SERVICIO GEOLOGICO MEXICANO

ARQUITECTA LAURA LORENA GONZALEZ MENDOZA


Concurso No.

Fecha:

4/11/2011

Obra:

REORDENAMIENTO DE CAJONES DE ESTACIONAMIENTO Y PUNTOS DE REUNION.

Lugar:

SERVICIO GEOLOGICO MEXICANO OAXACA

Ciudad:

SAN PABLO ETLA, OAXACA


PRESUPUESTO DE OBRA

Cdigo

Concepto

REORDENAMIENTO DE CAJONES

TRA0030

TRAZO Y NIVELACION DEL TERRENO CON

Unidad
M2

Cantidad

P. Unitario

Importe

656.00

$5.06

$3,319.36

TRANSITO Y NIVEL; INCLUYE CRUCETAS Y

$0.00

ESTACAS, PARA ESTABLECER EJES DE

$0.00

REFERENCIAS Y BANCOS DE NIVEL

$0.00
$0.00

EXC0010OK

EXCAVACION DE CEPAS DE 35 CMS X 35 CMS

M3

14.50

$110.04

$1,595.58

EN PROMEDIO DE PROFUNDIDAD PARA LA

$0.00

FABRICACION DE SARDINALES, QUE SERVIRAN

$0.00

PARA SEPARAR LOS CAJONES DEL ESTACIONAMIENTO

$0.00

INCLUYE;ACARREO DE ESCOMBRO A BANCO,

$0.00

HERRAMIENTA Y MANO DE OBRA.

$0.00
$0.00

CADDES15X25

NIVELACION DEL TERRENO PARA DESPLANTE DE

M2

180.00

$45.21

$8,137.80

SARDINELAS DONDE LA REQUIERA, INCLUYE;

$0.00

ACARREO DE ESCOMBRO A BANCO,

$0.00

HERRAMIENTA Y MANO DE OBRA.

$0.00
$0.00

PIS10OK

MURO CABECERO DE 14 CMS DE ESPESOR POR 60

ML

12.00

$335.80

$4,029.60

CMS EN PROMEDIO DE ALTURA A BASE DE TABICON

$0.00

PARA RETENCION DE RELLENO EN AREA DE

$0.00

ESTACIONAMIENTO, INCLUYE;GRAPA COMO CASTILLOS

$0.00

EN AMBOS LADOS Y CADENA DE CERRAMIENTO,

$0.00

LAS CADENAS Y LOS CASTILLOS SERAN CON MITADES

$0.00

DE ARMEX, MATERIAL, HERRAMIENTA Y MANO DE O.

$0.00
$0.00

SAPIES10-AZU

RELLENO DEL TERRENO CON MATERIAL MEJORADO

M3

128.00

$220.90

$28,275.20

TRAIDO FUERA DE LA OBRA PARA SUBIR EL NIVEL

$0.00

DEL ESTACIONAMIENTO, INCLUYE; SUMINISTRO Y

$0.00

ACARREO PARA EL RELLENO, HERRAMIENTA Y

$0.00

MANO DE OBRA.

$0.00
$0.00

SAPIES10-VER

FABRICACION DE SARDINELAS DE 8 CMS DE ESPESOR ML

115.00

$179.80

$20,677.00

POR 25 CMS DE PERALTE A BASE DE CONCRETO

$0.00

F'C= 150 KG/CM2, ARMADO CON ARMEX TRIANGULAR,

$0.00

INCLUYE; MATERIAL, HERRAMIENTAS Y MANO DE

$0.00

OBRA.

$0.00
$0.00

SAPIES10-ROJ

SUMNISTRO Y COLOCACION DE GRAV TRITURDA

M2

345.00

$45.20

$15,594.00

SIMILAR A LA EXISTENTE, EN LOS CAJONES DE

$0.00

ESTACIONAMIENTO, DE 5 CMS DE ESPESOR,

$0.00

INCLUYE; MATERIAL, ACARREOS, MANO DE OBRA

$0.00

Y HERRAMIENTAS

$0.00
$0.00

TABBASQ01

SUMINISTRO Y APLICACIN D EPINTURA ESMALTE

ML

145.00

$54.35

$7,880.75

COLOR AMARILLO TRAFICO D ECOMEX, EN SARDINEL

$0.00

INCLUYE;MATERIAL, MANO D EOBRA, LIMPIEZA,

$0.00

SERVICIO GEOLOGICO MEXICANO

ARQUITECTA LAURA LORENA GONZALEZ MENDOZA


Concurso No.

Fecha:

4/11/2011

Obra:

REORDENAMIENTO DE CAJONES DE ESTACIONAMIENTO Y PUNTOS DE REUNION.

