How to Apply For Electricity Connection

This handbook is published by SP PowerGrid Ltd in collaboration with SP Services Ltd

Aug 2010 Procedures and requirements highlighted in this handbook are correct at the time of printing. Any changes that may arise will be reflected in the next edition. ISBN: 981-04-6932-3

Important Contact Numbers


Tel No SP SERVICES LTD General Enquiry on Application For Connection to Transmission System Consumer Connection Agreement Contracts Section Testing and Turn-on Appointment Supply Application Section Installation Section Opening of Utilities Accounts Enquiry SP POWERGRID LTD Endorsement of Substation Drawings East zone West zone Installation of Meters Deputy Director (Meter) Enquiry 68238287 68238340 Fax No 68238289

68238282

68238289

68238287 63092612

68238289 63092614

1800-2222333

68238229

68238555 68238556

68238564 68238564

62777000 62777005

62777008

Table of Contents

1. GENERAL INFORMATION ................................................................................... 6


1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 1.9 INTRODUCTION ....................................................................................................... 6 CONNECTION VOLTAGES AND SUPPLY FREQUENCY ....................................... 6 SUBMISSION OF APPLICATION ............................................................................. 7 PROVISION OF A SUBSTATION .............................................................................. 7 DOMESTIC PREMISES AND LOAD REQUIREMENT NOT EXCEEDING 45KVA ... 8 METER ...................................................................................................................... 8 TARIFFS FOR NON-CONTESTABLE CUSTOMERS ............................................... 9 PAYMENT FOR ELECTRICITY CHARGES BY CONTESTABLE CUSTOMERS ..... 9 OPENING ACCOUNT AND PAYMENT OF SECURITY DEPOSIT FOR USE OF SYSTEM (UOS) CHARGES ...................................................................................... 9 1.10 1.11 TERMINATION OF ACCOUNT ................................................................................. 9 DISCONNECTION OF SERVICE CABLES UPON TERMINATION OF ACCOUNT . 9

2. APPLICATION FOR LOAD CONNECTION ........................................................ 11


2.1 2.2 DISTRIBUTION CONNECTION .............................................................................. 11 TRANSMISSION CONNECTION ............................................................................ 14

3. TRANSMISSION CHARGES ............................................................................... 16


3.1 3.2 CONSUMER CONNECTION AGREEMENT........................................................... 15 USE OF SYSTEM (UOS) CHARGES ...................................................................... 16

4. 4.1

ENERGISATION AND TURN-ON PROCEDURES........................................................ 22 PREMISES WHERE ELECTRICAL INSTALLATIONS ARE PREVIOUSLY INSPECTED AND ENERGISED ............................................................................. 22

4.2

PREMISES WITH DIRECT CONNECTION FROM SPPAS TRANSMISSION SYSTEM .................................................................................................................. 23

4.3 4.4

BOOKING AN APPOINTMENT ............................................................................... 25 PREMISES WITH INDIRECT CONNECTION (I.E. PREMISES IN A MULTIMETERED DEVELOPMENT).................................................................................. 27

4.5 4.6 4.7

MODIFICATION TO AN EXISTING ELECTRICAL INSTALLATION ....................... 28 LICENCE TO USE OR OPERATE AN ELECTRICAL INSTALLATION ................... 29 CERTIFICATES AND STATEMENTS FOR FIRST ENERGISATION OF SERVICE CONNECTION ........................................................................................................ 29

4.8 4.9

LEAD-TIME FOR APPLICATION FOR SERVICE CONNECTION .......................... 30 NOTES TO BE READ IN CONJUNCTION WITH APPLICATION PROCEDURE.... 32

5. CUSTOMER'S INSTALLATION .......................................................................... 36


5.1 5.2 5.3 REQUIREMENTS FOR HT AND LT CONNECTION (22KV AND BELOW) ............ 36 REQUIREMENTS FOR EHT CONNECTION (230KV AND 66KV) ........................... 38 INFORMATION ON SPPA NETWORK EARTHING SYSTEM (230KV, 66KV AND 22KV)....................................................................................................................... 39

6. METERING REQUIREMENTS ............................................................................ 40


6.1 6.2 6.3 GENERAL .................................................................................................................. 40 LOCATION OF METER ........................................................................................... 41 METER/SERVICE BOARD SPECIFICATIONS (SINGLE-PHASE AND 3-PHASE SERVICES, NOT EXCEEDING 100A PER PHASE) ............................................... 43 6.4 WIRING, LAYOUT OF METERS, MCBS, ETC IN CENTRALISED METER ROOMS, METER COMPARTMENTS/RISER DUCTS/CUPBOARDS ................................... 43 6.5 6.6 SUBMISSION OF LAYOUT PLANS ........................................................................ 43 METERS FOR 3-PHASE LOW TENSION CONNECTION (EXCEEDING 100A PER PHASE) ................................................................................................................... 43 6.7 6.8 6.9 6.10 HIGH TENSION / EXTRA-HIGH TENSION METERING ......................................... 45 TESTING OF METERING CTS AND VTS ................................................................ 46 METERING REQUIREMENTS ................................................................................ 47 CONTESTABLE CUSTOMERS .............................................................................. 48

7
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

Appendices
Application Form For Connection To SPPA Transmission System Consultation Form For Connection To SPPA Transmission System Form CS/3 Letter Of Consent From The Landlord/Management Corporation Form CS/3H Letter Of Consent From The Housing & Development Board Request To Handover Substation Application For The Supply Of Water, Electricity And/Or Gas Application For Interbank GIRO Form CS/5 Application For Inspection Of Electrical Installation Types And Layout Of Substation Submission Of Substation Site And Design Plans 6.6kV/LT Substation (4 drawings) 22kV/LT Substation (5 drawings) Heavy Aluminium Louvred Door For Electric Substation (6 drawings) Gate Details (2 drawings) Checklist For Substation Building Plan Submission Substation Layout Requirements To Be Incorporated In The Architectural Plans General Requirements For EHT Substation (66kV And 230kV Only) Protection Requirements For Customers 22kV and 6.6kV Main Incoming Switchgear Protection Requirements For Customers LT Main Incoming Switchgear Type 1: Customer 66kV Feeder Connection (Without Embedded Generation Plant) Type 2: Customer 66kV Feeder Connection (With Embedded Generation Plant) Type 3: Customer 66 kV Feeder Transformer Connection Type 4: Customer 230kV Feeder Connection Type 5: Customer 230kV Feeder Transformer Connection Application For De-Energisation/Re-Energisation (ADRE) Statement For De-Energisation And Re-Energisation (SDRE) Certificate Of Readiness For The Energisation Of Service Connection Form CS/6 Request For Installation Of Electricity kWh Meter For New Supply Under Direct Supply From SPPA (Contestable Customer) Form CS/7 Request For Installation Of Electricity kWh Meter (For Load Exceeding 45 kVA) Under Multi-Metered Building Scheme Application For Appointment For Energisation Of Service Connection By Fax Technical Requirements For Service Cable And Meter Compartment For Landed Houses Standard Meter Compartments At Gate Pillar Standard Meter Board Standard Size For Single-Phase Meter Board Standard Size For Three-Phase Meter Board CT Meter Panel For Low Tension Supply Methods Of Sealing Meter Panels Enclosure For Low Tension Metering Current Transformers HT Metering Kiosk Requirements (For 1 or 2 Feeders) HT Metering Kiosk Requirements (For 3 or 4 Feeders) HT Metering Panel Requirements (For 1 or 2 Feeders) Voltage Ratio, Sequence And Phase Angle Tests Report Basis For The Service Connection Charge

49
50 52 53 54 55 56 57 58 60 61 62 66 71 77 79 80 82 83 84 85 86 87 88 89 90 91 92 94 95 96 97 98 99 100 101 102 103 104 105 106 108 109 110

19 20 21 22.1 22.2 23 24

25 26 27 28 29 30 31 32 33 34 35

36 37 38 39 39A 40

41 42 43 44 45

Standard Service Connection Cables Certificate Of Compliance Statement Of Turn-On Of Electricity Requirements For Exempt Generation Facility not Exceeding 1MW Capped Capacity Scheme List Of Standards IEC Standards British Standards Singapore Standards Other Standards Form CS/12 Application for Electrical Installation Inspection (up to 45kVA) Application for Contestibility Status Application to Open a MSS Account Completion Certificate For Modification of Small Electrical Installation Form E Certificate of Fitness of Residential Unit

111 112 113 114

115 118 119 119 120 121 122 123 124

2.

General Information

1.1
1.1.1

INTRODUCTION
SP Services Ltd (SPSL), SP PowerAssets Ltd (SPPA) and SP PowerGrid Ltd (SPPG) are subsidiaries of Singapore Power Ltd. SPSL provides support services for the electricity market. It receives requests for electricity service connection; offers terms and conditions of service connection; arranges for service connection energisation/turn-on; and collects transmission charges, security deposits and charges for other services on behalf of SPPA. SPSL also bills customers for consumption. SPPA is the Transmission Licensee and owner of the transmission and distribution network. SPPG, the managing agent for and on behalf of SPPA, develops, operates and maintains the transmission and distribution facilities. The supply of electricity and electrical installation practices are governed by the Electricity Act and its subsidiary legislation.

1.1.2

1.2
1.2.1

CONNECTION VOLTAGES AND SUPPLY FREQUENCY


In Singapore, the customers load installations are connected at the following voltages: Transmission voltage of 66kV and 230kV Distribution voltage consist of 230V, 400V, 6.6kV, 22kV (may vary within 6%) The supply voltages are classified in the following categories:

1.2.1.1 1.2.1.2

1.2.1.3 1.2.1.4 1.2.1.5 1.2.1.6

Low Tension (LT) refers to 230V,single-phase and 400V, 3-phase High Tension (HT) refers to 22kV and 6.6kV Extra-High Tension (EHT) refers to 66kV Ultra-High Tension (UHT) refers to 230kV

1.2.2

The following connection schemes are provided, according to customers load requirements: 230V, 50 Hz, single-phase, up to a maximum of 23kVA, 100A 400V, 50 Hz, 3-phase, 4-wire. 22kV, 50 Hz, 3-phase, 3-wire for a Contracted Capacity of:

1.2.2.6 1.2.2.7 1.2.2.8

1.2.2.8.1 between 1,700 kW and 12,750kW for 2 HT 22kV services 1.2.2.8.2 between 12,751kW and 25,500kW for 4 HT 22kV services. 1.2.2.9 66kV, 50 Hz, 3-phase, 3-wire for connection with minimum Contracted Capacity of 25,500 kW.

1.2.2.10 230kV, 50 Hz, 3-phase, 3-wire for connection with minimum Contracted Capacity of 85,000 kW. 1.2.3 Where the customer requires a connection voltage and/or frequencies that differ from those specified above, the customer is required to provide, install and maintain the necessary transformation equipment.

1.3

SUBMISSION OF APPLICATION
SPSL serves as a one-stop customer service centre. It receives all application forms on behalf of SPPA, and responds to all applications made by the Licensed Electrical Worker (LEW), who acts as the customers agent for connection to the transmission system. Customers applying for their installations to be connected to SPPAs transmission system must submit their applications through their LEWs. Every application must be accompanied by all supporting documentation requested by SPSL. A copy of the Application Form is shown in Appendix 1. For a development in the conception/planning stage, the customer is advised to seek consultation regarding SPPAs requirements, such as the provision of a substation, for load connection. The Consultation Form (Appendix 2) must be submitted directly to SPPG by the customers LEW.

1.4
1.4.1

PROVISION OF A SUBSTATION
Direct service connection from SPPA's LT network to the customers installation is available for a small load requirement not exceeding 280kVA (400A). However, the provision of a direct service connection is dependent on the available network capacity in the vicinity. If there is insufficient capacity, the customer is required to provide a substation for the connection.

1.4.2

For a larger load requirement exceeding 280kVA (400A), the customer has to provide a substation for SPPA to install necessary equipment to cater for the load.

1.5

DOMESTIC PREMISES AND LOAD REQUIREMENT NOT EXCEEDING 45kVA


For premises where the electricity meter has already been installed by SPPA and no extension or rewiring work is required, electricity service connection will be turned-on on the next working day from the date of the opening of an account with SPSL. For premises where there is no electricity meter or where extension or rewiring work is required, the customer has to engage a LEW and submit an application for load connection (See Section 2).

1.5.1

1.5.2

1.6

METER
All meters required for measuring a customers electricity consumption and demand (where applicable) are provided and maintained by SPPA. The customer provides meter boards, compartments, kiosks, etc as SPPA may require for the installation of its metering equipment.

1.6.1

Master- And Sub-Metering A Master-meter is a meter measuring the consumption for all units and common areas in a building or cluster of buildings, which are used or occupied by multiple consumers. A Sub-meter is a meter measuring the consumption for a unit in a building or cluster of buildings used or occupied by multiple consumers, whose electricity is taken through a Master-meter. A master and sub-metering scheme is applicable for multi-tenanted premises. Under this scheme, the electricity supply is metered at the intake point and each tenants supply is also separately metered and billed under the appropriate tariff. The owner/developer/landlord shall be billed for the difference in the consumption between that metered at the intake point and the summated consumption of the tenants. Where the owner/developer/landlord takes supply at high tension and is responsible for stepping down the supply to 230V/400V for distribution to tenants, then a rebate of 2% on the summated consumption of the tenants will be granted.

1.6.1.1

Multi-Metered Premises The following are categories of multi-metered premises:

1.6.1.1.1 Residential premises which have landlord and tenant supply connections 1.6.1.1.2 Commercial complexes which have landlord and tenant supply connections

1.6.1.1.3 Multi-storey factories or industrial complexes which have landlord and tenant supply connections 1.6.1.1.4 All multi-metered premises fall under the Master- and Sub-metering scheme with the exception of HDB residential premises.

1.7
1.7.1

TARIFFS FOR NON-CONTESTABLE CUSTOMERS


Tariffs are currently charged for low tension, high tension and extra-high tension electricity consumption. Tariffs are subject to change and are published by SPSL from time to time. Online information on the latest electricity tariffs is available at www.spservices.com.sg.

1.7.2

1.8

PAYMENT FOR ELECTRICITY CHARGES BY CONTESTABLE CUSTOMERS


Contestable customer pays to SPSL or authorised retailers, charges for electricity consumption as ascertained by meters, and transmission charges and other fixed charges as determined by SPSL. Payment for electricity charges must be made on or before the due date specified in the bill.

1.9

OPENING ACCOUNT AND PAYMENT OF SECURITY DEPOSIT FOR USE OF SYSTEM (UOS) CHARGES
The customer must open an account and place a security deposit for UOS charges with SPSL upon application for energisation of service connection.

1.10

TERMINATION OF ACCOUNT
Non-contestable customers must give 4 business days' notice and contestable customers must give 12 business days notice to terminate an account. Such notices must be in writing to SPSL.

1.11

DISCONNECTION OF SERVICE CABLES UPON TERMINATION OF ACCOUNT


Disconnection work involves the de-energisation and removal of service cables and equipment. The following are indicative lead times for the work:

1.11.1

After the disconnection of LT, the lead-time is about 5 business days for the removal of LT service cables where road-opening work is not involved. Where road opening work is involved, a lead-time of 1 month is required. After the disconnection of 6.6KV and 22KV where removal of service cables and equipment are involved, the lead-time is about 1 month. For disconnection of 66kV and 230kV service cables, the service cable and equipment are de-energised within 10 business days, subject to the approval of the Power System Operator (PSO). The subsequent removal of service cables and equipment will depend on the operational requirement and approval of the PSO.

1.11.2

1.11.3

10

Application For Load Connection


2.1
2.1.1

DISTRIBUTION CONNECTION
Introduction Each premises can have only one customers intake connection point. For modification of connection (such as upgrading of the load requirement) to existing premises, the customer is required to amalgamate the existing service connection into one intake.

2.1.2

Consultation For a development in the initial planning stage, the customer is advised to seek consultation with SPPG to ascertain SPPAs requirements for a new or modified connection to the transmission system. The LEW is required to submit the Consultation Form (Appendix 2), together with a site/location plan to SPPG. After receipt of the submission for consultation, SPPG will send a reply stating the approved load and other technical requirements, such as the provision of substation requirements necessary for the load connection to the transmission system.

2.1.3

Application The Application Form (Appendix 1) together with a copy of the site/location plan, must be submitted to SPSL by the LEW for new or modified connections of new or existing premises to the transmission system.

2.1.3.1

Processing of Application Generally, SPSL responds to applications within 10 business days.

11

The responses are made according to the following customer categories: 2.1.3.1.1 Contestable Customer - A Consumer Connection Agreement, containing the service connection charge payable, the offer letter and the standard terms and conditions with respect to the distribution service connection. - If a substation is required, a letter stipulating the requirements will be forwarded to the customer, and an Agreement offered after the substation plans are endorsed. 2.1.3.1.2 Non-Contestable Customer - A Quotation, containing service connection charge payable and the conditions of service with respect to the distribution service connection - If a substation is required, a letter stipulating the requirements will be forwarded to the customer. A Supply Agreement including the service connection charge payable and the terms & conditions with respect to the distribution service connection, is offered after the substation plans are endorsed. 2.1.3.2 Commencement of Work - SPPG commences work only when the Agreement has been signed and received by SPSL, together with payment of service connection charges. 2.1.4 2.1.4.1 Type of Premises Multi-Metered Premises

2.1.4.1.1 A multi-metered premises is one where the landlord/MCST (i.e. a master-metered consumer or directly connected consumer) receives bulk intake service connection from SPPA, and transforms/reticulates the supply to all the tenants (i.e. sub-metered consumers) within the premises. Any application for new or modified connection (including upgrading) for the bulk intake to the multi-metered premises must be made by the landlord through its LEW. A master-metered consumer means a consumer that is responsible for the common usage of a master-metered installation, which is connected to the transmission system. A master-metered installation means an installation in which supply is received by a master-metered consumer and sub-metered consumers A sub-metered consumer means a consumer, other than a master-metered consumer, that receives supply in a master-metered installation via the electrical system owned by a master-metered consumer. 2.1.4.1.2 The landlord/MSCT or HDB, in the case of HDB premises, must ensure that the total applied load requirement for service connections to the multi-metered premises meet the total existing and future load requirements for all tenants. All 12

tenants applying for any upgrading of load must do so through their mastermetered consumer. In this regard, the master-metered consumer must approve the load of all tenants within the premises. 2.1.4.1.3 If the landlords existing approved load is insufficient to cater for the tenants load requirement, the landlord, as a master-metered consumer, must submit an application to SPSL for modification (upgrading) of service connection to the existing premises. In this case, the existing service cables are amalgamated with the new intake. Hence, there will not be separate direct connections to the tenants of such premises. 2.1.4.2 Premises in Private Housing, Industrial Estates, Commercial Developments Requiring Provision of Low Tension (LT) Distribution Network

2.1.4.2.1 For connection to premises where several parcels of land are to be sold or leased individually, one or more substations must be provided by the developer. Where the individual parcels of land are to be sold prior to development of these substations, details of the substation requirements and approved load must be included in the sales agreement by the future land parcels owner or lessee. 2.1.4.2.2 The developer must provide the developments total load requirement and include the breakdown of the individual premises load requirement (as specified in the sales agreement) and the communal load requirement, if applicable. 2.1.4.2.3 In the case of landed housing estate development, the LEW must liaise with National Parks Board for the siting of overground distribution boxes on turfed areas. SPPA will provide and install the LT distribution network and service connection cables for the development. 2.1.4.3 Premises Involving Temporary Connection With Provision Of Substation

2.1.4.3.1 Special terms and conditions apply in such cases for temporary connection to construction worksites and other temporary premises. The term granted for temporary connection is usually 24 months. 2.1.4.3.2 Where there is a need for the provision of a temporary substation, the customer must provide the site and construct the structure of the substation according to the requirements of SPPA. 2.1.4.3.3 There will be a need to install the necessary cables and equipment to facilitate the temporary connection to the distribution network. The customer pays outright costs for the cables and a monthly hiring charge for the use of the equipment (including the cost of insuring the equipment) during the term for temporary connection.

