You are on page 1of 34

Financial Training Company

Corporate and
2007 Business Law- F4
(Zimbabwe)
Casebook

Doctrine of fundamental breach


The doctrine of fundamental breach has unleashed numerous legal and judicial headaches. No
proper definition can be given to it but it has been generally regarded as a breach that goes to
the root of the contract or renders the contract inoperative. Charles Worth describes the
doctrine as a failure to undertake a certain obligation that concludes an obligation. The
fundamental breach doctrine is of English origin and our courts have ‘flirted’ with it. Thus
Professor R.H. Christie submitted that:
‘Our courts have flirted with the English doctrine of fundamental breach but the romance has not
blossomed, and it is probably even better that it should not as the doctrine is pregnant with
difficulties.’
The application of this doctrine in the Roman-Dutch Law is traced in a number of cases of which
the case of Harsales Ltd v Wallis (1956) bears testimony – where it was held that an exemption
clause will not avail a guilty party to a breach that goes to the root of the contract.

However, complexities of this doctrine, which lead our legal writers into disliking this doctrine is
the question of whether it is a rule of law or merely a rule of construction. According to
Cheshire and Fifoot, a rule of law is to be applied whether or not it defeats the intention of the
parties. A rule of construction exists to give effect to that intention. Our courts, even English
courts themselves are not consistent as to whether the doctrine is a rule of law or construction.
Thus in the case of Minor Shipping (Pty) Didcott J expressed doubt about the concept of
fundamental breach and treated it as a matter of construction.

Following the acceptance of the fundamental breach doctrine in Roman-Dutch law, and since
our common law is the Roman-Dutch law, the doctrine could be applied in Zimbabwean cases.
This is illustrated by the case of Transport Crane Hire (Pvt) Ltd v Hurbert Davies and Co (Pvt)
Financial Training Company

Ltd (1991). The facts of the case are as follows. The Appellant purchased a Foden truck which
the respondent had assembled. After travelling 43,730 km, the steering column of the truck was
found to have been improperly assembled by the respondent, causing it to fall apart and to veer
off the road and overturn. The Appellant sued for damages based on negligence. The High
Court ruled that the respondent had acted negligently but because of the existence of an
exemption clause he was not liable.

The exemption clause read as follows:


‘The company hereby guarantees within a period of nine months or 75,000 km of delivery at its
option either to repair or replace any part which may prove to be defective through material or
workmanship … Liability for direct or consequential loss of whatsoever nature or however
arising is expressly excluded.’
On Appeal, Korsah JA held that the breach of contract was a fundamental breach, and the
exemption clause could not exempt the respondent from liability for such fundamental breach.
McNally JA also held that the negligent assembly of the steering column was not an act
intended to be covered by the exemption clause, properly construed, based on a policy
approach to interpretation of such clauses in a contract.

This case clearly shows us that the fundamental breach doctrine was part of our law in
contractual cases. However, that was the law as it was, the position has now changed with the
coming of the Consumer Contracts Act [Chapter 8:03] which came into effect in 1994. It is
therefore submitted that the statute overrides the common law. Where there is a clear statute
law to regulate any matter that statutory provision should be applied. What the courts were
trying to achieve by applying the fundamental breach doctrine is now regulated by a statute. In
terms of s.5 (1)(d) of the Act read with s.4:
‘A court may find a consumer contract to be unfair for the purpose of this Act … if the consumer
contract imposes obligations or liabilities which are not reasonably necessary to protect the
interests of or if the consumer contract is contrary to commonly
accepted standards of fair dealing.’
In terms of s.4(1)(c)(i) the court was empowered to cancel the whole or any part of the
consumer contract, if it imposes obligations or liabilities which are not reasonable or if the
contract is contrary to commonly accepted standards of dealing.

In so far as the Consumer Contracts Act is concerned there is nothing called ‘fundamental
breach’ but the Act empowers the court to set aside contracts presumed to be unreasonably
unfair. It can therefore be said that the fundamental breach doctrine is no longer part of our law.
It was indeed part of our law before 1994 but now the Act takes precedence over the common
law principle.

Page 2
Financial Training Company

Remedies
There are five remedies available for breach of contract or a threatened breach of contract. The
remedies include specific performance interdict, declaration of rights, cancellation and
damages. The first three may be regarded as methods of enforcement and the last two as
recompense for non performance. It should be noted that, the choice between these remedies
rests solely and primarily with the injured party, who may elect more than one of them either in
the alternative or together of course subject to the overriding principles that he must not claim
inconsistent remedies and that he must not be overcompensated.

Specific Performance
Specific performance can be defined by any of the following;
(i) An order to perform a specified act in pursuance of a contractual or any other obligation (ad
factum praestandum).
(ii) An order to perform a specified act or pay money (ad percunian solvendum).
(iii) An order to perform a specified act in pursuance of a contractual obligation.
A plaintiff is entitled to specific performance. Zimbabwean law is clear that a plaintiff is always
entitled to claim specific performance and assuming he makes out a case his claim will be
granted subject only to the court’s discretion. In the case of Farmers Co-op Society (Leg) v
Berry (1912) Innes J said,
‘Prima facie every party to a binding agreement who is ready to carry out his own obligation
under it has a right to
demand from the other party so far as it is possible ...’
Specific performance will not be granted where it is impossible to comply with the order, where
it causes undue hardships on the defendant and generally in contracts for personal services like
contracts of employment or where the item that is being claimed by the plaintiff is readily
available on the market.
It is true that courts will exercise a discretion in determining whether or not decrees of specific
performance should be made. In the case of Haynes v Kingwilliamstown Municipality (1951) De
Villiers AJA said,
‘The discretion which a court enjoys although it must be exercised judicially is not confined to
specific types of cases,
nor is it circumscribed by rigid rules. Each case must be judged in the light of its own
circumstances’
In the case of Shakinovsky v Lawson and Smulowitz (1904), the purchaser, Shakinovsky, sued
for the specific performance of a contract of sale of a shop and business with no alternative for

Page 3
Financial Training Company

damages. It appeared from the evidence that the seller, Lawson, could not give specific
performance as the subject matter to the sale had subsequently been sold to Smulowitz, a bona
fide purchaser. The court emphasised that it will certainly not decree specific performance
where the subject matter of a contract has been disposed to a bona fide purchaser or where it is
impossible for specific performance to be effected.

Where the thing claimed can readily be bought anywhere a decree of specific performance
cannot be ordered.
De Villiers AJA said in the case of Haynes v Kingwilliamstown Municipality (1951)
‘In our law a grant of specific performance does not rest upon any special jurisdiction, it is an
ordinary remedy to which, in a proper case the Plaintiff is entitled … so in contracts for the sale
of shares which are daily dealt with in the market can be obtained without difficulty specific
performance will not ordinarily be granted . . .’
It should however be noted that the decree of specific performance would not be granted where
damages would adequately compensate the injured party. Due to that possibility, the injured
party usually adds to his prayer for specific performance an alternative prayer for damages. See
the case of Woods v Walters (1921) wherein Innes C J said:
‘It is common practice . . . to add to a prayer for specific performance an alternative prayer for
damages.’
Interdict
This is a remedy to prevent breach or threatened breach of contract. It takes the form of a court
prohibiting the defendant from doing whatever is specified in the order.

Declaration of Rights
This is remedy whereby parties approach the court for an order declaring the position of their
rights. This remedy was
underscored in the South African case of Government of Self-Governing Territory of KwaZulu v
Mahlanga (1994) where Eloff J pointed out that,
‘. . . the court is limited to a question of right. The nature and scope of the right might be
inquired into, but in the
absence of proof of such a right, or at least a contention that there is such a right, the court has
no jurisdiction.’
It should also be borne in mind that courts are not there to rule on abstract concepts or any
dispute and as far as declaratory orders are concerned, only legally recognisable and
enforceable rights are determinable.

Cancellation
The act of cancellation, which is also sometimes described as acceptance of the repudiation,

Page 4
Financial Training Company

rescission and repudiation may be performed by the innocent party himself, without the
assistance of the court. In essence, the court order would confirm the act which has already
been done. The object of cancellation unlike rescission, is intended to terminate the primary
obligations of the contract there and then but not retrospectively. Restitution by either party or
both parties should therefore be ordered only to the extent necessary to avoid unjust
enrichment. See Feinstein v Niggoli (1981) in Segal v Mazziv (1920) Watermeyer AJ said, ‘Now,
when an event occurs which entitles one party to a contract to refuse to carry out his part of the
contract, that party has a choice of two courses. He can elect to take advantage of the event or
he can elect not do so. He is entitled to take reasonable time to make up his mind, but once he
has made his mind, he is bound by that election . . .’

