You are on page 1of 20

Kerala State Electricity Board

Abstract

KSEB - Introducing Uniform Labour Data – Orders Issued


--------------------------------------------------------------------------------------------------------------
Distribution Profit Centre
BO (FM) (Genl) No 226/2011 (DPC II/AE/Proposal.07 /2010)Dated Thiruvananthapuram, 18.01.2011
--------------------------------------------------------------------------------------------------------------
Read: 1 BO (FM) No. 2899/2008 (CP/R&P/Plg.1/AP/2008-09) dated 27.11.2008
2 Note No CP/R&P/Plg.1/AP/2011-12 dated 28.09.2010of Chief Engineer (Corporate
Planning)
3 Minutes of Meeting of representatives of KSEB and Contract Workers’ Association,
held on 04.03.2010
4 Ltr No DPC II/General.09/2010-11 dated 16.04.2010 of Member (Distribution)
5 BO (FB) No 2360/2010 (MG/General/2003) dated 09.09.2010
6 Recommendation of Distribution Advisory Committee
Order
The estimates for various works in Distribution Wing are prepared based on labour data. At present
these labour data are prepared at Electrical Circle / Electrical Division level, based on the prevailing
PWD Schedule of Rates. Preparation of the labour data in the field level has been a laborious and
time-consuming process. Rates differ widely from one office to another, even in the same region.
The man-hour requirement anticipated for the same work varies from one Electrical Circle to another
and from one Electrical Division to another, which is not logical.
Board has authorized a committee for simplification of procedures related with the execution of
distribution works. This committee also had recommended to have state wide uniform labour data
and suggested that items in the labour data need to be properly loaded so as to rationalize the
works. Board vide order 1st cited approved the report of that committee ‘in principle’. Contractor
Workers’ Associations, in its various representations to the Board also requested the Board to have
uniform labour data across the State for various works under Distribution Wing. Meanwhile Sri Kalid
P, Assistant Engineer, Electrical Division Manjeri and Sri ET Murali Mohan, Assistant Engineer,
Electrical Division Ponnani conducted a detailed work-study for assessing the man-hour requirement
for various works and proposed a uniform labour data and developed a spreadsheet template for
simplifying the office works associated with various Distribution Works. The specification and rates
were scrutinised and modified by the Distribution Advisory Committee based on the prevailing rates
in various regions.
Board after considering the issues in detail, approved Uniform Labour Data given in Annexure
appended to this Board Order. The rates are inclusive of Contractors’ Profit @ 10%.Rates for works
which are not included in the uniform labour data at present shall be approved by the concerned
Executive Engineer / Deputy Chief Engineer, as per the prevailing practice. For Hilly areas 15 %
increase in the rates may be allowed. Deputy Chief Engineers shall identify the terrains where such
higher rates are applicable. These rates will be applicable for works for which quotations / tenders
are invited in future only.
Orders are issued accordingly
By Order of the Board
Sd/-
B Mohanan
Secretary

Page 1 of 20
To
Chief Engineer (Distribution South / Central / North)
Copy to:
LA&DEO / Chief Vigilance Officer / Financial Advisor
All Deputy Chief Engineers of Electrical Circles
Director (IT) / Special Officer (Revenue)
TA to Chairman / Member (Distribution)/ Member (Trans)/ Member (Gen)
All Executive Engineers of Electrical Divisions
All Regional Audit Officers
Resident Audit Officer, ECA, Vydyuthi Bhavanam
All Assistant Executive Engineers, Electrical Sub Divisions / PRO
All Assistant Engineers, Electrical Sections
PA to Member (Finance)/ CA to Secretary
The Fair Copy Superintendent / Library/ Stock File

Forwarded / By Order

Assistant Engineer

Page 2 of 20
Uniform Labour Data for Distribution Works in KSEB - Based on PWD Schedule of Rates 2010
Appended to BO (FM) (Genl) No 226/2011 (DPC II/AE/Proposal.07 /2010) dated 18.01.2011

Amount
Sl No Detailed description of work Unit including
10% CP
HT LINE WORKS

HC 01 Surveying one km 11kV line using Theodilite km 1650.00

HC 02 Surveying one km 11kV line using Ranging Rod km 1106.00

Transporting one HT TW/RSJ/Rail pole by Hand cart - for an average distance of one km
HC 03 P/km 206.00
(limited to 1 km).
Transporting one HT TW/RSJ/Rail pole by Hand cart - for every additional km (limited to 4
HC 04 P/km 103.00
km).
Transporting one HT PSC/RCC pole by Hand cart - for an average distance of one km
HC 05 P/km 281.00
(limited to 1 km).
Transporting one HT PSC/RCC pole by Hand cart - for every additional km (limited to 4
HC 06 P/km 140.00
km).
Transporting 'A' type special pole of all sizes by Hand cart - for an average distance of one
HC 07 P/km 347.00
km (limited to 1 km).
Transporting 'A' type special pole of all sizes by Hand cart - for every additional km (limited
HC 08 P/km 173.00
to 4 km).
Transporting Four legged 'A' type special pole of all sizes by Hand cart - for an average
HC 09 P/km 487.00
distance of one km (limited to 1 km).
Transporting Four legged 'A' type special pole of all sizes by Hand cart - for every additional
HC 10 P/km 243.00
km (limited to 4 km).
Transporting one HT TW/RSJ/Rail pole by Head load - for an average distance of one km
HC 11 P/km 421.00
(Normally limited to 0.3 km)
Transporting one HT PSC/RCC pole by Head load - for an average distance of one km
HC 12 P/km 784.00
(Normally limited to 0.3 km)
Transporting 'A' type special pole of all sizes by Head load - for an average distance one km
HC 13 P/km 916.00
(Normally limited to 0.3 km)
Transporting Four legged 'A' type special pole of all sizes by Head load - for an average
HC 14 P/km 1271.00
distance one km (Normally limited to 0.3 km)
Fitting and erecting one HT TW/RSJ/Rail Single Pole in position, including fitting cross
HC 15 arm, digging and back filling pit in ordinary soil, drawing sufficient length of GI earthing No 561.00
leads to the ground for earthing (excluding provision of earthinging).
Fitting and erecting one HT PSC/RCC Single Pole in position, including fitting cross arm,
HC 16 digging and back filling pit in ordinary soil, drawing sufficient length of GI earthing leads to No 990.00
the ground for earthing (excluding provision of earthing).
Fitting and erecting one HT 'A' type Single Pole in position, including fitting cross arm,
HC 17 digging and back filling pit in ordinary soil, drawing sufficient length of GI earthing leads to No 1254.00
the ground for earthing (excluding provision of earthing).
Fitting and erecting one HT Four legged 'A' type Single Pole in position including fitting
HC 18 cross arm, digging and back filling pit in ordinary soil, drawing sufficient length of GI No 1815.00
earthing leads to the ground for earthing (excluding provision of earthing).
Additional rate for providing one disc set, complete, per phase on any type of HT pole for
HC 19 No 45.00
making cut point.
Fitting and erecting one HT Double Pole Structure using TW/RSJ/Rail pole in position
including fitting 2 Nos channel cross arm, digging and back filling pit in ordinary soil,
HC 20 No 1762.00
drawing sufficient length of GI earthing leads to the ground for earthing (excluding
provision of earthing).