13

2.1.5 2.1.5.1

Provision of Substation When an application for load connection necessitates the provision of a substation (See Appendices 9 and 10), a site must be provided and a substation constructed by the customer at its own cost. The customer can either choose his substation to be a dedicated or non-dedicated one (See Appendix 35). If the customer opts for a dedicated substation, he has to inform SPPG when he applies for connection. Otherwise, it shall be assumed that the substation would be non-dedicated. The customer is advised to site the substation at an inconspicuous location, away from the main entrance of the development and major public roads. The customer is also encouraged to harmonise, blend and integrate the substation with its development. SPPGs officers and vehicles will have full and unrestricted access to the substation. Service Connection Cables Generally, SPPA supply, install and maintain customer service cable. However, if the customer intake point is at different level to the substation building, or service cable to be installed in cable tray/ladder, the customer shall supply, install and maintain the service cable. In the event that customer supplies the service cable, the customers LEW shall ensure that the service cable complied with SPPA cable specification, and submit cable sample and specification to Distribution Engineering Section for approval prior to procurement. The general type of cables for service connection is shown in Appendix 36.

2.1.5.2

2.1.5.3

2.1.5.4 2.1.6

2.2
2.2.1 2.2.1.1

TRANSMISSION CONNECTION
Consultation A customer may choose to seek preliminary comments from SPPG via the connection consultation process before submitting a formal application. This practice is encouraged as incorporating SPPAs requirements in a developers preliminary proposal would expedite the application process at a later stage. To initiate the connection consultation process, the customer has to submit the Consultation Form (Appendix 2) through an LEW to SPPG. Application The following are steps in the application for service connection:

2.2.1.2

2.2.2

2.2.2.1

The customer submits the Application Form (Appendix 1) through an LEW to SPSL.

14

2.2.2.2

A connection proposal, duly endorsed by the PSO, is given to the customer. It outlines the connection scheme, connection voltage, connection equipment and facilities required of the customer and the estimated connection charges. SPPG endeavors to respond to the customer, through SPSL, within 60 business days and 100 business days for 66kV connections and 230kV connections respectively. Where the application requires the provision of an EHT substation, the customer must adhere to the general requirements attached in Appendix 17. Once customer acknowledges acceptance of SPPGs connection proposal, SPPG proceeds to execute the Consumer Connection Agreement through SPSL. The Agreement contains an Offer Letter, the standard terms and conditions associated with the connection and an estimation of the connection charges Lead-Time for Application of Transmission Connection The timely provision of electricity supply to a development involves the joint efforts of SPSL, SPPG, and the customer and their agents, such as the LEW. While SPSL and SPPG will make every effort to engineer and implement the connection scheme, it is at the same time essential for the new customers and their agents to co-operate via timely submission of applications and plans, timely acceptance of the terms and conditions of connection and compliance with the necessary SPPA or Transmission Code requirements. As a guide for the customer and their agents, the normal lead-times for the events leading to the energisation of 66kV service connections are listed in the box below. The actual time-lead to energisation may vary for each connection, depending on the actual service cable length and the progress of intermediate events leading to completion of service connection works. Customers will be informed accordingly either at the point of application or at any time a review is required. For 230kV service connections, the customer will be informed of the lead-time only at the point of application.

2.2.2.3

2.2.2.4

2.2.3 2.2.3.1

2.2.3.2

NORMAL LEAD TIME FOR ENERGISATION OF 66kV SERVICE CONNECTION New 66kV Connection from SPPAs Existing Substation 21 months New 66kV Connection from New 66kV Substation Provided by Connection Applicant 26 months*

Events From day of execution of Consumer Connection Agreement to energisation of service connection

Notes: * The Customer is required to handover the substation 8 months prior to target date of energisation of service connection.

15

2.

Transmission Charges

3.1
3.1.1

CONSUMER CONNECTION AGREEMENT


All customers are required to enter into a Consumer Connection Agreement with SPPA and to pay Use of System (UOS) charges. Customers having a direct connection to the transmission system must also pay a service connection charge. For non-contestable customers, the Connection Agreement is part of the Supply Agreement. The Consumer Connection Agreement for customers taking HT supply at 6.6 kV/22 kV, EHT supply at 66 kV or UHT supply at 230 kV and above will, inter alia, state the Contracted Capacity, which is deemed to be the requirement for a period of five years. Customers cannot reduce their Contracted Capacity until the expiration of the 5-year period or additional 5-year period. Furthermore, a customer who terminates the supply agreement during the 5-year period or additional 5-year period will be required to pay SPPA through SPSL/Retailer, the Contracted Capacity Charge for the unexpired portion of the 5-year period. UOS charges are payments for the use of the transmission services. The UOS charges are paid for electricity consumption at each metered intake supply point in accordance with the voltage at which a customer receives the electricity supply. The UOS charges are subject to annual review and the revised UOS charges will be published by SPPA. In the case of HT and EHT supply to multi-metered premises, the landlord has to enter into a Connection Agreement for the network capacity required for his own load only, i.e. supply for common services, etc.

3.1.2

3.1.3

3.1.4

16

3.1.5

The UOS Charges are applicable for the following categories of supplies : Low Tension (LT) Supplies (400V/230V) Supply to Low Tension-Small Consumer Supply to Low Tension-Large Consumer High Tension (HT) Supplies (22kV and 6.6kV) Supply to High Tension-Small Consumer, whose Contracted Capacity is less than 1,700 kW per month at each metered intake supply point. Supply to High Tension-Large Consumer, whose Contracted Capacity is at least 1,700 kW per month at each metered intake supply point. Extra-High Tension (EHT) Supplies (66kV) Supply to Extra-High Tension Consumer Ultra-High Tension (UHT) Supplies (230kV and above) Supply to Ultra-High Tension Consumer Temporary Supplies Temporary Supplies apply only to LT and HT supplies for temporary civil engineering and building construction sites.

3.2 3.2.1

USE OF SYSTEM (UOS) CHARGES


Low Tension Small Customer LT supplies (in kWh) to all non-contestable LT consumers are metered on a monthly basis. A flat per kWh UOS rate is levied at each metered intake supply point.

3.2.2

Low Tension Large Customer The large industrial and commercial LT consumers, who are contestable and have time-of-day metering, come under this category. LT Supplies to these contestable consumers are metered on energy (kWh) on a half-hourly time-of-day basis. The respective per kWh charges shall be levied at a Peak and an Offpeak period for the energy supplied at each metered intake supply point.

3.2.2.1

Peak Period Charge The Peak Period Charge payable shall be the monthly charge based on the energy (in kWh) supplied to an installation during the peak period, 7.00 am to 11.00 pm, in that month.

17

3.2.2.2

Off-Peak Period Charge The Off-Peak Period Charge payable shall be the monthly charge based on the energy (in kWh) supplied to an installation during the off-peak period, 11.00 pm to 7.00 am, in that month.

3.2.3

High Tension, Extra-High Tension and Ultra-High Tension Supplies For HT (i.e. HT Small and HT Large), EHT and UHT Supplies, UOS Charges shall be levied at each metered intake supply point as follows : a. b. c. d. e. f. Contracted Capacity Charge; Peak Period Charge; Off-peak Period Charge; Reactive Power Charge; Uncontracted Capacity Charge, and Uncontracted Standby Capacity Charge (applicable to consumers with embedded generation who opt to cap their power demand drawn from the network).

3.2.3.1 3.2.3.1.1

Contracted Capacity Charge The Contracted Capacity Charge is a monthly charge payable in any month for the Contracted Capacity at each metered intake supply point of a consumer. The Contracted Capacity of a consumer's installation shall be the supply capacity (in kW), which is requested for that metered intake supply point. For the avoidance of doubt, and without prejudice to paragraph 3.2.3.1.3 herein, the consumer shall not be allowed to reduce the declared Contracted Capacity upon the signing of the Consumer Connection Agreement / Supply Agreement, notwithstanding the fact that the energisation of the new supply has still not taken place. For a new supply, the Contracted Capacity shall be deemed to be the consumer's requirement for a binding period of 5 years from the target date or the commissioning date for SPPAs plant and equipment, except for the service cable, whichever is later. For new HT, EHT and UHT supplies, the minimum Contracted Capacity for each metered intake supply point shall be as follows : HT with 1 or 2 feeders HT with 3 or more feeders EHT UHT 1,700 kW, 12,750 kW, 25,500 kW, 85,000 kW.

3.2.3.1.2

For new supplies, a request may be made for intermediate steps before the full Contracted Capacity is implemented during the first year of the 5-year binding period. The first step shall be at least one quarter () of the consumers requested full Contracted Capacity at each metered intake supply point. 3.2.3.1.3 After the initial 5-year period, the consumer may, by giving one month's notice in writing, reduce his Contracted Capacity at each metered intake supply point subject to the following minimum values :

18

HT with 1 or 2 feeders HT with 3 or more feeders EHT UHT

850 kW, 6,375 kW, 12,750 kW, 42,500 kW.

Any such reduction in Contracted Capacity shall be deemed to be the consumers requirements for one year commencing from the first day of the billing cycle that follows after the end of the notice period and the consumer shall not be entitled to make any further reduction in the Contracted Capacity within one year following any such reduction. Market Support Services Licensee will inform the consumer of the date of their billing cycle. 3.2.3.1.4 Upward revision of the Contracted Capacity may be allowed during the validity of the binding period of 5 years or 1 year of the Contracted Capacity. The revised Contracted Capacity shall in such cases commence from the first day in which it is effective and shall apply for the remainder of the initial 5-year period or for a minimum period of 1 year, whichever is the greater, provided SPPA is not required to install new or additional equipment. Downward revision during such binding periods will not be allowed. A consumer whose revised contracted capacity requires SPPA to install new or additional equipment shall be considered as receiving a new supply with a new 5-year binding period. For a new development with landlord and tenants, the supply capacity required by the landlord himself must meet the minimum values set out in paras 3.2.3.1.2 to 3.2.3.1.5 above in order for the landlord to qualify for HT, EHT or UHT supplies. For those HT, EHT or UHT consumers whose Contracted Capacity are below the minimum values specified above before the implementation of these rates, they may request to increase (but not decrease) their Contracted Capacity in the manner as described above. Peak Period Charge The Peak Period Charge payable shall be the monthly charge based on the energy (in kWh) supplied to an installation during the peak period, 7.00 am to 11.00 pm, in that month. 3.2.3.3 Off-Peak Period Charge The Off-Peak Period Charge payable shall be the monthly charge based on the energy (in kWh) supplied to an installation during the off-peak period, 11.00 pm to 7.00 am, in that month. 3.2.3.4 Reactive Power Charge The Reactive Power Charge is a monthly charge payable in any month for the installation's excess kVArh consumption. The excess kVArh shall be the

3.2.3.1.5

3.2.3.1.6

3.2.3.1.7

3.2.3.2

19

difference by which the installation's kVArh consumption drawn from the network in that month is greater than 62% of its kWh consumption drawn from the network in the same month. 3.2.3.5 3.2.3.5.1 Uncontracted Capacity Charge The Uncontracted Capacity Charge is a monthly charge payable in any month for the Uncontracted Capacity utilised. The Uncontracted Capacity is the capacity in kW by which the maximum demand in kW (measured by the half-hour integration meter) exceeds the Contracted Capacity at that metered intake supply point. The Uncontracted Capacity Charge shall apply to the following HT, EHT and UHT consumers : a. b. Normal consumers without embedded generation; Consumers with embedded generation whose monthly maximum demand in kW is the maximum summated demand in kW in the month, determined by summating the kW demand drawn from the network and the kW output from embedded generation (i.e. Summation Scheme); and Consumers with embedded generation who opt to cap their power demand in kW drawn from the network in the event that the maximum demand in kW (measured by the half-hour integration meter) exceeds the Contracted Capacity at that metered intake supply point (i.e. Capped Capacity Scheme or Extended Capped Capacity Scheme). The Uncontracted Capacity for these consumers shall be limited to 20% of the Contracted Capacity.

3.2.3.5.2

c.

3.2.3.6 3.2.3.6.1

Uncontracted Standby Capacity Charge The Uncontracted Standby Capacity Charge is a monthly charge payable in any month for the Uncontracted Standby Capacity utilised. The Uncontracted Standby Capacity Charge shall apply to those HT, EHT and UHT consumers with embedded generation who opt for the Capped Capacity Scheme or Extended Capped Capacity Scheme. For Capped Capacity Scheme, the Uncontracted Standby Capacity Charge applies in the event the demand in kW drawn from the network (measured by the power meter) exceeds 120% of the Contracted Capacity at that metered intake supply point for a duration of more than 10 seconds continuously. For Extended Capped Capacity Scheme, the Uncontracted Standby Capacity Charge applies in the event : the demand in kW drawn from the network exceeds 120% and up to 200% of the Contracted Capacity at that metered intake supply point for a duration of more than 100 seconds continuously; or

3.2.3.6.2

3.2.3.6.3

20

the demand in kW drawn from the network exceeds 200% of the Contracted Capacity at that metered intake supply point for a duration of more than 10 seconds continuously.

3.2.3.6.4

For the avoidance of doubt, in the event Uncontracted Standby Capacity Charge applies in accordance with Clauses 3.2.3.6.2 and 3.2.3.6.3 above, Uncontracted Capacity Charge shall also be applicable for the Contracted Capacity portion which is 20% above the customers declared Contracted Capacity.

3.2.4
3.2.4.1

TEMPORARY SUPPLIES
Temporary Supplies apply only to LT and HT supplies for temporary civil engineering and building construction sites. The UOS charges applicable for the LT and HT temporary supplies shall be the same as those used for LT and HT supplies respectively. For temporary supplies at HT, the Contracted Capacity shall apply for a minimum binding period of 1 year up to a maximum of 2 years. Upward revision of the Contracted Capacity may be allowed during the validity of the binding period of the Contracted Capacity. The revised Contracted Capacity shall in such cases apply for a minimum period of 1 year, provided SPPA is not required to install new or additional equipment. Downward revision during such binding period will not be allowed. A consumer whose revised Contracted Capacity requires SPPA to install new or additional equipment, shall be considered as receiving a new temporary supply. The term granted for temporary connection is 2 years.

3.2.4.2

21

2.

Energisation and Turn-on Procedures

The term energise, in the case of a customers installation that is directly connected to the transmission system, refers to the closing of a circuit breaker or other isolating device that is owned and controlled by SPPA. Energisation, de-energisation and re-energisation and all grammatical variations of the term shall be interpreted accordingly. Arrangements need to be made with SPSL for energisation of the service connection and turn-on of a customers electrical installation. This is taken care of by the LEW. The following are arrangements needed by type of premises:

4.1

PREMISES WHERE ELECTRICAL INSTALLATIONS ARE PREVIOUSLY INSPECTED AND ENERGISED NON-DOMESTIC PREMISES (LOAD REQUIREMENT NOT EXCEEDING 45kVA), AND DOMESTIC PREMISES WHERE ELECTRICAL INSTALLATIONS ARE PROVIDED AND PRE-INSPECTED OR PREVIOUSLY INSPECTED AND ENERGISED
This category includes all new HDB apartments and dwelling units in some private residential developments where electrical installations are provided and inspected in advance. It also includes non-domestic premises (supply capacity not exceeding 45kVA) and domestic premises where the existing electrical installations and service connections are intact and only the supply is required to be re-energised. The customer has to open an account with SPSL for electricity service connection (See 4.9.2). The customer is given an appointment for turn-on of service connection. This appointment date is normally the next working day from the date the account is opened. For electrical safety reasons, the customer or his representative must be present at the premises for the turn-on of electricity service connection.

4.1.1

4.1.1.1

4.1.1.2

4.1.1.3

22

4.1.2

NON-DOMESTIC PREMISES (LOAD REQUIREMENT EXCEEDING 45kVA) WHERE ELECTRICAL INSTALLATIONS ARE PREVIOUSLY INSPECTED AND ENERGISED
This category includes non-domestic premises (supply capacity exceeding 45kVA) where the existing electrical installations, meters and service connections are intact and only the supply is required to be re-energised. The customer has to open an account with SPSL for electricity service connection (See 4.9.2). The customer has to apply for a licence from Energy Market Authority (EMA) to use or operate the electrical installation through an appropriate class of licensed electrical worker. Upon submission of the licence, the customer is given an appointment for turn-on of service connection. This appointment date is normally the next working day from the date of receiving the licence. The licensed electrical worker must be present at the premises to issue a Certificate of Compliance (COC) to SPSL during the turn-on of electricity service connection.

4.1.2.1

4.1.2.2

4.1.2.3

4.1.2.4

4.2

PREMISES WITH DIRECT CONNECTION FROM SPPAS TRANSMISSION SYSTEM


Domestic Premises (all load requirements) The customer opens an account with SPSL, if an account has not already been opened (See 4.9.2). Upon completion of the electrical installation and receipt of notification from SPPG on energisation/readiness of the service connection, the LEW books an appointment with SPSL for inspection and turn-on of the customers installation. For load below 45kVA, this is done by submitting Form CS/5 (Appendix 8) Application For Inspection of Electrical Installation and the Certificate of Compliance (COC) (See 4.7.1) to Supply Application of SPSL. If the Application is done through facsimile, Form CS/12 (Appendix 41) Application for Electrical Installation Inspection (up to 45kVA) is required. For load above 45kVA, this is done by submitting the Inland Revenue Authority of Singapore (IRAS) letter stating the official addresses, COC, Form E (Appendix 45) Certificate of Fitness of Residential Unit and the as-build Single Line Drawing (SLD) to Installation Section of SPSL. The electrical installation is connected to SPPAs transmission system on the scheduled turn-on date if the electrical installation is safe to receive electricity supply. The LEW must be present during inspection of the electrical installation by SPSL. For electrical safety reasons, the customer or his representative must also be present at the premises for the turn-on of electricity service connection. A PASS Inspection Report is issued by SPSL on-site upon successful turn-on of the customers installation.

4.2.1 4.2.1.1

4.2.1.2

4.2.1.3

23

4.2.2 4.2.2.1

Non-Domestic Premises Load Requirement Not Exceeding 45kVA

4.2.2.1.1 The customer opens an account with SPSL, if this has not already been done (See 4.9.2). 4.2.2.1.2 Upon completion of the electrical installation and receipt of notification from SPPG on energisation of the service connection, the LEW books an appointment with SPSL for inspection and turn-on of the electrical installation. This is done by submitting Form CS/5 (Appendix 8) Application For Inspection of Electrical Installation and the COC form (See 4.7.1) to Supply Application of SPSL. If the Application is done through facsimile, Form CS/12 (Appendix 41) Application for Electrical Installation Inspection (up to 45kVA) is required.