Damages
Damages for breach of certain special types of contracts, such as sales, leases and contracts of
employment are frequently assessed according to principles that have evolved to meet the
special requirements of the particular contract. Unlike damages for delict, damages for breach
of contract are not intended to recompense the innocent party for his loss, but to put him in the
position he would have been in if the contract had been properly performed. See Victoria Falls
and Transvaal Powerco Ltd v Consolidated Langlaagte Mines Ltd (1915) AD1. In this case C
ordered a supply of electric power from V on 25 February 1911. V was informed that the power
was required by 1 July 1912 and was for a new reduction plant. V replied ‘we have duly noted
these requirements and will make the necessary arrangements’. The power was not actually
supplied until 29 September 1912. C sued V for damages for loss in extraction, for deferred
profits, for loss on development and for loss on shaft-sinking.
In considering the principles to be applied Innes C J said;
‘we must apply the general principles which govern the investigation of the most difficult
question of fact – the
assessment of compensation for breach of contract. The sufferer by such a breach should be
placed in the position he
would have occupied had the contract been performed . . . and without undue hardship to the
defaulting party. The
reinstatement cannot invariably be complete, for it would be inequitable and unfair to make the
defaulter liable for
special consequences which could not have been in his contemplation when he entered into the
contract . . .’
The law relating to awarding of damages ensures that undue hardship is not imposed on the
defaulting party by obliging the sufferer to take reasonable steps to mitigate his loss or damage.
Additionally, the defaulting party’s liability is limited in terms of the broad principles of causation
and remoteness. The latter gives rise to damages that flow naturally and generally from the kind

Page 5
Financial Training Company

of breach of the contract and which the law presumes the parties contemplated as a probable
result of the breach and damages that although caused by the breach of contract, ordinarily
regarded in law as being too remote to be recoverable unless special circumstances are
established attending the conclusion of the contract. To that end two types of damages exist i.e
general damages and special damages. That contemplation is a prerequisite for special
damages is a common trite principle enunciated in various case law. See also the case of
Shartz Investments (Pty) Ltd v Kolovyrnas (1976).
As regards mitigation, the principle was exhausted in the case of Hazis v Transvaal and
Delagoa Bay Investment Ltd (1939).
Tindall JA stated:
‘It was of course the duty of the company to take all reasonable steps to mitigate the loss
consequent to the breach of
the lease, but the duty did not impose on the plaintiff an obligation to take any steps which a
reasonable and prudent
man would not ordinarily take in the course of his business.’
All in all the principles have been re-stated by Corbett JA in Holmdene Brickworks (Pty) Ltd v
Roberts Construction Co. Ltd (1977) wherein it was stated that:
‘the fundamental rule in regard to the award of damages for breach of contract is that the
sufferer should be placed
in a position he would have occupied had the contract been properly performed so far as that
can be done by the
payment of money and without undue hardship on the defaulting party . . .’

Glossary terms
(a) Set-Off
Where two parties to a contract are reciprocally indebted to each other, the debts are
automatically extinguished if they are of the same amount or, if one is larger than the other, the
smaller is extinguished and the larger reduced by the amount of the smaller debt. Lester
Investment (Pvt) Ltd v Narshi (1951)

(b) Novation
Novation takes place where the parties to a contract agree to replace it completely with a new
contract. A new obligation is introduced, replacing the existing obligation e.g. a contract of sale
being converted into a donation or one of exchange. Such agreement may be express or

Page 6
Financial Training Company

inferred from all the circumstances of the case. The court will not lightly infer a novation. It will
do so only if the circumstances raise such a necessary inference.

(c) Locus standi in judicio


A party desiring to enter into a contract must have the capacity to sue or be sued, (locus standi
in judicio) according to the Legal Age of Majority Act (1982). Natural persons who have attained
majority status (18 years) have locus standi in judicio. Mhondoro Muchabaiwa v Katekwe (1984)
Certain categories of persons such as unassisted infants, mentally ill persons, inebriates,
insolvent persons and enemy aliens lack locus standi in judicio. On the other hand a company
that is registered in terms of the law acquires contractual capacity upon its registration (section
9 of the Companies Act).

(d) Quasi-Mutual Assent


This is also known as the Smith v Hughes doctrine and essentially the position is that in
deciding whether there was an intention to (where a dispute has arisen) the test is objective
rather than subjective. This intention is determined or inferred from the manner in which the
person concerned conducts himself. As was said by the court in Pieters and Co. v Salomon
(1991), .When a man makes an offer in plain and unambiguous language which is understood
in its ordinary sense by the person to whom it is addressed, and accepted by him bona fide in
that sense, then there is a concluded contract.

Any unexpressed reservations hidden in the mind of the promisor are in such circumstances
irrelevant. He cannot be heard to say that he meant his promise to be subject to a condition
which he omitted to mention, and of which the other party was unaware.. The rule will not be
applied where there was a mutual mistake, the parties honestly attaching different meanings to
words in a contract which are not self-explanatory.

Void and voidable contracts


A valid contract gives rise to rights, obligations and powers that are vested in one or both of the
parties to the contract. These rights always include a personal right to claim performance from
the other party. If the latter does not perform in terms of the contract, he may face a claim based
on breach of contract. The parties however must achieve consensus ad idem (meeting of
minds) before a contract can come about. Where a party understood something incorrectly it is
said that he acted as a result of mistake and in cases of mistake one cannot be said to have
consented to that which the other party has in mind. There is therefore no consensus between

Page 7
Financial Training Company

the parties and likewise no contract. In cases involving duress, undue influence and
misrepresentation, consensus will have been obtained improperly and therefore it would be
defective. Such a contract would be voidable at the
instance of the weaker party.

From the foregoing it is clear that there are factors which may influence consensus between the
parties to the extent that the contract may be rendered void and voidable.
These factors which will be discussed in detail below are the following:
1. Mistake (error)
2. Misrepresentation
3. Duress
4. Undue Influence

1. Mistake
Error or mistake is one of the greatest defects that can occur in a contract, for agreements can
only be formed by the consent of the parties and there can be no consent where the parties are
in error in relation to the object of their agreement. Mistake can be described as a
misunderstanding or misapprehension by one or both of the parties regarding facts, events or
circumstances in the contract. The rule is that a mistake renders the contract void if it is:
(a) one of fact rather than law
(b) essential (material)
(c) reasonable (justus error)
This mistake (error) must concern only the facts of the contract and in particular the essential
facts of the agreement in order to have any influence on the consensus between the parties.
In Maritz v Pratley (1894) items were displayed for auction each bearing a number for
identification. Prospective purchasers were requested to inspect the goods which were to be put
up for auction. A mirror was displayed on a marble table and Pratley made a bid on the table
thinking that the mirror formed part of the table. He refused to pay separately for the mirror and
was sued by the auctioneer for the purchase price. The court ruled that there had been a
mistake (error) regarding a fact material to the contract and consequently that no consensus
had been reached and the contract was therefore void.
The fact that the error is essential and therefore that there is dissensus between the parties is
not sufficient on its own to render the contract void. In addition the mistake must be a justus
error (reasonable mistake). An error is justus when it is reasonable or excusable in all the
circumstances of a particular case. This means that the mistake (error) must not be due
to the negligence of the party who relies on mistake in order to avoid liability.
In George v Fairmead (1958). A guest at an hotel signed the register without acquainting
himself with a clause which

Page 8
Financial Training Company

indemnified the hotel from claims arising from theft. George maintained that his action was a
case of mistake but the court decided that it was not a reasonable mistake and therefore had no
effect on the contract.

