You are on page 1of 1

C A S E H I S T O R Y

Cement Permeation Grouting to support foundations for


a new basement excavation – Watson’s Bay, Sydney

The excavation of P ro j e c t Construction


The owner of a 100 year old cottage wished Due to extremely limited space on site the
a new basement to extend his living space underneath his project was carried out with light, handheld
below an existing existing floor space. During initial excavation drilling and injection equipment, while the grout
19th Century works it became evident that improvement was mixed and pumped remotely using electric
of the soil below the foundations would be colloidal mixers and low controlled volume
cottage required a required to ensure stability. piston pumps.
discrete solution.
Soil Conditions Following injection the grouted soil was left for 7
The property was underlain by dry fine to days prior to excavation sufficient time to allow
coarse Aeolian Sands of loose to medium the grout to achieve the required compressive
dense consistency. strengths of greater than 1MPa, while 28 day
results of >5Mpa were achieved.
Solution
Keller Ground Engineering was requested to Keller’s Permeation grouting system can be
stabilise the sands to allow the excavation of utilised to increase the strength and bearing
AUSTRALIA a vertical face of 1.8m below ground level and capacity of soils and is suitable for the
NEW ZEALAND 1.2 m below the existing footings. underpinning of structures, improving the
bearing capacity of foundations and control of
PACIFIC ISLANDS ground water flow.
Keller proposed the use of permeation
INDONESIA grouting to cement the sands insitu.
Permeation Grouting uses a low pressure Specialist Geotechnical
Enquiries to: injection of a cement suspension grout to fill Contractor:
PO Box 7974 the voids between the soil particles. In this Keller Ground Engineering Pty Ltd
Baulkham Hills NSW 1755
instance, due to the presence of fine sand
Level 1, 4 Burbank Place particles, a fine grained cement known as
Baulkham Hills NSW 2153 ‘microfine cement’ was used to ensure the
Australia grout flow through the small apertures between
t: (02) 8866 1155 the fine sand grains.
f: (02) 8866 1151
e: info@kellerge.com.au

GROUND ENGINEERING

You might also like