AGRARIAN REFORM INFRASTRUCTURE SUPPORT PROJECT - PHASE III ARISP III

PROJECT INFORMATION
1. the approved straight-line diagram)

Name of Project and Length (Project Scope and Details using

Name: REHABILITATION OF PROGRESO CAMBAOL CAYACAY NAPO ROAD IN DEL UNTAGA PROCAYACAP ARC , ALICIA, BOHOL WITH NAPO BRIDGE & CAYACAY RCBC AND ITS APPROACHED SLAB.

Contract Amount: Php 31, 850, 129.00 Contractor: ZION Construction Date of Notice to Proceed: MAY 24, 2011 Contract Effectivity: MAY 30, 2011 Actual Date Started: June 1, 2011 Contract Time: 400 Calendar Days Contract Expiry: JULY 03, 2012

Actual Project Accomplishment as of Sept. 30, 2011


a) Installation of Project Billboard (1 unit installed) = 0.02% b) Construction of Field Office (80% completed) c) Test Piles (For Driving) d) Regular Piles (Rebars) e) Concrete Railings (Pre-cast) f) Pipe Culverts(900 & 600mm) (Delivery) g) Roadway Excavation = 0.25% = 0.61% = 1.05% = 0.10% = 0.33 % = 3.64 % 6.00 %

Project Status as of September 30, 2011


Schedule Accomplishment as of Sept. 30, 2011 (S-curve) = 7.05 % Actual Accomplishment as of Sept. 30, 2011 = 6.00 % Slippage = (-)1.05 %

Length: 5,916.53 m . (net length) Date of Approval: May 18, 2011 Napo RCDG Bridge = 21.00 m. Bridge Approached Slabs = 8.00 m. Cayacay RCBC = 10.20 m. PCCP = 2,295.13 m. Gravel Pavement = 3,582.20 m.