and the Contractor shall
be considered liable for any damage reported or found at a later date....................10
1.7.8 Handling of Materials other than Pipe..................................................................................10
1.7.8.1 Materials other than pipe materials such as, but not limited to, valves, fittings,
scraper traps etc., shall be lifted by suitable equipment provided by the Contractor
at Company’s storage yard and at all other locations. When lifting lugs are provided
on materials, suitable lifting hooks shall be used for lifting the materials. It is
prohibited to use delicate parts such as hand wheels, nozzles, etc. for lifting of the
materials..................................................................................................................10
1.7.8.2 Materials other than pipe materials will be issued to the Contractor whenever
possible in their original sealed shipping cases/crates. Blinded openings of materials
shall be kept closed until installation. The blinds shall be replaced by the Contractor
in case of damage during transport or storage........................................................10
1.7.8.3 During transport, materials shall be secured by suitable non-metallic non-abrasive
slings........................................................................................................................10
1.7.8.4 For materials which shall be stored cool and/or dry as required by the manufacturer
or the Specifications, Contractor shall provide suitable storage, transport and
handling facilities in accordance with the requirements of the manufacturer and/or
the Specifications.....................................................................................................10
1.7.8.5 Contractor shall provide a separate fenced storage area for Company supplied
materials. Stored materials shall be protected from ground surfaces by using timber
covered with non-metallic soft materials. Ground surfaces in storage areas shall be
clean and flat. It is prohibited to store and transport fragile materials in more than
one layer..................................................................................................................10
1.7.8.6 Distribution and supply of materials from Contractor’s storage yard to the worksites
shall be limited to quantities required for approximately one day’s production. Timing
of the issue of materials shall be as per the Company approved work schedule.....10
1.7.9 Reconciliation........................................................................................................................10
1.7.9.1 At the end of the project, Contractor shall give reconciliation for all Company
supplied materials issued, detailing materials installed, materials wasted and
scrapped, and surplus materials. Contractor shall compile a list of the surplus
materials, indicating quantity, description and MESC / SAP number when available.
.................................................................................................................................11
1.7.9.2 On approval of the surplus list by the Company, Contractor shall return all surplus
materials to Company’s storage yard......................................................................11
1.8 R.O.W. and Trenching....................................................................................................11
1.8.1 Pipeline Right-of-Way and Working Strip.............................................................................11
1.8.1.1 Scope........................................................................................................................11
1.8.1.2 Survey......................................................................................................................11
1.8.1.3 ROW Width ..............................................................................................................11
1.8.1.4 Planning/Approvals...................................................................................................11
1.8.2 Staking, Clearing and Grading..............................................................................................12
1.8.2.1 Scope........................................................................................................................12
1.8.2.2 Definitions.................................................................................................................12
1.8.2.3 Staking......................................................................................................................12
1.8.2.4 Below and Aboveground Services............................................................................13
1.8.2.5 Clearing the Working Strip........................................................................................14
1.8.2.6 Explosives (not used for blasting as part of the construction work)..........................14
1.8.2.7 Grading the Working Strip........................................................................................15
1.8.3 Trenching..............................................................................................................................15
1.8.3.1 Scope........................................................................................................................15
1.8.3.2 Excavation................................................................................................................15
1.8.3.3 Blasting.....................................................................................................................17
1.8.3.4 Definition of Rock......................................................................................................18
1.8.3.5 Sloping Trenches......................................................................................................18
1.8.3.6 Trench Width............................................................................................................18
1.9 Stringing and Bending....................................................................................................18
1.9.1 Scope 18
1.9.2 Stringing................................................................................................................................19
1.9.2.1 No pipe shall be strung before the trench is excavated to full depth and accepted by
the Company to meet the requirements of this Specification. Pipe shall not be
placed directly on the ground but on wooden skids with proper protective padding.
The skids and protective padding material shall be subject to Company (CSR)
approval. Dragging, skidding or dropping of the pipe is not permitted. Wooden
wedges shall be used to prevent movement of each strung pipe............................19
1.9.2.2 Where possible the skid elevations shall be planned such that minor differences
between grade profile and bottom of trench profile (e.g. at locations where an
increased trench depth is required) can be accommodated without requiring an
additional tie-in. The distance between the trench edge and the pipe string shall be
planned such that safe working space is provided...................................................19
1.9.2.3 Contractor shall be responsible for proper stringing and locating of the pipe by size,
wall thickness, specification and manufacturer. Company may supply line pipe from
different manufacturers. Contractor shall string all line pipe of one manufacturer
before commencing the stringing of line pipe supplied by the second manufacturer.
Pipes of different manufacturers shall not be mixed per line section without prior
approval of the Company.........................................................................................19
1.9.2.4 Contractor shall string the pipe in such a manner so as to cause no interference with
public roads, footpaths, tracks, etc. Suitable gaps shall be left at intervals as
necessary to permit the passage of live stock and/or equipment across the Right-of-
Way and as directed by the Company.....................................................................19
1.9.2.5 Contractor shall layout and measure the pipes such that, the number of pieces cut-
off with less than one metre length is kept to a minimum........................................19
1.9.2.6 The length of pipe string shall be planned with due consideration of thermal
expansion and other expected or accidental movement of the pipe string. Special
attention shall be paid to strings with one or more bends, in view of the inherent
increased risk of failure of skids due to movements of the pipe. Length of individual
pipe strings shall be subject to Company approval and shall generally not exceed 1
km............................................................................................................................19
1.9.2.7 Pipe shall be strung with the use of a spreader bar and two guide lines. (See Section
2.3 for requirements for slings and hooks)...............................................................19
1.9.3 Pipe Bending.........................................................................................................................19
1.9.3.1 Contractor shall make all necessary bends required for proper construction of the
pipeline, following a trigonometric survey to establish the number and degree of
bends required, to ensure that the installed pipe shall conform to the contours of the
pre-padded trench....................................................................................................19
1.9.3.2 Contractor shall, before the start of the Work, submit and demonstrate to the
Company a bending procedure, which shall conform to the recommendations of the
manufacturer of the bending machine. This procedure shall be subject to
Company’s approval. The procedure shall include amongst others, step length,
degrees per pull and method and accuracy of measurement during pulling of the
bend.........................................................................................................................19
1.9.3.3 Elastic bends with radius of curvature less than 500 x D, D being the pipeline
diameter are not allowed unless approved by the Company...................................19
1.9.3.4 The radius of cold bends shall be not less than: ......................................................20
1.9.3.5 The cold bends shall be made by a smooth stretch bending machine. Bends with
ripples with a depth exceeding 0.5 mm, wrinkles and kinks are not acceptable.
Contractor shall provide a procedure for measuring ripples which shall be approved
by the Company.......................................................................................................20
1.9.3.6 The pads, dies and rolls of the bending equipment shall have soft surfaces to avoid
damage to the pipe coating. Where applicable, fully retaining bending shoes shall
be used. Roller type bending machines are preferred. Bends in pipe of diameter 8"
or greater shall be made by using an internal (hydraulic or pneumatic) mandrel.....20
1.9.3.7 All bends shall be tested in the presence of the Company with a gauging plate of
97.5% of the nominal internal diameter of the pipe prior to installation....................20
1.9.3.8 The procedure for bending shall be such that the extremities of each joint remain
straight over a minimum distance of 2 m or twice the pipe diameter, whichever is
greater. Contractor shall lay out and measure the pipe for bending such that the
length of off-cuts is kept to a minimum....................................................................20
1.10 Welding and NDT.........................................................................................................20
1.10.1 Scope 20
1.10.2 Off-Plot Pipelines................................................................................................................20
1.10.3 On-Plot Pipework................................................................................................................21
1.11 Anti-Corrosion Field Joint Coating................................................................................21
1.11.1 Scope 21
1.11.2 Materials..............................................................................................................................21
1.11.2.1 Only materials supplied by Company approved manufacturers shall be used in the
Work........................................................................................................................21
1.11.2.2 Contractor shall as a minimum follow manufacturer’s recommendations regarding
material storage, application methods, equipment, spares and tools. Contractor
shall submit for Company approval and demonstrate to the Company, the proposed
work methods for coating application and coating repair, two weeks prior to
application................................................................................................................21
1.11.2.3 The materials, at time of application by the Contractor, shall not be older than the
shelf life stated by the manufacturers......................................................................21
1.11.2.4 The coating materials shall be properly packed and clearly marked with:..............21
1.11.2.5 Coating materials shall be kept dry and stored as long as possible in the
manufacturer’s original packaging, not exposed to direct sunlight, and in accordance
with manufacturer’s instructions...............................................................................22
1.11.2.6 The list of Company approved wrap-around shrink sleeves is given in the Approved
Vendors, Manufacturers and Equipments (AVME) list of the company...................22
1.11.3 Surface Preparation............................................................................................................22
1.11.3.1 Prior to coating, the field joint area shall be blast cleaned. Surface preparation,
including blast cleaning, shall be carried out in accordance with SP-1246 and this
specification.............................................................................................................22
1.11.3.2 The blast surface visual appearance shall conform to ISO 8501 grade Sa 2 1/2.
Any field joint not coated within 4 hours of grit blasting shall be reblasted prior to the
application of the coating.........................................................................................22
1.11.3.3 The surface profile attained by the grit blasting shall conform to ISO 8503-2 and
shall be 40-75 microns peak to trough or as specified by field joint coating
manufacturer............................................................................................................22
1.11.3.4 The surface cleanliness shall conform to ISO 8502-1 to 4 and shall be such that
the chloride contamination is less than 20 mg/m2...................................................22
1.11.3.5 Coating of the field joint shall not take place until the weld has been non-
destructively tested and approved by the Company................................................22
1.11.4 Shrink Sleeve Application...................................................................................................22
1.11.4.1 Contractor shall propose the application procedure for Company approval. The
application procedure shall be in accordance with manufacturer’s instructions and
the minimum requirements specified below, whichever are the most stringent, and
shall be demonstrated to the Company prior to field application by means of a
procedure qualification test joint...............................................................................22
1.11.4.2 The joint shall be heated to a temperature required by the procedure. Induction
heaters, ring burners or propane torches of a suitable type may be used for pipe
diameters smaller than 16". Induction heaters shall be used for pipe diameters of
16" and larger where the pre-heat temperature exceeds 100° C. In all other cases
burners or torches may be used. Torches may be used for tie-in welds at
Company’s discretion. To check that the required preheat temperatures have been
achieved, a digital contact thermometer shall be used............................................22
1.11.4.3 The sleeve shall be wrapped entirely around the joint. The closure patch shall be
positioned off to one side of the pipe. There shall be a minimum overlap of 50 mm
onto the factory applied coating...............................................................................22
1.11.4.4 The procedure for shrinking the sleeve shall ensure that all entrapped air is forced
out at either end using gloved hands and hand rollers. Special attention must be
given to the closure patch and overlapping areas....................................................23
1.11.4.5 The installed sleeve shall be left undisturbed for 4 hours or until the adhesive has
been solidified, whichever is the longer...................................................................23
1.11.4.6 The sleeves shall be visually inspected for the following points:............................23
1.11.5 F.B.E. Application...............................................................................................................23
1.11.5.1 The mill applied epoxy coating of the linepipe shall be applied in accordance with
DEP 31.40.30.32. The epoxy material for the field joints shall be compatible with the
linepipe coating and shall conform to the material requirements of DEP 31.40.30.32.
.................................................................................................................................23
1.11.5.2 Contractor shall propose the application procedure for Company approval. The
application procedure shall be in accordance with manufacturer’s instructions and
the minimum requirements specified below, whichever are the most stringent, and
shall be demonstrated to the Company prior to field application by means of a
procedure qualification test joint. Contractor shall also submit test data to
demonstrate that the applied coating satisfies the requirements DEP 31.40.30.32,
with respect to:.........................................................................................................23
1.11.5.3 The resin powder shall be stored in waterproof containers which are insulated and
cooled by refrigeration or air conditioning to a temperature not exceeding 27°C.
Temperature recorders shall be used to monitor the storage temperature inside
each container. During the daily powder coating operations, the powder in the fluid
bed can be kept at ambient temperatures up to 85°C, but must be returned to the
normal storage temperature below 27°C at the end of the day. For any powder that
has temporarily experienced temperatures in excess of 27°C, gel time tests as per
first few joints and at each change or replenishment of grit. Before applying the
coating, the surface shall be free of rust or residual grit. The surface profile shall be
evaluated from the replicas in accordance with manufacturer’s instructions, using a
recently calibrated micrometer. As an alternative to the above, the Company may
allow the surface profile to be tested on site by a suitable profile gauge in
accordance with SP-1246........................................................................................26
1.11.7.4 Additionally, general checks at random shall be carried out such as monitoring of
particle size of copper slag, grit/shot used for blast cleaning, cleanliness of materials
used for blast cleaning and coating, and temperature control of the pipe surface.. .26
1.11.7.5 Contractor shall supply all equipment required for inspection and testing including
dry film thickness gauges and holiday detectors. All equipment shall be approved by
the Company prior to use.........................................................................................26
1.11.7.6 Shrink Sleeves Testing...........................................................................................27
1.11.7.7 Fusion Bonded Epoxy Testing................................................................................27
1.11.7.8 Holiday detection of 100% of the surface area of all coated pipeline shall be carried
out immediately prior to lowering in the ditch. The holiday detection equipment
which shall be Company approved shall be set at 2000 Volts DC for Fusion Bonded
epoxy and 22000 Volts DC for PE coated pipes based on 5V per micron of coating
thickness. However, the voltage setting for holiday detection may be lowered
slightly at Company’s discretion if coating gets damaged. The electrode shall be a
conductive rubber or a spiral metal ring. Brush type electrodes shall not be used.
The voltage applied by the holiday detection equipment shall be measured by
means of a voltage read out. Alternatively a means of calibration of the applied
voltage of holiday detection equipment shall be provided to enable daily calibration
of each piece of equipment. All holidays, imperfections and damaged areas shall be
identified with a waterproof marker at sufficient distance from the defect to allow
surface preparation and patching to take place without detriment to the adhesion of
the coating...............................................................................................................28
1.11.7.9 Company will carry out a ‘Pearson Survey’ to check the integrity of the buried
coating. If coating defects are found on any portion of the coating, Contractor shall
excavate, repair and backfill at Contractor’s expense..............................................28
1.12 Lowering-In, Backfilling and Reinstatement .................................................................29
1.12.1 Scope 29
1.12.2 Pre-Padding........................................................................................................................29
1.12.2.1 All trenches shall be padded before lowering in of pipe string. No padding shall be
placed until the Company has inspected and approved the trench bottom..............29
1.12.2.2 To ensure that fine and clean padding material is used, the Contractor shall use
mobile screening plants that enable a continuous direct application of padding from
the plant to the trench. The type of screening plant is to be approved by Company
prior to mobilisation to site (minimum sieve size shall be 5 x 5 mm). Mobile
screening plants are defined as screening plants which move along the trench whilst
they are in operation. Only in those areas where mobile screening plants cannot be
used due to access problems, pre-screened material may be used after approval of
the source by the Company. Pre-screened material shall be stored in areas which
have been cleared of rocks and stones and protected with plastic sheets to prevent
contamination with unacceptable padding materials................................................29
1.12.2.3 The installed padding material shall be free of sharp rocks, stones, metal parts,
roots, clods, etc. and without sharp edges which could damage the pipeline. Base
materials from which pre and post padding material will be produced shall consist
mainly of sandy material. More than 75% by weight of the screened material should
have grain size between 0.06 and 3.0 mm and no more than 25% by weight shall
have a grain size between 3.0 and 5.0 mm. To ensure compliance with the above
requirements, the Contractor shall produce a grading curve with typical screened
material from the proposed source of sand or a representative section of the
working strip. If the base material is not sourced from the working strip, sources of
padding material shall first be approved by the Company. Suitable base material
from the working strip may not always be available or acceptable, in which case it
shall be Contractor’s responsibility to obtain suitable padding material from a source
approved by the local government authorities. Near residential areas and roads,
padding material shall be dust free (e.g. 'coarse sand' with a minimum grain size of
0.6 mm) in order to avoid inconvenience or danger to the public.............................29
1.12.2.4 The bottom of the trench shall be padded with sand throughout its length, whether
in normal ground or rock, so as to provide a minimum compacted padding thickness
of 150 mm below the invert of the pipe. Contractor shall keep the pre-padding
operation within 1 km of the lowering-in operation...................................................29
1.12.3 Lowering-in and Post-Padding............................................................................................29
1.12.3.1 Welded pipe strings shall be lowered-in within 96 hours of completion of joint
coating.....................................................................................................................29
1.12.3.2 Immediately before commencing the lowering-in operation, the coating shall be
checked for holiday and if necessary, repaired to the satisfaction of the Company,
as specified in Section 2.7.6....................................................................................29
1.12.3.3 Wide non-abrasive slings or belts shall be used in all lowering-in operations and
care shall be taken when removing the slings from around the coated pipe after it
has been lowered into the trench. Any damage caused to the pipe and coating
during lowering operations shall be repaired before backfill commences................29
1.12.3.4 The trench shall be maintained in a dry condition during lowering-in and backfill
operations................................................................................................................31
1.12.3.5 Contractor shall take measures to restrain the pipe in the trench by means of
‘plugging’, i.e. placing sand on top and around the pipe at regular intervals (one 2m
‘plug’ on every welded joint) or Company approved equivalent method. Contractor
shall plan the work such that the lowering in and ‘plugging’ operations take place
during the hottest part of the day. Company may, at its sole discretion, waive the
requirement for ‘plugging’ and allow the post-padding operation to be executed as
one continuous operation, dependant on completion time and ambient temperature
considerations..........................................................................................................31
1.12.3.6 Sand padding shall be placed around and above the pipe, so as to fill the trench to
a depth of 300 mm above the crown of the pipe, with the sand padding shaped to its
natural angle of repose and with a minimum of 150 mm at any point around the
pipe. No pipe shall be left overnight in the trench without sand padding around and
above the pipe.........................................................................................................31
1.12.3.7 Where the trench has been excavated through or along drive-ways, walk ways,
roads, etc. and at live stock passage ways and other locations indicated on the
drawings, the sand padding shall be thoroughly compacted by watering and
Company approved hand tools, to achieve a compacted sand fill around the pipe
and up to 300 mm above the crown of the pipe.......................................................31
1.12.4 Tie-ins.................................................................................................................................31
1.12.5 Backfilling............................................................................................................................31
1.12.5.1 The trench shall not be backfilled until the Company has approved the sand
padding around and above the pipe and has approved starting the backfilling
operation. Backfilling shall be performed as soon as possible after padding has
been approved.........................................................................................................31
1.12.5.2 In areas containing buried cables, backfilling shall not be performed until all tiles
have been replaced and protected and/or all cables have been supported to
Company’s satisfaction. The backfill around all underground services shall be
thoroughly compacted by hand................................................................................31
1.12.5.3 The material used for initial backfill shall be from the screening plant or other loose
material not greater than 100 mm in diameter, all subject to Company approval. The
fill material shall be placed in such a manner as to avoid disturbing the sand
padding and excessive penetration (more than 150 mm) of rocks into the sand
layer. Contractor shall demonstrate that his proposed method of backfilling achieves
this requirement. The initial backfill shall be placed in the trench to a level slightly
above surrounding ground.......................................................................................31
1.12.5.4 After the initial backfill, the remaining excavated material shall be neatly crowned
over the trench (the windrow), except in wadi areas. Where rock is excessively
large, in Company’s opinion, shall be removed from site and not used as windrow
material. On either side of road crossings, the windrow shall be tapered from full
height to ground level to improve the visibility of drivers on the ROW.....................31
1.12.5.5 Trenches crossing ditches shall be backfilled with the material excavated from the
trench at the location. If the excavated material, in Company’s opinion is not
suitable for backfilling, Contractor shall provide and use suitable material from
another source. Ditches with lined or otherwise improved surfaces shall be
resurfaced in a manner satisfactory to and approved by the Company and the
Authorities. Backfill in or on banks of ditches, wadis shall be compacted as
necessary to prevent soil erosion or other damage which might be caused by the
construction of the pipeline......................................................................................32
1.12.5.6 Where the trench has been excavated through or along drive-ways, walks, roads,
etc., and at live stock passage ways and other locations indicated on the drawings,
the initial backfill shall be thoroughly compacted by mechanically tamping the
material into place. The surface of such areas shall be stabilised and/or restored to
its original condition to the satisfaction of the Company and the Authorities...........32
1.12.5.7 ‘Sloping trenches’ (see Section 2.4.3.5) shall be backfilled as shown on Standard
Drawing TYP 3 0015 001.........................................................................................32
1.12.6 Stabilising Sand Areas........................................................................................................32
1.12.7 Livestock Passageways......................................................................................................32
1.12.8 Reinstatement.....................................................................................................................32
1.12.8.1 Contractor shall clean-up the Working Strip and all working areas used by the
Contractor regularly during the course of the work, and shall restore the lands
traversed, to the satisfaction of the Company. Areas of soft sand in the continuous
6 m wide vehicle access strip shall be removed and replaced by approved infill
material so as to leave the vehicle access strip in a safe condition for driving. The
vehicle access strip shall be deviated at road crossings in order to give a visual
indication to drivers of the presence of the road......................................................32
1.12.8.2 The excess soil in the working strip shall be levelled in a manner satisfactory to the
Company. All loose rock exposed by the construction operations which is scattered
over the working strip or adjacent property shall be removed and placed over the
windrow. However, rocks larger than 750mm in diameter shall not be placed directly
on the backfill material, but may be placed next to the windrow..............................32
1.12.8.3 All creeks, water courses, wells, syphons, drains, streams, wadis, ditches and
irrigation channels shall be reinstated by the Contractor to their former condition and
their banks shall, if deemed necessary by the Company, be pitched with stone
and/or faced with special protection to prevent washing out or erosion...................34
1.12.8.4 All enclosures, walls, gates, etc. shall be restored by the Contractor to at least as
good a condition as they were prior to the commencement of the Contractor’s
operations to approval of the Company...................................................................34
1.12.8.5 All private roads, bridges and other private structures used by the Contractor for
access or haulage shall be restored by the Contractor to a condition equal to or
better than that which existed prior to the commencement of the Contractor’s
operations................................................................................................................34
1.12.8.6 Construction roads, used at escarpments, may be required by the Company to be
left as they are.........................................................................................................34
1.12.8.7 Construction markers shall not be removed, unless requested by the Company.. .34
1.12.8.8 All rubbish/debris left over after removal of camp facilities shall be removed to
designated scrap dumps. The sites shall be levelled and cleared in accordance with
the Regulations for Pipeline Contractor Camps in the Interior and to Company’s
satisfaction...............................................................................................................34
1.13 Road and Wadi Crossings............................................................................................34
1.13.1 Scope 34
1.13.2 Road Crossings..................................................................................................................34
1.13.2.1 The carbon steel pipeline shall cross all roads and highways, without the
installation of casings. All road crossings shall be made by the open cut method.
