You are on page 1of 5

BI-74 INSTALLATION DAILY REPORT SUMMARY

PROJECT / AREA /
DATE 12/8/2021 PROGRAM RDNE REGION CENTRAL AREA REPORT NO. TEAM NOS.

SITE / LOCATION, TOOL BOX SITE WIRING & INSULATION & REDLINE
BUILDING CODE & FORECASTED (EQUIPMENT LIST) SCOPE ITEM EQUIPMENT MODEL EQUIPMENT TERMINATION LABELING RFI CONTINUITY REMARKS
MEETING PREPARATION DRAWING
ROOM No. INSTALLATION TEST

Supervisor (THALES) Supervisor (BAZY) Area Coordinator (THALES) Area Coordinator (BAZY)

Name VICTORINO VERA CRUZ TAHSIN RAZA

Date 12/8/2021 12/8/2021 12/8/2021 12/8/2021

Signature
BI-74 INSTALLATION DAILY REPORT SUMMARY
PROJECT / AREA /
DATE 10/16/2010 PROGRAM RDNE REGION CENTRAL AREA REPORT NO. 1 TEAM NOS. 2, 3, 4

SITE / LOCATION, TOOL BOX SITE WIRING & INSULATION & REDLINE
BUILDING CODE & FORECASTED (EQUIPMENT LIST) SCOPE ITEM EQUIPMENT MODEL EQUIPMENT TERMINATION LABELING RFI CONTINUITY REMARKS
MEETING PREPARATION DRAWING
ROOM No. INSTALLATION TEST

DHAB1800 ON-SITE DELIVERY OF MATERIALS ✘ DONE: 10/16/2010

208 DHAB1800-R00-02X ACCESS HP 3500yl-24P ✘ ✘ DELIVERED: 10/16/2010 INSTALLED: 10/16/2010

COMMS ROOM DHA-1800-PE6 DISTRIBUTION JUNIPER MX480 ✘ ✘ DELIVERED: 10/16/2010 INSTALLED: 10/16/2010

COMMS ROOM DHAB1800-UPS-1U UPS UPS-5KVA ✘ ✘ DELIVERED: 10/16/2010 INSTALLED: 10/16/2010

(STACK) HP 3500yl-
COMMS ROOM DHAB1800-R00-01X ACCESS ✘ ✘ DELIVERED: 10/16/2010 INSTALLED: 10/16/2010
24P
(STACK) HP 3500yl-
COMMS ROOM DHAB1800-R00-03X ACCESS ✘ ✘ DELIVERED: 10/16/2010 INSTALLED: 10/16/2010
24P

DHAB0325

(STACK) HP 3500yl- GOT PERMISSION TO ACCESS THE ROOM BUT NO SPACE


218B DHAB0325-R218B-07X ACCESS ✘
24P AVAILABLE TO INSTALL THE HP SWITCHES. SITE
(STACK) HP 3500yl- SUGGESTED FOR HOT-CUT PROCEDURE; TO BE
218B DHAB0325-R218B-08X ACCESS CONFIRMED WITH AIT & SAPMT
24P

Supervisor (THALES) Supervisor (BAZY) Area Coordinator (THALES) Area Coordinator (BAZY)

Name REYNALDO BASTRO VICTORINO VERA CRUZ TAHSIN RAZA

Date 10/16/2010 10/16/2010 10/16/2010 10/16/2010

Signature
BI-74 INSTALLATION DAILY REPORT SUMMARY
PROJECT / AREA /
DATE 10/17/2010 PROGRAM RDNE REGION CENTRAL AREA REPORT NO. 2 TEAM NOS. 2, 3, 4

SITE / LOCATION, TOOL BOX SITE WIRING & INSULATION & REDLINE
BUILDING CODE & FORECASTED (EQUIPMENT LIST) SCOPE ITEM EQUIPMENT MODEL EQUIPMENT TERMINATION LABELING RFI CONTINUITY REMARKS
MEETING PREPARATION DRAWING
ROOM No. INSTALLATION TEST