2. Misrepresentation
A contract can be set aside by the aggrieved party on the ground of misrepresentation where:
(a) A representation was made by one party or his agent to the other in order to induce him to
enter into the contract.
(b) The representation was material
(c) It was false in fact
(d) The other party entered into the contract on the faith of the representation.
A party cannot claim misrepresentation unless he has been induced thereby to conclude the
contract. He must therefore prove that he accepted the represented facts as being true and that
they constituted a reason for him to conclude the contract before he will be able to contest the
contract. The test which is applied is whether the innocent party would have concluded the
contract if the misrepresentation had not been made.
In Poole and McLennan v Nourse (1918) a misrepresentation was made concerning the
qualities of a farm. However before the purchaser bought the farm they were acquainted with
the true facts and they nevertheless decided to go ahead and purchase the farm. The court
decided that they had not been induced to purchase the farm by the misrepresentation and
therefore the contract could not be rescinded.
The choice between the enforcement and setting aside of the contract must be made by the
innocent party within a reasonable time after knowledge of the deception. He has a choice
between enforcing or rescinding the contract and once he has chosen, he is bound by his
choice and he loses the alternative option. (Bowditch v Peel and Magill (1921).
In our law a distinction is drawn between fraudulent/intentional, innocent and negligent
misrepresentation. The party alleging that a misrepresentation is fraudulent has to prove the
absence of honest belief by showing in the words of Lord Herschell in Derry v Peek (1889) that
a false representation has been made.
(1) knowingly or
(2) without belief in its true or
(3) recklessly careless whether it be true or false.
The person to whom the fraudulent misrepresentation was made has the choice of the following
remedies.
(a) He may ignore the contract and if sued on it use the fraud as a defence.
(b) He may rescind the contract and claim restitution – Dibley v Furter (1951)
(c) He may claim rescission of the contract, restitution and damages – Gous v De Kock (1887)
(d) He may treat the contract as binding and claim damages for any loss he has suffered.

Page 9
Financial Training Company

Coomers Motor Spares (Pvt) Ltd v Albania (1979)

3. Simple/Innocent Misrepresentation
A misrepresentation made without fraud and without negligence is a simple misrepresentation.
The party making the
misrepresentation genuinely believes the facts to be true while they are actually false.
The only remedy available in circumstances involving innocent misrepresentation is rescission
and damages are not available. The remedy of rescission is available to all the three forms of
misrepresentation.
Rescission means that the parties have to be restored to the status quo ante. The innocent
party is entitled to claim back whatever he has parted with as a result of the contract but he is
also obliged to return what he has taken from the other party.
Harper v Webster (1956)
Negligent misrepresentation occurs where the maker of a misrepresentation fails to display that
degree of care which a reasonable man in his position would display. He is negligent if he
should have verified the truth of the facts before conveying them to the other contracting party.
Whilst the remedy of rescission is available for negligent misrepresentation for many years it
was a debatable point as to whether damages were available for negligent misrepresentation in
Zimbabwean law. It is now settled law that in appropriate cases damages are available for
negligent misrepresentation. Autorama (Pvt) Ltd v Farm Equipment Auctions (1984).

4. Duress
Duress may be described as a threat or intimidation which engenders fear in a person, causing
him to conclude a contract as a result of this fear. In order to succeed voiding the contract the
fear to which the threat gives rise must be reasonable fear, in other words it must be clear that a
reasonable person would also have been fearful in the given circumstances. The innocent party
must have been threatened by the other contracting party and not by an outsider.
In our law the leading case on this subject is Broodryk v Smuts (1942) where Broodryk was
threatened with internment or arrest if he were to refuse to enlist with the defence force.
The requirements for duress were set out in this case and are the following:
(a) the fear must be reasonable
(b) the fear must be caused by a threat of ‘considerable evil’ and directed at the contracting
party or his family or property
(c) it must be a threat of immediate danger which cannot be averted
(d) the threat or intimidation must be contra bones mores (contrary to good morals)
(e) the moral pressure which is exerted must cause damage.
Duress renders the contract voidable at the option of the threatened person and he has the
choice between enforcing and setting aside the contract, as well as the right to claim damages.

Page 10
Financial Training Company

5. Undue Influence
Undue influence and the consequences thereof were described by Fagan JA in Preller and
Others v Jordaan (1956).
As the influence which one person has over another which weakens the latter’s resistance and
renders his resolve pliable so that the other person may exercise his influence in an
unconscionable manner to persuade the victim to conclude a prejudicial
contract which he would normally not have concluded. Once again because the weaker party’s
consent has been improperly obtained the contract is consequently voidable at the instance of
the person who has suffered.
The requirements for undue influence are as follows:
(a) one party obtains influence over the other party
(b) this influence weakens the other party’s resistence and renders his resolve malleable
(c) the party exerting the influence uses this influence in an unscrupulous manner
(d) this influence leads to the conclusion of a contract which is to the detriment of the other
party. Patel v Grobbelaar (1974)

Void ab initio
One of the essential requirements for the validity of a contract is that performance must be
possible. As a general rule it can be stated that if performance of the envisaged contract is
impossible from the initial instance the contact will be void ab initio (invalid from the beginning).
With commercial contracts performance is impossible if the thing which has to be delivered no
longer exists or never existed; is incapable of being traded or already belonged to the purchaser
when the contract of sale was concluded.

Another form of impossibility usually involves physical impossibility for example the house which
was to be surrendered for occupation has been razed to the ground. A distinction can be drawn
between initial impossibility and supervening impossibility of performance.
Initial impossibility of performance exists where performance was impossible at the time of the
conclusion of the contact whereas supervening impossibility of performance refers to the case
where performance was possible at the inception of the contract but subsequently became
impossible.
The impossibility must be objectively beyond the control of the parties. In other words, it must
be caused by vis major (an act of God) or casus fortuitous (an inevitable accident). Between the
two phenomena we are looking at events which cannot be foreseen with reasonable foresight in

Page 11
Financial Training Company

as much as they cannot be prevented with reasonable care.


In the case of Peters, Flamman and Co Ltd v Kokstad Municipality (1919), the municipality had
concluded a contract with the appellants in terms of which the latter were to supply electricity to
the town for a number of years. During the currency of the agreement, the second World War
broke out and the appellants who were German nationals were interned as enemy aliens and
their business was wound up under the relevant wartime legislation. Upon their release from
prison they were sued for breach of contract by the Municipality and the court decided that
supervening impossibility had terminated the contract.
Solomon A.C.J said:
‘By the civil law a contract is void if at the time of its inception its performance is impossible. So
also where a contract has become impossible of performance after it had been entered into the
general rule was that the position is then the same as if it had been impossible from the
beginning.
The authorities are clear that if a person is prevented from performing his contract by vis major
or
casus fortuitous, under which could be included such an act of state as we are concerned with
in
this appeal, he is discharged from liability.’
The concept of supervening impossibility as we know it in Roman-Dutch law more or less
equates with the doctrine of frustration in English law. Some terse examples drawn from
English law will probably suffice. In Taylor v Caldwell (1866) the contract was deemed to have
been frustrated after a music hall which had been hired for a series of concerts was burnt down.

In Condor v Barron Knights (1966) the drummer of a pop group became ill and was forbidden by
his doctor from performing for more than four nights each week thereby frustrating his contract
which extended for seven nights. Apart from subsequent physical impossibility there may be a
change in the law after the contract was made which renders it illegal to perform the contract.
For example, an outbreak of war will frustrate a contract, as would illegally trading with the
enemy (Avery v Bowden (1855).

Equally the basis of the contract may be negated as when an agreement is dependent upon
some future event which does not take place. In Chandler v Webster (1904) the coronation of
King Edward (VII) was postponed because of the sudden illness of the king and contacts for the
hire of rooms along the route of the procession were as a result frustrated. From these cases, it
is clear what effect supervening impossibility of performance has on a contract. As soon as
performance has become impossible in its entirety the contract is terminated and the parties are
freed of their obligations. This rule applies to all contracts where the passing of the risk rule
does not form part of the contract.

Page 12
Financial Training Company

In cases where the passing of the risk rule forms part of the contract, for example the contract of
sale, where the purchaser bears the risk for incidental damage, the contract is not terminated by
supervening impossibility. The purchaser is still obliged to perform although performance has
become impossible for the seller Pahad v Director of Food Supplies (1949).

However under Roman-Dutch law a contract is not terminated by supervening impossibility of


performance in the following situations:
(a) where performance has become impossible as a direct result of the debtor’s own wrongful
act. In Benjamin v Myers (1946) M let a garage to B. B undertook that at all times he would be
available for the sale of sufficient supplies of such brands of petrol and oils as he was permitted
to stock and sell on the premises in terms of the lease. On breach of this undertaking M was
entitled to cancel the lease. B ceased to hold and sell petrol and M cancelled the lease and
sued for B’s ejectment. B pleaded that he had been prevented from selling petrol by the
Controller of Petrol. M replied that this was a result of B’s wrongful act. It was held that finding
the Controller had in fact prevented B from selling petrol but had done so because B has been
found guilty of a breach of the relevant regulations, the magistrate’s judgment granting an order
of ejectment should be upheld and B’s appeal dismissed. Herbstein AJ said:
‘A defendant cannot rely on a self-created impossibility . . . In my opinion the magistrate was
correct in holding that the performance of the contract was made impossible as a direct result of
the defendant’s own wrongful act.’