Lugar:

SERVICIO GEOLOGICO MEXICANO OAXACA

Ciudad:

SAN PABLO ETLA, OAXACA


PRESUPUESTO DE OBRA

Cdigo

Concepto
Y HERRRAMIENTA.

Total: REORDENAMIENTO DE CAJONES

Unidad

Cantidad

P. Unitario

Importe
$0.00
$89,509.29

SERVICIO GEOLOGICO MEXICANO

ARQUITECTA LAURA LORENA GONZALEZ MENDOZA


Concurso No.

Fecha:

4/11/2011

Obra:

REORDENAMIENTO DE CAJONES DE ESTACIONAMIENTO Y PUNTOS DE REUNION.

Lugar:

SERVICIO GEOLOGICO MEXICANO OAXACA

Ciudad:

SAN PABLO ETLA, OAXACA


PRESUPUESTO DE OBRA

Cdigo

Concepto

Unidad

Cantidad

P. Unitario

Importe

4.00

$956.32

$3,825.28

$0.00

PUNTOS DE REUNION

SCPOSFOGO4" ELABORACION DE BASE DE CONCRETO DE F'C=

PZA

150 KG/CM2 DE 10 CMS DE ESPESOR, POR 1.90

$0.00

X 1.90 MTS PARA COLOCAR LOS PUNTOS DE

$0.00

REUNION, INCLUYE; MATERIAL, HERRAMIENTA

$0.00

Y MANO DE OBRA.

$0.00
$0.00

REDVOL01

ELABORACION DE ROTULOS PARA LOS PUNTOS

PZA

5.00

DE REUNION QUE DIRA " PUNTO DE REUNION"

$522.43

$2,612.15
$0.00

A BASE DE PINTURA ESMALTE S.R. ACRILICO


SCPOST01

COLOR VERDE, COLOR BLANCO, AMBOS CON


CATALIZADOR, INCLUYE TINER AMERICANO,
MATERIAL MANO DE OBRA Y HERRAMIENTA.
Total: PUNTOS DE REUNION

Total del Presupuesto sin IVA:

$6,437.43
$95,946.72

I.V.A 16.00 %

$15,351.48

Total del Presupuesto:

$111,298.20

(*CIENTO ONCE MIL DOCIENTOS NOVENTA Y OCHO PESOS 20/100 M.N. *)

ATENTAMENTE
ARQUITECTA LAURA LORENA GONZALEZ MENDOZA
CED. PROF. 5714005

MUNICIPIO DE OAXACA DE JUAREZ


Dependencia:

DIRECCION GENERAL DE OBRAS PUBLICAS


DIRECCION DE LICITACIONES Y CONTROL PRESUPUESTAL

Concurso No.

DLCP-UCP-0181/2011

Obra:

RESCATE PARQUE CENTRAL TRINIDAD DE VIGUERA

Fecha: 2011/03/30

Lugar:

CALLE INDEPENDENCIA ESQ. LIBERTAD, AGENCIA TRINIDAD DE VIGUERA

Ciudad:

OAXACA, OAXACA
LISTADO DE INSUMOS QUE INTERVIENEN EN LA INTEGRACION DE LA PROPUESTA

Cdigo

Concepto

Unidad

Fecha

PZA

Cantidad

Precio

Importe

%Incidencia

1 MATERIALES
A83040R

ADOPASTO REDONDO NATURAL 30x40x8

22-Mar-2011

1,509.48

$16.81

$25,374.36

0.94%

ABO0090

abono.

M3

30-Mar-2011

75.1590

$95.00

$7,140.11

0.26%

ACE0010

Acero del No. 2 ( alambrn).

KG

22-Mar-2011

2,197.93

$12.06

$26,507.05

0.98%

ACR6MM01

PLACA DE ACRIL. 6MM IMPRESA (VINIL)

M2

22-Mar-2011

0.2400

$827.59

$198.62

0.01%

AGL0010

Membrana de curado

LT

22-Mar-2011

512.1575

$13.47

$6,898.76

0.26%

AGU0010

Agua

M3

22-Mar-2011

558.3643

$45.00

$25,126.40

0.93%

AL0010

Alambre recocido No. 18.

KG

22-Mar-2011

546.6001

$12.93

$7,067.54

0.26%

ANGULO 1" X

angulo de 1"x1"x1/4"

ML

22-Mar-2011

114.0000

$21.73

$2,477.22

0.09%

ml

22-Mar-2011

190.2500

$67.00

$12,746.75

0.47%

1/4"
ANGULO 2 1/2"

Angulo de 2 1/2" x 2 1/2" x 1/4"

1/4"
ARBOLVAR

ARBOL ESPECIES NATIVAS

pza

22-Mar-2011

77.0000

$175.00

$13,475.00

0.50%

ARBT13WATTS

ARBOTANTE 13 WATTS.

PZA.

