Professional Documents
Culture Documents
Foreword
The Precast/Prestressed Concrete Institute (PCI) updates and publishes the PCI Design Handbook: Precast and Prestressed Concrete1 in cycles coincident with publication of the American Concrete Institutes (ACIs) Building Code Requirements for Structural Concrete (ACI 318-05) and Commentary (ACI 318R-05).2 The seventh edition of the PCI Design Handbook, published in 2010, continues that tradition. Each update of the PCI Design Handbook reflects the modifications adopted by ACI 318 as well as the most recent research and experience of designers regularly engaged in the design of precast and prestressed concrete structures.
Introduction
The publication of the seventh edition of the PCI Design Handbook continues to meet the goals set forth by the Precast/Prestressed Concrete Institute, which was established in 1954 as the Prestressed Concrete Institute. The current name was adopted in 1989 to better reflect the interests of both prestressed concrete producers and those that manufacture nonprestressed precast concrete components. The goal is to advance the design, manufacture, and use of precast and prestressed concrete. The seventh-edition PCI Design Handbooks primary objective remains the same as it was with the first edition, published in 1971; that is, to make it easier for architects and engineers to use prestressed and precast concrete. It is intended to be a working tool, assisting the designer in achieving optimum solutions in minimum time. The seventh edition of the PCI Design Handbook background and discussion paper is the sixth document of its type. The first was published for the second-edition PCI
Consulting Members
Robert F. Mast, P.E., S.E., FPCI, HACI Jagdish C. Nijhawan, P.E., FPCI J. Robert Norris, P.E.
Editor
Helmuth Wilden, P.E., FPCI
129
Design Handbook and was an authored paper titled Background and Discussion on PCI Design Handbook, Second Edition. It was published in the JanuaryFebruary 1980 issue of the PCI Journal. Subsequent papers with the same intent and similar titles were published as follows: For the third-edition PCI Design Handbook: May June 1988, PCI Journal
It includes the correction of errors in the sixth edition that were published as errata in the MayJune 2007 issue of the PCI Journal. It incorporates comments by the sixth-edition PCI Design Handbook Blue Ribbon Review Committee that could not be included in the sixth edition. It includes updated information based on current standard practices of the industry. It includes updated information based on results of recent research in the industry. It expands text of selected topics to provide morecomprehensive discussion. Selected text, figures, tables, Design Aids, and examples are rewritten, modified, and edited for improved clarity.
For the fourth-edition PCI Design Handbook: NovemberDecember 1996, PCI Journal For the fifth-edition PCI Design Handbook: JulyAugust 1998, PCI Journal For the sixth-edition PCI Design Handbook: March April 2006, PCI Journal
Purpose
The main purpose of the background and discussion of the seventh edition of the PCI Design Handbook is to identify significant changes from the sixth edition on a chapter-bychapter basis and explain the rationale for these changes. Other purposes are to describe current work in progress toward the eighth edition of the PCI Design Handbook and to establish goals for future work.
The user of the PCI Design Handbook will observe several somewhat subtle differences from the sixth edition: Equations are numbered consecutively in each chapter. For example, Eq. 6.5.2.1 in the sixth edition is now Eq. (6-2) and Eq. 6.12.1.1 is now Eq. (6-93). A complete list of design examples is included at the end of the foreword to the handbook. Previous charts shown as figures are now Design Aids, and a complete list is included at the end of the foreword to the handbook. All figures and tables are identified with a three-digit number. For example, Table 6.6.5.2 in the sixth edition is now Table 6.6.3 and Fig. 6.7.3.1 is now Fig. 6.7.1. The first digit refers to the chapter, the second digit refers to the main section in which the figure or table appears, and the third digit represents the consecutive order in the main section. Chapters are identified on each page with a tab box at the edge of the page for easy reference. The term member, representing a precast concrete unit, has been changed to component throughout the handbook. This was done to be consistent with the title for chapter 5 of the seventh-edition PCI Design Handbook. For the most part, American Concrete Institute nomenclature and formatting has been used.