Page 3 of 20
Amount
Sl No Detailed description of work Unit including
10% CP
Fitting and erecting one HT Double Pole Structure using PSC/RCC pole in position
including fitting 2 Nos channel cross arm, digging and back filling pit in ordinary soil,
HC 21 No 2620.00
drawing sufficient length of GI earthing leads to the ground for earthing (excluding
provision of earthing).
Fitting and erecting one HT Double Pole Structure using 'A' type pole in position including
fitting 2 Nos channel cross arm, digging and back filling pit in ordinary soil, drawing
HC 22 No 3148.00
sufficient length of GI earthing leads to the ground for earthing (excluding provision of
earthing).
Fitting and erecting one HT Double Pole Structure using Four legged 'A' type pole in
position including fitting 2 Nos channel cross arm, digging and back filling pit in ordinary
HC 23 No 4270.00
soil, drawing sufficient length of GI earthing leads to the ground for earthing (excluding
provision of earthing).
Fitting and providing one HT Stay for 11 kV pole, including digging and back filling pit in
HC 24 No 408.00
ordinary soil.
Fitting and providing one Strut using HT TW/RSJ/Rail pole, including digging and back
HC 25 No 495.00
filling pit in ordinary soil.
Fitting and providing one Strut using HT PSC/RCC pole including digging and back filling
HC 26 No 924.00
pit in ordinary soil.
Fitting and providing one Strut using 'A' type pole, including digging and back filling pit in
HC 27 No 1188.00
ordinary soil.
Fitting and providing one HT Fly stay for 11 kV pole using HT TW/RSJ/Rail pole, including
HC 28 digging and back filling pits in ordinary soil drawing sufficient length of GI earth leads to No 1014.00
the ground for earthing (excluding provision of earthing).
Fitting and providing one HT Fly stay for 11 kV pole using HT PSC/RCC pole including
HC 29 digging and back filling pits in ordinary soil drawing sufficient length of GI earth leads to No 1443.00
the ground for earthing (excluding provision of earthing).
Fitting and providing one HT Fly stay for 11 kV pole using 'A' type pole including digging
HC 30 and back filling pits in ordinary soil drawing sufficient length of GI earth leads to the ground No 1707.00
for earthing (excluding provision of earthing).

Insertion of one HT TW/RSJ/Rail pole in existing OH line including in digging &


HC 31 backfilling pit in Ordinary Soil, fitting cross arm, insulators, binding etc., drawing sufficient No 606.00
length of GI earth leads to the ground for earthing (excluding provision of earthing).

Insertion of one HT PSC/RCC pole in existing OH line including in digging & backfilling
HC 32 pit in Ordinary Soil, fitting cross arm, insulators, binding etc., drawing sufficient length of No 1035.00
GI earth leads to the ground for earthing (excluding provision of earthing).
Insertion of one HT 'A' type pole in existing OH line including in digging & backfilling pit
HC 33 in Ordinary Soil, fitting cross arm, insulators, binding etc., drawing sufficient length of GI No 1299.00
earth leads to the ground for earthing (excluding provision of earthing).

Insertion of one HT Four legged 'A' type pole in existing OH line including in digging &
HC 34 backfilling pit in Ordinary Soil, fitting cross arm, insulators, binding etc., drawing sufficient No 1948.00
length of GI earth leads to the ground for earthing (excluding provision of earthing).

HC 35 Additional rate for excavation of one Pit for HT Pole/ HT Stay in Laterite No 132.00

HC 36 Additional rate for excavation of one Pit for HT Pole/ HT Stay in Hard Laterite No 264.00

HC 37 Additional rate for excavation of one Pit for HT Pole/ HT Stay in Soft Rock No 396.00

HC 38 Additional rate for excavation of one Pit for HT Pole/ HT Stay in Rock No 792.00

Page 4 of 20
Amount
Sl No Detailed description of work Unit including
10% CP

HC 39 Additional rate for excavation of Pit for 'A' type pole in Laterite. No 198.00

HC 40 Additional rate for excavation of Pit for 'A' type pole in Hard Laterite. No 396.00

HC 41 Additional rate for excavation of Pit for 'A' type pole in Soft Rock. No 594.00

HC 42 Additional rate for excavation of Pit for 'A' type pole in Rock. No 1188.00

Stringing of one km 11 kV line with ACSR Raccoon (3 conductors) after fitting insulators
and giving jumper connections including cutting removing tree branches wherever
HC 43 km 10362.00
necessary and conveyance of all materials (except poles) to an initial distance of 200 m from
stacking place, after cutting and removing tree branches wherever necessary
Stringing of one km 11 kV line with ACSR Rabbit (3 conductors) after fitting insulators and
giving jumper connections including cutting removing tree branches wherever necessary
HC 44 km 8712.00
and conveyance of all materials (except poles) to an initial distance of 200 m from stacking
place, after cutting and removing tree branches wherever necessary
Fitting 5 Nos channel cross arm, AB switch, DO fuse, LA, HT & LT connections up to OH
lines, etc. on existing DP structure, earthing the same using earth pipe, digging & back
HC 45 No 4368.00
filling pit in ordinary soil (5 Nos), provision for one set (3 Nos) of LT fuses. excluding
mounting of Transformer on poles.
Fitting 3 Nos channel cross arm, AB switch, DO fuse, LA, HT & LT connections up to OH
lines, etc. on existing DP structure, earthing the same using earth pipe, digging & back
HC 46 No 4368.00
filling pit in ordinary soil (5 Nos), provision for one set (3 Nos) of LT fuses. excluding
mounting of Transformer on plinth.
Erecting one CT-PT unit /25/50/63 kVA Transformer from any vehicle/Ground to existing
HC 47 DP/ Plinth and giving connections (including expenses for transporting transformer in No 1460.00
departmental lorry from SRS/any other stores in District).
Erecting one 100/150/160 kVA Transformer from any vehicle/Ground to existing DP and
HC 48 giving connections(including expenses for transporting transformer in departmental lorry No 2153.00
from SRS/any other stores in District).
Erecting one 100/150/160 kVA Transformer from any vehicle/Ground to existing Plinth
HC 49 and giving connections(including expenses for transporting transformer in departmental No 1873.00
lorry from SRS/any other stores in District).
Erecting one 250/315/500 kVA Transformer from any vehicle/Ground to existing Plinth and
HC 50 giving connections(including expenses for transporting transformer in departmental lorry No 2500.00
from SRS/any other stores in District).
Installing One DTR Meter with box (Normally 40x25x100 size) on existing poles and giving
HC 51 No 1106.00
the complete connections including conveyance of materials.
Fitting one additional Fuse unit and giving connection from Transformer to fuse and fuse to
HC 52 No 101.00
LT OH line.
Providing one Earth using GI earth pipe of size 38.1mm dia, 2.5 m length including digging
HC 53 separate pit (45cm x 45cm x 2.5 m) at standard distance (1.5 m) away from the No 413.00
pole/structure in Ordinary Soil & backfilling.

HC 54 Additional rate for excavation of one Earth Pit (2.5 m depth) in Laterite No 264.00

HC 55 Additional rate for excavation of one Earth Pit (2.5 m depth) in Hard Laterite No 528.00

HC 56 Additional rate for excavation of one Earth Pit (2.5 m depth) in Soft Rock No 792.00

Page 5 of 20
Amount
Sl No Detailed description of work Unit including
10% CP
Providing one Coil Earth using No.8 GI-earth wire (50 mm dia, 115 turns) including digging
HC 57 separate pit (45cm x 45cm x 1.5 m) at standard distance away from the pole/structure in No 264.00
Ordinary Soil & backfilling

HC 58 Fitting One set (3 Nos) 11 kV LA and giving connections excluding earthing. No 140.00

HC 59 Fitting One set (3 Nos) 11 kV DO Fuse and giving connection. No 140.00

Fitting one set AB switch, DO fuse (3 Nos), LA (3 Nos), giving all connections from HT
HC 60 line to Transformer bush and drawing earth leads to the ground for earthing excluding No 1106.00
provision of earthing.
Fitting one set AB Switch, giving connection and earthing the same using one earth pipe
HC 61 No 1238.00
(2.5 m) including digging pit in Ordinary Soil & back filling
Conveyance of one Km 11kV line materials from section store/ stacking place to the work
HC 62 km/km 528.00
site (excluding poles).
Fitting one Additional V / Angle / Channel cross arm in existing single pole including
HC 63 No 140.00
conveyance of materials
Fitting one Additional Angle / Channel cross arm in existing 11 kV DP including
HC 64 No 172.00
conveyance of materials
Fitting one LT 2 line cross arm on HT or LT existing poles including fitting insulators and
HC 65 No 41.00
binding the same with LT Line.
Fitting one LT 4 line cross arm on HT or LT existing poles including fitting insulators and
HC 66 No 62.00
binding the same with LT Line.
Providing Bucket type cradling for one span 11kV line using 8 SWG GI wire including
HC 67 No 3696.00
excavation of earth pit and earthing at both ends using earth pipe 2.5m

HC 68 Providing barbed wire anti-climbing protection 2.5Mtr height for one 11kV pole No 68.00

LT LINE WORKS

Transporting one LT TW/RSJ/Rail pole by Hand cart - for an average distance of one km
LC 01 P/km 96.00
(limited to 1 km).
Transporting one LT TW/RSJ/Rail pole by Hand cart - for every additional km (limited to 4
LC 02 P/km 48.00
km).
Transporting one LT PSC/RCC pole by Hand cart - for an average distance of one km
LC 03 P/km 230.00
(limited to 1 km).
Transporting one LT PSC/RCC pole by Hand cart - for every additional km (limited to 4
LC 04 P/km 115.00
km).
Transporting one LT TW/RSJ/Rail pole by Head load - for an average distance of one km
LC 05 P/km 215.00
(Normally limited to 0.3 km)
Transporting one LT PSC/RCC pole by Head load - for an average distance of one km
LC 06 P/km 429.00
(Normally limited to 0.3 km)
Erecting one LT TW/RSJ/Rail Pole in position including digging & back filling pit in
LC 07 No 347.00
ordinary soil.
Erecting one LT PSC/RCC Pole in position including digging & back filling pit in ordinary
LC 08 No 611.00
soil.