22-Mar-2011

1.0000

$264.34

$264.34

0.01%

ARGOLL1"

ARGOLLA DE 1"

PZA

22-Mar-2011

154.1850

$5.00

$770.93

0.03%

ARGOLL1/4"

Argolla de 1/4"

pieza

22-Mar-2011

26.0000

$3.50

$91.00

0.00%

ARRASTRE 4 X

Arrastre de seccion4"x4"x.4

PT

22-Mar-2011

274.6921

$7.50

$2,060.19

0.08%

BANCAJUMBO

BANCA TRADICIONAL DE FIERRO COLADO

pza

25-Mar-2011

15.0000

$2,725.00

$40,875.00

1.51%

BARROTE DE

Barrote de 1 1/2"x4"x8"

PT

22-Mar-2011

210.3357

$7.50

$1,577.52

0.06%

22-Mar-2011

10.0000

$1,390.00

$13,900.00

0.51%

4X4

MADERA
BASEPREFAB.

BASE PREFABRICADA CONCRETO F'C=200

PZA.

KG/CM
BISA020

Bisagra de hierro de 3/8" alargada de 76

pieza

22-Mar-2011

152.2000

$29.90

$4,550.78

0.17%

BOMB 2HP

BOMBA ELECT. 2HP

pza

22-Mar-2011

2.0000

$11,150.00

$22,300.00

0.83%

BOQUICREST

Boquicrest ultra colores arena, grises o

kg

22-Mar-2011

10.2322

$6.38

$65.28

0.00%

CABLE N6

CABLE THW N6

ML

22-Mar-2011

894.3696

$26.00

$23,253.61

0.86%

CABLE N10

CABLE THW N10

ML

22-Mar-2011

104.7922

$13.00

$1,362.30

0.05%

CABLE THW

Cable THW No. 12 cubierto

ML

22-Mar-2011

13.7400

$10.40

$142.90

0.01%

22-Mar-2011

9.0000

$16.31

$146.79

0.01%

22-Mar-2011

120.0000

$5.50

$660.00

0.02%

NO. 12
Cable THW No. 8 Cubierto

CABLE THW

ml

NO. 8
CABLETHWCAL CABLE THW CAL. 10

ML.

0.10
CACH01

Cachetes de seccion 1"x4"x.055 ml.

PT

22-Mar-2011

249.0542

$7.50

$1,867.91

0.07%

CADENA1"

Cadena de 1" de ancho Ced-30

ML

22-Mar-2011

3.9000

$30.00

$117.00

0.00%

CANAL DE

canal de amarre

ml

22-Mar-2011

37.8624

$5.95

$225.28

0.01%

AMARRE
CAR0010

Cartn asfaltico.

M2

22-Mar-2011

271.1321

$5.32

$1,442.42

0.05%

CCUAD3/4

chalupa galvanizada para contacto 3/4"

pza.

22-Mar-2011

1.0000

$2.55

$2.55

0.00%

MUNICIPIO DE OAXACA DE JUAREZ


Dependencia:

DIRECCION GENERAL DE OBRAS PUBLICAS


DIRECCION DE LICITACIONES Y CONTROL PRESUPUESTAL

Concurso No.

DLCP-UCP-0181/2011

Obra:

RESCATE PARQUE CENTRAL TRINIDAD DE VIGUERA

Fecha: 2011/03/30

Lugar:

CALLE INDEPENDENCIA ESQ. LIBERTAD, AGENCIA TRINIDAD DE VIGUERA

Ciudad:

OAXACA, OAXACA
LISTADO DE INSUMOS QUE INTERVIENEN EN LA INTEGRACION DE LA PROPUESTA

Cdigo

Concepto

Unidad

Fecha

Cantidad

Precio

Importe

%Incidencia

1 MATERIALES
CEM0010

Cemento gris normal

TON

22-Mar-2011

171.6935

$1,754.00

$301,150.37

11.15%

CEM0020

Calhidra

TON

22-Mar-2011

0.4730

$1,336.00

$631.88

0.02%

CEM0031

Cemento blanco

22-Mar-2011

0.1536

$3,060.34

$470.05

0.02%

CEM0040

Color para cemento rojo

KG

22-Mar-2011

52.3550

$77.59

$4,062.22

0.15%

CEM0050

Color para cemento beige

KG

22-Mar-2011

85.3930

$22.41

$1,913.66

0.07%

CEMENTO

Cemento para PVC pegaln

lt

22-Mar-2011

58.2651

$138.54

$8,072.05

0.30%

PZA

22-Mar-2011

1.0000

$238.46

$238.46

0.01%

ml

22-Mar-2011

40.6800

$35.00

$1,423.80

0.05%

ton

PARA PVC
Centro de carga Square D QO-2

CENT CARG
QO2

Cimbra cilindrica de carton 0.20 cms de

CIMB CIL
CARTON 20CM
CIN01

Cinta para proteccin de peatones.

