Professional Documents
Culture Documents
Atlas Copco
Supporting your business
wherever you are
Rock & Soil
Reinforcement
third edition
www.rockreinforcement.com
www.atlascopco.com
a technical reference edition
Printed matter no. 9851 6283 01b
RR3 CONT.qxd 19/7/05 8:33 Page 1
Contents
Foreword 99 Front Stabilization Using MAI Rock Anchors:
pre-reinforcement as a means of ground control in
2 Foreword by Federico Scolari, Vice President Marketing, Germany, Italy and Taiwan.
Atlas Copco Craelius. 104 Boltec at Kemi Mine: integrated process control
demands reliable and consistent mechanized
Talking Technically 109
rockbolting.
Overcoming Squeezing Ground at Mitholz:
supporting deformed strata while fresh support is
3 Innovative Solutions for Rock & Soil Reinforcement installed.
5 Investing in Rock Reinforcement 113 Mechanized Bolting at Zinkgruvan: better rock
7 Controllable Rock Reinforcement reinforcement improves production and safety.
11 Swellex Manganese Offers Improved Work Index 115 Seismic Tunnelling at Bolu: crucial motorway tunnels
13 Swellex Premium Line recover from earthquake using Self Drilling Anchors.
15 Hollow-Core SDA System 119 SDA in the Baltic States: novel uses for grouted SDA
17 Atlas Copco MAI Self Drilling Anchors as micropiles to support ancient buildings.
19 Symmetrix For Large Holes 124 Increasing Land Use: SDA applied to subsoil
22 Sacrificial Drill Bits stabilization prior to housebuilding in UK.
24 Mechanized Bolting 127 Soil Nailing UK Transport Routes: securing major
28 Using Rocket Boomers to Install Rockbolts road and rail infrastructure using SDA.
33 Connectable Swellex 129 Portal Support Using Swellex: stabilization of
35 Rockbolt Corrosion in Mining and Tunnelling entrances to Porte tunnel in Italy.
38 Grouting for Support in Tunnels 131 Driving From Budapest to Nürnberg: difficult tunnels
41 Rock Mass Stability with Swellex using advanced rock reinforcement techniques.
43 Secoroc Uppercut – New Tapered Equipment 135 Systematic Grouting at Oslo Subway: Craelius
45 Getting the Drift with Magnum SR Unigrout provides the perfect solution for water ingress.
47 Rock Mechanics and Rock Reinforcement
51 Swellex in Shear Stress
55 Using ROC Drillrigs to Install SDA
59 3-D Imaging for Rock Support Design Product Specifications
61 Introducing Swellex Hybrid
139 Swellex Manganese Line
144 Plasticoated Swellex
Case Studies 145 Swellex Premium Line
148 Swellex Hybrid
63 Swellex in Mining: project reports from Canada, 149 Swellex Face Plates & Washers
Portugal, Turkey and Peru. 150 Swellex Pumps
69 Removing Bottlenecks in Austria: upgrading the 152 MAI SDA
European highway system in Central Europe. 164 Tophammer Crawlers
73 Extreme Temperatures: rock reinforcement in 166 Boltec Rigs
permafrost in Northern Quebec and volcanic strata in 172 Rocket Boomer Drillrigs
Hokkaido. 174 Hydraulic MAI Bolt Support
75 Coated Swellex at Kvarntorp: longlife installation of 175 Hydraulic Rock Drills
rockbolts in a corrosive environment. 178 Hydraulic Feeds
77 Nuclear Quality Assurance: long-term tunnel support 180 Symmetrix Overburden Casing System
for the Exploratory Studies Facility at Yucca Mountain, US. 188 Unigrout Grout Plant
81 Versatility in Tunnelling: project reports from China, 189 Pusherleg Drills
Germany, Madeira, Spain, and Switzerland. 190 Secoroc Threaded Equipment
87 Rapid Support Close to the Face: reporting use of 204 Secoroc Tapered Equipment
Swellex at three important Italian TBM tunnelling sites.
91 Large Hydroelectric Projects: widely differing demands Front cover: Different applications involving rock reinforcement.
at sites in Austria, Bhutan, India, Philippines and Portugal. Atlas Copco reserves the right to alter its specifications at any
97 Top Combinations in Japan: reliable support in time. For latest updates contact our local Customer Centers or
sedimentary and volcanic rock formations in railway and refer to www.rockreinforcement.com
road tunnels.
Produced by tunnelbuilder ltd for Atlas Copco Rock Drills AB, SE-701 91 Orebro, Sweden, tel +46 19 670-7000, fax -7393.
Publisher Ulf Linder ulf.linder@atlascopco.com Editor Mike Smith mike@tunnelbuilder.com Picture Editor Jan Hallgren
jan.hallgren@atlascopco.com Contributors Anders Arvidsson, Claes Hillblom, Federico Scolari, Francois Charette, Gunnar
Nord, Hans Fernberg, Juha Hyvaoja, Jukka Ahonen, Lorne Herron, Mario Bureau, Mark Bernthaler, Olle Karlsson, Per-Olof
Einarsson, Sara Sjödin, Sten-Ake Peterson, all name.surname@atlascopco.com. Adriana Potts, adriana.potts@ntlworld.com.
Maurice Jones, maurice@tunnelbuilder. com. Wulf Schubert, Markus Potsch, Andreas Gaich, all surname@tugraz.at.
Foreword
O
ngoing development of faster, safer and more exotic tunnelling techniques places a con-
stant pressure on manufacturers to provide more efficient rock support solutions which
will help the shortening cycle time.
The use of versatile drilling jumbos for mechanized installation of a variety of rock support
systems is part of the leading practice used in modern tunnelling. As ground conditions get more
and more demanding, emphasis is placed on flexible and intelligent support systems in which rock
and soil reinforcement is expected to contribute to the productivity and safety of the operation.
The trend has been to provide rock support/reinforcement systems that are easy to install, assure
efficiency and provide safety, both during and after excavation.
For the last 25 years, Atlas Copco has been offering the Swellex concept as a unique, safe and
reliable system of rock support. As the market leader in underground rock excavation technology,
Atlas Copco has also been developing safer and more efficient rock reinforcement products such
as the Manganese Line rock bolts, which are manufactured from a special type of steel. Another
development is the Swellex Premium Line of rock bolts, for use where high yield load and stiff-
ness are expected from the reinforcement system. The recent acquisitions of MAI and Rotex have
introduced a whole new range of products, which are now being developed for mechanized instal-
lation by both surface and underground drillrigs, creating fresh applications in rock and soil rein-
forcement.
Atlas Copco’s Rock Reinforcement Competence Centre at Feistritz/Drau, Austria brings togeth-
er the skills necessary for the development of superior rock reinforcement products to serve the
tunnelling, mining and construction industries worldwide. In 2005, the centre became a part of
Atlas Copco Craelius, which is active in ground engineering with Symmetrix and ODEX overbur-
den casing drilling systems, and Unigrout and Logac grouting equipment, and produces multipur-
pose drilling rigs such as the Mustang. The combined product portfolio includes Swellex and MAI,
bringing together all elements of the Atlas Copco rock and soil reinforcement strategy.
As a result, market-driven product development at this new facility is already setting the scene
for another quarter-century of development in rock reinforcement and ground engineering.
Federico Scolari
Vice President Marketing
Atlas Copco Craelius
federico.scolari@se.atlascopco.com
TALKING TECHNICALLY
Leading the Way • Swellex Manganese for increased launched the Boltec 500, a new rig for
tensile strength and higher elongation fully mechanized rock bolting, primar-
When Atlas Copco applied for patents capacity ily to increase productivity and to
for the Swellex rock bolt in 1979, it • Swellex Premium Line for improve safety when installing the
was a significant milestone in rock improved yield characteristics and ten- bolts. Safety is an especially important
reinforcement technology. This inflat- sile strength with slightly less elonga- consideration on sites with poor rock
able bolt was extremely easy and tion. conditions.
quick to install in a 38 mm hole, and However, the extreme conditions of
provided immediate support. Specialized Rigs rock bolting, in which water and rock
The advantages proved to be so
effective that over the next decade At the same time as applying for Atlas Copco Boltec LC is a highly productive
several million Swellex bolts were patents for Swellex, Atlas Copco machine developed specifically for rock bolting.
used in demanding ground conditions
worldwide.
In the years that followed, this suc-
cess led to the development of several
new versions including:
• Coated Swellex with rust protec-
tion to withstand corrosive environ-
ments
• Super Swellex for larger hole
diameters and a 20-tonne load-bearing
capacity
• Connectable Swellex for tunnels
where the length of the bolt required is
more than the height of the tunnel
• Swellex Hanger for suspending
such facilities as conveyor belts and
working platforms
TALKING TECHNICALLY
Competence Centre
The recent opening of the dedicated
competence centre at Feistritz/Drau,
Austria heralds a new era for the
development of superior rock rein-
forcement products to serve tun-
nelling, mining and construction
industries worldwide.
A considerable amount of market-
driven product development will now
be possible, and customers around the
Innovative two boom cable bolting rig drills with one boom while feeding and grouting cable with the other. world can expect to see many new and
interesting products in this area
cuttings pour down along the drill this technology, continually setting new coming from Atlas Copco in the years
string and onto the rock drill, feed and standards and breaking new ground. ahead.
moving components, had a negative In 2002, the company added self - The scene is now set for another
effect on the service life of these rigs. drilling anchors (SDAs) to its ever quarter-century of development in
Their performance was affected even widening product range, through the rock reinforcement and ground engi-
more when cement-grouted bolts were acquisition of SDA specialist MAI neering.
used, due to cement spilling out of the Ankertechnik of Austria. On the following pages, Atlas Copco
hole onto the bolting unit. These fully-threaded anchors, fitted presents some technical papers, case
In response to these challenges, with sacrificial drill bits, are designed studies and product specifications to
Atlas Copco continued to develop fur- for exceptionally poor ground condi- demonstrate this technology in action.
ther generations of more rugged and tions where holes collapse and con-
reliable bolting rigs that had fewer ventional bolts cannot be used. In by Federico Scolari
moving parts. addition, they are used in combination
The current fourth generation rigs are with crawler drillrigs for surface appli- Twenty five years of innovative solutions to rock
capable of impressive performances. For cations, such as soil nailing in slope reinforcement problems.
example, the Boltec LC working in a
Finnish mine recently installed more
than 120 Swellex Manganese bolts in a
single 8-hour shift.
Boomer face drilling rigs also began
to be used for tunnelling in poor
ground, drilling holes for rock bolts as
well as for the installation of pipe roof-
ing systems and self-drilling anchors.
TALKING TECHNICALLY
Investing in Rock
Reinforcement
Safety and Economy
Time was, in tunnelling and
mining, that rock reinforcement
was considered a burden, a cost,
and a necessary pain. The aim
seemed to be to get around the
support work in the easiest and
cheapest way possible, and con-
centrate all efforts on excavating
the greatest amount of rock, in
the shortest time.
As the awareness of the con-
sequences of poor rock reinforce-
ment becomes more widespread
amongst clients, engineers,
miners and contractors around
the world, a sounder attitude to
this work is emerging. There is
now a wish to achieve the
required demands on quality, to
carry out the support and rock
reinforcement in the right order,
to properly monitor what has
been carried out, and to evaluate
the results of the rock reinforce-
ment effort. The latest Atlas Copco Boltec offers a new dimension in rockbolting safety.
As contractors and miners have
a reputation for looking after their
money, new ideas are born on The Atlas Copco focus is on total In a linear situation, for instance, if
how to carry out the support and economy, by fast installation of rock it takes 100 days for one man to dig a
reinforcement work in cost effi- support, adequately proven perfor- defined dyke, 100 men can do it in one
cient ways, and they are often pre-
sented as alternatives in their mance of reinforcement, and a tech- day. In tunnelling, life is not that easy.
quotations on underground con- nology that has the capacity to meet There may be only one face to work
struction projects. In mining, there modern quality demands. at, and there is usually little space for
is continuous ongoing evaluation In this presentation of the Atlas increased efforts at that face. The only
aimed at optimization of the exca- Copco approach, we discuss the cost remaining option for the tunnellers is
vation reinforcement method.
implications of the time taken for the to improve mechanization.
round in tunnel excavation, the quality The leading process has been
Practical Solutions of the Atlas Copco rock reinforcement drilling at the face. Since the introduc-
programme, and working environment tion of the original Swedish Method,
At Atlas Copco, as a supplier of rock and safety aspects. the drilling performance has improved
drilling equipment as well as rock dramatically. The introduction of
reinforcement tools and material, there Improving Performance heavy pneumatic drifters mounted on
is an ongoing drive to create new or articulated booms, followed by three
improved solutions to rock reinforce- Going back 20 years or so, and look- generations of hydraulic drill rigs, has
ment problems. This topic is generally ing into the time needed to excavate a further multiplied productivity.
broached at an early stage of a project round and how this has developed, If we consider a tunnel with 80 sq m
by the contractors, and is brought up will indicate the direction in which cross-section being driven in fractured
constantly by the mining industry. As tunnelling technology is going. limestone with clays strata, through
a result, Atlas Copco is right at the The round cycle is just as real today a couple of major faults, and with
core of practical solutions for rock as it was then. By doubling the 350 m overburden and significant
reinforcement, and this has con- effort, the time taken will reduce by water inflow, the drilling phase has
tributed to our approach. 50%. decreased from 40% of the total
TALKING TECHNICALLY
Investing in Rock
Reinforcement
The Atlas Copco commitment is
towards a safer and more ergonomic
working environment. This commitment
is translated into ergonomic machines
and reliable rockbolts. There are no
shortcuts in this process. Swellex offers
Figure 1. Development of face excavation over the last 25 years, showing the changes in time taken for immediate support, with full column
various components of the round. contact, and pumps check the inflation
pressure of the bolts. Self Drilling
drilling time 20 years ago, to just 20% with all resources mobilized and the staff Anchors (SDA) are replacing manual
today. taking home their salaries, the cost will installation of rockbolts in collapsing
Figure 1 illustrates the development be at least half of the forecast cost. holes, where the manual job is more dif-
of drilling and ancillary face opera- Conversely, if the work is carried out in ficult. Boltec offers a new dimension in
tions over 25 years. Not all the differ- half of the set time, the reduction in cost rockbolting safety, while Cabletec does
ent phases in the cycle have the same will be at least 25%. the same for cable bolting.
development. Shotcreting shows a Assume a tunnel of 1.2 km in Assuming that you have done
positive trend on time reduction, while length, with a cross-section of 70 sq m, everything to optimize your face
mucking has a less noticeable devel- will be excavated over a time period of drilling, and that your detonators and
opment. These figures would improve one year. This is an average advance of explosives are the best available. You
for a smaller cross section. Scaling 100 m/month, at an estimated cost of have a modern ventilation system, the
shows a large increase in time, since €5,000/m or €6 million in total. The most powerful mucking equipment,
heavy hydraulic breakers now play an time related cost will then be at least and the most efficient shotcrete robot.
important role in improving the pull of €3 million, or €2,500/m. If a reduction And you still stay with the most
the blasted round by cleaning off the in construction time of one month can conventional rockbolting system?
face, as well as trimming the profile of be achieved, it results in a reduction Then it’s time to invest in rock
roof and sides to make safe. of the cost by €250,000. Further, reinforcement.
If we consider traditional, fully assuming that the working time is
grouted rockbolts, installed with a 500 hours/month, then the cost saving by Gunnar Nord
jumbo or with an automatic bolting rig,
the increase in productivity does not Rocket Boomer L1 C-DH drilling rockbolt holes at Auersmacher in Germany.
keep pace with the drilling. In our ref-
erence tunnel we can register a poor
saving of 10% in total time consump-
tion. Rock reinforcement, and in par-
ticular, rockbolting, is a bottleneck in
the excavation cycle, and this has to be
tackled in order to boost productivity.
Time is Money
In tunnelling the time related cost is most
likely in the range of 50- 60% of the total
cost. This means that, if no work is car-
ried out during the set construction time,
TALKING TECHNICALLY
Controllable Rock
Reinforcement
Helping Rock to
Support Itself
Modern computer-based geot-
echnical monitoring techniques
indicate that the greatest relax-
ation or movement of the rock
mass occurs immediately follow-
ing excavation. They confirm
that, after a certain period, the
rock will establish a new equilib-
rium based on its own inherent
self-supporting capacity. The best
quality rock will remain self-sup-
porting for extensive periods of
time without the need for extra
support. As the rock quality
declines, support requirements
increase proportionally. The poorer
the quality of the rock, the greater
the degree of support required, Sequence of installation of a Swellex bolt.
and it becomes increasingly crucial
to install reinforcement as quickly
and as close to the face as possible functional. The basic underlying fac- immediate and full support action
after excavation. tors are: the inherent sensitivity of from the Swellex bolts. The moment
Engineers involved in the resin to heat, age and improper stor- the Swellex bolt is expanded in the
design of rock reinforcement sys- age; parameters during installation; hole, it interacts with the rock to main-
tems must satisfy ever increasing
hole annulus; cartridge damage during tain its integrity. The quality of the
demands to optimize the design
to gain maximum safety and insertion; injection nozzle alignment; bolt installation is automatically con-
economy. The primary objective presence of cracks and flowing water; firmed when the pump stops, and is
in the design of the support and levels of operator skill and care. independent of rock mass conditions
system is to assist the rock mass This is a highly unsatisfactory result or operator experience.
to support itself. Accordingly, in terms of worksite safety, and is Controllability means safety.
quality and time are the two
main parameters which must be
equally unfavourable in terms of econ- Control brings peace of mind at every
taken into account when deter- omy. Split-set type bolts may be quick step:
mining the type of rockbolt to be to install, but their anchorage capacity 1) Swellex bolts are manufactured
used for rock reinforcement, in is too low to keep stress concentration following a very strict quality
both mining and construction at distance from the rock face. control procedure using specific
applications. By contrast, the Swellex concept steels for which origin and com-
entails that the rock is secured by position are known and controlled.
Controllability Means Safety High pressure water expands the Swellex bolt into contact with the strata.
TALKING TECHNICALLY
Immediate Support
Modern drilling and excavation equip-
ment used in civil engineering and
mining applications has led to major
increases in efficiency and productivi-
ty. In fact, development has been so
rapid that conventional rockbolting
methods frequently act as production
bottlenecks.
Developments in the speed and
ease with which rock reinforcement
Plasticoated Swellex with cap and without cap.
can be applied to improve equipment
All the manufacturing parameters Swellex rockbolts reinforce and utilization, limit machine downtime,
are filed and linked to a number improve the condition of the interfac- and increase productivity, while simul-
on the Swellex bolt bushing for ing rock, increasing its load-bearing taneously complying with safety
traceability. capacity. requirements, is of interest to all those
2) Installation of Swellex bolts is Depending on the rock mass involved in tunnelling and mining.
controlled by sturdy Atlas Copco strength, the pressure exerted during The Swellex concept has kept pace
pumps to assure a perfect installa- installation may compact the rock sur- with these advances, with a single
tion. The new patented HC1 rounding the borehole, increasing the operator installing 50 to 100
pump, once started, will only stop friction along the bolt, and/or deform bolts/shift.
when the set pressure is reached, its profile to match the irregularities of Timing of the rock reinforcement
independently of the operator. the rock, providing a combination of measures is of particular importance in
3) Pull-tests can be performed at any strong mechanical interlocking and NATM, the New Austrian Tunnelling
time on Swellex bolts. Whether high friction. The resulting high Method. In brief, NATM can be
they were installed a year ago in a anchorage capacity makes Swellex expressed as a sequence of activities
corrosive environment, or 10 bolts an integral part of the supporting for tunnel development: drilling and
years ago in a dry area, it is possi-
ble to control their load bearing Mn24H hanger rockbolts for suspending utilities while reinforcing the rock.
and yielding capacity. Expertise
has also been developed for exam-
ining the bolts with a fibre optic
camera to control internal corro-
sion or shearing.
