FACULTY OF CIVIL & ENVIRONMENTAL

ENGINEERING
DEPT.OF GEOTECHNICAL AND
TRANSPORTATION ENGINEERING

GEOTECHNICAL ENGINEERING LABORATORY

REPORT

SUBJECT CODE

TEST CODE & TITLE
COURSE CODE

TESTING DATE

STUDENT NAME

GROUP

GROUP MEMBER NAMES
1.
2.
3.
4.
5.

LECTURER/ INSTRUCTOR/ TUTOR
NAME


REPORT RECEIVED DATE


MARKS
ATTENDANCE/ DISCIPLINE
& INVOLVEMENT
/15%
DATA ANALYSIS /20%
RESULT /20%
DISCUSSION /25%
CONCLUSION /20%
TOTAL /100%
EXAMINER COMMENT








RECEIVED STAMP














































STUDENT CODE OF ETHIC
(SCE)

DEPT. OF GEOTECHNICAL AND TRANSPOTATION ENGINEERING

FACULTY OF CIVIL & ENVIRONMENTAL ENGINEERING



I, hereby confess that I have prepared this report on my own effort. I also admit not
to receive or give any help during the preparation of this report and pledge
that everything mentioned in the report is true.




_________________
Student Signature



Name :

Matric No. :

Date :







FACULTY: CIVIL & ENVIRONMENTAL ENG. PAGE NO.: 1/5
DEPARTMENT: GEOTECHNICAL AND
TRANSPORTATION
ENGINEERING
EDITION:
REVIEW NO.:
TEST TITLE : FALLING HEAD
PERMEABILITY TEST

EFFECTIVE
DATE:
1/12/11
AMENDMENT
DATE:
24/3/11

1.0 OBJECTIVE
TO DETERMINE PERMEABILITY OF SOILS OF INTERMEDIATE AND LOW PERMEABILITY
(LESS THAN 10
-4
m/s), I.E. SILTS AND CLAYS.


2.0 LEARNING OUTCOME
At the end of this experiment, students are able to:
- Describe the general accepted practice to determine the coefficient of permeability of silts
and clays.
- Identify the relationship between permeability and pore size of the fine grained soils.
- Measure the coefficient of permeability of silts and clays.


3.0 THEORY

In the falling head test a relatively short sample is connected to a standpipe which provides both the
head of water and the means of measuring the quantity of water flowing through the sample. Several
standpipes of different diameters are normally available from which can be selected the diameter most
suitable for the type of material being tested.

In permeability tests on clays, much higher hydraulic gradients than are normally used with sands can
be applied, and are often necessary to induce any measurable flow. The cohesion of clays provides
resistance to failure by piping at gradients of up to several hundred, even under quite low confining or
surcharge pressures. Dispersive clays however are very susceptible to erosion at much lower gradient.

The falling head principle can be applied to an undisturbed sample in a sampling tube and to a sample
in an oedometer consolidation cell. The equation used in determine the permeability of fine grained
soils is given in Eqn (1).

|
|
.
|

\
|

=
2
1
1 2
log
) (
,
h
h
t t A
aL
k ty Permeabili
e
..Eqn (1)

The time difference (t
2
-t
1
) can be expressed as the elapsed time, t (minutes). The heights h
1
and h
2
and
the length, L are expressed in millimetres, and the areas A and a in square millimetres. Eqn (1) then
becomes Eqn (2).


) / ( log
60
,
2
1
s mm
h
h
t Ax
aL
k ty Permeabili
e
|
|
.
|

\
|
= ..Eqn (2)

To convert natural logarithms to ordinary (base 10) logarithms, multiply by 2.303. If k is epxressed in
m/s, the above equation becomes Eqn (3).






FACULTY: CIVIL & ENVIRONMENTAL ENG. PAGE NO.: 2/5
DEPARTMENT: GEOTECHNICAL AND
TRANSPORTATION
ENGINEERING
EDITION:
REVIEW NO.:
TEST TITLE : FALLING HEAD
PERMEABILITY TEST

EFFECTIVE
DATE:
1/12/11
AMENDMENT
DATE:
24/3/11


) / ( log
60 1000
303 . 2
,
2
1
10
s m
h
h
t xAx
aL
k ty Permeabili
|
|
.
|

\
|
= ..Eqn (3)


Where: a = area of cross-section of standpipe tube,
A = area of cross section of sample
h
1
= heights of water above datum in standpipe at time t
1

h
2
= heights of water above datum in standpipe at time t
2

L = heights of sample
t = elapsed time in minutes

4.0 TEST EQUIPMENTS

1. Permeameter cell, comprising:
Cell body, with cutting edge (core cutter), 100 mm diameter and 130 mm long.
Perforated base plate with straining rods and wing nuts.
Top clamping plate.
Connecting tube and fittings.


