DHAB1965 ON-SITE DELIVERY OF MATERIALS ✘ ✘ DONE: 10/17/2010

632 DHA-1965-PE24 DISTRIBUTION JUNIPER MX480 ✘

632 DHAB1965-UPS-1U UPS UPS-5KVA NO SPACE TO INSTALL THE NEW RACK; NEEDS REMEDY
REQUEST TO DETERMINE THE RIGHT LOCATION OF THE
632 DHAB1965-RKTBD01 NEW RACK CPI - 7 Feet Rack NEW RACK AND HAS TO BE DECIDED BY AIT & SAPMT

632 DHAB1965-R632-03X ACCESS HP 3500yl-24P

635 DHAB1965-R635-01X ACCESS HP 5406zl-72P ✘ ✘ ✘ DELIVERED: 10/17/2010 INSTALLED: 10/17/2010

655 DHAB1965-R655-02X ACCESS HP 5406zl-72P ✘ ✘ ✘ DELIVERED: 10/17/2010 INSTALLED: 10/17/2010

731 DHAB1965-R731-03X ACCESS HP 8212zl<192 ports ✘ ✘ ✘ DELIVERED: 10/17/2010 INSTALLED: 10/17/2010

835 DHAB1965-R835-05X ACCESS HP 8212zl<192 ports ✘ ✘ ✘ DELIVERED: 10/17/2010 INSTALLED: 10/17/2010

853 DHAB1965-R853-06X ACCESS HP 8212zl<192 ports ✘ ✘ ✘ DELIVERED: 10/17/2010 INSTALLED: 10/17/2010

757B DHAB1965-R757B-04X ACCESS HP 8212zl<192 ports ✘ ✘ ✘ DELIVERED: 10/17/2010 INSTALLED: 10/17/2010

DHAB0840
IBM eServer Blade
Center H Chassis w/
R1000 2x2900w PSU ✘ ✘ ✘ INSTALLED: 10/17/2010
DHA-840-BC-01 NMS UltraSlim Enhance
Burner
Observer Reporting
R1000 NQ-ORS-840-01 NMS ✘ ✘ INSTALLED: 10/17/2010
Server,
Observer Suite, NIMS
R1000 NQ-OSS-840-01 NMS ✘ ✘ INSTALLED: 10/17/2010
server

R1000 AAA Server ✘ ✘ INSTALLED: 10/17/2010


AAA SERVER NMS

Supervisor (THALES) Supervisor (BAZY) Area Coordinator (THALES) Area Coordinator (BAZY)

Name VICTORINO VERA CRUZ TAHSIN RAZA

Date 10/17/2010 10/17/2010 10/17/2010 10/17/2010

Signature
BI-74 INSTALLATION DAILY REPORT SUMMARY
PROJECT / AREA /
DATE 10/18/2010 PROGRAM RDNE REGION CENTRAL AREA REPORT NO. 3-A TEAM NOS. 2, 3, 4

SITE / LOCATION, TOOL BOX SITE WIRING & INSULATION & REDLINE
BUILDING CODE & FORECASTED (EQUIPMENT LIST) SCOPE ITEM EQUIPMENT MODEL EQUIPMENT TERMINATION LABELING RFI CONTINUITY REMARKS
ROOM No. MEETING PREPARATION INSTALLATION TEST DRAWING

DHAB1965 ON-SITE DELIVERY OF MATERIALS ✘ ✘ DONE: 10/17/2010

don
632 DHA-1965-PE24 DISTRIBUTION JUNIPER MX480 ✘ ✘ ✘ ✘ DELIVERED: 10/17/2010 INSTALLED: 10/18/2010
e
don
632 DHAB1965-UPS-1U UPS UPS-5KVA ✘ ✘ ✘ DELIVERED: 10/17/2010 INSTALLED: 10/18/2010
e
don
632 DHAB1965-RKTBD01 NEW RACK CPI - 7 Feet Rack ✘ ✘ ✘ DELIVERED: 10/17/2010 INSTALLED: 10/18/2010
e
don
632 DHAB1965-R632-03X ACCESS HP 3500yl-24P ✘ ✘ ✘ DELIVERED: 10/17/2010 INSTALLED: 10/18/2010
e
635 DHAB1965-R635-01X ACCESS HP 5406zl-72P ✘ ✘ ✘ DELIVERED: 10/17/2010 INSTALLED: 10/17/2010