ML

22-Mar-2011

10.8790

$2.00

$21.76

0.00%

CINTA AISLAR

CINTA DE AISLAR DEL N . 22

PZA

22-Mar-2011

48.5900

$3.50

$170.07

0.01%

CINTA DE AISLAR DEL N 33

PZA

22-Mar-2011

48.5900

$8.16

$396.49

0.01%

CINTA DE VINILO

PZA

22-Mar-2011

48.5900

$5.00

$242.95

0.01%

23
CINTA AISLAR
33
CINTA DE
VINILO
CLA0010

Clavo de 2.5"

KG

22-Mar-2011

159.5486

$13.79

$2,200.18

0.08%

CO PVC 90| 4"

CODO DE PVC DE 90 X 4"

PZA

22-Mar-2011

15.7484

$182.72

$2,877.54

0.11%

COM001

Diesel.

LT

22-Mar-2011

6,347.81

$7.10

$45,069.48

1.67%

COM060

Gas butano LP

22-Mar-2011

1.2000

$7.50

$9.00

0.00%

CONDUCTOR

CONDUCTOR DESNUDO No. 8

ML.

22-Mar-2011

120.0000

$8.30

$996.00

0.04%

Disco de diamante

PZA

22-Mar-2011

0.9461

$2,134.92

$2,019.90

0.07%

ML

22-Mar-2011

1.7400

$4.47

$7.78

0.00%

ML

22-Mar-2011

9.0000

$1.04

$9.36

0.00%

PZA

22-Mar-2011

15.7486

$21.00

$330.72

0.01%

kg

DESNUDO
DISCO DE
DIAMANTE
ELECTRODUCT Electroducto naranja de 19 mm. de diamet
O 19 MM
ELECTRODUCT ELECTRODUCTO NARANJA DE 1/2" DE
O N. 13 M

DIAMETRO

EMPAQUE DE

Empaque de plomo de 4"

PLOMO 4"
ENE01

Energa elctrica

KW

22-Mar-2011

460.9369

$2.50

$1,152.34

0.04%

ESTOPA

ESTOPA

KG

22-Mar-2011

10.0000

$24.56

$245.60

0.01%

FESTERMIP3

Festermip APP PS. de 4.0 H terracota.

M2

22-Mar-2011

2.5421

$1,140.00

$2,897.99

0.11%

GASOLINA

Gasolina sin plomo.

LTO

22-Mar-2011

1,144.46

$7.62

$8,720.81

0.32%

HIDRANTE

Hidrante de bronce salida de 1/2"

pza

22-Mar-2011

7.0000

$125.00

$875.00

0.03%

HIDROPRIM19

hidroprimer

LT

22-Mar-2011

0.3041

$943.48

$286.94

0.01%

INTTER1X25

Interruptor termomagnetico de 1 x 25 amp

PZA

22-Mar-2011

1.0000

$684.00

$684.00

0.03%

JGOANCLAS

Juego de anclas (4 pzas.) de 3/4 x 0.60

22-Mar-2011

19.0000

$134.80

$2,561.20

0.09%

pza

MUNICIPIO DE OAXACA DE JUAREZ


Dependencia:

DIRECCION GENERAL DE OBRAS PUBLICAS


DIRECCION DE LICITACIONES Y CONTROL PRESUPUESTAL

Concurso No.

DLCP-UCP-0181/2011

Obra:

RESCATE PARQUE CENTRAL TRINIDAD DE VIGUERA

Fecha: 2011/03/30

Lugar:

CALLE INDEPENDENCIA ESQ. LIBERTAD, AGENCIA TRINIDAD DE VIGUERA

Ciudad:

OAXACA, OAXACA
LISTADO DE INSUMOS QUE INTERVIENEN EN LA INTEGRACION DE LA PROPUESTA

Cdigo

Concepto

Unidad

Fecha

Cantidad

Precio

JUEGO INF.XOLPARK, CLAVE AXL-08A

PZA

22-Mar-2011

lija siamat 0600 oxido alum.

pza.

22-Mar-2011

2.7450

m2

22-Mar-2011

16.6530

22-Mar-2011

25.5990

$185.00

22-Mar-2011

25.2139

22-Mar-2011

5.0000

PZA.

22-Mar-2011

10.0000

PZA

Importe

%Incidencia

1 MATERIALES
JUEGO

1.0000

$108,799.96

$108,799.96

4.03%

$9.48

$26.02

0.00%

$78.00

$1,298.93

0.05%

$4,735.82

0.18%

$20.19

$509.07

0.02%

$32,000.00

$160,000.00

5.92%

$1,536.50

$15,365.00

0.57%

AXL-080A
LI002

LOSETINTER30 Loseta marca Interceramic 0.30x0.30 para


X30
LOSINTE33.