4.2.2.1.3 The electrical installation is connected to SPPAs transmission system on the scheduled turn-on date if the electrical installation is safe to receive electricity supply. The LEW must be present during inspection of the electrical installation by SPSL. For electrical safety reasons, the customer or his representative must also be present at the premises for the turn-on of electricity service connection. A PASS Inspection Report for the customers installation is issued by SPSL onsite upon successful turn-on. 4.2.2.2 Load Requirement Exceeding 45kVA

4.2.2.2.1 The customer submits an application for an account (See 4.9.2), to SPSL if this has not already been done, and applies for a licence from Energy Market Authority (EMA) to use or operate an electrical installation. 4.2.2.2.2 Upon completion of the electrical installation and receipt of notification from SPPG on the readiness of service connection, the LEW must inspect and test the electrical installation before booking an appointment with SPSLs Installation Branch for the installation of meter and energisation of service connection by SPPG. This is done by submitting a letter of confirming the readiness of the service connection and the COC form (See 4.7.1). Alternatively, the LEW can submit the Application for Appointment for Energisation of the Service Connection By Fax (Appendix 23). 4.2.2.2.3 The LEW requesting for energisation of supply line has to arrange for the LEW responsible for the operation of the electrical installation and the customer (or his representative) to be present during the energisation.

4.2.2.2.4 The electrical installation is connected to SPPAs transmission system on the scheduled energisation date if the electrical installation is safe to receive electricity supply. The LEW must issue a Certificate of Readiness (COR) form (See 4.7.2) to SPPG at site, prior to energisation of the service connection. 4.2.2.2.5 Upon successful energisation of service connection to the customers installation from SPPAs direct connection, all parties are to acknowledge on the Statement of Turn-On of Electricity (See 4.7.3).

24

4.3
4.3.3

BOOKING AN APPOINTMENT
Before booking an energisation and turn-on appointment, the LEW must ensure the following: Metering requirements, where applicable, have been submitted and formal clearance has been given by SPPGs Meter Section. All necessary meters have been installed. The customers main incoming switchgear, protection system and earthing system have been successfully tested by an LEW. The HT metering panel has been provided, and testing of the metering current transformers/voltage transformers have been carried out and meters installed by Meter Section. The service cables to the installation are ready to be energised. A utilities account has been opened, an Agreement has been signed, and a security deposit for UOS has been paid by the customer. A licence to use or operate the electrical installation, where applicable, has been obtained from EMA. For service connection at a system voltage level of 66kV and above, the final clearance for the EHT switching procedure must be obtained from the PSO prior to the confirmation of the first energisation date. Notes: (1) The EHT switching procedure must be jointly prepared and endorsed by the LEW, who is authorised to perform EHT switching (at customers installation), and SPPGs Project Engineer. (2) For 66kV and above, the LEW must submit the COC form to SPPGs Project Engineer.

4.3.3.1

4.3.3.2

4.3.3.3 4.3.3.4

4.3.3.5

4.3.3.6

25

4.3.4

Making An Appointment for Energisation Of Service Connection Direct From SPPAs Transmission System: Load Requirement Not Exceeding 45kVA To make an appointment to turn-on electricity supply, the LEW shall submit Form CS/5 (Appendix 8) Application For Inspection of Electrical Installation on behalf of the customer, and a copy of the Certificate of Compliance (COC) to request for an inspection and turn-on to the premises. The LEW is encouraged to submit application via: Fax to: Mail to: 68238289 Customer Services Supply Application Section 111 Somerset Rd, #01-10 Singapore Power Building Singapore 238164

4.3.4.1

Or drop the application into our drop-in box located in our Customer Service Centre at the above address. 4.3.4.2 Load Requirement Exceeding 45kVA Up To 22kV Supply Voltage An appointment for energisation of electricity service connection of load requirements greater than 45kVA and up to 22kV supply voltage can be made as follows: To make an appointment in person to energise the service connection, the LEW or his representative submits the letter confirming the readiness of service connection and the COC to SPSLs Installation Section at 7th storey, St. James District Office, Keppel Road. Alternatively, the LEW can submit the Application for Appointment for Energisation of the Service Connection together with COC Form by Fax (Appendix 23) to Installation Section. The original copy of the COC Form must be submitted to SPPG on the scheduled energisation date. 4.3.4.3 A lead-time of 14 business days is required for the LEW to request for the energisation of SPPAs service connection and turn-on of the customers installation. Energisation of service connection involves several parties. An officer at SPSLs Installation Section co-ordinates with SPPG for the energisation of the service connection for supply taken directly from SPPAs transmission system.

4.3.4.4

26

4.3.5

Submission Of Application For New EHT And HT Consumers Who Wish To Be Contestable At Time Of Turn-On The consumer must subscribe and install one dedicated telephone line per metering point (adjacent to meter panel) to be used for the purpose of remote metering. The LEW shall submit a copy of the duly completed Form CS/6 (Appendix 22.1) Request from Contestable Customer for Installation of Electricity kWh Meter with the active dedicated telephone line number clearly stated to SPSL for the installation of TOD Meter. The LEW shall proceed to liaise directly with Meter Section of SP PowerGrid to have the TOD meter installed. Upon completion of the installation of the TOD meter and telephone line, the consumer shall submit a copy of the duly completed Application for Contestability Status (Appendix 42) and Application to open a MSS Account (Appendix 43) to Client Relations Branch of SPSL at 111 Somerset Road, #06-05 or via fax: 68236800 at least 12 business days prior to your arrangement for the turn-on appointment. If the customer chooses to purchase electricity from a Retailer with effect from the turn-on date, the Retailer must submit a transfer request to SPSL at least 1 business day before the turn-on date. Otherwise, SPSL will arrange to buy electricity for the customer from the wholesale electricity market and the customer will be charged for the electricity consumption at prevailing wholesale spot prices. In this case, a security deposit to SPSL is required. The LEW shall proceed to apply to EMA for EI Licence. The LEW shall submit a copy of COC, EI Licence, IRASs Letter stating official address and book an appointment for energisation of service connection at Installation Section of SPSL at St James District Office (for HT Supply) or at Transmission Projects III Section of SP PowerGrid @ Kallang Bahru District Office (for EHT Supply).

4.3.5.1

4.3.5.2

4.3.5.3

4.3.5.4

4.3.5.5

4.3.5.6

4.3.5.7 4.3.5.8

4.4

PREMISES WITH INDIRECT CONNECTION (I.E. PREMISES IN A MULTI-METERED DEVELOPMENT)


Load Requirement Not Exceeding 45kVA The customer opens an account with SPSL (See 4.9.2) if this has not already done. The customer submits an Application for Inspection of Electrical Installation (Appendix 8) to SPSL through the LEW together with a Letter of Consent from the

4.4.1 4.4.1.1

4.4.1.2

27

Landlord/Management Corporation or HDB (Appendices 3 and 4). The LEW can also book an appointment for inspection of the electrical installation at the time of submission of the application and, in the meantime, proceed to carry out the wiring/extension work. The procedure of booking an appointment is as in 4.3.4.1 above. 4.4.1.3 The LEW is responsible for arranging the energisation of the service connection with the relevant party responsible where connection is taken via the landlords switchboard - such as in HDB, JTC or other private multi-metered buildings. Service connection will be turned-on on the scheduled inspection date if the electrical installation is safe to receive electricity supply. The LEW must be present during the inspection. A PASS Inspection Report for the customers installation will be issued on-site by SPSL upon successful turn-on. The LEW must issue a Statement of Turn-On of Electricity and this must be acknowledged by the relevant parties. Load Requirement Exceeding 45kVA (Multi-Metered Building Scheme) When the premises is ready for installation of meters, the customer shall proceed to open a utilities account with payment of security deposit to SPSL. The LEW shall proceed to apply to EMA for EI Licence before the electricity supply is turned on. The LEW shall submit Form CS/3 (Appendix 3) or Form CS/3H (Appendix 4), Form CS/7 (Appendix 22.2) - Request for Installation of Electricity kWh Meter (for Load Exceeding 45kVA) and a copy of COC and EI Licence to SP Services declaring the account activation date (which is the proposed turn-on date). The LEW shall proceed to liaise with Meter Section of SP PowerGrid to install meters. For HT Supply, the consumer is required to sign an agreement with SP PowerGrid before SP Services can process the application for installation of TOD meter. The LEW shall be responsible for arranging the energisation of the service connection with the relevant party where the connection is taken via landlords switchboard such as HDB, JTC or private multi-tenanted buildings. Landlords LEW shall issue the Statement of Turn-On of Electricity (SOTO) upon successful turn-on.

4.4.1.4

4.4.2 4.4.2.1

4.4.2.2

4.4.2.3

4.4.2.4

4.4.2.5

4.4.2.6

4.4.2.7

4.5
4.5.1

MODIFICATION TO AN EXISTING ELECTRICAL INSTALLATION


Modification work (e.g. extension, rewiring, shifting of meter) carried out to an existing electrical installation where a licence to use or operate is not required, must be inspected by SPSL before the new/modified portion of the wiring can be used.

28

4.5.2

The LEW must submit an application for inspection (Form CS/5, Appendix 8) by SPSL for the modified electrical installation. Submission Of Completion Certificate For Modification of Small Electrical Installation (Exempted From Licensing) The LEW shall submit to SPSL the duly completed Form CS/5 (Appendix 8), together with Form CS/3 (Appendix 3) or Form CS/3H (Appendix 4) and the Completion Certificate for Modification of Electrical Installation (Appendix 44) on behalf of the customer. (Note: First-time inspection is free-of-charge and Form CS/3 or Form CS/3H is not required for HDB residential premises) SPSL conducts spot-checks for those system-selected applications. For those applications not selected, acknowledgement letters will be sent to both the customer and the LEW. If the inspection is Failed, the LEW will have to come to SPSL with a copy of the Failed letter to arrange for a re-inspection. A re-inspection fee is payable. If the inspection is Passed, acknowledgement letter will be sent to both the customer and the LEW.

4.5.3

4.5.3.1

4.5.3.2 4.5.3.3

4.5.3.4

4.5.3.5

4.6
4.6.1

LICENCE TO USE OR OPERATE AN ELECTRICAL INSTALLATION


For service connection to non-domestic premises, residential buildings and condominiums with an approved load greater than 45kVA, and temporary connection for building construction and engineering work, irrespective of connection load, the customer must obtain a licence from EMA to use or operate the electrical installation. It must be noted that SPPG cannot energise the service connection until such a licence is issued to the customer.

4.6.2

4.7

CERTIFICATES AND STATEMENTS FOR FIRST ENERGISATION OF SERVICE CONNECTION


Certificate of Compliance (COC) The LEW must ensure that the electrical installation complies with the requirements of the Electricity Regulations, Singapore Standards CP5, relevant technical requirements and all other applicable standards. This compliance must be made in the COC form (Appendix 37). The COC form must be submitted to SPPG through SPSL when requesting for an energisation appointment.

4.7.1 4.7.1.1

29

4.7.2 4.7.2.1

Certificate of Readiness (COR) The LEW has to certify the readiness of the installation. This certification must be made in the COR form (Appendix 21). The LEW must hand over the COR form to SPPGs Project Officer on the actual date of first energisation. Statement of Turn-On of Electricity Immediately after the successful first energisation of the service connection, SPPG will issue a Statement of Turn-On of Electricity (Appendix 38). All parties are to acknowledge by signing the form. The completed form will be given to all parties and a copy forwarded to SPSL.

4.7.3 4.7.3.1

4.8
4.8.1

LEAD-TIME FOR APPLICATION FOR SERVICE CONNECTION


The timely provision of electricity supply to a development involves the joint efforts of SPSL, SPPG, and the customer and his agents, such as the LEW. While SPSL and SPPG will make every effort to engineer and implement the connection scheme, it is at the same time essential for the new customers and their agents to play their part such as the early submission of applications and plans, the acceptance of terms and conditions of connection including making the necessary payments and the compliance of the necessary SPPA or Transmission Code requirements. As a guide for the customer and his agents, the normal lead-times for the various events are listed on the following page. Depending on the progress and completion time of precedent events, the actual completion dates of events leading to the energisation of the service connection may need to be reviewed and adjusted.

4.8.2

30

NORMAL LEAD TIME FOR ENERGISATION OF SERVICE CONNECTION UP TO 22KV


Installation with existing Service Connection Not Exceeding 45kVA or Domestic Premises Pre-inspected Inspection Installation or Required Reconnection Submission of application to SPSL Submission of substation plans to SPPG Acceptance of Agreement Handover of substation to SPPG+ Opening of account with SPSL Arrangements to inspect customer's installation (not exceeding 45kVA) by SPSL Application to EMA for licence to use or operate an electrical installation Request for energisation of service connection
*

NA NA

14 days* NA

Nondomestic Installation with Existing Service Connection Exceeding 45kVA 4 weeks NA

New Connection from SPPA's Low Tension Mains

New Connection from New Substation

3 months NA 7 weeks** NA 14 days NA

6 months 5 months 11 weeks* 10 weeks* 11 weeks NA

4 days NA 4 days NA

14 days NA 14 days 10 days

14 days NA 14 days NA

NA

NA

10 days

10 days

10 days

NA

NA

14 days

14 days

14 days

These are critical events. Failure to adhere to the schedule may result in delay in the turn-on of supply.

**

Implementation of connection work shall only be effected upon the payment of service connection charge and execution of the Connection Agreement by the customer.
For connection by underground cable, SPPG will have to seek road opening approval from the relevant authorities before cable work can commence. The approval process usually takes about 3 weeks. Depending on the length of cable to be installed, supply will normally be available 4 to 6 weeks from the date customer's premises is ready to receive the service cable. Energisation of service connection will normally take place within 10 weeks of handing over of substation. This lead-time may vary from case to case, depending on the customers schedule.

31

4.9

NOTES TO BE READ IN CONJUNCTION WITH APPLICATION PROCEDURE


Licensed Electrical Worker There are three classes of LEW, namely Licensed Electrician, Licensed Electrical technician and Licensed Electrical Engineer. Licensed electrical workers of various class are licensed to design, install, repair, maintain, operate, inspect and test an electrical or supply installation in accordance with the condition stated below:
Electrical Workers Electrician Electrical Technician Electrical Engineer Approved Load of Installation Not exceeding 45kVA Design: Not exceeding 150kVA Install: Not exceeding 500kVA No limit Voltage Not exceeding 1,000V Not exceeding 1,000V Subject to licence conditions

4.9.1 4.9.1.1

4.9.1.2

The customer should appoint an LEW appropriate to the capacity and voltage of the proposed installation, and inform SPSL immediately of any change of LEW during the course of the project. Opening An Account Before supply to an installation can be turned on, the customer must open an account with SPSL. An application to open an account for electricity supply can be made either personally, through the post or Internet. A sample of the Application(s) for the Supply of Water, Electricity and /or Gas and GIRO forms to be completed are shown in Appendix 6 and Appendix 7 respectively. Application in person can be made at SPSL's Customer Services Centre, Upper First Storey, 111 Somerset Road #01-10, Singapore Power Building; or at SPSL's Application counter at Woodlands Civic Centre #02-06, 900 South Woodlands Drive, Singapore 730900. Applications through the post should be addressed to: Deputy Director (Customer Services) SP Services Ltd P O Box 341 Orchard Post Office Singapore 912312

4.9.2 4.9.2.1

4.9.2.2

4.9.2.3

The following documents must be shown at the time of application in person:

4.9.2.3.1 Identity Card/Passport of owner/tenant/authorised signatory* 4.9.2.3.2 Copy of Business/ Company Registration Certificate* 4.9.2.3.3 Documentary proof of occupation of premises, e.g. rent receipt or sales letter from HDB confirming the purchase of the premises 4.9.2.3.4 Bank account book to effect GIRO deduction from the account

32

*applicable for account in company's/organisation's name. 4.9.2.4 For applications submitted through the post, copies of the above-mentioned documents must be enclosed. An initial deposit is payable on opening an account. Customers may call the Customer Enquiry Auto-Link (U-Link) at 1800-7380038 to enquire about the opening and closing of accounts. For domestic premises, the deposits are as follows:

4.9.2.5

4.9.2.6

Type of Premises

HDB 1/ 2 rooms HDB 3/ 4/ 5 rooms HDB Executive/ HUDC/ Terrace Private Apts/ Semi-Detached/ Condo Bungalow/ Penthouse/ Townhouse
4.9.2.7

Deposit GIRO Non-GIRO Customers Customers S$ 40 S$ 60 S$ 70 S$ 100 S$ 100 S$ 150 S$ 150 S$ 250 S$ 250 S$ 400

The deposit for non-domestic premises varies according to the electricity load required, the estimated water consumption, the floor area and type of operations. For enquiry on the amount of deposit required, customers can call 1800-2222333. Handover Of Completed Substation The handover of substation to SPPG for installation of equipment is a key event, which determines the earliest date when supply can be made available. One week prior to the intended handover of the substation, the LEW must submit a Request to Handover Substation form (Appendix 5) to Deputy Director (Customer Projects - East / West / Distribution Projects), SPPG. Before this is done, the LEW must ensure that the customer/developer has accepted the terms and conditions of connection, including the payment of necessary charges. It must be emphasised that SPPG will take over the substation only when it is completed in accordance with plans and specifications approved by SPPG and the relevant authority. It is particularly important that the access to the substation must be clear and passable for transportation of heavy equipment.

4.9.3 4.9.3.1

4.9.3.2

4.9.3.3

33

4.9.3.4

Floor frames are needed for some types of switchgear. Prior to the final rendering of the switchroom floor, the LEW is to notify the project engineer-in-charge to make arrangements for the floor frame to be installed, if it is necessary. Requirements on handover of a completed transmission substation are given in General Requirements for EHT Substation (Appendix 17). Installation Of Current Transformer Operated Meters On the day the LEW arranges with SPSL for a date for energisation of the service connection, he should also bring the letter of appointment for energisation of the service connection to Meter Section to arrange for the installation of meters. On the appointed day of meter installation, the LEW or his representative must be present to provide a 230V 13A single-phase supply for testing of the meters. Procedure For Application For Licence To Use Or Operate An Electrical Installation General

4.9.3.5

4.9.4 4.9.4.1

4.9.5

4.9.5.1

4.9.5.1.1 Under The Electricity Act, electrical installations in non-domestic premises, residential buildings and condominiums with an approved load greater than 45kVA are required to be licensed. In addition, certain premises classified as engaging in dangerous trades, are also required to be licensed even though they may have approved electrical loads not exceeding 45kVA. 4.9.5.1.2 Customer is required to appoint an appropriate class of licensed electrical worker to take charge of his electrical installation and submit application for Electrical Installation licence through his appointed licensed electrical worker via EMA website at www.ema.gov.sg. The validity of the licence is for a period of 12 calendar months. 4.9.5.2 Conditions For The Issue Of The Licence

4.9.5.2.1 Conditions for the issue of the electrical installation licences are governed by EMA. 4.9.5.2.2 The minimum grade of LEW required to take charge of the electrical or supply installation is determined by the total approved load. The grades of Electrical Workers and their authorisation conferred under the respective EMA licences are shown in the table in paragraph 4.9.1.1.