Trench less methods such as horizontal drilling, pipe jacking may be considered for
major road crossing to avoid disruption of traffic.....................................................34
1.13.2.2 The construction of road crossings shall meet the requirements of API RP 1102
latest issue and shall be installed as shown on the drawings. The crossings shall be
installed to meet at all times the requirements and conditions set forth by the
Authorities having jurisdiction...................................................................................34
1.13.2.3 Contractor shall install an off-set diversion road, when specifically permitted or
required to do so by the Company and/or responsible Authorities and provide
adequate maintenance to ensure safe passage of vehicles. The diversion shall not
cross the pipeline where it has already been installed.............................................34
1.13.2.4 Contractor shall at all times and at every unfinished road crossing provide
adequate and proper traffic aids, such as warning signs, and other safeguards to
the satisfaction of the Company and the Authorities to ensure safety of the public.
All warning signs shall be in both Arabic and English language...............................34
1.13.2.5 Contractor shall comply with the following minimum requirements of the Directorate
General of Roads for major road crossings:............................................................34
1.13.3 Wadi-Crossings...................................................................................................................35
1.13.3.1 ‘Wadi’ shall mean dry river bed which could be temporarily filled with water
following rain. The wadis will be identified on the Alignment Sheets as ‘Flood plains’,
‘Wadi type ‘A’’, ‘Wadi type ‘B’’, or ‘Wadi type ‘C’’. Pipe installed in ‘Flood plains’
does not require casing protection, but shall be stabilised at 3 meter intervals by
means of bags of dry cement/sand mix placed on top of the pipeline. The
Contractor shall demonstrate by calculations that the weight of the cement bags
and soil overburden (excluding the windrow and post padding) is sufficient to
counteract the buoyancy force of the pipeline in empty condition. Wadis may be
classified based on judgement and careful evaluation of the crossing location with
due consideration to wadi’s width, bed slope, past discharge history and erosion
potential at the crossing location. The wadi types are described below...................35
1.13.3.2 Wadi crossings shall be installed to meet at all times the requirements and
conditions issued by the Authorities having jurisdiction in the area.........................35
1.13.3.3 All concrete coated pipes shall be electrically tested on site prior to installation in
order to demonstrate that there is no contact between the reinforcing steel and the
pipe steel. The concrete shall be applied in accordance with Section 2.10, following.
.................................................................................................................................35
1.13.3.4 At locations where concrete protection has been applied, the trench shall be
backfilled with coarse gravel and rock with a minimum dimension of 50 mm up to a
level 500 mm below grade level...............................................................................35
1.13.3.5 For type `C` wadi-crossing, gabions consisting of packages of boulders with
dimensions between 100 and 200 mm contained in galvanised, coated steel wire
mesh, shall be placed on top, up to grade level over the full width of the trench. The
type of wire mesh shall be approved by the Company prior to use.........................36
1.13.3.6 Normally the windrow shall not be installed over the pipeline through the wadi
section. However for wide wadi crossings, greater than 100m, the windrow shall be
installed intermittently in order to mark the location of the pipeline (Windrow lengths
shall be approximately 25m at 75m intervals)..........................................................37
1.14 Concrete Coating for Wadi Crossings..........................................................................37
1.14.1 Scope 37
1.14.2 General...............................................................................................................................37
1.14.2.1 Contractor shall be responsible for the supply and installation of all concrete
coatings, including all associated handling and transport of linepipe etc. Contractor
shall furnish all materials, equipment, labour, supervision, worksite and services
incidental to and necessary for the application of concrete in accordance with this
specification and all subject to Company approval..................................................37
1.14.2.2 The concrete shall have a minimum dry density of 2400 kg/m3 after 28 days. The
minimum thickness shall depend on the pipe outside diameter as specified below:37
1.14.2.3 The mill identity of each pipe length shall be preserved and records kept during and
after the coating process. A certified permanent record shall be supplied to the
Company showing the serial number, average outside diameter, length and all
weights.....................................................................................................................37
1.14.2.4 The concrete coating of line pipe shall be applied either in an approved coating
plant or in the field, at Contractor’s option. Field application shall be by dry mix
gunite technique or Company approved equivalent. The plant application procedure
and the coating plant may involve methods other than guniting and shall be
Company approved..................................................................................................37
1.14.3 Concrete Materials..............................................................................................................39
1.14.3.1 The cement shall be ordinary Portland cement conforming to BS EN197 or ASTM
C150. Cement which is held in stock for longer than three months, or any cement
which shows signs of deterioration, partial setting or other defects or which fails
when tested, shall be rejected.................................................................................39
1.14.3.2 Aggregates shall be naturally occurring washed sand and shall be hard, dense,
durable, clean, sharp and graded evenly from fine to coarse, as per the grading
limits specified below, and be in compliance with BS 882. If in the opinion of the
Company, the aggregate contains an undesirable proportion of chemicals, dust,
clay, organic matter or other undesirable constituents, the consignment shall be
rejected. The grading of aggregate when plotted against sieve size shall be within
the limits tabulated below: .......................................................................................39
1.14.3.3 Water for use in concrete shall be clean and free from all substances which may be
injurious to concrete or steel. It shall satisfy the requirements of BS 3148 and
contain no staining or colouring...............................................................................39
1.14.3.4 Reinforcement of concrete coating shall be by one layer of electrically welded
galvanised steel mesh fabric reinforcement to BS 4483. Maximum mesh dimensions
shall be 38mm x 38mm x 2 mm wire diameter. The minimum overlap between two
consecutive rolls of mesh shall be 50 mm except at field joints where no overlap is
required. The reinforcement shall be placed at the centre of the concrete coating
layer by using P.V.C. spacer blocks or a Company approved equivalent. The
reinforcement shall be clean, free from scale, mud, grease, hardened rebound or
anything likely to destroy adhesion or promote corrosion........................................39
1.14.4 Application...........................................................................................................................39
1.14.4.1 Prior to concrete coating, Contractor shall apply a protective layer or ‘barrier coat’
to epoxy coated pipe. The type of barrier coat to be used shall be a two component
fibre reinforced cementetious coating such as FBE Brushcrete, Fosroc H.I.M,
Epoxytar, Rezex water based epoxy coating ES2 or equivalent. Contractor shall
demonstrate to the satisfaction of the Company that the proposed barrier coat
prevents the occurrence of holidays in the epoxy coating due to the concrete
application process, and promotes a good bond between the epoxy and concrete
coating.....................................................................................................................39
1.14.4.2 Batching, proportioning and mixing of the materials shall be such that a concrete
coating is provided with the minimum specified strength and density. No batch of
cement and aggregate shall be used in the work if it has stood for more than half an
hour after mixing. No rebound material shall be mixed into any batch.....................40
1.14.4.3 Contractor shall pay attention to the moisture content of the sand used for guniting.
If the sand is too wet, the hose will block and a mortar layer will build up inside the
gun. If the sand is too dry the cement will not adhere to the sand grains on mixing
and excessive separation will occur in the hose. In case the moisture content falls
outside the critical range of 5 to 8%, Contractor shall make the sand suitably damp
either by spraying the dry sand with water or mixing wet sand with specially
supplied dry sand.....................................................................................................40
1.14.4.4 The mixing equipment shall be capable of providing a uniform mix. The dry mix
used for guniting shall be screened to prevent inclusion of stone, flakes from the
mixer drum, pieces of cement bag, etc. Mix temperature shall not exceed 32°C....40
1.14.4.5 Concrete shall not be placed until:..........................................................................40
1.14.4.6 Since the technique of guniting relies significantly on the skill of the nozzle man, he
shall have at least 3 years experience in work of a similar nature. Other operators of
the guniting crew shall have a minimum of one year’s experience. Written evidence
of such experience shall be furnished to the Company. Contractor shall have a
minimum of five years experience in guniting or alternatively shall subcontract the
guniting work to a specialist Sub Contractor with similar minimum experience level.
The guniting crew shall demonstrate their ability to consistently coat pipe to this
specification by guniting at least three separate quarter length pipe samples prior to
start of production....................................................................................................40
1.14.4.7 Before directing the guniting nozzle onto the pipe surface the nozzle man shall
ensure that the proportioning of water and dry mix is correct. Further regulating of
the water supply should be kept to a minimum to ensure uniform concrete quality.
The nozzle shall be held in the optimum position for placement at all times i.e. 0.6 to
1.2 m from and at right angles to, the surface of the pipe........................................40
1.14.4.8 The outer surface of the concrete coating shall be smooth, without corrugations
and concentric with the steel pipe. At both ends of each pipe, a distance of approx.
0.30 m from the end shall be completely left free of concrete to facilitate field joints.
The concrete shall taper back from these points at a two-to-one slope until the
required thickness of coating is reached..................................................................40
1.14.5 Curing42
1.14.5.1 The finished concrete coating shall be completely protected from wind, draught,
rain, spray, etc. for a minimum period of 7 days by wrapping with suitable hessian
or polyethylene sheeting. Also during this period the pipe shall not be exposed to
direct sunlight and/or temperature below freezing point. After a period of 4 hours
from placement and for the 7 days curing period, the concrete surface shall be kept
wet...........................................................................................................................42
1.14.5.2 The concrete coated pipe shall not be lifted or transported from the curing area
during the 7 day curing period. The Contractor shall take precautions to prevent
detrimental movement of line pipe after concrete coating to minimise handling
stresses whilst concrete is hardening and curing.....................................................42
1.14.5.3 For factory applied coating, any other curing methods apart from that mentioned in
2.10.5.1 may be adopted subject to approval of the Company................................42
1.14.6 Inspection and Testing........................................................................................................42
1.14.6.1 Every length of coated pipe shall be inspected visually and by spiral ring holiday
detector and repaired, in accordance with Section 2.7, Anti-Corrosion Coatings,
prior to concrete application.....................................................................................42
1.14.6.2 The concrete shall be visually inspected immediately after the application and after
approximately 3 days. If concrete is faulty, Contractor shall remove cores from the
suspected pipe. If the compressive strength tests of the cores fail to meet the
specified strengths, Contractor shall remove the defective coatings by Company
approved method, inspect and where necessary repair the corrosion coating or
reapply the concrete coating. Contractor may optt not to wait for the test results and
immediately initiate the stripping and subsequent coating repair work....................42
1.14.6.3 Test panels, made from mild steel, shall be made every day, one at the start of
work, and one during the day as instructed by the Company. These test panels
shall be positioned alongside the work and in a position similar to the work
(horizontal, vertical or overhead) and gunited. On a regular basis, to be decided by
the Company, cores shall be taken from each test panel after it has cured in a
similar manner as the coated pipe...........................................................................42
1.14.6.4 Core samples shall be obtained using a diamond core cutter set to ensure that the
cut is perpendicular to the surface and fitted with a positive depth of cut limit to
ensure that the core barrel shall not penetrate closer than 6 mm to the corrosion
coat of the line pipe, where applicable.....................................................................42
1.14.6.5 The thickness of applied concrete coating shall be measured on every joint at three
or more points to check compliance with the minimum requirements as per Section
2.10.2.2. The three points shall be spaced at approximately equal intervals with
distance between the end points at least eighty (80) percent of the coated length.
Concrete coatings not in accordance with the dimensional requirements shall be
repaired or stripped and recoated at the discretion of the Company.......................43
1.14.6.6 Factory applied coated pipes shall be weighed and weight of each coated pipe shall
have a tolerance of +10% on any one joint and a tolerance of –4% on the total
length as calculated from the specified density and thickness. Weighing devices
used to determine the weights of the coated joints shall be certified in writing to
provide an accuracy of one half on one percent (0.5%)...........................................43
1.14.6.7 Effective electrical separation between reinforcing steel and pipe shall be
determined for each pipe joint by electrical tests.....................................................43
1.14.7 Concrete Coating Repairs..................................................................................................43
1.14.7.1 Concrete coating that is found to be defective at the time of coating shall be
immediately stripped from the pipe and the pipe recoated. All other defects shall
only be repaired once the concrete has hardened...................................................43
1.14.7.2 Defective concrete coating areas affected by spalling due to compression or
shearing caused by impact against other objects which have caused a loss of not
more than twenty five percent (25%) of the total thickness of the coating shall be
repaired. An area of less than 0.1 m2 per joint where the concrete remaining on the
joint is sound shall be accepted without repairs. Should the area affected be more
than 0.1 m2 and less than 0.33 m2 per joint, the concrete remaining in place over
that area shall be undercut so as to provide a key lock for the same basic material
as the coating. Should the damaged area be more than 0.33 m2 per joint, the
coating shall be removed around the entire periphery of the line pipe throughout the
entire damaged area and repaired...........................................................................43
1.14.7.3 Concrete cracks that are in excess of 1.5 mm in width and extend over 180°
circumferentially around the pipe, or where cracks are over 330 mm in length
longitudinally along the pipe irrespective of width, shall be repaired. Repairs shall be
made by chiselling the crack out to width of not less than 25 mm throughout the
length of the crack. The crack shall be repaired with materials similar to that from
which the coating is made and in a manner similar to that outlined above..............43
1.14.7.4 Core sample holes shall be repaired with materials similar to that from which the
coating is made and in a manner similar to that outlined above. The repairs shall be
kept moist and allowed to remain undisturbed for a period of not less than 36 hours.
Further curing shall be in accordance with the Specification...................................44
1.15 Permanent Markers and Barriers.................................................................................44
1.15.1 Scope 44
1.15.2 General...............................................................................................................................44
1.15.3 Chainage Markers...............................................................................................................44
1.15.4 Block Valve Station Markers...............................................................................................44
1.15.5 Road Crossing Markers......................................................................................................44
1.15.6 Wadi Crossing Markers......................................................................................................44
1.21.2.1 The work permit system shall apply to all work on live pipe systems. Contractor
shall do all that is necessary to obtain work permits and to execute the Work in
adherence to the work permit..................................................................................53
1.21.2.2 Specialised tools and equipment as required for the performance of work on live
pipe systems shall only be acquired form the Company approved vendors. A
vendor’s representative shall be present at all times during the use of such tools
and equipment.........................................................................................................53
1.21.2.3 Hot tapping on live pipe systems shall be carried out in accordance with DEP
31.38.60.10. Welding on pressurised pipes shall be carried out in accordance with
SP-1167...................................................................................................................53
1.22 As-Built Records and Hand-Over Documentation........................................................53
1.22.1 Scope 53
1.22.2 Storage Format...................................................................................................................53
1.22.3 Storage Location.................................................................................................................54
1.22.4 Pipeline As-Built Documentation........................................................................................54
1.22.5 Documents..........................................................................................................................54
1.22.6 Test, Calibration and Inspection Reports...........................................................................54
1.22.7 Material Certificates............................................................................................................54
1.22.8 As-built Drawings and Pipeline Data Sheets......................................................................55
1.23 Effective Period............................................................................................................55
1.24 Review and Improvement.............................................................................................55
Appendix A Glossary of Definitions, Terms and Abbreviations...........................................56
i. Terms and Definitions.................................................................................................................56
ii. Abbreviations..............................................................................................................................56
Appendix B Reference Documents.....................................................................................57
Appendix C: Facilities For Company Personnel..................................................................61
Appendix D: List of Handover and As-built Documentation.................................................64
Appendix E List of Typical Drawings for Pipeline Construction...........................................69
Appendix F CONSTRUCTION REQUIREMENTS FOR GRE PIPELINES.........................95
User Comment Form.........................................................................................................105
1 Introduction
1.1 Purpose
This document shall be used as the base specification for construction of all new carbon
steel pipelines required in PDO operations. Hydrostatic testing and Pre-commissioning
of new pipelines are covered separately in SP-1212 and DEP 31.40.50.30 respectively.
Appendix – F of this specification specifies requirements for construction of GRE
pipelines.