Loseta marca Interceramic de 33.5x33.5 c

M2

5X33.5
LUB001

Aceite multigrado.

LU-ENA-40

LUMINARIA URBANA SOLAR ENALTO

LUM.

LUMINARIA TIPO VENUS INC: GABINETE,

TIPOVENUS

BALA

LUMPISA

luminaria para piso cilindrica mod. 95/8

LUM-SPOTSLA- LUMINARIA TIPO SPOT MOD. SLA

LT
pza

22-Mar-2011

3.0000

$2,379.73

$7,139.19

0.26%

pza

22-Mar-2011

6.0000

$622.00

$3,732.00

0.14%

S13Q

S13Q-41-120

MAD0010

Madera de pino de 3a.

PT

22-Mar-2011

1,628.46

$9.73

$15,844.90

0.59%

MAD0020

Chaflan de pino de 3/4"

ML

22-Mar-2011

439.2887

$3.50

$1,537.51

0.06%

MALLA CROW

Malla Ground Cover

m2

22-Mar-2011

368.6473

$28.73

$10,591.24

0.39%

MALLA6,6-10,10 MALLA ELECTROSOLDADA 6,6-10,10

M2

22-Mar-2011

2,152.29

$12.16

$26,171.85

0.97%

MALLATEX-RED MALLA TEXTIL DE RED PROFESIONAL

M2

30-Mar-2011

211.5520

$176.46

$37,330.47

1.38%

22-Mar-2011

1.0000

$650.00

$650.00

0.02%

MARCO Y

Marco y contramarco de angulo de1 1/2"x3

PZA

CONR. 40X40X
MCO.010

Marco y contramarco de angulo est. de 1"

22-Mar-2011

1.0000

$100.00

$100.00

0.00%

pza

22-Mar-2011

4.0000

$4,129.31

$16,517.24

0.61%

METAL DESPLEGADO CALIBRE 22

ML

22-Mar-2011

45.7560

$50.00

$2,287.80

0.08%

MUFA PARA INTEMPERIE DE 64mm (2 1/2").

pieza

22-Mar-2011

1.0000

$264.00

$264.00

0.01%

NEU001

neumatico para camin volteo o camin pi

PZA

22-Mar-2011

0.3595

$1,780.48

$640.13

0.02%

NEU002

Neumatico cargador frontal.

22-Mar-2011

0.0342

$3,207.33

$109.60

0.00%

NEU0020

Neumtico para revolvedora.

PZA

22-Mar-2011

0.1419

$300.00

$42.57

0.00%

NEU004

Neumatico para motoconformadora.

PZA

22-Mar-2011

0.1586

$2,282.80

$362.10

0.01%

NEU0060

Neumtico para compresor.

22-Mar-2011

0.0020

$390.00

$0.78

OBJ-LUD

OBJETO LUDICO VIVIR MEJOR

PZA

30-Mar-2011

1.0000

$16,465.44

$16,465.44

0.61%

PAGO CFE

Pagos de tramites y libranzas a CFE

lote

30-Mar-2011

1.0000

$5,538.46

$5,538.46

0.21%

MESAJUMBOPV MESA PVC- MACA JUMBO

PZA

C
METDESP
CAL22
MUFAINTEMP2
1/2"
PZA

PZA

INDEPEN
PAP-50

PAPELERA MOD. PRIMA 50 LTS

PZA

25-Mar-2011

15.0000

$1,783.59

$26,753.85

0.99%

PASTO

PASTO ALFOMBRA

M2

25-Mar-2011

375.8055

$43.10

$16,197.22

0.60%

25-Mar-2011

57.7320

$178.00

$10,276.30

0.38%

ALFOMBRA
PASTSIN30MM

PASTO SINTETICO DE 30 MM DE ALTO

M2

MUNICIPIO DE OAXACA DE JUAREZ


Dependencia:

DIRECCION GENERAL DE OBRAS PUBLICAS


DIRECCION DE LICITACIONES Y CONTROL PRESUPUESTAL

Concurso No.

DLCP-UCP-0181/2011

Obra:

RESCATE PARQUE CENTRAL TRINIDAD DE VIGUERA

Fecha: 2011/03/30

Lugar:

CALLE INDEPENDENCIA ESQ. LIBERTAD, AGENCIA TRINIDAD DE VIGUERA

Ciudad:

OAXACA, OAXACA
LISTADO DE INSUMOS QUE INTERVIENEN EN LA INTEGRACION DE LA PROPUESTA

Cdigo

Concepto

Unidad

Fecha

Cantidad

Precio

Importe

%Incidencia

MUESTR

22-Mar-2011

0.0527

$1,500.00

$79.11

0.00%

lts

22-Mar-2011

47.6250

$69.56

$3,312.80

0.12%

1 MATERIALES
PBA0021

muestra y prueba de calidad de los mater

PC100

pintura vinilica comex

PEG0021

Pegazulejo mca. niasa. bulto 20 kgs.

