Supply, fitting & fixing window grills made of M.S.

se cti on 3/4" x 1/8" with outer


frame s 1" x 1/4" .
For 1 No. window grill
Considering 3'-6" x 4'-6" = 15.75 sft. of work
A. Cost of mate rials:
i) 1" x 1/4" F.I. bars (@ 1.28 Ibs per rft.)
2 x 4' - 6" = 9 rft.
2 x 3' - 6"= 7 rft.
= 16 rft.
Add wastage 5%= 0.8 rft.
= 16.8 rft.
= 21.504 Ibs. @ T k. 7.71 Per Ib. = T k. 165.74
ii) 3/4" x 1/8" F.I. bars (@ 0.319 Ibs per rft.):
Horizontal: 5 x 3'-6" = 17.5 rft.
Vertical: 4 x 4'-6" = 18 rft.
Diagonal: 30 x 2'-0" = 60 rft.
= 95.5 rft.
Add wastage 5%= 4.775 rft.
= 100.28 rft.
= 31.99 Ibs. @ T k. 7.71 Per Ib. = T k. 246.76
B. Workshop charge:
Labour cost for manufact uring, welding
including supply of necessary electrode, cutting steel
to required sizes etx complete. 15.75 sft. @ T k. 20.00 Per sft. T k. 315.00
C. Labour charges:
Labour charges for fitting and fixing in position of grills
i) Mason 0.33 No. @ T k. 150.00 each = T k. 49.50
ii) Skilled labour 0.33 No. @ T k. 120.00 each = T k. 39.60
iii) Cost of screws 3 dzn. @ T k. 6.00 Per dzn. = T k. 18.00
D. Carriage charge for steel materials from market to
workshop and carrying the window grill from
workshop to building sit e. 1 No. @ T k. 15.00 each = T k. 15.00
Total = Tk. 849.60
Contractor's profit 10.00% = Tk. 84.96
Overhead expenses 3.50% = Tk. 29.74
Tk. 964.30
VAT 4.50% = Tk. 43.39
Grand total = Tk. 1,007.69
Rate per sft. = Tk. 63.98
Rate pe r sqm. = Tk. 688.68

Say, Tk. 689 .00 Pe r sqm.


T k. 165.74

T k. 246.76

T k. 315.00

T k. 49.50
T k. 39.60
T k. 18.00

T k. 15.00
Tk. 849.60
Tk. 84.96
Tk. 29.74
Tk. 964.30
Tk. 43.39
Tk. 1,007.69
Tk. 63.98
Tk. 688.68
Supply, fitting & fixing Verandah grills made of M.S. section 1/2" x 1/2"

A. Cost of materials:
i) 1" x 1/4" F.I. bars (@ 1.28 Ibs per rft.)
10mm Solid Bar = 0.715 Kg
5 mm FI Bar= 0.403 Kg
= 1.118 Kg
Add wastage 5%= 0.0559 Kg
= 1.1739 Kg
= 1.1739 Kg @ Tk. 65.00 Per kg. = Tk. 76.30
ii)
1.5" x1.5" Box 0.16 rft.
Add wastage 5%= 0.008 rft.
= 0.17 rft.
= 0.17 Ibs. @ Tk. 75.00 Per Rft. = Tk. 12.60
B. Workshop charge:
Labour cost for manufacturing, welding
including supply of necessary electrode, cutting steel
to required sizes etx complete. @ Tk. 40.00 Per sft. Tk. 35.00
C. Labour charges:
Total = Tk. 123.90
Contractor's profit 10.00% = Tk. 12.39
Overhead expenses 3.50% = Tk. 29.73
Tk. 136.29
Rate per sqft. = Tk. 136.29
Sa
Tk. 137 .00 Per sqft.