The user will also observe that some sections of the sixth edition have been omitted from the seventh edition. They are:
130
Table 1. Comparison of 6th and 7th editions of the PCI Design Handbook Sixth edition Chapter 1 2 3 4 5 6 7 8 9 10 Ch. 5 in 6th New Sect. 9.3 in 6th Sects. 9.1 and 9.2 in 6th Sect. 9.7 in 6th Ch. 8 in 6th Ch. 10 in 6th Ch. 11 in 6th New New Ch. 2 in 6th Ch. 3 in 6th Ch. 4 in 6th Pages 32 n.a. 58 124 132 102 22 36 n.a. 26 Figures 58 n.a. 8 20 25 39 15 27 n.a. 19 Tables 5 n.a. 32 2 8 5 3 4 n.a. 13 Design examples n.a. n.a. n.a. 19 43 23 n.a. 6 n.a. 5 Design Aids n.a. n.a. 8 26 14 15 n.a. n.a. n.a. n.a. Pages 28 18 64 98 152 116 36 28 42 26 Figures 63 n.a. 8 34 38 39 18 27 22 17 Seventh edition Tables n.a. n.a. 32 4 8 11 4 4 10 13 Design examples n.a. n.a. n.a. 13 48 26 3 4 n.a. 4 Design Aids n.a. n.a. 11 26 15 14 n.a. n.a. n.a. n.a.
11
23
15
n.a.
26
15
n.a.
12 13 14 15 Appendix Totals
8 34 36 58 n.a. 691
10 34 36 62 22 776
Section 9.5, Quality Assurance and Control. The committee felt that this section was redundant because three major PCI quality-control manuals already exist. They are MNL-1163 for structural precast concrete, MNL-1174 for architectural precast concrete, and MNL-1305 for glass-fiber-reinforced concrete. Section 9.9, Precast Segmental Construction. This topic is outside the area of building construction, which is the emphasis of the handbook, and more up-to-date
information is available in other publications. Section 9.10, Coordination with Mechanical, Electrical and Other Sub-Systems. At the time of publication of the seventh edition, it was the intent of PCI to develop a recommended practice and guidelines for total precast concrete structures and the committee considered that this new publication would provide more information than could be included in the handbook.
131
9.
Based on these approved versions, a blue-ribbon-review version was created. This final review phase consisted of the Blue Ribbon Review Committee, made up of plant engineers, specialty engineers, consulting engineers, academics, and associate members. Each member of the Blue Ribbon Review Committee is a recognized leader in the analysis and design of precast and prestressed concrete structures or an expert in a closely related field. The members of the Blue Ribbon Review Committee are noted in the foreword to the handbook. After a six-week review period, this group met for three days and offered valuable comments that were considered by the Industry Handbook Committee. Most were accepted as improving the publication. Others will be considered as new business for the eighth edition.
10. A final version of each chapter was then created and reviewed thoroughly by the original chapter subgroup. This review resulted in a few corrections and further improvement. 11. In addition, a comprehensive editorial and technical review of the handbook was carried out by the PCI Publications Department, led by Emily Lorenz, editorin-chief of the PCI Journal, as well as Jason Krohn, PCIs Managing Director of Technical Activities. It is commendable that the seventh edition of the PCI Design Handbook was created primarily through the volunteer efforts of the committee members and many others. Thousands of hours were devoted to its development, which, at normal consulting rates, would easily exceed a value of $2 million. The following presents a chapter-by-chapter review of the contents, outlining the general content and emphasizing changes from the sixth edition as well as the rationale behind these changes.
2.
3.
4.
5. 6.
7. 8.
132
the prestressed concrete industry in the United States. For additional information related to the history of the industry, refer to Reflections on the Beginnings of Prestressed Concrete in America,9 published in 1981, and PCI Visions Taking Shape,10 published in 2004. These documents commemorate the 25th and 50th anniversaries of PCI, respectively. The sixth-edition figure of typical products has been replaced with a collage of photographs to better illustrate the variety of products available (Fig. 2). Because of the growing emphasis on sustainability, section 1.1.3, Sustainability and LEED Considerations, has been added to describe the benefits of precast and prestressed concrete in achieving long-lasting and energy-efficient structures. A new section 1.2.1.7, Educational Facilities, has been added to better illustrate the importance of these applications and to present to the user of the handbook the superior solutions that precast and prestressed concrete offers to the owners of these facilities. The sixth-edition section 1.3, Materials, was completely removed from chapter 1. It was extensively expanded and has become the new chapter 9 of the PCI Design Handbook, seventh edition. See the discussion in this article on chapter 9 for further details of the changes and additions on the subject of materials.
stairs, and section 3.3.12 and Design Aid 3.12.11, which provides guidelines for stadium riser sections. Design Aid 3.12.7 has been added to assist in preliminary sizing of non-load-bearing wall panels.