34

4.9.6 4.9.6.1

Procedure For De-Energisation / Disconnection Of Service Cables De-Energisation Of Service Cable For Maintenance Purpose

4.9.6.1.1 The LEW who needs to de-energise an existing service cable for the purpose of maintenance or upgrading of the customers installation must submit the ADRE form to SPPG 7 business days in advance (Appendix 19). For Contestable Customers, an advance notice of 14 business days is required. 4.9.6.1.2 The SDRE form (Appendix 20) must be used to ensure that the service cable is safely isolated after de-energisation and fit to be energised before re-energisation. Both SPPGs officer in-charge and the LEW must duly complete and sign Part I and Part II of the form after de-energisation and before re-energisation of the service cable respectively. For Contestable Customers, the LEW must duly complete and sign Part III of the SDRE form.

35

2.

Customer's Installation Requirements

5.1
5.1.1 5.1.1.1

REQUIREMENTS FOR HT AND LT CONNECTION (22kV AND BELOW)


Short-Time Withstand Current Ratings of Switchgear For electrical installations taking electricity supply directly from SPPAs network, the customers main supply incoming switchgear must comply with the following short-time withstand current ratings:

5.1.1.1.1 For supply at 22kV - 25kA for 3 sec 5.1.1.1.2 For supply at 6.6kV - 20kA for 3 sec 5.1.1.1.3 For supply at low tension, a) Single-Phase 230V 6kA for supply capacity up to 15kVA 9kA for supply capacity more than 15kVA and up to 23kVA b) 3-Phase 400V 9kA for supply capacity up to 75kVA 25kA, 3 sec for supply capacity more than 75kVA and up to 180kVA 36kA, 3 sec for supply capacity more than 180kVA. Note: The 3-second duration is not applicable to switchgear incorporating direct acting tripping devices. 5.1.1.2 For electrical installations taking electricity supply from the landlords or management corporations electrical installations, the LEW in-charge must ensure that the customers main supply incoming switchgear is capable of withstanding the prospective short-circuit current at the connection point.

36

5.1.2 5.1.2.1

Protection Requirements Typical schemes and the protection requirements for customers HT and LT main incoming switchgear taking electricity supplies from SPPAs system are shown in Appendix 18. It must comply in general to conditions as set out in the Transmission Code, Section 6.3 and Appendix F3. For electrical installations taking electricity supply from the landlords or management corporations electrical installations, advice on protection requirements must be sought from the LEW responsible for the respective licensed electrical installation. Protection Requirement For 22kV Customer Connection The main protection for the 22kV customer connection must be pilot wire differential protection. The current transformers of ratio 500/5 must be of Class X and the CT secondary star-point must be towards the protected line. The standard overcurrent/earth fault setting for the incomer is shown in Appendix 18.

5.1.2.2

5.1.2.3

5.1.2.3.1

To effect fast fault clearence, the 22KV cable terminations and metering CTs/VTs installed at the incomers must be included in the 'Protected Zone' of the cable's Unit Protection, as shown in Appendix 18. The LEW of the customer installation is responsible for:

5.1.2.3.2 5.1.2.3.3 5.1.2.4

proper specification, setting / commissioning of the protection system at the customer incomers, and ensuring that the 22kV circuits within the customer installation are equipped with unit protection for fast fault clearance, inclusive of fault at cable terminations. Protection Requirement For LT Supply Connection The customers incoming circuit breaker shall be set according to the approved load. For approved load exceeding 300A, external overcurrent relays of IDMTL or DTL characteristics and earth fault protection (DTL) must be provided at the incoming switchgear. The current transformer must be of Class 5P10, 15VA or better. Details are shown in Appendix 18.

5.1.2.5

Every low tension electrical installation of supply capacity exceeding 75kVA must be provided with short-circuit protection in the form of direct acting trip element at the incoming switchgear as follows: Approved Load Above 1500A 400A< Approved Load < 1500A 260A < Approved Load < 400A 200A < Approved Load < 260A 200A and below Direct Acting Trip Setting Up to 4500A Up to 3200A Up to 2400A Up to 2000A Up to 1200A

Alternatively, a backup HRC fuse may be used in place of direct acting trip.

37

5.2
5.2.1

REQUIREMENTS FOR EHT CONNECTION (230kV and 66kV)


Short-Time Withstand Current Ratings Of Switchgear For electrical installations taking electricity supply directly from SPPAs network, the customers main supply incoming switchgear must comply with the following short-time withstand current ratings:

5.2.1.1

For 230kV Switchgear 63kA (1 sec) For 66kV Switchgear 40kA (3 sec) Protection Requirement For 66kV and 230kV Customer Connection General

5.2.1.2

5.2.2 5.2.2.1

5.2.2.1.1 The protection system for the connections has to comply in general to the conditions as set out in the Transmission Code. 5.2.2.1.2 All circuits connected to SPPAs transmission network, inclusive of busbars for 230kV and above, must be provided with unit protection for fast fault clearance. 5.2.2.1.3 Engineering details and protection settings will be discussed with the customer during the project implementation. 5.2.2.1.4 The relays used for a unit protection scheme, and the characteristics of its associated current transformers should be matched. For reason of obsolescence or availability, the type of protection relays, signaling equipment and the protection schemes is subject to review and confirmation during the consultation period. 5.2.2.1.5 Wherever applicable, protection signaling equipment is to be provided for teleprotection function and for end-to-end transfer of intertrip and interlock signals. 5.2.2.1.6 Generally, the star-point of the current transformer secondary circuit must be towards the protected object / zone. 5.2.2.1.7 Generally, the location of the current transformers for the circuit and that of the installations busbar protection system for 230kV and above must be overlapped across the circuit breaker to eliminate protection blind zone. 5.2.2.1.8 Current transformers supplied for unit protection must be rated in accordance with IEC 60044 Part 1 & 6, BS 3938. They must be adequately dimensioned and of an accuracy class meeting the specified relays requirement. The characteristic of the current transformers installed at both ends of the connected circuit must be closely matched with each other to ensure stability.

38

5.2.2.1.9 The LEW of the customer's installation is responsible for the proper specification, setting/commissioning of the protection system at the customer 230KV or 66KV incomers. 5.2.2.2 The proposed settings for the backup protection for the 66KV customer incomer must generally be as follows:

PROPOSED RELAY SETTING FOR 66kV CUSTOMER INCOMER Protection Relay Over Current Protection (IDMTL) Feeder Circuit Feeder Transformer Circuit (for 75MVA transformer) Earth Fault Protection (IDMTL) Feeder Circuit Feeder Transformer Circuit (for 75MVA transformer) General Setting Setting 150% 0.15 200% 0.15 100% 0.20 Hi-Set: 27A 125% 0.16 Hi-Set: 34A 10% 0.10 15% 0.10

CT Ratio (1000/5) (800/5) (1000/5) (800/5) (1000/5) (800/5) N/A

Notes: The coordinated setting for the backup protection is applicable to the standard protection scheme proposed for a feeder or feeder-transformer type customer connection and is applicable to radial feed connection only. (Refer to Appendix 18) The overcurrent and earth fault setting are subjected to periodic review by SPPG.

5.3

INFORMATION ON SPPA NETWORK EARTHING SYSTEM (230KV, 66kV and 22kV)


Where customer is connected directly to SPPAs network, customer shall note the following earthing system at each voltage level. 230kV Solidly earthed system. 66kV Resistive earthed system with neutral ground resistor (NGR) of 19.5 ohms. 22kV Resistive earthed system with neutral ground resistor (NGR) of 6.5 ohms. Customer shall ensure that all equipment including CTs, VTs, and protection systems connected to SPPA network meet the technical specification required for the respective earthing system in accordance with the relevant standards.

5.3.1

5.3.1.1

5.3.1.2

5.3.1.3

5.3.2

39

2.

Metering Requirements

6.1
6.1.1

General
All metering requirements must comply with EMAs Metering Code. SPPG will determine the location where the supply line terminates in the premises, based on ease of accessibility to SPSL and SPPG personnel. The developer or customer bears the cost of providing and maintaining the meter boards, miniature circuit breakers (MCBs), isolators and wiring for installation of meters. The meters are supplied and maintained by SPPA. Meters can be mounted on any of the following types of meter boards: Teak board or any hardwood board chemically treated against attacks by termites. Plywood should not be used. The meter board must be at least 20mm thick and rigidly fixed with a minimum of 4 fixing screws. Metal panel with nylon inserts accurately positioned to accommodate the meter. Glass reinforced polyester base fitted with nylon inserts accurately positioned to accommodate the meter. If item 6.1.3.2 or 6.1.3.3 is provided, SPPGs Meter Section has to be consulted on the locations of the nylon inserts.

6.1.2

6.1.3 6.1.3.1

6.1.3.2 6.1.3.3

6.1.4

The LEW must ensure that all metering requirements are complied with, and submit, at the planning stage, all relevant drawings on meter locations, meter board size, meter rooms, meter compartments/riser ducts/ cupboard, etc to Meter Section for approval. Sample units of each approved type of meter compartment / riser duct / cupboard and meter board must be provided for final inspection and approval by Meter Section before meters are installed.

6.1.5

If the doors of centralised meter rooms, meter gate posts, meter compartments/ riser ducts/ cupboards, etc are to be locked, they must be fitted with locksets which can be opened with one of the following master keys: 40

6.1.5.4 6.1.5.5 6.1.5.6

Abloy master key code reference MK 911047 Chubb (Union) master key code reference G1HBG Yale master key code reference MK48 The doors of meter rooms/compartments must be able to be opened from the inside without the need to use a key or other devices/tools.

6.1.6

All access doors to meter rooms/compartments/riser ducts/cupboards, etc must have a clear access opening of at least 600mm (width). The doors must be fitted with doorknobs or handles. Security access systems installed in any premises must not impede access by SPSL and SPPG personnel.

6.1.7

6.2
6.2.1 6.2.1.1

LOCATION OF METER
General The service board accommodating SPPA's service MCBs and meters must be located near the termination of the service line. The meter/service position must be easily accessible at all times to SPSL and SPPG personnel for maintenance and reading of meters. Meters must be installed in a safe location where they will not be damaged or be a cause of danger to personnel (viz, in a clean and dry location, not exposed to weather, mechanical damage, vibrations, extremes of temperature or dampness). The height of the meter on the meter board must be between 1.0m and 1.8m above ground level, and the depth of the compartment for installation of meters must be between 200mm and 300mm. It is advisable that the service board is housed in an approved box of noncombustible high-impact material to give added protection to the metering equipment and safety.

6.2.1.2

6.2.1.3

6.2.2

Grouping of Meters Meters must be installed outside each tenant unit for ease of meter reading, maintenance, etc. Where this is not possible for practical reasons, meters may be grouped together in easily accessible centralised meter rooms or meter compartments/riser ducts/cupboards in multi-metered premises (e.g., residential, office, shopping or industrial high-rise building/complex).

41

6.2.3 6.2.3.1 6.2.3.2 6.2.3.3

Meters in Meter Compartments / Riser Ducts / Cupboards Meters are to be grouped on the same floor as the tenant units. There may be more than one group metering location on each floor. There must be adequate lighting in the group meter location to facilitate meter installation/maintenance and meter reading. Meter boards in meter compartments/riser ducts/cupboards must be such that meters can be mounted facing the doors. All meter compartments/riser ducts/cupboards where meters are installed are to be clearly and permanently labeled. Tenant unit numbers on permanent labels must be fixed adjacent to their respective meters. Meter compartments/riser ducts/cupboards housing the meters must have clear glass windows provided on the doors, if these are locked, for ease of meter reading. The window for each meter must not be less than 200mm (W) x 300mm (H) x 6mm (thickness) and must be correctly positioned in front of where the meter is to be installed. Plastic windows and UV resistant polycarbonates are not acceptable. Full glass doors are not acceptable. Meters in Centralised Meter Rooms The height of the meter board or panel must be such that meters can be mounted with the highest row not exceeding 1.8m above floor level and the lowest row not less than 1m above floor level. There must be standing space of at least 700mm in front of the meter panel. However, if the meters are mounted on a free-standing panel, a clearance of 700mm all round the panel is required. The meter board or panel must be rigidly and vertically mounted. The doors of the panel must be hinged. The meter room must not be used as a storeroom. Meters Installed in Landed Properties The meters and service cables must be installed in a weatherproof compartment located at the gate pillar or perimeter wall. For supply capacity up to 100A 3 phase, the technical requirements for this compartment are as given in Appendix 24. For supply capacity greater than 100A 3-phase where a CT-operated meter will be installed, the LEW has to submit the technical requirements to Meter Section for approval.

6.2.3.4

6.2.3.5

6.2.3.6

6.2.4 6.2.4.1

6.2.4.2

6.2.4.3

6.2.4.4 6.2.5 6.2.5.1

6.2.5.2

If there is no gate pillar or fencing around the perimeter of the landed properties, 42

meters must be installed inside a weatherproof meter box/compartment and easily accessible to SPSL and SPPG personnel. Meters must not be installed inside the house.

6.3

METER/SERVICE BOARD SPECIFICATIONS (SINGLE-PHASE AND 3PHASE SERVICES, NOT EXCEEDING 100A PER PHASE)
The meter/service board for SPPA's service MCBs and meters must be as specified in Section 6.1.3 and in accordance with the drawings in Appendices 25, 26 and 27.

6.4

WIRING, LAYOUT OF METERS, MCBs, ETC IN CENTRALISED METER ROOMS, METER COMPARTMENTS/RISER DUCTS/CUPBOARDS
All wiring leading in and out of the group meter location must comply with SS CP5. The landlord's wiring must be segregated from the tenant's wiring. Meters are to be mounted together with their associated service MCBs / neutral connectors such that each meter can be visually identified with its associated service MCBs. Each meter position must be clearly labeled according to the tenant unit number. There should be a space of 70mm between vertically mounted meters. Meters are to be mounted in neat vertical columns and/or horizontal rows. Service MCBs shall be sealable. MCBs must be clearly labeled according to the tenant units served. The labeling must also correspond to the labels used for the meters. All wiring on the meter boards from service MCBs / neutral connectors to the meters and from the meters to the customer's main switches must be neatly run on the surface - horizontally and/or vertically.

6.4.1

6.4.2

6.4.3 6.4.4

6.4.5

6.5

SUBMISSION OF LAYOUT PLANS


The layout of the meter rooms, meter compartments/riser ducts/cupboards together with the meter board drawings and plans of the units served, must be submitted at the planning stage by the LEW for approval by Meter Section.

6.6

METERS FOR 3-PHASE LOW TENSION CONNECTION (EXCEEDING 100A PER PHASE)
Meters for connections exceeding 100A per phase are operated from metering current transformers and are to be fixed on a pre-wired metering panel on the customers main switchboard. However, where the length of the connecting leads are not excessive, the pre-wired metering panel may, with the prior approval of Meter Section, be wall-mounted away from the main switchboard or in a separate meter room. The pre-wired metering panel with Meter Section approved type test block, 6A (10kA) MCB, pilot lights and metering cables to the busbars and the three metering current transformers, must be provided by the customer. Drawings 43

6.6.1

of the pre-wired meter panel can be obtained from Meter Section at St James District Office, Telok Blangah Road. 6.6.2 6.6.2.1 Meter Panel Compartment Specifications Meter panels must be of mild steel of at least 1.6mm thickness or other materials subject to approval by Meter Section The panels must be detachable and of a size given in Appendix 28. The compartments must have a minimum depth of 100mm between cover and base. There must be openings with appropriate bushing for the meter wires. The cover must have at least 3 hinges and be able to swing and open out at least 90o. Facilities for sealing must be provided. Methods of sealing are illustrated in the drawings in Appendix 29. Meter Installation Requirements The switchboard must be complete and securely mounted in its final position before meters can be installed. The top of the meter panel must not exceed 2.0m from the ground. A 50mm x 50mm trunking of metal or other approved material between the switchboard and the meter panel must be provided to house the meter cables if the latter is installed away from the customers main switchboard. A 6.0mm tap-hole plus screw/washer on each busbar must be provided to facilitate connection of the voltage cables to the meter voltage coils. If the meter panel is away from the customers main switchboard, sealable 30A HRC fuse for each phase and a sealable 3-pole ganged MCB of 6A 10kA rating must be provided on the front of the switchboard panel near the metering CT enclosure for the protection of the meter voltage wiring. The MCB must be appropriately labeled. Mounting of metering current transformers must be as follows: Current transformers must be mounted on jumpers for easy installation. Bakelite clamps must be provided to secure the meter current transformers in position. Adequate insulation between the metering current transformers and the busbar must be provided. The metering current transformers and meter voltage tap off points must be installed after the incoming connection main protection current transformers. 44

6.6.2.2 6.6.2.3

6.6.2.4 6.6.2.5

6.6.2.6

6.6.3 6.6.3.1

6.6.3.2 6.6.3.3

6.6.3.4

6.6.3.5

6.6.3.6

6.6.3.7

Enclosure A rigid enclosure of mild steel plate of thickness not less than 1.6mm must be provided solely for housing the metering current transformers and voltage tap off points. The enclosures must have facilities for sealing. A typical construction of the enclosure is shown in Appendix 30.