This revision updates the earlier Pipeline Construction Specification (SP-1208) Version
1.0 April 2001. With the inclusion of requirements for GRE pipeline construction in this
revision, the existing SP-1247 (Dec.2002) stands withdrawn.
1.4 Exceptions
The user shall obtain written approval prior to construction from the appropriate
Technical Authority within PDO for any deviation from or exception to the requirements
of this Standard. The appropriate technical authorities are set out in GU-272.
Any work completed with unauthorised modifications may be rejected by the Company.
Any subsequent re-work shall be in accordance with this specification and shall be to the
Contractor’s expense.
2 Specification Requirements
1.5 Health, Safety and Environment (HSE)
1.5.1 Scope
This Section of the Specification covers the minimum HSE requirements required during
installation work.
1.5.2 General
The Contractor shall comply in all respects with all HSE Specifications listed in C-6 and
C-9 documents of the Contract, paying particular attention to: The requirements for
construction and lifting equipment in SP-1143, SP-1239, SP-1251 and PR-1508; the
specification for Aqueous Effluents SP-1006; The Transport Operations manual
TOM/04/001 as well as SP-2000 “Road Transport” and GU-140.
Contractor shall appoint one or more HSE Advisors, to be approved by the Company,
reporting directly to the Contractor’s Project Manager.
The HSE Advisor shall be fully conversant with the Work and shall have previous
experience and qualifications as specified in the HSE Regulations. Details of
qualifications and experience of the HSE Advisor(s) proposed by the Contractor shall be
submitted to the Company for approval before mobilisation of the HSE Advisor(s).
The work of the HSE Advisor(s) is to ensure that all Contractor’s work and conditions are
in accordance with the Company’s HSE Regulations.
The Contractor’s HSE Advisor(s) shall make daily reports about all accidents, unsafe
acts, unsafe situations etc. noticed by himself or brought to his attention. The daily report
shall be transmitted to Contractor’s Project Manager on each morning following the
reported day. A copy shall be handed to the Company’s Site Engineer. The daily report
is in addition to those required by the Safety Regulations. Contractor’s Project Manager
shall advise the Company’s Site Engineer in writing within 24 hrs of the report being
issued, what action has been taken to prevent re-occurrence of any incidents reported.
The HSE Advisor(s) shall carry out his work from the moment the Contractor starts
mobilisation and until the date of completion.
Contractor shall provide a dedicated vehicle with VHF radio, for the sole use of the HSE
Advisor(s), for communications with Contractor’s Construction camp/head office.
Contractor shall specifically instruct all personnel of the dangers relating to the internal
inspection of pipelines. Only under special circumstances shall anyone be allowed to
enter a pipeline, and only after a specific procedure has been agreed and approved by
the Company.
During construction of pipelines, the working strip shall be marked with road traffic signs
and specific warning signs relating to the construction activities. This applies particularly
to road crossings.
This Section of the Specification and SP-1171 “Specification for Quality Assurance of
Design, Construction and Engineering Works” covers the minimum requirements of
Quality Assurance required for the Work.
1.6.2 General
Before starting the Work, Contractor shall submit his proposed quality assurance
procedures and organisation to the Company for Company’s approval. Contractor’s
proposed plan shall include the internal procedures to report non conformances, how
corrective action requests are to be generated and how it will be demonstrated that such
actions have been carried out and are effective.
It is the duty of the Quality Assurance Team to ensure that the Work is carried out in
accordance with this Specification and other Contract Specifications. The Contractor
shall have a full time Quality Assurance Team and all necessary equipment at the Work
Site. The Team shall have no other work or responsibilities apart from Quality
Assurance.
One Contractor’s Quality Assurance Engineer responsible for procedure preparation and
implementation, drawing and document control and supervision.
Quality Inspector’s duties include but not limited to the following activities:
- materials certification
- traceability of materials
- trench depth
- sand padding
- lowering in
- backfilling
- as-built drawings
- document control
1.6.3.1 Personnel
The Head of Quality Assurance shall have a detailed knowledge of welding and NDT
and other activities of pipeline construction. He shall have experience in quality
assurance matters and be suitably qualified.
All Contractor’s inspectors shall be fully conversant with and experienced in the aspects
of the Work for which they will be employed. They shall have previously worked on
similar projects in similar capacities. All Contractor inspectors shall be suitably qualified
and a copy of all qualification certificates relevant to the inspection function for which
they are proposed by the Contractor and shall be submitted for Company approval
before mobilisation of the Inspectors. All Contractor’s inspectors shall have a dedicated
vehicle.
Following Company’s approval and the arrival of the Inspectors on site, Company has
the right to request all Inspectors to an examination to ensure their suitability for the
work they are required to do, and reject any Inspector who is found unsuitable, at the
Company’s sole discretion.
1.6.3.2 Organisation
The Head of Quality Assurance shall report directly to the Contractor’s Project Manager.
His duties shall be to liaise with the Company, organise the Contractor’s Inspectors so
that they carry out their duties in an efficient manner, and prepare all necessary reports.
The Head of Quality Assurance shall not carry out inspection work himself other than in
supervision of the Contractor’s Inspectors.
Company will employ a team of Inspectors throughout the contract period, to monitor all
work activities including safety aspects. These Company Inspectors are hereafter
referred to as the Inspectors.
The Inspectors will have authority to stop the work in the case of unsafe situations and
non-compliance with the HSE Specifications, as well as documented non compliance
with agreed installation or quality procedures which could impact on the future safety of
the pipeline during hydro testing or in service.
The inspectors will report non-compliances with this specification and other contract
standards to the CSR, who will advise the Contractor formally of any required corrective
action.
This Section of the Specification covers the minimum requirements for handling, storage
and administration of all materials, either Company or Contractor supplied, to be
incorporated in the Work.
1.7.2 General
1.7.2.1 Handling, including but not necessarily limited to receipt, checking, lifting,
loading, transport, unloading, stacking, and storage of materials shall be
carried out by the Contractor in such a manner as to avoid any damage and
loss of materials. Method and means of transport and handling (including
documentation) shall be subject to approval by the Company.
1.7.2.2 Contractor’s material control and storage procedure shall be submitted to the
Company within two weeks of the start of mobilisation on site, for approval.
1.7.2.3 Contractor shall give the Company at least 2 Company working days notice in
writing on each occasion when he intends to start transporting Company
supplied materials. A lapse greater than 2 working days shall require re-
notification. Pipe can be removed from Company’s yard 7 days per week
during daylight hours, unless otherwise specified by the Company. Contractor
shall provide the Company with a written confirmation of receipt of all materials
(identified by type and quantity) and a written reconciliation of all materials
(identified by type and quality) transported by them from Company’s storage
yard on a weekly basis.
1.7.2.4 Contractor is required to supply lifting equipment for lifting materials at all
locations. Lifting equipment and operations shall be in accordance with SP-
1239.
1.7.2.6 Contractor shall not be held responsible for manufacturing defects in Company
supplied materials, but shall be held responsible for any delays to the Work
caused by Contractors failure to report defects discovered during inspection by
the Contractor within 24 hours of such inspection.
1.7.2.7 Contractor’s procedures for material receipt and return of surplus materials
shall conform to Company’s materials procurement/administration procedures.
1.7.3.1 The Contractor shall visually inspect at the Company storage yards, all pipes
internally and externally for damages, surface defects and defective bevels.
The Contractor shall satisfy himself at this stage of the suitability of each pipe
for welding and shall accept all responsibility thereafter for all damages
however caused.
1.7.3.2 Prior to haulage of pipe from Company’s storage yard, Company and
Contractor shall carry out a joint survey of pipe coating damage and bevel
damages. On the basis of this survey, Company will pay the Contractor a lump
sum for repair of all bevel and coating damage, based on the submitted unit
rates in the Schedule of Rates, in accordance with this specification. For bevel
damages between 1 and 3 mm deep, the repair shall be by grinding. For bevel
damage depth greater than 3 mm, the repair shall be by re-bevelling.
1.7.4.1 Pipe shall not be allowed to drop or strike objects which may damage the pipe
and/or coating but shall be lifted, moved and lowered from one position to
another by suitable equipment. When lifting pipe, non-abrasive wide nylon pipe
slings or special lifting hooks equipped with a non-metallic bevel protectors
curved to fit the curvature of the inside of the pipe shall be used. Temporary
attachments for handling or lifting shall not be welded to any pipe. A spreader
bar shall be used for all bulk pipe lifting/handling (excluding welding
operations).
1.7.4.2 Trucks used to transport coated or bare pipes shall be free of any materials
that might damage or contribute to movement of the pipe during transport.
Pipes shall be protected against truck beds and side metallic posts by means
of non-metallic soft materials. Pipes shall be loaded and stacked on trucks in
such a manner that flexing and shifting of the pipe during transport is avoided.
After loading, suitable non-metallic slings shall be used to tie the pipes
securely to the truck. During transport the tension of these slings shall be
regularly checked. Pipe ends shall be protected from contact with other
metallic materials. Contractor shall ensure that no bevel protectors are lost
during transport. Pipes shall only be transported on trucks (lifting equipment
shall not be used to transport pipe).
1.7.4.3 Trucks used for loading of pipes will be checked by the Company prior to lifting
the pipes to ensure that the trucks and loading/load securing arrangements
comply with the requirements of PDO’s Transport Manual TOM/04/001, SP-
2000 ‘Road Transport’ and government regulations.
1.7.5.1 Ground surfaces to be used for stacking of pipe shall be reasonably flat.
Stacked pipes shall be raised above ground surfaces and prevented from
movement by berms of screened sand covered by polyethylene sheeting or by
using timber covered with non-metallic soft materials. When stacked, the
bottom layer of pipes shall be wedged or clipped. Pipes of different diameter,
wall thickness, grade or manufacturer shall be stacked separately. Each stack
shall be properly marked to the satisfaction of the Company.
1.7.5.2 Epoxy-coated pipes shall be stacked during transport and storage using rubber
or other suitable separator strips.
1.7.5.3 Pipes shall not be stacked higher than 3.5 metres. Pipes shall be stacked in
such a way that no water is retained inside the pipe during storage.
1.7.6.2 Minimum average pipe length shall be 11.50m as per above DEP. The
minimum and maximum length of pipe shall be between 9m and 13.7m long.
1.7.7.1 Upon receipt of any materials, the Contractor shall ensure that they conform to
the required specification and are suitable for their intended application. Any
damage/defects shall be reported to the Company within 24 hours of receipt of
these materials and prior to transportation to the Contractor’s own storage
yard. Visual inspection shall be adequate for this purpose.
1.7.7.2 In the case of materials delivered in their original sealed crates, Contractor
shall only open the crates to examine the materials upon arrival at his own
storage yard, except in the case of damaged crates which shall be noted and
the contents examined when Contractor takes receipt at Company’s storage
yard.
1.7.7.3 If no report is issued for damaged materials 24 hours after receipt (or in the
case of 2.3.7.2 above, 24 hours after arrival of materials at the Contractors
storage yard), then the materials shall be considered free from damage and
the Contractor shall be considered liable for any damage reported or found at a
later date.
1.7.8.1 Materials other than pipe materials such as, but not limited to, valves, fittings,
scraper traps etc., shall be lifted by suitable equipment provided by the
Contractor at Company’s storage yard and at all other locations. When lifting
lugs are provided on materials, suitable lifting hooks shall be used for lifting the
materials. It is prohibited to use delicate parts such as hand wheels, nozzles,
etc. for lifting of the materials.
Temporary attachments for handling or lifting shall not be welded to any materials.
Fittings shall only be handled by suitable non-abrasive slings.
1.7.8.2 Materials other than pipe materials will be issued to the Contractor whenever
possible in their original sealed shipping cases/crates. Blinded openings of
materials shall be kept closed until installation. The blinds shall be replaced by
the Contractor in case of damage during transport or storage.
1.7.8.4 For materials which shall be stored cool and/or dry as required by the
manufacturer or the Specifications, Contractor shall provide suitable storage,
transport and handling facilities in accordance with the requirements of the
manufacturer and/or the Specifications.
1.7.8.5 Contractor shall provide a separate fenced storage area for Company supplied
materials. Stored materials shall be protected from ground surfaces by using
timber covered with non-metallic soft materials. Ground surfaces in storage
areas shall be clean and flat. It is prohibited to store and transport fragile
materials in more than one layer.
1.7.8.6 Distribution and supply of materials from Contractor’s storage yard to the
worksites shall be limited to quantities required for approximately one day’s
production. Timing of the issue of materials shall be as per the Company
approved work schedule.
1.7.9 Reconciliation
1.7.9.1 At the end of the project, Contractor shall give reconciliation for all Company
supplied materials issued, detailing materials installed, materials wasted and
scrapped, and surplus materials. Contractor shall compile a list of the surplus
materials, indicating quantity, description and MESC / SAP number when
available.
1.7.9.2 On approval of the surplus list by the Company, Contractor shall return all
surplus materials to Company’s storage yard.
1.8.1.1 Scope
This Section of the Specification covers the minimum requirements for the Pipeline
Right-of-Way (ROW) and the Working Strip.
1.8.1.2 Survey
The Company shall survey the route for the pipeline and prepare route maps from which
the centreline of the pipeline shall be staked out.
The actual centreline of the pipeline can in some instances deviate from the line staked
e.g. at station approaches. This should be taken into account where the word
`centreline` is used in the remainder of this Section.
The Right-of-Way for the pipeline is a corridor of 50 metres overall width and comprises:
The “Restricted Area”, a strip of land 25 meters wide on either side of the pipeline
measured from the centre line of the pipeline.
Where two or more pipelines are laid in parallel in the same corridor, the Right Of Way
corridor shall be enlarged by the space between the pipelines. The space between two
pipelines shall not be less than 2 meters from the existing or new pipeline.
Contractor may make use of a Working Strip, having a width of 31 metres (including a
continuous 6 metre wide vehicle access strip) from one edge of the Restricted Area.
Variations, if any, in this width caused by local conditions will be indicated on the
drawings or instructed to Contractor by the Company.
1.8.1.4 Planning/Approvals
Contractor shall, before starting any clearing operations, familiarise himself with any
requirements by the Authorities for work along the pipeline route or in connection with
the use of other lands or roads for construction purposes.
Contractor shall notify the Company 7 days in advance before start of work at road,
pipeline, cable, stream, river and wadi crossings and crossings of other existing
structures, if any.
Contractor shall not commence work on such crossings before having obtained approval
from the Authorities and landowners concerned.
The crossings shall be installed to meet all requirements and conditions of the permits,
issued by the Authorities concerned.
In the absence of any specific requirements by the Authorities, Contractor shall comply
with the Company’s instructions.
Where the pipeline is laid close to any existing buried or above ground pipeline, flowline
and utility cables, the Contractor shall propose methods to safeguard the existing line
(e.g. a demarcation fence). No work is allowed in such an area without Company
approval. Work near live pipelines shall comply with the requirements of ERD 38-11,
‘Guidelines for Excavating and Working around Live Pipelines’ and paragraph 2.4.3.2–f)
of this specification.
1.8.2.1 Scope
This Section of the Specification covers the minimum requirements for staking, clearing
and grading along the pipeline route as required for the Work.
Company will have obtained ‘approval in principle’ for laying the pipelines along the
routes. Contractor however will have to obtain permission from the concerned
Authorities to execute the work.
1.8.2.2 Definitions
a) ‘Clearing’ shall mean but is not necessarily limited to the cutting and
disposal of trees, farm crops, bushes and undergrowth.
b) ‘Grading’ shall mean but is not necessarily limited to removal and disposal
of rock, sand dunes, tree stumps and roots.
1.8.2.3 Staking
ii) The markers are angle-iron profiles or wooden posts with sequential
numbers, starting with no. 1 at start point of the pipeline. Reference
markers are marked with the letter ‘A’ or ‘B’. All markers extend
approximately 500 mm above grade. The ‘A’ and ‘B’ markers are
located at the same side of the centreline marker, ‘A’ being closest
to the pipeline centreline.
d) The Contractor shall verify that the radius of curvature of the pipeline
trench in any plane is greater than the minimum allowable bending radius
specified. Any deviation from the routing as staked by the Company
and/or indicated on the route maps shall be approved by the Company
prior to the clearing operations.
b) Contractor shall take utmost care to mark all exposed obstacles to avoid
any possible damage throughout the performance of the Work and restore
them to their previous state if damage occurs.
e) Contractor shall furnish all angle iron and other support material required
at crossings of underground obstacles. Contractor shall furnish and install
all tiles and tile supports to replace existing damaged ones encountered in
the course of the Work. Telephone, telegraph or electric power cables or
foreign piping encountered in the pipeline trench shall be supported prior
to sand padding and backfilling by a Company approved method.
g) Contractor shall liaise closely with relevant Authorities and give adequate
notice to them of trench excavation, and subsequently backfilling, in the
vicinity of all underground services to allow such Authorities to inspect and
witness such excavation and backfilling should they required to do so.
h) Contractor shall repair without delay any ‘falaj’ (gravity water transport
system) damaged during the performance of the Work and restore it to the
same state as before the damage occurred.
i) Line and cable marking posts, tiles, etc. shall be replaced by the
Contractor in the correct position.
a) The Working Strip shall be cleared over its entire width, unless restricted
by the terrain or other features shown on the drawings. Contractor shall
carry out all operations within the limits of the Working Strip and shall not
operate within 25 meters from existing pipe lines without Company
approval.
b) Holes remaining, after stumps have been grubbed, shall be filled with
suitable fill material and compacted.
1.8.2.6 Explosives (not used for blasting as part of the construction work)
In the event, the Contractor finds explosives in or along the Working Strip the Contractor
shall notify the Company and the appropriate Authority without delay. Contractor shall be
responsible for making all necessary arrangements to have the explosives removed by a
specialist approved by the controlling Authorities.
a) Contractor shall grade off high points and fill low points to allow the pipe to
be bent and laid within the limits set forth herein with due regard to the
minimum radius of bends allowed and shall drill, blast, and excavate rock
or other material which cannot be graded off with ordinary grading
equipment in order to provide an adequate working space along the
pipeline route. Contractor shall in general be required to grade the whole
of the Working Strip, but a narrower width may be allowed by the
Company, depending on ground conditions.
c) In rough or steep terrain, Contractor may wish to grade access roads into
the Working strip to facilitate moving in materials, personnel and
construction equipment. Where such roads are required by the Contractor
he shall obtain the necessary permission in writing from the Authorities
concerned and shall furnish the Company with a copy of such permission,
prior to commencing any work on roads. Contractor shall be responsible
for and make good, all damage caused by the construction and use of
such roads.
d) Contractor shall only obtain access to the Working Strip from existing road
where such roads cross the Working Strip, or via access roads
constructed by the Contractor between existing roads and the Working
Strip at all other locations. Such access roads shall be agreed with the
Company prior to commencement of Right-of-Way preparation, and shall
be sign posted. Existing pipeline ROW shall not be used for access to the
Working Strip.