The Swellex concept is designed to
optimize the effectiveness of each
bolt, so the bolting operation matches
the required safety levels as planned
by the engineers. Alternatively, com-
pared to other rock support, the same
bolting effort using the Swellex
system can result in increased safety,
since each installed Swellex bolt pro-
vides full support.
Swellex rockbolts have been used
successfully to complete many tunnels
in difficult rock conditions while, at
the same time, greatly reducing sup-
port costs.
TALKING TECHNICALLY
blasting; mucking and scaling; and in Canada has proved that Swellex
immediate initial rock mass support by boosted metres of advance by 10%
systematic rockbolting and shotcret- and reduced bolting costs by 10%. As
ing. more bolts were installed per working
The initial support system restricts shift, fixed costs for manpower and
ground movements after excavation, rigs were diluted, resulting in
thereby maintaining the inherent increased metres of advance/shift with
strength of the rock mass. This is the improved safety. For similar reasons,
essential idea behind NATM. The per- Swellex has became a standard in
manent lining is installed when the most European countries and in Japan.
rock has reached a state of equilibri- To summarize, when the Swellex
um, and deformation has ceased. bolt is installed in heavily fissured
Swellex rockbolts provide immedi- rock, the radial stresses enhance the
ate support, as well as the ability to contact forces between blocks of rock
accommodate large ground move- surrounding the bolt, leading to an
ments at maximum load-bearing increase in rock mass strength. In
capacity. Shear tests performed by soils, Swellex bolts provide consolida-
several international institutes have tion immediately around the bolt,
shown that, depending on rock com- leading to an increase in the strength
pressive strength, Swellex bolts can of the material, and improved anchor-
accommodate up to 90-100% of their Hybrid bolt for long anchorage in rock. ing capacity of the rockbolt. In hard
tensile strength under shear loading, rock, 0.5 m of anchored Swellex rock-
an exceptionally high figure. Joint ground water around the rockbolt and bolt gives a pullout resistance equal to
shear displacement at bolt failure can inflation water within the rockbolt. the breaking load of the bolt. A strong
be up to 35 mm/56 mm at a 90 degree It has been established that, for anchorage capacity will help to dis-
angle between the bolt and the surface medium term corrosion protection, the tribute the stress around the excava-
of the joint, showing that Swellex bitumen coating is best. However, tion and avoid stress concentration
bolts accommodate the same amount plasticoated Swellex offers longterm close to the surface that can lead to
of shear displacement as the diameter corrosion protection, independently of rock falls or strain burst.
of the drill hole, and even more in the rock mass parameter. There are Swellex rockbolts for
softer rock. If shotcrete or sealant are used, the almost any environment and purpose.
threat from atmospheric corrosion Swellex Mn12 and Pm12 are perfect
The Right Protection diminishes. In the case of Swellex, it for regular daily support in mining and
will seal and protect the inside of the tunnelling. When high loading capaci-
When it comes to choosing the right bolt, leaving a reduced corrosion ty is needed, Swellex Mn24 or Pm24
product for longevity, or for use in a potential to the external side only. If is the answer. Swellex Mn16 and
corrosive environment, it is advisable there is no shotcrete or sealant applied Pm16 are a cost-effective solution
to proceed with caution. There are after bolt installation, caps can be used when 43-52 mm drilling is preferred.
many products that offer what appears to seal the bolt internally. In highly corrosive conditions, or
to be lifetime protection. A real level of safety is achieved where there are demands for long life,
Unfortunately, in reality, the rock mass with Swellex, as the corrosion is Coated or Plasticoated Swellex may
properties such as water, joints, rock assessed, and the bolt can be con- be the choice. In situations where very
movement, may be unknown, and the trolled using pull test or internal visual long bolts are required, or in confined
quality of rockbolt installation may be inspection over time. space, Mn24E Extendable Swellex
unquantifiable. offers fast installation of up to 12 m-
Conventional types of rockbolts Total System Approach long bolts.
made from carbon steel are susceptible Recent years have seen the devel-
to corrosion. As only 50-70% of resin The cost and time involved in rock opment of the Mn24H, a type of
coated and grouted bolts are properly reinforcement compels project engi- Swellex that is part of the rock support
installed, they do not represent a reli- neers to evaluate a total system and is also used to hang heavy loads
able solution against corrosion. Also, approach. The cost of the rockbolt without inducing unfavourable stress
there is extra delay and cost associated itself, or such properties as tensile in the bolt’s head bushing.
with these bolts, compared to the strength, are seldom of primary inter- Atlas Copco is also proud of its
Swellex solution. est. The decisive factors are the result- latest patented hybrid system of rock
To help choose the right alternative, ing safety, the total cost, and the time reinforcement, see article in this issue.
Atlas Copco is using reputable corro- required to fulfil the mission.
sion institutes around the world to A productivity study comparing
assess the corrosion potential of Swellex to other bolts in a gold mine by Mario Bureau
TALKING TECHNICALLY
TALKING TECHNICALLY
and a series of alloys and high tensile a higher loading capacity and, at the
Summary of steels were considered. Only a limited same time, enhanced elongation. Figure
number of options can handle the 1 shows that, beyond yielding point,
Swellex® user severe requirement of Swellex rock- the manganese steel increases the load
benefits bolts with respect to radial deforma- capacity due to the hardening process.
tion during expansion, and weldability The curve continues to point up-
● Swellex provides cost- to assure perfect watertight contacts at wards until a 10% elongation is
effective rock the bushings. It was decided to use a achieved, then a long horizontal seg-
reinforcement in most better quality steel, with a higher man- ment goes above the 30% level before
rock types and conditions. ganese content. the profile breaks up. This extraordi-
Produced in a cold forming mill, nary behaviour gives the capacity to
● Swellex installation the steel reaches a very high tensile absorb a substantially higher quantity
procedure ensures that strength and high loading capacity, of energy, as indicated in the 80%
every bolt installed will but unsatisfactory elongation. A post- increase in the Work Index shown in
provide optimum production heat treatment is then used to Figure 2.
reinforcement. produce the extraordinary elongation
properties needed for the Swellex profile. Total Reliability
● Swellex rock bolts are
quickly installed, and very Improved Behaviour The heat treatment used during the
little training is required to production of the new Swellex
use the equipment. Figure 1 compares typical load/ Manganese Line further improves
deformation curves for Super Swellex repeatability of the performance
● Swellex rock bolts provide and the new Swellex Mn24. In obtainable by the bolts. A large
full column interlock with particular, the regular Swellex steel number of pull tests, representative for
the surrounding rock, profile shows a classical behaviour for millions of rockbolts, show very little
without the need for carbon steel. Beyond the yielding variation in the results.
mechanical locking point (200 kN), the profile accepts a As a result, engineers, miners, rock-
devices or grouting large amount of deformation, but with mechanics and consultants can rely on
slightly lower strength. When a 20% safe and quality controlled rockbolts,
agents.
elongation is reached, the profile through the entire process from manu-
● Swellex requires no breaks down. facturing to installation.
environmentally harmful The new, high-strength and fully
chemical grouts to anchor annealed Manganese Line now offers by Federico Scolari
the bolt in the rock. Work Index for
● The quick and easy various types of
bolts.
installation, and the
assurance that every bolt
provides immediate full
load-bearing capacity,
makes Swellex the most
cost-effective rock
reinforcement.
TALKING TECHNICALLY
300
Pm24
250 Mn24
200
150
LOAD(kN)
100
50
0
0 5 10 15 20 25 30 35
STRAIN (%)
TALKING TECHNICALLY
Premium Line
The Pm Line is also made of high
strength steel but having different
properties than the steel used for Checking nut and plate on Swellex Premium bolt.
the Mn Line. No heat treatment is
given to the Pm bolts, resulting in a Typical applications for the Pm Atlas Copco is continuously invest-
very stiff behaviour at high load, Line are where deformation/stress of ing in research and development to
because the yielding strength is the rock mass is stable in time and offer the market the best rock rein-
very close to the maximum tensile high stiffness is required. These situa- forcement products with safety and
strength. tions occur in tunneling, beam consol- productivity in mind. The right steel
Pm Line bolts are used where maxi- idation of strata in mining, mining for the application adds safety and
mum control of the rock mass conver- where the rock mass stress and move- productivity!
gence is targeted, and a high yielding ment are low or stable in time, and the
load capacity (Rp02) and stiffness are yielding load will never be reached,
required, as in civil tunnelling projects. and mining and tunnelling in soft rock. by Mario Bureau
Choice of Reinforcement Type
Soft Rock and high Stresses Yielding and high Swellex Mn Line +
Weathered hard rock or laminated/ anchorage Connectable and Hybrid
schistose rock and high stresses
TALKING TECHNICALLY
TALKING TECHNICALLY
TALKING TECHNICALLY
TALKING TECHNICALLY
TALKING TECHNICALLY
More Applications
The ODEX method of overburden
drilling with an eccentric bit is well
established amongst drillers, particu- overburden drilling, the specially- Symmetrix RC system used in Turku, Finland.
larly when it comes to shallow, small designed Mustang rigs for anchor
dimension holes. Now, with the intro- drilling and micropiling, and the the concreting process the support is
duction of the Symmetrix system, DTH products provided by Atlas transferred from the temporary drill
Atlas Copco has opened the door to an Copco Drilling Solutions in the casing, which is gradually withdrawn,
infinite number of applications where US, provide sufficient combina- to the concrete that forms the pile
casing drilling is the preferred solution tions to meet most overburden shaft. Likewise, the casing may be left
for forepoling, micropiling and other challenges. in place as additional structural sup-
types of ground engineering work. port, or for protection of the pile. For
Symmetrix enables drillers to go Case for Casings exploration and well drilling, the
larger and deeper than ever before. casing can become the conduit for
Whereas the ODEX method is ideal There is no doubt that the use of bringing the debris to the surface.
for drilling holes up to 273 mm in drilled casings in underground con- For these reasons, designers and
diameter, Symmetrix handles the struction is becoming increasingly owners turn to drilled casings, and DTH
installation of casings up to 1.2 m in popular worldwide, primarily due to drilling with Symmetrix is often the only
diameter, in holes of 100 m-deep (300 ft) the expansion of building and infra- method that can drill through all ground
and beyond. structure growth in areas that are less conditions, boulders and solid rock.
This unique capability gives con- than ideal for such development.
tractors the power to tackle any type Pile driving in dense urban condi- Symmetrix in Sensitive
of casing advancing work, from tions can disturb surrounding structures Conditions
micropiling, tunnel forepoling, and or utilities, and is often difficult to
foundation piling, to opening ‘rat- estimate in terms of costs. This is The Marina Palace Hotel, a large hotel
holes’ for oil and gas wells, as well as compounded by other problems, such and congress center located in the old
horizontal casing drilling. as ground settlement, soil compaction city of Turku on the south western
In addition, the Symmetrix and lateral soil displacement. coast of Finland, is going through a
system is a perfect complement to When using a drill casing, soil, rock main renovation scheme.
Atlas Copco’s extensive range of and other debris are removed within a Part of the project is to enlarge the
DTH (Down-The-Hole) equipment. protective steel tube and brought to parking capacity by building an under-
The Secoroc DTH hammers for the surface. For foundations, during ground parking lot. Ground conditions
TALKING TECHNICALLY
ROTARY MOTOR
DUAL WALL
DRILL PIPE
INTERCHANGE
1 2 3
CASING SHOE
SYMMETRIX BIT deep on the southern riverside. For the
garage foundation, steel casings are
in Turku are problematic, with The old town is built mainly on being drilled 1 m or 2 m into the solid
mainly post glacier clays at surface wooden driven piles. These are being bed rock, which means that longest
overlaying sand layers containing replaced by steel casings drilled all the casings are 67-68 m-long. Drilling
high water pressure. This is followed way to bedrock, for which several work is being carried out by Skanska
by till containing very hard boulders underpinning projects are underway on and their subcontractor, Sotkamon
typically sitting on steeply inclined the northern banks of the Aura river. Porakaivo. Casing sizes are from 140
non-weathered hard granite or dia- In the Marina Palace Hotel parking mm to 508 mm, all of which are thick
base. garage project, clay and till layers walled to form load bearing members.
reach 35 m-deep in the northern Most of these casings are in sensi-
Completing a deep pile at Marina Palace Hotel,
corner of the site, and the till is 65 m- tive conditions very close to existing
Turku.
buildings and their foundations, so a
unique drilling system is required.
Atlas Copco Rotex has developed
reverse flushing drill bits in order to
control the air flushing in sensitive
conditions. Symmetrix RC is designed
to give the straightness the consulting
engineers require, control of flushing
media needed under existing founda-
tions, and high productivity in virtual-
ly any ground condition.
The Symmetrix RC system specified
by the supervising design engineering
company for the Marina Palace Hotel
job is being used on all four drillrigs.
Hard, rubber-like clays are normally
expected to be problematic, but sub-
contractor Sotkamon Porakaivo reports
TALKING TECHNICALLY
Future Development
The technology of casing drilling is
constantly developing, and the
demand is increasing fast in many dif-
ferent applications.
Drilling close to existing structures.
One of the biggest growth areas is
in drilling in urban environments,
that Symmetrix RC has made drilling Symmetrix Secret where it is no longer possible to open
very easy and productive, with casings up the streets for further drilling work
going in very straight and fast all the So what makes the Symmetrix casing without disturbing vital installations.
way through clays, sands, boulders, advancing method so unique? Basically, Here, Symmetrix will have a major
till, and even into very hard bedrock. the secret lies in the patented design of role to play.
Large city subways are typical
What it means for the contractor cases where tunnel roofs have to be
Symmetrix systems come in a large number of versions and sizes to suit a wide pipe-drilled in order to connect one
range of applications. These include: piling; forepiling and micropiling using underpass to another. With Symmetrix
both temporary and permanent casing; underpinning with grouted columns; well on board, Atlas Copco is able to pro-
drilling; and horizontal casing drilling. For the overburden drilling contractor vide customers with state-of-the-art
this means: straight holes without risk of deviation; quick setup and high pro- casing drilling technology that can
duction rates; less torque required in all formations; easy to lock and relock; meet these challenges, and many more
convenient drilling at any angle; no jamming and lost bits; can be used in all besides.
ground conditions and at any angle down to 100 m (300 ft) and beyond; and
by Jukka Ahonen
significant economic savings.
Product Manager, Atlas Copco Rotex
TALKING TECHNICALLY
Sacrificial Drillbits
TALKING TECHNICALLY
TALKING TECHNICALLY
TALKING TECHNICALLY
TALKING TECHNICALLY
Significant Improvements
When Atlas Copco introduced its new
series of mechanized rock bolting units
in late 2001, a wide range of radical
improvements was incorporated.
Based on the unique single feed
system with cradle indexing, the new
mechanized bolting unit, MBU, is con-
siderably more robust, and less sensi-
tive to falling rock, than its
predecessor. Holes are easy to relocate,
and the stinger cylinder improves col-
laring and the ability to install bolts
under uneven, rugged roof conditions.
Major re-engineering has resulted in
30% fewer parts. Less maintenance
and stock inventory are required, and
high availability has been recorded.
Furthermore, the chain feeds used in
the new Boltec series feature an auto-
matic tensioning device, which guaran-
Boltec MC equipped with screen handling arm.
tees even and strong feed force for the
rock drill, while a stinger cylinder
improves collaring and the ability to Boltec series based on RCS, the opera- Screen Installation
work under uneven roof conditions. tor copes easily with the more
The completely redesigned drill demanding cement grouting and resin In Canadian mines the combination of
steel support provides sufficient space cartridge shooting applications, by rockbolts and screen, or wire mesh, is
for bolt plates passing through, and controlling all functions from the commonly used for rock support. Since
facilitates extension drilling. cabin seat. Up to 80 cartridges can be rock reinforcement is potentially one of
The most outstanding benefit, how- injected before the magazine needs the most dangerous operations in the
ever, is the computer-based rig control refilling. Also, because meshing is work cycle, mechanized rockbolting
system, RCS. This system, which has often carried out in combination with has become more popular. A computer-
already been successfully incorporated bolting, an optional screen arm can be ized Boltec MC, equipped with screen
on the latest Boomer and Simba series fitted parallel to the bolt installation handling arm, has been in use for a
of drillrigs, offers simplified fault detec- arm, to pick up and install the bulky couple of years at Creighton Mine,
tion, operator interactivity, and the basis mesh screens. Up to 10 different pre- installing screen with split-set bolts.
for logging, storing and transferring of programmed cement-water ratios, and In general, the screen is 3.3 m-long
bolt installation production and quality various additives, can be remotely x 1.5 m-wide, and is installed in both
data. controlled. roof and walls, down to floor level.
The Boltec is equipped with the The new generation rigs offer the Typical spacing of bolts is 2.5 ft. Three
new rock drill, the COP 1532, which is operator a modern working environ- different types of bolts are used,
short and compact, and features a ment in a safe position. Low posi- depending on rock conditions, and all
modern double dampening system tioned, powerful lights provide bolting must be done through the
which, combined with the RCS, trans- outstanding visibility of the entire screen, with the exception of pre-bolt-
mits maximum power through the drill drilling and bolting cycle. ing at the face. In general, galvanized
string. The long and slender shaped The new Boltec family has two split-set are used for wall bolting,
piston, which is matched to the drill members: the Boltec MC, for bolt while resin grouted rebar or mechani-
steel, permits high impact energy and lengths of 1.5-3.5 m and roof heights cal bolts are used in the roof, and
long service life of all drilling consum- up to 8 m; and the larger Boltec LC for Swellex in sandfill.
ables. bolt lengths of 1.5-6.0 m, primarily for Once the screen handling arm has
large tunnelling projects having roof picked up a screen section and fixed it
Versatility and Ergonomics heights of up to 11 m. in the correct position, the powerful
The initial positive response from COP 1432 hydraulic rock drill quickly
Modern bolting rigs can handle instal- operators and mechanics confirms that completes the 35 mm diameter, 6 ft and
lation of most types of rockbolts, such the new generation of Boltec will pave 8 ft holes. The bolting unit remains
as Swellex, as well as resin and the way for further acceptance of firmly fixed in position after the hole is
cement grouted rebars. Using the new mechanized bolting. drilled, and the cradles are indexed,
TALKING TECHNICALLY
Boltec MC Flexibility
The Boltec MC delivered to the
Creighton mine is capable of handling
several types of bolts: split-set, mechan-
ical-anchors, resin grouted rebar and
Swellex. The switch of accessories
between different bolt types takes 5-10
minutes. To minimize water demand
during drilling, water-mist flushing is
used. The Boltec MC can also be Stoping sequence at Kemi underground mine. Cabletec drilling upwards, and Simba drilling downwards.
equipped with a portable operator’s
panel connected by a 50 m-long cable. drill unit can rotate 360 degrees and tilt 32 m. The cable cassette has a capacity
Cartridge shooting is remote con- 10 and 90 degrees, backwards and for- of 1,700 kg and is readily refilled
trolled for the Boltec MC, and up to 80 wards respectively. The new rig is thanks to the fold-out cassette arm. The
cartridges can be injected before refill- designed on proven components and cement mixing system is automated,
ing is needed. A unique feature is the technology featuring two booms - one comprising a cement silo containing
possibility to use two different types of for drilling and the other for grouting 1,200 kg of dry cement. The cement is
cartridges, with fast or slower curing and cable insertion. It also features an mixed according to a pre-programmed
times, housed separately in the dual on-board automatic cement system with formula, resulting in a unique quality
cartridge magazine. The operator can WCR (Water Cement Ratio) control. All assurance of the grouting process. The
select how many cartridges of each these features facilitate a true single cement silo capacity is adaptable for up
type to inject into any hole. For operator control of the entire drilling and to 20 m-long, 51 mm-diameter holes.
instance, he can inject two fast curing bolting process. The two boom concept To date, most holes have been
cartridges for the bottom of the hole, has drastically reduced the entire drilling drilled in the 6-11 m range, for which
and follow up with slower-curing car- and bolting cycle time and, by separat- the rig has grouted and installed cable
tridges for the rest of the hole, all with- ing the drilling and bolting functions, the at a rate of more than 40 m/h.
out leaving his operator’s panel! risk of cement entering the rock drill is Depending on type of geology and hole
eliminated. The operator is able to pay diameter chosen, the drilling capacity
Cabletec L for Cable full attention to grouting and cable inser- can vary between 30 and 60 m/h.
