Agenda
Capital Improvement Program Overview Consent Decree Compliance Deep Rock Tunnel Connector Update Ancillary Projects
Sanitary projects Septic Tank Elimination Program (STEP) projects Stormwater projects
$75M
Construction:
Details:
Collection interceptor: 46,000 feet of pipe Sewer separation
Details:
Brill/Troy STEP
Project Cost: $8 million Bid Date: June 2009 Construction: July 2009-November 2010 Details:
Located on south side of Indianapolis Approximately 650 properties Project Scope: Install new sanitary sewers, manholes and lift stations
Details:
Located in northwestern Marion County Approximately 400 properties Project Scope: New sanitary sewer, manholes, lift stations, street resurfacing, drainage improvements
*Cost and schedule includes Phase II projects that have not yet bid. (Fox/Hill/Hoover STEP bid April 30.)
Details:
Located in northwestern Marion County Approximately 1,520 properties Project Scope: New sanitary sewer, manholes, lift stations, street resurfacing, drainage improvements
Ph. I Project Cost: $35 million Ph. II Project Cost: $13 million Bid Dates: February 2011, March 2013
Construction:
April 2011-April 2013 April 2013-November 2014
Details:
Located on southeast side of Indianapolis Approximately 1,660 properties Project Scope: Installing new sanitary sewers, manholes and lift stations in neighborhood streets and rights-of-way; improved drainage for Phase I only *Cost and schedule includes projects that have not yet bid. (Southeastern/Troy STEP bid April 30.)
Stormwater Projects
Questions?