LC 09 Providing Stay for LT poles including digging & back filling pit in ordinary soil. No 276.00

Providing Strut using LT TW/RSJ/Rail pole including digging and back filling pit in
LC 10 No 307.00
ordinary soil.
Providing Strut using LT PSC/RCC pole including digging and back filling pit in ordinary
LC 11 No 571.00
soil.

Page 6 of 20
Amount
Sl No Detailed description of work Unit including
10% CP
Providing Fly stay for LT pole using LT TW/RSJ/Rail pole including digging and back
LC 12 No 653.00
filling pit in ordinary soil.
Providing Fly stay for LT pole using LT PSC/RCC pole including digging and back filling
LC 13 No 917.00
pit in ordinary soil.

LC 14 Additional rate for excavation of one Pit for LT Pole/ LT Stay in Laterite No 66.00

LC 15 Additional rate for excavation of one Pit for LT Pole/ LT Stay in Hard Laterite No 132.00

LC 16 Additional rate for excavation of one Pit for LT Pole/ LT Stay in Soft Rock No 198.00

LC 17 Additional rate for excavation of one Pit for LT Pole/ LT Stay in Rock No 396.00

Stringing, shackling, fitting cross arms, insulators and binding, giving jumper connection etc
using ACSR Rabbit for Phase and Neutral, for one km LT S ph 2 wire line including cutting
LC 18 km 5016.00
removing tree branches wherever necessary and conveyance of all materials (except poles)
from stacking place.

Stringing, shackling, fitting cross arms, insulators and binding, giving jumper connection etc
using ACSR Rabbit for Phase & Neutral and ACSR Weasel for street main, for one km LT S
LC 19 km 7046.00
ph 3 wire line including cutting removing tree branches wherever necessary and conveyance
of all materials (except poles) from stacking place.

Stringing, shackling, fitting cross arms, insulators and binding, giving jumper connection etc
using ACSR Rabbit for Phase and ACSR weasel for Neutral, for one km LT 3 ph 4 wire line
LC 20 km 9075.00
including cutting removing tree branches wherever necessary and conveyance of all
materials (except poles) from stacking place.

Stringing, shackling, fitting cross arms, insulators and binding, giving jumper connection etc
using ACSR Rabbit for Phase and ACSR weasel for Neutral & Street Main, for one km LT 3
LC 21 km 11105.00
ph 5 wire line including cutting removing tree branches wherever necessary and conveyance
of all materials (except poles) from stacking place.

Stringing, shackling, fitting cross arms, insulators and binding, giving jumper connection etc
for one km additional conductor (ACSR Rabbit/Weasel) on existing LT line including
LC 22 km 2030.00
cutting removing tree branches wherever necessary and conveyance of all materials (except
poles) from stacking place.

Stringing, shackling, fitting insulators (excluding fitting of cross arm) and binding, giving
jumper connection etc, for one km additional conductor (ACSR Rabbit/Weasel) on existing
LC 23 km 1370.00
LT line including cutting removing tree branches wherever necessary and conveyance of all
materials (except poles) from stacking place.

Conversion of one km LT single phase line to LT three phase line including dismantling the
LC 24 existing 2 conductors, stringing 3 ACSR Rabbit conductor for Phase & One Weasel for km 10478.00
Neutral and conveyance of materials
Fitting one No Section fuse on LT line with dropping cables, crimping sockets, connecting
LC 25 No 70.00
with bolt & nut etc.
Providing Guarding LT line using No.8 SWG GI wire one span for road crossing including
LC 26 No 2310.00
earthing (using 2.5 m earth pipe) both ends.
Fitting one set (3Nos) LT lightning arrestors in three phase line and giving connections
LC 27 No 140.00
excluding earthing

Page 7 of 20
Amount
Sl No Detailed description of work Unit including
10% CP

SERVICE CONNECTION

Giving one single phase WP Service connection including conveyance of materials, fixing
SC 01 No 528.00
meter, drawing WP wire, with GI support wire etc. as per standards.
Giving one three phase WP Service connection including conveyance of materials, fixing
SC 02 No 792.00
meter, drawing WP wire with GI support wire etc. as per standards.
Giving one three phase WP Service Connection using CT including conveyance of
SC 03 No 1056.00
materials, fixing meter, CT, drawing WP wire etc. as per standards.
Converting single phase WP Service connection to three phase Service Connection by
SC 04 replacing existing S Ph meter with 3 Ph meter, WP wire with GI support wire and other No 1056.00
accessories including conveyance of all materials
Converting three phase WP Service connection to single phase Service Connection by
SC 05 replacing existing 3 Ph meter with S Ph meter, WP wire with GI support wire and other No 924.00
accessories including conveyance of all materials
Constructing one span single phase OH line for giving Service Connection using
SC 06 TW/RSJ/Rail pole with one stay including digging & back filling 2 pits in ordinary soil, No 824.00
cutting removing tree branches, excluding WP portion and transportation of pole.
Constructing One span Single phase OH line for giving Service Connection using PSC/RCC
SC 07 pole with one stay including digging & back filling 2 pits in ordinary soil, cutting removing No 1088.00
tree branches, excluding WP portion and transportation of pole.
Constructing One span Single phase OH line for giving Service Connection using
TW/RSJ/Rail pole with TW/RSJ/Rail strut (without stay) including digging & back filling 2
SC 08 No 854.00
pits in ordinary soil, cutting removing tree branches, excluding WP portion and
transportation of poles.

Constructing One span Single phase OH line for giving service connection using PSC/RCC
SC 09 pole with PSC/RCC strut (without stay) including digging & back filling 2 pits in ordinary No 1382.00
soil, cutting removing tree branches, excluding WP portion and transportation of poles.

Constructing One span Single phase OH line for giving Service Connection using
SC 10 TW/RSJ/Rail pole without stay/strut including digging & back filling pit in ordinary soil, No 547.00
cutting removing tree branches, excluding WP portion and transportation of poles.

Constructing One span Single phase OH line for giving service connection using PSC/RCC
SC 11 pole without stay/strut including digging & back filling pit in ordinary soil, cutting removing No 811.00
tree branches, excluding WP portion and transportation of poles.
Constructing One span Three phase OH line for giving Service Connection using
SC 12 TW/RSJ/Rail pole with one stay including digging & back filling 2 pits in ordinary soil, No 986.00
cutting removing tree branches, excluding WP portion and transportation of pole.
Constructing One span Three phase OH line for giving service connection using PSC/RCC
SC 13 pole with one stay including digging & back filling 2 pits in ordinary soil, cutting removing No 1250.00
tree branches, excluding WP portion and transportation of pole.
Constructing One span Three phase OH line for giving Service Connection using
TW/RSJ/Rail pole with TW/RSJ/Rail strut (without stay) including digging & back filling 2
SC 14 No 1016.00
pits in ordinary soil, cutting removing tree branches, excluding WP portion and
transportation of poles.

Constructing One span Three phase OH line for giving service connection using PSC/RCC
SC 15 pole with PSC/RCC strut (without stay) including digging & back filling 2 pits in ordinary No 1544.00
soil, cutting removing tree branches, excluding WP portion and transportation of poles.