(b) When the debtor has taken it upon himself the risk of performance becoming impossible. In
Yodaiker v Angerhrn and Piel (1914), Y by contract agreed to supply A with a certain quantity of
coal – two trucks of forty tons each per week – for a period of twelve months. Owing to a railway
strike which might have continued for an indefinite period, Y, although called upon to fulfil the
contract, was unable to supply the coal required between 7 and 15 January 1914 and notified A
to that effect. A thereupon cancelled the contract. When Y sued for damages, the magistrate
found that A and P were justified in cancelling the contract and Y could not receive damages. Y
appealed. It was held that the appeal should be dismissed. Curlewis J said:
‘The fact that the plaintiff was prevented by the strike from carrying out his obligations is no
answer
to the respondents. That is a risk which he took upon himself when he entered into the contract,
and he had to bear the burden of that risk.’
(c) When performance is more difficult or costly but not impossible to undertake (Herman v
Shapiro and Company (1926) supra).
(d) Where the impossibility is partial, in which case the obligation remains in existence in so far
as the part that is still possible is concerned (Stansfeld v Kuhn 1940).

Page 13
Financial Training Company

(e) Where the debtor is only temporarily disabled from fulfilling his obligation, Baretta v
Rhodesia Railways (1914).
Tredgold J said:
‘The law is clear that when a contract becomes finally and completely impossible of
performance
by reason of an act of state, it is discharged. But this does not cover the situation in which one
party is temporarily disabled from fulfilling his undertaking. Upon a temporary disability
preventing
one party from fulfilling his obligation the contract continues. If the disability persists for a period
which judged on the circumstances of the particular case renders it unreasonable that the other
party should continue bound whilst receiving no benefit from the contract such party is entitled
to
terminate the contract.’

Void for vagueness


Those agreements where the language used is so vague and uncertain that it cannot be
decided what was in fact agreed upon by the parties. South African Reserve Bank v Photocraft
(Pvt) Ltd 1969 in which a written lease agreement provided that ‘the lessor hereby grants to the
lessee an option to renew this lease for a further period of three years at a rental to be mutually
agreed upon under the same terms and conditions as herein contained’. P, the lessee exercised
the option but the bank which had purchased the building replied that it was unable to negotiate
in
regard to any extension of the lease as the buildings would be demolished. Held;
The clause was of no force or effect in the absence of any agreement as to rental and further
that the agreement to negotiate was so vague as to its import, significance or consequence as
to be unenforceable.
And in Baretta v Baretta (1924) a contract between the parties by which a debt was
acknowledged and certain property pledged, provided that the debtor ‘hereby undertakes to pay
off a substantial sum every year.’
Held; This stipulation was too vague to be enforceable in law.

Those where the agreement is not final and there are still terms to be negotiated the contents of
which cannot be determined. Schneier and London Ltd v Bennet (1927)
B was employed as manager of S and L’s timber department at a monthly salary of forty pounds
plus a small commission to be agreed at a later date between the parties. He was dismissed

Page 14
Financial Training Company

before any agreement had been reached as to commission. He sued S and L for commission at
the rate of one-fifth per cent on turnover, which rate he contended was reasonable. Held;
It seems impossible to say what is the meaning of the words ‘small commission on the
turnover’. The agreement is too vague to enforce.
From the foregoing it is quite clear that if an agreement is perceived by the courts as too vague
it becomes void for vagueness and of no force or effect.

Contract made void due to age of consent


The Legal Age of Majority Act, 1982 conferred majority status on all Zimbabweans above the
age of eighteen years. African women who were hitherto perpetual minors acquired majority
status at the age of eighteen years. As a result all African women older than eighteen years of
age are emancipated from the authority of guardians (like their male counterparts). In Katekwe v
Muchabaiwa (1984) the Supreme Court ruled that as a result of the Legal Age of Majority Act
upon attaining eighteen years of age an African woman acquires locus standi in judicio
(contractual capacity).

In our law an agreement which is so vague that its meaning cannot be ascertained by a court is
void ab initio (from the initial instance). In Baretta v Baretta (1924) a contract between parties by
which a debt was acknowledged and certain property pledged, provided that the debtor ‘thereby
undertakes to pay off a substantial sum every year’. The court said that this stipulation was too
vague to be enforced in law.
On the other hand the mere fact that a contract appears to be incomplete or uncertain does not
render it void for vagueness if its meaning can in fact, be determined by a court on the evidence
before it. In Anegate v Muckulal’s Estate (1954) A was employed by his uncle who agreed to
pay him ‘something, sometime for his services’. The court held that the language of the contract
was not so much vague as silent and the amount of remuneration could easily be determined by
having recourse to the ordinary rules governing implication of terms into a contract. There was
therefore in this case an implied term requiring the uncle to pay a reasonable remuneration.

Undue influence
A contract can be set aside by the aggrieved party on the ground of undue influence where as
was said by Fagan J A in the case of Preller and Others v Jordaan (1956).

Page 15
Financial Training Company

(a) One person obtains an influence over another which weakens the latter’s powers of
resistance and renders his will pliable.
(b) Such a person then uses his influence in an unconscionable manner to persuade the other
to agree to a prejudicial transaction which he would not have entered into with normal freedom
of will.
The burden of proof lies with the party who wants to ask the court to set aside a contract on the
ground of undue influence and he must prove the following:
(i) The other party exercised an influence over him
(ii) This influence weakened his powers of resistance and made his will pliable.
(iii) The other party exercised this influence in an unscrupulous manner in order to induce him to
consent to a transaction (a) which is to his detriment and (b) which he with normal free will,
would not have concluded.
In Patel v Grobbellaar (1974) G claimed the cancellation of a Mortgage Bond registered against
property owned by him in favour of P for $40 000·00, ostensibly the balance due in respect of
money lent by P to G. This was done under a power of attorney which P has persuaded G to
sign. At all relevant times, G believed P possessed supernatural powers and as a result of this
belief P acquired an influence over G. G would not
have signed the power of attorney with normal freedom of volition as he had not borrowed any
money from P. A lower court ordered cancellation of the contract and on appeal against that
decision by P the Appeal Court ruled that he had satisfied the onus of proof and that the appeal
should be dismissed.

Influence may be exerted by anyone but it is more likely to exist where there is a special
relationship between the parties such as that of parent and child, teacher and pupil, attorney
and client, doctor and patient.
In the case of Preller and Others v Jordaan (1956) J, an elderly farmer, claimed re-transfer of
four farms that he had donated and transferred to P, who at that time was his doctor. J alleged
that the transaction had taken place when he was old, spiritually, mentally weak and exhausted
through P.s influencing him in an improper and unlawful manner to give and transfer the farms
to P, to be administered by P for the benefit of J.s wife and farm labourers. J further argued that
he would not have done so had he not been so weak and exhausted and under P.s influence. In
the meanwhile P had in turn donated and transferred ownership of three of the farms to his son
and daughter. In a judgment which underlines the fundamental distinction between void ab initio
and voidable agreement the appeal court ruled that as the transaction which was induced by
undue influence was voidable and not void and as transfer ad been passed to the two children J
could not claim back the three farms from them. However he could still claim the one farm which
remained in the hands of the defendant (P) at the time of the action. On the other hand if the
contract had been void ab initio J would have been able to recover all the four farms.

Page 16
Financial Training Company

Illegal contracts
One of the primary essentials of a valid contract is that for it to be enforceable the agreement
must be lawful. A valid contract cannot come into existence if the agreement is unlawful
because
(i) it is prohibited by statute, the prohibition referring to either the form of the contract or the
performance to be made.
(ii) it is prohibited by common law, being regarded as contrary to public policy or contra bonos
mores (contrary to accepted standards of morality).
The ex turpi causa rule (from a base cause, no action arises) is rigorously applied by our courts
and even if the parties are unaware of the illegal nature of the agreement, the courts will not
enforce it. It is often said that an agreement which violates statute law or the common law is
void ab initio (from the initial instance).
It is a well established if not universal rule that the court is bound to refuse to enforce a contract
which is illegal even though no objection to the legality of the contract is raised by the parties.
In Cape Dairy v General Livestock Auctioneers (1924), a firm of auctioneers in breach of a
Transvaal statute, sold to S certain cattle on Sunday. The firm successfully sued in the
Magistrate’s Court for the balance of the price. On appeal to the Transvaal Provincial Division,
the court of its own motion raised the point that the sale was illegal and refused to enforce it.
Innes CJ said:
‘when a court is asked to enforce a contract which the law expressly forbids, it is not only
justified but bound to
take cognisance of the prohibition and the consequent illegality . . .’
In Lion Match Co Ltd v Wessels (1946) W sued for the price of wood sold and delivered by him
to LM. The requisite
governmental permit had not been obtained. The court held that the sale was illegal and
therefore unenforecable. It is clear that the video cassette was smuggled into Zimbabwe in
contravention of the Customs and Excise Act and because the agreement between Harry and
Michael is tainted by statutory illegality it is unenforceable. Equally, the agreement between the
two parties is void ab initio (from the initial instance) on the basis of common law illegality.
Certain types of contract are forbidden at common law and therefore prima facie illegal. Some
of the more common examples are the following:

(i) agreements in restraint of trade


(ii) agreements in interfering with justice

Page 17
Financial Training Company

(iii) agreements to stifle the prosecution for a crime


(iv) agreements allowing the parties to avoid judicial remedies and to take the law into their own
hands
(v) agreements derogating from marriage
(vi) agreements encouraging immorality. In this case the agreement pertains to pornography
and it would be viewed with disapproval by the courts.