6.7
6.7.1 6.7.1.1

HIGH TENSION / EXTRA-HIGH TENSION METERING


General Requirements The customer is required to provide, install and maintain, at his own expense, current transformers, voltage transformers, a pre-wired metering panel with test blocks, MCBs, pilot lamps and accessories, at his receiving HT switchboard. These must meet SPPAs requirements. Drawings of the pre-wired metering panel can be obtained from Meter Section at St James District Office, Telok Blangah Road. All metering current and voltage transformers must be used solely for SPPA's revenue metering equipment. No other apparatus of the customer is permitted to be connected to such metering current and voltage transformers. However, a voltmeter may be allowed to be connected via a 100 mA fuse (sealable) subject to approval by Meter Section. The customer must also provide a metering kiosk to be located close to where the metering current and voltage transformers are installed, such that the route length of the cables from the current and voltage transformers to the metering kiosk does not exceed 20m. Where this cannot be complied with because of site constraints, the LEW must consult Meter Section concerning the type and size of cables to be provided and installed by the customer. The requirements for the kiosk are given in Appendices 31 and 32. The access to the metering kiosk must be from outside the HT switchroom and fitted with any one of SPPA's approved master lock series as specified in Section 6.1.5. The customer must provide an appropriate metering panel of a size given in Appendix 33 and install a 50mm x 50mm trunking of metal or other approved material between the customers HT switchboard and the metering panel together with the required type and size of cables. Facilities for sealing connections of all metering wire termination at the customer's HT switchboard must be provided. A schematic and wiring diagram of the customers switchboard must be supplied to facilitate installation of the meters. Specifications For Metering Current Transformers The customer will provide two metering current transformers of 30VA burden for 66kV connection or 15VA burden for connection at 6.6kV or 22kV. These must be of accuracy class 0.5 complying with SS 318 or IEC 60044-1. 45

6.7.1.2

6.7.1.3

6.7.1.4

6.7.1.5

6.7.1.6

6.7.1.7

6.7.2 6.7.2.1

6.7.2.2

The current transformers are to be installed on the red and blue phases at the cable end for each of his receiving switchboard. The current transformer ratio will be determined by SPPG based on the customers load requirement. For connection at 230kV, the LEW will liaise with Meter Section on metering requirements. The rated short-time current rating must not be less than 63kA 1 second, 40kA 3 seconds, 25kA 3 seconds and 20kA 3 seconds for connection at 230kV, 66kV, 22kV and 6.6kV respectively. Specifications for Voltage Transformers For each of the customers receiving switchboard, one of the following voltage transformers must be provided:

6.7.2.3

6.7.3 6.7.3.1

6.7.3.1.1 One unit 3-phase 66kV/110V, 22kV/110V or 6.6kV/110V voltage transformer of 100VA burden per phase, connected star-star with the yellow phase terminal of the secondary winding earthed, or 6.7.3.1.2 Three units single phase, 66kV 110V or 22kV 110V or 6.6kV 110V

Voltage transformers of 100VA burden per phase, connected star-star with the yellow phase terminal of the secondary winding earthed. 6.7.3.1.3 Voltage transformers must be of accuracy class 1.0 complying with BS3941 or IEC 60186. 6.7.3.1.4 The secondary wiring of the voltage transformer must terminate in a sealable MCB incorporated in the switchgear panel. The MCB must be rated at 6A, 110V, 50Hz with breaking capacity not less than 10kA and the terminals of the MCB must be able to accept cables of cross section up to 6mm2. 6.7.3.1.5 The voltage transformers must be fused and adequate stock of spare high-voltage fuses must be kept by the customer.

6.8
6.8.1

TESTING OF METERING CTs AND VTs


All metering current transformers and voltage transformers together with their manufacturers' test certificates must be submitted for testing and approval by Meter Section at least 2 weeks before connection is required. Voltage transformers at 66kV and 230kV are exempted from testing and only the manufacturers test certificates have to be submitted. The metering VTs, after re-installation onto customers switchgear, have to be tested and phase out, and a test report as per Appendix 34 have to be submitted to Meter Section for approval before installation of meters. 46

6.8.2

6.9
6.9.1 6.9.1.1

METERING REQUIREMENTS
Low Tension Customer Single Customer - More Than 75kVA

6.9.1.1.1 The customer will provide three metering current transformers (CTs) of 5VA burden and accuracy class 0.5 complying with SS 318 or IEC 60044-1 and the pre-wired metering panels on the customers intake switchboard. The pre-wired metering panel must be fitted with SPPA approved type test block, MCB and pilot lights and connected with metering cables to the CTs and busbars. The CTs together with their manufacturers test certificates must be submitted for testing and approval at least 2 weeks before connection is required. 6.9.1.1.2 A request for appointment to fix meters should be made only after the LEW has arranged with SPSL for a date to energise the service connection. 6.9.1.1.3 Meter Section will arrange to install the meters upon production of the energisation appointment letter issued by SPSL and requires at least 4 business days before the energisation of service connection date. 6.9.1.2 Multi-Metered Buildings

6.9.1.2.1 Submission of floor plans of building showing the locations of metering kiosks, meter room, meter compartments/riser ducts/cupboards. 6.9.1.2.2 Submission of dimensioned metering layout showing the plan, front and side elevations of the meter boards/rooms/compartments/riser ducts/cupboards, etc. 6.9.1.2.3 Arrangements for sample units of each approved type of meter compartment/riser duct/cupboard and meter board to be inspected and approved by Meter Section before meters are installed. 6.9.1.3 Landed Housing Development

6.9.1.3.1 Submission of site plans of building showing the locations of meter compartments at gate pillars. 6.9.1.3.2 Submission of dimensioned metering layout showing the plan, front and side elevations of the meter compartments in the gate pillars. 6.9.1.3.3 Arrangement for sample units of each approved type of meter compartment and meter board to be inspected and approved by Meter Section before meters are installed. 6.9.2 6.9.2.1 High Tension / Extra-High Tension Customer The revenue metering equipment will be installed at the customers end of the service connection. The customer will provide a suitable metering kiosk at his intake station, and metering CTs and VTs for each of his receiving 47

switchboard. The metering CTs ratio will be based on declared demand as shown in Section 6.9.2.4. 6.9.2.2 The customer will provide and maintain at its own cost, a fixed telephone line to the metering kiosk to be used exclusively for the purpose of remote meter reading. This telephone line must be terminated in a standard telephone socket at the metering kiosk. Provision of this telephone line must be made before installation of meters. If the customer is unable to provide the fixed telephone line due to site constraint, a GSM line can be considered subject to approval by Meter Section. Based on the contracted capacity stated in the application form, the customer is required to provide the correct metering CTs as follows:

6.9.2.3

6.9.2.4

Contracted Capacity MW 22kV Service Connection 0.0-0.8 0.81-1.7 1.71-2.5 2.51-3.2 3.21-5.0 5.01-6.6 6.61-10.0 0.0-5.0 5.01-10.0 10.01-20.0 20.01-30.0 30.01-40.0 40.01-80.0

CT Ratio

66kV Service Connection

50/25/5 100/50/5 150/75/5 200/100/5 300/150/5 400/200/5 500/300/5 100/50/5 200/100/5 400/200/5 500/300/5 800/400/5 1000/500/5

6.10
6.10.1

CONTESTABLE CUSTOMERS
Eligibility The eligibility of contestable customers is determined by EMA.

6.10.2

Additional Requirements For Contestable Customers A contestable customer must provide and maintain at its own cost a fixed telephone line to be used exclusively for the purpose of remote meter reading. The LEW must liaise with Meter Section for the location and termination of this telephone line.

48

Appendices

49

APPLICATION FORM FOR CONNECTION TO THE TRANSMISSION SYSTEM


To : SP Services Ltd 111 Somerset Road #01-10 Singapore 238164

For official use only Application Number : Date Received :

PART 1

APPLICANTS DETAILS

All connections with Distributed Generation (e.g. PV system) are required to submit this application.
I request you to provide/upgrade the load connection service to my premises as given in Part 2 by my Licensed Electrical Worker undertaking the project

Name of Company/Applicant * : ______________________________________________ ROC/NRIC No. : __________________ Name of Authorised Person & Designation * : ___________________________________________________________________ Forwarding Address: __________________________________________________ Postal Code: Singapore ______________ Tel: _________________ Fax: __________________ Mobile Phone: ___________________ Pager: __________________ Email: _________________________ Signature of Applicant: _______________________________ Date: _______________

PART 2

INSTALLATION DETAILS (To be completed by LEW)

Project Description: _______________________________________________________________________________________ Site Address: ________________________________________________________ Postal Code Singapore ______________ Utility Account No. (existing): _____________________________ Existing Approved Load: _____________________ kVA/kW * Any previous Consultation? Yes / No* If Yes, please provide Consultation No.: _____________________

TYPE OF CONNECTION (Please tick the appropriate boxes)


New Connection Temporary Connection Replacement of switchboard (no load upgrading) [ same / different switchroom * ]

New Connection with Distributed Generation (Please specify): ____________________________________________________________ Existing Connection with Distributed Generation (Please specify): __________________________________________________________ Upgrading the existing connection point Others (Please specify) : Change of intake connection point (involving new switchroom) Re-energise existing connection

____________________________________________________________________________________________

TYPE OF DEVELOPMENT (Please tick the appropriate boxes)


Industrial Commercial Residential Renewable Energy

Others (Please specify) : __________________________________________________________________________________ Type of Business Activity (Brief Description) : _________________________________________ Voltage Dip Sensitive? Yes / No *

LOAD REQUIREMENT (One intake connection point per premises)


Total load requirement (to include existing load, if any) 30A/60A/100A* 230V single-phase 22kV
(min. 1,700kW for 2 HV services, min. 12,751kW for 4 HV services)

30A/60A/100A* 400V three-phase

__________ kVA at 400V three-phase 66kV/230kV*


(min. 25.5MW for 66kV, min. 85MW for 230kV)

SINGLE USER PREMISES (HIGH TENSION / EXTRA HIGH TENSION) Total Contracted Capacity of ________________ kW at ____________________ kV via __________ service cable(s). Initial Contracted Capacity of ______________ kW (shall not be less than of the Contracted Capacity) for _________ months (not exceeding 12 months)

13/11/08

MULTI-TENANTED / MULTI-TENANTED MASTER-SUB PREMISES (HIGH TENSION / EXTRA HIGH TENSION) Total Contracted Capacity of ________________ kW at ____________________ kV via __________ service cable(s). Landlords Contracted Capacity (minimum 1,700kW) : ______________________ kW Initial Landlords Contracted Capacity: ______________ kW (shall not be less than of the Landlords Contracted Capacity) for _________ months (not exceeding 12 months) Target date of Energisation : ________/_________/___________ Estimated ultimate load : ___________________ kVA/kW*

(Please refer to expected lead time in handbook. For service costing job, supply will normally be available 4 to 6 weeks from the date customer switchboard/meterboard and cable entry pipes of your premises is ready to receive the service cable. For major work where substation is involved, you shall handover the substation building 10 weeks before the target date of energisation.)

TYPE OF PREMISES (Please tick the appropriate box)


Single user premises Multi-tenanted premises Multi-tenanted Master-sub premises
Estimated Landlord Load __________ kVA/kW* For multi-tenanted installation with the exception of HDB residential installation, the metering scheme shall be designed as Master/Sub-metering scheme.

TYPE OF METERING SCHEME


Please specify the metering scheme: Master / Normal*
(For master metering scheme, the common services load must be at least 10% of the total load for the premises.)

Any change in metering scheme? Yes / No*. If yes, please specify _________________________________________________

TO BE COMPLETED FOR INSTALLATION EXCEEDING 45kVA


Total Land Area: ___________________________ m2 Gross Floor Area: ______________________________ m2

PLANS AND DETAILS (Mandatory)


2 copies of Architects site and location plan Substation Land Ownership: SLA / URA / HDB / JTC / Private / Others*, please specify: _____________________ 2 copies of plan showing proposed customers intake connection point and the existing intake point (if applicable) Details of the type, floor area & designed load of individual premises for multi-metered premises 1 copy of Fault Level Report (distributed generation and applicants with large motors only)

PART 3

LEW DETAILS

I confirm that the above information is correct and agree to advise SP Services should there be subsequent changes.

Name of Authorised LEW: ______________________________________ License Number:______________________________ Registered Forwarding Address: ______________________________________________________________________________ ______________________________________________________________________ Postal Code: Singapore ______________ Tel: _________________ Fax: __________________ Mobile Phone: ___________________ Pager: __________________ Email: ___________________________________________________________________________________________________

Signature of Authorised LEW: _____________________________________________________ Date: _____________________

PART 4

QUALIFIED ELECTRICAL CONTRACTOR (QEC) DETAILS (if applicable)

Name of Authorised QEC: ______________________________________ License Number:______________________________ * Delete where not applicable
13/11/08

Appendix 2
CONSULTATION FORM FOR CONNECTION TO THE TRANSMISSION SYSTEM To : SP PowerGrid Ltd 111 Somerset Road #08-05 Singapore Power Building Singapore 238164 CONSULTATION DETAILS
Sub-metered consumers (tenants) are not eligible for this application. All tenants in multi-metered premises are required to obtain supply from their landlord/MCST or HDB for HDB premises. Reference to the consultation, I hereby enclose one copy of site & location plans including proposed customers intake connection point Drawing No. ____________________________________________________________ for your advice on connection requirements.

For official use only Consultation Number. : Date Received :

SITE DETAILS
Connection Applicant/Developer* : _____________________________________________________________________________ Project Description : Site Location Lot & Mk No : _____________________________________________________________________________ _____________________________________________________________________________

Street Name : __________________________________________________________ Blk/Unit No :_______________________

LOAD REQUIREMENT (One intake connection point per premises)


New Connection Change of intake connection point Upgrading the existing service cable Temporary Connection

Other Services (Please specify):________________________________________

Type of Premises : Industrial/Commercial/Residential/Others*_________________________Gross Floor Area(m2): _____________ Type of Business Activity (for non-residential premise only) : _______________________________ Existing Utility A/C No.(if any) : ________________________________ Existing Approved Load (kVA) : ________________________________ at 230V/400V/22kV/66kV/230kV* Load Requirement (kVA) : ____________________________________ at 230V/400V/22kV/66kV/230kV* Target date of Energisation :__________/___________/__________ Previous consultation No. (if any) : _________________ Additional information : ______________________________________________________________________________________ ______________________________________________________________________________________ Voltage Sensitive? Yes / No *

LEW DETAILS I confirm that the above information is correct and agree to advise SP PowerGrid should there be subsequent changes.
Name of Authorised LEW : _____________________________________ Licence Number:_______________________________

Company Forwarding Address :________________________________________________________________________________ ___________________________________________________________ Postal Code : Singapore __________________________ Tel : ______________________ Fax : __________________ Mobile Phone : _____________________ Pager : _______________ Email : ___________________________________________________________________________________________________

Signature of Authorised LEW ______________________________________________________ Date ______________________

* Delete where not applicable

52

Appendix 3
Form CS/3 Letter of Consent from the Landlord/Management Corporation
To: SP Services Ltd 111 Somerset Road #06-05 Singapore Power Building Singapore 238164

ELECTRICITY SUPPLY TO :______________________________________________________________________ (Full Address of the Customer) FOR :________________________________________________________________________________________ (Name of Customer) TOTAL LOAD ALLOWED FOR: _______________________________ AT ___________________________ VOLTS _____________________________________________________________________________________________ PART I 1. I have checked the loading of the electrical installation of the abovementioned building/complex and hereby confirm that the abovementioned load requirement can be catered for from the rising/horizontal mains system/main switchboard of the building/complex, and the total approved load to the entire building/complex will not be exceeded. I have no objection for the abovementioned load to be connected to the rising/horizontal mains system/main switchboard of the building/complex. The Electrical Installation Licence No. of the building/complex is ______________________. The electrical installation of the building/complex from which this load is to be connected is Unmetered (i.e. without Master Account) Metered under Master Account No. ________________________. 5. I will check to ensure that the abovementioned installation is compatible with the electrical installation of the building/complex. Date: ______________ Tel No: __________________

2. 3. 4.

_____________________________________ Signature of Licensed Electrical Worker Licence No: _____/___________ Name: ______________________________________

Address: _____________________________________________________________________S (______________) _____________________________________________________________________________________________ PART II I hereby give consent for the abovementioned customer to tap electricity supply of a capacity indicated above from the rising/horizontal mains system/main switchboard of the building/complex. ___________________________________ Signature of authorised person __________________________________________ Name Official Stamp of the landlord/developer/management corporation Date: ________________ ________________________ Designation

53

Appendix 4
FORM CS/3H Letter of Consent from Housing & Development Board
To: SP Services Ltd 111 Somerset Road #06-05 Singapore Power Building Singapore 238164

ELECTRICITY SUPPLY TO :______________________________________________________________________ (Full Address of the Customer) FOR : ________________________________________________________________________________________ (Name of Customer) TOTAL LOAD ALLOWED FOR: ________________________________ AT _________________________ VOLTS _____________________________________________________________________________________________ PART I 1. I have checked the loading of the electrical installation of the above-mentioned building/complex and hereby confirm that the above-mentioned load requirement can be catered for from the rising/horizontal mains system/main switchboard of the building/complex, and the total approved load to the entire building/complex will not be exceeded. I have no objection for the above-mentioned load to be connected to the rising/horizontal mains system/main switchboard of the building/complex. The Electrical Installation Licence No. of the building/complex is ___________________________. The electrical installation of the building/complex from which this load is to be connected is Unmetered (i.e. without Master Account)

2. 3. 4.

Metered under Master Account No. _________________________________. 5. I will check to ensure that the above-mentioned installation is compatible with the electrical installation of the building/complex.

________________________________ Signature of LEW Licence No.: ______________________________________ Name: __________________________________________

Date: _______________________

Tel No.: _____________________

Address: _____________________________________________________________________________________ _____________________________________________________________________________________________ PART II I hereby give consent for the above-mentioned customer to tap electricity supply of a capacity indicated above from the rising/horizontal mains system/main switchboard of the building/complex. ________________________________ Signature of Authorised Person For and on behalf of Housing & Development Board ________________________________ Name Official Stamp of the Landlord/Developer/Management Corporation Date: _______________________

____________________________ Designation

54

Appendix 5
Request to Handover Substation
Date: To: SP PowerGrid Ltd 111 Somerset Road #08-05 Singapore Power Building Singapore 238164 Attn: Deputy Director (Customer Projects East / West / Distribution Projects) Dear Sir PROJECT: ELECTRICITY SUPPLY TO ________________________________________________________________________ 1. In connection with the electrification scheme (SPSL Appln No: ________________), I wish to advise that the proposed SPPA substation has been completed in accordance with plans and specifications approved by your Company and the Competent Authority. 2. I confirm that the structural Professional Engineer in-charge has certified that the substation structure is constructed according to the approved plan to withstand the load specified by your Company. 3. I also certify that the electrical installation at the substation has been inspected and tested in accordance with the requirements of your Company as follows: a b c d e f g h 4. Earth value of electrode system is ______________ ohms. The continuity of each circuit protective conductor is satisfactory. All metal conduits have been bonded to earth. Polarity throughout the installation is correct. All single pole control devices are in live conductors only. The insulation resistance of the fixed wiring installation is ___________ Megaohm. All flexible cords, switches, fuses, plugs and socket outlets are in good serviceable condition. The installation includes ______________ Nos lighting points and _______________ Nos socket outlets.

I shall be obliged if you could send your representative for a joint site inspection on _____________________, and thereafter to takeover the said substation.

Yours faithfully

_______________________________ Signature of Licensed Electrical Worker Name: _______________________________________________________________________________________________

Address: _______________________________________________________________________________________________ Tel No: _______________________

NB:

This form must be submitted one week prior to the date for joint site inspection, which shall normally take place from 10 am to 12 noon.

55

Appendix 6

56

Appendix 7
APPLICATION FOR INTERBANK GIRO
Please tick: New Application Change of Bank Account

PART 1: FOR APPLICANTS COMPLETION


Date: Name of SP Services Customer

To: Name of Bank:

SP Services Account Number (1 account per form)

Branch

(a)

I/We hereby instruct you to process SP Services instructions to debit my/our account. You may also at your discretion allow the debit even if this results in an overdraft on the account and impose charges accordingly.

(b) You are entitled to reject SP Services debit instructions if my/our account does not have sufficient funds and charge me/us a fee for this. (c) This authorisation will remain in force until termination by written notice sent to my/our address last known to you or upon receipt of
my/our revocation through SP Services. My/Our Name(s) As in Bank Account: My/Our Bank Account No: Bank Account Holder NRIC No/ P/P No: My/Our Contact (Tel/Pager/Handphone) No(s)

Please remember to sign in this box. Please impress your thumbprint clearly if your bank account is operated by thumbprint.