655 DHAB1965-R655-02X ACCESS HP 5406zl-72P ✘ ✘ ✘ DELIVERED: 10/17/2010 INSTALLED: 10/17/2010

731 DHAB1965-R731-03X ACCESS HP 8212zl<192 ports ✘ ✘ ✘ DELIVERED: 10/17/2010 INSTALLED: 10/17/2010

835 DHAB1965-R835-05X ACCESS HP 8212zl<192 ports ✘ ✘ ✘ DELIVERED: 10/17/2010 INSTALLED: 10/17/2010

853 DHAB1965-R853-06X ACCESS HP 8212zl<192 ports ✘ ✘ ✘ DELIVERED: 10/17/2010 INSTALLED: 10/17/2010

757B DHAB1965-R757B-04X ACCESS HP 8212zl<192 ports ✘ ✘ ✘ DELIVERED: 10/17/2010 INSTALLED: 10/17/2010

DHAB0320 ON-SITE DELIVERY OF MATERIALS ✘ ✘ DONE: 10/18/2010

104 DHA-0320-PE32 DISTRIBUTION JUNIPER MX480 ✘ ✘ DELIVERED: 10/18/2010 INSTALLED: 10/18/2010

104 DHAB0320-UPS-1U UPS UPS-5KVA NOT AVAILABLE (NOT STAGED YET)

104 DHAB0320-R00-01X ACCESS HP 8212zl<192 ports ✘ ✘ DELIVERED: 10/18/2010 INSTALLED: 10/18/2010

DHAB2202 ON-SITE DELIVERY OF MATERIALS ✘ ✘ DONE: 10/13/2010

135 DHAB2202-R135-01X ACCESS HP 5406zl-72P ROOM STILL NOT ACCESSIBLE; NEED SPECIAL ACCESS
✘ ✘ (10/18/2010); RESCHEDULED FOR TOMORROW

135 DHAB2202-R135-02X ACCESS HP 8212zl<192 ports ROOM STILL NOT ACCESSIBLE; NEED SPECIAL ACCESS
✘ (10/18/2010); RESCHEDULED FOR TOMORROW

259 DHAB2202-R259-01X ACCESS HP 8212zl<192 ports ✘ ✘ ✘ DELIVERED: 10/13/2010 INSTALLED: 10/13/2010

159A DHA-2202-PE37 DISTRIBUTION JUNIPER MX480 ✘


Materials Delivered in 10/13/2010; Only HP 8212zl
installed in 10/13/2010; As per IFC Drawing, there is no
159A DHAB2202-UPS-1U UPS UPS-5KVA space available to install the MX480 and UPS in the given
location or Rack ID; need to be resolved by concerned
parties such as AIT, PMT & Data Design Team
(Rescheduled for tomorrow)
159A DHAB2202-R159-02X ACCESS HP 8212zl>192 ports ✘ ✘

Supervisor (THALES) Supervisor (BAZY) Area Coordinator (THALES) Area Coordinator (BAZY)

Name VICTORINO VERA CRUZ TAHSIN RAZA


Date 10/18/2010 10/18/2010 10/18/2010 10/18/2010

Signature
BI-74 INSTALLATION DAILY REPORT SUMMARY
PROJECT / AREA /
DATE 12/21/2010 PROGRAM RDNE REGION CENTRAL AREA REPORT NO. TEAM NOS. 2, 3, 4

SITE / LOCATION, TOOL BOX SITE WIRING & INSULATION & REDLINE Total no. of
BUILDING CODE & FORECASTED (EQUIPMENT LIST) SCOPE ITEM EQUIPMENT MODEL MEETING PREPARATION EQUIPMENT TERMINATION LABELING RFI CONTINUITY DRAWING Idle Working REMARKS
ROOM No. INSTALLATION TEST Hours

8:00 TEMPORARY ACCESS NOT DONE BY STEZA

YANB0409

GATE PASS FOR OUR TOOLOS


JEDDAH130
JEDDAH209

8:00 TEMPORARY ACCESS NOT DONE BY STEZA


JEDSDAH302

Supervisor (THALES) Supervisor (BAZY) Area Coordinator (THALES) Area Coordinator (BAZY)
Name VICTORINO VERA CRUZ TAHSIN RAZA

Date

Signature