As a general rule, a party who has fulfilled his obligations under an unlawful agreement is not
permitted to reclaim what he has performed. In other words the consequences of an agreement
containing an illegality is that the agreement does not constitute a contract. It is void of the legal
effect intended by the parties.
(York Estates v Wareham 1949)

The maxim in pari delicto pitio est conditio


possedentis
Kerr notes that although consent of the party against whom the right is held is not necessary,
there are certain exceptions to this principle. The exception to this rule is that where there is a
conditional clause in a contract, cession will not prevail. This exception to the general principles
of cession was applied by Ludorf J in the Seegrey Bag Man case where it was held that the
presence of a conditional clause tips the scale in favour of the view that the contract is not
capable of cession.

The maxim in pari delicto pitio est conditio possedentis applies where the parties are equally in
the wrong. The position that he who is in possession will prevail would be relaxed for
considerations of justice between the parties. Chanetsa is entitled, to the relaxation of the in pari
delicto rule, to retain possession of the property in question, if justice is to prevail. This verdict
would be in reliance on the judgment of Schreiner J in the case of Petersen v Jajbhay. The
learned judge notes that, ‘… the lease though invalid, public policy seems to me to point prima
facie to his removal from the property otherwise in case of this … there would be unjust
enrichment …’

Page 18
Financial Training Company

Latent defects
One of the primary obligations of the seller is to guarantee the purchaser against the existence
of latent defects in the merx (merchandise). The seller is obliged to deliver the thing sold to the
purchaser without defects. If the merx is latently defective, the tacit warranty against latent
defects comes into operation. This warranty is inherent to the contract of sale and in terms
thereof the seller guarantees that the thing sold is free of latent defects or other abnormalities.
The seller is therefore liable for any latent defects in the thing sold irrespective of whether he
was unaware of such defect at the time of the conclusion of the contract or not.
A latent defect is a hidden defect, one which would not be apparent upon reasonable inspection
by the average diligent person.
Before the purchaser can hold the seller liable for latent defects he will have to prove:
(i) that the defect existed at the time of conclusion of the contract
(ii) that the defect is in fact latent i.e it could not readily have been noticed
(iii) that the purchaser was unaware of the defect at the conclusion of the contract and that the
defect is material in that it renders the merx useless or less useful for the purposes for which it
was bought.
It is abundantly clear that the new Bashem hockey sticks which Sue, Jane and the other team
members bought are latently defective. When there is a latent defect in the thing sold the
purchaser has special remedies against the seller. The purchaser is entitled to the aedilitian
remedies which are the actio redhibitoria (rescission of contract) and the actio quanti minoris
(reduction of the purchase price).
Actio redhibitoria
In this case, the defect is so serious that the hockey sticks cannot be used for their normal
purpose or for the purpose for which they were bought and accordingly the buyers are entitled
to cancel the contract.
The underlying rationale is that the purchasers would not have bought the hockey sticks had
they known of the defect
beforehand. Since redhibitoria involves cancellation of the contract, the purchasers must return
the merx (hockey sticks). On the other hand, if the article has been destroyed, through no fault
of the buyer, he is of course unable to return the article, but that does not prevent the buyer
from instituting the actio redhibitoria.

In Dodd v Spitaleri (1946) the purchaser bought a horse which was suffering from a debilitating
disease. There was
conclusive veterinary evidence that the disease was incurable although the purchaser had the
horse shot, he was still able to recover his purchase price.

Page 19
Financial Training Company

And in African Organic Fertilizers v Sieling (1949) the buyer sought to rescind the sale of kraal
manure which proved unfit for the purpose for which the seller knew the buyer intended it.
However the manure – having already been used could not be returned. The court held that the
purchaser could still recover his purchase price.
If the latent defect is of such a nature that it simply affects the value of the thing, the actio quanti
minoris in terms of which a reduction in price is claimed is instituted. The reduction amounts to
the difference between the purchase price and the actual value of the thing sold.

Warranty against latent defects

One of the fundamental obligations of the seller is the duty to deliver property which is free from
latent defects. This duty only relates to defects which are material and an objective test is used
to determine materiality. (Dibley v Furter 1951).
A latent defect is one which would not be apparent upon a reasonable inspection by a prudent
man even though it might not escape the notice of an expert.
In Roman–Dutch law, a buyer who inspects the property cannot be heard to complain of the
patent defects which the inspection should have revealed. A seller who sells property voetstoots
(as it stands) is protected from liability in the event that the merchandise turns out to be latently
defective. However a voetstoots clause does not protect the seller from fraudulent
nondisclosure of latent defects. Thus in the Zimbabwean case of Matambo v Chakauya (1992)
the plaintiff purchased a house voetstoots from the defendant. When the rainy season arrived it
was discovered that there were bad leaks of water through the roof. The court ruled that the
defect was a latent one and the defendant had deliberately not disclosed it at the time of the
conclusion of the agreement of sale. As a result of the fraud the court ruled that the seller was
not absolved of liability,
notwithstanding the voetstoots clause.

Where the sale is not voetstoots and the buyer discovers that the merchandise is latently
defective he is entitled to claim one of the Aedilition remedies, namely the Actio Redhibitoria
(action for rescission of the contract) and the Actio quanti minoris (reduction of purchase price).
The Actio Redhibitoria is an action for cancellation of the contract because the defect is so
serious as to make
the property unfit for the purposes intended by the contract.
The rationale underlying this remedy is that if the purchaser had known of the defect prior to the
conclusion of the agreement of sale he would not have bought the article when he did. The
defect is so fundamental that it makes the merchandise unsuitable for the purpose for which it

Page 20
Financial Training Company

was bought. By instituting this action, he cancels the contract. He thus claims the return of the
purchase price, interest, repayment of all expenses with regards to the delivery and
preservation of the article and reimbursement of improvements effected by him.

The purchaser must however return the article together with anything that has accrued to it.
Before the purchaser can hold the seller liable for latent defects he will have to prove that:
(1) the defect existed at the time of the conclusion of the contract
(2) the defect is in fact latent i.e it could not readily have been noticed
(3) the purchaser was unaware of the defect at the conclusion of the contract and that
(4) the defect is material in that it renders the merx useless or less useful for the
purpose for which it was bought.

Some examples of latent defects in the merchandise are:


(a) lung sickness in cattle (Haviside v Jordan (1903)
(b) heartwater disease in sheep (Ackermann v Komfass (1904)
(c) a welded crankshaft in a motor vehicle (Goldblatt v Sweeney (1918)
(d) a leaking roof (Matambo v Chakauya (1992)
Under the Actio Redhibitoria, it is a condition precedent that the purchaser should restore the
article plus any fruits and accessories to the seller if he wants to recover the purchase price and
his interest back. The purchaser forfeits the right to the remedy of redhibitoria in the following
situations:
(a) if the article is not capable of redelivery to the seller;
(b) if the article has been materially damaged because of the purchaser’s negligence
or by a person for whom he is responsible;
(c) where the purchaser by exercising unequivocal acts of ownership over the article
has delayed to such an extent as to amount to a waiver;
(d) where the defect is of a trivial nature.
On the other hand, if the merx has perished due to the very defect complained of and in the
absence of fault on the part of the purchaser he will still be entitled to recover the purchase
price despite the fact that the merchandise would be incapable of redelivery to the seller.
In Dodd v Spitaleri (1949) the purchaser bought a horse which was suffering from a severe
bone disease. There was conclusive veterinary evidence that the disease was incurable and to
save it from any further pain the purchaser had the horse shot. The court ruled that the
purchaser could recover his purchase price despite the fact that he was unable to return the
horse.