My/Our Signature(s)/Thumbprint(s)/Company Stamp (as in banks records)

PART 2: FOR SP SERVICESS COMPLETION


Bank Branch

SP Servicess Account Number

Utilities Account Number

Bank

Branch

Account Number To Be Debited

PART 3: FOR BANK/FINANCIAL INSTITUTIONS COMPLETION


To: SP Services Ltd This application is hereby REJECTED (Please tick) for the following reason(s): Signature / Thumbprint # differs from Financial institutions records Signature / Thumbprint# incomplete / unclear# Account operated by signature / thumbprint# ___________________________________ Name of Approving Officer ___________________________ Authorised Signature Wrong account number Amendment not countersigned by customer Others:______________________________ _____________________________ Date # Please delete where inapplicable Co. Registration. : 199504470N

57

Appendix 8
FORM CS/5 APPLICATION FOR INSPECTION OF ELECTRICAL INSTALLATION For official use To: SP Services Ltd 111Somerset Road #06-05 Singapore Power Building Singapore 238164 APPLICATION NO:

PART I I/We, #Mr/Mrs/Miss/Messrs____________________________________________________________________________________


(# Delete as appropriate). (name of applicant/company)

Utility Account No : ___________________________________________________________________________________________ request you to provide an electrical installation inspection and install Details of my/our application are as follows: (Please fill in the appropriate box below) An application for electricity supply service has been submitted earlier and approved. SP Services Application Reference No is: _______________________________________ OR This is a new application with details as given in Part II by my/our Licensed Electrical Worker undertaking the project. (Form CS/3 or CS/3H shall be attached for supply connection from landlords or HDBs electrical installation.) My/Our particulars: NRIC number/Company ROC number: ________________________________ Name of Authorised Person for Company:_________________________________________________________________
(if applicable)

kWh meter. (Please tick if meter is required)

Forwarding Address: _________________________________________________________________________________ ________________________________________________________Postal Code: ______________ Tel:___________________ Fax : ___________________ Mobile phone: ___________________ Pager:_____________ Email: ____________________________

---------------------------------------------------------------------------------------------Signature of Applicant Date ___________________________________________________________________________________________________________


PART II (INSTALLATION DETAILS - To be completed by Licensed Electrical Worker if there is no application submitted earlier)

Project Description: ________________________________________________________________________________________ Site Address: ___________________________________________________________________Postal Code: ________________ Type of Application (Please tick the appropriate boxes) New Supply Extension Amalgamation Temporary Supply Rewiring Shifting of Meter Upgrading of Supply Downgrading of Supply

Replacement of switchboard/switchgear

Conversion to Master/Sub Metering Scheme Other Services (Please specify)

58

Appendix 8
Supply Connection from: SP PowerAssets installation/mains Landlords installation (Form CS/3 is to be submitted) HDBs installation (HDB's endorsement is required) Public Lighting Network (Form CS/3 PL is to be submitted)

Type of Development:

Industrial

Commercial

Residential

Others

Metering Scheme: *Master / Sub / Normal *(Delete as appropriate) Type of Business (Brief Description): ___________________________________________________________________ Total supply capacity (including existing requirement, if any) 30/40A# 230V single-phase (# Delete as appropriate) 60A/80A/100A# 230V single-phase 30A/60A# 400V three-phase .............kVA at 400V three-phase

PART III DETAILS OF PROPOSED INSTALLATION OR EXTENSION. For HDB residential unit, erasure/amendment to any of

the QTY figure below is NOT acceptable.)

QTY 5A socket outlets 13A socket outlets 15A socket outlets 10A SPN/DP ISO 10A TPN ISO 15/16A SPN ISO 20A SPN ISO 20A TPN ISO 30/32A SPN ISO 30/32A TPN ISO 60A SPN/DP ISO 60A TPN ISO

QTY Cooker Point Connection Unit Fan Point Hair Dryer Point Hand Dryer Point Lamp points

QTY Oven Point Shaver Unit Urinal Sensor Point Washing Machine Water Heater Points Other Equipment

QTY

15/16A TPN ISO Cooker hob point Neon Sign ( A completed Certificate of Compliance is required to be submitted if a new meter is required.) Name of LEW : _____________________ __________________________________ Signature of Licensed Electrical Worker LEW Licence No. : _____________

Date : ______________________

Forwarding address (as registered with EMA): __________________________________ Fax No.: ____________________ _______________________________________________________________________ Contact No.: ___________________ Postal Code: ________________ __________________________________________________________________________________________________ PART IV Endorsement by HDB (applicable for HDB residentiaI premises) 1 I have checked the loading of the electrical installation of the abovementioned building/complex and hereby confirm that the abovementioned load requirement can be catered for from the rising/horizontal mains system/main switchboard of the building/complex, and the total approved load to the entire building/complex will not be exceeded. 2 I hereby give consent for the abovementioned customer to tap electricity supply of a capacity indicated above from the rising/horizontal mains system/main switchboard of the building/complex.

_______________________________________ Name/designation/signature of authorised person for and on behalf of Housing & Development Board

Date: ___________________

59

Appendix 9
Types and Layout of Substation
The type of substation required will depend on the customer's load requirement. SPSL shall endeavour to provide the requirement of the substation within 10 business days following the receipt of application form. Typical layout plans and details for substations of the independent building type are given in Appendices 11 to 14. As a guide, the types of substations applicable for the various load requirements are as follows: -

Load Requirement

Primary Distribution Voltage 6.6kV 22kV

Type of rooms

Drawings Applicable/Substation size

Up to 1,000 kVA at 400/230V

Appendices 11 Switchroom Transformer Switchroom 7.6M x 6.2M x 5.6M 4.0M x 4.5M x 3.6M Appendices 12 6.9M x 6.2M x 5.6M

Up to 2,000 kVA at 400/230V Up to 4,250 kW at 22kV

22kV 22kV

The functional requirements of the substation structure, however, must be complied with. For example, the minimum clear height of the cable chamber and switchroom must be 1.5m and 3.1m respectively even if the substation is integrated into a multi-storey building. Subject to the layout and access being suitable, the customer may incorporate the substation as part of his main building. The typical layout plans shown in this handbook depict only the functional requirements.

60

Appendix 10
Submission of Substation Site and Design Plans
Before construction of the substation, the LEW shall submit to SPPG, 2 sets of plans showing the location of the proposed substation in relation to the rest of the development and detailed layout plans for the substation. One set of plan will be endorsed and returned to the LEW. All plans/drawings to be submitted must be on appropriate A1 or A2 size paper and endorsed by the LEW responsible for the planning, design and supervision of the installation. To facilitate processing, SPSL's Application Reference Number must be indicated in all submissions which shall be accompanied by a Checklist Substation Plans (Appendix 15). In the case of re-submission of plans, all amendments (addition/deletion/revision) made must be highlighted in the new set of drawings and listed out in covering letters. All plans are to be drawn to scale and dimensions used shall be in metric units. for Submission of

Substation Site Plans


These plans should show the location of the proposed substation(s) in relation to the surrounding area and should include the following: (i) (ii) (iii) (iv) (v) (vi) (vii) The proposed substation(s) The customer's switchroom(s) The proposed SPPA's incoming cable and customer's service cable routes The orientation of other buildings within the development site The proposed driveway to the substation entrance (to be shaded in red) The existing and proposed drains; and North-East Gridlines or 2 NE survey coordinates.

Substation Design/Layout Plans


It is mandatory that the drawings must include 1 The detailed requirements for the design of the substation are listed in Appendix 16. Unless explicit waiver is granted, these requirements are to be incorporated in the architectural plans. 2 Plan, Front, Rear and Side Elevations of the substation and at least 2 cross-sections showing the surrounding roads, cable chamber, switchroom beams and clear height, switchroom floor openings, transformer plinths and other pertinent details. 3 Details of immediately adjoining upper floor, basement as well as adjacent space all around the substation shall be depicted, if the substation is part of a larger building It is the responsibility of the LEW in charge to ensure that all the requirements as endorsed on the drawings are incorporated in the architectural and structural plans before construction work of the substation begins.

61

6.6KV/LT SUBSTATION

Appendix 11

6.6kV/LT

62

6.6KV/LT SUBSTATION

Appendix 11

63

6.6KV/LT SUBSTATION

Appendix 11

64

6.6KV/LT SUBSTATION

Appendix 11

65

Appendix 12

22KV/LT SUBSTATION

22kV/LT

66

Appendix 12

22KV/LT SUBSTATION

67

Appendix 12

22KV/LT SUBSTATION

68

22KV/LT SUBSTATION

Appendix 12

69

Appendix 12

22KV/LT SUBSTATION

70

Appendix 14 GATE DETAILS

78

Appendix 15
SPPG CHECKLIST FOR SUBSTATION BUILDING PLAN SUBMISSION
Proposal: Name of Licensed Electrical Worker: BP No (if any) : Yes Applicable 1) Drawings are in A1 or A2 series. 2) Plan, front, rear and side elevations are included. 3) Cross-sections in relation to roads and immediate surroundings are included. 4) Detailed layout scales of 1:50 for all plans and 1:100 for all sections and elevations. 5) Substation requirements stated in Handbook on How to Apply for Electricity Connection including latest updating are complied with. 6) Plans are signed by the Licensed Electrical Worker. 7) Proper vehicular access to the substation from main road is coloured. 8) I have advised the structural PE that substation structure is to be designed to withstand the loading specified in the Handbook and all structural requirements have been reflected in this submission. 9) All trenches/floor openings are not affected by any beam. 10) Required clear height (from underside of any beam) of all equipment rooms and cable chamber are complied with. 11) No column within substation 12) No wet area above substation 13) Location of Customer's Switchroom shown with proposed service cable route shown 14) I undertake to advise the architect and structural PE to ensure that all the requirements, as endorsed, are incorporated into the architectural and structural plans prior to substation construction 15) Previous drawings with SPPG's comments are attached (for resubmission case) 16) All additions/deletions/amendments are coloured 17) Any encumbrances? Not

. Signature & Stamp of Licensed Electrical Worker Note: Please tick in appropriate box for all items. This checklist is to be submitted for every submission/re-submission. License No Date

79

Appendix 16 Rev 1 SP POWERGRID LTD (SPPG) SUBSTATION LAYOUT REQUIREMENTS TO BE INCORPORATED IN THE ARCHITECTURAL PLANS
Item Cable Entry Duct Requirement Heavy duty 150mm dia. UPVC pipes in concrete jacket to be provided and terminated 300mm after the roadside drain. To be sealed with removable water-tight plugs at both ends of pipes. To have piling, if necessary. Cross Sectional views to be shown. <= 150mm wide removable hot-dipped galvanized mild steel gratings to be provided. Walls and floors to be plastered and rendered waterproof. Washed dry sand filling to be carried out after cable installation. No beams shall be allowed within / across the trenches. Openings to be covered by removable hot-dipped galvanized mild steel gratings. Gratings of <=300mm width which is able to support at least 100 kg. To take a load of 1,600 kg per sq m. Floor beam is to be 200mm away from the HV floor opening. All floor openings to be free of beam.

Cable Entry Ramp / Ramp Cable Trenches Switchgear Floor Switchroom

Louvred heavy duty aluminium door complying with Appendix 13 drawings. Size 2.9M x 1.8M wide nett for 22KV switchroom. 2.7M x 1.8M wide nett for 6.6KV switchroom. Hasp and staple (150mm x 65mm X 6mm) complying with Appendix 13B. Door hinges to be of brass or stainless steel. Floor to have a 50mm thick cement rendering including a 20mm granolithic smooth finish of cement, granite chips and sand in the ratio of 1:1:1 plus 9kg ironite or equivalent approved hardener to each 45kg of cement. For 22kV substations, final rendering of switchroom floor to be done after installation of switchgear floor frame. HT and LT openings to be beam-free. All floor beams supports to be shown. Height: No part from floor to ceiling beams to be less than 3.1M. No column allowed within the switchroom. Hot-dipped galvanized mild steel/stainless steel railing to be provided for stairs and loading platform. (Removable type in front of door. Glass block and ventilation panels to be installed at high level only.

Transformer Room

Noise level of 60 dB emitted from each transformer to be considered in the choice of location of transformer yard. Adequate natural cross air ventilation required. Provisions of PC vent block or Aluminium ventilation panels at high level. Each transformer plinth to be able to take a dead load of 6 tonnes. Door: 2.7M x 2.7M nett for each transformer. Heavy duty aluminium louvred doors complying with Appendix 13 drawings. Hasp and staple (150mm x 65mm x 6mm) complying with Appendix 13B for doors indicated only. Door hinges to be of brass or stainless steel. LV trench of 800mm min. width for every 1.5MVA or 2 x 1MVA transformers. Separate LV trench to be provided for additional transformers.

Wall / Column Finishes

All concrete surfaces shall be properly prepared and 20mm cement plastering work carried out such that there should be no cracks, blisters and other defects The emulsion painting system used for external walls shall be suitable for outdoor application. There shall be a five (5) years warranty of the textured coating on all walls against all defects arising from colour-fastness, faulty workmanship and / or materials, etc.

80

Appendix 16 Rev 1 (Cont)


Item Electrical Installation Requirement Schematic layout to be shown. All wiring to be in surface conduits. Circuits to be controlled by miniature circuit breakers and ELCB. 20A DP isolators for battery charger, RTU & PWS to tap supply by-passing ELCB. Substation to be adequately lit. T5 type light fittings are to be installed at 3M (suspension in type) and 2.4M (wall-mounting type) from floor level. Wire-mesh casing to be provided for T5 type light fittings installed in cable chamber. To label circuits at DB (distribution board) corresponding to the respective switches, sockets and isolators, etc. Trap door floor openings 760mm x 760mm leading to cable chamber to have: (a) Hinged aluminium chequered covers complete with wall catch. (b) Cat ladders with 6 non-skip steps. Details as shown on drawings. Adequate natural ventilation required with new PC vent block panels only. - Height : 2.0m with no part less than 1.5m. - To paint the front and back of all beam with 50mmH red luminous paint. - Chamber floor to be suspended type capable of supporting 400 kg/m2 (min). Floor level : 150mm above the immediate external road/driveway level and above highest recorded flood level Wall and floor to be waterproofed and adequate drainage to be provided, where necessary. Heavy Duty aluminium Door : 1-leaf of dimension 1200W x 1500H, with door handle and 5 nos. of shoot bolts on internal side. Door details complying with Appendix 13A rev 2 drawing. To be provided for SPPG (see Appendices 31 to 33) when customer is taking HV supply. To be suitably painted and anti-termite treated for all woodwork. To be smooth finishes and emulsion painted. All beam to be encased in RC concrete. To be of flat RC suitably waterproofed and laid to falls of 1:80 minimum. Roof eaves with multiple 150mm wide long slot openings to be incorporated for rain water to free-fall direct into apron drain. Proper drainage around the substation to be provided with hinged hot-dipped galvanized m.s. gratings. To be 1.8m high and designed to blend aesthetically with the overall development. Hollow section anodized aluminium gates complying with Appendix 14. Fence to be embedded into inner end of 600mm wide external concrete apron. To withstand heavy vehicles with laden load of 10 tonnes for all 22kV and 6.6kV substations. Width of driveway to be 4000mm (min) and surface to be paved with premix/tarmac, concrete or interlocking paviours only No car parking lots are to be drawn in such a way as to obstruct vehicular access to substation.

Cable Chamber Basement (where required)

Metering Kisoks Woodwork, Metal Work, etc Ceiling Roof

Drainage Gate / Perimeter Fencing (where required)

Access Road

NOTES

(a) Appointed project LEW is to liaise closely with Architect and Structural Engineer to obtain all their respective requirements for incorporation into final layout plans submitted for SP PowerGrids endorsement. (b) All dimensions and figures as shown on plans endorsed by SPPG are to be checked by the Architect / structural engineer / appointed project LEW prior to substation construction.
(c) If the Management Committee (MCST) / building owner / occupier were to subsequently replace the security personnel with other means e.g. electronic security system etc; SP PowerGrid Ltd shall be consulted on the free unrestricted / unimpeded access arrangement to the substation. (d) LEW/M&E consultants are to ensure that the proposed substation is constructed according to plans endorsed by SPPG.

81

Appendix 17
GENERAL REQUIREMENT FOR EHT SUBSTATION (66KV and 230KV ONLY)
1. Where an application for supply of electricity necessitates the provision of a substation, the site shall be provided and substation constructed by the applicant consumer at his own cost. The Guidelines/Requirements for EHT Substation Buildings will be made available in SPPGs service connection proposal to the applicant. The applicant shall grant SPPG, its officers and agents an irrevocable licence at all times to have full and unrestricted use of the substation and have free access thereto. SPPA may utilize the substation and site in such manner as it deems fit. Subject to the applicants requirement being fully provided for, SPPA shall be at liberty to use the substation for the purpose of supplying other customers or for the improvement of the transmission network (e.g. upgrading, modification to substation structure, alteration and addition works, etc.) The substation site within the substation perimeter fence shall be intended solely for the substation development. The substation structure may be an independent building or form part of a larger building. It shall be located at the 1st storey level and must be readily accessible from the public road. Proper vehicular access to the substation shall be provided for transportation of substation equipment by normal means, i.e. truck and trailer. The gradient of the access road to the EHT substation site (66kV and above) shall not be more than 1:20. There shall be no danger from flooding and fire hazards. The substation site shall be free from all encumbrances (existing and future proposed services). Suitable and proper cable access shall be provided on at least two sides of the substation site for all cables entering and leaving the proposed site. If there is any roadside drain fronting/surrounding the substation site, the applicant shall be required to install cable ducts under-crossing the drain. If the depth of the drain is more than 2.0 meters from the proposed substation ground level, the cable ducts shall be installed to over-cross the drains with approval from the relevant authorities.

2.

3.

4. 5.

6. 7. 8.

10. The applicant consumer shall consider the effect of noise disturbance to neighbouring development in its selection of the substation site. 11. The site of the substation shall be approved by SPPG and the relevant authorities. The applicant shall ensure that all necessary approval for the substation site be obtained from the relevant authorities. 12. The applicant shall consult SPPG on the substation site before commencement of detail design for the substation building. The applicant shall submit the necessary architectural and M&E design drawings, incorporating the necessary requirements in the above-mentioned guidelines/requirements, for SPPGs review and clearances. The applicant shall also obtain the necessary clearances from the relevant authorities.

82

Appendix 18
PROTECTION REQUIREMENTS FOR CUSTOMERS 22KV MAIN INCOMING SWITCHGEAR
INCOMING SUPPLY FROM SPPA SUB-STATION CABLE TERMINATIONS METERING CTs/PTs TO SPPGS REQUIREMENTS 500/5 CLASS 5P20 15VA OR BETTER R Y B O C O C
PILOT WIRES TO SPPAS SWITCHGEAR

REVENUE METERS

O C A E/F

500/5 CLASS X

PW

CB

CUSTOMERS 22kV MAIN INCOMING SWITCHBOARD


O/C E/F PW A CB Notes: 1. Pilot wire protection CTs shall comply with the following requirements: a. b. c. 2. 3. Rated knee point voltage at maximum secondary turns not less than 80V. Exciting current at the rated knee point voltage not more than 150mA. Resistance of the secondary winding, corrected to 75oC not more than 0.15 ohm. Overcurrent relay type IDMTL with 3/10 characteristics. Plug Setting =100%, Time Multiplier=0.1. Earth fault relay type IDMTL with 3/10 characteristics. Plug Setting =20%, Time Multiplier=0.1. Pilot wire protection relay Solkor R/ RF, HOR 4, MHOR. Ammeter Circuit breaker To circuit breaker trip circuit

No other auxiliary device shall be connected to the pilot wire protection CTs. Pilot wire protection CT star-point shall be towards protected line. Where there is more than one incoming service, a bus-section breaker shall be provided and be electrically and mechanically interlocked against parallel operation of the incoming services. All 22kV circuits in the customer installation shall be equipped with unit-protection for fast fault clearance, inclusive of fault at cable terminations.