Chapter 2Notations
This chapter is completely new and includes the notations for the entire handbook. This is the result of the PCI Industry Handbook Committees intention to make the handbook similar to ACI 318-05. It was the original intention to include definitions in this chapter, but the committee considered it more user friendly to include definitions either at the beginning of each chapter or in the text where a term is used. It is important to recognize that notations identical to those used in ACI 318-05 are identified with (ACI) after the definition.
133
134
bays at
Elevator
typical
typical
Ramp up
Stair well
Figure 3. Collector force demand diagram for shear walls in a parking garage. See note a in Postpublication Notes at the end of this article.
Examples for shear-wall buildings and for precast concrete diaphragms have been updated to clarify diaphragm and collector design procedures. Diaphragm design has been expanded, and more detail is provided for collectors.
Figures 3 and 4 illustrate the intent of ASCE 7-05 and IBC 2006. An entirely new section (section 4.9) on blast-resistant design has been added to the chapter. This section discusses the special considerations of large-magnitude,
Double-tee deck
Figure 4. Perspective view of shear wall and collectors. PCI Journal | Fa l l 2010 135
bays at
Shear walls
Ramp down
Table 2. Recommended shear-friction coefficients (6th edition) Crack interface condition 1. Concrete to concrete, cast monolithically 2. Concrete to hardened concrete, with roughened surface 3. Concrete to concrete 4. Concrete to steel Recommended 1.4 1.0 0.6 0.7 Maximum e 3.4 2.9 2.2 2.4 Maximum Vu = Vn 0.302f ' Acr 10002Acr c 0.252f ' Acr 10002Acr c 0.202f ' Acr 8002Acr c 0.202f ' Acr 10002Acr c
Table 3. Recommended shear-friction coefficients (7th edition) Case 1 2 3 4 Crack interface condition Concrete to concrete, cast monolithically Concrete to hardened concrete, with roughened surface Concrete placed against hardened concrete not intentionally roughened Concrete to steel a 1.4 1.0 0.6 0.7 Maximum e 3.4 2.9 Not applicableb Not applicableb
c
Maximum Vu / 0.30f 'c Acr 1000Acr 0.25f 'c Acr 1000Acr 0.20f ' Acr 800Acr c 0.20f ' Acr 1000Acr c
a. In accordance with ACI 318-05 Section 11.7.4.3. b. The use of e is not applicable for concrete placed against hardened concrete not intentionally roughened or against steel. c. The handbook shows this as 0.30f ' Acr 1000Acr. This is incorrect. It should be 0.20f ' Acr 1000Acr. c c
short-duration loads on precast concrete systems with large mass and inertia. Topics include blast loads, dynamic material properties, and blast-design methods. A blast-design example for a cladding panel is also included.
