You are on page 1of 14

DAILY PROGRESS REPORT ( WORK EXECUTED ON 09.01.

10 )
No
S. No.

1
2

4
5

CONSTRAINTS:-

WSW-11 ( Flow line 315 mtrs )

1
2
3
4
5
6
1
2
3
4

1
2
3
4
5
6
7
9
10
11
12
13
14
15
16
17
18
19
20
21
ILY PROGRESS REPORT ( WORK EXECUTED ON 09.01.10 )
NSF/FSF-4/DPR/ 10 / 01 / 10

Highlights of the Day

Site Activities

WSW -11 A/G spool erection and joint welding completed @ well side.
WSW -11 A/G spool erection and box up @ WSW-03.

WSW-11 Electrical work in RMU and Transformer completed.

WSW-11 erection of Fence for RMU building completed.


WSW-11 NDT of A/G joint welding completed.

Fabrication Yard.

House keeping of Pipe fittings materials in Yard.

NSTRAINTS:-

SW-11 ( Flow line 315 mtrs )

Piping & Mechanical ( Work Shop )


Pre-fabrication of crash barrier for well head
RMU work
A/G Spool fabrication .
NDT & Radiography of A/G weld joints
Support fabrication
A/G Spool blasting & primer .
INSTALLATION
1 - Civil Works at site
ROW for flow line
Excavation works
Back filling
On Pad Piling work
2 - Piping, Mechanical ( Site Works )
Stringing of flow line pipes
Welding of flow line pipe joints
NDT & Radiography of weld joints
Coating of flow line weld joints
Holiday Test of Joint coating
Lowering of pipe sections to trench
Field tie in works
RT of the tie-in joints
Joint coating of field tie-in joints
Pigging of pipeline
Water filling & hydrotesting
Flow line tie in with well head Hook up
Piling pipe shifting
Piling pipe cutting , cap plate welding and Support Installation
Installation of A/G spools
A/G Spool Tie in Joint Welding
box up hook up spools A/G
NDT of A/G Tie in Joints
Hook up hydrotesting
Touch up Painting

Kiran Kumar D
Mechanical Supervisor
Actual
Scope REMARKS
Previous Today Cumm.
10.01.2010

100 100 0 100


100 100 0 100
100 100 0 100
100 100 0 100
100 100 0 100
100 100 0 100
100 100 0 100
100 100 0 100
100 0 0 0
100 100 0 100

100 100 0 100


100 98 0 98
100 100 0 100
100 100 0 100
100 100 0 100
100 0 20 20
100 0 0 0
100 0 0 0
100 0 0 0
100 0 0 0
100 0 0 0
100 0 50 50
100 100 0 100
100 100 0 100
100 90 5 95
100 100 0 100
100 40 40 80
100 0 100 100
100 0 0 0
100 0 0 0

You might also like