Bolting tion, while drilling of the next hole after
collaring is performed automatically, Conclusion
Atlas Copco has developed a fully including pulling the rods out of the
mechanized rig for drilling and cable hole. Rock support, including scaling, bolt-
bolting by a single operator. The first Cabletec is equipped with the well ing, screening, and cablebolting, is still
unit is in operation at Outokumpu’s proven COP 1838 ME hydraulic rock the bottleneck in the working cycle in
Kemi chromite mine in northern drill using reduced impact pressure underground mining and tunneling
Finland, and a second unit has gone to with R32 drill string system for 51 mm applications. Clearly, any reduction in
Chile. The Cabletec L is based on the hole diameter or R35 for 54 mm holes. the time required to install the neces-
long hole production drilling rig Simba Alternatively, the COP 1638 rock drill sary support has a direct impact on the
M7, with a second boom for grouting can be used. Maximum hole length is overall cycle time, and consequently
and cable insertion. the overall productivity and efficiency
The booms have an exceptionally Cabletec main technical of the operations. The fully mecha-
long reach and can drill a line of up to nized bolting rig of today, incorporat-
data
4.7 m of parallel holes from the same rig ing all of the benefits of modern
setup. Likewise, the booms can reach up Length: 13.9 m computer technology, constitutes a
to 7.8 m roof height, allowing the Width: 2.7 m major leap towards improved produc-
Cabletec L to install up to 20 m-long tivity, safety and operator environment.
cable bolt holes in underground mining Height: 3.3 m
applications such as cut and fill mining Turning radius: 4.3m / 7.5 m
and sub level stoping. Furthermore, the by Hans Fernberg
TALKING TECHNICALLY
TALKING TECHNICALLY
Swellex Hybrid
The Swellex® Hybrid consists of a
3
Swellex bolt coupled with one or more
MAI Self Drilling Anchors (MAI
Mechanized Road adding RAS. SDA®). A special connection cou-
pling welded on to the Swellex bolt,
the drill hole, using the feed-force drill rods. Recommended drill hole enables it to be inflated and the SDA
from the hammer; and inflate the diameter is 45-48 mm, with maximum portion to be grouted. After inflating
Swellex bolt using the on-board 51 mm, using R28 drifter rods with a the Swellex bolt, the rock mass
hydraulic Swellex pump. All done, coupling diameter of 44 mm. The between the face plate and the Swellex
and ready for the next bolt! installation sequence is as follows: is pre-tensioned to the desired value.
drill the bolt hole a little bit longer than The rock mass is then exposed to con-
Connectable Swellex the full bolt length; recover the drill finement pressure and the hole annu-
string, and remove it from the feed; lus grouted through the centre hole of
When there is a need for very long place the top-section of the Swellex the SDA. In this way, the pre-ten-
bolts to be installed in a narrow drift, Pm 24C or Mn 24C into the drill steel sioned support element is grouted for
tunnel or cavern, the solution can be support, and feed the bolt section into full protection and long lasting
the Swellex Pm or Mn 24C con- the drill hole, either manually, or using anchorage.
nectable rock bolt. This system com- the COP rock drill; grip the bolt with
prises three different types of bolt the BSH 110, or the retainer; thread in Installation sequence of the new Atlas Copco
section that can be combined to practi- the required number of middle sections Swellex Hybrid.
cally any required length. Each of
these three sections is characterized by
its function. The first section is sealed
at its top end and threaded at its bottom
end. The middle sections are threaded
at both ends, and the bottom section is
threaded at one end and designed to fit
into the Swellex chuck at the other.
The sections are threaded together to
form a tight connection. Installing
Swellex Pm or Mn 24C utilizes the
same optional components as for the
installation of long Swellex bolts, with
the addition of either the BSH 110
Swellex version, or by using a Swellex
retainer to keep the connectable
Swellex in place when tying in
Swellex sections. The RAS system can
greatly assist handling of the Swellex
Pm 24C or Mn 24C sections, using its
two gripper arms attached to the BMH
feed, which are remotely controlled by
the Boomer operator. The bolt hole is
drilled to full depth using extension
TALKING TECHNICALLY
Swellex Hybrid
The Swellex ®Hybrid consists of a
Swellex bolt coupled with one or more
MAI Self Drilling Anchors (MAI
SDA ®). A special connection cou-
pling located between Swellex and
SDA enables the Swellex bolt to be
inflated and the SDA portion to be
grouted.After inflating the Swellex
bolt,the rock mass between the face
plate and the Swellex is pre-tensioned
to the desired value.The rock mass is
then exposed to confinement pressure
and the hole annulus grouted through Atlas Copco SDA system is built around the Boomer, with add-on standard options, and backed up by Atlas
the centre hole of the SDA. In this way, Copco worldwide presence, know how and support.
the pre-tensioned support element is
grouted for full protection and long has a static load carrying capacity of then be suspended directly from the
lasting anchorage. 200 kN and is designed for hanging ser- eyebolt. The bolt, with faceplate,
vices while reinforcing the rock. After becomes part of the rock support pat-
Swellex Hanger the bolt has been installed by using an tern, with all the advantages of Swellex.
inflation adapter, a forged eyebolt Swellex® Pm 24H hanger rockbolts
Swellex® Pm 24H is a versatile rock- (M30/M36) is screwed on. Utilities can are recommended for rock support in
bolt having a flanged head which has a tunnelling, civil engineering and
female M30 or M36 thread. The bolt New Swellex PM24 Hanger rockbolt. mining applications where suspending
utilities in an underground excavation
is needed. The bolts are designed as
anchor points for hanging utility pipes,
ventilation columns and rails, while at
the same time reinforcing the rock.
Cables can also be passed through the
eyebolts to form lacing or trusses in
rockburst prone ground, or to reinforce
friable or weak formations. Swellex®
Pm 24H can be installed using a stan-
dard Swellex pump combined with an
inflation adapter.
TALKING TECHNICALLY
BSH 110
The BSH 110 is a hydraulic drill steel
support providing gripping and guid-
ing functions. The BSH has to be
equipped with the rubber bushing and
steel bushing halves to match the SDA
dimension.
The standard BSH 110 will manage
anchors up to size R51. There is also a
special version, BSH 110 available for
SDA installation, which minimizes the
part of the bolt protruding from the
rock and can fit SDA bars up to the
dimension of T76. All versions of
BSH 110 have to be equipped with
special SDA bushing halves when
handling SDA.
Atlas Copco semi-mechanized MAI bolt installation from a Rocket Boomer.
Installing SDA
fractured, or weak that a normal drill SDAs on a standard Boomer. The
hole will collapse before a standard shank connector is added to the shank Most current rockbolt installation
rock bolt can be inserted. The SDA adapter on the hammer, and should be methods are manual. However, when
system comprises standard items like chosen to match the thread that is used the operation is assisted by a Rocket
the sacrificial bit, a variety of bolt sec- on the SDA. Most frequently used Boomer, productivity and safety are
tions, couplings, faceplate and spheri- threads are R32 and R38, but also com- greatly improved. Using the optional
cal nut. Atlas Copco has developed binations for the R51 and T76 SDA equipment available for the standard
some components and functions for the systems are available. Once the SDA Boomer, a typical SDA bolting semi-
Rocket Boomer to make it the perfect activity is finished, the shank connector mechanized sequence will be as follows.
tool for installing SDA. The standard is removed and normal drilling can 1) Modify the rock drill by attach-
feed on the Boomer should be equipped resume. ing a suitable SDA shank adapter and
with the new BSH 110 drill steel sup-
port. This is used to guide the bolt Length of anchor protruding after installation, depending on BSH 110 used.
when drilling, and when extending the
SDA bolt sections. The new BSH 110
is designed to leave a minimum of the SDA length outside tunnel face = 405
bolt protruding from the rock face, thus
utilizing the full length of the installed 565
COP 1838
bolts. The BSH 110 has remote-con-
trolled functions for guiding, gripping
and drilling, giving the operator full BSH 110B
control of the bolting sequence from
the drilling position. The BSH 110 is
fully compatible with any BMH 6000 256
feed. For those worksites where a lot of
SDA drilling will be done, the COP
1238 or COP 1838 rock drills can be
fitted with a special SDA shank adapter SDA length outside tunnel face = 281
and a conversion kit. The SDA shank
adapter has a female end to eliminate 565
COP 1838
the need for a loose coupling sleeve,
saving time when unthreading the bolt.
This makes handling easier when BSH 110SDA
extending the SDA bolts, boosting pro-
ductivity and improving safety. At
work sites where SDAs are not in daily
use, a suitable solution is to use a shank 301
connector to simplify the handling of
TALKING TECHNICALLY
Grouting SDA
The installation sequences described
above use water flushing for drilling.
The commonly used method for MAI
bolts is post grouting. This is carried
out manually from the Boomer basket,
or any other service platform, by
connecting a grouting unit to the
protruding end of the MAI bolt.
TALKING TECHNICALLY
Connectable Swellex
Alternative to
Cable Bolts
The Mn24C connectable rock bolt
is a relatively new addition to the
Swellex family. With a profile
made of Mn24 tubing, the sec-
tions of Mn24C are coupled
together with threaded connec-
tions that can support loads at
least as high as the profile
strength. Through an ingenious
assembly, the Mn24C combines
the exceptional ease of installa-
tion of Swellex with the length
capability of coupled bars or
cable bolts. Advantages of
Mn24C rockbolts are ease and
speed of installation, and quality
assurance of installation and per-
formance. Many mine operators
already consider Connectable
Swellex Mn24C threaded connection was launched in 2003.
Swellex Mn24 to be the best
solution to their ground control
problems in stoping. Although total cost ranged between C$13/m and saving is sizeable with long cable
manual installation does not C$35/m, a high standard deviation that bolts, it is not appreciable with lengths
appear attractive on a large scale,
operators are extremely interest- can be explained by disparities in the of less than 8 m-10 m, when Mn24C
ed in replacing their time con- costing systems across the sample becomes a good alternative.
suming cable bolting operations mines.
with the simpler and safer Swellex The market for very long cable Time is Money
system. With a semi-mechanized bolts is not targeted, as longer bolts
installation, Connectable Swellex
is very competitive, and is are usually installed by mechanized A comparison has been made for
deemed profitable in both North means. However, while the time typical underground mining practices,
America and South America.
Installing Connectable Swellex into a pilot drive.
Market Study
The following conclusions resulted
from a market study performed in
1995 in Canada on 71 responses from
109 underground mines, some 68 of
which are mining metal and industrial
minerals, excluding potash and salt.
The most-used mining method
reported was longhole stoping, fol-
lowed by Vertical Crater Retreat,
Sub-Level Caving and Cut & Fill.
An estimated 870,000 m of cable
bolts are installed every year in
Canada’s hard rock mines. Most mines
using cable bolts range in output
between 1,000 t/day and 5,000 t/day.
The average total cost of drilling and
installing the cable bolts was reported
at C$23.00 ± C$6.60/m. However,
TALKING TECHNICALLY
Table 1. Comparison of typical installation performances for Cable bolts and Mn24C.
Calculation Base: Calculation Base: Calculation Base: Calculation Base: Calculation Base:
40 double Cable 60 single Cable 60 Connectables 60 Connectables 60 Connectables
bolts 6 m long bolts 6 m long 6 m long 6 m long 6 m long
Drilling (Long Hole): Drilling (Long Hole): Drilling (Long Hole): Drilling (Long Hole): Drilling (Long Hole):
1.3 shifts x 1 man 1.4 shifts x 1 man 1.4 shifts x 1 man 1.4 shifts x 1 man 1.4 shifts x 1 man
64 mm diameter 50 mm diameter 50 mm diameter 50 mm diameter 50 mm diameter
holes holes holes holes holes
Total: 9.8 man-shifts Total: 13.6 man-shifts Total: 6.0 man-shifts Total: 3.7 man-shifts Total: 2.8 man-shifts
Elapsed time: Elapsed time: Elapsed time: Elapsed time: Elapsed time:
5.0 shifts 6.0 shifts 3.7 shifts 3.7 shifts 2.8 shifts
Drilling costs: Drilling costs: Drilling costs: Drilling costs: Drilling costs:
$5.80/m $5.00/m $5.00/m $5.00/m $ 5.00/m
Supplies cost: Supplies cost: Supplies cost: Supplies cost: Supplies cost:
$8.50/m $6.40/m $17.00/m $17.00/m $ 17.00/m
Install.: Install.: Install.: Install.: Install.:
$11.20/m ($45/h) $12.20/m ($45/h) $4.60/m ($45/h) $2.30/m ($45/h) $1.40/m ($45/h)
Total: $25.50/m Total: $23.60/m Total: $26.70/m Total: $24.40/m Total: $23.40/m
installing manual or semi-mechanized operating marginal cost similar to cable efficiency. Quality of installation was
cable bolts, using a 40 double strand bolts. Increase in productivity still has not jeopardized by geological cracking
cable bolts block or a 60 single strand to be analyzed in term of costs saving. and voids, or water, and there was no
cable bolts block. It was assumed that wait for curing before tensioning.
the support capacity required by the Conclusion The increase in productivity can be
designed pattern of double strand utilized to accelerate development of
cable bolts would be met by an array Productivity and costs analyses have stopes, adding flexibility to mine plan-
of 60 Mn24C rockbolts. The cost also been carried out to assess the ning, and facilitating the timely
analysis presented in Table 1 shows competitiveness of the Mn24C rock- extraction of ore and its delivery to the
that, in a semi-mechanized installa- bolts with cable bolting. mill. The added productivity would
tion, using Mn24C rockbolts to Field testing in Canadian mines also mean less overtime and schedul-
replace short cable bolts of less than demonstrated higher productivity in ing conflicts.
8 m-long saves a good deal of time. In ore extraction and development, due To summarize, Mn24C is not only a
addition, quality control is better, and to the flexibility of installation of the very efficient means of ground sup-
training is very simple. Analysis of Mn24C bolts. Perfect installation by port, it also underpins a smooth
Table 1 shows also that, for an Mn24C non-specialized crews, with immedi- mining operation.
price of C$16.50/m for the bolts, the ate support over the entire length of
combined system would have an the bolt, contributed to a higher by François Charette
TALKING TECHNICALLY
TALKING TECHNICALLY
Figure 4. Snapshot of inside view of Swellex bolt with borehole camera – no Figure 5. Snapshot of inside view of Swellex bolt with borehole camera –
corrosion visible inside the Swellex profile. corrosion visible inside the Swellex profile.
TALKING TECHNICALLY
Table 1. Corrosion Rate Assessment of Unprotected Steel for Underground Sites Using DIN 59 929
Sites Ca (mg/l) Cl (mg/l) SO4 (mg/l) HCO3 (mg/l) pH Assessed Corrosion Rate
German DIN 50 929 for
Uniform/Pitting (mm/year)
the Swedish Corrosion Institute in accurately. However, predictive meth- and corrosion resistance. At a depth of
extremely aggressive environments, ods can be helpful to evaluate the need 300 m, the sodium chloride content of
and proved not to be affected by high for corrosion protected rockbolts. the seawater increases dramatically to
chloride or sulphuric acid levels for Field observations, followed by pro- 1.5%.
periods over 10 years. In Table 1, the tective coating of the rockbolt where Sydkraft Konsult chose Swellex for
Swedish Corrosion Institute has assessed necessary, can be used to control cor- the job, because of their high degree
that the life span (at Aspo) of a Coated rosion, both in temporary and perma- of versatility and quality of installa-
Swellex in a very aggressive environ- nent rock reinforcement applications. tion. The corrosion protection on
ment would be of more than 20 years. This approach to corrosion of rock- Coated Swellex met their demands for
The most critical parameters in corro- bolts has been developed by Atlas long duration use, and they found the
sion protection are the characteristic Copco to deal with the need for life quick and simple installation, with full
corrosion sensibility of the coating, and expectancy assessment in the mining support over the entire length of the
the physical state of the coating with and construction industries. bolt, extremely reassuring. Short
reference to scratches and indentations. 90 cm Swellex bolts were used for net
Tests performed by the Swedish Case Study at Aspo fixing, and 2.4 m-long Swellex bolts
Corrosion Institute for Swellex were used for the main rock reinforce-
immersed in sulphuric acid have The 4 km-long subsea tunnel driven to ment duties.
shown that, while the corrosion rate access the site of the Aspo nuclear The views of the project manage-
of unprotected Swellex would be waste research laboratory at ment were borne out by a study car-
0.5 mm/year in the simulated environ- Oskarshamn, Sweden required some ried out by the Swedish Corrosion
ment, the Coated Swellex showed no rock reinforcement, despite high quali- Institute to estimate the risk of corro-
traces of general corrosion, and pitting ty rock over most of its length. In sion of Swellex rock bolts used at
at scratch locations stayed very local- areas requiring support, rockbolts, Aspo laboratory, from which the fol-
ized. In these conditions, corrosion in rockbolts with wire mesh, and rock- lowing conclusions were made.
unprotected areas would not migrate bolts with wire mesh and steel fibre Bolts with an intact corrosion pro-
to a protected area, the coating mini- reinforced shotcrete were used. Test tection layer are not attacked for many
mizing corrosion and controlling its drilling showed that rock reinforce- years. In places where the layer is
spread. ment would get more difficult as the damaged, there is a risk for general as
It has been demonstrated that corro- tunnel progressed, because fissure well as local corrosion. The attack
sion is a very complex process, and zones and saltwater leakage would will, however, be limited and, as such,
corrosion rates are very hard to predict place high demands on holding power less significant for the strength of the
bolt. The time for fracture due to gen-
CORROSION POTENTIAL ASSESSMENT STEPS eral corrosion for a 2 mm-thick bolt
1. PRELIMINARY ANALYSIS USING DIN 50 929 can be considerably longer than 20
years, mainly due to low oxygen con-
2. FOLLOW UP OF PERFORMANCE OF ROCKBOLTS – CAPACITY
tent in the water. The attack will, how-
MEASUREMENT – ENDOSCOPY – WATER ANALYSIS TO MONITOR
ever, be limited and, as such, be less
CHANGES IN CONDITIONS
significant for the strength of the bolt.
