Bar Char on progress of work Name of the work :- CPWS Scheme to Poosapatirega and other habitations Grant: NABARD

RIDF XVI : Est.Rs.250.00 Lakhs Milestone1 Milestones Sl No 1 4 months Durations 2 Apr11 3 May11 4 June11 5 July11 6 Aug11 7

Vizianagaram District Milestone 2 4months Sep11 8 Oct11 9 Nov11 10 Milestone 3 3 Months Dec11 11 Jan12 12 Feb12 13 Milestone4 35Days Mar12 14

A At Intermediate pumping station 1 Construction of 60KL capacity Sump at chowduwada 2 Construction of 10kl sump at Pittapeta B OHBR'S/ BPTS 1 40KL OHBR with 25m staging at Akkivaram 2 10KL BPT with 6.3m staging at Kanimetta C OHSRs 1 40KL OHSR with 9.55 m staging at Barripeta 2 3 4 40KL OHSRs with 6.30 m staging at Kamavaram 20KL OHSR with 6.30 m staging at Yathapeta 20KL OHSR with 6.30 m staging at Krishnapuram Staging completion Raft completed Staging completion Staging completion Raft completed 100% completion 100% completion 100% completion 100% completion 100% completion 100% completion

Staging completion 100% completion Bottom slab completion Staging completed 100% completion

20KL OHSR with 6.30 m staging at Konayyapalem

Staging completion Staging completion Staging completion Bottom slab completion Staging completed

100% completion 100% completion 100% completion 100% completion

6 15KL OHSR with 6.30 m staging at Gollapeta (Pprega) 7 15KL OHSR with 6.30 m staging at Yathapeta (Akkivaram) 8 10KL OHSR with 6.30 m staging at Konatalapalem

9 10KL OHSR with 6.30 m staging at Reesupeta 10 10KL OHSR with 6.30 m staging at Tulasidibba 11 10KL OHSR with 6.30 m staging at Gollapeta (Akkivaram) D Pump houses/Watchman quarters 1 3mx4m size at Pittapeta 2 3mx6m size at Chowduwada E Pumping Main 1 HDPE/CI Pipe line total length=8880m

Staging completion Staging completion Staging completion

100% completion 100% completion 100% completion

Plinth level Plinth level

100% completion 100% completion

Procurement , L&J

Testing

110m/8 Kgs- 2000 L&J out of 4000 Procurement F Gravity Main 1 HDPE Pipe line total length=13760m G Valves & Chambers H Pump sets I Commissioning Executive.Engineer RWS(p), Vizianagaram Dy.Ex.Engineer RWS(p), Vizianagaram Asst.Ex.Engineer RWS(p), Vizianagaram Procurement Laying, Jointing & testing 100% completion Procurement &Erection comissioning

Indicates Progress of work

18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36

VISHWANADHAPURAM MOGIDIPETA GUDISALAPALEM ALAMANDAPETA KOMMAVANIVALASA RADHIKAPURAM Kalisettibadi KILARIPETA REDDIPETA NAGAMPETA CHINTHALAPETA MODUGULAPETA KOTHAVURU (PERIPI) KOTHAVURU (SIVARAM) ALAKANARAYANAPURAM Mettabadi EJJIPURAPUPETA DUDLAPETA VALLIIPETA

Bar Chart on progress of work Name of the work :- CPWS Scheme to Dattirajeru and other habitations
Grant: NABARD RIDF XVI : Est.Rs.3500.00 Lakhs Milestones Sl No 1 A 1 Durations 2 Head works Construction of IF wells-3nos As per Progress Construction of collection well cum pump house-1no 100%Completion Steering completed (60%) of work 100%Completion Mile stone 1 6months May11 4 June11 5 July11 Vizianagaram District Mile stone 2 6months Mile stone 3 6months Mile stone 4 6months

Apr11 3

August Sep11 Oct11 Nov11 Dec11 Jan12 Feb12 March12April12 May12 June12 July12 Aug12 Sep12 Oct12 Nov12 Dec12 11 6 7 8 9 10 11 12 13 14

B 1

Sumps Construction of 90KL capacity Sump at P Lingalavalasa

100% completion

Construction of 40kl sump at Akulakatta

100% completion

Construction of 40kl sump at Papayyavalasa Construction of 300kl sump at Gadasam jn Construction of 120kl sump at T Burjavalasa jn Construction of 100kl sump at Chowdantivalasa jn

100% completion

50% completion

50% completion

50% completion

50% completion

50% completion

50% completion

Construction of 20kl sump at Dasaripeta

50% completion

50% completion

C 1

OHBR'S/ BPTs 90KL OHBR with 13.2m staging at B Ramachandrapuram 60KL BPT with 30m staging at Chukkapeta jn

50% completion

100%completion

75% completion

100%completion

60 KL BPT 18m staging at Shikaruganji jn

75% completion

100%completion

40 KL OHBR 20m staging at Ravivalasa jn 40 KL BPT 20m staging at S Chintalavalasa jn

50% completion

100%completion

75% completion

100%completion

40 KL BPT 20m staging at Vangara jn

100% completion

40 KL OHBR 20m staging at Chowdantivalasa jn

100% completion

40 KL BPT 18m staging at Manapuram village

100% completion

20 KL BPT 13.35m staging at Kannam

100% completion

D 1

OHSRs 90 KL OHSR 13.2m staging -2nos 50%completion 100%completion

60 KL OHSR 9.75m staging -8nos

50%completion

100%completion

40 KL OHSR 9.55m staging-27nos

14nos-50% completion 14nos-100% completion 13nos-50%completion 13nos-100% completion

20 KL OHSR 6.3m staging -12nos

4nos-50% completion 4nos-100% completion 8nos-50%completion 8nos-100% completion

15 KL OHSR 6.3m staging -12nos

4nos-50% completion 4nos-100% completion 8nos-50%completion 8nos-100% completion

10 KL OHSR 6.3m staging -3nos

50%completion

100%completion

Pump houses/Watchman quarters

Pump house of size 6mx4m -3nos

3nos-50%completion 3nos-100% completion

Pump house of size 3mx2m -5nos Gas chlorination rooms of size 6mx4m 2nos

100% completion

100% completion

Watchman quarters of size 6mx4m -3nos

100% completion

F 1

Pumping Main DI/HDPE/CI Pipe line total length=21137mm Gravity Main AC/HDPE/PVC Pipe line total length=116935m

9.50km-50% completion 9.50km-100% completion 10.637km-50% completion 10.637km-100% completion

G 1

60.0km-50%completion

60.0km - 100% completion 56.935km-50%completion

56.935km-100% completion

Valves & Chambers

25% completion

75% completion

Pump sets

100% completion

J Note:-

Commissioning Indicates Progress of work

Executive.Engineer RWS(p), Vizianagaram

Dy.Ex.Engineer RWS(p), Vizianagaram

Asst.Ex.Engineer RWS(p), Vizianagaram

18 19 20 21 22 23 24 25 26 27 28 29

VISHWANADHAPURAM MOGIDIPETA GUDISALAPALEM ALAMANDAPETA KOMMAVANIVALASA RADHIKAPURAM Kalisettibadi KILARIPETA REDDIPETA NAGAMPETA CHINTHALAPETA

30 31 32 33 34 35 36

MODUGULAPETA KOTHAVURU (PERIPI) KOTHAVURU (SIVARAM) ALAKANARAYANAPURAM Mettabadi EJJIPURAPUPETA DUDLAPETA VALLIIPETA

Mile stone 4 6months Jan13 Feb13 Mar13

100% Commissioning