the original research, use of the effective coefficient of friction with concrete placed against hardened concrete not intentionally roughened and concrete-to-steel interfaces has been disallowed, and the formulas for maximum shear stress (right column of Table 4.3.6.1 in the sixth edition) have been revised to remove the squared from the lambda terms. Other sections using shear friction have been updated to be consistent with these revisions. A comparison of the sixth-edition and seventh-edition tables is shown in Tables 2 and 3. Based on recent experience with self-consolidating concrete (SCC) in which the surface remained slick after curing, a warning has been included regarding selection of the appropriate interface condition when corbels are cast on the up face of components cast using SCC. In section 4.5 of the sixth edition, Beams with Ledges, the table for ledge design m factors has been removed because the committee felt that solving Eq. (5-52) of the seventh edition is as easy as looking up a value for m in the chart. Also, Fig. 5.5.3 includes corrections for determining the m factor for an inverted-tee beam based on the original research.14
136
Concerns raised by PCI Professional Members suggested the need for better clarity of the detailing requirements for dap-ended members. Accordingly, the committee modified Fig. 5.6.3 by enlarging the alternative dap reinforcement detail to clarify and emphasize the importance of dap reinforcement detailing and placement. Section 5.8, Camber and Deflection, was expanded, primarily to provide guidance for the use of ACI 318-05 Table 9.5(b) Maximum Permissible Computed Deflections (PCI Design Handbook Table 5.8.1). Section 5.9, Compression Components, contains several significant revisions. In section 5.9.1, the section allowing elimination of lateral ties in certain instances based on Recommended Practice for the Design of Prestressed Concrete Columns and Walls15 has been removed because the reference no longer contains these exceptions. In Example 5.9.1.1, the interaction curve has been modified to better show its actual shape. In Example 5.9.3.1, the stiffness-reduction factor has been changed to K = 0.85, as suggested by ACI 318-05 section R10.11.1. Section 5.9.4, Concrete Brackets or Corbels, has been moved into this chapter from chapter 6, Design of Connections, in the sixth edition, on the basis that this is part of the component design rather than a connection. Section 5.10, Shear Walls, is a completely new section. It provides an introduction to the design of precast concrete shear walls, including a design example. Section 5.11, Sandwich Panels, was moved into this chapter from chapter 9 of the sixth edition, Thermal, Acoustical, Fire and other Considerations, because it is an important aspect of many precast concrete structures and is more appropriate with a discussion about component design. Section 5.12.1, Point Loads on Double-Tee Flanges, is a new section, though the design example was in the Analysis Using Strain Compatibility subsection of the Flexure section of the sixth edition. Determination of the effective resisting width for a point load has been revised to more accurately reflect load test data.16 Section 5.12.7, Warping of Deck Components, is a completely new section. It addresses the warping of doubletees, especially in parking structures, to obtain desired drainage patterns. Recommendations are based on experience and relatively recent research.17 Design Aid 5.14.15 now provides updated corbel capacities and more clearly illustrates whether the capacity is limited by flexure, shear, or maximum Vu.
137
Table 4. Diaphragm overstrength factorsa factor table design element A Diaphragm to SFRS connection Bearing-wall systems Building-frame systems Moment-resisting systems Dual system with special moment frames Dual system with intermediate moment frames Inverted pendulum system and cantilevered-column systems Diaphragm chord element Bearing-wall systems Building-frame systems Moment-resisting systems Inverted-pendulum system and cantilevered-column systems DiaphragmDESIGN OF CONNECTIONS joint shear connection Bearing-wall systems Building-frame systems 1 1 1 1 1 1 1 1 1b 1b 1b 1b 2 2 1 1 2 2 1 1 2 2 1 1 1 1 1 1 1 1 1 1 1b 1b 1b 1b 2 2 1 1 2 2 1 1 2 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 2.5a 2.5a 2.5a 2.5a 2.5a 2.5a 2.5a 2.5a 3a 2.5a 2.5a 2 2.5a 2.5a 3a 2.5a 2.5a 2 2.5a 2.5a 3a 2.5a 2.5a 2 B Seismic design category C D E F
The size of the bar must be such that for combined Moment-resisting systems the actual stress 0.9Fy flexure and tension
Inverted-pendulum system and cantilevered-column systems For flexure:
Zrequired = Mu the y = [Vu(lp + g + c + 0.5S a. The tabulated value of /Fdiaphragm overstrength factor w) may be reduced by subtracting 0.5 for structures with flexible diaphragms but shall not be taken as less than + Nfor any structure. 2.0 u (0.5)Y]/Fy (Eq. 6-81)