1.8.3 Trenching
1.8.3.1 Scope
1.8.3.2 Excavation
i) Minimum depth of cover shall be measured from the top of the pipe
to the top of the undisturbed surface of the soil or top of graded
Working Strip which ever is smallest. Fill material in Working Strip
shall not be considered to add to the depth of cover. However,
surface of fill material placed to fill low points to accommodate pipe
bending limitations may be used to determine depth of cover subject
to approval by the Company of detailed location-specific design
drawings including soil stabilisation measures such as rip-rap or
gabions.
d) Contractor shall excavate and grade the trench sufficiently deep and wide
to provide space for 150 mm of padding material after compaction all
around the pipe and for the continuous length of the pipeline.
e) The trench bottom and sides shall be kept free of all brush, skids, pipe
protectors, rocks, large clods, sticks, projecting rocks and other hard
objects at all times. Any such items encountered shall be removed prior to
pre-padding operations so that the pipe is not damaged, punctured or
abraded.
f) Where the pipeline crossed other pipelines, sewers, water lines, cables,
conduits or other underground structures of any kind, Contractor shall
excavate and grade the trench to a depth in such a manner that the top of
the pipeline will be at a minimum of 500 mm below the bottom of the
underground structure crossed, subject to compliance with the minimum
specified bending radius of the pipe. If clearance of more than 500 mm is
required by the Authorities having jurisdiction, Contractor shall provide
such increased clearance. The construction over or under all existing
structures such as roads, water lines, telephone lines, and other pipelines
shall be the responsibility of Contractor. In the event that the pipeline
crosses over existing structures, the same clearance as described above
shall be maintained and depth of cover as per paragraph (c) above. For
crossings of buried live pipelines, the requirements of ERD38-11 shall
apply.
g) In locations where the trench is cut across roads, tracks, paths, walkways,
etc. Contractor shall provide temporary bridges or diversion road of
adequate strength and properly constructed to allow the passage of
normal traffic with a minimum of inconvenience and interruption.
Whenever it is permissible to open cut a road, Contractor shall remove
and restore the surface in accordance with the requirements of the
Authorities having jurisdiction thereof or as directed by the Company.
Wherever possible, Contractor shall arrange to complete the trenching,
laying and backfilling of such crossings and to remove the temporary
bridging before the end of the regular work day in order to minimise
hazard to night traffic. Proper warning signals shall be placed and
maintained while such crossings are open. If the crossings are open at
night, Contractor shall provide and use warning lights or lanterns, all as
required and approved by the Authorities having jurisdiction and/or the
Company.
h) Contractor shall provide and use sheet piles, struts, walling, jacks, pumps
etc., as required to maintain the trench in good condition until the pipe is
laid in place and backfilled.
j) If Contractor elects to carry out a rip survey, then the results of this survey
shall be made available to Company. The extent of rock encountered
during trenching shall be recorded on the as-built Alignment Sheets by the
Contractor, whether or not a rip survey is carried out.
1.8.3.3 Blasting
All activities including but not limited to storage, transportation of explosives and blasting
shall be carried out in accordance with the N.F.P.A. No. 495, BS 5607 and the
instructions of the Authorities and/or the requirements in this section, whichever are the
most stringent.
For depth of cover purposes, rock in trench is defined as the rocky part of the specified
trench which cannot be removed by ditching machines, rock plough, back hoe or ripper,
to be decided after two passes of a D9 Caterpiller tractor (or one pass of a tandem D9)
or equal, equipped with proper ripping equipment.
Trenches having a longitudinal slope of more than 10% shall be provided with structures
or retaining barrier(s) as specified on the drawing TYP 3 0015 001 provided in Appendix
E of this specification. No retaining barriers are required in areas of sand dunes.
In the case of a single pipeline to be laid in the trench, the trench width shall normally be
outside diameter of the pipe plus 300 mm (i.e. 150 mm on each side of the pipe) unless
otherwise approved by the Company (refer drawing TYP 3 0002 001). In the case of
more than one pipeline to be laid in common trench, the trench width shall normally be
the sum of the diameters of the pipes plus 300 mm (i.e. 150 mm on each side of the
pipe) plus 500 mm clearance between the outside edges of adjacent pipes unless
otherwise approved by the Company.
This Section of the Specification covers the minimum requirements for stringing the line
pipe along the trench side and for cold bending of metallic pipe as required for the work.
1.9.2 Stringing
1.9.2.1 No pipe shall be strung before the trench is excavated to full depth and
accepted by the Company to meet the requirements of this Specification. Pipe
shall not be placed directly on the ground but on wooden skids with proper
protective padding. The skids and protective padding material shall be subject
to Company (CSR) approval. Dragging, skidding or dropping of the pipe is not
permitted. Wooden wedges shall be used to prevent movement of each strung
pipe.
1.9.2.2 Where possible the skid elevations shall be planned such that minor
differences between grade profile and bottom of trench profile (e.g. at locations
where an increased trench depth is required) can be accommodated without
requiring an additional tie-in. The distance between the trench edge and the
pipe string shall be planned such that safe working space is provided.
1.9.2.3 Contractor shall be responsible for proper stringing and locating of the pipe by
size, wall thickness, specification and manufacturer. Company may supply line
pipe from different manufacturers. Contractor shall string all line pipe of one
manufacturer before commencing the stringing of line pipe supplied by the
second manufacturer. Pipes of different manufacturers shall not be mixed per
line section without prior approval of the Company.
1.9.2.5 Contractor shall layout and measure the pipes such that, the number of pieces
cut-off with less than one metre length is kept to a minimum.
1.9.2.6 The length of pipe string shall be planned with due consideration of thermal
expansion and other expected or accidental movement of the pipe string.
Special attention shall be paid to strings with one or more bends, in view of the
inherent increased risk of failure of skids due to movements of the pipe. Length
of individual pipe strings shall be subject to Company approval and shall
generally not exceed 1 km.
1.9.2.7 Pipe shall be strung with the use of a spreader bar and two guide lines. (See
Section 2.3 for requirements for slings and hooks).
1.9.3.1 Contractor shall make all necessary bends required for proper construction of
the pipeline, following a trigonometric survey to establish the number and
degree of bends required, to ensure that the installed pipe shall conform to the
contours of the pre-padded trench.
1.9.3.2 Contractor shall, before the start of the Work, submit and demonstrate to the
Company a bending procedure, which shall conform to the recommendations
of the manufacturer of the bending machine. This procedure shall be subject to
Company’s approval. The procedure shall include amongst others, step length,
degrees per pull and method and accuracy of measurement during pulling of
the bend.
1.9.3.3 Elastic bends with radius of curvature less than 500 x D, D being the pipeline
diameter are not allowed unless approved by the Company.
1.9.3.5 The cold bends shall be made by a smooth stretch bending machine. Bends
with ripples with a depth exceeding 0.5 mm, wrinkles and kinks are not
acceptable. Contractor shall provide a procedure for measuring ripples which
shall be approved by the Company.
1.9.3.6 The pads, dies and rolls of the bending equipment shall have soft surfaces to
avoid damage to the pipe coating. Where applicable, fully retaining bending
shoes shall be used. Roller type bending machines are preferred. Bends in
pipe of diameter 8" or greater shall be made by using an internal (hydraulic or
pneumatic) mandrel.
1.9.3.7 All bends shall be tested in the presence of the Company with a gauging plate
of 97.5% of the nominal internal diameter of the pipe prior to installation.
The longitudinal weld of the cold bend shall be located approximately within 10° from the
pipe’s neutral axis. The position of the longitudinal weld for successive pipe joints shall
be chosen such that the longitudinal welds are staggered and always occur in the top
half of the pipe (as specified in the welding specification).
1.9.3.8 The procedure for bending shall be such that the extremities of each joint
remain straight over a minimum distance of 2 m or twice the pipe diameter,
whichever is greater. Contractor shall lay out and measure the pipe for bending
such that the length of off-cuts is kept to a minimum.
This Section of the Specification covers the minimum requirements for the fabrication,
welding, and non-destructive testing of ‘on-plot’ piping and ‘off-plot’ pipelines for oil and
gas service, as required for the Work.
‘Off-Plot’ Pipelines are defined as all pipelines and pipe work covered by Codes ASME
B31.4 or ASME B31.8 as specified in the drawings. This includes all pipeline work, block
valve stations and most parts of the pig trap stations.
The minimum requirements for welding are contained in Specification SP-1177 (for
Class 1 Pipelines), SP-1174 (for Class 2 & 3 Pipelines) and SP-1097 (for Duplex
Stainless Steel Pipelines).
‘On-Plot’ Pipework is defined as all pipework and pipe runs covered by the code ASME
B31.3 as specified in the drawings.
This Section of the Specification covers the minimum requirements for the external field
coating of pipeline weld joints and repair of damaged coating. Painting of station
pipework, valves, fittings etc. is specified in Section 2.12, Station Works.
Line-pipe is supplied with mill applied anti-corrosion coating unless specifically stated to
the contrary in the contract Scope of Work. The type of field joint coating that can be
applied shall be compatible with and have good adhesion to the mill applied coating:
- For Fusion Bonded Epoxy (FBE) coated line pipe, the field joint coating shall
be by FBE field joint coating.
- For Polyethylene (PE) / Polypropylene (PP) coated line pipe, the field joint
coating shall be by heat shrink sleeves.
Contractor shall supply all equipment including spares and skilled manpower required for
pipe cleaning, application of coating, coating repair in the field, and inspection and
testing of the same in accordance with this Specification.
1.11.2 Materials
1.11.2.3 The materials, at time of application by the Contractor, shall not be older than
the shelf life stated by the manufacturers.
1.11.2.4 The coating materials shall be properly packed and clearly marked with:
- Batch number
- Date of manufacture
- Storage temperatures
1.11.2.5 Coating materials shall be kept dry and stored as long as possible in the
manufacturer’s original packaging, not exposed to direct sunlight, and in
accordance with manufacturer’s instructions.
1.11.2.6 The list of Company approved wrap-around shrink sleeves is given in the
Approved Vendors, Manufacturers and Equipments (AVME) list of the
company.
1.11.3.1 Prior to coating, the field joint area shall be blast cleaned. Surface preparation,
including blast cleaning, shall be carried out in accordance with SP-1246 and
this specification.
Any weld spatter or sharp edges of the mill coating shall be removed by filing or light
grinding prior to blast cleaning. If the mill coating is disbonded along the edges, or if
there is an evidence of corrosion under the coating, the coating shall be cut-back until
sound coating has been obtained. Polyethylene coating shall be chamfered by torch and
knife and F.B.E. coating shall be feathered over a distance of 10-15 mm during grit
blasting.
Abrasives for blast cleaning shall be certified in accordance with the relevant parts of
ISO 11124 or ISO 11126. Certificates shall be maintained by the Contractor. The
blasting nozzle shall be fitted with a dead man’s handle so that the equipment will not
operate unless the handle is held.
1.11.3.2 The blast surface visual appearance shall conform to ISO 8501 grade Sa 2
1/2. Any field joint not coated within 4 hours of grit blasting shall be reblasted
prior to the application of the coating.
1.11.3.3 The surface profile attained by the grit blasting shall conform to ISO 8503-2
and shall be 40-75 microns peak to trough or as specified by field joint coating
manufacturer.
1.11.3.4 The surface cleanliness shall conform to ISO 8502-1 to 4 and shall be such
2
that the chloride contamination is less than 20 mg/m .
1.11.3.5 Coating of the field joint shall not take place until the weld has been non-
destructively tested and approved by the Company.
1.11.4.1 Contractor shall propose the application procedure for Company approval. The
application procedure shall be in accordance with manufacturer’s instructions
and the minimum requirements specified below, whichever are the most
stringent, and shall be demonstrated to the Company prior to field application
by means of a procedure qualification test joint.
1.11.4.2 The joint shall be heated to a temperature required by the procedure. Induction
heaters, ring burners or propane torches of a suitable type may be used for
pipe diameters smaller than 16". Induction heaters shall be used for pipe
diameters of 16" and larger where the pre-heat temperature exceeds 100° C.
In all other cases burners or torches may be used. Torches may be used for
tie-in welds at Company’s discretion. To check that the required preheat
temperatures have been achieved, a digital contact thermometer shall be used.
1.11.4.3 The sleeve shall be wrapped entirely around the joint. The closure patch shall
be positioned off to one side of the pipe. There shall be a minimum overlap of
50 mm onto the factory applied coating.
1.11.4.4 The procedure for shrinking the sleeve shall ensure that all entrapped air is
forced out at either end using gloved hands and hand rollers. Special attention
must be given to the closure patch and overlapping areas.
1.11.4.5 The installed sleeve shall be left undisturbed for 4 hours or until the adhesive
has been solidified, whichever is the longer.
1.11.4.6 The sleeves shall be visually inspected for the following points:
a) Adhesive extruded from the ends of the sleeve indicates proper application. The
ends of the sleeve shall be firmly bonded to the surface of the coated pipe.
1.11.5.1 The mill applied epoxy coating of the linepipe shall be applied in accordance
with DEP 31.40.30.32. The epoxy material for the field joints shall be
compatible with the linepipe coating and shall conform to the material
requirements of DEP 31.40.30.32.
1.11.5.2 Contractor shall propose the application procedure for Company approval. The
application procedure shall be in accordance with manufacturer’s instructions
and the minimum requirements specified below, whichever are the most
stringent, and shall be demonstrated to the Company prior to field application
by means of a procedure qualification test joint. Contractor shall also submit
test data to demonstrate that the applied coating satisfies the requirements
DEP 31.40.30.32, with respect to:
- impact resistance
- hardness
- cathodic disbondment
In the event that the Contractor cannot demonstrate that the coating satisfies these
requirements, in Company’s opinion, then the Contractor shall perform field tests
followed by full laboratory testing of the coating in accordance with DEP 31.40.30.32. A
Manufacturer’s representative shall be present on site full time during field applied epoxy
coating work.
1.11.5.3 The resin powder shall be stored in waterproof containers which are insulated
and cooled by refrigeration or air conditioning to a temperature not exceeding
27°C. Temperature recorders shall be used to monitor the storage temperature
inside each container. During the daily powder coating operations, the powder
in the fluid bed can be kept at ambient temperatures up to 85°C, but must be
returned to the normal storage temperature below 27°C at the end of the day.
For any powder that has temporarily experienced temperatures in excess of
27°C, gel time tests as per manufacturer’s recommendation must be carried
out on each box of powder before use.
1.11.5.4 The area of the pipe to be coated shall be preheated by induction heating coil
to a maximum temperature of approximately 250°C. The actual temperature
range shall be in accordance with the powder manufacturer’s
recommendations. If the ambient temperature falls, it may be necessary to
increase the preheating temperature slightly to provide adequate curing
energy. Powder application shall start as soon as the metal temperature is
within the qualified temperature range, such that the metal temperature does
not drop below the specified lower temperature limit during coating application.
Metal temperatures shall be checked by means of digital contact
thermometers.
1.11.5.5 For pipeline sizes equal to or greater than 12", Contractor shall use automatic
coating machines, capable of applying the powder at a uniform rate over the
entire width of the area to be coated. For smaller pipeline sizes, Company may
accept powder application by a hand held device used by a skilled operator,
using a technique which achieves an even coating thickness. There shall be a
minimum overlap of 50 mm onto the factory coating.
1.11.5.6 The applied coating shall have a minimum dry film thickness of 400 ± 75
micron. Dirt or deleterious materials shall not contaminate the powder coated
area during the application and curing stages. In the event of contamination,
the coating shall be rejected, stripped and recoated to the original procedure.
The cured coating shall be free of blisters, pinholes, scratches or any other
irregularities and shall be of uniform gloss and thickness.
1.11.5.7 All operators shall wear Company approved safety equipment to prevent
inhalation of powder dust and contact with eyes. Smoking shall not be allowed
in the vicinity of the coating operation.
1.11.5.8 The powder container, hoses, etc. on the application unit shall be cleaned after
each day’s work.
1.11.6.1 Coating repairs shall be executed on all coating damage and imperfections
detected visually or by holiday testing.
1.11.6.2 The coating repair procedure and the required materials for this, including the
installation of repair sleeves when applicable, shall be in accordance with a
procedure submitted by the Contractor and approved by the Company.
1.11.6.3 The repair procedure for mill applied polyethylene / polypropylene coatings
shall be selected based on the criterion of magnitude of the damaged area,
i.e.:
c) for damages with a greater diameter than 100 mm, a thermoplastic wrap-
around shrink sleeve shall be used.
1.11.6.4 The repair procedure for both mill and field applied fusion bonded epoxy
powder coatings shall be selected based on the criterion of magnitude of the
damaged area, i.e.:
b) Damages, other than scratches, with a diameter or width greater than 100
mm, are above the maximum limit for liquid epoxy repair shall be repaired
by using FBE coating method for field joints, to the original specification.
The damaged coating shall be removed around the entire circumference
by grit blasting.
1.11.7.1 The testing and inspection for acceptance of the coating system shall be
carried out and recorded by the Contractor as instructed and witnessed by
Company’s representative. The frequency of testing as specified herein may
be altered by the Company at Company’s sole discretion.
1.11.7.2 The cleanliness of the blast cleaned surfaces for every field joint shall be
inspected and shall be in accordance with ISO 8501 grade Sa 2 1/2. After the
surface has been blast cleaned and dusted off, a strip of transparent cellotape
shall be applied to the surface, and subsequently removed and examined for
particle contamination. This shall be done on the first joint cleaned each day,
plus two more times during the day and when a new batch of grit is used. If in
the opinion of the Company the test has failed, Contractor shall undertake to
perform additional cleaning to the specified standard.
1.11.7.3 The profile of the blast cleaned surfaces shall be tested by means of Testex
Replica Tape (type X-course), produced at least twice a day and additionally
the first few joints and at each change or replenishment of grit. Before applying
the coating, the surface shall be free of rust or residual grit. The surface profile
shall be evaluated from the replicas in accordance with manufacturer’s
instructions, using a recently calibrated micrometer. As an alternative to the
above, the Company may allow the surface profile to be tested on site by a
suitable profile gauge in accordance with SP-1246.
1.11.7.4 Additionally, general checks at random shall be carried out such as monitoring
of particle size of copper slag, grit/shot used for blast cleaning, cleanliness of
materials used for blast cleaning and coating, and temperature control of the
pipe surface.
1.11.7.5 Contractor shall supply all equipment required for inspection and testing
including dry film thickness gauges and holiday detectors. All equipment shall
be approved by the Company prior to use.
- From each test sleeve one or more strips of 2.5 cm wide and 20 cm
long shall be cut perpendicular to the pipe axis and slowly peeled
off, using an approved peel strength gauge.
- The temperature of sleeve and pipe during such a peel test shall be
as per manufacturer’s recommendation, i.e. the time of day of the
testing shall be taken into account.
- The required peel strength for the above strip shall be in accordance
with the manufacturer’s temperature/strength correlation data.
Repair shall be carried out as per Section 2. 7.6.
c) Following the peel test, the Company may request the Contractor to
remove the entire sleeve to check the overall degree of adhesion and
absence of bare metal voids achieved. After removal of the shrink sleeve,
the bulk of the adhesive layer which remains on the pipe surface shall be
essentially free from voids, although a certain amount of voids may be
allowed at the discretion of the Company, upto a maximum of 6 mm x 6
mm. Voids exposing bare metal shall not be acceptable and shall be
reason to fail the shrink sleeve application. In the event that the test fails,
it shall be repeated on the two sleeves adjacent to the tested sleeve.