Page 8 of 20
Amount
Sl No Detailed description of work Unit including
10% CP
Constructing One span Three phase OH line for giving service connection using
SC 16 TW/RSJ/Rail pole without stay/strut including digging & back filling pit in ordinary soil, No 710.00
cutting removing tree branches, excluding WP portion and transportation of pole.
Constructing One span Three phase OH line for giving Service Connection using PSC/RCC
SC 17 pole without stay/strut including digging & back filling pit in ordinary soil, cutting removing No 974.00
tree branches, excluding WP portion and transportation of pole.
Conversion of one span OH single phase service line to three phase service line including
SC 18 dismantling existing conductors, stringing new conductors (ACSR Rabbit for phase and No 419.00
Weasel for neutral) and conveyance of all materials.
Insertion of one LT PSC pole in existing single phase OH line including digging & back
SC 19 filling pit in ordinary soil, fitting cross arm, insulator, binding etc. excluding transportation No 667.00
of poles.
Insertion of one LT PSC pole in existing Three phase OH line including digging & back
SC 20 filling pit in ordinary soil, fitting cross arm, insulator, binding etc. excluding transportation No 717.00
of poles.
Providing WP support with PSC pole including digging & back filling pit in ordinary soil.
SC 21 No 590.00
excluding transportation of poles.
Providing WP support with TW pole including digging & back filling pit in ordinary soil.
SC 22 No 326.00
excluding transportation of poles.

HT MAINTENANCE WORK

Renewal of existing damaged /old 11 kV TW/RSJ/Rail pole with new TW/RSJ/Rail pole in
HM 01 place including excavation of pole pit, erection of new pole, backfilling pit and refitting of No 934.00
all items etc and conveyance of all materials except poles.
Renewal of existing damaged /old 11 kV TW/RSJ/Rail Pole with new PSC/RCC pole in
HM 02 place including excavation, erection of new pole, backfilling pit and refitting of all items etc No 1363.00
and conveyance of all materials except poles.
Renewal of existing damaged /old 11 kV PSC/RCC Pole with new PSC/RCC pole in place
HM 03 including excavation, erection of new pole, backfilling pit and refitting of all items etc and No 1577.00
conveyance of all materials except poles.
Renewal of existing damaged /old 11 kV TW/RSJ/Rail Pole with new 'A' type pole in place
HM 04 including excavation, erection of new pole, backfilling pit and refitting of all items etc and No 1660.00
conveyance of all materials except poles.
Renewal of existing damaged /old 11 kV TW/RSJ/Rail Pole with new Four legged 'A' type
HM 05 pole in place including excavation, erection of new pole, backfilling pit and refitting of all No 2490.00
items etc and conveyance of all materials except poles.
Renewal of existing damaged /old 11 kV PSC/RCC Pole with new 'A' type pole in place
HM 06 including excavation, erection of new pole, backfilling pit and refitting of all items etc and No 1874.00
conveyance of all materials except poles.
Renewal of existing damaged /old 11 kV PSC/RCC Pole with new Four legged 'A' type pole
HM 07 in place including excavation, erection of new pole, backfilling pit and refitting of all items No 2812.00
etc and conveyance of all materials except poles.
Renewal of existing damaged /old 11 kV 'A' type pole with new 'A' type pole in place
HM 08 including excavation of pole pit, erection of new pole, backfilling pit and refitting of all No 1907.00
items etc and conveyance of all materials except poles.
Renewal of existing damaged /old 11 kV Four legged 'A' type pole with new Four legged 'A'
HM 09 type pole in place including excavation of pole pit, erection of new pole, backfilling pit and No 2861.00
refitting of all items etc and conveyance of all materials except poles.
Renewal of existing damaged /old 11 kV TW/RSJ/Rail DP (2 channel cross arm) with new
HM 10 TW/RSJ/Rail DP in place including excavation of pole pit, erection of new pole, backfilling No 2680.00
pit and refitting of all items etc and conveyance of all materials except poles.

Page 9 of 20
Amount
Sl No Detailed description of work Unit including
10% CP
Renewal of existing damaged /old 11 kV TW/RSJ/Rail DP (2 channel cross arm) with new
HM 11 PSC/RCC DP in place including excavation, erection of new pole, backfilling pit and No 3538.00
refitting of all items etc and conveyance of all materials except poles.
Renewal of existing damaged /old 11 kV PSC/RCC DP (2 channel cross arm) with new
HM 12 PSC/RCC DP in place including excavation, erection of new pole, backfilling pit and No 3967.00
refitting of all items etc and conveyance of all materials except poles.
Renewal of existing damaged /old 11 kV TW/RSJ/Rail DP with new 'A' type DP in place
HM 13 including excavation, erection of new pole, backfilling pit and refitting of all items etc and No 4066.00
conveyance of all materials except poles.
Renewal of existing damaged /old 11 kV TW/RSJ/Rail DP with new Four legged 'A' type
HM 14 DP in place including excavation, erection of new pole, backfilling pit and refitting of all No 6098.00
items etc and conveyance of all materials except poles.
Renewal of existing damaged /old 11 kV PSC/RCC DP with new 'A' type DP in place
HM 15 including excavation, erection of new pole, backfilling pit and refitting of all items etc and No 4495.00
conveyance of all materials except poles.
Renewal of existing damaged /old 11 kV PSC/RCC DP with new Four legged 'A' type DP in
HM 16 place including excavation, erection of new pole, backfilling pit and refitting of all items etc No 6742.00
and conveyance of all materials except poles.
Renewal of existing damaged /old 11 kV 'A' type DP with new 'A' type DP in place
HM 17 including excavation of pole pit, erection of new pole, backfilling pit and refitting of all No 4627.00
items etc and conveyance of all materials except poles.
Renewal of existing damaged /old 11 kV Four legged 'A' type DP with new Four legged 'A'
HM 18 type DP in place including excavation of pole pit, erection of new pole, backfilling pit and No 6940.00
refitting of all items etc and conveyance of all materials except poles.
Renewing one damaged TW/RSJ/Rail Transformer DP structure with a new TW/RSJ/Rail
Transformer DP including excavation, dismantling accessories like AB switch, DO fuse, LA
HM 19 ,LT fuses, HT, LT and earth connections, dismantling existing Transformer, keep it in safe No 7982.00
custody and re erecting all accessories including Transformer on the new DP as per
standards (excluding renewal of pipe earthing)
Renewing one damaged TW/RSJ/Rail Transformer DP structure with a new PSC/RCC
Transformer DP including excavation, dismantling accessories like AB switch, DO fuse, LA
HM 20 ,LT fuses, HT, LT and earth connections, dismantling existing Transformer, keep it in safe No 8840.00
custody and re erecting all accessories including Transformer on the new DP as per
standards (excluding renewal of pipe earthing)
Renewing one damaged PSC/RCC Transformer DP structure with a new PSC/RCC
Transformer DP including excavation, dismantling accessories like AB switch, DO fuse, LA
HM 21 ,LT fuses, HT, LT and earth connections, dismantling existing Transformer, keep it in safe No 9269.00
custody and re erecting all accessories including Transformer on the new DP as per
standards (excluding renewal of pipe earthing)

HM 22 Renewal of one damaged HT Pin insulator No 84.00

HM 23 Additional rate for refitting/ redoing one Disc set while renewing any type of 11kV cut pole. No 215.00

Additional rate for reinstalling LT line on the renewed 11kV pole having both HT and LT
HM 24 No 215.00
(HT/LT) lines.
Renewal of existing damaged /old 11 kV Stay with new stay in place including excavation &
HM 25 No 547.00
backfilling of pit, dismantling, refitting of all items and conveyance of all materials.

HM 26 Renewal of existing damaged / broken old 11kV Stay to the existing stay rod. No 172.00

HM 27 Replacing/ inserting HT stay insulator on the existing stay. No 172.00

Page 10 of 20
Amount
Sl No Detailed description of work Unit including
10% CP
Renewal of any type of existing damaged /old 11 kV Strut with new TW/RSJ/Rail strut in
HM 28 place including excavation & backfilling of pit, consolidating, dismantling and refitting of No 743.00
all items and conveyance of all materials except pole.
Renewal of any type of existing damaged /old 11 kV Strut with new PSC/RCC strut in place
HM 29 including excavation & backfilling of pit, consolidating, dismantling and refitting of all No 1386.00
items and conveyance of all materials except pole.

Renewal of existing damaged /old 11 kV Fly Stay with new Fly stay using HT TW/RSJ/Rail
HM 30 pole in place including excavation & backfilling of pit, consolidating, dismantling and No 1521.00
refitting of all items and conveyance of all materials except pole (if pole is also renewed)..

