IRCON International Limited

J&K Rail Project, Srinagar

Construction of Platform etc. at various Railway


stations in Zone PF-1 between km0.00 to 45.00
1 Name of work (Package PF-1) on Qazigund Baramulla section of
new BG Rail line Project, J&K.

2 Name of Contractor AM Contractors, Gaziabad, Anchidora, Anantnag, J&K

IRCON/ 1008/ J&K- DLI/ Platform/ PF-1/6762;


3 LoA No& Date
Dated: 05/01/2006
5 Oiginal Contract value Rs5,22,08,012.14.

6 Revised Contract value NA


Scheduled Date of
7
completion of work:
As per Original contract 04/01/2006
Reference of contractor’s Reference of contractors letter no:AMC/8111/42 Dt:19-12-
8 Letter seeking extension of 2006 and
time: Letter no:AMC/8111/44; Dt:31-12-2006
Time Extension
9 31-07-2007
Recommended up to:
10 Present status of work
Financial Rs.2,50,58,950.43
Physical 40%
Expected time required for
11 Three months
Completion:
12 Details of time lost due to:
Variation in quantities/ scope 1. Due to variation of quantity- 225 Days
of work 2. For fixation of rate ----- days. NA
3. Snow fall-16 days
Snow fall & weather condition.
4. Rainfall-61 days

Law and Order Situation NA

Land Acquisition: NA

TOTAL: 317 Days

a) the work remained suspended due to bad weather


for a long period from in different periods due to
Heavy snow/rain fall.
Reasons details for granting b) Qty of work has increased 62% above the BOQ, so
13
time extension: it requires additional 225 days for completing the
revised volume of work.
c) There were so many days work has stopped due to
local strikes, holiday etc in the working season.
Delay in completion of work is
14
attributable to :
Contractor Nil

IRCON Nil
Neither to IRCON or
Neither to IRCON or contractor
contractor:
Time extension Recommended
15 31-07-2007
upto:
With or without penalty Without penalty

With or without PVC With PVC

Submitted for kind approval.

(Surajit Ghosh)
Assistant Manager / Civil

(Samir Haloi)
Manager/ Civil

JGM/ Civil

AGM/ Finance

GM/ Srinagar