b. For seismic design categorytrial section check that the actual the maximum distributed design force at that level is used. Then based on a C diaphragms, it has been assumed that
stress due to combined flexure and tension is 0.9Fy For shear: Actual shear stress is 0.9(0.6Fy) 4. Provide anchor reinforcement distributed uniformly over 0.8d as illustrated in Fig. 6.9.2(b) to resist 1.33 Vu. Section 6.13, Typical Connections, has been added to represent typical connection details used in total precast concrete structures. Example 6.13.6, Wall-to-Wall Shear Connection with Combined Loading, is new and illustrates a combined shear and tension connection and the interaction equations for each component and the capacity region of the assembly. Example 6.13.8, Deformed Bar or Reinforcing Bar Connection Plate Supporting Steel Beam, is new and illustrates a typical connection for a steel, wide-flange beam connected to a plate with deformed bar anchors. See note c in Postpublication Notes at the end of this article. Design Aids 6.15.4 and 6.15.5 no longer show weld size and minimum plate thickness requirements for welds using E70 electrodes for ASTM Grade 60 reinforcing bars because this is no longer allowed by AWS D1.4.19
nents lows
Au Av =
1.33Vu fy
(Eq. 6-82)
-79)
Check minimum area required: where: b s A = 0.75 fc' w fy not less than 50bw
flexstartments
s fy
(Eq. 5-24)
bw = width of component (see Fig. 6.9.2(b)) s 5. = 0.8d The conservative and simplifying assumption that strap weld forces are concentrated at the strap centerline is implicit in the 0.5Sw factor in the value of a in Eq. 6-80. Fall 2 0 1 0 | PCI Journal
Table 5. Seismic overstrength factorsa o factor table design element A Collectors (drag-ties) Bearing-wall systems Building-frame systems Moment-resisting systems Dual system with special moment frames Dual system with intermediate moment frames Inverted-pendulum system and cantilevered-column systems Collectors (drag-tie) transfer to vertical resisting element Bearing-wall systems Building-frame systems Moment-resisting systems Dual system with special moment frames Dual system with intermediate moment frames Inverted-pendulum system and cantilevered-column systems a. Table shown is condensed from ASCE 7-05, Table 12.2-1. b. The tabulated value of the system overstrength factor o may be reduced by subtracting 0.5 for structures with flexible diaphragms but shall not be taken as less than 2.0 for any structure. 1 1 1 1 1 1 1 1 1 1 1 1 2.5 2.5 3 2.5 2.5 1.25 2.5 2.5 3 2.5 2.5 1.25 2.5 2.5 3 2.5 2.5 1.25 2.5 2.5 3 2.5 2.5 1.25 1 1 1 1 1 1 1 1 1 1 1 1 2.5 2.5 3 2.5 2.5 1.25 2.5 2.5 3 2.5 2.5 1.25 2.5 2.5 3 2.5 2.5 1.25 2.5 2.5 3 2.5 2.5 1.25 B Seismic design category Cb Db Eb Fb
1 1
/2b d b An Nu d h bw b
/2p
3a s = 0.8d
Nu
p g c
d Strap, Sw
Main reinforcement
(a)
Seismic force
C.G.
Floor level Seismic reactions (a) Wall panels Note: Gravity and out-of-plane loads to connectors not shown; C.G. = center of gravity
Tie-back connection
Example 7.5.3.1, Architectural Precast Concrete Panel with Earthquake Loading. This example is the same as Example 3.2.4.2 in the sixth edition, but has been expanded to reflect appropriate seismic factors. It includes comparisons of critical loads from the two previous wind-load examples to illustrate the actual design procedure that an engineer would use. Seismic drift considerations have been added to illustrate the need for some connections to move in different directions to avoid unintended forces acting on the cladding and/or the supporting structure. This is illustrated in Fig. 6. The chapter has added recommendations for where to locate connections on cladding panels to provide predictable behavior. This is illustrated in Fig. 7.
140
2 b2 e> a 2 2
Optional for long panels Figure 8. Stability during erection.
observed firsthand that the equation shown in Fig. 5.6.2 of the sixth edition for the distance from the lower rolling block to the center of gravity is incorrect. This is shown in Fig. 8. A paper written by Don Logan, P.E., in the Winter 2010 PCI Journal21 explains in detail the potential risks associated with using this equation. As a result, the Industry Handbook Committee has recommended the rigging arrangement illustrated in Fig. 9 to avoid this condition. Section 8.7, Erection Bracing, was reduced to an abbreviated version, and design examples were removed. This was a topic that was debated significantly by the Industry Handbook Committee, primarily as a result of the difference between the experiences of the committee members and the requirements of ASCE 37-02 Design Loads on Structures During Construction.22 It was concluded that because ASCE 37-02 is not a mandatory code, the loads imposed on precast concrete structures during erection should be the responsibility of the experienced precast concrete designer. With that responsibility must go the authority to define the loading requirements during this temporary stage.