Tests shall continue until the sleeves which are inspected are acceptable.
d) Company shall have the right to test one out of every hundred shrink
sleeves applied or one sleeve out of every days production if less than
one hundred sleeves are applied in any day.
a) Every day at least one representative epoxy coated field joint shall be
subjected to an adhesion test. With a Stanley knife, two cuts shall be
made through the coating to the substrate to form a vee with an
intersection at about 30 degrees. Starting at the point of the vee,
Contractor shall attempt to force the coating from the substrate with the
Stanley knife. Peel off exposing bare metal constitutes a failure. This test
shall be carried out on the same day that the coating is applied. In the
event of failure, the joint on either side shall also be tested. The test area
of the passed joints shall be repaired with the liquid epoxy system as per
2.7.6. Failed joints and other joints rejected on the basis of the test results
shall be stripped and recoated to the original specification.
b) Every day at least one representative epoxy coated field joint shall be
subjected to a cure test. This is done by rubbing a smooth coated area,
free from overspray and surface powder contamination, with a suitable
solvent and judge the amount of colouration as compared with a
previously carried out test on a laboratory prepared and cured panel. No
softening of the coating shall be noticeable by comparing the rubbed area
with the adjacent non rubbed area of the joint. This can be checked by
pushing a finger nail in the rubbed area and the adjacent untreated area
and judge the difference between the two impressions. The solvent shall
be either MEK (Methyl Ethyl Ketone), MIBK (Methyl Iso Butyl Ketone), or
others (ref SP-1246) as per powder manufacturer’s recommendation and
the outcome of the laboratory test. Contractor shall provide a fully cured
laboratory prepared sample. During the test, the coated substrate must be
cooled down to ambient temperature. The test shall be carried out on the
same day that the coating is applied. In the event of failure, the joints on
either side shall also be subjected to a cure test. Failed joints and other
joints rejected, on the basis of the test results shall be stripped and
recoated to the original specification.
c) The gel time of fusion bonded epoxy powders shall be tested daily, by
spreading a sample of approximately 0.5 gram un-ground or powdered
epoxy resin onto a hot plate (at controlled and stable temperature) and
measuring the time lapse between the start of melting and the formation of
a gelled product, all in accordance to Company approved procedure. At a
temperature of 204°C, the epoxy powder shall exhibit a gel time within the
range of 25 to 50 seconds.
d) The dry film thickness of epoxy coatings shall be measured at each joint
or application by means of a Company approved type of coating thickness
gauge, which shall be calibrated at regular intervals (at least daily).
1.11.7.8 Holiday detection of 100% of the surface area of all coated pipeline shall be
carried out immediately prior to lowering in the ditch. The holiday detection
equipment which shall be Company approved shall be set at 2000 Volts DC for
Fusion Bonded epoxy and 22000 Volts DC for PE coated pipes based on 5V
per micron of coating thickness. However, the voltage setting for holiday
detection may be lowered slightly at Company’s discretion if coating gets
damaged. The electrode shall be a conductive rubber or a spiral metal ring.
Brush type electrodes shall not be used. The voltage applied by the holiday
detection equipment shall be measured by means of a voltage read out.
Alternatively a means of calibration of the applied voltage of holiday detection
equipment shall be provided to enable daily calibration of each piece of
equipment. All holidays, imperfections and damaged areas shall be identified
with a waterproof marker at sufficient distance from the defect to allow surface
preparation and patching to take place without detriment to the adhesion of the
coating.
1.11.7.9 Company will carry out a ‘Pearson Survey’ to check the integrity of the buried
coating. If coating defects are found on any portion of the coating, Contractor
shall excavate, repair and backfill at Contractor’s expense.
This Section of the Specification covers the minimum requirements for pre and post
padding, lowering the pipe and backfilling, compacting and stabilising the trench as
required for the work.
1.12.2 Pre-Padding
1.12.2.1 All trenches shall be padded before lowering in of pipe string. No padding shall
be placed until the Company has inspected and approved the trench bottom.
1.12.2.2 To ensure that fine and clean padding material is used, the Contractor shall
use mobile screening plants that enable a continuous direct application of
padding from the plant to the trench. The type of screening plant is to be
approved by Company prior to mobilisation to site (minimum sieve size shall be
5 x 5 mm). Mobile screening plants are defined as screening plants which
move along the trench whilst they are in operation. Only in those areas where
mobile screening plants cannot be used due to access problems, pre-screened
material may be used after approval of the source by the Company. Pre-
screened material shall be stored in areas which have been cleared of rocks
and stones and protected with plastic sheets to prevent contamination with
unacceptable padding materials.
1.12.2.3 The installed padding material shall be free of sharp rocks, stones, metal parts,
roots, clods, etc. and without sharp edges which could damage the pipeline.
Base materials from which pre and post padding material will be produced shall
consist mainly of sandy material. More than 75% by weight of the screened
material should have grain size between 0.06 and 3.0 mm and no more than
25% by weight shall have a grain size between 3.0 and 5.0 mm. To ensure
compliance with the above requirements, the Contractor shall produce a
grading curve with typical screened material from the proposed source of sand
or a representative section of the working strip. If the base material is not
sourced from the working strip, sources of padding material shall first be
approved by the Company. Suitable base material from the working strip may
not always be available or acceptable, in which case it shall be Contractor’s
responsibility to obtain suitable padding material from a source approved by
the local government authorities. Near residential areas and roads, padding
material shall be dust free (e.g. 'coarse sand' with a minimum grain size of 0.6
mm) in order to avoid inconvenience or danger to the public.
1.12.2.4 The bottom of the trench shall be padded with sand throughout its length,
whether in normal ground or rock, so as to provide a minimum compacted
padding thickness of 150 mm below the invert of the pipe. Contractor shall
keep the pre-padding operation within 1 km of the lowering-in operation.
1.12.3.1 Welded pipe strings shall be lowered-in within 96 hours of completion of joint
coating.
1.12.3.2 Immediately before commencing the lowering-in operation, the coating shall be
checked for holiday and if necessary, repaired to the satisfaction of the
Company, as specified in Section 2.7.6.
1.12.3.3 Wide non-abrasive slings or belts shall be used in all lowering-in operations
and care shall be taken when removing the slings from around the coated pipe
after it has been lowered into the trench. Any damage caused to the pipe and
coating during lowering operations shall be repaired before backfill
commences.
1.12.3.4 The trench shall be maintained in a dry condition during lowering-in and backfill
operations.
1.12.3.5 Contractor shall take measures to restrain the pipe in the trench by means of
‘plugging’, i.e. placing sand on top and around the pipe at regular intervals (one
2m ‘plug’ on every welded joint) or Company approved equivalent method.
Contractor shall plan the work such that the lowering in and ‘plugging’
operations take place during the hottest part of the day. Company may, at its
sole discretion, waive the requirement for ‘plugging’ and allow the post-padding
operation to be executed as one continuous operation, dependant on
completion time and ambient temperature considerations.
1.12.3.6 Sand padding shall be placed around and above the pipe, so as to fill the
trench to a depth of 300 mm above the crown of the pipe, with the sand
padding shaped to its natural angle of repose and with a minimum of 150 mm
at any point around the pipe. No pipe shall be left overnight in the trench
without sand padding around and above the pipe.
1.12.3.7 Where the trench has been excavated through or along drive-ways, walk ways,
roads, etc. and at live stock passage ways and other locations indicated on the
drawings, the sand padding shall be thoroughly compacted by watering and
Company approved hand tools, to achieve a compacted sand fill around the
pipe and up to 300 mm above the crown of the pipe.
1.12.4 Tie-ins
Unless otherwise agreed by the Company, tie-ins shall take place in the trench. For tie-
ins outside the trench, holding and lowering operations shall be undertaken in such a
manner as to minimise stresses in the pipe and therefore avoid movement of the pipe
from the skids, for safety reasons. Due consideration shall be given to ambient
temperature changes throughout the day and the resultant pipe length
changes/stresses.
1.12.5 Backfilling
1.12.5.1 The trench shall not be backfilled until the Company has approved the sand
padding around and above the pipe and has approved starting the backfilling
operation. Backfilling shall be performed as soon as possible after padding has
been approved.
1.12.5.2 In areas containing buried cables, backfilling shall not be performed until all
tiles have been replaced and protected and/or all cables have been supported
to Company’s satisfaction. The backfill around all underground services shall
be thoroughly compacted by hand.
1.12.5.3 The material used for initial backfill shall be from the screening plant or other
loose material not greater than 100 mm in diameter, all subject to Company
approval. The fill material shall be placed in such a manner as to avoid
disturbing the sand padding and excessive penetration (more than 150 mm) of
rocks into the sand layer. Contractor shall demonstrate that his proposed
method of backfilling achieves this requirement. The initial backfill shall be
placed in the trench to a level slightly above surrounding ground.
1.12.5.4 After the initial backfill, the remaining excavated material shall be neatly
crowned over the trench (the windrow), except in wadi areas. Where rock is
excessively large, in Company’s opinion, shall be removed from site and not
used as windrow material. On either side of road crossings, the windrow shall
be tapered from full height to ground level to improve the visibility of drivers on
the ROW.
1.12.5.5 Trenches crossing ditches shall be backfilled with the material excavated from
the trench at the location. If the excavated material, in Company’s opinion is
not suitable for backfilling, Contractor shall provide and use suitable material
from another source. Ditches with lined or otherwise improved surfaces shall
be resurfaced in a manner satisfactory to and approved by the Company and
the Authorities. Backfill in or on banks of ditches, wadis shall be compacted as
necessary to prevent soil erosion or other damage which might be caused by
the construction of the pipeline.
1.12.5.6 Where the trench has been excavated through or along drive-ways, walks,
roads, etc., and at live stock passage ways and other locations indicated on
the drawings, the initial backfill shall be thoroughly compacted by mechanically
tamping the material into place. The surface of such areas shall be stabilised
and/or restored to its original condition to the satisfaction of the Company and
the Authorities.
Where wadis or roads are graded, trenched or otherwise disturbed, the Contractor shall
restore the property to its original contour and condition even to the extent of hauling in
and placing new fill materials, gravel and stabilising materials or compounds, or by using
special compaction methods, as necessary to obtain the approval of the Company and
the Authorities.
To ensure the retention of sand cover in active sand areas (i.e. where the windrow
consists of sand only), the backfill shall be stabilised, preferably with a 150 mm layer of
marl or other stable material. The width of stabilisation shall be 3 metres on each side of
the pipeline (plus 0.6 metres for every 3 metres of dune height if the line passes through
a sand dune).
1.12.8 Reinstatement
1.12.8.1 Contractor shall clean-up the Working Strip and all working areas used by the
Contractor regularly during the course of the work, and shall restore the lands
traversed, to the satisfaction of the Company. Areas of soft sand in the
continuous 6 m wide vehicle access strip shall be removed and replaced by
approved infill material so as to leave the vehicle access strip in a safe
condition for driving. The vehicle access strip shall be deviated at road
crossings in order to give a visual indication to drivers of the presence of the
road.
1.12.8.2 The excess soil in the working strip shall be levelled in a manner satisfactory to
the Company. All loose rock exposed by the construction operations which is
scattered over the working strip or adjacent property shall be removed and
placed over the windrow. However, rocks larger than 750mm in diameter shall
not be placed directly on the backfill material, but may be placed next to the
windrow.
1.12.8.3 All creeks, water courses, wells, syphons, drains, streams, wadis, ditches and
irrigation channels shall be reinstated by the Contractor to their former
condition and their banks shall, if deemed necessary by the Company, be
pitched with stone and/or faced with special protection to prevent washing out
or erosion.
1.12.8.4 All enclosures, walls, gates, etc. shall be restored by the Contractor to at least
as good a condition as they were prior to the commencement of the
Contractor’s operations to approval of the Company.
1.12.8.5 All private roads, bridges and other private structures used by the Contractor
for access or haulage shall be restored by the Contractor to a condition equal
to or better than that which existed prior to the commencement of the
Contractor’s operations.
1.12.8.8 All rubbish/debris left over after removal of camp facilities shall be removed to
designated scrap dumps. The sites shall be levelled and cleared in accordance
with the Regulations for Pipeline Contractor Camps in the Interior and to
Company’s satisfaction.
This Section of the Specification covers the minimum requirements for road and wadi
crossings as required for the work.
1.13.2.1 The carbon steel pipeline shall cross all roads and highways, without the
installation of casings. All road crossings shall be made by the open cut
method. Trench less methods such as horizontal drilling, pipe jacking may be
considered for major road crossing to avoid disruption of traffic.
1.13.2.2 The construction of road crossings shall meet the requirements of API RP
1102 latest issue and shall be installed as shown on the drawings. The
crossings shall be installed to meet at all times the requirements and
conditions set forth by the Authorities having jurisdiction.
1.13.2.3 Contractor shall install an off-set diversion road, when specifically permitted or
required to do so by the Company and/or responsible Authorities and provide
adequate maintenance to ensure safe passage of vehicles. The diversion shall
not cross the pipeline where it has already been installed.
1.13.2.4 Contractor shall at all times and at every unfinished road crossing provide
adequate and proper traffic aids, such as warning signs, and other safeguards
to the satisfaction of the Company and the Authorities to ensure safety of the
public. All warning signs shall be in both Arabic and English language.
1.13.2.5 Contractor shall comply with the following minimum requirements of the
Directorate General of Roads for major road crossings:
c) Approvals must be obtained from all Utility Authorities and the Ministry of Land
Affairs and Municipalities prior to seeking permission from the Directorate
General of Roads.
d) Final approval of any proposed road works must be obtained from the Royal
Oman Police.
1.13.3 Wadi-Crossings
1.13.3.1 ‘Wadi’ shall mean dry river bed which could be temporarily filled with water
following rain. The wadis will be identified on the Alignment Sheets as ‘Flood
plains’, ‘Wadi type ‘A’’, ‘Wadi type ‘B’’, or ‘Wadi type ‘C’’. Pipe installed in
‘Flood plains’ does not require casing protection, but shall be stabilised at 3
meter intervals by means of bags of dry cement/sand mix placed on top of the
pipeline. The Contractor shall demonstrate by calculations that the weight of
the cement bags and soil overburden (excluding the windrow and post
padding) is sufficient to counteract the buoyancy force of the pipeline in empty
condition. Wadis may be classified based on judgement and careful evaluation
of the crossing location with due consideration to wadi’s width, bed slope, past
discharge history and erosion potential at the crossing location. The wadi types
are described below.
a) Type ‘A’ wadis are those where low velocity flow is expected after heavy
rains. At these wadi crossings, line pipe without concrete protection shall
be installed (TYP 3 0008 001) with a minimum cover of 1500 mm.
b) Type ‘B” wadis are those where erosion due to high velocity flow is
expected after heavy rains At these wadi crossings, line pipe with
continuous concrete protection shall be installed (TYP 3 0009 001) with a
minimum cover of 1500 mm.
c) Type ‘C” wadis are those where heavy erosion due to high velocity flow is
expected after heavy rains combined with the existence of large stones
and boulders. At these wadi crossings, line pipe with continuous concrete
protection shall be installed (TYP 3 0010 001) with a minimum cover of
1500 mm. Additionally, the pipeline trench shall be protected with gabions
placed at the surface.
1.13.3.2 Wadi crossings shall be installed to meet at all times the requirements and
conditions issued by the Authorities having jurisdiction in the area.
1.13.3.3 All concrete coated pipes shall be electrically tested on site prior to installation
in order to demonstrate that there is no contact between the reinforcing steel
and the pipe steel. The concrete shall be applied in accordance with Section
2.10, following.
1.13.3.4 At locations where concrete protection has been applied, the trench shall be
backfilled with coarse gravel and rock with a minimum dimension of 50 mm up
to a level 500 mm below grade level.
1.13.3.5 For type `C` wadi-crossing, gabions consisting of packages of boulders with
dimensions between 100 and 200 mm contained in galvanised, coated steel
wire mesh, shall be placed on top, up to grade level over the full width of the
trench. The type of wire mesh shall be approved by the Company prior to use.
1.13.3.6 Normally the windrow shall not be installed over the pipeline through the wadi
section. However for wide wadi crossings, greater than 100m, the windrow
shall be installed intermittently in order to mark the location of the pipeline
(Windrow lengths shall be approximately 25m at 75m intervals).
This Section of the Specification covers the minimum requirements for concrete coating
of the pipeline at Wadi crossings type B and C as required for the work.
1.14.2 General
1.14.2.1 Contractor shall be responsible for the supply and installation of all concrete
coatings, including all associated handling and transport of linepipe etc.
Contractor shall furnish all materials, equipment, labour, supervision, worksite
and services incidental to and necessary for the application of concrete in
accordance with this specification and all subject to Company approval.
1.14.2.2 The concrete shall have a minimum dry density of 2400 kg/m3 after 28 days.
The minimum thickness shall depend on the pipe outside diameter as specified
below:
Up to 6.625" : 40 mm
6.625" to 12.75" : 50 mm
over 12.75" : 60 mm
1.14.2.3 The mill identity of each pipe length shall be preserved and records kept during
and after the coating process. A certified permanent record shall be supplied to
the Company showing the serial number, average outside diameter, length and
all weights.
1.14.2.4 The concrete coating of line pipe shall be applied either in an approved coating
plant or in the field, at Contractor’s option. Field application shall be by dry mix
gunite technique or Company approved equivalent. The plant application
procedure and the coating plant may involve methods other than guniting and
shall be Company approved.
The Contractor shall prepare, and submit to the Company for approval, a minimum of 1
month before commencement of the work, a detailed coating procedure specification
containing, but not limited to, the following.
1.14.3.2 Aggregates shall be naturally occurring washed sand and shall be hard, dense,
durable, clean, sharp and graded evenly from fine to coarse, as per the grading
limits specified below, and be in compliance with BS 882. If in the opinion of
the Company, the aggregate contains an undesirable proportion of chemicals,
dust, clay, organic matter or other undesirable constituents, the consignment
shall be rejected. The grading of aggregate when plotted against sieve size
shall be within the limits tabulated below:
passing a no. 8 65 - 90
passing a no. 16 45 - 75
passing a no. 30 30 - 50
passing a no. 50 10 - 22
1.14.3.3 Water for use in concrete shall be clean and free from all substances which
may be injurious to concrete or steel. It shall satisfy the requirements of BS
3148 and contain no staining or colouring.
1.14.4 Application
1.14.4.1 Prior to concrete coating, Contractor shall apply a protective layer or ‘barrier
coat’ to epoxy coated pipe. The type of barrier coat to be used shall be a two
component fibre reinforced cementetious coating such as FBE Brushcrete,
Fosroc H.I.M, Epoxytar, Rezex water based epoxy coating ES2 or equivalent.
Contractor shall demonstrate to the satisfaction of the Company that the
proposed barrier coat prevents the occurrence of holidays in the epoxy coating
due to the concrete application process, and promotes a good bond between
the epoxy and concrete coating.
To this end one or more sections of a test joint shall each be coated with a proposed
barrier coat, in accordance with manufacturer’s recommendations. The number of
applications, film thickness and curing time shall be representative for the application in
the production process. The test joint shall be concrete coated, whereupon the concrete
is immediately washed off and each test section subjected to a holiday test and an
adhesion test both in accordance with Section 2. 7.
1.14.4.2 Batching, proportioning and mixing of the materials shall be such that a
concrete coating is provided with the minimum specified strength and density.
No batch of cement and aggregate shall be used in the work if it has stood for
more than half an hour after mixing. No rebound material shall be mixed into
any batch.
1.14.4.3 Contractor shall pay attention to the moisture content of the sand used for
guniting. If the sand is too wet, the hose will block and a mortar layer will build
up inside the gun. If the sand is too dry the cement will not adhere to the sand
grains on mixing and excessive separation will occur in the hose. In case the
moisture content falls outside the critical range of 5 to 8%, Contractor shall
make the sand suitably damp either by spraying the dry sand with water or
mixing wet sand with specially supplied dry sand.