4.

83

Appendix 18
PROTECTION REQUIREMENTS FOR CUSTOMERS LT MAIN INCOMING SWITCHGEAR

INCOMING SUPPLY

X
R

CB
Y B N

CLASS 5P10 15VA OR BETTER

O C O C E/F O C
METERING CTs

KWH CUSTOMERS LT INCOMING SWITCHBOARD


O/C -

REVENUE METER

E/F

CT CB

Overcurrent relay type IDMTL with 3/10 characteristics or DTL relay. For DTL relay, the setting shall be 100% of approved load with a time lag of not more than 0.5 sec. For IDMTL relay, the plug setting shall be 100% of approved load with a time multiplier of 0.1 (or 0.2 for approved load more than 1.5kA and up to 2.2kA and with source from SPPAs 22kV substation). Earth fault relay operating at primary fault current of 20% of approved load subject to a maximum of 120 Amp with time lag of not more than 0.5 second. Note: LEW is reminded that under CP5, the overall ohmic resistance of earthing system should not exceed one ohm. The maximum earth fault current setting shall be equal to 50V divided by the earth resistance value. Current transformer Class 5P10, 15VA or better. Circuit breaker with adequate breaking capacity and circuit breaker using shunt trip shall be provided with series trip (Direct acting trip) device that operates with no time delay under short-circuit condition, or with HRC fuses in series. To circuit breaker trip circuit.

Note: Where there is more than one incoming service, a 4-pole bus-section breaker shall be provided and be mechanically interlocked against parallel operation of the incoming services.

84

Appendix 18
TYPE 1: CUSTOMER 66KV FEEDER CONNECTION (WITHOUT EMBEDDED GENERATION PLANT)

Type 1a : Supply from SPPA 66kV Source Station


SPPA 66kV S/S

Numerical Relay System (OFC) (see note iii) Feeder Main 1 Feeder Main 2 Inter-tripping Remote End Interlock (on ES & DS) Current Differential 1 Current Differential 2 Current Differential 1 Mechanical

Feeder Main 1 (plus Main 2 if 87L Source S/S)

Electromechanical Relay System (Metallic pilot wire) (see note iii) Feeder Main 1 Feeder Main 2 Inter-tripping Remote End Interlock (on ES & DS)
Interface points

Solkor - Rf Translay S Solkor-Rf Mechanical

SPPAs Scope Customers Scope

Type 1b : Supply from SPPA 66kV Non-Source Station Numerical Relay System (OFC) (see note iii) Feeder Main 1 Inter-tripping Remote End Interlock (on ES & DS) Electromechanical Relay System (Metallic pilot wire) (see note iii) Current Differential Current Differential Mechanical

Pilot/OFC Marshalling Box

87L

Feeder Main 1 Inter-tripping Remote End Interlock (on ES & DS)


Customer 66kV S/S

Solkor - Rf Solkor-Rf Mechanical

Notes: i) ii) All electromechanical feeder protection relays are to be equipped with supervision and guard relays. Engineering and Protection details including interlocking and intertripping shall be discussed on application. Relays, signalling equipment and protection schemes shall subject to review and confirmation during the consultation period. iv) Intertrip and interlock schemes, where applicable, shall be implemented via the numerical current differential system or the dedicated signalling equipment if supplied. v) Customer to supply and install pilot marshalling board of approved design to accommodate the optic fibre cables and other auxiliary cables.

iii) For reason of obsolescence or availability, the type of

vi) Customer shall be responsible for all termination works at their equipment.

85

Appendix 18
TYPE 2: CUSTOMER 66KV FEEDER CONNECTION (WITH EMBEDDED GENERATION PLANT)
Type 2a : Supply from SPPA 66kV Source Station Numerical Relay System (OFC) (see note iii) Feeder Main 1 Feeder Main 2 Inter-tripping Remote End Interlock (on ES, DS & CB) Switching sequencing Current Differential 1 Current Differential 2 Signalling equipment Mechanical & Electrical (via signalling equipment) Signalling equipment
Feeder Main 1 (plus Main 2 if Source S/S)

SPPA 66kV S/S

Electromechanical Relay System (Metallic pilot wire) (see note iii) Feeder Main 1 Feeder Main 2 Inter-tripping Remote End Interlock (on ES, DS & CB) Switching sequencing Solkor - Rf Translay S Signalling equipment Mechanical & Electrical (via signalling equipment) Signalling equipment

Signalling equipment
For inter-tripping and remote electrical interlock

87L

Interface points

SPPAs Scope Customers Scope

Type 2b : Supply from SPPA 66kV Non-Source Station Numerical Relay System (OFC) (see note iii) Feeder Main 1 Inter-tripping Remote End Interlock (on ES, DS & CB) Switching sequencing Current Differential Signalling equipment Mechanical & Electrical (via signalling equipment) Signalling equipment

Pilot/OFC Marshalling Box

87L Signalling equipment

Electromechanical Relay System (Metallic pilot wire) (see note iii) Feeder Main 1 Inter-tripping Remote End Interlock (on ES, DS & CB) Switching sequencing Notes: i) ii) All electromechanical feeder protection relays are to be equipped with supervision and guard relays. Engineering and Protection details including interlocking and intertripping shall be discussed on application. iii) For reason of obsolescence or availability, the type of Relays, signalling equipment and protection schemes shall subject to review and confirmation during the consultation period. iv) Customer to supply and install pilot marshalling board of approved design to accommodate the optic fibre cables and other auxiliary cables. Solkor - Rf Signalling equipment Mechanical & Electrical (via signalling equipment) Signalling equipment v)

Customer 66kV S/S

Customer shall be responsible for all termination works at their equipment.

86

Appendix 18
TYPE 3: CUSTOMER 66KV FEEDER TRANSFORMER CONNECTION

Type 3a : Supply from SPPA 66kV Source Station Numerical Relay System (OFC) (see note iii)
SPPA 66kV S/S Feeder Main 1 (plus Main 2 if Source S/S) 87L

Feeder Main 1 Feeder Main 2 Inter-tripping Remote End Interlock (on ES & DS & neutral)

Current Differential 1 Current Differential 2 Current Differential 1 Mechanical

Electromechanical Relay System (Metallic pilot wire) (see note iii) Feeder Main 1 Feeder Main 2 Inter-tripping Remote End Interlock (on ES & DS & neutral)
Interface points

Solkor - Rf Translay S Signalling equipment Mechanical

SPPAs Scope Customers Scope

Type 3b : Supply from SPPA 66kV Non-Source Station Numerical Relay System (OFC) (see note iii) Feeder Main 1 Inter-tripping Remote End Interlock (on ES & DS & neutral) Current Differential Current Differential Mechanical

Pilot/OFC Marshalling Box 87L

87T

Include REF, TF Diff, OC/EF & other local protection system

Electromechanical Relay System (Metallic pilot wire) (see note iii) Feeder Main 1 Inter-tripping Remote End Interlock (on ES & DS & neutral) Notes: i) ii) All electromechanical feeder protection relays are to be equipped with supervision and guard relays. Engineering and Protection details including interlocking and intertripping shall be discussed on application. Relays, signalling equipment and protection schemes shall subject to review and confirmation during the consultation period. iv) Intertrip and interlock schemes, where applicable, shall be implemented via the numerical current differential system or the dedicated signalling equipment if supplied. Solkor - Rf Signalling equipment Mechanical

Customer 22kV S/S

iii) For reason of obsolescence or availability, the type of

vi) Customer shall be responsible for all termination works at their equipment.

v)

Customer to supply and install pilot marshalling board of approved design to accommodate the optic fibre cables and other auxiliary cables.

87

Appendix 18
TYPE 4: CUSTOMER 230KV FEEDER CONNECTION
Supply from SPPA 230kV Source Station Numerical Relay System (OFC) (see note ii) Feeder Main 1 : Feeder Main 2 : Teleprotection Inter-tripping Remote End Interlock (on ES, DS & CB): Switching sequencing: Current Differential Current Differential with Distance Protection Signalling equipment Signalling equipment Mechanical & Electrical (via signalling equipment) via signalling equipment
Signalling equipment
For teleprotection inter-tripping and remote electrical interlock Main 1 and Main 2

SPPA 230kV S/S

87L

Notes: i) ii) Engineering and Protection details including interlocking and intertripping shall be discussed on application. For reason of obsolescence or availability, the type of relays, signalling equipment and protection schemes shall subject to review and confirmation during the consultation period. iii) Customer to supply and install pilot marshalling board of approved design to accommodate the optic fibre cables and other auxiliary cables. iv) Customer shall be responsible for all termination works at their equipment.

Interface points

SPPAs Scope Customers Scope

Pilot/OFC Marshalling Box

Signalling equipment

87L

Customer 230kV S/S

88

Appendix 18
TYPE 5: CUSTOMER 230KV FEEDER TRANSFORMER CONNECTION

Supply from SPPA 230kV Source Station Numerical Relay System (OFC) (see note ii)
SPPA 230kV S/S

Feeder Main 1 Feeder Main 2 Teleprotection Inter-tripping Remote End Interlock (on ES, DS & CB) Switching sequencing Notes: i)

Current Differential Current Differential with Distance Protection signalling equipment signalling equipment Mechanical & Electrical (via signalling equipment) signalling equipment

Main 1 and Main 2 Signalling equipment


For teleprotection inter-tripping and remote electrical interlock

87L

Interface points

Engineering and Protection details including interlocking and intertripping shall be discussed on application. For reason of obsolescence or availability, the type of relays, signalling equipment and protection schemes shall subject to review and confirmation during the consultation period.

ii)
SPPAs Scope

Pilot/OFC Marshalling Box 87L

Customers iii) Customer to supply and install pilot marshalling board of Scope

approved design to accommodate the optic fibre cables and other auxiliary cables.

Signalling equipment

87T

Include T/F Diff, REF, OC/EF & other local protection system Customer 230kV S/S

iv) Customer shall be responsible for all termination works at their equipment.

89

Appendix 19 APPLICATION FOR DE-ENERGISATION / RE-ENERGISATION (ADRE)


Licensed Installation No Name of Installation: Address of Installation: Requested De-energisation Date Contestable Customer: *Yes / No To: *Deputy Director (EHV Network) *Deputy Director (Regional Network *West / Central / East / North / South) *Deputy Director (Customer Projects *East / West) *Deputy Director (Distribution Projects)
Section EHVN RNW RNC RNE RNN RNS CPE CPW DP Fax No 62909124 66609390 62799590 62409203 67653745 62909110 62409225 62799532 62909140 Tel No 62909121 66609301 62799501 62409218 63146172 62909101 62409257 62799559 62909139

Service No

Voltage

Requested Re-energisation *am/pm Date #MSS A/C No: Time *am/pm

Time

#Name of Customer:

#Name of Retailer:

(1)

I, the undersigned LEW for the above installation, wish to apply for a *de-energisation / re energisation at the time stated above. My work, after the de-energisation, will involve the following: *1 2 Routine Servicing
(Please Specify)

(2)

* I / or ________________________________________ (Name / Licence No of appointee approved by Regulation Division of EMA) will attend to the *de-energisation / re-energisation PERSONALLY. I understand that: (a) No work is to be carried out on the service cable until both SP PowerGrid officer and myself have signed the SDRE (Statement for De-energisation and Re-energisation) after we have safely isolated the service cable at both ends. (b) I am required to be on time on the approved date of de-energisation or re-energisation, failing which the SP PowerGrid officer may cancel any appointment made.

(3)

Signature: ______________________________ Name: _________________________________ Date: _______________

Telephone / HP No.: __________________

Licence No: _________________

* Grade: Engineer Technician Electrician

Notes:

(a) All requested date and time are subject to SP PowerGrids approval. (b) For non-contestable customers, this form should reach SP PowerGrid 7 business days before the requested date. (c) For contestable customers, this form should reach SP PowerGrid 14 business days before the requested date. (d) For urgent work on Sundays / Public Holidays and after office hours, LEW is required to coordinate with SP PowerGrid personally. (e) * Delete whichever not applicable. (f) # To be filled in for contestable customer.

90

Appendix 20
SP POWERGRID LTD

A No. 00001

STATEMENT FOR DE-ENERGISATION AND RE.ENERGISATION (SDRE)


Part I & II concern the de-energisation and re-energisation of the service cable specified below. Each statement is valid only when it is signed by both the LEW of the installation and the SP POWERGRID officer-in-charge of the de-energisation or reenergisation. Name Of Installation: __________________________________________________________________________________ Service Cable No.: *1 / 2 / 3 / 4 Isolated From (Substation Name, OG Box Etc): _____________________________________________________________ This de-energisation is *due to tripping/requested by SP PowerGrid / requested by LEW. * - please delete whichever is not applicable ___________________________________________________________________________________________________

PART I: DE-ENERGISATION STATEMENT (TO BE SIGNED AFTER DE-ENERGISATION)

(This statement is required only when work is to be done on the service cable by either the LEW or the SP PowerGrid officer, or both) Date: ________________________________ Time: ____________________________

DECLARATION BY LEW: I, the undersigned LEW, hereby declare that the above service feeder has been turned off and safely isolated from the customers intake switchboard. Signature: ___________________ Name: _____________________ Licence No.: __________________________

DECLARATION BY SP POWERGRID OFFICER I, the undersigned SP POWERGRID officer, hereby declare that the above service cable has been de-energised and safely isolated from the SP PowerAssets network. Signature: ___________________ Name: _____________________ Section: _____________________________ As agent for and behalf of SP PowerAssets Ltd ___________________________________________________________________________________________________

PART II: RE-ENERGISATION STATEMENT (TO BE SIGNED BEFORE RE-ENERGISATION)


DATE: ____________________________________ TIME: _____________________________

DECLARATION BY LEW: I, the undersigned LEW, hereby declare that the consumer's switchgear, to which the above mentioned service feeder is connected, is cleared of all earthing leads, labour and tools, and that the switchgear is fit for reenergisation from SP POWERASSETS end with effect from the time specified above. I undertake to ensure that no work by any person will be carried out on the service feeder at the consumer's end until a new shutdown statement is signed by both parties. Signature: ___________________ Name: _______________________ Licence No: ______________________________ ACKNOWLEDGEMENT BY SP POWERGRID OFFICER: Signature: ___________________ Name: _______________________ Section: _________________________________ As agent for and behalf of SP PowerAssets Ltd ___________________________________________________________________________________________________

PART III: DECLARATION BY LEW ON THE TIME OF TURN-OFF AND TURN-ON OF INCOMING SUPPLY AT CUSTOMERSS INTAKE SWITCHBOARD (for Contestable Customer only) To: SP SERVICES LTD (Fax no: 63092509, Tel no: 63092543)
Name of Customer: ___________________________________________

MSS A/C No: _______________________

Address of Installation: ________________________________________________________________________________ DECLARATION BY LEW: I, the undersigned LEW, hereby declare that I had turned-off and turned-on the incoming supply at customers intake switchboard at the following date / time: Date of Turn-Off: ___________________________ Date of Turn-On: ___________________________ Signature: ____________________ Time of Turn-Off: __________________________________ Time of Turn-On: __________________________________ Licence No. ______________________

Name: _________________________

91

Appendix 21
CERTIFICATE OF READINESS FOR THE ENERGIZATION OF SERVICE CONNECTION

Name of Customer Installation: Address: Customer Installation Licence No/Expiry Date: Connection Voltage: Approved Load: Name of Connection Cable(s): Owned by Connection Applicant (Yes / No) MSS Account No: Name of Retailer:

Certification By LEW I, ______________________(name) the undersigned LEW, hereby certify that the service connection*, the equipment and works at the above installation (Licence No: ______________) is now ready and fit for energisation with effect from the date and time specified below. Date: Time: I certify that: a. protection details are as follows: CT Ratio: /1A or 5A* Short-Time Withstand Current Ratings of Main Supply incoming Switchgear kA for 1 sec or 3 sec Main 1 Type: Main 2 Type*: Direct Acting Tripping Setting :___________ O/C Type: Setting: E/F Type: Setting: b. the switching equipment/transformer/service connection* and all associated apparatus related to the service connection have been tested and checked by me and they have passed the pre-commissioning checks and tests in compliance with the Market Rules, Transmission Code, Handbook on How to Apply for Electricity Connection, Connection Agreement, all other applicable standards, and the associated protection systems have all been proven effective The main protection schemes for the service connection have been commissioned by load simulation method on date: _______________**. *for multi-metered installation with the exception of HDB residential installation, the metering scheme has been designed as master/sub-metering scheme.

c. d.

* **

Delete where applicable To indicate NA where protection scheme is not applicable

92

Appendix 21

e. f. g.

all necessary meters have been installed. the safety coordination requirements of the Transmission Code have been fully complied with. all workmen have been withdrawn and warned that it is no longer safe to continue to work on the equipment without a Permit-to-work (PTW), and that all tools, scaffolding, ladders, construction materials including any temporary local earthing connections have been removed from the equipment, and all protective screens or guards, if any, have been securely fixed and the appropriate warning signs displayed and that all keys, if any, necessary for the isolation and operation of the equipment have been handed to me. all circuit earth on equipment to be energized are removed. equipment to be energized in this request (the diagram must clearly indicate the portion of the equipment to be energized. If space is insufficient, please provide diagram as attachment) is shown below:

h. i.

Name & Signature of LEW requesting for energisation of supply line

Licence No.

Date

93

Appendix 22.1

FORM CS/6
REQUEST FROM CONTESTABLE CUSTOMER FOR INSTALLATION OF ELECTRICITY KWH METER
For Official Use

Serial No. : ________________________

CMS Installation no. : _____________________

PART I : Customer Details To be completed by LEW

To Meter Section, SP PowerGrid Ltd through SP Services Ltd Name of Customer(Mr/Mdm) /Company(Messrs): __________________________________________ NRIC/Company ROC: ____________ Telephone No. : ____________ Pager/Handphone No. : _________ Existing MSS Account no (if any) : ___________________ Master Account No.(if any) : ______________ Application no.: ____________________ Type Of Business: ___________________________ Site Address as given by IRAS :___________________________________________________________
(You are required to enclose a copy of the IRAS letter.)