3. RE-ASSESSMENT OF ADEQUACY OF CORROSION RESISTANCE
TOOLS: WATER ANALYSIS, PULL TESTING, BOREHOLE CAMERA
by François Charette
TALKING TECHNICALLY
TALKING TECHNICALLY
Pregrouting
The cost for pregrouting can be
5-10 % of the cost of postgrouting for
reaching comparable and satisfactory
results.
The main reason is that both the
Grouting of the curtain cone. grout pressure and the grout flow can
be fully utilized in undisturbed rock
This demand is difficult to meet Grouting in Tunnels whereas postgrouting always is done
when pre-grouting in tunnels, where against a free surface, often cracked
spacing is reduced to ensure that Tunnels are constructed for many dif- up from blasting and excavation.
fissure planes, with an unfavourable ferent purposes, and under widely Investigation drilling is done during
orientation to the grout holes, will be varying geographic and geological the actual tunnel work and parallel
grouted properly. Here, the diameter conditions. Tunnels carrying fluids, be with the pregrouting in order to inves-
of the drillhole has very limited influ- it fresh water or sewage, should not tigate the rock properties, like cracks,
ence on the grouting result. leak; and all tunnels should resist the fissures and fissure systems, occur-
Because of the stiffness of the inflow of water from the surrounding rence of water, and soft or weathered
drill string, larger hole diameters in ground. rock, for the next 50 metres or so.
general result in straighter, albeit more The latter requirement may be Pregrouting means that the rock is
expensive, holes. The setting of necessary to avoid draining natural treated ahead of excavation.
packers is more expensive and diffi- water into the tunnel, which could These two operations are repeated
cult in large diameter holes, as is the lead to a general lowering of the until a satisfactory result is achieved.
grouting. ground water table in a wide area The pregrouted zone should always
General requirements for drilling above its alignment. Movement of the go beyond the area that is disturbed by
equipment in tunnelling work are as water table may result in subsidence blasting, bolting or excavation.
follows. If possible, drill all holes and damage to existing surface struc- Grouting and pregrouting of tunnels
from a single set up, and with two dif- tures, loss of capacity of drinking have three different purposes:
ferent rod sizes and three different water wells, and similar undesirable stabilization, strengthening and seal-
hole diameters for blast hole, cut hole consequences. ing of the ground.
and grout hole. Use a service platform In other instances, especially in Stabilization grouting creates a
and a rod adding system (RAS) with unstable ground containing running skeleton of grout in weak parts or
rod magazine: drilling for a grout material under pressure, or in karst areas of the rock, to avoid sliding in
round may involve handling some 5 t formations, grouting may be necessary cracks, fissures or bedding planes.
of drill steel. A positioning control to stabilize, strengthen and seal the This type of is grouting is to support a
instrument is a necessity, together with strata. temporary construction or when a con-
good working lights, and an elevated Tunnels that have to be watertight, crete casting is done at a later stage.
sound-protected cabin for full view of as well as tunnels in weak ground that Strengthening grouting is done for
the face. A stepless mix of flushwater have to have a long service life, are reinforcing a tunnel permanently. In
and air is advisable, bearing in mind usually lined. This lining is often most cases it is less expensive to uti-
that one drill rig uses 200-300 lit/min placed concurrently with the tunnelling lize and strengthen the existing rock
of water. High pressure cleaning process itself, particularly in TBM structure compared to replacing it with
equipment will be necessary for the bored tunnels where it is constructed a new construction of concrete.
grout holes and the drilling and grout- of rings of prefabricated segments. Sealing grouting is strengthening
ing equipment. Even in bored tunnels, where the grouting developed to almost water
Grouting is too often planned and excavated shape and diameter are tightness. Sealing grouting is divided
carried out as an off time shift, when controlled within narrow limits, into different sealing classes depend-
the drilling equipment is elsewhere. there will be a slight annular gap ing on permissible water inflow.
Thus, when there is a need for addi- between the outside of the lining In Scandinavia normal tunnels are
tional grout hole drilling, this cannot be and the inside of the bore. Grouting said to present insignificant problems
undertaken immediately. Consequently behind the lining serves the purpose when the leakage is in the range of
the driller cannot easily pass his of filling this gap, so that the lining less than 5 lit/min per 100 m. If
information and observations to the will support the ground from the it exceeds 10-20 lit/min per 100 m,
grouting technician. beginning, without settlement. This then significant problems will occur.
TALKING TECHNICALLY
Drammen Case Study water flows, a major operation for two sizes of grout cylinders: 110 mm
which Selmer invested in a sophisti- and 150 mm diameter; and two types
At the Norwegian port of Drammen, a cated Atlas Copco Craelius truck- of valves: ball valves for normal
second single-tube 2.3 km-long tunnel mounted Unigrout E 400-100 WB. grouting applications, and disc valves
with bi-directional traffic flow was This comprised a containerized for when a smooth flow and minimal
required to relieve congestion on the mixing and pumping plant with exter- pressure drop are required. Main-
north bank of the river. The tunnel is nal cement feed and additive hoppers, tenance is easy, by way of a self
on a curved alignment beneath the and liquid additive tank. Inside the cleaning cement fluid end, water
Bragernes Ridge, an outcrop of igneous container were two Cemag units, and flushing of cement and hydraulic
rock comprising 50% porphyry and two 400 lit/min Pumpac units, with a piston rods, and only one 46 mm
50% basalt. The main face had an single 400 litre Cemix WB weight wrench for servicing the cement pump.
excavated arched cross-section of batching mixer. The unit’s nominal The Logac system is a computer
70.5 sq m, which included a large drain. capacity is 4 t/h of dry cement, but up based logging system for sampling
The main contractor was Selmer, to 66 t of cement was successfully and storing of data during the grouting
for client Statens Vegvesen Buskerud, injected into a particularly wet round operation. The recorder is housed in a
the local agency of the Norwegian over a 15 h period. cabinet with a Craelius Flow Pressure
State Highways Authority. (CFP) meter unit equipped with cable
A condition on the construction of Pumping and Logging and quick coupling for easy connec-
the tunnel demanded that there be no tion. The CFP meter unit consists of
interference with the water table, and The Atlas Copco Craelius Pumpac an electromagnetic flow-meter and a
the tunnel itself be kept dry. The maxi- System is based on a double acting pressure-meter. The logged parameters
mum ingress of water allowed before pump principle. The system has been are flow, pressure, volume, time, real
grouting was 30 lit/min/100 m towards made simple and user-friendly by way time and hole number. The standard
the tunnel ends, and 10 lit/min/100 m of modularized parts, independent and flow meter operates in a range of 0-
in the centre section. stepless variable pressure and flow, 200 lit/min with a maximum pressure
The grouting sequence commenced easy and fast change of valve assem- of 40 and 100 bar respectively. The
with the drilling of 27 m-long, 51 mm- bly units, and environmentally friend- standard pressure sensor covers a
diameter holes ahead of the face to test ly hydraulic fluid. Then the whole life range of 0-100 bar. All parameters are
for water. These were drilled by an cost is kept to a minimum by system shown in real time on the Logac 4000
Atlas Copco Rocket Boomer 353S, adaptability. The system features a recorder display, and stored on a PC-
using threaded extension steel, which hydraulic switch-over system, inte- card. The Logac 4000 samples data six
was manually attached. Generally, ten grated in the hydraulic cylinder, and a times per second, and stores it on the
forward holes were drilled, with a split cotter fast-locking system of the card every 10th second. The card can
10 m overlap, allowing 17 m advance two piston rods for easy dismantling be kept as a permanent record for
between events. of the cylinder assembly. Three sizes future references, or reused over and
The contract envisaged injection of of electric motors are available: over again. The control panel consists
2,370 t of grout to achieve the objective 7.5 kW, 15 kW and 22 kW. There are of an on/off switch for the recorder, a
display, a separate button for each of
Container mounted grout mixing and injection system to be carried on a truck. the eight groutlines, and a 10-key
keypad. Each groutline shows time,
real time, flow, pressure and volume.
There is a button to show either one
single line, or all eight lines simultane-
ously, and two diodes, one for telling
when logging is on, and the other for
informing when the memory card is
90% full.
One reason for Selmer’s success at
Drammen was that they could continu-
ously pump high volumes of stable
grout at high pressures. A normal
pumping rate is 110-120 lit/min at 50-
60 bar, and they used 80 bar as stop
criterion, and sometimes even 90 bar.
The water/cement ratio ranged from
1.0 to 0.5.
by Sten-Äke Pettersson
TALKING TECHNICALLY
TALKING TECHNICALLY
behind the face. At 10 m behind the extends to more than 4 m, due to the
face, 50 kN was generated at the time lapse for grout hardening.
crown and 131 kN at the sidewall. When using Swellex rock bolts,
For both cases, loads on rockbolts maximum bonding with the strata is
do not increase more than 1D behind achieved right after installation, so the
the face, due to the convergence ten- required bolt length is shorter than
dency of rock mass displacement. with grouted bolts.
Except for right after installation, axial
force generated is about 1.5 times Summary
larger for Swellex than for grouted.
The excellent support effect of
Laboratory testing has determined the relationship
between curing time and load capacity for grouted
Natural Arch Swellex rockbolts can be summarized
in four points as follows.
rebars.
The difference of crown settlements Compared with grouted rockbolts,
for grouted bolts and Swellex was Swellex exhibits a much greater sup-
grouted rockbolts as input for numeri- 0.5 mm, 1.2 mm, and 1.5 mm at 1 m, port effect right after installation, and
cal modelling. Using these values, 10 m, and 20 m behind the face, contributes to stabilization of the rock
two-dimension and three-dimension respectively. mass near to the face. In a continuous
models simulated pull-out tests. Using grouted bolts, a plastic rock mass, Swellex has a greater con-
The rockbolt axial force generated region of about 4 m is generated from trol effect over the plastic region. In
at the tunnel crown in the case of the crown to the sidewall section. In heavily jointed rock, Swellex con-
grouted rockbolts was 1 kN immedi- the case of Swellex, the plastic region tributes more to the formation of the
ately after installation, rising to 32 kN near the crown tends to decrease, and natural arch by controlling the shear
maximum. In the case of Swellex, the value is controlled at about 2 m. behaviour of joints, improving the
30 kN was generated immediately, Where there is no support, the value is stress continuity of the rock mass.
rising to 38 kN. For Swellex, the axial 6 m at the crown, and 4 m at the side Swellex controls tunnel deformation
force is more than 60% of the maxi- wall section. better, and exhibits excellent support,
mum value from the beginning, and is The tunnel is stabilized by generat- making it superior to the equivalent
about 1.6 times that of grouted rock- ing a natural arch of the surrounding grouted rockbolt.
bolts. rock mass, preserving its continuity Because stabilization of the rock
Overall distribution of rockbolt for tangential stress. In the case of the mass close to the face was a key point
axial force was measured at 1 m, Swellex rockbolt, since the continuity for the Tomei tunnel, Swellex rock-
10 m, 20 m, and 30 m behind the face. for ground stress of the arch section is bolts were specified. Swellex enables
Using grouted rockbolts, almost no greater than when using grouted rock- a tunnel structure to be stabilized by
axial force was generated from crown bolts, it is thought to have a major support, without the impediment of
to sidewall immediately behind the effect on tunnel stabilization. curing time for shotcrete and grouting
face. At 10 m (0.5D) behind the face, Joint shear displacement is generated materials. By installing Swellex bolts
30 kN was generated at the crown within 4.0 m of the tunnel profile, and immediately after excavation, it is
and 82 kN at the sidewall. Using this can be controlled immediately possible to avoid rock instability.
Swellex, 33 kN was generated at the using a 4 m-long Swellex bolt. With
crown, and 66 kN at the sidewall right grouted rockbolts, shear displacement by Federico Scolari
Displacement contour, rockbolt axial force, longitudinal, for grouted rebars. Displacement contour, using shorter Swellex rockbolts.
TALKING TECHNICALLY
TALKING TECHNICALLY
range comprises button and cross-type drilling costs, and is taking market
bits in an extensive selection of design share from integrals, especially in
configurations. These designs can be mining applications and the dimen-
used in a variety of rock formations sional stone industry.
for maximum productivity.
Moreover, there are two new by Jan Lindkvist
models, with an extra front button for
improved hole straightness, higher
The Secoroc Uppercut
penetration rate and longer service
life. Furthermore, the Secoroc range of
Rod
ballistic button bits is in the process of ● Special anti-corrosion oil to
being extended to meet ever more protect the flushing hole of
diverse demands. the rod
● Surface hardened taper
Prepared for the Future end for high wear
resistance and a longer
Secoroc Uppercut tapered equipment service life
can be used in all types of applications ● Stainless steel flushing
and rock formations. The lowest tube lining to prevent
cost/metre drilled, a claim that has corrosion and breakage
Uppercut tapered rod and button bit ready to drill. long been synonymous with Secoroc ● Drifted flushing hole with
products, is now lower than ever with stainless steel lining at the
shank length 108 mm for 4 degree 46 this range, along with higher drilling shank end prevents
minute, 7 degree, 11 degree and 12 productivity. breakage and increases
degree tapers. Uppercut rods with 25 Tapered products, which first appeared service life
mm hexagonal rod section and shank on the scene in the 1960s,
● Surface hardened shank
length 159 mm are available with 12 can readily handle the impact energy from end for high wear
degree taper. modern pneumatic and hydraulic rock resistance and a longer
drills, while they are also ready to cope with service life
High Performance Bits the stronger rock drills currently on the
● Z708 steel for superior
drawing board.
Secoroc bit design and production fatigue and bending
Nowadays, tapered equipment is
processes are in a state of constant strength
favoured for increased penetration
refinement. The Secoroc Uppercut rate, longer service life and lower
Range of Uppercut tapered rods and bits from Atlas Copco Secoroc.
TALKING TECHNICALLY
Thread of Innovation
To solve the problem, Atlas Copco
Secoroc faced two choices: either Magnum SR used in a bolting application.
increase the dimensions of the rods
and bits in the same way as everybody
else, or find a new way. Being notori- diameter is larger at the end of the The new Magnum SR system for drift-
ously stubborn innovators, the choice thread and smaller at its tip. By adding ing and rockbolting, specially designed
was easy. considerably more steel at the end of for the new generation of powerful drill-
During the creative process, three the thread, the new design was given a rigs, delivers more and straighter holes
important insights emerged. First, the distinctive, conical shape. This con- per shift and has a considerably longer
hole sizes should remain as for drilling cept not only upped the fatigue resis- service life than any competing system.
with standard equipment. Second, the tance of the rods, but also reduced the
bits should be easy to uncouple. And tendency to deviate during collaring. Field Tests Worldwide
third, the old thread design had to be The Magnum SR thread design also
left behind. has the added bonus that the bits are Extensive field tests with the Magnum
As with all genuinely groundbreak- very easy to uncouple and change, SR were carried out on four conti-
ing endeavours, the solution was saving time and equipment, and result- nents, and involved more than a half
deceptively simple. The secret of the ing in more holes drilled. Magnum SR million metres of drilling over a
Magnum SR thread design is that the has proved a big hit with operators. period of one year.
TALKING TECHNICALLY
TALKING TECHNICALLY
tion of the structural fabric of the rock can fail violently under
mass including aspects such as joints, the right conditions (see Massive rock subjected to low in situ Massive rock subjected to high in situ
stress levels. Linear elastic response stress levels. Spalling, slabbing and
faults, shear zones; the evaluation of figure 3). Very frac- with little or no rock failure. crushing initiates at high stress
the mechanical parameters of the tured rock will tend to concentration points on the boundary
and propagates into the surrounding
intact rock and structures; the identifi- yield to stresses, and rock mass.
cation and quantification of the failure often deforms in a
modes based on stress and structural problematic manner
analysis; the influence of the excava- (figure 4). Obviously,
Jointed rock
tion mode; and the design of the rock excavation shape, size
reinforcement itself. and orientation also
Massive rock, with relatively few Massive rock, with relatively few
Differently formulated, it could be affect the response to discontinuities, subjected to low in discontinuities, subjected to high in
said that stresses and rock structures the acting forces at situ stress conditions. Blocks or situ stress conditions. Failure occurs
wedges released by intersecting as a result of sliding on discontinuity
are the two most important factors play. discontinuities, fall or slide due to surfaces and also by crushing and
gravity loading. splitting of rock blocks.
affecting the stability of any excava-
tion in natural strata material. Optimized
Heavily jointed block
TALKING TECHNICALLY
Rock Reinforcement
Rock reinforcement devices and sur-
face support are used to control the
rock masses within a certain range,
Figure 3. Rubble created from a dynamic failure of Numerical Modelling allowing safe and economical access
a mine roof. to the excavated areas.
Long term excavation planning can Historically, before the 1900s, typi-
is now regularly used to optimize the benefit from detailed analysis like cal roof support in mines was timber
performance of mining excavations in numerical modelling. Stress regimes posts and beam. Then, as early as
rock. Using rock mechanics leads to a can be predicted and mining 1905, roof bolts were reportedly used
better understanding of the behaviour sequences optimized to keep the stress in coal mine roofs in the United
of the rock masses, which in turn leads level at a comfortable level: not too States. In late 1920, systematic rein-
to a more effective and safer opera- high to create seismic events, and not forcement of mine roofs was intro-
tion. Stress analysis is also more com- to low to create major structural insta- duced to allow the use of mechanical
monly performed on site, and results bilities. For day-to-day operation, full-revolving loading shovels, by pro-
are easier to analyze thanks to the use numerical analysis will give results viding room to manoeuvre free of con-
of powerful desktop computers. that must be confirmed by field obser- ventional timber posts. Inclusion of
The design process should also be vation, but can be used to plan with channel irons, fastened by rock bolts
repeated at later stages of the mining the right kind of conditions in mind. to support large area of roof led to the
operation, as field conditions will principle of “suspension roof sup-
almost always change for the worse. Figure 4. Ground conditions leading to yielding ports”. The need for early support to
It is critical that the correct assess- walls and roof. secure the lower roof layer to avoid
ment of failure mode is made, as this
understanding will lead to proper
reinforcement instead of using a long
and arduous trial and error methodol-
ogy.
As an example, when hard and
massive rock fails, producing small
fragments like those seen on figure
5, it is often a sign that the rock is
overstressed and is rupturing in a
brittle and uncontrolled way. This
could be the precursor of seismic
events and dynamic failure, which
most rock reinforcement would be
unable to control. It is also a fact
that, as long as well-recognized
brands of rock reinforcement are
used, the support devices rarely fail
as a result of poor material quality,
but rather as a result of inadequate
applications.