Renewal of existing damaged /old 11 kV Fly Stay with new Fly stay using HT PSC/RCC
HM 31 pole in place including excavation & backfilling of pit, consolidating, dismantling and No 2164.00
refitting of all items and conveyance of all materials except pole (if pole is also renewed).

Re-Tensioning one span 11 kV line including replacing pin insulators, pin binding,
HM 32 jumpering, replacing insulators cross arms disc, tightening stay, cutting tree branches etc No 213.00
wherever necessary including conveyance of all materials complete.
Re-joining one snapped HT conductor after removing damaged portion including Re-
HM 33 No 487.00
Tensioning and conveyance of all materials complete.
Repairing of one limb of AB switch by replacing male and female contacts, damaged
HM 34 insulators, applying petroleum jelly, lubricants etc and reconnecting the same including No 206.00
reconditioning of the operating mechanism.

HM 35 Replacing one set AB switch including dismantling existing AB, giving connections etc. No 1238.00

Renewal of one No 11 kV LA including conveyance, reconnecting and dismantling old LA


HM 36 No 70.00
(excluding earthing)
Renewal of one No 11 kV DO Fuse including conveyance, reconnecting and dismantling old
HM 37 No 70.00
DO Fuse (excluding earthing)
Renewing 11 kV Jumper connection for one phase from OH line to Transformer through AB
HM 38 switch, DO Fuse and connection to LA using copper / ACSR conductor as per standard No 215.00
specification including dismantling old jumpers.
Renewing one 11 kV Jumper connection using copper / ACSR conductor as per standard
HM 39 No 126.00
specification (in loop formation for tapping from line)
Renewing one 11 kV Jumper connection using copper / ACSR conductor as per standard
HM 40 No 87.00
specification.
Renewing one V / angle / channel cross arm on the 11 kV Pole including dismantling and
HM 41 No 235.00
conveyance.

HM 42 Renewing one Channel cross arm on the 11 kV DP including dismantling and conveyance. No 215.00

Providing stay (temporary nature) by piling Cut Ends in kole land providing insulator,
HM 43 No 429.00
including fabrication of cut ends conveyance of materials.
Straightening one slanted 11 kV pole after unbinding the line and binding the line after
HM 44 No 338.00
work.
Straightening one slanted 11 kV Cut pole after lowering down the existing line and stringing
HM 45 No 561.00
the line after work.
Dismantling existing CT/PT unit/ 25 /50/63 kVA Transformer, erecting new CT/PT unit / 25
HM 46 /50/63 kVA Transformer in place giving connections etc including loading / unloading of No 2322.00
old and new CT/PT unit/ 25 /50/63 kVA Transformer at site.
Dismantling existing 100/160 kVA Transformer, erecting new transformer in place giving
HM 47 No 3510.00
connections etc including loading / unloading of old and new transformer at site.

Page 11 of 20
Amount
Sl No Detailed description of work Unit including
10% CP
Dismantling existing 250/315/500 kVA Transformer, erecting new transformer in place
HM 48 No 4030.00
giving connections etc including loading / unloading of old and new transformer at site.
Enhancing Transformer by dismantling existing 50/63 kVA Transformer, erecting new
HM 49 100kVA transformer in place giving connections etc including loading / unloading of old No 3032.00
and new transformer at site.
Enhancing Transformer by dismantling existing 100/160 kVA Transformer, erecting new
HM 50 250/315/500kVA transformer in place giving connections etc including loading / unloading No 3725.00
of old and new transformer at site.
Reconductoring one km 11 kV copper/ old AAC/ACSR line of 3 conductors with New
HM 51 ACSR Raccoon including cutting of tree branches wherever necessary, conveyance of km 12796.00
materials to and from the stacking place.
HM 52 Drilling hole of various sizes on existing Channel / Cross Arm. No 5.00

HM 53 Drilling oval shaped hole of various sizes on existing Channel / Cross Arm/ GI/MS cleat etc. No 11.00

HM 54 Cutting Channel / Cross Arm/ Angle Iron in to two pieces. No 21.00

LT MAINTENANCE WORK

Renewal of existing damaged /old LT TW/RSJ/Rail (S Ph line) pole with new TW/RSJ/Rail
pole in place including excavation of pole pit, erection of new pole, backfilling pit and
LM 01 No 656.00
refitting of all items except street light fitting etc. and conveyance of all materials except
poles.
Renewal of existing damaged /old LT TW/RSJ/Rail (S Ph line) pole with new PSC/RCC
pole in place including excavation of pole pit, erection of new pole, backfilling pit and
LM 02 No 920.00
refitting of all items except street light fitting etc. and conveyance of all materials except
poles.

Renewal of existing damaged /old LT PSC/RCC (S Ph line) pole with new PSC/RCC pole in
LM 03 place including excavation of pole pit, erection of new pole, backfilling pit and refitting of No 1052.00
all items except street light fitting etc. and conveyance of all materials except poles.

Renewal of existing damaged /old LT TW/RSJ/Rail ( 3 phase line) pole with new
TW/RSJ/Rail pole in place including excavation of pole pit, erection of new pole,
LM 04 No 771.00
backfilling pit and refitting of all items except street light fitting etc. and conveyance of all
materials except poles.
Renewal of existing damaged /old LT TW/RSJ/Rail ( 3 phase line) pole with new PSC/RCC
pole in place including excavation of pole pit, erection of new pole, backfilling pit and
LM 05 No 1035.00
refitting of all items except street light fitting etc. and conveyance of all materials except
poles.
Renewal of existing damaged /old LT PSC/RCC ( 3 phase line) pole with new PSC/RCC
pole in place including excavation of pole pit, erection of new pole, backfilling pit and
LM 06 No 1167.00
refitting of all items except street light fitting etc. and conveyance of all materials except
poles.
LM 07 Additional rate for refitting/ redoing one Shackle Set while renewing any type of LT pole. No 112.00
Renewal of existing damaged /old LT stay with new stay in place including excavation of
LM 08 stay pit, erection of new stay, backfilling pit and refitting of all items and conveyance of all No 349.00
materials.
LM 09 Renewal of existing damaged / broken old LT stay in existing stay rod. No 132.00

LM 10 Replacing/ inserting LT stay insulator on the existing stay. No 132.00

Page 12 of 20
Amount
Sl No Detailed description of work Unit including
10% CP
Renewal of existing damaged /old LT Strut of any type with new TW/RSJ/Rail strut in place
LM 11 including excavation of pit, erection of new strut, backfilling, consolidating, dismantling and No 394.00
refitting of all items and conveyance of all materials except pole.
Renewal of existing damaged /old LT Strut of any type with new PSC/RCC strut in place
LM 12 including excavation of pit, erection of new strut, backfilling, consolidating, dismantling and No 790.00
refitting of all items and conveyance of all materials except pole.
Renewal of existing damaged /old LT Fly Stay of any type of pole with new Fly stay using
LT TW/RSJ/Rail pole in place including excavation of pit, erection of new Fly stay,
LM 13 No 913.00
backfilling and dismantling and refitting of all items and conveyance of all materials except
pole (if pole is also renewed)..
Renewal of existing damaged /old LT Fly Stay of any type of pole with new Fly stay using
LT PSC/RCC pole in place including excavation of pit, erection of new Fly stay, backfilling
LM 14 No 1309.00
and dismantling and refitting of all items and conveyance of all materials except pole (if
pole is also renewed).
Reshackling one Span LT S Ph 2 wire OH line including pin binding, jumpering, replacing
LM 15 insulators/ cross arms/ shackle, tightening stay, cutting tree branches etc wherever necessary No 77.00
including conveyance of all materials.
Reshackling one Span LT 3 Ph 4 wire OH line including pin binding, jumpering, replacing
LM 16 insulators/ cross arms/ shackle, tightening stay, cutting tree branches etc wherever necessary No 145.00
including conveyance of all materials.
Reshackling one Span LT OH Additional conductor including pin binding, jumpering,
LM 17 replacing insulators/ cross arms/ shackle, tightening stay, cutting tree branches etc wherever No 34.00
necessary including conveyance of all materials complete.
Re-joining one snapped LT conductors after removing damage portion including
LM 18 No 201.00
Reshackling and conveyance of all materials complete.
Renewing one LT Jumper connection using copper / ACSR conductor as per standard
LM 19 No 42.00
specification (in loop formation for taping from line)
Renewing one LT Jumper connection using copper / ACSR conductor as per standard
LM 20 No 29.00
specification.