And in the case of Marks v Laughton (1932) the buyer sought to rescind the sale of eggs which
had been condemned as unfit for human consumption and as a consequence had already been

Page 21
Financial Training Company

destroyed by the local authority. The seller argued that the buyer’s inability to restore the eggs
was fatal to his right to rescind the contract.
The court said, ‘despite the basic prerequisite that latently defective goods must be returned,
the Actio Redhibitoria may nevertheless apply even where goods cannot be returned if this is
because they have been destroyed due to the latent defects and without fault on the part of the
purchaser . . .’
The Actio quanti minoris (action for reduction of the purchase price) is instituted when the latent
defect is not so material as to render the article completely useless. Alternatively, the purchaser
might opt not to rescind the contract and have the purchase price reduced in circumstances in
which if he had so desired he could have cancelled the agreement on account of the gravity or
seriousness of the defect. Under Actio quanti minoris, the defect however affects the value of
the article. The purchaser keeps the article but claims a price reduction which is the difference
between the purchase price and the actual value of the article.

Aedilitian remedies are available to the seller only in cases where the thing sold has latent
defects. Depending on the
circumstances they offer him only cancellations or a price reduction. However ordinary
damages cannot be claimed in the case of latent defects except in three cases (and where
ordinary damages are awarded for latent defects, they are given in addition to the Aedilitian
remedies) which are as follows:
(a) where the seller acted fraudulently by not disclosing to the purchaser the existence of a
latent defect of which he was aware. This is not simply withholding information, the intention of
the seller is to defraud the purchaser.
(b) where the seller is the manufacturer of the thing sold or a dealer who publicises his expert
knowledge and skills regarding the article he may also be held liable ex empto for damages.
In Odendaal v Bethlehem Romery (1954) the purchaser bought livestock feed form a dealer.
The dealer dealt almost exclusively in stock feeds. The feed was infested with a particular germ,
but both parties were unaware of this. After the purchaser had fed the feed to his stock, thirteen
head of cattle died. The seller was held liable for damages because he was a dealer with expert
knowledge regarding that which was sold.
(c) where the seller gives an express warranty against latent defects, he will be liable for
damages if there should be a defect in the thing purchased.

Failure to deliver in a sale agreement


The general principle is that a seller who fails to deliver may be ordered to do so by an order of
specific performance. Damages caused by the delay in delivery may be awarded in addition,

Page 22
Financial Training Company

Rhodesia Cold Storage and Trading Company Ltd v Liquidatior Beira Cold Storage Ltd 1905. If
the buyer claims damages instead of or as an alternative to specific performance, the normal
measure of damages is the difference between the price and the value (that is, the prevailing
market price) on the date delivery ought to have been made, Novik v Benjamin 1972.

Where there is no available market, the damages must be calculated from the best evidence
available. The buyer’s loss of profit resulting from non-delivery of the property may be recovered
if the seller knew at the time of contracting that the buyer required the property for resale or for
use in manufacturing for sale, Plywood Products Ltd v Tropical (Commercial and Industrial) Ltd
1955. It should be noted that when the scope of an exemption clause is in issue, neither an
exemption from liability for representations nor for warranties will relieve the seller from liability
for delivering property of a different kind from that promised, Melfort Motors (Pvt) Ltd v Finance
Corp of Rhodesia Ltd 1975.

Damages
The problem area predominantly revolves around the issue of damages for breach of contract
and the approach which the Supreme Court is likely to adopt.
The general approach of our courts is that the injured party is entitled to be put in the position
he would have been in had the contract been properly performed, so far as this can be done by
the payment of money and without undue hardship to the defaulting party. In order to ensure
simple justice between man and man, the defaulting party’s liability is limited in terms of the
broad principle of causation and remoteness to:
(a) those damages that flow naturally and generally from the kind of breach of contract in
question and which the law
presumes the parties contemplated as a probable result of the breach and
(b) those damages that although caused by the breach of contact are ordinarily regarded in law
as being too remote to be recoverable unless, in the special circumstances attending the
conclusion of the contract, the parties actually or
presumptively contemplated that they would probably result from its breach.
(Shatz Investments v Kalovyrnas 1976)
As was noted by the court in the famous English case of Hadley v Baxendale,
‘where two parties have made a contract which one of them has broken, the damages which the
other party ought
to receive in respect of such breach of contract should be such as may fairly and reasonably be
considered either
arising naturally or such as may reasonably be supposed to have been in the contemplation of

Page 23
Financial Training Company

both parties at the


time they made the contract . . .’
There are a number of cases drawn from the Roman-Dutch law jurisdictions which define the
concept of causation and
remoteness of damages in breach of contract situations in a very neat way.
In Holmdene Brickworks v Roberts Construction Co 1977) R bought bricks from H for the
erection of factory building.
After R had used all the bricks, it discovered that a substantial number were defective, in as
much as they manifested
‘efflorescence’ which made them crumble and decompose. To remedy the position R
demolished the walls containing
defective bricks and rebuilt them with bricks obtained from another source. The cost of doing so
amounted to a sum of R27 000 which R now claimed from H on the basis that it represented
consequential loss suffered by reason of a latent defect in the goods sold.The Transvaal
Provincial Division gave judgment for R and H appealed.
Held;
H’s appeal should be dismissed. Corbett JA said: ‘It seems to me that respondent’s loss was
one flowing naturally and generally from appellant’s breach of contract and one which the law
should presume to have been contemplated by the
parties as a probable result of the breach. It, therefore, falls fairly and squarely within the
category of loss for which
general damages are available. Also in the case of Victoria Falls and Transvaal Power
Company v Consolidated Mines (1915) the court ruled that the sufferer by such a breach should
be placed in the position he would have occupied had the contract been performed,
so far as that can be done by the payment of money and without undue hardship to the
defaulting party. The
reinstatement cannot invariably be complete, for it would be inequitable and unfair to make the
defaulter liable for
special consequences which could not have been in his contemplation when he entered into the
contract.

In light of cases applicable to our jurisdiction it would appear that the High Court’s approach in
awarding
$20 000 000.00 damages as per item (i) and declining to award $5 000 000.00 damages as per
item (ii) is correct.
Damages under item (i) flow naturally from the breach and should be deemed to have been
within the contemplation
of the parties whereas those falling under (ii) are remote. Likewise, the Supreme Court would be

Page 24
Financial Training Company

expected to adopt the same approach.

Damages for sentimental loss in breach of contract

The general approach of our courts in the case of breach of contract is that we are not
concerned with the mental or bodily sufferings of the creditor. The action for damages in such a
case is intended to place the creditor as much as possible in the same position as regards his
property as he would have been in if the contract had been performed. Hence the damages
must have been in satisfaction of some pecuniary loss.
This principle has been restated in a number of cases; Corbett J A in Holmdene Brickworks v
Roberts Construction (1977) made the following observation,
‘The fundamental rule in regard to the award of damages for breach of contract is that the
sufferer should
be placed in the position he would have occupied had the contract been properly performed, so
far as
this can be done by the payment of money and without undue hardship to the defaulting party . .
.’
To ensure that undue hardship is not imposed on the defaulting party the sufferer is obliged to
take reasonable steps to mitigate his loss or damage. In addition the defaulting party’s liability is
limited in terms of the broad principle of contractual causation and remoteness of damages to:
(a) those damages that flow naturally and generally from the kind of breach of contract in
question and which the law presumes the parties contemplated as a probable result of the
breach;
(b) those damages that although caused by breach of contract are ordinarily regarded in law as
being too remote to be recoverable
unless in the special circumstances attending the conclusion of the contract the parties actually
or presumptively
contemplated that they would probably result from its breach Shartz Investments Ltd v
Kalovyrnas (1976).
The general approach of our courts would appear to be that in an ordinary commercial contract
damages may not be claimed for sentimental loss or injured feelings unlike in an action founded
in the law of delict or tort.
In Jockie v Meyer (1945) J, a Chinese and second officer on a British ship having reserved a
room at M’s hotel in Port Elizabeth was allotted the key to room 309 and took occupation. A few
minutes later M sent for J, told him that there was a mistake as to the room number and asked
him to return the key. J did so and was then told that the hotel was full and there was no room