Figure 9. Stability during erection.
Center of gravity
tion, reinforcement, waterproofing, and in-service repairs. The chapter also includes a number of new figures, graphs, and tables to augment the text. Because the handbook is often used as a textbook at the university level and many students have not been exposed to typical materials used in the industry, several photographs have been includedfor example, prestressing strand (Fig. 10) and standard reinforcement (Fig. 11). Section 9.2, Concrete, covers the constituent materials of the concrete matrix, consisting of cement, supplementary cementitious materials (SCMs), aggregates, admixtures, and pigments. Detailed descriptions are provided with relevant references to ASTM standards. Physical properties of concrete are introduced, such as compressive and tensile strength, modulus of elasticity, volume changes, and durability. Tables presenting common material parameters are given and photographs of good concrete and common deterioration mechanisms are presented, as illustrated in Fig. 12 and 13, respectively.
141
Figure 10. Wire prestressing strand of various sizes. Figure 13. Planar cracking marking freezing and thawing damage.
viding protection against deterioration are covered within the context of waterproofing with coatings, joint sealant types and issues, and expansion joint sealant systems. In the event that a precast concrete component is damaged during transportation or erection, in-service repairs are reviewed. Other in-service conditions are also examined, and suggested maintenance and strengthening means are provided. The chapter concludes with section 9.9, Relevant Standards and Publications, which is a comprehensive listing of reference standards and publications relevant to materials. These standards may also appear in project specifications prepared by the engineer of record or architect of record.
Section 9.4, Connection Materials, reviews the common steel sections, bearing pads, and bolts used in connections. This is followed by a discussion on the galvanic series and its importance in examining service life and protection of connections. Protection means are discussed, including painted systems, galvanized steel, and stainless steel, and the proper means of specifying them. Section 9.6, Reinforcement, describes various systems for precast and prestressed concrete components and the various deterioration mechanisms that can occur. Different means of embedded steel protection are presented to mitigate common deterioration problems. Other means of pro-
142
A new section 10.8, Requirements for Parking Structures, has been added to assist the user in applying the requirements and tables in IBC 2006 to the design of precast and prestressed concrete components typically used in parking structures. Several paragraphs that outline recent research at Lehigh University are included in this section. This research was performed to evaluate realistic vehicle-fire loads (time-temperature or time-heat flux relationships) for precast concrete parking structures. This work investigated the influence of the structural geometry and fire characteristics on the resulting fire load.
12 11 10 9
10
DT
32
8D
2 2+
T2
4+
12
2
+2
4H
DT
28
+2
15
6 FS +2
DT
+ C8 4H 2
C1
34
30
12
DT
Span, ft
Figure 14. Natural frequency of selected floor units. PCI Journal | Fa l l 2010 143
designer in the chapter. It has been updated to reflect ACI 318-05 and has had extensive review by the PCI Building Code Committee and TAC. Sections 14.2 and 14.3 are brief descriptions of the guide specifications for structural and architectural precast concrete, respectively. They have both been updated to the latest ACI 301 and AIA Masterspec.24,25 The full guide specifications are on the CD in the front jacket pocket of the PCI Design Handbook and are in a usable word-processing format. Section 14.4, Standard Operations Practice Recommendations for Precast Concrete, has been updated to reflect current practices in the industry. Section 14.5, Recommendations on Responsibility for Design and Construction of Precast Concrete Structures, remains essentially the same as in the sixth edition.
