HowtoupdateanotherscheduleinadifferentEPS Whatyouhavetodoistocreateabaselineoracopyofyourcurrentschedulethenupdatethe baselinewithnewactivitiesandordeletedactivities. 1.OpentheprojectandselectProjectthenMaintainBaseline 2.NextselectAddandchooseSaveacopyofthecurrentprojectasanewbaselinethenselect OK.

3.NextselectAssignBaselineandchoosethenewprojectthatitcopied.

Ifyoulookbelowyoucanseethecurrentprojectinredandthebaselineortheotherprojectin orangebelowit.Thereareonly3activitiesinthecurrentscheduleandthreeintheother schedule(thebaselineschedule)

NowIadded1newactivitytothecurrentschedule.Ifyoulookbelowthereare4activitiesin thecurrentschedulebutonly3activitiesinthebaselineorotherschedule.NOorangebar (whichrepresentstheotherschedule)showhereforthelastactivity.

4.ThekeytoupdatingtheotherscheduleorthebaselineistoselectProjectMaintainBaselines

5.NextchooseUpdate

6.Thisiswhereyouwilldecidewhatgetsupdatedfromthisscheduleintotheotherschedule. MakesuretocheckAddnewactivitiesandDeleteactivities.

7.YoualsocanchangetheUpdateOptionstoincluderesourcesandwhateverelseyouwant updatedontheotherprojectbyselectingtheUpdateOptionsbutton. Thisiswhereyoumaychooseadditionalitemstobeupdated.

8.ChangeyouroptionstowhatyouwantthemtobeandselectOK 9.ThenselectUPDATE Youwillreceiveadialogboxstatingthattheupdateprocesswascomplete

Nowifyoulookattheactivitiesagainintheganttchartareayouwillseethenewactivityinthe correspondingbaselinescheduleorotherschedulenowshowupORANGEBARNOWPRESENT

Thismeansthattheotherscheduleaddedthisactivityfromthisschedule.