LM 21 Providing/ Inserting 2 line spacer on the existing LT OH line No 25.00

LM 22 Providing/ Inserting 3 line spacer on the existing LT OH line No 31.00

Transferring LT S Ph 2/3 wire OH line to newly erected HT/LT pole including dismantling
LM 23 No 261.00
existing cross arm and insulators, refitting the same on the new pole, binding etc. complete.

Transferring LT 3 Ph 4/5 wire OH line to newly erected HT/LT pole including dismantling
LM 24 No 505.00
existing cross arm and insulators, refitting the same on the new pole, binding etc. complete.

LM 25 Straightening one slanted LT pole after unbinding the line and binding the line after work. No 309.00
Straightening one slanted LT Cut Pole after lowering down the existing line and stringing
LM 26 No 421.00
the line after work.
Reconductoring (Changing) one km LT S Ph 2 wire OH copper/ old AAC/ACSR conductor
LM 27 line with equivalent/ higher size new ACSR conductor including conveyance of materials to km 4987.00
and from the stacking place
Reconductoring (Changing) one km LT 3 Ph 4 wire OH copper/ old AAC/ACSR conductor
LM 28 line with equivalent/ higher size new ACSR conductor including conveyance of materials to km 10302.00
and from the stacking place
Reconductoring (Changing) one Km LT OH copper/ old AAC/ACSR one conductor with
LM 29 equivalent/ higher size New ACSR conductor including conveyance of materials to and km 2658.00
from the stacking place

Page 13 of 20
Amount
Sl No Detailed description of work Unit including
10% CP
MAINTENANCE OF SERVICE CONNECTION.
Disconnecting and lowering down the Single phase WP service connection with guy wire
SM 01 No 28.00
from the pole and reconnecting the same after completing the line work.
Disconnecting and lowering down the Three phase WP service connection with guy wire
SM 02 No 43.00
from the pole and reconnecting the same after completing the line work.
Redoing Single Phase WP Service connection complete including lowering down the guy
wire portion, repairing or changing WP wire ,GI wire ,Fuse unit etc. Changing Energy Meter
SM 03 No 264.00
cutout ,neutral link etc. if necessary and reconnecting the same including conveyance of
material to site from Section office at various location.
Redoing 3 Phase WP Service connection complete including lowering down the guy wire
portion ,repairing or changing WP wire ,GI wire ,Fuse unit etc. Changing Energy Meter
SM 04 No 330.00
cutout ,neutral link etc. if necessary and reconnecting the same including conveyance of
material to site from Section office at various location.
Shifting One No. Single phase Service Connection Metering equipment with all fittings
including lowering down the WP service wire, dismantling Meter Board without making
SM 05 No 267.00
damage and refitting the same at new location and redoing the WP service wire with all
fittings
Shifting One No. Three phase Service Connection Metering equipment with all fittings
including lowering down the WP service wire, dismantling Meter Board without making
SM 06 No 495.00
damage and refitting the same at new location and redoing the WP service wire with all
fittings
METER CHANGING
Changing Faulty single phase energy meter including Dismantling of old meter, connecting
SM 07 of new meter/ giving electric connection including transporting of new meter to the site and No 33.00
returning old meters to section store.
Changing Faulty three phase energy meter including Dismantling of old meter, connecting
SM 08 of new meter/ giving electric connection including transporting of new meter to the site and No 60.00
returning old meters to section store.
Changing Faulty three phase CT energy meter including Dismantling of old meter, replacing
SM 09 CTs, renewing PT connection, connecting new meter/ giving electric connection including No 347.00
transporting of new meter to the site and returning old meters to section store.
DISMANTLING – HT
Dismantling one damaged 11 kV TW/RSJ/Rail pole after disconnecting stays, strut etc
HD 01 No 325.00
attached thereon and stacking the same.
Dismantling (with out damage) one No. 11 kV TW/RSJ/Rail pole after disconnecting stays,
HD 02 No 538.00
strut etc attached thereon and stacking the same.
Dismantling one damaged 11 kV PSC/RCC pole after disconnecting stays, strut etc attached
HD 03 No 540.00
thereon and stacking the same.
Dismantling (with out damage) one No. 11 kV PSC/RCC pole after disconnecting stays,
HD 04 No 942.00
strut etc attached thereon and stacking the same.
Dismantling one damaged 11 kV 'A' type pole after disconnecting stays, strut etc attached
HD 05 No 672.00
thereon and stacking the same.
Dismantling (with out damage) one No. 11 kV 'A' type pole after disconnecting stays, strut
HD 06 No 944.00
etc attached thereon and stacking the same.
Dismantling one damaged 11 kV Four legged 'A' type pole after disconnecting stays, strut
HD 07 No 1007.00
etc attached thereon and stacking the same.
Dismantling (with out damage) one No. 11 kV Four legged 'A' type pole after disconnecting
HD 08 No 1416.00
stays, strut etc attached thereon and stacking the same.
Dismantling one damage HT TW/RSJ/Rail Strut pole including removal of clamps and
HD 09 No 248.00
stacking.

Page 14 of 20
Amount
Sl No Detailed description of work Unit including
10% CP
Dismantling (with out damage) one HT TW/RSJ/Rail Strut pole including removal of
HD 10 No 462.00
clamps and stacking.
Dismantling one damage HT PSC/RCC Strut pole including removal of clamps and
HD 11 No 462.00
stacking.
Dismantling (with out damage) one HT PSC/RCC Strut pole including removal of clamps
HD 12 No 861.00
and stacking.
Dismantling (with out damage) One km 11 kV line (Three conductors) including
HD 13 dismantling cross arm, insulators, disc, disconnecting jumper connection, rolling the km 4142.00
conductor and stacking the materials.
Dismantling (with out damage) One HT stay including digging pit in all classes of soil and
HD 14 No 270.00
backfilling, and bringing back to section store
Dismantling (with out damage) one V cross arm / Channel cross arm from existing Pole and
HD 15 No 56.00
bringing back to section store.
Dismantling (with out damage) one Channel cross arm from existing DP structure and
HD 16 No 86.00
bringing back to section store.
Dismantling (with out damage) one AB switch from existing structure and bring back to
HD 17 No 495.00
section store.
DISMANTLING – LT
Dismantling one damaged LT TW/RSJ/Rail pole after disconnecting stays, strut etc attached
LD 01 No 173.00
thereon and stacking the same.
Dismantling (with out damage) one LT TW/RSJ/Rail pole after disconnecting stays, strut etc
LD 02 No 314.00
attached thereon and stacking the same.
Dismantling one damaged LT PSC/RCC pole after disconnecting stays, strut etc attached
LD 03 No 305.00
thereon and stacking the same.
Dismantling (with out damage) one LT PSC/RCC pole after disconnecting stays, strut etc
LD 04 No 586.00
attached thereon and stacking the same.
Dismantling (with out damage) LT stay including digging pit in all classes of soil and
LD 05 No 138.00
backfilling
Dismantling one damaged LT TW/RSJ/Rail Strut pole including removal of clamps and
LD 06 No 153.00
stacking.
Dismantling (with out damage) one LT TW/RSJ/Rail Strut pole including removal of clamps
LD 07 No 284.00
and stacking.
LD 08 Dismantling one damage LT PSC/RCC Strut pole including removal of clamps and stacking. No 285.00

Dismantling (with out damage) one LT PSC/RCC Strut pole including removal of clamps
LD 09 No 482.00
and stacking.
LD 10 Dismantling one LT 2 line cross arm with clamp from existing pole and stacking. No 21.00

LD 11 Dismantling one LT 4 line cross arm with clamp from existing pole and stacking. No 31.00
Dismantling Single phase WP Service connection with meter & all accessories and bring
LD 12 No 264.00
back to section store
Dismantling Three phase WP Service connection with meter & all accessories and bring
LD 13 No 396.00
back to section store
Dismantling (with out damage) one span of HT or LT cradling and stacking the same neatly
LD 14 No 677.00
and in good condition for re-use.
Dismantling (with out damage) one km LT S Ph 2 wire OH line conductor by dismantling
LD 15 km 1898.00
cross arms insulators and stacking the conductors in rolls properly
Dismantling (with out damage) one km LT 3 Ph 4 wire OH line conductor by dismantling
LD 16 km 3440.00
cross arms insulators and stacking the conductors in rolls properly
Dismantling (with out damage) one km LT Additional conductor line by dismantling cross
LD 17 km 875.00
arms insulators and stacking the conductors in rolls properly

Page 15 of 20
Amount
Sl No Detailed description of work Unit including
10% CP
STREET LIGHT
Wiring and installing one new Ordinary street light/ CFL / LED fitting on existing pole and
SL 01 No 69.00
giving connections
Dismantling (with out damage) one Ordinary street light / CFL / LED fitting from the pole
SL 02 No 42.00
and stacking.
Dismantling one ordinary street light/ CFL / LED fitting from existing pole cleaning,
SL 03 rewiring, repairing/ replacing the holder, changing bulbs and refitting the same in position No 104.00
and giving connection.
Wiring and installing new set 2 x 40 W fluorescent tube fitting on existing poles including
SL 04 No 124.00
giving connection.
Dismantling one set 2 x 40 W fluorescent tube fitting from existing pole cleaning, rewiring,
SL 06 repairing/replacing holder, changing tubes and refitting the same in position and giving No 186.00
connection.