SACO

22-Mar-2011

25.3512

$43.48

$1,102.27

0.04%

PER0010

Perfil monte MT14 5 mts.

KG

22-Mar-2011

145.9934

$11.56

$1,687.68

0.06%

PERFACINTA

Perfacinta

ml

22-Mar-2011

23.0400

$0.22

$5.07

0.00%

PET0010

Arena

22-Mar-2011

319.5999

$186.78

$59,694.88

2.21%

PET0020

Grava agregado 3/4"

M3

22-Mar-2011

295.7146

$275.00

$81,321.51

3.01%

PET0040

Revestimiento (Material de banco.)

M3

22-Mar-2011

1,092.97

$120.00

$131,156.40

4.86%

PIN0040

Pintura esmalte anticorrosiva 100 comex

litro

22-Mar-2011

65.5510

$69.87

$4,580.05

0.17%

PIN-ESMALTE

pintura de esmalte

lt

22-Mar-2011

62.5000

$70.00

$4,375.00

0.16%

PINTURA

PINTURA ESMALTE

LT.

22-Mar-2011

15.0000

$74.87

$1,123.05

0.04%

placa de acero 5/8"

M2

22-Mar-2011

0.2940

$1,375.80

$404.49

0.02%

M2

22-Mar-2011

3.1388

$1,666.88

$5,232.00

0.19%

M2

22-Mar-2011

0.4400

$1,077.59

$474.14

0.02%

PT

M3

ESMALTE
placaacero5/8

PLACAESTRUC PLACA ESTRUCTURAL DE 1/2"


T1/2
PLACESTRUC3/ placa estructural de 3/8"
8
POLIN

polin de 3 1/2"x3 1/2"

POSTE DE 6 M.

POSTE DE 3" X 6.00 DE ALTO

POSTEACERO4 POSTE DE ACERO 4"

22-Mar-2011

525.8392

$7.50

$3,943.79

0.15%

PZA.

22-Mar-2011

10.0000

$1,100.00

$11,000.00

0.41%

ml

22-Mar-2011

18.0000

$217.89

$3,922.02

0.15%

"
PVC 3/4

PVC HID. 3/42

ML

22-Mar-2011

138.9882

$37.00

$5,142.56

0.19%

RED VOLEIB.

RED PARA CANCHA DE VOLEIBOL. MED

PZA

22-Mar-2011

1.0000

$1,465.52

$1,465.52

0.05%

MED REGL

REGL.

REDIMIX

redimix

kg

22-Mar-2011

1.7572

$4.46

$7.84

0.00%

REFHOLP

REFLECTOR 250W

PZA

22-Mar-2011

13.0000

$103.50

$1,345.50

0.05%

RENT

Renta de planta electrica (para soldar)

HORA

22-Mar-2011

13.2614

$75.39

$999.78

0.04%

hora

22-Mar-2011

113.0000

$1.25

$141.25

0.01%

LTO

22-Mar-2011

28.5750

$25.46

$727.52

0.03%

22-Mar-2011

1.0000

$2,350.00

$2,350.00

0.09%

SOLDADE
RENTA

Renta de andamio metalico hasta una altu

ANDAMIO
10MTS
SEL0010

Sellador vinilico 5x1

SE0020

Suministro y colocacin de seal informa

SOL0030

Soldadura 60-13

KG

22-Mar-2011

80.7488

$35.00

$2,826.21

0.10%

SOL020

Soldadura 70-18

kg

22-Mar-2011

28.5707

$37.50

$1,071.40

0.04%

SOLERA21/2"

solera de 2 1/2" x 1/4"

kg

22-Mar-2011

978.9734

$15.94

$15,604.84

0.58%

TAB001-D

TABLAROCA

m2

22-Mar-2011

16.1280

$74.48

$1,201.21

0.04%

TAB020

Tabicn 10 x 14 x 28 cm

22-Mar-2011

34,166.65

$2.58

$88,149.95

3.26%

PZA

X1/4"
PZA

MUNICIPIO DE OAXACA DE JUAREZ


Dependencia:

DIRECCION GENERAL DE OBRAS PUBLICAS


DIRECCION DE LICITACIONES Y CONTROL PRESUPUESTAL

Concurso No.

DLCP-UCP-0181/2011

Obra:

RESCATE PARQUE CENTRAL TRINIDAD DE VIGUERA

Fecha: 2011/03/30

Lugar:

CALLE INDEPENDENCIA ESQ. LIBERTAD, AGENCIA TRINIDAD DE VIGUERA

Ciudad:

OAXACA, OAXACA
LISTADO DE INSUMOS QUE INTERVIENEN EN LA INTEGRACION DE LA PROPUESTA

Cdigo

Concepto

Unidad

Fecha

Cantidad

Precio

Importe

%Incidencia

PZA.

