Supply, fitting & fixing Verandah grills made of M.S. section 1/2" x 1/2"
A. Cost of materials:
i) 1" x 1/4" F.I. bars (@ 1.28 Ibs per rft.)
10mm Solid Bar = 0.715 Kg
5 mm FI Bar= 0.403 Kg
= 1.118 Kg
Add wastage 5%= 0.0559 Kg
= 1.1739 Kg
= 1.1739 Kg @ Tk. 65.00 Per kg. = Tk. 76.30
ii)
1.5" x1.5" Box 0.16 rft.
Add wastage 5%= 0.008 rft.
= 0.17 rft.
= 0.17 Ibs. @ Tk. 75.00 Per Rft. = Tk. 12.60
B. Workshop charge:
Labour cost for manufacturing, welding
including supply of necessary electrode, cutting steel
to required sizes etx complete. @ Tk. 40.00 Per sft. Tk. 35.00
C. Labour charges:
Total = Tk. 123.90
Contractor's profit 10.00% = Tk. 12.39
Overhead expenses 3.50% = Tk. 29.73
Tk. 136.29
Rate per sqft. = Tk. 136.29
Sa
Tk. 137 .00 Per sqft.