SL 07 Replacing bulb / CFL on existing street light. No 19.80

Dismantling one ordinary street light / CFL / LED fitting from existing pole and refitting the
SL 08 No 111.00
same on newly erected pole including disconnecting and reconnecting wires.
Dismantling one 2 x 40 W fluorescent tube fitting from the existing pole and refitting the
SL 09 No 198.00
same on newly erected pole including disconnecting and reconnecting wires.
Wiring and installing new set Sodium Vapour/ Mercury Vapour/ Metal Halide lamp fitting
SL 10 No 442.00
on existing poles including giving connection (without using aerial lift).
Wiring and installing new set Sodium Vapour/ Mercury Vapour/ Metal Halide lamp fitting
SL 11 No 221.00
on existing poles including giving connection (using aerial lift).

Dismantling one Sodium Vapour/ Mercury Vapour/ Metal Halide lamp fitting from existing
SL 12 pole cleaning, rewiring, repairing/replacing holder, tube, bulb, igniter, choke, capacitor etc. No 708.00
and refitting the same in position and giving connection (without using aerial lift).

Dismantling one Sodium Vapour/ Mercury Vapour/ Metal Halide lamp fitting from existing
SL 13 pole cleaning, rewiring, repairing/replacing holder, tube, bulb, igniter, choke, capacitor etc. No 276.00
and refitting the same in position and giving connection (using aerial lift).

Dismantling one Sodium Vapour/ Mercury Vapour/ Metal Halide lamp fitting from the
SL 14 existing pole and refitting the same on newly erected pole including disconnecting and No 708.00
reconnecting wires (without using aerial lift).
Dismantling one Sodium Vapour/ Mercury Vapour/ Metal Halide lamp fitting from the
SL 15 existing pole and refitting the same on newly erected pole including disconnecting and No 354.00
reconnecting wires (using aerial lift).
Replacing holder, fused bulb / CFL, changing wires, giving connection etc. of street light
SL 16 No 40.00
including conveyance of all materials.

CLEARING TOUCHINGS (HT)

Clearing touchings on 11 kV HT lines, cutting branches of tree, bamboo clusters, coconut


TC 01 cudjans etc. from above the lines for a distance of 1.8 mfrom the outer conductor as km 541.00
specified by dept. Urban/Town
Clearing touchings on 11 kV HT lines, cutting branches of tree, bamboo clusters, coconut
TC 02 cudjans etc. from above the lines for a distance of 1.8 m from the outer conductor as km 677.00
specified by dept. Rural/ Remote
Clearing touchings on HT/LT lines, cutting branches of tree, bamboo clusters, coconut
TC 03 cudjans etc. from above the lines for a distance of 1.8 m from the outer conductor as km 624.00
specified by dept. Urban/Town

Page 16 of 20
Amount
Sl No Detailed description of work Unit including
10% CP
Clearing touchings on HT/LT lines, cutting branches of tree, bamboo clusters, coconut
TC 04 cudjans etc. from above the lines for a distance of 1.8 m from the outer conductor as km 792.00
specified by dept. Rural/ Remote
Clearing touchings on 33 kV lines, cutting branches of tree, bamboo clusters, coconut
TC 05 cudjans etc. from above the lines for a distance of 2.0 m from the outer conductor as km 812.00
specified by dept. Urban/Town
Clearing touchings on 33 kV lines, cutting branches of tree, bamboo clusters, coconut
TC 06 cudjans etc. from above the lines for a distance of 2.0 m from the outer conductor as km 1015.00
specified by dept. Rural/ Remote
CLEARING TOUCHINGS (LT)
Clearing touchings on LT lines, cutting branches of tree, bamboo clusters, coconut cudjans
TC 07 etc from above the lines for a distance of 1.8 mtr from the outer conductor as specified. km 508.00
Urban/Town
Clearing touchings on LT lines, cutting branches of tree, bamboo clusters, coconut cudjans
TC 08 etc from above the lines for a distance of 1.8 mtr from the outer conductor as specified. km 594.00
Rural/Remote

Tree Cutting
Cutting trees having girth beyond 30 cm but up to and including 60cm (felling trees
TC 09 including cutting of trunks and branches) and removing the root completely and stacking No 138.00
etc. 1 No.
Cutting trees having girth beyond 60 cm but up to and including 120 cm (felling trees
TC 10 including cutting of trunks and branches) and removing the root completely and stacking No 237.00
etc. 1 No.
Cutting trees having girth beyond 120 cm but up to and including 180 cm (felling trees
TC 11 including cutting of trunks and branches) and removing the root completely and stacking No 362.00
etc. 1 No.

Cutting Trees having girth beyond 30 cm but up to and including 60cm, in between the line
TC 12 and Buildings where space for falling trees is not available/enough (felling trees including No 212.00
cutting of trunks and branches) and removing the root completely and stacking etc. 1 No.

Cutting Trees having girth beyond 60 cm but up to and including 120 cm, in between the
line and Buildings where space for falling trees is not available/enough (felling trees
TC 13 No 385.00
including cutting of trunks and branches) and removing the root completely and stacking
etc. 1 No.
Cutting Trees having girth beyond 120 cm but up to and including 180 cm in between the
line and Buildings where space for falling trees is not available/enough (felling trees
TC 14 No 540.00
including cutting of trunks and branches) and removing the root completely and stacking
etc. 1 No.
LOADING AND UNLOADING
Labour charges for loading HT TW/RSJ/Rail pole from the stacking place and unloading the
LU 01 No 107.00
same at work site (transportation by any vehicle).
Labour charges for loading HT PSC/RCC pole from the stacking place and unloading the
LU 02 No 233.00
same at work site (transportation by any vehicle).
Labour charges for loading HT 'A' type pole from the stacking place and unloading the same
LU 03 No 277.00
at work site (transportation by any vehicle).
Labour charges for loading HT Four legged 'A' type pole from the stacking place and
LU 04 No 389.00
unloading the same at work site (transportation by any vehicle).
Labour charges for loading LT TW/RSJ/Rail pole from the stacking place and unloading the
LU 05 No 78.00
same at work site (transportation by any vehicle).