1.14.4.4 The mixing equipment shall be capable of providing a uniform mix. The dry mix
used for guniting shall be screened to prevent inclusion of stone, flakes from
the mixer drum, pieces of cement bag, etc. Mix temperature shall not exceed
32°C.
a) The line pipe corrosion coating has been holiday detected and approved
by the Company.
b) The barrier coat (if required) has been applied and cured.
d) Shading has been installed to prevent the line pipe temperature exceeding
35°C.
1.14.4.6 Since the technique of guniting relies significantly on the skill of the nozzle
man, he shall have at least 3 years experience in work of a similar nature.
Other operators of the guniting crew shall have a minimum of one year’s
experience. Written evidence of such experience shall be furnished to the
Company. Contractor shall have a minimum of five years experience in
guniting or alternatively shall subcontract the guniting work to a specialist Sub
Contractor with similar minimum experience level. The guniting crew shall
demonstrate their ability to consistently coat pipe to this specification by
guniting at least three separate quarter length pipe samples prior to start of
production.
1.14.4.7 Before directing the guniting nozzle onto the pipe surface the nozzle man shall
ensure that the proportioning of water and dry mix is correct. Further regulating
of the water supply should be kept to a minimum to ensure uniform concrete
quality. The nozzle shall be held in the optimum position for placement at all
times i.e. 0.6 to 1.2 m from and at right angles to, the surface of the pipe.
1.14.4.8 The outer surface of the concrete coating shall be smooth, without
corrugations and concentric with the steel pipe. At both ends of each pipe, a
distance of approx. 0.30 m from the end shall be completely left free of
concrete to facilitate field joints. The concrete shall taper back from these
points at a two-to-one slope until the required thickness of coating is reached.
1.14.5 Curing
1.14.5.1 The finished concrete coating shall be completely protected from wind,
draught, rain, spray, etc. for a minimum period of 7 days by wrapping with
suitable hessian or polyethylene sheeting. Also during this period the pipe shall
not be exposed to direct sunlight and/or temperature below freezing point.
After a period of 4 hours from placement and for the 7 days curing period, the
concrete surface shall be kept wet.
1.14.5.2 The concrete coated pipe shall not be lifted or transported from the curing area
during the 7 day curing period. The Contractor shall take precautions to
prevent detrimental movement of line pipe after concrete coating to minimise
handling stresses whilst concrete is hardening and curing.
1.14.5.3 For factory applied coating, any other curing methods apart from that
mentioned in 2.10.5.1 may be adopted subject to approval of the Company.
1.14.6.1 Every length of coated pipe shall be inspected visually and by spiral ring
holiday detector and repaired, in accordance with Section 2.7, Anti-Corrosion
Coatings, prior to concrete application.
1.14.6.2 The concrete shall be visually inspected immediately after the application and
after approximately 3 days. If concrete is faulty, Contractor shall remove cores
from the suspected pipe. If the compressive strength tests of the cores fail to
meet the specified strengths, Contractor shall remove the defective coatings by
Company approved method, inspect and where necessary repair the corrosion
coating or reapply the concrete coating. Contractor may optt not to wait for the
test results and immediately initiate the stripping and subsequent coating repair
work.
1.14.6.3 Test panels, made from mild steel, shall be made every day, one at the start of
work, and one during the day as instructed by the Company. These test panels
shall be positioned alongside the work and in a position similar to the work
(horizontal, vertical or overhead) and gunited. On a regular basis, to be
decided by the Company, cores shall be taken from each test panel after it has
cured in a similar manner as the coated pipe.
1.14.6.4 Core samples shall be obtained using a diamond core cutter set to ensure that
the cut is perpendicular to the surface and fitted with a positive depth of cut
limit to ensure that the core barrel shall not penetrate closer than 6 mm to the
corrosion coat of the line pipe, where applicable.
The minimum diameter of the core shall be at least three times the nominal maximum
aggregate size. The length to diameter ratio of the core when trimmed for testing shall
not be less than one-to-one. Sampling, storing, testing and calculation shall be in
accordance with the provisions of BS 1881. Cores shall be cut four days after concreting
and stored in a curing tank until tested.
Company may accept any other method of testing that Contractor can demonstrate to
give a consistently reliable measure of strength attained by the concrete coating. Cube
tests will be accepted for crushing strength instead of core samples, but the required
compressive strengths will be 20% greater than specified for core tests. The Contractor
shall arrange for an independent agency acceptable to the Company to test these
cubes.
1.14.6.5 The thickness of applied concrete coating shall be measured on every joint at
three or more points to check compliance with the minimum requirements as
per Section 2.10.2.2. The three points shall be spaced at approximately equal
intervals with distance between the end points at least eighty (80) percent of
the coated length. Concrete coatings not in accordance with the dimensional
requirements shall be repaired or stripped and recoated at the discretion of the
Company.
1.14.6.6 Factory applied coated pipes shall be weighed and weight of each coated pipe
shall have a tolerance of +10% on any one joint and a tolerance of –4% on the
total length as calculated from the specified density and thickness. Weighing
devices used to determine the weights of the coated joints shall be certified in
writing to provide an accuracy of one half on one percent (0.5%).
1.14.6.7 Effective electrical separation between reinforcing steel and pipe shall be
determined for each pipe joint by electrical tests.
1.14.7.1 Concrete coating that is found to be defective at the time of coating shall be
immediately stripped from the pipe and the pipe recoated. All other defects
shall only be repaired once the concrete has hardened.
Repairs shall be made by satisfactorily restoring the reinforcing, removing all cracked or
broken concrete at the point of coating damage, wetting the fresh surface of the broken
coating (unless the coating is still too ‘green’ to require it), and troweling a stiff mixture of
cement, water and aggregate, of the same materials and proportions as the coating, into
and through the reinforcing. This mixture shall be built up until the surface is level with
the coating around the repair. The pipe shall then be allowed to moist cure for a
minimum of four days. The resulting coating shall be equal in weight, density, uniformity,
strength and characteristics to the originally applied coating.
1.14.7.3 Concrete cracks that are in excess of 1.5 mm in width and extend over 180°
circumferentially around the pipe, or where cracks are over 330 mm in length
longitudinally along the pipe irrespective of width, shall be repaired. Repairs
shall be made by chiselling the crack out to width of not less than 25 mm
throughout the length of the crack. The crack shall be repaired with materials
similar to that from which the coating is made and in a manner similar to that
outlined above.
1.14.7.4 Core sample holes shall be repaired with materials similar to that from which
the coating is made and in a manner similar to that outlined above. The repairs
shall be kept moist and allowed to remain undisturbed for a period of not less
than 36 hours. Further curing shall be in accordance with the Specification.
This Section of the Specification covers the minimum requirement for the supply and
installation of permanent pipeline markers and access barriers, as required for the Work.
1.15.2 General
The Contractor shall supply and install permanent pipeline markers along the pipeline
route as close as possible to the windrow. Construction details of all types of markers
are shown on the drawings. Each marker consists of a post sealed with a cap end,
mounted with two marker plates as per the drawings. Marker plate no. 1 shows general
information about the pipeline involved, whereas marker plate no.2 shows relevant
information for each location. The different types of pipeline markers are listed below.
As-built chainage shall be indicated on the marker plates with an accuracy of one meter.
(The start point of the pipeline, KP 0, shall be the pipeline isolation valve in the scraper
trap station).
Crude : red
Gas : blue
Water : green
The marker plates shall be parallel with the pipeline i.e. they shall face the R.O.W.
access road. Separate markers are required on parallel lines.
Chainage markers shall be installed along the pipeline at each one (1) kilometre
chainage station. A chainage marker is not required if the distance between its location
and any other type of pipeline marker, as mentioned hereafter in this section is less than
200 metres.
Block valve station markers shall be installed along the pipeline at each block valve
station. A schematic diagram of the block valve station pipe work layout shall be installed
on the block valve station fencing.
Road crossing markers shall be installed at both sides of each paved or graded road
crossing. Location shall be 5metres from the borders of the road.
Wadi crossing markers shall be installed at both sides of each wadi crossing.
Cable crossing markers shall be installed at each crossing with an existing underground
cable.
Markers shall be installed at the tangent points of each horizontal bend, with an
indication of the actual bend angle of the pipeline at that location.
At all C.P. test stations, bonding stations and negative connection stations, a pipeline
marker shall be installed. Locations shall preferably be combined with chainage markers.
At pig trap stations, the insulating joint test station post/marker shall be installed outside
the station fence but no further than 25 m from the insulating joint.
A marker shall be installed adjacent to each Pearson Survey earthing hole. Ref. GEN-2-
1632-01.
At each road crossing, permanent `STOP` signs shall be installed on the R.O.W. access
strip, at both sides of the road for the attention of drivers of maintenance vehicles on the
R.O.W.
A marker shall be installed adjacent to each of the corrosion monitoring pit, in the case
where the pit is not located inside a station. The marker shall be inside the pit with
fencing.
1.15.14.3 Painting of access barriers shall be in black and yellow bands of 0.3 m length.
Paintings shall be carried out in accordance with Section 2.12, Station Works.
This Section of the Specification covers the minimum requirements for all above and
below ground station works, including pig trap and block valve stations. The sections
below make reference to relevant PDO Specifications and detail any additional
requirements. The following works are included in this Section:
- Earthworks
- Painting
- Instrumentation
- Electrical Works
- Fencing
Requirements for the following related activities are included in other sections of this
document or other Specification.
- Materials
- Cathodic Protection
- Hydrotesting
- Use of explosives
- Access barriers
Contractor shall supply all materials and equipment unless stated otherwise in the
Schedules.
1.16.2 Earthworks
a) Pig trap station plots will be prepared, by others, to final elevations unless
specifically stated otherwise in the Scope of Work/Drawings.
1.16.3.1 General
a) All station works shall be fabricated and installed in accordance with the
Drawings and this Specification, including standard Civil and Mechanical
drawings from ERD 10-11 and ERD 38-04, respectively.
c) Contractor shall maintain the elevations shown on the drawings and carry
out any pipework adjustment necessary to achieve this.
d) Valves with flow arrows shall be installed in the normal flow direction of
the product.
c) Anchor bolts, pipe sleeves, anchor rails, insert and sliding plates shall be
built in as formwork proceeds. They shall be positioned accurately and be
firmly fixed such that no movement shall occur during the concrete pour. If
provision is to be made to allow for slight adjustment in position of anchor
(holding-down) bolts, this shall be clearly indicated on the detail foundation
drawings with the method(s) to be applied.
The on-plot Specification states that all welding shall be by the uphill
technique. In certain circumstances, downhill welding may be considered
for filling and capping runs, any proposals for which shall be reviewed on a
case by case basis by the Company welding TA-2 and endorsed by the
CFDH Welding.
f) In the event that anchors are required, these shall be installed at the
locations shown in the drawings. The anchor flange with a pipe joint
welded at both ends shall be completely installed prior to start of civil
work. The anchor flange to be embedded in the concrete shall be coated
in accordance with Section 2.12.4 below. Pipe coating shall be tested with
the holiday detector prior to embedding in concrete. The concrete work
shall be backfilled and left to cure a minimum of three weeks before
further joints are allowed to be welded to the anchor flange assembly.
1.16.4 Painting
a) All above and below ground steel surfaces (with the exception of
polyethylene or epoxy coated pipework and items supplied in a
manufacturer’s finish) shall be prepared and painted in accordance with
this Specification.
b) Valves and insulating joints shall be supplied with a single coat primer
only, in accordance with SP-1246.
Handrails black
1.16.5 Instrumentation
Contractor shall carry out instrumentation works in accordance with SP-1088 and DEP
62.10.08.11 GEN.
1.16.7 Fencing
a) The fencing required for the Work shall be of the medium security type,
and be supplied and constructed in accordance with SP1279-P. The exact
requirements for each location are shown in the drawings.
1.17.1.1
1.17.1.3 When a complete new C.P test points connects to an existing system, then the
Contractor shall employ a qualified C.P supervisor who shall have the prior
approval of the Company. When solar panels are required, Contractor shall
sub-contract the supply/installation to a Company approved
supplier/contractor.
1.17.1.4 Contractor shall give the Company 5 days notice prior to installation of special
C.P items i.e. solar stations, T/R units and ground bed anode systems, in order
to mobilise a Company CP Inspector.
1.17.2 Materials
Contractor shall procure all materials required for the Work, unless stated otherwise in
the Schedules. Specifications for materials shall be as shown on the drawings. The
following Company Specifications are applicable:
1.17.3 Installation
1.17.3.1 Installation of the C.P. System shall be carried out concurrently with the main
pipeline laying work.
1.17.3.3 Cable connections to the pipeline (Ref. STD-7-2001) shall also be required, as
shown on the Drawings, at the following locations:
- pipeline crossings
- negative connections
- earthing electrodes
- insulating joints
1.17.3.4 All C.P. testing facilities shall be installed in accordance with SP-1129.
1.17.3.5 Where Foreign Service Bonding Facilities are required on foreign services, for
cross bonding, the connection pad may be attached by welding a pad on the
foreign services (Ref. STD-7-3005).
1.17.3.6 Current Measuring Stations shall be installed on the pipeline every 10 km,
unless shown otherwise on the drawings (Ref. STD-7-3004).
1.17.3.7 A Grounding Facility shall be installed at power line crossings and where the
pipeline runs parallel to, and within 50m of a power line (Ref. STD-7-3006).
1.17.3.8 Drain Point Facilities shall be installed as shown on the Drawings (Ref. STD-7-
3003).
1.17.3.10 All C.P. cables shall be installed in accordance with SP-1129. Cable to pipeline
connections shall be made prior to hydrostatic testing. Cable markers shall be
installed in accordance with drawing STD-7-7001.
1.17.3.11 Ground beds, when required and shown on the Drawings, shall be installed in
accordance with SP-1129(Ref. STD-7-6001, STD-7-6002, STD-7-6003, and
STD-7-6004).
In the case that the pipeline is to be buried in a highly corrosive soil and when the
installation of the permanent cathodic protection system cannot be finalized before the
pipeline is buried (pipelines with long construction periods) a temporary cathodic
protection system shall be installed. Such a system shall be designed in the same way
as a permanent cathodic protection system with the exception that material quantities
and quality shall be adequate to cover a lifetime equal to the time of the pipeline
construction until the expected commissioning of the permanent cathodic protection
system. Anode connections shall be constructed such that they can easily be
connected / disconnected during and/or after commissioning of the permanent system.
1.17.5.1 Company will carry out a ‘Pearson Survey’, after installation of the pipeline, to
check the integrity of the buried pipeline coating. In order to achieve good
earthing for this survey, Contractor shall install Pearson Survey Earthing Points
adjacent to each 2 km C.P. Standard Test Post. If coating defects are found on
any portion of the coating, Contractor shall excavate, repair and backfill at
Contractor’s expense.
1.17.5.2 These earthing points shall be constructed during the main pipelay work, in
accordance with drawing GEN-2-1633-01.
1.17.6 Commissioning
The minimum requirements for precommissioning of oil and gas pipelines including but
not limited to bulk dewatering, final dewatering, cleaning, drying and preservation of oil
and gas pipelines as required for the Work are covered under a separate DEP
31.40.50.30.
1.20.2 General
1.20.2.1 Contractor shall make detailed proposals, for Company approval, for the
precommissioning work including but not limited to detailed procedures,
programme and schedule for Work. Contractor’s proposals shall include
complete information regarding the following aspects:
- complete summary and lay out of the temporary pipework, equipment and
facilities including spares for each section to be pre-commissioned.
- a summary of the amount of material and consumables and the number and
qualifications of personnel, to be used for the precommissioning work.
- calculations and any other evidence necessary to demonstrate that the work
will be executed in accordance with the requirements of the Contract. The
sizing of drying equipment and calculations of the time required for drying shall
be based on a film thickness of residual water of not less than 0.1 mm. Lower
values may be assumed if the Contractor can demonstrate, to the Company's
satisfaction, their validity from previous experience.
This Section of the Specification covers the minimum requirement for work on live pipe
systems as required for the Work.
1.21.2 General
1.21.2.1 The work permit system shall apply to all work on live pipe systems. Contractor
shall do all that is necessary to obtain work permits and to execute the Work in
adherence to the work permit.
1.21.2.2 Specialised tools and equipment as required for the performance of work on
live pipe systems shall only be acquired form the Company approved vendors.
A vendor’s representative shall be present at all times during the use of such
tools and equipment.
1.21.2.3 Hot tapping on live pipe systems shall be carried out in accordance with DEP
31.38.60.10. Welding on pressurised pipes shall be carried out in accordance
with SP-1167.
This Section of the Specification covers the minimum requirements for keeping and
maintaining records, drawings and documents of all aspects of the pipeline project.
These requirements supplement those contained in SP-1131, to which reference should
be made for the definitions and general requirements. The scope includes new pipeline
construction and modifications to existing lines and related facilities.
Where any conflict occurs with the requirements of SP-1131, this specification shall take
precedence.
Retention of information as hard copy shall be minimised and wherever possible master
copies of documentation shall be acquired and stored in a suitable electronic format.
Route survey data shall be presented in accordance with XTO documents TS18v1-0:
Pipeline Data Specification and TS19v1-0: Flowline Data Specification. All master
documents should be classified, coded and compiled on to a minimum number of fully
indexed compact discs or other media that may be specified by the Company. Controlled
and separately stored back-up copies of key items shall be maintained.
Documentation available only as hard copy shall be scanned for archiving. In the cases
where the required storage life is short (say, less than 2 years), or the document is not
suitable for scanning, exceptions to this requirement should be agreed by the
responsible Project Engineer in consultation with the relevant CFDH or nominated
discipline engineer.
Hard copies of whichever master documents are required for day to day operation and
maintenance, or for permanent reference to support future engineering activities during
the operational life, may be made as required provided documents maintained ‘As-Built’
are formally issued as controlled copies.
Master copies of all textual documentation after handover shall be held by the pipeline
owner (Asset Manager) in a properly managed archive. This shall include storage of
pipeline radiographs for the prescribed retention period before disposal. Autocad
drawings shall be stored and referenced in EDMS in accordance with Company practice.
Controlled hard copies of documents required for pipeline operation and maintenance
(Operating Manuals, Design Reference Manual, PEFS etc. as per Appendix D) should
be provided to Operations as part of the handover package. Issue of further documents
should be authorised and controlled by the Asset Manager.
A detailed listing shall be filed within EDMS Business Records of the storage location of
all master documents for each pipeline. This list, along with copies of all key drawings
within EDMS and the basic pipeline design and operating data held in SAP, shall be
linked to the relevant pipeline location in GIS to enable the data to be readily identified
and/or retrieved.
Original pipeline drawings and other documents required to be maintained ‘As-Built’ (see
Appendix D) shall be updated during the construction and commissioning phase in line
with SP-1131, Section 4. Subsequent revisions of the master documents shall be
authorised and all As-Built copies issued on a properly controlled basis in accordance
with CP-102.
1.22.5 Documents
Unless otherwise stated, Contractor shall provide originals of documents plus two
copies.
Contractor shall make available inspection, calibration and testing reports, (including
welding procedures, NDT procedures, radiographs, ultrasonic test reports, hydrostatic
testing and drying reports), as specified in applicable Sections of the Specification.