30-Mar-2011

5,716.88

$1.95

$11,147.92

0.41%

PZA

22-Mar-2011

2.0000

$3,500.00

$7,000.00

0.26%

1 MATERIALES
TABI014

Tabique rojo recocido de 7x14x28 cms. de

TABLEROBASQ Suministro y colocacion de tablero de Ba


UET
TAQUETES

Taquetes plastico de 1/4"

pieza

22-Mar-2011

76.8000

$0.20

$15.36

0.00%

TBO3"

POSTE 3 " DIAM CED 30

ML

22-Mar-2011

73.1000

$95.38

$6,972.28

0.26%

TBOFOGO4"

TUBO DE FoGo DE 4" CED-40

ML

22-Mar-2011

162.1400

$289.94

$47,010.87

1.74%

22-Mar-2011

436.7550

$11.66

$5,092.56

0.19%

22-Mar-2011

15.7484

$239.20

$3,767.01

0.14%

CED4O
TBTIPP52MM

tubo de pvc tipo pesado de 2".

TEE PVC H 4 X

TEE DE PVC DE 100 X 100 (4" X 4")

ml
PZA

4
TEPEXIL

Tepexil

THINER

Thiner estandar

Tinher

M3

22-Mar-2011

15.0000

$327.60

$4,914.00

0.18%

litro

22-Mar-2011

1.6470

$14.36

$23.65

0.00%

tinher comex

lt

22-Mar-2011

22.5000

$14.50

$326.25

0.01%

TORNILLOS

tornillos de 1"

pieza

22-Mar-2011

76.8000

$0.37

$28.42

0.00%

TORNILLOS 1

tornillos de 1 1/2"

pieza

22-Mar-2011

38.4000

$0.95

$36.48

0.00%

22-Mar-2011

1.0000

$12,983.62

$12,983.62

0.48%

22-Mar-2011

106.8716

$109.18

$11,668.24

0.43%

1/2"
transtri30kva

transformador tri 30 kva

TRIPLAY DE

Tripay de pino de 16 mm. de espesor.

pza
M2

PINO 16 M
TUBACE4"C-40

Tubo de acero de 4" de diam. ced-40

22-Mar-2011

4.2900

$362.32

$1,554.35

0.06%

TUBO 2"

Tubo de 2" de diam. Ced-40

ML
ML

22-Mar-2011

166.7050

$26.51

$4,419.35

0.16%

TUBO PVC 4"

TUBO DE PVC SAN REFORSADO 4"

ML

22-Mar-2011

95.4349

$36.77

$3,509.14

0.13%

TUBO PVC

Tubo de PVC Sanitario de 4" de diametro.

ml

30-Mar-2011

1.0000

$36.77

$36.77

0.00%

22-Mar-2011

107.9295

$27.08

$2,922.73

0.11%

ML

22-Mar-2011

37.3560

$86.33

$3,224.94

0.12%

pieza

22-Mar-2011

12.0000

$1.80

$21.60

0.00%

CED-40

SANIT. 4"
TUBULAR DE 3" X 11/2"

TUBULAR

ML

3"X11/2"
TUBULAR DE 4" X 2" CAL 18

TUBULAR 4" X
2"

Tuerca de 3/4" hexagonal

TUERCA
ACER.HEX 3/4"
UNI1CM

UNICEL 1 CM DE ESPESOR

M2

22-Mar-2011

63.8514

$4.00

$255.41

0.01%

VALVGLOBO13

Valvula de globa marca Urrea de 13 mm

PZA

22-Mar-2011

5.0000

$46.09

$230.45

0.01%

VARILLA # 3

Varilla del No. 3

TON

22-Mar-2011

7.0380

$10,690.00

$75,236.24

2.79%

VARILLA # 5

Varilla del No. 5

TON

22-Mar-2011

0.4260

$8,793.00

$3,746.23

0.14%

VARILLA # 6

Varilla del No. 6

TON

22-Mar-2011

0.0669

$14,782.60

$988.51

0.04%

VARILLA DEL #

Varilla del No. 4

ton

22-Mar-2011

0.0433

$10,690.00

$462.87

0.02%

MM

4
Total: MATERIALES

$1,763,755.75

MUNICIPIO DE OAXACA DE JUAREZ


Dependencia:

DIRECCION GENERAL DE OBRAS PUBLICAS


DIRECCION DE LICITACIONES Y CONTROL PRESUPUESTAL

Concurso No.

