Professional Documents
Culture Documents
Additional Practice problems (Not Required) 1. Use trial and error to balance the assembly line described in the following table and Figure 1 so that it will produce 40 units per hour. a. What is the cycle time? b. What is the theoretical minimum number of workstations? c. Which work elements are assigned to each workstation? d. What are the resulting efficiency and balance delay percentage? e. Work Element A B C D E F G H I J K Total Time (sec) 40 80 30 25 20 15 60 45 10 75 15 415 Immediate Predecessor(s) None A A B C B B D E,G F H,I,J
Answer: a. b. c. d. 2.
90 sec/unit 4.611 5 Five workstations - ACE---B---GD---HFI---JK Efficiency = 92.2% Johnson Cogs wants to set up a line to serve 60 customers per hour. The work elements and their precedence relationships are shown in the following table. a. What is the theoretical minimum number of stations? b. How many stations are required using trial and error to find a solution? c. Suppose that a solution requiring five stations is obtained. What is its efficiency? Work Element A B C D E F G H I J Total Time (sec) 40 30 50 40 6 25 15 20 18 30 Immediate Predecessor(s) None A A B B C C D,E F,G H,I
MRP
What is dependent demand? How is it different from independent demand? What is MRP? What are the purposes of using MRP? What are the main inputs to MRP? What does MRP tell you? Are you able to give examples of MRP in services? What are the main benefits of using MRP?
Understanding Module 03
These questions are intended to help you see if you understand how this modules topics all tie together. 1. Look around the room, what was manufactured? What was assembled? What type of facility do you think was used to make that item? Where do you think that item produced? Where were the components produced? 2. Think of a major item. How would you produce that item on an assembly line? What value could you add to the item by utilizing a Flexible Flow or Hybrid system? 3. Choose 4 US cities. What would be the key considerations associated with locating a factory in each city? Do the same for 4 different international cities/countries. 4. While you are unlikely to ever balance an assembly line on your own, what are some lessons that you can take away from line balancing that might be useful to you in starting your own business? 5. Why arent we recommended to continuously hold dependent demand items? 6. What information do you need for running a MRP system and what information could a MRP system provide you?
Practice Questions:
2.
3.
4.
5.
5 A
15 B 25 15 D 10 C 20 G E 10 F
6.
If the cycle time is 30 seconds, which of the following would NOT be acceptable as the first workstation? Use the above precedence diagram. A. AC B. ADC C. DB