Conclusion
Most of the goals established by the PCI Industry Handbook Committee for the seventh edition have been accomplished. However, several were not and will remain goals for the eighth edition, as noted in the following paragraphs. Chapter 2, Notations, was intended to include definitions used throughout the handbook, as well as other terms typically used in the industry that might not be specifically used in the handbook. Terms such as down-in-form, chuck, stripping, dunnage, and the like are used in everyday conversation in plants and may be helpful for the inexperienced designer or student using the handbook. A review of chapter 2 also resulted in the observation that the notation used in the handbook could be improved with a complete overhaul. Many of the same notations have different meanings, which can cause confusion. Examples include the notation R, which is the response modification factor for seismic design in chapter 4 and the thermal resistance of a precast concrete component in chapter 11. There are numerous less-critical topics and suggested changes brought forward for consideration, but the decision to incorporate them was postponed because of timing and publishing constraints. Similar thoughts occurred during the blue-ribbon review. The committee has gathered these items for future consideration and has provided them to the next PCI Industry Handbook Committee, to be chaired by Tim Salmons, P.E., S.E. The list of items for the eighth edition of the PCI Industry Handbook Committee to address also includes: ACI 318 intends a major revision in 2013, with only an interim revision in 2011. PCIs TAC will direct the PCI Industry Handbook Committee as to which versions of ACI 318, IBC, and ASCE will be used for the eighth edition. Consider making the publication a two-volume set, with one including material that does not necessarily change with the code cycles. Use 3 in. (75 mm) topping for double-tee load tables instead of 2 in. (50 mm).
144
Reintroduce material related to erection bracing and include examples. Create a uniform format for all examples and all figures. Consider providing a final draft of the eighth edition to the entire engineering community for public comment. While the seventh edition has had a very intense review process, it cannot be considered a consensus document. Responding to public comments would allow the document to achieve this status. Update the handbook to reflect ongoing research.
3.
PCI Plant Certification Committee. 1999. Manual for Quality Control for Plants and Production of Structural Precast Concrete Products. MNL-116-99. 4th ed. Chicago, IL: PCI. PCI Architectural Precast Concrete Services Committee and Plant Certification Committee. 1996. Manual for Quality Control for Plants and Production of Architectural Precast Concrete Products. MNL-117-96. 3rd ed. Chicago, IL: PCI. PCI Glass Fiber Reinforced Concrete Panels Committee. 2009. Manual for Quality Control for Plants and Production of Glass-Fiber Reinforced Concrete Products. MNL-130-09. Chicago, IL: PCI. American Society of Civil Engineers (ASCE). 2005. Minimum Design Loads for Buildings and Other Structures. Structural Engineering Institute (SEI)/ ASCE 7-05 and Supplement No. 2. Reston, VA: ASCE. International Code Council. 2006. International Building Code 2006. Falls Church, VA: ICC. PCI Bridge Design Manual Steering Committee. 1997. Precast Prestressed Concrete Bridge Design Manual. MNL-133-97. 1st ed. Chicago, IL: PCI. PCI. 1981. Reflections on the Beginnings of Prestressed Concrete in America. Chicago, IL: PCI.
4.
5. As stated in the foreword, the PCI Design Handbook is a living document. Comments related to any aspect of the handbook are encouraged and much appreciated. This handbook has had a very intensive review at several levels. It must be understood, however, that all errors may not have been observed and corrected during these reviews. PCI therefore intends to publish errata based on input of the users of the handbook over the next several months. The errata will also be posted on PCIs website at www.pci.org. Address all comments to PCIs Managing Director of Technical Activities at PCI, Jason Krohn, 200 West Adams Street, Suite 2100, Chicago, IL 60606.
6.
7. 8.
Postpublication Notes
After publication of the handbook, several errata that affect this article were observed as follows. These and other errata will be published in a future issue of the PCI Journal. a. Figure 4.8.4 of the seventh edition is not correct in that the horizontal line just above the lower shear wall on the right side of the plan should line up with the end of that shear wall. Figure 3 in this article is correct. Example 5.2.3.2 does not correctly reflect the text of the seventh edition in that it does not properly account for load in the partially developed strands. Use of E70 electrodes has been a common practice in the industry for years. The statement that this is no longer allowed by AWS D1.4 is incorrect. Refer to the sixth-edition PCI Design Handbook, which is correct. 9.