TALKING TECHNICALLY
20
bolts were introduced by Atlas Copco. (9) (8) (7) (6) (5) (4) (3) (2)
These two products started the use of 10 4.0 m
ESR
3
m
m m
friction anchored rock bolts in under- m m 3.0 m
m
m
m
m m
0m 90
m
0 a
40
0
25 15 12 are
50
TALKING TECHNICALLY
TALKING TECHNICALLY
Testing Configuration
Figure 1 shows the testing apparatus
used to simulate the action of seismic
events on Swellex rock bolts. All
impact tests were performed on 2.1 m-
long Swellex Mn12 bolts. The static
weight of moving part was one metric
tonne, or 1000 kg. In field failure, the
Swellex bolts are usually broken at a c
distance varying from 10 cm to 50 cm
from the head bushing. Failure of the
bushing weld almost never occurs in distance from the head as to mobilize
the field. To try to reproduce the fail- load from the anchorage and retaining
ure pattern observed in the field, the force generated by the bushing-plate
Swellex bolts were inflated in two ensemble.
steel tubes, with the top tube generat- The friction inside the steel tube
ing the anchorage. The second (see was not sufficient to create failure of
Figure 1) shorter, impact tube also the bolt profile, and this highlighted
generates some friction above the the need to better simulate steel/rock
bushing and plate assembly, which anchorage capacity. However, this
dampens the impact. The rationale is reduced friction demonstrated interest-
that, since no bolts are breaking at the ing behaviour that has led to a better
bushing weld in field events, it must understanding of anchorage require-
be that the bulking occurs at such a ments in dynamic loading.
TALKING TECHNICALLY
25
used to preliminary assess the theoreti-
15 cal energy absorption capacity, but it
5 has been found that load and deforma-
-5
tion are different from static tests.
0.95 1.05 1.15 1.25 1.35 1.45 1.55 Measurements show that the impact
time (s)
load exceeds the ultimate static tensile
strength by a factor of about 1.5, while
Figure 2. Typical signature of impact test on Swellex bolts: a) Typical phases of an impact test; b) actual when shearing was observed (Figure 3),
impact test with sliding of bolt inside steel tube. the impact load exceeded the ultimate
shear strength, taken as 60% of tensile
measured at time intervals of according to the load level. If the load strength, by a factor of about 1.4.
0.00005 seconds. reaches, or exceeds, the ultimate From the tests performed during the
strength, then the bolt simply breaks. spring of 2004, the bolts showed only
Impact Tests Analysis However, based on the test results, minimum yielding for loads exceeding
Table 1. Typical Impact Tests Results
Upon starting the test, the weight is
elevated to a pre-determined height
Result Test 1 Test 2 Test 3 Test 4
above the impact point. After being
released, the weight accelerates until it Impact Load (T) 10.4 15.3 17.8 18.2
reaches the impact point. At this point,
K(kJ) 9.1 8.6 6.1 9.1
the impact load is measured. Under
the impact load, the bolt starts to Status of bolt Failed in Failed in Failed in Slided
deform, but almost simultaneously, it shear shear and tension
also starts to slide inside the steel tube. tension
The sliding reduces the load on the
bolt, so that it does not fail if it is not Table 2. Theoretical energy absorption capacity based on quasi-static
pinned or restrained. During sliding, load -strain properties
frictional energy is dissipated accord-
ing to the friction generated on the Description Peak Load Displacement Energy
wall of the tube. As the weight slows (kN) (mm) Absorption
(kJ)
down, the friction coefficient increases
19 mm resin-grouted rebar 100 – 170 10 – 30 1–4
toward its static value, and the bolt is
16 mm cable bolt 160 -240 20 – 40 2–6
finally stopped. The momentum cre-
16 mm, 2 m long mech. Bolt 70 – 120 20 – 50 2–4
ates harmonic oscillations in the bolt,
16 mm, 4 m debonded cable 160 – 240 30 – 50 4–8
which acts as a stiff spring, and these
16 mm grouted smooth bar 70 – 130 50 – 100 4 – 10
are damped very rapidly. When the
Standard Swellex bolt 105 – 110 25 – 35 2–4
bolt is clamped or fixed so that it
Mn12 Swellex bolt 120 – 125 45 – 100 5.4 – 12.5
cannot start to slide at both ends, if the
Mn24 Swellex bolt 220 – 240 80 – 120 18 – 29
transmitted load at the restricted loca-
Split Set bolt 50 – 100 80 – 200 5 – 15
tion does not reach the ultimate
16 mm cone bolt 90 - 150 100 - 200 10 – 25
strength of the steel, the bolt only
deforms elastically and plastically, (Data from Kaiser, 1995)
TALKING TECHNICALLY
Swellex Atlas 9 kJ
Mn12 Copco/
2.1 m NTC
TALKING TECHNICALLY
static loading, but the deformational coupled to the static anchorage capaci-
energy absorption seems to be quite ty. This operation was successful with References
similar. steel tubes instead of rock. The next
Tests results from NTC and Atlas step is to increase the friction against 1. Charette, F. Performance of
Copco also demonstrated another the bolt in order to simulate an anchor- Swellex rock bolts under dynamic
important fact. This is that maximum age capacity of 130 to 180 k/m, and loading conditions, The South
energy can be absorbed when the fric- repeat the same testing with Mn24 African Institute of Mining and
tion properties are tightly matched to bolts. Metallurgy. Second International
the strength of the material. When this It is also very interesting to consid- Seminar on Deep and High Stress
right combination is reached, the bolt er what kind of energy dissipation Mining, Johannesburg 2004.
head will move just before the could be achieved when using an 2. Ortlepp, W.D., Stacey, T.R.
shank/bolt body enters the deformation Mn24 instead of an Mn12 bolt. As the Testing of tunnel support: Dynamic
phase. This allows maximum energy bolt itself is twice as strong, the maxi- load testing of rock bolt elements to
absorption without failure of the unit, mum load could be doubled, and, provide data for safer support
and provides a consistent energy since the friction could be adjusted in design (GAP423), June 1998.
absorption capacity, coupled with order to provide the right anchorage 3. Kaiser, Canadian Rockburst
stable static load bearing capacity, capacity, the energy absorption could Design Handbook, 1995.
equivalent to the rated capacity of the certainly be in the order of +18 kJ per 4. Kaiser et al, Drift Support in
bolt. event. burst-prone ground, CIM Bulletin,
The conclusions obtained from March 1996.
Conclusion these laboratory tests is being 5. Kaiser, Support Against Rock
applied to the Hybrid Swellex bolt Burst – Short Course 1995–2003.
Dynamic testing at the laboratory has that combines the controllable slid- 6. Falmagne, V. Etude de fais-
shown that Swellex bolts can accept ing ability of the Swellex with the abilité: tests d’impact sur Swellex.
and dissipate a reasonable amount of strength and reliability of MAI Centre Technologie Noranda, Mai
energy without failing, and still provide bars. 2003.
an adequate load capacity, as long as
the anchorage length is adequately by François Charette
TALKING TECHNICALLY
Advantages of Self Drilling Installation of SDA R38 N with ROC D7 at Carriere d’Arvel, Switzerland.
Anchors
thread, affording the flexibility to Method of Installation
Since the slow cased borehole drilling adjust the nail to the actual require-
methods were superceded, the speed ments on site, without waste or delay, Self Drilling Anchors are installed
of installation has increased consider- as construction proceeds. with air driven or hydraulic rotary
ably, up to 20-30 soil nails/day using Transportation and handling of percussion drilling equipment, using
MAI SDA, and the risk of re-drilling MAI SDA to and on site is safe and a borehole flush medium suitable for
time spent cleaning collapsed bore- economical, because of the commonly the specific ground conditions.
holes has been eliminated. used rod length of 3 m or 4 m. These There are three types of borehole
The selection of the drilling equip- can be extended using couplings to flush: water flush for long boreholes in
ment for MAI SDA installation is also allow installation of soil nails up to 15 dense to very dense sand, gravel forma-
more flexible, especially for working m depth, depending on the geology. tion or rock conditions, for a better
in confined space. There is also the option to use simulta- transportation of large cuttings and cool-
MAI SDA rods are manufactured neous drilling and grouting installation ing of the drill bit; air flush for short
with a continuous ISO standard techniques. boreholes in soft soil such as chalk and
TALKING TECHNICALLY
TALKING TECHNICALLY
TALKING TECHNICALLY
TALKING TECHNICALLY
Evaluated 3D image generated with JointMetriX3D®. Joints are represented by traces and areas. The
Introduction arrows indicate the orientation of an area by its normal vector while the spherical triangles indicate the
orientation of the plane fitted through the trace. The absolute position and orientation of the joints is
Currently the assessment of potential directly determined.
for excessive overbreak and disconti-
nuity controlled block falls or slides A 3D image combines a large take two free positioned images. In
heavily relies on experience. number of three-dimensional surface order to allow for measurements, the
Measurement of discontinuity pattern measurements with a high-resolution camera is calibrated. Scale and local
and orientations is done manually, if colour image, thus easing visual orientation is introduced by locating a
at all. The evaluation of the incom- inspection of the rock mass. vertically levelled bar somewhere
plete and inaccurate data with respect within the region of the images.
to block fall hazard is slow, and usual- Imaging at the Tunnel Site The whole data acquisition process
ly does not allow for the determina- requires only about one minute.
tion of appropriate rock support in The major goal is to record the actual Processing the images leads to 6 MPix
time. rock mass conditions comprehensively 3D images with several hundred thou-
In order to master these shortcom- by producing images that allow repro- sand 3D measurements.
ings with respect to efficiency and ducible assessments. The stereo-pho-
accuracy, a 3D imaging system has togrammetric principle of Panoramic Line Scanner
been developed consisting of an imag- JointMetriX3D® requires two images
ing device and 3D evaluation software of the same area captured from differ- For very high-resolution images, the
components. Named the ent positions in order to obtain 3D panoramic line scanner should be
JointMetriX3D® system, it unites sev- information. Currently, two options for applied. This scanner is capable of
eral features: imaging are available. The first one producing images of more than 100
• Data (image) recording at the face uses conventional calibrated single Mpix, recording very fine details.
• 3D image generation and assessment lens reflex (SLR) cameras, while the During scanning, the device head
• Metric and accurate measurement other uses a panoramic line scanner. rotates, recording the face column by
of discontinuity orientations, dis- column. A major advantage of the
tances, persistence, and other geo- SLR Camera panoramic principle is that existing
metrical properties reflective targets in the tunnel can be
• Link to other applications, such as A conventional SLR camera with a used to establish a reference of the
CAD minimum 6 MPix sensor is used to image to the tunnel. Data acquisition
TALKING TECHNICALLY
on site typically takes in the region of All measurements are metric and An imaging system, such as
ten minutes, leading to 3D images referenced either to a relative or the JointMetriX3D® can be installed on a
which are referenced to the tunnel tunnel coordinate system, and can be drilling jumbo, allowing for an instant
coordinates. exported directly into standard file for- imaging during work. Recorded data
mats. are transferred to the office for evalua-
3D Image Generation and A free copy of JMX Analyst is tion, and the necessary information for
Measurements available for download at www.joint- the rock reinforcement transferred
metrix.com/. back to the drilling equipment within
From a stereoscopic image pair a 3D minutes.
image is reconstructed by purpose- Prediction of Block Failure
built software. This can be carried out by Wulf Schubert, Markus Pötsch
Modes and Support Design and Andreas Gaich
by personnel on-site or off-site, using
secure Internet connections. The measurements derived from 3D
Once a 3D image is ready, assess- images are used to establish a consis- 3D imaging with SLR camera.
ments and measurements are taken tent and accurate ground model. Using
from it using the 3D software JMX the acquired information on the rock
Analyst. This software allows the mass structure, potentially unstable
inspection of 3D images thoroughly, blocks are identified with respect to
giving a realistic impression of the their location, volume, and weight.
actual conditions. Once the failure mode and the
Measurements are taken directly on properties of the blocks are identified,
the 3D image using the software, such the quantity, location and length of
as: required bolts to stabilize the blocks is
• Joint locations, orientations, spac- determined.
ing, persistence, etc. Further processing of the existing
• Lithological boundaries data can be used to extrapolate the
• Areas rock mass structure in a representa-
• Volume of overbreak tive volume around the tunnel,
JMX Analyst contains a tool to plot allowing an assessment of the condi-
joint data in stereographic projection tions ahead of the face. This
and the variation of orientations of enhances the quality of short-term
joint sets (cone of confidence, spheri- prediction, thus reducing any sur-
cal aperture, etc). prises during excavation.
TALKING TECHNICALLY
TALKING TECHNICALLY
use the same principle of having a part efficiency of rock reinforcement for When used for seismicity, Swellex
of the system that can disengage and seismicity, in order to make the system plasticoated and galvanized MAI SDA
absorb energy through friction or defor- absorb the energy and preserve the anchors are recommended for corrosion
mation. The efficiency of these systems rock mass between each bolt. protection. A plug can be used to protect
depends on the quality of the installa- the inside of the Swellex in the long term.
tion, which varies significantly with the Life Expectancy
quality of grout and de-bonding agent, Installation Sequence
rock mass condition, and experience When it comes to protecting the
and training. Often, because of poor investment, for long life expectancy For pre-tensioning and grouting:
quality of installation, these systems Swellex Hybrid offers solutions to 1-Drill the hole to the required
have not achieved the expected success match the threat. length using 48 to 51 mm bit.
and efficiency underground. When used for pre-tensioning and 2-Insert Swellex (the length can be
The advantage with the Hybrid grouting: determined from pull test – should
system is that, once the anchorage Atlas Copco has developed a spe- be sufficiently long to generate pull
capacity (kN/m) is deduced from on- cial grouting device that is coupled out resistance equal or higher to its
site pull test of the short Swellex seg- between the Swellex segment and yielding strength into the hole).
ment, it is easy to calculate the length MAI rods. This allows the Swellex 3-Thread the SDA rod all the way into
of the Swellex required to reach the Hybrid to be inflated, pre-tensioned the grouting valve on the Swellex.
maximum sliding strength that would when required, and then grouted Extend with additional SDA rods
not damage the bolt under dynamic through the MAI SDA rods. The and special Hybrid couplings (good
conditions, and the free sliding length grout then protects the Hybrid bolt, for 300 bar) to match the hole depth.
needed to dissipate the energy. The preserving the MAI rods from contact 4- Install plate and nut
installation is easy and, above all, with the environment. For full protec- 5-Attach inflation coupling to the
always perfect, as it is controlled by tion from a corrosive environment, or last SDA rod.
the Swellex pump. The installed for long life expectancy, MAI rods 6-Inflate Swellex through the SDA
system can also be tested at any time can be supplied galvanized, and rods using a standard Swellex pump
to make sure it is working according Swellex in Plasticoated or coated ver- having 300 bars in water pressure.
to calculation. sions. The grout will then offer the 7-Open the grout valve (in the Grouting
first protection layer, followed by the device) by rotating the MAI rods by
Site Testing zinc layer, or the plasticoating on the a 1/2 turn anti-clockwise.
Swellex. As the MAI bolts are grouted 8-Detach the inflation coupling.
The Hybrid bolt is now being tested at from inside out, there is no access for 9-Pre-tension the bolt.
WASM facility in Australia to deter- corrosive elements. 10-Grout (MAI 400 NT Grout Pump
mine the optimal anchorage for maxi- is recommended).
mal energy absorbancy of the system Installation sequence of the Atlas Copco Swellex
under dynamic loading conditions. Both Hybrid. For seismicity:
the Hybrid bolt and its system of con- 1-Drill the hole to the required length
trolled energy absorbancy are patented. using 48 to 51mm bit.
If, for example, a 1 m Swellex 2-Insert Swellex (the length can be
Pm24C offering a 150 kN anchorage determined from pull test – should
is proven to slide (yielding strength = be sufficiently short to generate pull
200 kN) under dynamic conditions out resistance lower to its yielding
without damaging the bolt, a sliding of strength into the hole).
0.15 m would consume as much as 3-Thread the SDA rod to the Swellex.
22.5 kJ of energy. 4-Install plate and nut.
Once sliding behaviour is tested and 5-Attach inflation coupling to the last
the system proven, a sliding pull test SDA rod
(on a short bolt segment inflated) per- 6-Inflate Swellex through the SDA
formed on site will confirm the anchor- rod using a standard Swellex pump
age capacity. The length of the Swellex having 300 bars in water pressure.
will then be chosen to match the maxi- 7-Detach the inflation coupling.
mum sliding strength, and sliding dis- 8-Pre-tension the bolt.
tance calculated according to the energy By combining the merits of the
to be dissipated. This system offers the Swellex and MAI SDA systems, Atlas
facility to be tested at any time. Copco has invented a completely new
Recent studies have shown that the approach to rock bolting.
quality of surface support is of para-
mount importance for ensuring the by Mario Bureau
MINING WORLDWIDE
Swellex in Mining
Safe and Speedy
Support
Rock support is often a bottleneck in
the business of underground mining,
and an obvious solution is faster
rockbolting. The cost is negligible
when compared to the higher profits
that can be made by keeping equip-
ment fully and economically employed
to increase production.
The mining industry is increasingly
recognizing that Atlas Copco Swellex
rockbolts, which are quickly and
safely installed to give immediate
support, are speeding up operations
and boosting revenues. Over the past
two decades, the Swellex rockbolting
system has become world famous as
schedule. This means that operations must Bieniawski diagram showing stand-up
be synchronized so that one does not fall times for different spans and rock
the simplest, fastest and most reliable
ground reinforcement technology behind, holding up the others and wasting classes.
available. time and money.
The Swellex bolt is a folded steel The development of Atlas Copco’s
tube, which is inserted into a pre-
drilled hole in the rock. Water is
Rocket Boomer and Boltec rigs is
blasted into the tube at high pres- constantly reducing drilling time, making
sure, blowing out the fold and Swellex the perfect partner to provide
expanding the tube into the exact reinforcement quickly, so that the next
shape of the hole, adapting to every operation can start without delay.
irregularity.
Bolt installation takes less than 30
Drilling ahead of the tunnel face to
seconds, and provides full and imme- install bolts or grout as pre-reinforcement,
diate support along the entire hole is a common way of improving the rock
length, in ground conditions ranging quality before excavation takes place.
from the hardest rock to clay and Instead of relying on supporting the ground
even non-cohesive material.