Page 17 of 20
Amount
Sl No Detailed description of work Unit including
10% CP
Labour charges for loading LT PSC/RCC pole from the stacking place and unloading the
LU 06 No 147.00
same at work site (transportation by any vehicle).
Unloading one Transformer (up to and including 160 kVA) from any vehicle to ground
LU 07 No 413.00
including conveyance up to 25m at site
Unloading one Transformer (above 160 kVA) from any vehicle to ground including
LU 08 No 693.00
conveyance up to 25m at site
Loading one Transformer (up to and including 160 kVA) from ground to any vehicle
LU 09 No 545.00
including conveyance up to 25m at site
Loading one Transformer (above 160 kVA) from ground to any vehicle including
LU 10 No 825.00
conveyance up to 25m at site
Dismantling one Transformer (up to and including 160 kVA) from existing structure and
LU 11 No 578.00
loading to any vehicle directly, including disconnecting HT/LT/Earth connections.
Dismantling one Transformer (above 160 kVA) from existing plinth and loading to any
LU 12 No 718.00
vehicle directly, including disconnecting HT/LT/Earth connections.
Dismantling one Transformer (up to and including 160 kVA) from existing structure to
LU 13 No 718.00
ground, including disconnecting HT/LT/Earth connections.
Dismantling one Transformer (above 160 kVA) from existing plinth to ground, including
LU 14 No 858.00
disconnecting HT/LT/Earth connections.
Transportation of Transformer/pole by lorry
Transporting poles by hired vehicle to a distance up to 5 Kms and carrying up to 4 numbers
TR 01 Trip 600.00
of poles excluding loading& unloading charges.
Transporting poles by hired vehicle to a distance beyond 5 Kms and carrying up to 4
TR 02 km 25.00
numbers of poles. (Running Km)
Transporting Transformers by hired vehicle to a distance up to 5 Kms and carrying up to 2
TR 03 Trip 600.00
numbers of 63/100/160/250kVA Transformers excluding loading& unloading charges.
Transporting Transformers by hired vehicle to a distance beyond 5 Kms and carrying up to 2
TR 04 km 25.00
numbers of 63/100/160/250kVA Transformers (Running Km).
Transportation of Transformer/pole by Country boat/ Vallam

TR 05 Engaging one boat man with Boat / Country Boat/ Vallam day 275.00

Transporting HT TW/RSJ/Rail Poles by Country boat/ Vallam up to 6 Kms including


TR 06 No 148.00
loading and unloading charges and hire charge of Country boat/ Vallam

TR 07 Transporting HT TW/RSJ/Rail Poles by Country boat/ Vallam beyond 6 Km km 13.20

Transporting HT PSC/RCC Poles by Country boat/ Vallam up to 6 Kms including loading


TR 08 No 348.00
and unloading charges and hire charge of Country boat/ Vallam

TR 09 Transporting HT PSC/RCC Poles by Country boat/ Vallam beyond 6 Km km 26.00

Transporting 'A' type Poles by Country boat/ Vallam up to 6 Kms including loading and
TR 10 No 410.00
unloading charges and hire charge of Country boat/ Vallam

TR 11 Transporting 'A' type Poles by Country boat/ Vallam beyond 6 Km km 40.00

Transporting Four legged 'A' type Poles by Country boat/ Vallam up to 6 Kms including
TR 12 No 615.00
loading and unloading charges and hire charge of Country boat/ Vallam

TR 13 Transporting Four legged 'A' type Poles by Country boat/ Vallam beyond 6 Km km 59.00

Transporting LT TW/RSJ/Rail Poles by Country boat/ Vallam up to 6 Kms including


TR 14 No 120.00
loading and unloading charges and hire charge of Country boat/ Vallam

Page 18 of 20
Amount
Sl No Detailed description of work Unit including
10% CP

TR 15 Transporting LT TW/RSJ/Rail Poles by Country boat/ Vallam beyond 6 Km km 10.60

Transporting LT PSC/RCC Poles by Country boat/ Vallam up to 6 Kms including loading


TR 16 No 292.00
and unloading charges and hire charge of Country boat/ Vallam

TR 17 Transporting LT PSC/RCC Poles by Country boat/ Vallam beyond 6 Km km 24.00

Transporting 63/100/160 kVA Transformer by Country boat/ Vallam up to 6 Kms including


TR 18 No 580.00
loading and unloading charges and hire charge of Country boat/ Vallam

TR 19 Transporting 63/100/160 kVA Transformer Poles by Country boat/ Vallam beyond 6 Km km 53.00

Transporting 250/315/500 kVA Transformer by Country boat/ Vallam up to 6 Kms


TR 20 No 690.00
including loading and unloading charges and hire charge of Country boat/ Vallam

TR 21 Transporting 250/315/500 kVA Transformer Poles by Country boat/ Vallam beyond 6 Km km 66.00

Painting
Painting the surface of line supports where numbers are to be inscribed, Pole numbers shall
be painted in circular background, with a dimension of 20 cm diameter using approved
quality anti algal yellow paint in two coat after scrapping and cleaning the surface at a
PG 01 No 27.00
height of 2.5 meter above ground level. The number and letters should be in black synthetic
enamel paint. The size of the number should be at least 2 cm in height x 1.5 cm in width.
including cost of paint.

Preparing index register (book & soft copy) showing name of Transformer, post numbers,
PG 02 No 1.80
consumer numbers (in separate column of excel sheet) etc.

Object Marking (traffic signal painting) in one LT, HT, HT/LT pole for a height of 1.5M
PG 03 from ground level using approved quality primer one coat and two coats anti algal black and No 115.00
fluorescent white paint in alternate rings of 25 cm width including cost of paints

Supplying and fixing permanently, Screen printed consumer premises identification Number
PG 04 Card of size 10x7 cm using screw/adhesives. (Con.No of digit 2 cm height 1.5cm width & No 11.40
0.5 cm thick, Name of section of character 1cm height 1cm width & 0.25 cm thick)

Painting 'A' pole structure with one coat Synchromate primer and two coat grey enamel
PG 05 No 846.00
paint/ aluminium paint including cost of paint.

Numbering of Tree (marking for cutting the tree) using yellow enamel paint as specified
PG 06 No 6.00
including cost of paint.

Page 19 of 20
Amount
Sl No Detailed description of work Unit including
10% CP
UG Cable

Excavation of cable trench in all classes of soil, 1.2m deep and 0.35m wide, conveying 3 x
300 sqmm HT XLPE UG cable from Sub Regional Store/stacking place to work site and
laying it carefully using cable rollers, taking through HDPE / stone ware/G.I.pipes at road
crossing/culverts/bridges etc. where ever necessary, providing identification tags at 5m
intervals, placing bricks on either side of the cable, filling the space between the bricks with
UG 01 m 297.00
soil riddled at site, covering the same with bricks and refilling and consolidating the
trenchin layers of 75 cms., providing Cable route markers at 100M intervals, inclusive of
cost of all materials, labour, hiring and transportation charges, but excluding cost of UG
cable and pipe which will be supplied departmentally at store, as per the direction of
departmental officials
Doing straight joint on 3 x 300 sqmm HT XLPE UG cable using the cable jointing kit
supplied departmentally as per specification after providing proper traffic signalling and
UG 02 No 1183.00
caution board fencing etc. wherever necessary including charges for cable jointer and other
sundries etc. as per the direction of departmental officers at site.
Doing one cable end termination on 3 x 300 sqmm HT XLPE UG cable using the cable
jointing kit supplied departmentally after making fencing,caution board and all other safety
UG 03 No 850.00
measures including charges for cable jointer etc. completed as per the direction of the
departmental officers.
Mounting 3 x 300 sqmm HT XLPE UG cable ends with special type cable clamps, bolts,
UG 04 nuts etc.including cost of extra materials if needed and giving necessary jumper No 480.00
connections.

Excavation of cable trench (Soil surface) and digging out the faulty portion of the cable from
UG 05 the trench for redoing straight through joint, relaying the cable after jointing, refilling and m 100.00
consolidating thetrench as per standard specification (excluding joining)

Excavation of cable trench (tarred/concreted surface) and digging out the faulty portion of
UG 06 the cable from the trench for redoing straight through joint, relaying the cable after jointing, m 199.00
refilling and consolidating thetrench as per standard specification (excluding joining)

Dismantling the faulty cable end from the structure/pole after disconnecting 11 kV jumper
UG 07 connections and mounting the same after redoing End termination and giving jumper No 288.00
connections

Civil works

Constructing Transformer plinth of size 1.5m x 1.5m x 1.5m on 1.8m x 1.8m x 0.75m
basement inclusive of cost of all material. [Excavation 1.8m x1.8m x 0.75m, Random
CW 01 Rubble in CM(1:6) 1.8m x 1.8m x 0.75m + 1.5m x 1.5m x 1.5m, concrete(1:2:4, 20mm) No 9872.00
1.5m x1.5m x10cm, plaster CM(1:3) 12mm, 1.5m x 1.5m, Pointing CM(1:3) 1.5m x 1.5m x
4 sides.]
Providing concrete muffing of size 45cm x 45cm 1.5m (0.5m above GL and 1m below GL).
CW 02 Excavation 0.45m x 0.45m x1m, Concrete (1:3:6, 20mm) 0.45m x0.45m x1.5m, Plastering No 2400.00
(1:3) 12mm 0.45m x 0.45m x4+0.45m x 0.45m.

Secretary

Page 20 of 20