Contractor shall make available Mill and Test Certificates, where applicable, for all
materials supplied by Contractor and incorporated in the permanent facilities.
Contractor shall return to the Company one copy of each drawing (provided by the
Company) corrected with as-built information for those drawings in the Drawing List
which are indicated to be revised as as-built. These as-built drawings shall be submitted
for approval to the Company within 2 weeks of the Completion Date and shall be
approved by the Company before Acceptance of Work.
- Measured top of pipe level at each installed joint location, with chainage
- The chainage, elevation, size, type, shape of all roads, wadis, pipes, cables
and other objects crossing and/or obstructing the pipeline.
- The identification and the location of circumferential welds and pipe lengths
with the manufacturer’s number, heat number, sequence number and length
installed.
Contractor shall provide a site-based experienced, full-time ‘As-Built’ surveyor, with valid
driving licence and vehicle, throughout the duration of the Contract. He shall maintain the
Pipeline Data Sheets (originals provided by the Company) and shall collect and maintain
all data required for the ‘As-Built’ drawings. Refer to Pipeline Data Base requirements in
Appendix D.
‘As-Built’ drawings shall be prepared during the progress of the Construction Work and
Contractor shall provide a drawing office, personnel, and all necessary equipment and
facilities, to the approval of the Company, for the purpose of producing as-built drawings.
Preliminary ‘As-Built’ drawings shall be submitted to the Company for approval on a
weekly basis within 2 weeks of the completion of backfilling of the trench on that part of
the pipeline route contained on the drawing concerned.
ii. Abbreviations
REFERENCE REF #
PDO STANDARDS
Code of Practice
Corporate Document Management CP-102
Health Safety and Environment Management System CP-122
Specification
Civil and Building Standard Drawings ERD 10-11
Mechanical Standard Drawings ERD 38-04
Guidelines for excavation and working around live pipelines ERD 38-11
Specification for Qualification, application and inspection of ERD 48-04
shrink sleeves for corrosion protection
Specification for Aqueous Effluents SP-1006
Specification for Waste Management SP-1009
Specification for Site Preparation, Abandonment and SP-1012
Restoration
Mounting of Plant Instruments SP-1088
Specification for welding of Duplex Stainless Steel Pipelines SP-1097
Electrical Installation Practice SP-1099
Electrical Safety Rules SP-1104
Electrical Standard Drawings SP-1105
Specification for Earthing and Bonding SP-1109
Specification for Cathodic Protection Design SP-1128
Specification for Construction, Installation and SP-1129
Commissioning of Cathodic Protection System
Specification for Cathodic Protection Materials and SP-1130
Equipment
Specification for Handover and As-built Documentation SP-1131
Specification for Cathodic Protection Standard Drawings SP-1136
Specification for Earthmoving and Construction Equipment SP-1143
Specification for welding of martensitic Stainless Steel SP-1147
Pipelines
Specification for welding on pressurised pipes SP-1167
Specification for Quality Assurance of Design, Construction SP-1171
and Engineering works
Specification for welding of on-plot Pipework SP-1173
Specification for welding of Class 2 Pipelines (Flowlines) SP-1174
REFERENCE REF #
PDO STANDARDS
Specification for Welding of Class 1 Pipelines SP-1177
Specification for Application and selection of Standard Pipe SP-1187
Supports
Pipeline Operations and Maintenance SP-1210
Onshore Pipeline Engineering SP-1211
Hydrostatic Pressure Testing of New Pipelines SP-1212
Specification for Lifting Equipment and Lifting Operations SP-1239
Specification for painting and coating of oil and gas SP-1246
production facilities (Part 1 – 5)
Training requirements for lifting operations personnel SP-1251
HSE Specification, Camps, Offices, Laboratories, SP-1256
Workshops and Industrial Safety Specification
HSE Specification, Safety, Training Observation Programme SP-1259
(STOP)
Specification for Civil and Building Construction SP-1279
Specification for Reinforced Concrete – Production & SP-1282
Construction Guidelines
HSE Specification, Road Transport SP-2000
Procedure
Initial Start up Procedure PR-1169
Safe working Procedures for Cathodic Protection Systems PR-1234
Procedures for Lifting Operations PR-1508
Procedure for Analysis of Pipeline Road Crossings PR-1522
WinPCS Procedure PR-1561
Guideline
C-09 HSE Requirements and Guidance for use GU-140
Environmental Assessment Guideline GU-195
Guideline for the Granting of Engineering Technical GU-272
Authorities
Guidelines for the protection of buried sections of surface GU-368
laid Pipelines/Flowlines
REFERENCE REF #
SHELL STANDARDS
Index to DEP publications DEP 00.00.05.05-Gen.
Piping – General requirements DEP 31.38.01.11-Gen
Piping classes – exploration and production DEP 31.38.01.15-Gen.
Hot tapping on pipelines, piping and equipment DEP 31.38.60.10-Gen
Design of pipeline pig trap systems DEP 31.40.10.13-Gen.
Pipeline overpressure protection DEP 31.40.10.14-Gen
Upheaval buckling of pipelines DEP 31.40.10.16-Gen
GRP Pipelines and piping systems (amendments / DEP 31.40.10.19-Gen.
supplements to ISO 14692)
Line pipe induction bends (amendments / supplements DEP 31.40.20.33-Gen
to ISO 15590 – 1)
Linepipe for non-critical service DEP 31.40.20.35-Gen
(Amendments/supplements to ISO 3183-1)
Linepipe for critical service DEP 31.40.20.37-Gen
(Amendments/supplements to ISO 3183-3)
Pipeline Fittings (amendments / supplements to MSS DEP 31.40.21.30-Gen
SP – 75)
Pig signallers: Intrusive type DEP 31.40.21.33-Gen
Carbon and low alloy steel pipeline flanges for use in oil DEP 31.40.21.34-Gen
and gas operations (amendments / supplements to MSS
SP – 44)
Concrete coating of linepipe DEP 31.40.30.30-Gen.
External polyethylene and polypropylene coating for line DEP 31.40.30.31-Gen
pipe
External fusion-bonded epoxy powder coating for line DEP 31.40.30.32-Gen.
pipe
Thermoplastic lined pipelines DEP 31.40.30.34-Gen
Precommissioning of pipelines DEP 31.40.50.30-Gen
AMERICAN STANDARDS
Process Piping ASME B31.3
Pipeline Transportation Systems for Liquid Hydrocarbons and Other Liquids ASME B31.4
Gas Transmission and Distribution Piping Systems ASME B31.8
Issued by:
American Society of Mechanical Engineers
Publications and Distribution Section
1220 L Street Northwest
Washington DC 20005, USA
BRITISH STANDARDS
Code of Practice for the Safe Use of Explosives in the Construction Industry BS 5607
Issued by:
British Standards Institution
389 Chiswick High Road
London, W4 4AL, UK
INTERNATIONAL STANDARDS
Preparation of Steel Substrates before Application of Paints and Related
Products – Visual Assessment of Surface Cleanliness ISO 8501-1
Preparation of Steel Substrates before Application of Paints and Related
Products – Tests for the Assessment of Surface Cleanliness ISO 8502-1 to 4
Preparation of Steel Substrates before Application of Paints and Related
Products - Surface Roughness Characteristics of Blast-Cleaned Steel ISO 8503-1 to 4
Substrates
Preparation of Steel Substrates before Application of Paints and Related ISO 11124
Products - Specification for Metallic Blast-Cleaning Abrasives
Preparation of Steel Substrates before Application of Paints and Related ISO 11126
Products - Specification for Non-Metallic Blast-Cleaning Abrasives ISO 14692
Petroleum and Natural Gas Industries – Glass Reinforced Plastics (GRP) Piping
Petroleum and Natural Gas Industries – Induction bends, fittings and flanges for ISO 15590-1
pipeline transportation systems – Part 1: Induction Bends
Issued by:
International Organization for Standardization
1,Rue de Varembé
CH-1211 Geneva 20, Switzerland
C.2 Accommodation
C.2.1 Where the Contractor is required in the Contract Scope of Work to provide his own
camp, Contractor shall provide and maintain in its camp, good quality accommodation
for the number of Company’s senior personnel stated in the Scope of Work. Company
may choose to use this accommodation for personnel other than Company personnel.
C.2.2 Where the Contractor is required in the Contract Scope of Work to provide
accommodation for the Company’s personnel, the minimum accommodation
requirements for each of Company’s aforementioned senior personnel shall be:
a) Bed-sitting room of 14.0 square metres floor area. This shall be furnished
with:
C.2.3 Contractor shall replace all linen twice per week, clean all accommodation daily, and
keep all accommodation in good repair.
C.2.4 All accommodation provided for the Company’s use shall be subject to Company’s
approval.
C.3 Messing
C.3.1 Where the Contractor is required in the Contract Scope of Work to provide messing,
Contractor shall provide and maintain complete and clean messing facilities for the
Company personnel and shall provide adequate good quality meals with soft drinks at
such meals. The menu should have at least one alternative main course.
C.3.2 Contractor shall provide an adequate laundry service for the personal clothing of the
Company personnel.
C.3.3 Contractor shall keep the Company personnel refrigerators stocked with a selection of
soft drinks.
C.4.2 Unless otherwise agreed by the Company, office space for these persons shall have a
minimum floor area of 45 square metres and shall be supplied with the following for sole
use by the Company’s personnel:
C.4.3 The offices shall be interconnected. At each spread camp, the Contractor shall provide
and maintain for Company’s sole use such materials and equipment (computer,
stationary, etc.) as may be required for the Company’s clerical work at the camp.
C.4.4 As and when required, Contractor shall make available for Company’s use at the main
spread camp site, a furnished conference room of minimum floor area 24 square metres
and with seating for a minimum of 15 persons.
C.4.5 All offices and office services, provided for Company’s use shall be subject to
Company’s approval.
C.4.6 Contractor shall provide an administration clerk who is proficient in English, typing and
general office procedures, for Company use seven days per week throughout the
duration of the Contract.
C.4.7 Contractor shall provide a suitable Digital camera with two 128 MB memory sticks and
photo editing software for the exclusive use of the Company Site Representative.
C.5.2 Maintenance procedures shall be strictly in accordance with vehicle manufacturer’s local
representative’s recommendations for the specific terrain and climatic conditions
involved. A daily status check for all cars being used is required. Contractor shall
maintain vehicles of the Company with due diligence and utmost care to ensure safety of
the vehicles. Contractor shall keep a record of all checks and services for each
Company vehicle.
C.5.3 Contractor shall provide an English speaking driver with the necessary experience to
obtain a PDO driving licence for Company use seven days per week for the duration of
the Contract.
C.5.4 Where Contractor is required in the Scope of Work to provide vehicles for the use of
Company personnel, they shall at the start of the Contract be either new or have less
than 10,000 Km mileage. The vehicles shall be 4 wheel Drive, preferably Mitsubishi
Pajero V6 (LWB) or Company approved equivalent.
C.6.2 In each camp a 29” colour TV with DVD player shall be available for the sole use of
Company personnel.
C.6.3 Magazines and daily newspapers shall be provided by the Contractor as per Company’s
Site Representative’s requirements.
C.6.4 At each Contractor Camp, facilities shall be provided for outdoor sports (football, tennis,
etc.), type to be agreed with Company Site Representative.
Storage format
Document Category Remarks
Originator *
Retention time
Keep As-Built
Custodian **
Location
1.0 General Reports
1.1 Drawing control register DC (See remarks) N/A N/A Retained until drawings are as-built and stored in
EDMS.
1.2 Pipeline inspection reports CC Service life Electronic or Paper Archive Archived items to be referenced in EDMS.
1.3 Equipment reports Vendor Service life Electronic or Paper ✓ Archive Archived items to be referenced in EDMS.
1.4 Operating manual DC Service life Electronic ✓ EDMS Essential data for each line held in PACER,
accessed via GIS
1.5 Design reference manual DC Service life Electronic ✓ EDMS Essential data for each line held in PACER,
accessed via GIS
1.6 Soil investigation report SC 2 years Paper Archive Storage reference in EDMS.
1.8 Studies - feasibility/conceptual/ front end DC Project completion N/A N/A Conceptual data underlying chosen design options
(see remarks) to be retained with DRM (1.5 above)
1.9 Technical audit/HAZOP reports DC (See remarks) Electronic EDMS Retained until close out of HAZOP actions.
2.1 Plot plans DC Service life Electronic/Paper ✓ EDMS Drawing reference in GIS. Note, benchmark
locations included in plot plans.
2.2 Hazardous area classification drawing DC Service life Electronic/Paper ✓ EDMS Drawing reference in GIS.
2.3 Process flow schemes DC Service life Electronic/Paper ✓ EDMS Drawing reference in GIS.
2.4 Utility flow schemes DC Service life Electronic/Paper ✓ EDMS Drawing reference in GIS.
2.5 Process and engineering flow scheme DC Service life Electronic/Paper ✓ EDMS Drawing reference in GIS.
2.6 Utility and engineering flow scheme DC Service life Electronic/Paper ✓ EDMS Drawing reference in GIS.
2.7 Material identification diagram DC Service life Electronic/Paper ✓ EDMS Drawing reference in GIS.
3.2 Foundation location plan DC Service life Electronic/Paper ✓ EDMS Drawing reference in GIS.
3.3 Fencing and grading plan DC Service life Electronic/Paper ✓ EDMS Drawing reference in GIS.
3.4 Non-standard pipe supports, guides and anchors DC Service life Electronic/Paper EDMS Drawing reference in GIS.
Storage format
Document Category Remarks
Originator *
Retention time
Keep As-Built
Custodian **
Location
4.1 Piping key plans DC Service life Electronic/Paper ✓ EDMS Drawing reference in GIS.
4.2 Piping plans DC Service life Electronic/Paper ✓ EDMS Drawing reference in GIS.
4.3 Equipment data sheets Vendor Service life Electronic or Paper Archive Archived items to be referenced in EDMS.
4.6 Material/equipment requisitions DC/PE See remarks Electronic EMA Retain for longer of guarantee period or 2 years.
Reference in EDMS
5.1 Pipeline routing key plan DC Service life Electronic ✓ EDMS Drawing reference in GIS.
5.2 Route maps XTO/2 Service life Electronic or Paper ✓ GIS Ref. TS18V1-0.doc & TS-19V1-0.doc
5.3 Alignment sheets DC Service life Electronic/Paper ✓ EDMS Drawing reference in GIS.
5.4 Station approach drawings DC Service life Electronic/Paper ✓ EDMS Drawing reference in GIS.
6.1 Single line diagram DC Service life Electronic/Paper ✓ EDMS Drawing reference in GIS.
6.2 Power cable layout layout drawing DC Service life Electronic/Paper ✓ EDMS Drawing reference in GIS.
6.3 Earthing layout drawing DC Service life Electronic/Paper ✓ EDMS Drawing reference in GIS.
6.4 Lighting layout drawing DC Service life Electronic/Paper ✓ EDMS Drawing reference in GIS.
6.5 Cable schedule DC Service life Electronic/Paper ✓ EDMS Drawing reference in GIS.
6.6 Trench layout DC Service life Electronic/Paper ✓ EDMS Drawing reference in GIS.
6.7 Electrical material requisitions DC/PE See remarks Electronic EMA As 4.6, above.
7.1 Instrument location plan DC Service life Electronic/Paper ✓ EDMS Drawing reference in GIS.
7.2 Instrument data sheets DC Service life Electronic/Paper ✓ EDMS Drawing reference in GIS.
7.3 List of alarm and trip settings DC Service life Electronic/Paper ✓ EDMS Drawing reference in GIS.
7.4 Shutdown matrices DC Service life Electronic/Paper ✓ EDMS Drawing reference in GIS.
Storage format
Document Category Remarks
Originator *
Retention time
Keep As-Built
Custodian **
Location
7.5 Functional logic diagram DC Service life Electronic/Paper ✓ EDMS Drawing reference in GIS.
7.6 Loop diagrams DC Service life Electronic/Paper ✓ EDMS Drawing reference in GIS.
7.7 Alarm annunciator system DC Service life Electronic/Paper ✓ EDMS Drawing reference in GIS.
7.8 Control room layout DC Service life Electronic/Paper ✓ EDMS Drawing reference in GIS.
7.9 List of telemetry points DC Service life Electronic/Paper ✓ EDMS Drawing reference in GIS.
7.10 Control room instrument cable layout DC Service life Electronic/Paper ✓ EDMS Drawing reference in GIS.
7.11 Junction box layout DC Service life Electronic/Paper ✓ EDMS Drawing reference in GIS.
7.12 Instrument requisitions DC/PE See remarks Electronic ✓ EMA As 4.6, above
8.1 Ground bed layouts DC Service life Electronic/Paper ✓ EDMS Drawing reference in GIS.
8.2 Wiring diagrams/cable sizes DC Service life Electronic/Paper ✓ EDMS Drawing reference in GIS.
8.3 Cabling routing layout DC Service life Electronic/Paper ✓ EDMS Drawing reference in GIS.
8.4 Transformer rectifier plot layout DC Service life Electronic/Paper ✓ EDMS Drawing reference in GIS.
8.5 Layout of CP facilities DC Service life Electronic/Paper ✓ EDMS Drawing reference in GIS.
8.6 CP survey report SC Service life Electronic or Paper Archive Archived items to be referenced in EDMS.
8.7 CP material specification report SC Service life Electronic or Paper Archive Archived items to be referenced in EDMS.
8.8 CP installation specification SC Service life Electronic or Paper Archive Archived items to be referenced in EDMS.
9.1 Welding and NDT procedures CC Service life Electronic or Paper Archive Archived items to be referenced in EDMS.
9.2 Welding/NDT progress chart CC 2 years Paper Archive Storage reference in EDMS.
Storage format
Document Category Remarks
Originator *
Retention time
Keep As-Built
Custodian **
Location
9.3 NDT reports/Test packs CC Service life Electronic or Paper Archive Archived items to be referenced in EDMS.
Relevant data to be entered in PACER.
9.4 Radiographs CC 2 years Film Archive Storage reference in EDMS.
9.5 Commissioning documentation OTL 2 years Paper Archive Storage reference in EDMS.
9.6 Hydrotest certificates CC Service life Electronic or Paper Archive Archived items to be referenced in EDMS.
Relevant data to be entered in PACER.
9.7 Insulating coupling test forms CC Service life Electronic or Paper Archive Archived items to be referenced in EDMS.
Relevant data to be entered in PACER.
9.8 Instrument calibration certificates CC 2 years Paper Archive Storage reference in EDMS.
9.9 Launcher and receiver inspection form CC Service life Electronic or Paper Archive Archived items to be referenced in EDMS.
9.10 Punch list PE (See remarks) N/A N/A Retained until actions cleared.
9.11 CP Installation inspection report CC Service life Paper Archive Storage reference in EDMS.
9.12 Construction drawings CC (See remarks) N/A N/A Retained until master drawings are updated.
9.13 Misc. site correspondence, records, MOM etc. CC Project completion N/A N/A Selected documents of contractual significance
may be archived for 2 years.
10.0 Vendor Documents
10.1 Vendor drawings for end closures, valves, Vendor Service life Electronic or Paper Archive Storage reference in EDMS.
insulating couplings, barred tees
10.2 Material certification, reports and test data for Vendor/TPI Service life Electronic or Paper Archive Archived items to be referenced in EDMS. Surplus
linepipe and fittings. material documentation held by TSP.