The system speeds up rock rein-
following excavation, pre-reinforcement
forcement considerably and, over the increases rock strength prior to excavation.
years, has built up an enviable repu- There are several benefits to this. First,
tation for saving time and money, as a pre-reinforced rock mass will be less
well as providing a safer under- damaged, both by blasting and by the
ground environment for miners and
tunnellers alike.
elastic and non-elastic stress redistribution
In the tunnelling business, Swellex of the excavation process. Second, the
bolts are already accepted as the key rock mass is never without support, even
to better operational efficiency. Now at the split second following blasting of
they are ensuring higher advance the round. Third, the support can be
rates, productivity and quicker access
to orebodies in mines as well.
more active when installed early, rather
than passive when installed later. Fourth,
pre-reinforced ground will not deteriorate
Forward Stabilization Using or collapse as rapidly as a totally un-
Swellex supported excavation, allowing a safe
working period for installation of regular
In single-face development, high-speed support.
rockbolting obviously cuts the time to The Bieniawski diagram shows the rela-
completion. But in multiple face develop- tionship between the unsupported span and
ment or ore extraction, the objective is to stand-up time of an excavation with refer-
utilize manpower and equipment efficiently, ence to its rock mass quality. Empirical
as well as to advance the faces on observations have shown that, for a given
MINING WORLDWIDE
excavation size, a linear reduction in Rock stope exploitation, when production con-
Mass Rating (Bieniawski, 1974) will lead cerns may override ground support design
to a logarithmic reduction in unsupported concerns. The cohesive effect of the cable
stand-up time. Hence, a linear increase in is greater when added to undisturbed
excavation span results in a logarithmic ground than when added to weakened and
increase in instability potential. For large disturbed ground.
span drifts, the time period available to In tunnelling, the umbrella grouting
install roof support is significantly lower method of pre-reinforcement is frequently
than for small drifts. In the case of a 4.3 m- used. This method pre-supports the
span tunnel driven through poor to very planned roof area with steel rods. Large
poor quality rock, it may be logistically holes are drilled in the future roof peri-
impossible to support the roof before it meter, and grouted at high pressure with
collapses. Obviously, the operational and high strength, fine grained cement grout.
safety implications of such cases are Through each cemented hole, a smaller
important. hole is then drilled, in which a high-
Field observations show that cable bolts strength reinforcement bar is grouted.
installed in stopes before the first blocks Although highly effective for shallow tun-
are blasted are more effective than cable nels driven in very adverse ground condi-
bolts installed after the slot or cut has been tions, it is easy to see that such a
excavated. For cable bolts installed prior to work-intensive operation would be deemed
stope exploitation, the grout curing period neither practical nor economic for mining
is generally respected. This is not always applications, although the underlying con-
the case for cable bolts installed during cept could definitely be useful.
MINING WORLDWIDE
MINING WORLDWIDE
MINING WORLDWIDE
TUNNELS IN AUSTRIA
Removing Bottlenecks in
Austria
Crossroads of Europe Project: Parallel tube for existing bi-directional road tunnel.
Location: Graebern, on A2 Vienna-Klagenfurt highway.
With its position in the heart of Excavation method: Drill/blast and mechanical excavation.
Central Europe, Austria serves as a Contractor: Joint venture of Ostu Stettin, Hinteregger, and Porr
transportation hub for virtually any
business needing to move goods Tunnelbau.
across the continent. Rock: Mix of biotite gneiss and non-glaciated folded, faulted,
For traffic between the Balkan and tectonised strata.
States and the north, or diagonally Rock reinforcement requirement: Spiling followed by
across Europe from east to south, immediate face support.
Austria presents the shortest route.
Indeed, the risk of traffic nuisance is Rockbolts selected: Super Swellex and self drilling anchors.
such that trucks are currently banned
from its highways during the night
hours.
In its efforts to upgrade to full
European standards, Austria is build-
ing more dual carriageways, and
driving parallel tunnels for a number
of existing bi-directional tunnels across
the country. In the tunnels, the latest
in Atlas Copco technology is being
employed, including the Rocket
Boomer L2 C and self drilling anchors.
Two such projects are the parallel
tunnel recently completed at Graebern,
on the Vienna to Klagenfurt section of
the important A2 motorway which
connects Vienna with Carinthia and
Italy, and a twin tube tunnel project at
Steinhaus, located near Semmering, a
favourite skiing destination for the
Viennese.
TUNNELS IN AUSTRIA
TUNNELS IN AUSTRIA
KVARNTORP, SWEDEN
KVARNTORP, SWEDEN
Overcored Bolts
It was then decided to over-core two
Swellex bolts to establish their condition.
These were forwarded to the Swedish
Corrosion Institute for further examination.
All Swellex rock bolts are stamped with
an alpha-numerical identification. The
recovered bolts were marked 1.8 930125 B
STD Sweden, showing that this was a
1.8 m-long bolt manufactured in Sweden
on January 25, 1993. They were recovered
in mid-May, 2002, so were in the rock for
a little over 9 years.
At the Corrosion Institute, the rock cores
were removed and the bolts visually
inspected, after which cross-sectional pieces
Internal surface of bolt No 2 shows it However, it is still arduous and, as with were sawn out for more detailed inspection.
is practically free from corrosion. cement, there are high wastage factors. Observations by the investigating engi-
Both resin and cement grouting of rebar neer were that uniform corrosion on the
present the operator with a number of outside of the bolts was very small, less
installation quality concerns. These range than 0.1 mm-deep. Internal corrosion was
from inadequate grout in the hole or, as in mostly non-existent, with a few small shal-
the case of resin, “over-spin” or “under- low patches. One of the bolts had two
spin”, both of which adversely affect the small local corrosion penetrations that did
support capability of the installation. not affect the breaking strength.
NEVADA, USA
NEVADA, USA
NEVADA, USA
NEVADA, USA
Future Tunnelling
Further tunnelling since completion of the
ESF tunnel has included the 2.681 km-long
exploratory East-West Cross Drift Tunnel
across the potential repository. This
employed a 5 m-diameter Robbins hard-
rock TBM, which started at an intersection
Using the drill feed to press the screen confined space inside the bolt. A hole is with the North Ramp of the ESF and, after
against the rock while installing a then drilled in the lower bushing. When an initial curve, followed a tangential
Swellex rockbolt. the bolt has been positioned in the bore- alignment, and crossed over the proposed
hole, water is injected through the hole repository block west of the main loop of
drilled in the bushing, causing the tube to the ESF tunnel, to terminate in the
unfold. At 30 Mpa the bolt is full expanded Topopah Springs geological formation.
in the hole, and the pump automatically Once again, Super Swellex 1.8 m-long
stops. As the pressure inside the bolt rockbolts were used for ground support on
reaches 30 Mpa, the steel tubing adapts to a 1.2 m x 1.2 m grid over the full crown,
the shape of the borehole, and may consol- with welded wire mesh and 1.2 m-long
idate the surrounding material while it steel channels. A total of 20 steel sets was
expands to fit the irregularities of the hole. required in only one area of the tunnel,
The resulting frictional and mechanical where the Super Swellex bolts could not
interlocking reinforces and increases the provide long-term support. The TBM aver-
stability of the rock surrounding the drilled age advance was 25 m/day over 106
hole. mining days, with a best shift of 34.6 m,
When each batch of bolts arrived at site, best day of 73.2 m, and best week of
the Kiewit/PB Quality Control group car- 266.7 m. The TBM was mining for only
ried out thorough tests and inspections to 25% of the time, due to the concurrent
verify that they had not been contaminated scientific and environmental experiments
or damaged, and that the dimensions were being carried out.
according to the specifications. The design of the repository is not yet
Rockbolt drilling and installation was finalized. However, a system of tunnels
carried out at two stations on the TBM. At totalling more than 200 km is being
the first station, four Swellex bolts were discussed in which more than 1 million bolts
installed, together with the screen and the will be installed over a period of 20 years.
channel. At the second station three holes Following the signing of the Yucca
were drilled, and the remaining three bolts Mountain Resolution on 23rd July, 2002,
installed, including the bolt located at the the Nuclear Regulatory Commission is con-
highest point in the tunnel. The nominal sidering licensing the repository. ■
TUNNELS WORLDWIDE
TUNNELS WORLDWIDE
driven by drill/blast in a single direction early support, and 5% of these were ran-
from twin portals. domly tested at 10 t pulling pressure, as a
Top headings of 72 sq m section preced- routine stipulated in the contract.
ed the benches, advancing mainly in soft, Where immediate support is required,
mixed ground requiring a lot of support. Swellex rockbolts can be in place and pro-
The full, flattened ovoid section of viding full support up to seven hours
150 sq m was achieved with a 41 sq m earlier than conventional cement grouted
following bench, and a 37 sq m invert. bolts. This was invaluable in the softer
A total of eight Atlas Copco Boomer ground towards the ends of the tunnels,
352 drillrigs were used for face drilling, where pattern rockbolting was used.
rockbolting, and umbrella drilling. Face Elsewhere, in better rock conditions, the
drilling in the top headings was undertaken contractor favoured the system because
by two Atlas Copco 352 Boomers, stand- Swellex bolts are fast to install and offer
ing side by side. The added flexibility of guaranteed support. The consistent use of
the two-rig system speeded up the drilling top specification rockbolts was reckoned to
and charging process, to the extent that the improve the overall quality and integrity of
entire excavation cycle could be completed the tunnel.
in 2.5 h. This facilitated up to four rounds When the ground got too soft for con-
in each 24 h period, leaving 14 h available ventional excavation, two Atlas Copco
for support work and rock reinforcement, Boomer 352 machines equipped with drill-
much of which was scheduled for the night rod cassettes were available. These drilled
shift. 15 m-long holes around the periphery of
Heavy-gauge steel arches were set in the crown, using Odex eccentric bits and
the top headings, with two layers of Q378 extension drillrods. The holes were then
steel mesh and two applications of shot- lined with perforated steel tubes, through
crete to roof, sides and floor. A row of which cement grout was pumped to form a
4 m-long Swellex rockbolts was set in a protective umbrella. Beneath this umbrella,
22 m-long radial arch at the face to give a 12 m advance could safely be made.
TUNNELS WORLDWIDE
Hong Kong Cannot Wait Projects: Tai Lam tunnel–West Rail, 5.5 km, 110 sq m. Black Hill
and Pak Shing Kok tunnels, 20.5 km on the MTRC (metro),
Major new tunnelling operations in Hong
80 sq m.
Kong have used Atlas Copco drilling and
Location: Hong Kong, China.
bolting equipment fitted with the very
Excavation method: Drill/blast, full section.
latest computerized capabilities, together
Contractors: Nishimatsu-Dragages joint venture, Dumez.
with Swellex rockbolts and full service
Rock: Mainly hard rock, such as granite.
back-up agreements.
Rock reinforcement requirement: High productivity systems to
The 5.5 km, 110 sq m Tai Lam tunnel
speed up excavation.
on the West Rail development was a
Rockbolt selected: Standard Swellex.
Nishimatsu-Dragages joint venture, with
the two contractors driving the single
TUNNELS WORLDWIDE
TUNNELS WORLDWIDE
AlpTransit, Largest European Projects: Gotthard base tunnel, 57 km; Lotschberg base tunnel,
Tunnelling Project 34 km.
Location: Switzerland
Lotschberg was being driven from the Excavation method: Drill/blast, full section and top heading;
south by a 9.38 m-diameter TBM from the TBM 9.43 m diameter.
Raron portal and a similar machine from Contractors: Satco jv (Mitholz), MaTrans jv (Raron), Ast-
the Steg lateral adit. Both of these were Holzmann (Amsteg).
gripper TBMs, each equipped with work Designers: Consortium of best Swiss engineering and
platforms with anchor drills immediately consulting companies.
behind the face. Rockbolting and meshing Rock: Mainly hard rock such as granite, limestone, schist,
was undertaken 4.2 m behind the cutter- gneiss, granodiorite, amphibolite.
head, and this is followed by independently Rock reinforcement requirement: Safety; versatility to cope
operated shotcrete robots, which sprayed a with geology and load requirements; high productivity with
concrete lining over the crown. Yielding drill/blast and TBM; some rock bolts have to withstand rock
Swellex was installed to counter expected bursts.
problems of rockburst, caused by the Rockbolts selected: Standard Swellex, Super Swellex, Yielding
increased overburden in competent gneiss. Super Swellex.
In rockburst, the pressure builds up in the
rock around the tunnel perimeter, and can
yield explosively, causing dangerous Operations in the north were concentrat-
spalling. If the rockbolt is designed to take ed at the lateral adit at Mitholz, from where
up some of this swelling pressure, then the two faces were driven south, and one north,
bursting effect can be mitigated without using Atlas Copco Rocket Boomer XL3 C
compromising on support. three-boom rigs. These are each followed
Experience gained at Raron has been by a suspended trailing backup carrying
used to develop the new Swellex transformers, cable reels, ventilation fans
Manganese Line, which offers more load- and ancillary equipment. A full 8 m-wide x
ing capacity and enhanced elongation. 8.5 m-high face was drilled to 4.5 m depth
COP 1432 rock drills speeded up the for each blast. During and after mucking
drilling, and the easy and fast installation out, the blasted area was mechanically
of the Swellex bolts provided immediate scaled, and the roof and sides were shot-
support behind the TBM. The TBMs creted. Some 20-30 Swellex 3 m or 4 m
advanced an average of around 90 m/week. rockbolts were then installed into holes
TUNNELS WORLDWIDE
Table 1. Comparison of rock classifications methods. defined bedding, some clay content, and
zones of fractured and blocky rock. Rock
Class Bieniawski 1973 Deere 1969 Barton 1974 O-Norm
quality tends to change very rapidly, and
RMR RQD Q Class (3.9 m dia. TBM)
often from stroke to stroke of the TBM.
I 83 90 33.0 F1-F2 As a rock reinforcing tool, Swellex is
II 67 75-90 12.5 F3 effective over a particularly wide range of
III 52 50-90 8.5 F4 rock and soil types. In Ilbau’s table of rock
IV 29 25-50 1.5 F5 support for instance, Swellex is applicable
V 15 less than 25 0.09 F6 in all classes requiring rock bolts, from
class F1 to F6. By specifying Swellex, there
As part of its contract, Ilbau was respon- is no need to keep a stock of any other type
sible for the design of the pilot tunnel sup- of bolt on site. Together with its ease of
port. For more reliable estimating, and application and immediate support poten-
easier communication with its client, Ilbau tial, Swellex has the all-round advantage.
developed a rock class and support mea- In the first 1,918 m of the Alassio pilot
surement system specifically for TBM tun- tunnel, required support was mostly that of
nelling (Table 1). Adapted from established types F2 to F4, with 15% in type F5. Swellex
Austrian practice, the table not only consid- reinforcement over the same length averaged
ers the most appropriate rock support for about four bolts/linear metre, 60% of which
given rock conditions, but also specifies were 1.5 m-long, and the remainder 2.1 m.
where, and how quickly, the support should Support installed was about 10% more than
be installed. In better rock conditions originally estimated, with a corresponding
(Classes F1, F2 and F3) bolts, mesh and 10% reduction in productivity.
shotcrete could be installed from the work- Swellex, wire mesh and shotcrete were
ing platform without interrupting TBM used in fault zones where roof falls had
progress. In Classes F4, F5 and F6, support occurred. In other areas, thin layers of shot-
must be installed as close to the face as pos- crete spalled off, with small falls of rock
sible, and requires a halt in TBM advance. away from bedding planes. These created no
Class F7 constitutes rock with no self- serious safety hazards, and confirmed that
supporting capacity. In such conditions, Ilbau was installing adequate support for a
ground consolidation techniques, or full pilot tunnel, neither too much, nor too little.
lining support with ribs and timber lagging Rock support accounted for approxi-
or bolted liner plates, may be required. In mately 50% of TBM downtime on the
zones of extremely difficult ground, con- Alassio pilot tunnel, with most falling into
solidation and support measures ahead of support types F2 to F4, and 15% in type F5.
the TBM should be considered. To monitor the quantity and quality of
At Alassio, because of the potential support installed, the client’s consultant
impact on TBM utilization, the payment geologist visited the site about twice a
schedule for rockbolting and other support week. In addition, the consultant monitored
requirements varied according to where it geotechnical instrumentation installed by
was installed, with higher unit prices for Ilbau. Along the tunnel there were 15 con-
support installed close to the face, involv- vergence measuring stations, and three sta-
ing TBM downtime. tions containing three groups of 1.5 m, 3 m,
The client specified the use of Swellex and 4.5 m long extensometers in the crown
for rock reinforcement at Alassio, and sup- and into each wall, as well as five tangen-
plied the requisite bolts to Ilbau for installa- tial and five radial pressure cells. Data
tion. Although sometimes perceived as more gathered greatly assisted the main tunnel
expensive than alternative rock support and final support and lining designs.
reinforcement systems, the unit price of The TBM completed the 2,472 m-long
Swellex becomes substantially less signifi- pilot tunnel in eight months, working
cant when compared with the costs saved in 127 h/week on a 2 x 11 h shift/day, 5.5
labour and TBM downtime. The easy han- days/week, and broke through on schedule.
dling of Swellex is welcomed by tunnelling Average advance was about 15 m/day, with
crews, and its geomechanical properties and a best advance of 53 m/day in class 2 rock,
speed of installation are attractive to consult- installing 110 bolts, mainly from the backup
ing engineers, clients and contractors. platform. This was close to the optimum
Alassio geology comprises mainly soft, 60 m/day achievable in a short tunnel oper-
dry, non-abrasive calcareous marls with ating a single track muck hauling system.
WORLDWIDE HYDRO
WORLDWIDE HYDRO
Economical Support Solution will harness the flow of the Jhelum river,
and its 480 MW turbines will supply
at Uri much-needed electricity to the region.
The Uri project is located in the foothills Urico contractors, a design/construct
Atlas Copco Boomer H178 face drilling of the Himalayas, in the Kashmir Valley of joint venture led by Skanska and NCC,
at Uri hydro scheme. northern India. The new hydropower plant employed six Atlas Copco Boomer H178
drillrigs on the development of 22 km of
tunnels at Uri. The Boomer H178, with its
three booms, was selected as the most flex-
ible machine available to excavate faces of
cross-sections between 25 and 100 sq m,
together with the 22 m-wide machine hall
cavern. Average progress in the tunnels
was 250 m/week, with a best week of
278 m. Atlas Copco assisted the contrac-
tors with an extensive training programme
to teach the local employees how to
operate the rigs.
Rock reinforcement at Uri consisted of
shotcreting and bolting, with Swellex com-
prising 75% of the bolts used. The drillrigs
were used for all rockbolting work,
installing 700 x 3 m-long bolts/week.
Swellex was chosen wherever possible,
because they are quicker to install, and
more economical overall, than grouted
WORLDWIDE HYDRO
WORLDWIDE HYDRO
WORLDWIDE HYDRO
Rock Mass Stabilization at Project: Tala Hydro on Wangchu river, 1,020 MW.
Tala Hydro Client: Tala Hydro Power Authority (THPA).
Location: Wangka, Kingdom of Bhutan.
Tala Hydro scheme has been constructed Excavation method: Drill/blast.
in the remote Himalayan kingdom of Contractors: Jaiprakash; Hindustan Construction; Larsen &
Bhutan, using more than 40 items of capi- Toubro.
tal equipment supplied by Atlas Copco. Rock: Gneiss with quartzite bands and biotite schists.