DLCP-UCP-0181/2011

Obra:

RESCATE PARQUE CENTRAL TRINIDAD DE VIGUERA

Fecha: 2011/03/30

Lugar:

CALLE INDEPENDENCIA ESQ. LIBERTAD, AGENCIA TRINIDAD DE VIGUERA

Ciudad:

OAXACA, OAXACA
LISTADO DE INSUMOS QUE INTERVIENEN EN LA INTEGRACION DE LA PROPUESTA

Cdigo

Concepto

Unidad

Fecha

Cantidad

Precio

Importe

%Incidencia

2 MANO DE OBRA
%HERMENOR

% DE HERRAMIENTA MENOR

(%)mo

22-Mar-2011

0.0000

$0.00

$13.74

0.00%

%MO246

Mando Intermedio

(%)mo

22-Mar-2011

0.0000

$0.00

$75,316.30

2.79%

MO0010

topografo

jor

22-Mar-2011

1.7371

$423.79

$736.15

0.03%

MO0020

Operador de maquinaria pesada.

22-Mar-2011

28.2900

$436.64

$12,352.55

0.46%

MO0030

Operador de maquinaria menor

22-Mar-2011

62.7323

$256.83

$16,111.53

0.60%

MO0040

OFICIAL A

22-Mar-2011

1,047.83

$423.79

$444,059.95

16.44%

MO0050

Oficial B

22-Mar-2011

2.5018

$363.25

$908.78

0.03%

MO0060

Ayudante general

jor

22-Mar-2011

200.2258

$254.85

$51,027.54

1.89%

MO0070

Pen

jor

22-Mar-2011

1,119.70

$243.99

$273,196.34

10.11%

Total: MANO DE OBRA

jor
jor
jor
jor

$873,722.88

MUNICIPIO DE OAXACA DE JUAREZ


Dependencia:

DIRECCION GENERAL DE OBRAS PUBLICAS


DIRECCION DE LICITACIONES Y CONTROL PRESUPUESTAL

Concurso No.

DLCP-UCP-0181/2011

Obra:

RESCATE PARQUE CENTRAL TRINIDAD DE VIGUERA

Fecha: 2011/03/30

Lugar:

CALLE INDEPENDENCIA ESQ. LIBERTAD, AGENCIA TRINIDAD DE VIGUERA

Ciudad:

OAXACA, OAXACA
LISTADO DE INSUMOS QUE INTERVIENEN EN LA INTEGRACION DE LA PROPUESTA

Cdigo

Concepto

Unidad

Fecha

Cantidad

Precio

Importe

%Incidencia

3 EQUIPO Y HERRAMIENTA
C.F. EQ0253

Equipo de oxicorte

C.F. EQU00150

Soldadora de arco electrico

C.F. EQU00170

Bailarina (compactador mecanico).

C.F. EQU0030

Retroexcavadora marca caterpillar modelo

C.F. EQU0050

Compresor de aire marca atlas copco xas9

C.F.

Motoconformadora CAT 12-G

hora

22-Mar-2011

0.6000

$30.46

$18.28

0.00%

22-Mar-2011

65.0546

$8.44

$549.06

0.02%

22-Mar-2011

288.3644

$26.76

$7,716.63

0.29%

hora

22-Mar-2011

21.3571

$167.94

$3,586.72

0.13%

hora

22-Mar-2011

2.0000

$249.42

$498.84

0.02%

hora

22-Mar-2011

52.8735

$406.20

$21,477.21

0.80%

Camin volteo de 7 m3.

hora

22-Mar-2011

149.8031

$103.24

$15,465.67

0.57%

Cortadora

hora

22-Mar-2011

26.7281

$8.58

$229.33

0.01%

Revolvedora de 1 saco.

hora

22-Mar-2011

141.8968

$21.02

$2,982.67

0.11%

22-Mar-2011

33.8228

$118.13

$3,995.48

0.15%

hora

22-Mar-2011

18.2400

$20.03

$365.35

0.01%

hora

22-Mar-2011

106.4960

$12.53

$1,334.40

0.05%

hora
hora

MOTOCONF.
C.F. RENTA
CAMION VO
C.F. RENTA DE
CORTAD
C.F.
REVOLVEDORA
1S
C.F. ROTMART

ROTOMARTILLO MAKITA HR 3000C

hora

ENTRADA SDS
C.F. TRANSITO

Transito optico Rosbach con equipo.

ROSBAC
C.F. VIBRADOR Vibrador de gasolina.
DE GAS
GRUA20TON

GRUA NEUMATICOS 20 TON

RENTA

renta de pintarraya manual

HRS

22-Mar-2011

3.0000

$750.00

$2,250.00

0.08%

HR

22-Mar-2011

49.2125

$65.00

$3,198.81

0.12%

PINTARRAYA
M.
Total: EQUIPO Y HERRAMIENTA

$63,668.45