Page 25
Financial Training Company

for him. The real reason for the breach of contract was J’s race. J sued M in the Magistrates
court for two hundred pounds damages and was awarded fifty pounds damages, forty pounds of
which was in respect of the humiliation and annoyance felt by J. The appeal court set aside the
portion of the damages relating to J’s humiliation and annoyance.
Tindall, Judge of Appeal said:-
‘I have come to the conclusion that the ..... Magistrate was not entitled to award damages for
the injury
to the Plaintiff’s feelings which he suffered as a result of the refusal of accommodation by the
defendant’
As an exception to the general rule it can be said that where the pleasure to be obtained from
the proper performance is an important aspect of the contract, as it is when a travel agent
makes specific representations about the facilities and entertainment available at a hotel, or a
photographer undertakes to take wedding photographs the courts may take mental distress into
account in awarding damages. The argument then would be that emotional and mental
satisfaction is an important plank of the contract.
In Jarvis v Swans Tours Ltd (1973) J, a solicitor aged about 35 years booked a 15 day
Christmas winter sports holiday. He did so on the faith of S’s sales brochure which described
the holiday in very attractive terms. In the event the holiday was a great disappointment and
most of the things that had been advertised in the brochure like a house party, skiing etc were
not provided.
Allowing damages for sentimental loss Lord Denning MR said:
‘In a proper case damages for mental distress can be recovered in contract . . . One such case
is for a
holiday or any other contract to provide entertainment and enjoyment. If the contracting party
breaks his
contract, damages can be given for the disappointment, the distress, the upset and the
frustration
caused by the breach.’
In Diesen v Samson (1971), Mrs D engaged S, a professional photographer to take
photographs for her wedding. She paid a deposit for which she was given a receipt. S failed in
breach of his contract to appear at the wedding or at the reception. As a result Mrs D had no
photographs of her wedding and claimed damages for the resulting injury to her feelings. The
court ruled that
damages could competently be awarded.
‘If the contract is not primarily a commercial one in the sense that it affects not the plaintiff’s
business
interests but his personal, social and family interests, the door is not closed to awarding
damages for

Page 26
Financial Training Company

mental suffering should the court think that in the particular circumstances the parties to the
contract
had such damages in their contemplation . . .’
In summation, it can be noted that although the general rule is that our courts will award
damages for patrimonial or material loss in breach of contract cases, in appropriate and limited
cases an exception is made to award damages for sentimental loss as well.

Specific and general damages

It is an established principle of contract that, where there is a material breach, the injured party
may claim from the other party damages such as he can prove he has suffered as a result of
the breach. The injured party is entitled to be put in the hypothetical position he would have
been in had the contract been properly performed, in so far as that can be done by the payment
of money and without undue hardship to the other party. To ensure the other party does not
suffer undue hardship, the injured party must take reasonable steps to mitigate his loss. In
addition, in assessing damages, the court only awards such damages as naturally flow from the
breach (general damages) or as may reasonably be supposed to have been in the
contemplation of the contracting parties as likely to result from the breach (special damages).

These principles have been re-stated by Corbett JA in Holmdence Brickworks (Pvt) Ltd v
Roberts Construction Co Ltd (1977) where he aptly underscores the following ‘the fundamental
role in regard to the award of damages for breach of contract is that the victim should be placed
in the position he would have occupied had the contract been properly performed, so far as this
can be done by payment of money and without undue hardship on the defaulting party’.

Be that as it may, the approach to the court in this case will depend on whether or not there was
a breach by Virgin Airlines. It is contended inter alia on behalf of Virgin Airlines that they are
exempted from liability through the operation of the alleged exemption clause in the contract.
The law relating to exemption clauses is very trite. At common law, for a party to be exempted
the exemption clause must be reasonable and it must not go to the root of the contract as was
enunciated in the celebrated case of Hubert Davies v Crane Hire (1995). This position was
codified and classified in the Consumer Contracts Protection Act. Essentially the piece of
legislation seeks to protect vulnerable consumers from unreasonable and vague contractual
provisions to the extent that the court was given the power to strike down any unfair clauses in
consumer contracts. It is likely that in view of this piece of legislation,
the High Court of Zimbabwe is likely to strike out the exemption clause in question and as such,
the question which shall remain unanswered is that of damages.

Page 27
Financial Training Company

In Victoria Falls and Transvaal Power Company Ltd v Consolidated Langlaagte (1915) the court
had occasion to explain the issue of damages where it stated that ‘the defaulting party’s liability
is limited to the broad principle of causation and remoteness.’ This essentially points to those
damages that flow naturally and generally from the kind of breach of contract in question and
which the law presumes the parties contemplated as a probable result of the breach and those
damages that, although caused by the breach of contract are ordinarily regarded in law as being
too remote to be recoverable. This is so unless in the special circumstances attending the
conclusion of the contract, the parties actually or presumptively contemplated that they would
probably result from its breach.’

As regards claims (a) to (c) clearly these are general damages. However, on claim (a), the court
is likely to take into consideration the aspect of supervening impossibility in the form of vis major
caused by adverse weather conditions. At most the court is likely to grant damages for one
night, as the damages for the other night were due to no-one’s fault but an act of God. As
regards special damages, contemplation is pre-requisite if one is to succeed. The South African
position was put forward in Lavery and Co Ltd v Jungheinrich (1931) and upheld in Shatz
Investments (Pty) Ltd v Kalovyrnas (1976) that the defaulting party’s knowledge of special facts
must have been imparted to him in circumstances amounting to a tacit contract that he would
undertake liability for special damages should a breach occur. The Zimbabwean position here,
however, remains unclear.

Specific performance of the contract

An offer is an unconditional declaration by the offeror of his intention to conclude a contract


while all the terms on which he is prepared to contract are set out in this declaration. The
primary requirements of a valid offer are as follows:
(a) the offer must be clear and unambiguous. If any of the material terms of the offer are vague
and obscure or ambiguous, the offeree will not be able to form an idea of what the offeror has in
mind.
(b) the offer must be complete
(c) the offer must be communicated to the offeree. An offer is usually addressed to a specific
person but it can be made to the world at large (the general public). If an offer is addressed to a
specific person it cannot be accepted by a third party. (Baker v Crowrie (1962)
(d) The offer must be made with the intention that is shall serve as an offer so that it may be
accepted and result in a contract coming into existence.

Page 28
Financial Training Company

In Hyde v Wrench (1840) the defendant offered to sell land to the plaintiff for £1000·00. Plaintiff
then agreed to pay £950·00. The defendant rejected this. Plaintiff then agreed to pay £1000·00
after all. But by now the defendant no longer wished to sell. The plaintiff then sued for breach of
contract and the court ruled that the plaintiff had made a counter offer which ‘rejected the offer
previously made by the defendant’. Thus he could not afterwards ‘revive the proposal of the
defendant by tendering an acceptance of it’ and therefore there existed no obligation of any sort
between the parties.
The fundamental principle here is that a counter offer revokes the original offer to which the
counter offeror may therefore not return unless the original offeror agrees. Also in the case of
Watermeyer v Murray (1911) Murray sought to buy Watermeyer’s farm for £1700·00.
Watermeyer offered to sell at that price provided Murray paid all expenses plus £1000
immediately the agreement was signed. Murray agreed, but then through his attorneys
unilaterally drew up and signed an agreement stipulating that the £1000·00 was to be paid only
after the current lease on the farm had expired. Watermeyer rejected this new arrangement,
Murray then tried to revert to the original offer but Watermeyer now refused to sell. Murray sued
for specific performance or alternatively £1000 in damages for breach of contract.
The court ruled that there was no contract and therefore no breach, because as soon as the
defendant’s offer to sell on certain terms was rejected by the plaintiff making a counter offer to
buy on different terms, it follows that the defendant’s offer was no longer open for acceptance.
The principle underpinned by the two cases is that where an offer has been revoked by a
counter-offer and the original offerer has in turn rejected such counter offer, he cannot be bound
by any subsequent acceptance of his original offer unless he so wishes.