10. Schutt, Craig, ed. 2004. PCI 50 Years: Visions Taking Shape. Chicago, IL: Cherbo Publishing Group Inc. 11. Klein, G. J., and R. J. Lindenberg. 2009. Volume Change Movement and Forces in Precast Concrete Buildings. Research report, PCI, Chicago, IL. 12. Cleland, Ned and S. K. Ghosh. 2007. Seismic Design of Precast/Prestressed Concrete Structures. MNL140-07. Chicago, IL: PCI. 13. Mattock, A. H., W. K. Li, and T. C. Wang. 1976. Shear Transfer in Lightweight Reinforced Concrete. PCI Journal, V. 32, No. 1 (JanuaryFebruary): pp. 2039. 14. Klein, G. J. 1986. Design of Spandrel Beams. PCISFRAD project no. 5. PCI Journal, V. 31, No. 5 (SeptemberOctober): pp.76124. 15. PCI Committee on Prestressed Concrete Columns. 1988. Recommended Practice for the Design of Prestressed Concrete Columns and Walls. PCI Journal, V. 33, No. 4 (JulyAugust): pp. 5675. 16. Aswad, Alex, and George Burnley. 1991. Point Load
b.
c.
References
1. PCI Industry Handbook Committee. 2010. PCI Design Handbook: Precast and Prestressed Concrete. MNL120-10. 7th ed. Chicago, IL: PCI. American Concrete Institute (ACI) Committee 318. 2005. Building Code Requirements for Structural Concrete (ACI 318-05) and Commentary (ACI 318R-05). Farmington Hills, MI: ACI.
2.
145
Tests of Double-Tee Flanges. PCI Journal, V. 36, No. 4 (JulyAugust): pp. 6673. 17. Mack, P., G. Force, C. Magnesio, and K. Bryan. 2003. The Practice of Warping Double-Tees. PCI Journal, V. 48, No. 1 (JanuaryFebruary): pp. 3248. 18. Concrete Technology Associates (CTA). 2000. Ductile Pullout Connections. CTA Technical Bulletins, Vol. II. Chicago, IL: PCI. 19. American Welding Society (AWS). 2002. Structural Welding CodeReinforcing Steel. AWS D1.4-02. Miami, FL: AWS. 20. PCI Architectural Precast Concrete Committee. 2007. Architectural Precast Concrete. MNL-122-07. 3rd ed. Chicago, IL: PCI. 21. Logan, D. 2010. Erecting Long, Vertical Precast Concrete Members with One Crane and Two Operating Lines. PCI Journal, V. 55, No. 1 (Winter): pp. 118136. 22. American Society of Civil Engineers (ASCE)/Structural Engineering Institute (SEI). 2002. Design Loads on Structures During Construction. SEI/ASCE 37-02. Reston, VA: ASCE. 23. PCI Fire Committee. 1989. Design for Fire Resistance of Precast Prestressed Concrete. MNL-124-89. 2nd ed. Chicago, IL: PCI. 24. American Institute of Architects. 2006. Masterspec 2004. Salt Lake City, UT: ARCOM. 25. ACI Committee 301. 2010. Specifications for Structural Concrete. Farmington Hills, MI: ACI. 26. ACI. 1999. Details and Detailing of Concrete Reinforcement. ACI 315-99. Farmington Hills, MI: ACI. 27. ACI Committee 318. 2008. Building Code Requirements for Structural Concrete (ACI 318-08) and Commentary (ACI 318R-08). Farmington Hills, MI: ACI. 28. Ghosh, S. K. 2008. Significant Changes to ACI 318-08 Relative to Precast/Prestressed Concrete: Part 1. PCI Journal. Suppl. no. 53-2. 29. Ghosh, S. K. 2008. Significant Changes to ACI 318-08 Relative to Precast/Prestressed Concrete: Part 2. PCI Journal. Suppl. no. 53-3. 30. Ghosh, S. K. 2008. Significant Changes to ACI 318-08 Relative to Precast/Prestressed Concrete: Part 3. PCI Journal. Suppl. no. 53-5.
31. Ghosh, S. K. 2009. Significant Changes to ACI 318-08 Relative to Precast/Prestressed Concrete: Part 4. PCI Journal. Suppl. no. 54-3.
146