Figure 1: Compaction permeameter
(Courtesy of ELE International, 2007)






FACULTY: CIVIL & ENVIRONMENTAL ENG. PAGE NO.: 3/5
DEPARTMENT: GEOTECHNICAL AND
TRANSPORTATION
ENGINEERING
EDITION:
REVIEW NO.:
TEST TITLE : FALLING HEAD
PERMEABILITY TEST

EFFECTIVE
DATE:
1/12/11
AMENDMENT
DATE:
24/3/11

5.0 PROCEDURES

1. Assemble apparatus,
a. Set up the apparatus as shown in Figure 2. The volume of water passing through a
sample of low permeability is quite small and a continuous supply of de-aired water is
not necessary, but the reservoir supplying the de-airing tank should be filled with
distilled or de-ionised water
2. Calibrate manometer tubes,
a. Determined the areas of cross-section of the three manometer tubesfor each tube:
i. Fill the tube with water up to a known mark near the top of the scale,
observed to the nearest mm,
ii. Run off water from the tube into a weighted beaker, until the level in the tube
has fallen by about 500mm or more,
iii. Read the new water level on the scale, to the nearest mm,
iv. Weight the beaker containing water from the tube (weighings should be to the
nearest 0.01g)
v. Calculated the diameter of manometer as follows:


2 1
1000
,
h h
m
a diameter
w

= mm
2

If m
w
= mass of water (g),
h
1
= initial level in tube (mm),
h
2
= final level in tube (mm),
A = area of cross-section of tube (mm
2
)
vi. Repeat the measurements two or three times for each tube, and average the
results.
3. Preparing cell,
a. Dismantle the cell,
b. Make sure the cell body is clean and dry, and weight it to the nearest 0.1g,
c. Measure the mean internal diameter (D) and length (L) to the nearest 0.5mm
4. Prepare sample,
a. Undisturbed sample can be taken by means of core cutter.
b. Make sure that the sample is a tight fit in the body and there are no cavities around
the perimeter through which water could pass,
5. Assemble cell
6. Connect cell
7. Saturate and de-air sample
8. Fill manometer system
9. Run test
a. Open screw clip at inlet to allow water to flow down through the sample, and observe
the water level in the standpipe,
b. As soon as it reaches the level h
1
, start the timer clock,
c. Observe and record the time when the level reaches h
3
, and when it reaches h
2
, then
stop the clock,
d. Close screw clip at inlet.



FACULTY: CIVIL & ENVIRONMENTAL ENG. PAGE NO.: 4/5

DEPARTMENT: GEOTECHNICAL AND
TRANSPORTATION
ENGINEERING
EDITION:
REVIEW NO.:
TEST TITLE : FALLING HEAD
PERMEABILITY TEST

EFFECTIVE
DATE:
1/12/11
AMENDMENT
DATE:
24/3/11


10. Test is repeated
11. Permebeabilty is calculated
12. Result reported









































Figure 2: Falling head permeability cell with manometer tubes
(Courtesy of ELE International, 2007)




FACULTY: CIVIL & ENVIRONMENTAL ENG. PAGE NO.: 5/5


DEPARTMENT: GEOTECHNICAL AND
TRANSPORTATION
ENGINEERING
EDITION:
REVIEW NO.:
TEST TITLE : FALLING HEAD
PERMEABILITY TEST

EFFECTIVE
DATE:
1/12/11
AMENDMENT
DATE:
24/3/11

6.0 RESULTS AND CALCULATIONS

Falling Head Permeability test

Location: Sample no:
Operator: Date:

Soil description:
Method of
preparation:

Sample diameter, D: 99.075 mm Sample length, L: 232 mm
Sample area, A: 7709.35 mm
2
Sample volume, V: 1166 cm
3

Mass of mould: 1014.5 g Mass of sample + mould: 2717.9 g
Mass of sample: 1703.4 g

S.G. measured/assumed: Voids ratio:
Bulk density, : 16.43 kN/m
3
Dry density, : 16.19 kN/m
3

Moisture content: 10 % Test temperature: c

Standpipe diameter: 4.05 mm Standpipe area, a: 12.8 mm
2


Reading:

Reference
point
Height above
datum, y
(mm)
Height above
outlet, h
(mm)
Test
Height ratios
No. Time, t
(s)
1 900 800 1 4 1.125
2 800 700 2 10 1.142
3 700 600 3 15 1.167
4 600 500 4 20 1.200


Calculations:

) / ( log
60 1000
303 . 2
,
2
1
10
s m
h
h
t xAx
aL
k ty Permeabili
|
|
.
|

\
|
=

k
1
=

)

= 1.13 x 10
-5
m/s





k
2
=

)

= 5.14 x 10
-6
m/s


k
3
=

)

= 3.96 x 10
-6
m/s


k
4
=

)

= 3.51 x 10
-6
m/s



k =
(

) (

) (




= 5.98 x 10
-6
m/s















7.0 QUESTIONS


1. Determine the coefficient of permeability for the given sample of soil.

2. Give a conclusion for this test.