10.3 Material certification, reports and test data for static Vendor/TPI Service life Electronic or Paper Archive Archived items to be referenced in EDMS.
and rotating equipment
10.4 Certification, reports and test data for surplus Vendor/TPI Until required Electronic or Paper Archive Archived items to be referenced in EDMS.
materials
10.5 Operating instruction manuals Vendor Service life Electronic or Paper Archive Archived items to be referenced in EDMS.
10.6 Maintenance instruction manuals Vendor Service life Electronic or Paper Archive Archived items to be referenced in EDMS.
10.7 SPIR forms Vendor Service life Electronic or Paper Archive Archived items to be referenced in EDMS.
Abbreviations
CC Construction Contractor
Storage format
Document Category Remarks
Originator *
Retention time
Keep As-Built
Custodian **
Location
DC Design Contractor
SC Specialist Contractor
** The Project Engineer shall distribute the documents to the respective Custodians as per Company policy.
Sr.
Sketch No. Rev. Drawing Title
No.
NOTES:
SECTION A-A
The numbering system in this Appendix is designed to allow for easy reference back to
the main text by using the same numbering system contained therein. Wherever
applicable, only additional requirements and modifications pertaining to construction of
GRE pipelines are given in this Appendix.
Activities that are largely common to both material groups, e.g. HSE, clearing, trenching
etc., are included in the main text of this specification. Whilst these general topics may
be applied to the installation of any non-metallic linepipe material, including thermoplastic
liners, specific requirements and guidelines in the current version of this Appendix are
primarily concerned with GRE pipelines.
Apart from PE linings, GRE is the only non-metallic pipe material which has been used
by PDO for Class 1 pipelines in Hydrocarbon service. PE lining and RTP linepipe have
been in regular use for Class 2 pipelines (mostly flowlines) for a number of years.
Current PDO specifications DEP 31.40.30.34 / ERD 43-15 and ERD 43-16 apply for
procurement and installation of these materials. GRE pipelines shall be installed in
accordance with this specification and ISO 14692-4, taking due account of the limitations
noted in the GRE linepipe purchase requisition and associated stress analysis executed
by the GRE linepipe vendor.
2. Specification Requirements
2.2 Quality Assurance
2.2.3 Quality Assurance Team
2.2.3.1 Personnel
The Head of Quality Assurance shall have a detailed knowledge of installation and
inspection of GRE pipelines. He shall have general experience in quality assurance
matters and be suitably qualified.
2.2.3.2 Organisation
Contractor shall confirm to the Company at an early stage in the project that the testing
methods of factory made GRE spools, piping and fittings are acceptable for installation.
The Company shall review and approve the test results prior to start of construction.
2.3.3.1 The Contractor shall visually inspect and dimensionally check each pipe and fitting. For
Company supplied materials, the inspection shall be done before removal of the material
from the Company’s storage yards. Whereafter the Contractor shall accept responsibility
for all material losses and damage however caused. The inspection shall include a
detailed check for damage or dimensional non-conformances of bells and spigots. Any
shortages, dimensional non-conformance, missing end protectors or damage, including
scratches, gouges, crushing, cracking etc. shall be reported to the Company within 24
hours of receipt.
2.3.4.1 Pipe shall not be allowed to drop or strike objects which may damage the pipe but shall
be lifted, moved and lowered from one position to another by suitable equipment. Non-
abrasive wide nylon or canvas pipe slings of minimum width 200mm shall be used for
lifting pipe. Chains, cables or clamps shall not be used.
2.3.4.2 Trucks used to transport pipes shall be flat-bottomed and free of any projections or loose
materials that might damage or contribute to movement of the pipe during transport.
Pipes shall be protected against truck beds and side metallic protrusions by means of
non-metallic soft materials. Pipes shall be loaded and stacked on trucks in such a
manner that flexing and shifting of the pipe during transport is avoided. After loading,
suitable non-metallic slings shall be used to tie the load securely to the truck. During
transport the tension of these slings shall be regularly checked. The Contractor shall
ensure that no pipe end protectors can be lost during transport. Pipes shall only be
transported on trucks (sidebooms and other lifting equipment shall not be used to
transport pipe on site for distances in excess of 50 meters).
2.3.5.1 Ground surfaces to be used for stacking of pipe shall be reasonably flat. Pipe shall not
be laid directly on the ground, concrete floors or on to rails. Pipes shall be laid on
suitable supports, such as timber of 100mm x 50mm section. End protectors shall
remain in place during storage and care shall be taken to ensure adjacent socket and
spigot ends are kept out of contact. End protectors may be punctured with a 5mm drill to
prevent them blowing off the pipes.
2.3.5.2 Pipes may be stacked to a height of 1.5m provided suitable supports are provided both
at the sides of the stack and between layers. Typically, 100mm x 50mm timber (spacer
stripping) may be used for both purposes. Supports between layers should be in vertical
alignment, located no more than 3m apart and a minimum of 1m from the pipe ends.
Where strapping down of stacks is necessary, nylon straps should be used, and for long
storage periods a suitable cover should be fitted on each stack. Additionally, the
Contractor shall comply with GRE pipe manufacturer’s recommendations for pipe
stacking. In the case of a conflict or ambiguity, the Company will determine which
requirements shall apply.
2.3.5.3 Pipes of different diameter, wall thickness, pressure class, material grade or
manufacturer shall be stacked separately. Each stack shall be properly marked to the
satisfaction of Company.
2.3.6.1 Adhesives, resins and additives shall be stored in accordance with the manufacturer’s
written instructions in a cool air conditioned area, away from direct sunlight and
excessive humidity. Adhesives shall be kept in refrigerated conditions if the storage
period is in excess of one month, or as specified by the manufacturer, whichever is
shorter. Contractor shall demonstrate compliance with site storage procedures for all
consumables in accordance with detailed consumable handling procedures. A
continuous record of temperatures of adhesive storage conditions shall be maintained.
2.3.6.2 For reasons of safety, hardeners, catalysts and accelerators shall be stored separately
in accordance with manufacturer’s instructions. Solvents shall be similarly segregated as
required by the relevant Material Safety Data Sheets.
2.3.6.3 No consumables shall be stored or used beyond its stated shelf life.
2.3.6.4 GRE fittings shall be stored inside or in their original crates out of direct sunlight.
2.4.3.2 Excavation
d) The Contractor shall excavate and grade the trench sufficiently deep and wide to
provide a minimum of 500 mm working space on both sides of the pipe (where
jointing is done in the trench) and space for 150 mm of padding material after
compaction all around the pipe and for the continuous length of the pipeline. The
trench profile after excavation shall be such that the radius of curvature in any plane
is greater than the minimum allowable bending radius specified by the linepipe
vendor. Local high and low points in the trench bottom shall be levelled off to provide
a smooth continuous profile. The Contractor’s surveyor shall survey the trench and
submit a formal report with photographs, survey data and a detailed profile drawing
with invert levels at 12 m spacing, providing evidence that this requirement is
achieved.
i) The Contractor shall do hand work in the trench as is necessary to free the bottom
of the trench of loose rock, stones and all other irregularities so as to leave the
trench bottom in a clean and suitable condition to receive the pipe. A fulltime
dedicated crew shall be employed by the contractor to maintain the trench in a rock-
free condition before and after pre-padding has been installed, at all times until the
trench is completely backfilled.
2.5.3.1 Small changes in direction, in the vertical as well as the horizontal plane, may be
achieved by elastic bending, provided the bend radius is greater than the specified
minimum elastic bending radius specified by the pipe manufacturer for the supplied
linepipe. Where this is not possible, e.g. due to right-of-way restrictions, fabricated
elbows shall be used, as specified in the design drawings and approved by the linepipe
manufacturer and the Company. Special attention is required at transitions between
above ground and buried installation to avoid elastic bending. At locations where the
pipeline comes above ground, the bottom of the trench shall be flat for a minimum
distance of 25 m. In this section, elastic bends are not permitted. Any changes to the
design layout of the pipeline, including moving of bend locations shall be subject to
written approval of the Company and the linepipe manufacturer. This may require
revised stress analyses to be executed for the pipeline.
2.5.3.2 To allow for large expansion at bends such as those caused by wide temperature
fluctuations or hydrotest conditions, expansion cushions shall be installed as per design
behind each bend and extending to approximately 5 m each side of the bend. However,
it is required to accommodate the expansion of bends through proper design and stress
analysis.
2.6 Jointing
2.6.1 This section of the specification covers requirements for the jointing of GRE pipelines.
The requirements for qualification and production jointing of all types joints including
laminated joints are specified in ISO 14692-4.
2.6.2 The Contractor shall prepare a Method Statement covering the jointing work to be
carried out and a detailed procedure for each type and size of joint and fitting to be
joined. These shall be in accordance with the Manufacturer’s instructions, Company
specification and standards. Separate procedures shall be prepared for shop fabrication,
site jointing work and repair work. All joint types shall be qualified and approved by the
Company before its use in production joints.
2.6.3 In order to ensure piggability of the pipeline during hydrotest water filling, in service and
for future decommissioning work using foam pigs, particular attention shall be paid to the
need for effective internal cleaning of each completed GRE adhesive bonded joint after
fit-up, and prior to curing, in order to ensure that no significant amount of adhesive
protrudes from the inside seam of any glued joint. Reference is made ISO 14692-4 table
4.where it is specified under possible defects – excess adhesive shall not be more than
5% of inner diameter or 10mm which ever is less. The Contractor shall propose a
method for cleaning the internal joints for Company review and approval in his detailed
jointing procedure.
2.6.4 Each joint shall be inspected and certified by the QC Engineer to have been executed in
accordance with the approved jointing procedures. Inspection or witnessing of the make
up of any joints by the manufacturer’s field service engineer shall not absolve the
Contractor of his responsibilities to provide a fit for purpose joint. As a minimum, the
Contractor shall keep detailed records of make up and curing time, batch number of
adhesive components as well as jointer ID and date/time for each joint.
2.6.6 No more than 3 km of pipe shall be jointed prior to successful completion of the
hydrotest of the first section of 50 joints of installed pipeline.
2.6.7 All documents shall be submitted to the Company for approval. Procedures and
operators shall be qualified to the requirements of the controlling specifications before
commencement of any production jointing.
2.8.2.1 All trenches shall be fully pre-padded before lowering in or jointing in the trench. No
padding shall be placed until Company has inspected and approved the trench bottom
and the Contractor’s surveyor has confirmed that the trench bottom profile complies with
the pipe manufacturer’s minimum bending radius requirements.
2.8.3.1 All pipes shall be lowered in within 96 hours of completion of jointing. The Contractor
shall keep the lowering in operation within 1 km of the jointing operation.
2.8.3.3 A minimum of 3 sidebooms shall be used for lowering in strings of jointed pipe in excess
of 50 meter. Cranes shall not be used for lowering in operations of pipe strings longer
than 50 meters. The trench shall be maintained in a dry condition during lowering-in and
backfill operations. During lowering in operations the pipe shall not be subject to bending
in excess of the minimum allowable bending radius. A detailed procedure specifying the
means of demonstrating compliance with the minimum bending radius requirement shall
be submitted as part of the Contractor’s installation procedures, for Company approval,
at least 3 weeks prior to the planned commencement of any lowering in operations.
2.8.3.4 The Contractor shall take measures to restrain the pipe in the trench by means of
‘plugging’, i.e. placing sand on top and around the pipe at regular intervals (one 6m ‘plug’
in the middle of every pipe) or by a Company approved equivalent method. The
Contractor shall plan the work such that the lowering in and ‘plugging’ operations take
place together during the coolest part of the day, (i.e. in the morning). Strings longer
than 100 meter shall not be allowed to lie in the trench without sand plugging. This is to
avoid ‘snaking’ and abrasion of the pipe due to thermal movement.
2.8.3.5 Sand padding ‘plugs’ shall be placed around and above the pipe, so as to fill the trench
to a depth of 300 mm above the crown of the pipe, with the sand padding shaped to its
natural angle of repose and with a minimum of 150 mm at any point around the pipe. No
pipe shall be left overnight in the trench without sand padding around and above the
pipe. (Joints shall be left fully exposed around the joint circumference for inspection until
completion and acceptance of the hydrotest)
2.8.4 Tie-ins
2.8.4.1 Unless otherwise agreed by the Company, tie-ins of the pipeline sections shall take
place in the trench by means of the same type of connections as the pipeline or if the
pipeline connections are not of bonded type, by means of glued connections, using
couplings if necessary. For tie-ins outside or above the trench, holding and lowering
operations shall be undertaken in such a manner as to minimise stresses and bending in
the pipe and avoid movement of the pipe from the skids. Due consideration shall be
given to ambient temperature changes throughout the day and the resultant pipe length
changes and induced stresses.
2.8.4.3 All tie-in connections to metallic systems shall be by means of flanged connections. Tie-
ins to other GRE pipe systems may be made by flanged connections or by means of
bonded couplings.
2.8.5 Backfilling
2.8.5.1 The trench shall not be backfilled until the Company has approved the sand padding
around and above the pipe and has confirmed its approval for the backfilling operation to
commence. Backfilling shall be performed as soon as possible after padding has been
approved, but not prior to the successful completion of the hydrotest.
2.8.9.1 The need for concrete anchor or thrust blocks in the pipeline system will be determined
during detailed design, depending on the expected operational pressure surges,
temperature changes, nature of the ground and the geometry of the pipeline layout.
Approval shall be obtained from the relevant linepipe and fittings manufacturers, if
changes are required.
2.8.9.2 Anchor blocks should normally be located in line with fittings, tie-ins to steel pipe and to
exposed runs of pipe. The concrete should be poured in situ on to undisturbed or
compacted soil. Where parts of the pipe or fitting joints are to be encapsulated by the
block, hydrostatic pre-testing of the joint assembly should be completed first.
Alternatively blocks may be cast before pipe laying and the pipes fastened with brackets
inlaid with an elastomeric strip. All anchor blocks shall be installed and cured prior to
commencement of any hydrotesting activities on the pipeline.
2.8.9.3 For GRE lines, a layer of elastomeric material 6 – 10 mm thick shall be wrapped around
sections of pipes or fittings before concrete is applied. Concrete shall not be poured
directly on to unprotected GRE surfaces.
2.8.9.4 No more than half the circumference of the pipe or fitting shall be cast into the concrete
thrust block. Thrust block casting around entire fittings or joints shall be avoided.
Where GRE pipelines are required to cross under roads and highways, the pipe shall be
protected by installation within a steel or HDPE casing pipe with a minimum cover of
1500 mm to the top of the casing pipe.
• Cased pipes shall be fitted with spacers (minimum 4 per pipe length at a
maximum spacing of 3000 mm) to ensure the pipe is centred and to prevent
damage during installation.
• The ends of the casing shall be sealed with flexible bellows of approved design
to be fitted over the casing ends and the pipe to prevent influx of backfill
material into the annulus. Filling the entire annular space with polyurethane
foam is also acceptable.
• Prior to backfilling, suitable devices may be attached to both carrier pipe and
casing pipe on each side of the crossing to enable monitoring of differential
movement between the casing and the carrier pipeline.
2.9.3 Wadi-Crossings
All wadi crossings in GRE pipelines shall be through steel or HDPE casings with
sufficient negative buoyancy to prevent the casing and pipe from floating in empty
condition. Continuous buoyancy compensation and impact protection may be
provided by means properly designed concrete coating of the casing pipe along the
full length of the Wadi crossing. Casings shall be externally protected against
corrosion using an appropriate coating system.
Requirement for installation of the GRE pipe into the casing is covered in 2.9.2,
above. Concrete coating of the casing pipe is required in accordance with Section
2.10 of the main text.
2.15.1.1 On completion of installation, the GRE pipeline system shall be flushed, hydro tested
and certified in accordance with DEP 31.40.10.19, ISO-14692-4 and this specification.
2.15.1.2 The testing of each test section shall commence as soon as possible and, so far as is
practicable within the programme, shall be undertaken progressively throughout the
construction of the line. The first 500 meter of jointed pipe shall be tested within two
weeks of completion in order to provide confidence that the workmanship and
installation procedures are fit for purpose. If the 500 meter section hydrotest is
satisfactory, then the lengths of each subsequent test section shall be decided by the
Contractor. If the test on the first 500 meter fails, then the next 500 meter section shall
also be tested separately. The pipeline shall be tested in 500 meter sections until such
time that the Contractor demonstrates his ability to install a 500 meter section without
hydrotest failures.
2.15.1.3 Only soft foam pigs shall be used for cleaning, filling and dewatering of GRE pipelines.
2.15.1.4 No gauging of GRE pipelines is required as online pigging is not envisaged for GRE
pipelines.
Any ambiguities or lack of clarity between these requirements specified and the
requirements of DEP 31.40.10.19 shall be identified to the Company for the purposes
of specification improvement. However, in the case of clearly contradictory
requirements (e.g. tightness test calculations), the additional requirements of this
specification shall prevail over other specifications.
The pipeline shall be subjected to one(1) hour strength test to a pressure equal to 1.5
times the design pressure. The pressure shall be maintained at the test pressure +
100 kPa by bleeding or adding water as required.
If a leak is suspected the pressure shall be reduced to the pipeline design pressure
before carrying out a visual examination. No personnel shall come closer than 5
meters from the pipeline before the pressure has been reduced to design pressure.
Subsequently, a “step test” shall be performed. In this test the test section shall be re-
pressurised to the leak tightness test pressure and after each hour the pressure shall
be recorded and the section re-pressurised by adding water. The quantity of water
required to bring the section back to the test pressure shall be recorded. This shall
continue for a period of 24hours. If the quantity of water added shows a decreasing
trend then it may be considered that the pipeline is tight. If the quantity of water added
remains constant then it must be assumed that the pipeline is not leak tight. No work
shall be carried out to repair leaks until the pressure has been reduced to a safe
pressure i.e. static head plus 100 kPa.
During the test, deadweight tester readings shall be recorded every 30 minutes and
pipe, soil and air temperature recorded every 1.5 hours.
The pipeline shall be subjected to a 24 hour tightness test, immediately following the
strength test, at the pressure indicated on the drawings. (This should be 110% of
design pressure). No water shall be added or removed during the test.
The test shall demonstrate, to Company’s satisfaction that there are no leaks in the
pipeline. This shall be achieved by visual inspection of each joint every 4 hours during
the hydrotest period. A tightness test check calculation shall be made to verify that no
large leaks have been missed. Allowance shall be made for instrument inaccuracies
and also the pressure changes as a result of average temperature changes, calculated
from the formula given in DEP 31.40.10.19 (assuming a fully restrained line section).
The average temperature of the pipe may be used for this calculation. The
temperature measurements taken on the exposed pipe may be included in determining
the average pipe temperature.
In the event of there being any doubt about the tightness of the line, as determined
from the visual inspections, the test shall be extended or repeated to Company’s
satisfaction at no additional cost to Company. The tightness test calculation shall be
provided to the Company for information.
During the test, the pressure shall be recorded continuously, deadweight tester
readings shall be recorded every 30 minutes and pipe, soil and air temperatures
recorded at maximum 3 hour intervals. The temperature recording interval shall be
reduced to 30 minute duration for the first and last 2 hours of the 24 hours to assist
with the pressure/temperature variation check calculation.
Number:
Comments:
Suggestions:
Phone:
Document Control Section Actions
Comment Number: Date: CFDH
Ref. Ind.:
Recd.: To CFDH:
CFDH Actions