Abed Holdings Ltd.

Project: Al-Razi Complex 3/1/D, Purana Paltan,Dhaka-1000 Work Schedule of Deep tubeweel work (Mud Tank) Date: 13.09.11 Sl. Description of work Name of Date of Date of Duration No. Contractor Start Complition (Days) 1 Pavment tiles & R.C.C slab breaking Mr.Momotaj 13.09.11 14.09.11 2 Days 2 Earth excavation 2 days 3 5" Brick work Mr.Momotaj Mr.Shajahan 17.09.11 15.09.11 17.09.11 16.09.11 1 Day