The dam site is about 85 km by road from Rock reinforcement requirement: Roof support.
the border with India, and is located near Rockbolt selected: MAI SDA.
the village of Wangkha, on the Wangchu
river, some 3km downstream of the exist-
ing Chukha tailrace outfall. achieved up to 30% longer life than
Hindustan Construction found MAI expected.
anchors were crucial for stabilization of Hindustan Construction used MAI self
the walls of the desilting chambers at Tala, drilling anchors (SDA) for stabilizing the
and as primary support during excavation reinforced concrete wall of desilting
of the Head Race Tunnel (HRT). The same Chamber No 3. The wall of the chamber
anchors have also been found to be very was anchored to the deeper competent rock
useful in reducing pore water pressure using one row of 114 MAI SDA with 20 m
behind the support system. length and 38 mm-diameter at 3 m centres,
Major features of Tala are: three desilting and another row of 36 MAI SDA with 24
chambers sized at 250 m x 13.9 m x 18.5 m; m length and 51 mm-diameter at 3 m cen-
a 22.97 km-long, 6.8 m finished diameter, tres. 32 t pull out tests conducted on the 38
50 sq m modified horseshoeshaped, con- mm-diameter and 20 m-long MAI SDA
crete-lined headrace tunnel (HRT); and an resulted in displacements of 11 mm and 17
underground powerhouse 206 m-long by 19 mm respectively, well within specification.
m-wide and 45.5 mhigh, with transformer Hindustan Construction used the
cavern 191 m-long by 16 m-wide and 27 m- Drainage, Reinforcement, Excavation,
high. The HRT, which has been excavated Support Solution (DRESS) in the 330m-
at 7.5 m-diameter with rock cover of 60 m long section of HRT affected by adverse
to 1 km, utilized five construction adits. In geology in Package C4. Here, MAI SDAs
the tunnels, Atlas Copco Boomer 352s were were used both as radial bolts and as
used in rock classes 1, 2 and 3, where the drainage elements, in combination with
average advance was 120 m/month, and in Odex Piperoofs. For anchoring steel arches,
class 4 rock up to 70 m/month. Class 5 SDA of 8-12 m lengths were installed in a
rock, which had to be fully ribbed at 60-75 systematic pattern. If no water seepage
cm intervals, strutted, bolted, meshed and resulted, they were grouted. Two 38 t pull
shotcreted, slowed advances to 30 m/month. out tests were conducted on 38 mm-diame-
The Atlas Copco Secoroc button bits were ter, 8 m-long MAI anchors to check the
reported by the contractors to have efficacy of grouted anchors in the poor
strata in the HRT. These passed, with dis- Atlas Copco Boltec 435H at work in
placements of 16 mm and 22.8 mm.■ Tala headrace tunnel.
S.D. Jeur, Project manager, Hindustan Construction
Company, C4 Package used Atlas Copco Odex for
piperoofing, in combination with MAI SDAs, to make
tunnelling possible through soil.
MAINLAND JAPAN
MAINLAND JAPAN
SDA WORLDWIDE
SDA WORLDWIDE
SDA WORLDWIDE
are drilled ahead of the face, using casing. Installing 6 m-long SDA at Pakuashan.
Excavation is by backhoe, with a ripper for
profiling.
Presupport consists of 3 m-long fore-
poling using SDA around the arch and
sidewalls at 0.5 m spacing. Lattice arches
are then set at 1 m centres, and 4 m and
6 m SDA cement grouted rockbolts
installed, along with two layers of wire
mesh and 300 mm of shotcrete. A layer of
wire mesh and 200 mm of shotcrete are
laid on the floor of the top heading as
temporary support.
This is the first use of SDA in Taiwan.
One in 50 of the installed bolts is subjected
to a 17.6 t pullout test.
Maximum advance on a top heading has
been 3.3 m/day of 24 h, and the site works
7 days/week. Around 800 m from the por-
tals, the faces moved from compacted
gravel into sand with very little cohesion, in the centre of the alignment using NATM
slowing advance rates considerably. techniques, allowing four more faces to be
Effectiveness of the support regime is opened, and facilitating dewatering.
measured using arrays of convergence A 400 mm-thick cast concrete lining
bolts installed at 20 m intervals. There is with waterproofing membrane and drainage
also a cross section of extensometers at system will be installed as final support.
200 m intervals which measure at depths The mechanical behaviour and engi-
of 3 m, 6 m, and 9 m into the profile rock. neering characteristics of the gravel forma-
Every 500 m, radial pressure cells and tion are related to the degree of
strain gauges are installed in the shotcrete, cementation of the matrix and the percent-
together with measuring anchors to record age gravel content.
stress and strain in the ground. Results Based on the monitoring data, maximum
from all three sets of stations are analyzed crown settlements of about 400 mm have
and compared to theoretical behaviour. been observed in areas of fine sediments
In addition to the main tunnels, there with ground water, while in sections with
are nine pedestrian cross passages, three dense gravel, 50 mm is typical. Maximum
vehicle cross passages, and ten emergency shotcrete stresses of 150-200 kg/sq cm
parking bays. A 240 m-deep x 10 m-diam- have been measured, within the design
eter ventilation shaft has been constructed shotcrete strength of 210 kg/sq cm.
SDA WORLDWIDE
Swelling Clay
The Göggelsbuch tunnel runs exclusively
in the Feuerletten layer, with between 4
and 20 m of Feuerletten overhead. The
clay comprises a clay stone with fine to
medium sand, which is locally interrupted
by up to 5 m-thick sequences of pure sand-
stone, and by up to 10 m-thick sequences
with alternating sandstone and clay stone.
The layers of Feuerletten are usually
orientated horizontally.
The swelling of the clay, and the pres-
sure exerted, have been examined and ana-
The 35 km-long northern section of the lyzed precisely. All the tests demonstrated
railway line, including the Göggelsbuch that the pressure due to swelling, in con-
tunnel, is under construction by a joint nection with the hydrostatic load, was not
venture of Bilfinger Berger and Max Bögl. decisive in calculating the internal lining.
It has a reinforced concrete lining vary- Groundwater-filled layers of sandstone,
ing between 75 and 125 cm in thickness at and impermeable layers of clay with
the invert, and which is a constant 35 cm- groundwater flowing on them, were pre-
thick in the arch. A single 3 mm layer of sent during the complete advance works.
polyethylene membrane helps to seal the After the whole tunnel had been excavated,
tunnel lining against a water head of 30 m. an underground water flow of 5 l/s was
The anchorage systems used in the con- measured.
struction of the tunnel comprised 4 m-long Construction was from May, 1999 until
SN anchors and Hollow Bolt Type MAI September, 2000, advancing simultaneous-
anchors with varying lengths. Dywidag ly from both north and south portals. The
Systems International (DSI) supplied both top heading forming the crown was holed
systems. The DSI hollow bolt anchor type through before the bench and invert were
MAI is optimally used wherever geologi- started.
cal conditions would normally require Concrete lining, from south to north,
cased drilling to place anchoring or nailing took some five months from December,
elements. Its advantage lies in the simplic- 2000 with one wagon for the invert form-
Supporting the face at Göggelsbuch. ity of the system, the flexibility in its work, carrying two forms. Two separately
running forms were used for the crown
lining, which took another 4-5 months.
Supporting Production
The rock was excavated using a tunnel
excavator along its entire length, with a
hydraulic breaker in sections with thick
layers of sandstone. The advance per sec-
tion was limited to 1.3 m. The tunnel was
secured with a 20-35 cm-thick layer of
site-mixed shotcrete, and 4 m-long x
25 mm-diameter SN anchors were installed
for systematic rockbolting.
The crown invert was supported with a
temporary shotcrete layer to minimize
movement. Trials without the temporary
support showed unpredictable results, and
the roof above the crown had to be
SDA WORLDWIDE
strengthened over a length of 50 m, due to The excavation of the bench and the
excessive movement. invert of the tunnel were subsequently
While advance from the south pro- completed in about the half the scheduled
gressed with hardly any problems, the time, catching up on the contract.
north drive suffered poor face stability.
Despite continuously increasing the dens- Acknowledgements
ity of support, a face collapse occurred in
July, 1999. The supports that were Thanks are due to Thomas Müller of
installed at that time were: 30 cm of shot- Bilfinger Berger, and Frank Schmidt of
crete in the arch; 20 cm of shotcrete on the DSI, for describing the construction
arch invert; system anchorage with 4 m- process. Excavating the bench at Göggelsbuch.
long SN anchors, at 7 units/m; 10 cm of
reinforced shotcrete on the working face;
8 m-long MAI R32 face anchors, at 9 units
per section; and 6 m-long MAI R32 rods,
at 35 units/m.
It was decided to keep the same types of
support, but those guaranteeing the stability
of the working face were intensified. The
length of the MAI face anchors was
increased to 12 m, and the number doubled
to 18 per round. The length of the MAI
R32 steel rods was also increased from
6 m to a maximum 8 m. This intensified
system of face support was installed over a
length of 500 m, once the collapsed face
had been cleared. No further collapses
occurred on the remaining crown drive,
which was completed without further delay.
KEMI, FINLAND
market that has risen by an average of 5.5% EAR4 115 Repair shop FAR2
EAR3
KEMI, FINLAND
KEMI, FINLAND
KEMI, FINLAND
Rock Reinforcement
Swellex Mn12 2.4 m-long bolts are used for
support in ore contact formations. These are
being installed at a rate of 80-120 bolts/shift
using an Atlas Copco Boltec LC rig, which risk of cement entering the rock drill, thereby Atlas Copco Cabletec L installing cable
is returning drilling penetration rates of 3.2 reducing service and maintenance costs. bolts at Kemi.
to 4 m/min. The CAN-bus controlled LC rig Kemi tested the prototype Cabletec L
mounts the latest Swellex HC1 pump, for and eventually purchased the unit after
bolt inflation at 300 bar pressure, and minor modification proposals. During the
reports progress on the operator’s screen. testing period, where most holes were in
The HC1 hydraulic pump is robust, the 6 to 11 m range, the rig grouted and
simple, and with low maintenance cost. installed cables at rates of more than 40
Coupled to an intelligent system, it reaches m/hour. The capacity of the unit, which is
the 300 bar pressure level quickly, and governed by the rate of drilling, provided
maintains it for the minimum time for per- around 50 per cent extra productivity com-
fect installation. Combined with the rig’s pared with alternative support methods.
CAN-bus system, the pump can confirm The Cabletec L is equipped with a COP
the number of bolts successfully installed 1838 ME hydraulic rock drill using
and warn of any problems with inflation. reduced impact pressure with the R32 drill
Over 50,000 bolts have been installed to string system for 51 mm hole diameter.
date without problems. The machine’s cable cassette has a capac-
A series of slip-pull tests carried out ity of 1,700 kg and is easy to refill, thanks
throughout the mine proved the strong to the fold-out cassette arm. It features
anchorage capacity of Swellex Mn12, both automatic cement mixing and a silo with a
in the orebody and for the softer talc- capacity of 1,200 kg of dry cement, which
carbonate and mylonite zone. is mixed according to a pre-programmed
formula, resulting in unique quality assur-
Cable Bolting ance for the grouting process.
Kemi installs some 80 km of cable bolt each Bench Cut and Fill
year using its Atlas Copco Cabletec L unit,
which is based on the longhole production The current mining method is bench cut and
drilling rig Simba M7, with an added second fill, a type of sub-level stoping with down-
boom for grouting and cable insertion. The hole production drilling, in which primary
Rig Control System (RCS), enables the oper- stopes are 25 m high, 15 m wide and
ator to pay full attention to grouting and between 30 and 40 m long. Using a Rocket
cable insertion, while drilling of the next hole Boomer L2 C rig, the drifts for the primary
after collaring is performed automatically, stopes are developed laterally from the
including pulling the rods out of the hole. footwall through the ore zone. Then a Simba
The main benefit of the two-boom concept is M6 C production rig drills down 51 mm
to drastically reduce the entire drilling and diameter blastholes in fans 2 m apart. Each
bolting cycle time. Also, separating the stope yields between 25,000 and 35,000 t of
drilling and bolting functions prevents the ore.
KEMI, FINLAND
LOTSCHBERG, SWITZERLAND
LOTSCHBERG, SWITZERLAND
LOTSCHBERG, SWITZERLAND
LOTSCHBERG, SWITZERLAND
North Completion
In the north, probeholes were maintained
40 m ahead of the face, drilled in the
crown by one of the Rocket Boomer XL3
Cs equipped with a RAS rod adding
system. Detection of methane would trig-
ger a warning system on the drillrigs, and
the monitoring system on the suspended
Buckled arch with emergency backup would switch off HT electrics if a
retaining bolts. dangerous concentration were encoun-
tered.
Tunnelling at the north face was com-
pleted in May 2003, some 8 months ahead
of programme, as a result of which Satco
was awarded a further contract to excavate
some 800 m of the west tube from the
Frutigen portal. All cross passage excava-
tion between the east tube and the TBM
tunnel is now complete.
The main concrete lining operation
went well in the north drive, where pair of
12.5 m formworks returned 25 m/day of
completed lining. Concrete lining is pro-
ceeding apace in the south drives.■
Tungsten carbide bit used along with EYY type with
MAI SDA at Mitholz. Acknowledgements
carboniferous section would run out after Atlas Copco is indebted to Satco and
another 50 m in the west face and 10 m in Alptransit Lotschberg for permission to
Section of Lotschberg tunnel from the east face, following which there would be publish this article and, in particular, to
Frutigen to Raron. The unexpected a transition to comparatively good sandstone. Wolfgang Lehner of Strabag, project man-
area of soft sedimentary rock is It was decided to reline the deformed ager at Mitholz, for his assistance with
delineated by red dotted lines. tunnel in sections 50 m-long, installing interviews and site visit.
ZINKGRUVAN, SWEDEN
Mechanized Bolting at
Zinkgruvan
Partners in Production
Zinkgruvan Mining AB, Sweden’s
third largest mining company, is a
part of Lundin Mining Corporation.
Zinkgruvan Mining produces zinc and
lead concentrates for shipment to
smelters in northern Europe.
The mine has been continuously in
production since 1857, and ore output
now stands at about 835,000 t/year,
together with 185,000 t of waste
from development.
Production is obtained from open
stopes where, following difficulties
with seepage from hydraulic fill
when rock quality diminished, the
mine now uses paste fill. Rather than on a 2 x 7 h shift basis. The mine has an Atlas Copco Rocket Boomer L2 C
deepen the main hoisting shaft, the option to purchase a second twin-boom developing the sublevels.
main ramp access was developed Rocket Boomer, this time an M2 C, which
below the 800 m level, and will
bottom out at 1,100 m under present
is the mining version of their existing L2 C.
plans. Key to Zinkgruvan production
efforts is equipment supplied by Rock Reinforcement
Atlas Copco, which includes four
Simba production drillrigs, three The mine installs up to 20,000 resin
Rocket Boomers and two Boltec rigs,
together with maintenance and con-
anchored rockbolts each year, and, having
sumable supply contracts. upgraded its production process, found that
bolting became the new bottleneck. After
prolonged testing of the latest Atlas Copco
Lower Development Boltec LC, they ordered two units.
Using these machines, the working
In order to mine below the 800 m level, the environment for the bolting operatives has
mine uses three Kiruna Electric trucks for improved immeasurably, since the continu-
ore and waste haulage to the main crusher. ous manual handling of resin cartridges
A Simba M4 C longhole drilling rig is has been eliminated. The Boltec LC is a
used on production, drilling up to 40 m- fully mechanized rockbolting rig with
long x 76 mm or 89 mm-diameter blast- computer-based control system for high
holes. The machine produces some 50,000 productivity and precision. The Zinkgruvan
drillmetres/year, while an older Simba models feature a new type of magazine
1357 drills a similar number of metres in holding 80 resin cartridges, sufficient for
the 51-64 mm range. The mine is so installation of 16 rockbolts before refill. It
impressed with the stability of the Simba is equipped with a stinger, which applies
M4 C rotation unit that it has had an old constant pressure to keep it stable at the
Simba 1354 rebuilt to incorporate the same hole during the entire installation process.
unit. A Simba M7 C is being delivered for The operator can select the number of resin
cable bolt drilling. The drilling consum- cartridges to be shot into the hole, for
ables are supplied by Atlas Copco Secoroc which the rig air capacity is excellent.
under contract. The ramp will be driven
from the current 980 m to the 1,100 m level. Vital Combination
An Atlas Copco Rocket Boomer L2 C is
used on ramp and sublevel development, The Rig Control System (RCS) features an
where the requirement is for 18 rounds/week interactive operator control panel with
ZINKGRUVAN, SWEDEN
Acknowledgements
This article is based on a paper written by
Gunnar Nystrom. The editor also grate-
fully acknowledges the inputs of Jonas
Sodergren, Hans Sjoberg and Conny
Ohman, all of Zinkgruvan Mining.
BOLU, TURKEY
BOLU, TURKEY
Design Philosophy
When the Bakacak fault was recognized as
active, almost one year after the Duzce
event, the restoration of the original tunnel
was almost complete, and the shape and
type of the cross section adopted was
already defined. The bench pilot tunnels of
the original excavation had already been
backfilled.
BOLU, TURKEY
BOLU, TURKEY
Acknowledgements
Atlas Copco is grateful to the management
of the Bolu project for permission to visit
the site, and to Olivio Angelini, Gaetano
Germani and Aziz Õzdemir of Astaldi for
their help and assistance in preparation of
this article. Reference is made to Design
and Construction of Large Tunnel Through
Active Faults: a Recent Application by
M Russo and W Amberg (Lombardi
Engineering), and G Germani (Astaldi).
Stabilizing Foundations
in Baltic Cities
Ancient and Modern
The Baltic States of Northern Europe
have done well to preserve most of
their historic buildings, some dating
from the Middle Ages. However, subsi-
dence is now the main enemy in Riga,
Latvia and Tartu, Estonia, where the
race is on to underpin the buildings
most affected. This is being accom-
plished with minimum intrusion using
micropiling techniques, in which MAI
SDA and grout pumps are the key ele-
ments. Similar techniques are also
being used to great effect in Riga coal
docks, where the sheet piling of the
dock wall is being secured using long
grouted SDA while the harbour is
deepened. The diversity of these jobs
highlights the flexibility of MAI SDA as
an essential construction tool.
concrete cladding and the steel sheet Barge-mounted drillrig installing
pile. Then 47 m-long, 130 mm-diameter 48 m-long MAI SDA anchors at
Riga docks.
Riga Coal Dock holes were drilled 40 degrees below hor-
izontal through the surface sand to pene-
Riga coal dock handles a million t/y of trate the sandstone bedrock below. Each
coal from the Kuzbas region of Russia, and drillstring comprised a cross bit with 16
is looking to expand its business by using x 3 m-long threaded MAI T76 bars and
larger ships, for which the harbour has to 15 couplings. Continuous grout injection
be deepened. was carried out at 40-60 bar pressure in
It was necessary to anchor the existing the 4 h-long drilling operation, during
dock walls to solid ground prior to the which retarders were used to keep the
dredging operation, following which a cement workable.
new, deeper wall is being installed. Atlas A week later, a plate and nut were
Copco MAI anchors are being used as both screwed onto the protruding end of each
temporary and permanent support for the anchor, and stressed up to 60 t. Some 120
sheet piling operation. anchors were required for the first stage,
Their installation is being carried out by and these were installed in a horizontal line
the marine construction division of BMGS, above the high water mark at 3 m intervals.
a Latvian specialist contractor. This allowed dredging of the dock from its
The first stage involved anchoring the previous depth of 10 m to 13.5 m. Each
upper section of the existing steel sheet anchor was pull tested at 90 t.
piles by drilling from a purpose-built barge Sheet piling operations then took place
floating in the dock, an operation which during the winter 2004/2005, along the line
carried on 24 h/day, 7 days/week whenever of the new dock wall, which is around a
the dock was free. The barge had to be metre seawards from the previous position.
towed out of the way every time a coal The annulus between the two walls is
ship tied up. being concreted.