Specific performance as a remedy


Specific performance is a remedy aimed at the fulfilment of the contract because when it is
claimed by the innocent party, he is trying to achieve the result envisaged at the conclusion of
the contract by the parties. In general, the injured party has a right to claim specific performance
(an order compelling a party to a contract who is in breach, to perform his obligation in the
manner required by the terms of the contract) if ready to carry out his obligations under it.
However the courts will exercise a discretion in determining whether or not decrees of specific
performance should be made. In Farmers’ Co-op Society v Berry (1921) B who was a member
of F and as such obliged to send in his whole crop to F, notified it that he had a crop of 1200
bags of mealies but later refused to deliver any to F. F then sued B asking for specific
performance of a contract to deliver 1200 bags and in the alternative, damages and addressing
the question of specific performance the court ruled that:
‘Prima facie every party to a binding agreement who is ready to carry out his own obligation

Page 29
Financial Training Company

under it has a right


to demand from the other party, so far as it is possible a performance of his undertaking in
terms of the contract.
It is true that the courts will exercise a discretion in determining whether or not decrees of
specific performance
should be made.’
The discretion which the court enjoys in awarding (or declining to award) must be exercised
judicially and is not confined to specific types of cases, nor is it circumscribed by rigid rules.
Each case must be judged in light of its own specific and peculiar circumstances. The injured
party usually adds to his prayer for specific performance an alternative prayer for damages. As
was noted by the court in Woods v Walters (1921)
‘It is common practice to add to a prayer for specific performance an alternative prayer for
damages . . .’
Examples of the grounds on which the courts have exercised their discretion in refusing to order
specific performance although performance was not impossible, may be mentioned
(a) where damages would adequately compensate the injured party, for example, if the subject
matter of the contract can easily be bought on the open market as is the case with items like
cars, bicycles, shares etc.
(b) where it is impossible to effect
In Shakinovsky v Lawson and Smulowitz (1904) where the plaintiff purchaser sued for the
specific performance of a contract of sale of a shop and business with no alternative claim for
damages. L could not give specific performance as he had subsequently sold the same
business to Smulowitz who had no notice of the previous sale. The court said that it was not
practicable to award specific performance and the purchaser had to contend with damages.
‘Now a plaintiff has always the right to claim specific performance of a contract which the
defendant has refused
to carry out but it is in the discretion of the court either to grant such an order or not. It will
certainly not decree
specific performance where the subject matter of a contract has been disposed of to a bona fide
purchaser or
where it is impossible for specific performance to be effected, in such cases it will allow an
alternative of damages.’
(c) where the subject matter of the contract involves the rendering of services of a personal
nature
Since it is undesirable and indeed in some cases impossible to compel an unwilling party to
maintain continuous personal relations with another it is well established that a contract for
personal services is not specifically enforceable at the suit of either party.
‘The courts’, said Jessel, MR ‘have never dreamt of enforcing agreements strictly personal in

Page 30
Financial Training Company

their nature, whether they are agreements of hiring and service, being the common relationship
of master and servant, or whether they are agreements for the purpose of pleasure or for the
purpose of scientific pursuits, or for the purpose of charity or philanthropy.’ (Rigby v Cannol
1880).
(d) where the order would work great hardship on the defaulting party or the public at large
If the effect of a decree of specific performance is to cause undue and great hardship to the
defendant and members of the public alike the courts are unlikely to award it. In Haynes v
Kingwilliamstown Municipality (1951) the defendant contracted to supply the plaintiff with 250
000 gallons of water per day for a number of years. After some time the defendant was unable
to honour the agreement because of a crippling drought. An action for specific performance by
the plaintiff was dismissed by the court because full compliance with the agreement would have
resulted in a positive danger to the health of the Municipality’s citizens. In breach of contract
cases it is quite clear that the courts award specific performance on a discretionary basis rather
than as a matter of course.

Undue hardship
The general approach of the Zimbabwean courts in the case of breach of contract is that they
are not concerned with the mental or bodily sufferings of the creditor. The action for damages
in such a case is intended to place the creditor as much as possible in the same position as
regards his property as he would have been in if the contract had been performed. Hence the
damages must have been in satisfaction of some pecuniary loss.

This principle has been restated in a number of cases. Corbett J A in Holmdene Brickworks v
Roberts Construction (1977) made the following observation, ‘The fundamental rule in regard to
the award of damages of breach of contract is that the sufferer should be placed in the position
he would have occupied had the contract been properly performed, so far as this can be done
by the payment of money and without undue hardship to the defaulting party . . .’

To ensure that undue hardship is not imposed on the defaulting party the sufferer is obliged to
make reasonable steps to mitigate his loss or damage. In addition the defaulting party’s liability
is limited in terms of the broad principle of contractual causation and remoteness of damages
to:

(a) those damages that flow naturally and generally from the kind of breach of contract in
question and which the law presumes
the parties contemplated as a probable result of the breach;

Page 31
Financial Training Company

(b) those damages that although caused by breach of contract are ordinarily regarded in law as
being too remote to be recoverable unless in the special circumstances attending the
conclusion of the contract the parties actually or presumptively contemplated that they would
probably result from its breach Shartz Investments Ltd v Kalovyrnas (1976).

The general approach of our courts would appear to be that in an ordinary commercial contract
damages may not be claimed for sentimental loss or injured feelings unlike in action founded in
the law of delict or tort.
In Jockie v Meyer (1945) J, a Chinese and second officer on a British ship having reserved a
room at M’s hotel in Port Elizabeth was allotted the key to room 309 and took occupation. A few
minutes later M sent for J, told him that there was a mistake as to the room number and asked
him to return the key. J did so and was then told that the hotel was full and there was no room
for him. The real reason for the breach of contract was J’s race. J sued M in the Magistrates
Court for £200 damages and was awarded £50 damages £40 of which was in respect of the
humiliation and annoyance felt by J. The appeal court set aside the portion of the damages
relating to J’s humiliation and annoyance.

Tindall, Judge of Appeal said:


‘I have come to the conclusion that the . . . Magistrate was not entitled to award damages for
the injury to the Plaintiff’s feelings which he suffered as a result of the refusal of accommodation
by the defendant’
As an exception to the general rule it can be said that where the pleasure to be obtained from
the proper performance is an important aspect of the contract, as it is when a travel agent
makes specific representations about the facilities and entertainment available at a hotel, or a
photographer undertakes to take wedding photographs the courts may take mental distress into
account in awarding damages. The argument then would be that emotional and mental
satisfaction is an important plank of the contract.

In Jarvis v Swans Tours Ltd (1973) J, a solicitor aged about 35 years booked a 15 day
Christmas winter sports holiday. He did soon the faith of S’s sales brochure, which described
the holiday in very attractive terms. In the event the holiday was a great disappointment and
most of the things that had been advertised in the brochure like a house party, skiing etc were
not provided.

Allowing damages for sentimental loss Lord Denning MR said:


‘In a proper case damages for mental distress can be recovered in contract . . . One such case
is for a holiday or any other contract to provide entertainment and enjoyment. If the contracting
party breaks his contract, damages can be given for the disappointment, the distress, the upset

Page 32
Financial Training Company

and the frustration caused by the breach.’


In Diesen v Samson (1971), Mrs D engaged S, a professional photographer to take
photographs for her wedding. She paid a deposit for which she was given a receipt. S failed in
breach of his contract to appear at the wedding or at the reception. As a result Mrs D had no
photographs of her wedding and claimed damages for the resulting injury to her feelings. The
court ruled that damages could competently be awarded.

‘if a contract is not primarily a commercial one in the sense that it affects not the plaintiff’s
business interests but his personal, social and family interests, the door is not closed to
awarding damages for mental suffering should the court think that in the particular
circumstances the parties to the contract had such damages in their contemplation . . .’
In summation, it can be noted that although the general rule is that our courts will award
damages for patrimonial or material loss in breach of contract cases, in appropriate and limited
cases an exception is made to award damages for sentimental loss as well.

Supervening impossibility

Performance of a contract is the most common method of discharge of contracts. Cancellation


resulting from repudiation or breach is probably the next most common. It was said in Strachan
v Lloyd Levy (1923) that because contracts are made by agreement so may they be unmade by
agreement but they cannot be unilaterally varied or discharged. Thus variation and discharge of
contracts are all as a result of the act of the parties to the contract.

However, variation or discharge of contracts can also take place as a result of the operation of
law. This will happen if it is interrupted by irresistible force of inevitable accident of a contract
requiring continuity of performance. However, if this happens in a contract of employment, it will
not be treated as a supervening impossibility because it would obviously be unfair to treat the
contract as discharged when the interruption might turn out to be of short duration.

Beretta v Rhodesia Railways (Ltd) 1947 shows how in such a case the contract is not
discharged by operation of law but may be cancelled by the party to whom the performance is
due if the interruption continues for an unreasonably long time.

Irresistible force includes legislation or act of state making performance illegal, such as a
declaration of war ; but in William Maine & Son (Pvt) Ltd v Rhodesia Railways 1976 a ministerial

Page 33
Financial Training Company

directive given without statutory authority was held not to be irresistible force, so obedience to it
did not excuse non-performance. It will not be a case of supervening impossibility if the parties
did foresee and made provision for or accepted the risk of the very event that has happened.

Page 34

You might also like