At each anchor position, a 150 mm- The second stage of anchoring is being
diameter cored hole was drilled 1.5-2.0 undertaken in 2005, using the same princi-
m into the dock wall to penetrate the ples as for the first stage. In this case, the
Saving Riga
FORE, a leading Baltic micropiling con-
Installing MAI SDA using a handheld pneumatic tractor, has underpinned a number of
jackhammer. ancient buildings and office blocks in Riga
Old City.
situated, possibly conveniently close to the To support the new Hotel Man-Tess,
cement storage. FORE installed 200 micropiles to 8-9 m
The pullout force for a micropile is less using MAI R38. The 200 year-old adjacent Atlas Copco ROC 712HC used by FORE
than its load bearing capacity, so a building was supported by 114 mm steel to install MAI SDA.
hydraulic testing jack can be used to check
that any pile has achieved its design
capacity, without influencing its function.
Overall, micropiling offers a dependable,
fast, low-technology, and low intrusion
method of underpinning buildings, and
the drilling techniques used penetrate
both wood and masonry without prob-
lems.
L above: Ancient warehouse in Old Riga pipes installed to 8 m depth at half-metre block, which is being converted to offices
was saved by underpinning. spacing using an Atlas Copco 712HC drill- and flats. The piles are 15 m deep and 15
R above: Subsidence was arrested on rig, and filled with concrete. These were degrees from vertical, and designed to pass
the six-storey Pikadilja Cafe. then secured using 15 m-long MAI through the mud layer and penetrate 1 m
anchors drilled at 7 degrees from horizon- into the sand layer beneath. MAI R38 SDA
tal, each providing 30 t of anchoring force. grouted by an MAI M400 grout pump pro-
At Pikadilija Café on Valnu Iela, close duced high friction piles.
to the Opera House, the six-storey struc- A 14th Century grain warehouse in
ture has been subsiding into the very soft Aldaru Iela was underpinned by FORE in
deltaic riverine deposit, and needed stabi- 2002 using MAI R38 SDA to produce
lization before refurbishment. The crosspiles. The subsidence was arrested,
ground is non-supporting, and the and the building, situated close to
micropiles are designed to take the whole Parliament House, was refurbished.
weight of the building at around 20-25 In a totally different application, FORE
t/unit. is installing MAI R38 8 m-depth grouted
Located on the same street as Pikadilija anchors to provide stable foundations for
Café, the Terranova building has been new high-voltage electricity pylons cross-
underpinned by FORE using 350 ing Riga docklands.
micropiles formed from MAI R38 self
drilling anchors to 9 m depth grouted using Preserving Tartu
an MAI M400 grout pump at 25 bar pres-
sure. Work was undertaken from both the Tartu City Hall has been successfully
street and basement of the building to pro- underpinned using micropiling techniques
duce crosspile support. developed by local contractor Mikrovai,
In Valnu Street, FORE installed 350 and installed using Atlas Copco MAI SDA
micropiles in the basement of the existing self drilling anchors.
covered up to form the gardens of some of Setting out the embankments in the
central part of the housing
Daventry Development the new properties.
development. In the background soil
Most UK inland soil nailing applica-
tions are classified by geotechnical engi- nailing is progressing on the section
The main development contractor at
already marked out.
Daventry is a joint venture of Thomas neers as low-risk, lightly loaded, passive
Vale Construction (Site Manager Dave installations with a design life of 60 or
Casey) and Westpoint Construction, 120 years. Exceptions are coastal areas
tasked with building 26 houses, five pairs where the effect of saline water is signifi- Installing soil nails in one of the
of flats and two bungalows on the site. cant, or in other aggressive ground condi- development service road
The housing development is on a wedge- tions. embankments.
shaped, sloping site comprising a relative-
ly soft clay mix which, if developed by
conventional means, would probably
necessitate the excavation and construc-
tion of expensive deep foundations for the
houses and service roads. As facilitated by
the MAI Anchor soil nailing method, the
site has been terraced with embankments
supporting the service roads at the end of
the gardens of adjacent new properties.
The soil nails are installed by drilling into
these embankments at 15-20 degrees. A
substantial development cost saving will
result.
At the lower end of the site local condi-
tions over a short length did not permit the
creation of an embankment, so here the
MAI SDAs were inserted directly into a
level surface which would eventually be
MAI SDAs
The self-drilling anchors used by Keller at
Daventry were of the R32N hollow rope-
threaded bar design with 100 mm-diame-
ter, open-face, retroflush sacrificial drill
bits suitable for clay. The left-hand thread
allows connection to standard drill tooling.
The bar, measuring 32 mm diameter over
the threads or effectively 29.1 mm has an
ultimate strength in this size of bar of 280
kN and yield strength 230 kN.
MAI SDAs can be installed in unstable
ground without the need for temporary hole
casing by simultaneous drilling and grout-
ing. Depending on the type of bit used, they
are suitable for a wide range of ground
materials including soft clay (as at inclined 15-20 deg and at right angles to the Keller Ground Engineering’s Site
Daventry), sand, gravel, inconsistent fill, tracks, permitting the rig to be driven along Agent, John MacGregor Jr., views the
boulders, rubble, and weathered and frac- the row of soil-nails to be installed. The installation of some of the last soil
tured rock. drill bit and rotation speed are chosen to nails to be installed in the lower part
of the site.
ensure that the borehole is cut rather than
Installation
At Daventry, the consulting engineer’s
ground reinforcement pattern called for
soil-nail lengths of 5-13m depending on
their position on the site. This is achieved
by using coupling sleeves to connect the
standard lengths of threaded bar. In all
750-760 soil nails are being installed at
Admirals Way.
A surveyor first lays out each portion of
the site to be reinforced using red-painted
markers to indicate the planned entry
point for each soil nail according to the
design of the consulting geotechnical
engineer.
Keller used two of their own crawler-
track, hydraulic, rotary drilling rigs to
install the SDAs, generally with the boom
Reinforcement is complete with a
layer of geomat secured by SDA nuts
and plates holding fine wire mesh.
UNITED KINGDOM
UNITED KINGDOM
PORTE-TURIN, ITALY
Mixed Ground in rock comprising gneiss-greenstone and Reinforcement of the slope by the
gneiss mica-schist belonging to the meta- eastern portal of the La Turina tunnel
The project designer for the underground morphic substratum of the Cristallino with 4 m-long Swellex Mn 16
work is Geodata SpA of Turin, for the Massif of the Dora Maira. rockbolts.
client, a consortium known as Agency of Swellex rockbolts were used both
XX Winter Olympic Games of Turin 2006. underground for primary support, and to
The contractor, Baldassini and Tognozzi reinforce the rock walls above the eastern
SpA Costruzioni Generali of Firenze, Italy, portals of the tunnels.
is using drill/blast techniques in the rock
sections of the alignment, and a hydraulic Slope Stabilization Reinforcement of the slope at the
hammer in the loose ground. eastern entrance of the Craviale tunnel
Rock reinforcement is required to improve The geo-structural survey carried out on the using 6 m-long Swellex Mn16
the quality of the rock, for which Swellex Mn slopes housing the portals showed that the rockbolts.
16 rockbolts in lengths of 4 m and 6 m have
been used for supporting the portal area.
Project Description
The project for the diversion of the Colle
del Sestriere state road N23 is taking place
near the town of Porte, approximately 40
km from Turin, in the upper Chisone
Valley of the Piedmont Region.
In addition to embankments and dry
bridges along the river Chisone, two
single-tube, bi-directional natural tunnels
are being built, La Turina with a length of
601 m, and Craviale with length of 991 m.
La Turina tunnel is being driven partly
in rock and partly in softer ground, where-
as the Craviale tunnel was driven entirely
PORTE-TURIN, ITALY
Valik, Plzen
Valik tunnel is situated about 30 km from
the German border on the Czech Republic
section of the Prague-Nürnberg motorway.
Overall length of the tunnel is 380 m, com-
prising 330 m of natural tunnel, with 20 m
of cut-and-cover at the west end and 30 m of
cut-and-cover at the east end. There is also a
900 m-long surface cutting at the east end to
connect with the advancing motorway.
The natural tunnel is complicated by
shallow cover and a very narrow corridor with reinforced concrete before the main Atlas Copco Rocket Boomer L2 C
of surface rights beneath which it has to be tunnel drives could commence. starting south tube at Valik tunnel.
excavated. The twin tubes have to be The central pilot tunnel, within which the
extremely close together, requiring buttress reinforced concrete buttress for the main
to be excavated and replaced in entirety tunnel was constructed, was excavated from
the west end within a 4.5-month timespan.
It was driven as a 4 m-high top heading and
Symmetrix or Odex?
2 m bench, using an Atlas Copco Rocket
Boomer L2 C, one of two at site. Main con-
Both Symmetrix and Odex can be used
tractor Metrostav also has one Atlas Copco
for drilling holes up to 273 mm diameter,
Rocket Boomer 352 at Valik, together with
when the choice of bit will depend upon
four GIA DC16 service platforms based on
the specific ground conditions, the pres-
Atlas Copco carriers.
ence of rock and boulders, and the rig to
Excavation was in increments of 0.8 m,
be used.
1.0 m, and 1.2 m, depending upon the spe-
For shallow holes in soft ground, Odex cific ground conditions, and lattice girders
is cheaper to use, a little slower, will were set at similar intervals. In very soft
require more torque, and may deviate if ground, an excavator with scaling bucket
hard boulders are encountered. or hydraulic hammer was used instead of Valik tunnel west end showing south,
However, a skilled driller will overcome the drillrig. pilot and north tube excavations.
these conditions.
Main Tunnels
Main tunnel excavations are being under-
taken sequentially using NATM tech-
niques. This involves top heading and
Buttress formworks inside Valik pilot Immediate support was provided by 4 bench excavation of the outside shoulders
tunnel. m-long Atlas Copco Swellex Mn12 rock- of each tube using lattice girders, MAI self
bolts, with shorter 3 m versions being used drilling anchors SDA R 25 150kN in 3 m
in the stronger rock sections. Some 3,000 and 4 m lengths, and shotcrete.
of the longer units were installed, along The north tube is being developed in
with some 2,000 of the 3 m version. Up to advance of the south tube. Depending on
25 Swellex bolts were installed for each the geology, up to 27 SDA are being
metre of advance, with shotcrete being installed into each fan or profile, with a 1
applied systematically to roof and side- m distance between fans.
walls, and to the face when necessary. This is followed by two-phase excava-
tion of the upper sections of each tube to
Concrete Buttress form the main tunnel roofs, and then the
remaining bench can be removed to con-
The construction of the concrete support struct a curved invert. During the process,
buttress between the two tubes of the main the area above the concrete buttress is
tunnel required foundation works through being grouted for consolidation, to promote
four separate soft ground sections, com- transfer of the ground pressure away from
prising a total of 90 linear metres. To the main tunnel lining. The remaining ele-
improve the footing in these areas, 6 m- ments of the pilot tunnel lining are being
deep micropiles were installed in rows of removed on advance. The final lining of the
four and three at 1 m spacing. tunnel will comprise reinforced concrete of
Section of Valik tunnel showing This work was undertaken by a specialist varying thickness from 0.3 m to 0.5 m.
concrete buttress between main
subcontractor, who drilled 123 mm vertical Sitina tunnel is on schedule to open for
tubes.
traffic in August, 2006.■
Acknowledgements
Atlas Copco is grateful to Banske Stavby
engineers Vladimir Kotrik, Anton Sumerak
jr and Anton Petko for permission to
extract from their paper Technological
Procedure of Construction for the Sitina
Tunnel, and to Metrostav engineer
Miloslav Zelenka, manager at Valik tunnel,
for his assistance at site.
OSLO, NORWAY
Systematic Grouting at
Oslo Subway
Half Century Progress
The T-Baneringen project is the
biggest enlargement of the Oslo
Subway since the system got under-
way in the 1960s. It comprises sever-
al new subprojects, of which the first
to be undertaken is the section from
Ullevål Stadium to Storo. The align-
ment of the 1.24 km-long tunnel, with
a cross-sectional area of 65 sq m,
passes through a very difficult zone
between sections 700 and 750, which
called for an intense grouting opera-
tion.
Contractor Veidekke chose the lat-
est grouting technology from Atlas
Copco Craelius to handle this chal-
lenge, where absolute control over
the efficiency of the grouting opera-
tion was key to its success. The
Unigrout EH 400-100-90 WBC
described in this report proved to be guide the grouting operation. Leakage Ramp entrance to Oslo Subway tunnel
must be measured and recorded, and leak- development.
the right machine for the job in every
respect. age per drill hole must not exceed 10
lit/min. The grouting stop pressure is set at
35-45 bar.
Grouting Contract Leakage<100 l/min drillhole. Stop pres-
sure 40-50 bar and be standing for 5 min.
The contract differentiated between sys- There is a difference between leakage
tematic and sporadic grouting, with pay- per/min/100 m tunnel and leakage/min/
ment according to work and material drill hole.
quantities. The main components were: In Sweden, the leakage/min/100 m of
drilled metres for investigation; grouting tunnel the most important, while in
and check holes; quantities of cement; Norway leakage/min/drill hole is more
numbers of packers; and the working hours popular.
for the grouting operation. The total inflow of water in the tunnel
The systematic grouting procedure as was measured at 14.9 l/min/100 m. The
laid out in the contract included following: specification was set at 7 lit/min/100 m.
31 holes of 18 m-long; bottom of the hole Pore pressure measurements showed
has to be 5-6 m outside the tunnel contour; that, with the grouting undertaken and
and distance between two covers is set at with some infiltration, the groundwater
10 m, or two blasting rounds. level could be maintained at the same
In Scandinavian tunneling, leakage fig- level as before tunnel construction com-
ures are most important and are used to menced.
OSLO, NORWAY
OSLO, NORWAY
order receipts and mixing times are con- Controlling overall grouting operation.
trolled by the formula system.
The mixer is suspended on three strain
gauge load cells.
The Pumpac hydraulic control block
has levers and knobs for the high pressure
and low pressure valves and knobs for the
flow setting valves. Beside the hydraulic
Weight Batching
The electronic weight batching processor
Dosac SV 6804 is a compact modular-
Pumpac hydraulic control.
built, micro-controlled unit specifically
designed for use on systems utilizing strain
gauge load cells. control blocks are the hydraulic oil
It automatically weighs water, cement 1 manometers.
and cement 2 on scale 1, and admixture 1 The Cemix 403 HWB mixer container
on scale 2 and admixture 1 on scale 3. is supported by three load cells which send
All weighing can be done simultaneous- the weight information to the WBP, which
ly. All instructions for weighing, emptying, also controls the two admixture tanks
OSLO, NORWAY
ROCKBOLT SPECIFICATIONS
ROCKBOLT SPECIFICATIONS
ROCKBOLT SPECIFICATIONS
ROCKBOLT SPECIFICATIONS
ROCKBOLT SPECIFICATIONS
ROCKBOLT SPECIFICATIONS
ROCKBOLT SPECIFICATIONS
ROCKBOLT SPECIFICATIONS
ROCKBOLT SPECIFICATIONS
ROCKBOLT SPECIFICATIONS
ROCKBOLT SPECIFICATIONS
ROCKBOLT SPECIFICATIONS
ROCKBOLT SPECIFICATIONS
DRILLRIG SPECIFICATION
Main specifications
DRILLRIG SPECIFICATION
Main specifications
Main specifications
Boltec 235H-DCS
Rock drill 1 x COP 1532/1132
Bolting unit 1 x MBU
Boom 1 x BUT 35HB
Drilling system DCS 12-55
Bolting system DCS
Carrier DC 15C
Length,excl.bom 6192 mm
Width with bolt rack 2205 mm
Height 2300 mm
Turning radius 5800/3000 mm
Weight 16600 kg
Main specifications
Boltec SL
Rock drill 1 x COP 1028
Bolting unit MBU 16SL
Boom 1 x BUT 32SL
Drilling system EDS
Length,tramming 10000 mm
Width 2480 mm
Height,carrier 1300 mm
roof min/max 1300/1700 mm
Turning radius 6180/3550 mm
Weight 12800 kg
Main specifications
Boltec MC
Rock drill 1 x COP 1532/1132
Bolting unit 1 x MBU
Boom 1 x BUT 35HB
Drilling system RCS
Bolting system RCS
Carrier L-series
Length,tramming 13156 mm
Width,excl .bolt rack 2210 mm
Height,standard 3010 mm
Turning radius 6500/3600 mm
Weight 21600 kg
Main specifications
Boltec LC
Rock drill 1 x COP 1532/1132
Bolting unit 1 x MBU
Boom 1 x BUT 35HBE
Drilling system RCS
Bolting system RCS
Carrier L-series
Length,tramming 14096 mm
Width,excl bolt rack 2510 mm
Height,standard 3100 mm
Turning radius 7650/4450 mm
Weight 26000 kg
Main specifications
Cabletec LC
Rock drill 1 x COP 1838/1638
Boom 1 x BUT 35BB
Feed 1 x BMH 210-series
Drill steel support BSH 55
Rod handling RHS 17D
Control system RCS -Drilling
RCS -Cable installation
RCS -Cement handling
Carrier L-series
Length,tramming 14042 mm
Width,excl bolt rack 2710 mm
Height,standard 3100 mm
Turning radius 7500/4550 mm
Weight 28000 kg
Main specifications
Scaletec LC
Hammer 1 x SB 300 Scaler
Boom 1 x BUT SC
Control system RCS
Carrier M-series
Length,tramming 13828 mm
Width 2196 mm
Height,standard 3010 mm
Turning radius 6500/4000 mm
Weight 21000 kg
ROCKDRILL SPECIFICATIONS
ROCKDRILL SPECIFICATIONS
ROCKDRILL SPECIFICATIONS
HYDRAULIC FEEDS
HYDRAULIC FEEDS
OVERBURDEN DRILLING
OVERBURDEN DRILLING
OVERBURDEN DRILLING
OVERBURDEN DRILLING
OVERBURDEN DRILLING
OVERBURDEN DRILLING
OVERBURDEN DRILLING
OVERBURDEN DRILLING
Symmetrix Overburden
Casing System
The patented Symmetrix system can drill straight holes at
any angle, including horizontal, and to depths
beyond 100 metres.
GROUTING
ROCKDRILL SPECIFICATIONS
DRILLING EQUIPMENT
DRILLING EQUIPMENT
DRILLING EQUIPMENT
DRILLING EQUIPMENT
DRILLING EQUIPMENT
DRILLING EQUIPMENT
DRILLING EQUIPMENT
DRILLING EQUIPMENT
DRILLING EQUIPMENT
DRILLING EQUIPMENT
cont.
DRILLING EQUIPMENT
DRILLING EQUIPMENT
THREADED.QXD 10/8/05 9:35 Page 202
DRILLING EQUIPMENT
DRILLING EQUIPMENT
TAPERED EQUIPMENT
TAPERED EQUIPMENT
TAPERED EQUIPMENT
cont.
Button bit
TAPERED EQUIPMENT
TAPERED EQUIPMENT
152 exciting pages all about Face Drilling – Get your own copy at
www.min-con.com
Atlas Copco
Supporting your business
wherever you are
Rock & Soil
Reinforcement
third edition
www.rockreinforcement.com
www.atlascopco.com
a technical reference edition
Printed matter no. 9851 6283 01b