Telephone No(s)/point(s) : _______________________________________________________________


(For contestable customer, you are required to install telephone point(s) adjacent to the meter panel and provide the telephone no. before applying for the installation of the meters)

Supply Capacity :___________KVA/KW at ___________ Volts


[Form CS/3 or CS/3H(if supply is from landlord) and COC shall be submitted together with this form]

Metering Scheme: ________________ Source of supply : Type of connection : SP PowerAssets New Connection Landlord

Turn on date : ______________________ Upgrading Downgrading LEW License no. : ______________ Facsimile no. : ____________ Date : _______________________

I hereby confirm that the electrical wirings at the meter installation have been checked and certified correct. Name of LEW : ___________________ Signature : __________________________________ Telephone no. : _____________ Handphone no. : _____________

*Note: For new supply, customer may apply for contestability status & MSS account no. after meters have been installed. LEW shall apply for license under this MSS account no. to operate electrical installation before proceeding to Installation Section to book for turn on appointment date. __________________________________________________________________________________________________________________

PART II To be completed by SP Services Ltd To Meter Section, SP PowerGrid Ltd Application is in order. Please arrange to install the revenue meters. Name : _____________________ Signature: _____________________ PART III To be completed by Meter Section SP PowerGrid Ltd To Supply Application, SP Services Ltd Meters had been installed on _______________. Details in CMS. Name : _____________________ Signature: ________________________ PART IV (For official use) To Meter Data Management Branch, SP Services Ltd Facsimile no.:6737 2472 Date : _____________________ Data Entered by: ________________________ Signature : _______________
(Full Name) ________________________________________________________________________________________________________________

Date : _______________

__________________________________________________________________________________________

Date : _____________________

________________________________________________________________________________________________________________

.PART V (For official use) To Client Relation Branch (MSSL Section), SP Services Ltd Create MSS Account no. : ______________________
(Full Name)

Consumer has been notified MSS account no.

Date : ______________ Account Opened by: ________________________ Signature : _______________

94
04/07/05

Appendix 22.2 Form CS/7


REQUEST FOR INSTALLATION OF ELECTRICITY KWH METER (FOR LOAD EXCEEDING 45KVA)
For Official Use

Serial No. :______________________________

CMS Installation No. : ____________________

PART I Customer Details To be completed by LEW To Meter Section, SP PowerGrid Ltd through SP Services Ltd Name of Customer(Mr/Mdm) /Company(Messrs): _________________________________________________ NRIC/Company ROC:________________ Name of Contact Person for Company: _______________________ Telephone No. : ____________________ Pager/Handphone No. : ____________________ Site Address for Installation of Meter: ___________________________________________________________ Detail location of supply intake point: ___________________________________________________________ A/c no.: : _________________________ Master A/c no.: ___________________________ Source of supply : Type of connection : SP PowerAssets New Connection Landlord Upgrading HDB Downgrading Others : ____________

Supply Capacity :___________kVA/kW at ___________ Volts


(Form CS/3 or CS3/H and COC shall be submitted together with this form)

Type of Business: ______________________

Details of Landlord/MCST
Name of Landlord/MCST: _______________________________ Landlords Account no. : ___________________ Forwarding Address : _______________________________________________________Postal Code ________ Name of LEW in charge of landlords electrical installation : ____________________________________________ Contact no of Landlords LEW : _____________________________ ____________________________________________________________________________________________ I hereby confirm that the electrical wirings at the meter installation have been checked and certified correct. Name of LEW : ___________________ LEW Licence no. : ___________ Forwarding Address (as registered with EMA) : ____________________________________Postal Code_________ Telephone no. : _____________ Handphone no. : ______________ Facsimile no. : ______________

Signature : __________________________________ Date : ____________________ ____________________________________________________________________________________________ PART II - To be completed by SP Services Ltd To Meter Section, SP PowerGrid Ltd -- Application is in order. Please arrange to install the revenue meters. Name : Signature : Date :

PART III -To be completed by Meter Section SP PowerGrid Ltd To Supply Application, SP Services Ltd - Meters had been installed on ____________. Details in CMS. Name : Signature : Date :
_____________________________________________________________________________________________________________________________________________________________________________________

PART IV (For official use)


Check and perform Master-sub Tagging Sent to CRO for account move in on ____________ Move in/ Turn-On Date is on __________________

95

01/07/05

Appendix 23
APPLICATION FOR APPOINTMENT FOR ENERGISATION OF SERVICE CONNECTION BY FAX

FACSIMILE TRANSMITTAL SHEET To: Deputy Director, Installation Branch SP Services Ltd 62777044

Total No. of Pages (including this page): [ From [Name of LEW]: Company: Fax No.: Office Telephone No.: Pager/Handphone No.: Approved Load:

Company: Fax No.: Date: Application No.: MSSL A/C No.:

I would like to make an appointment for energisation of service connection to __________________________________________ _______________________________________________________________________________________________________. (site address)
The following documents are faxed together with this application.

Documents 1) Opening of Account with SP Services Ltd 2) Opening of Account with Electricity Retailer (for contestable consumer) 3) Confirmation of meters already fixed (for contestable consumer) 4) Electrical Installation Licence issued by EMA 5) Certificate of Compliance (original to be submitted to SPPGs project officer) 6) Letter from IRAS confirming official address

Tick if applicable

I will submit the Certificate of Readiness on site, failing which service connection shall not be energised and SPPG & SPPA shall not be liable for any loss arising therefrom. I understand that the date of appointment is subject to confirmation by SP Services Ltd and the appointment date shall not be earlier than 4 business days from this fax date. The preferred appointment dates are as follows:
st 1 choice:

Date: Date: Date:

Time: Time: Time:

Morning / Afternoon* Morning / Afternoon* Morning / Afternoon* ( *delete whichever not applicable )

2nd choice: 3rd choice:

Name & Signature of LEW Licence No. FOR OFFICIAL USE The appointment for energisation of service connection is fixed on __________________________ at ____________________. (date) (time) Please liaise with Meter Section of SPPG for the fixing of revenue meter before the energisation. For clarification, please contact ______________ at Telephone No.: 627770 __________.

96

Appendix 24
TECHNICAL REQUIREMENTS FOR SERVICE CABLE AND METER COMPARTMENT FOR LANDED HOUSES
1
2 3 4 The service cable termination and meter compartment shall be located at the front-gate pillar/perimeter wall such that it is accessible to SPSL's and SPPG's officer without the need to enter the customer's premises. It shall be constructed of concrete, brick or high impact fibre glass and shall be completely weatherproof. Provision shall be made to prevent any stagnation of water within the compartment. The main dimensions of the compartment are shown in the layout drawing (see Appendix 25). The depth of the compartment shall be between 250 mm and 300 mm. A meter board of 20 mm thick and constructed of teak wood or any hardwood chemically treated against termite attack shall be provided. Plywood board is not acceptable. A minimum space of 450 mm (W) x 800 mm (H) shall be allowed for the termination of the service cable and the installation of service MCBs and meters. Customer's MCBs or connectors shall be mounted on a separate board in a separate compartment. A hinged door with a clear glass viewing window shall be provided. The viewing window with a 200 mm (W) x 300 mm (H) x 6 mm (thickness) glass cover shall be positioned to be directly in front of the meter location. To avoid high humidity and condensation within the compartment, sufficient ventilation shall be provided. The access door shall not have less than 450 mm clear access opening. The door shall be constructed of stainless steel, anodised aluminium or high impact type fibre glass reinforced material. Where a metal door is provided, a means of earthing shall be provided. One 100mm diameter UPVC lead-in pipe shall be provided for SPPA service cable. The pipe shall be laid up to 100 mm from the floor slab of the electric meter compartment and shall undercross any drain in front of the compartment. There shall be adequate standing space in front of the compartment to facilitate meter reading, installation and maintenance work. Where there exists a drain in front of the compartment, a suitable concrete platform or hinged galvanised steel grating shall be provided. The compartment shall be exclusively used for service cable and electricity meter. No water meter, gas meter or other facilities shall be placed within the same compartment. Please obtain clearance from URA's Development Control Division if the meter-box structure exceeds their stipulated dimensions.

6 7

9 10

97

Appendix 24
STANDARD METER COMPARTMENTS AT GATE PILLAR

98

Appendix 25
STANDARD METER BOARD

99

Appendix 26

STANDARD SIZE FOR SINGLE-PHASE METER BOARD


MCB / cut-out Max 100 Amps Neutral

230 mm

230 mm (L = 300 mm for 35 sq mm cable)

280 mm

Single Phase Meter

PG Electrical Service Box

Fig A

40 mm

(L = 300 mm for 35 sq mm cable)

Neutral

Neutral

Neutral

280 mm

Single Phase Meter

Fig C

Neutral

Neutral

Load

Live

Fig B

1. 2. 3. 4. 5. 6. 7. 8. 9.

Minimum space for single-phase meter position (enclosed within broken lines): (i) 230mm (W) x 280 mm (H) for 25 sq. mm cable and below. (ii) 230mm (W) x 300 mm (H) for 35 sq. mm cable. A customers earthing terminal shall be provided on the meter board for termination of the earthing lead and earth continuity conductor. Not more than one wire should be connected to each terminal of the meter terminal block. All wires on the meter board from MCB/Cut-Out to the meter and meter to main switch should preferably be run on the surface. The size of cables to be used for connection to meters should not exceed 35 sq. mm. The length of wire L protruding from the meter board to the meter terminal shall be at least 200 mm. For meters grouped in a centralised meter room etc, an additional minimum spacing of 70mm is necessary between each row of meters for ease of installation/change. The meter cables should be colour-coded red for live and black for Neutral. Some typical layouts are shown in figures A, B and C.
Note : Drawing not to scale. All dimensions in mm.

100

40 mm

40 mm

MCB / cut-out Max 100 Amps

230 mm

Load

Live

280 mm

Single Phase Meter

(L = 300 mm for 35 sq mm cable)

Neutral

Neutral

Load

Live

Appendix 27

STANDARD SIZE FOR THREE-PHASE METER BOARD


450 mm

MCB / cut-out Max 100 Amps

Neutral

(L = 300 mm for 35 sq mm cable)

450 mm

450 mm
Neutral

Whole Current Poly Phase Meter

450 mm

Whole Current Poly Phase Meter

Typewritten on cable sleeve


MCB / cut-out Max 100 Amps

Type-written on cable sleeve

Overhead Type 1. 2. 3. 4. 5. 6. 7.

40 mm

UnderGround Type

Minimum space for three-phase meter position 450 mm (W) x 450 mm (H) (enclosed within broken lines). A customers earthing shall be provided on the meter board for termination of the earthing lead and earth continuity conductor. Not more than one wire should be connected to each terminal of the meter terminal block. All wires from the meter board from MCB/Cut-Out to meter and meter to main switch should preferably be run on the surface. The size of cables to be used for connection to meters should not exceed 35 sq. mm. The length of wire L protruding from the meter board to the meter terminal shall be at least 200 mm. The meter cables should be colour-type respective to their phases or be shrouded with coloured sleeving.

Note : Drawing not to scale. All dimensions in mm.

101

(L = 300 mm for 35 sq mm cable)

Main Load Main Load Main Load Neutral Load

Main Load Main Load Main Load Neutral Load

40 mm

Appendix 28
CT METER PANEL FOR LOW TENSION SUPPLY

102

Appendix 29
METHODS OF SEALING METERING PANELS

103

Appendix 30
ENCLOSURE FOR LOW TENSION METERING CURRENT TRANSFORMERS

104

Appendix 31
HT METERING KIOSK REQUIREMENTS (FOR 1 OR 2 FEEDERS)

Meter Panel

Note: Drawing not to scale. All dimension in mm

Side Elevation of Metering Kiosk for 1 or 2 feeder panel The following are required: a) b) c) d) e) f) Metering kiosk : 650mm by 1700mm by minimum height 2400mm of solid brick as shown. Floor opening 50mm by 50mm as shown. Staircase and 1000mm landing where required. Steel or heavy duty aluminium door of 1200mm wide by 2100mm height to be fitted with one of the SPPA approved master series locksets as given in section 6.1.5. One 13A switched socket outlet, one 40W lighting points and one fixed telephone c/w telephone socket outlet. If landing is above ground level, safety railings must be provided.

105

Appendix 32 HT METERING KIOSK REQUIREMENTS (FOR 3 OR 4 FEEDERS)

40W fluorescent lamp 100 mm thick 2100 mm high heavy duty aluminium door

610 mm 1000 mm

r.c. floor

100 mm x 60 mm floor opening BASEMENT STAIRS

Note : Drawing not be scale. All dimension in mm

Side Elevation of Metering Kiosk for 3 or 4 feeder panel The following are required : a) b) c) d) e) f) Metering kiosk : 810mm by 2650mm by minimum height 2400mm of solid brick as shown Floor opening 100mm by 60mm as shown. Staircase and 1000mm landing where required. Heavy duty aluminium door of 800mm width by 2100mm height to be fitted with one of the the SPPA approved master series locksets as given in section 6.1.5. One 13A switched socket outlet, two 40W lighting points and one fixed telephone line c/w telephone socket outlet. If landing is above ground level, safety railing must be provided.

106

Appendix 32
HT METERING KIOSK REQUIREMENTS (FOR 3 OR 4 FEEDERS)

40 W fluorescent lamp

a = 40W fluorescent lamps b = 13A switched socket outlet c = 5A switch for fluorescent lamps

107

Appendix 33
HT METERING PANEL REQUIREMENT (FOR 1 OR 2 FEEDERS)

108

Appendix 34
METERING VTS
Voltage Ratio, Sequence & Phase Angle Tests Report
Customer : Project Address : PT No. : For Feeder No. : I, and results are given below. I hereby certified that the VTs are correctly connected up for tariff metering. , EMA Licensed No. had carried out the above test ____ A/C No. : A/C No. : Voltage Ratio :

Stamp & Signature of LEW Date :

Primary ( Across

V)

Secondary Frequency Sequence Across RY RE Volt

Phase Angle Lead Lag

RY

YR YB BR YB YE BE YE

YB

BY BR RY BR BE RE BE

BR

RB RY YB RE YE

109

Appendix 35
BASIS FOR THE SERVICE CONNECTION CHARGE
1

Service Connection Charges for Low Tension (LT) Connection All LT consumers are required to pay a one-time upfront service connection charge. These charges which vary for different load requirements are categorised depending on the provision of a substation. For larger consumers with substations, their supply intake point is usually adjacent to the substation, which requires a service cable of approximately 15m in most instances. Therefore, the standard connection charge is computed based on a cost of service cable length of 15m. Consumers shall pay the additional cost for service cable exceeding 15m. In addition, consumers shall also pay for those dedicated assets, such as switchgear and transformers, which are serving them and do not benefit others. For individual small consumers without substations, the cost of LT service cable for the same capacity may vary widely depending on their locations with respect to the nearest LT mains. These consumers are not the sole beneficiaries of the extension of the LT network. To achieve a greater degree of equity in terms of cost for these general consumers, a standard cost approach is adopted based on similar requirements. The average global cost based on capacity is determined from past statistics. As such, this category of consumers which comprises mainly the individual landed residential owners, applying for the same applied load would pay the same standard connection charge regardless of the location of their premises from the existing LT network. Standard charges are only applicable to consumers who are connected to the shared network. The rates, which are approved by EMA, are available in the Transmission Services Rate Schedule. Standard charges are not applicable to consumers where the network created is unlikely to be shared by others. Some of these include supply to HDB premises, premises involving installation of bigger capacity cable in order to overcome the excessive voltage drop, temporary work sites, public installations and offshore island premises. These consumers would have to pay for the full connection network cost, based on user-pay principle, as they are the main beneficiaries.

Service Connection Charges for HT and EHT Connection Customers receiving HT and EHT connection shall pay the cost of the service connections to their intake equipment including cables, associated equipment and facilities to effect the connection of customers equipment to SPPAs substation/network. The service connection shall cater for single contingency. Customers requesting for additional level of contingency above single contingency are required to pay for the full cost of such provision.

Dedicated Network/Substation The customer shall pay the full cost for all associated equipment and facilities under a dedicated network/substation scheme which the network capacity is intended to serve to its development exclusively. Substation comprises land, building, electrical equipment and associated cables. Substations which serve a development or premises have to be provided and paid for by the developer or customer. As the capacity of electrical equipment is lumpy, the substations may have excess capacity. The developer or customer will carry the cost of this excess capacity which cannot be avoided. As these substations are required to serve the development or customer loads, they are dedicated substations. To reduce cost, a developer or customer can choose to let SPPA bear the cost of the electrical equipment and associated cables. In return, SPPA must therefore be allowed to sell off the excess capacity. Even after the excess capacity is sold off, SPPA remains committed to return the capacity to the customer if his demand grows later. At present, most substations provided by developer or customer are non-dedicated substations.

110

Appendix 36
STANDARD SERVICE CONNECTION CABLES
The type of service connection cables for terminating into a customers intake point for the applied load connected at the LT and 22kV level and the typical connection schemes are illustrated as follows: Voltage Level LT Applied Load (kVA) Up to 15 16 45 46 75 76 140 141 180 181 230 231 280 281 460 461 560 561 1000 1001 1500* 1001 2000^ 2001 3000^ Up to 12750kW^ 12751 25500kW^ 25501 38250kW^ Pilot cables Size of Cables 35mm 35mm2 35mm2 120mm2 185mm2 300mm2 300mm2 2x300mm2 2x300mm2 7x500mm2 7x1000mm2 2 sets of 7x500mm2 3 sets of 7x500mm2 2x300mm2 4x300mm2 6x300mm2 1.5 mm2
2

Type of cables 2Core 4Core 4Core 4Core 4Core 4Core 4Core 4Core 4Core 1Core 1Core 1Core 1Core 3Core 3Core 3Core 5 pair Cu/XLPE/SWA/PVC Cu/XLPE/SWA/PVC Cu/XLPE/SWA/PVC Al/XLPE/SWA/PVC Al/XLPE/SWA/PVC Al/XLPE/SWA/PVC Cu/XLPE/SWA/PVC Al/XLPE/SWA/PVC Cu/XLPE/SWA/PVC Cu/XLPE/PVC Cu/XLPE/PVC Cu/XLPE/PVC Cu/XLPE/PVC Cu/XLPE/DSTA/PVC Cu/XLPE/DSTA/PVC Cu/XLPE/DSTA/PVC Cu/PE/DSTA/PVC

22kV+

For installations where the customers supply, install and maintain the service cables, to ensure that these cables comply with SPPA's specifications, the customers shall seek approval from Distribution Engineering Section prior to procurement. * applies to upgrading of applied load. + The 22kV scheme is designed to cater for the outage of a single service connection circuit. The customer is required to reduce or maintain his load to within the rated capacity of the remaining service connection circuit(s) in the event of a busbar failure or outage for maintenance. ^ There must be an electrical and mechanical interlocking bus coupler between each set of cables terminating into the customers switchboard as shown below, and to ensure that there is no possibility of paralleling SPPA source:
Normally Open Bus Coupler 7x500mm
2

LT Customers SwitchBoard 1001- 2000kVA


2

1Core Normally Open

7x500mm

1Core LT Customers SwitchBoard 2001- 3000kVA

Normally Open Bus Coupler

Bus Coupler 7x500mm


2

1Core Normally Open

7x500mm

1Core

7x500mm

1Core Normally Open

Bus Coupler 300mm


2

Bus Coupler 300mm


2

3Core

HT Customers SwitchBoard Up to 12750kW

3Core

300mm

3Core 300mm2 3Core

HT Customers SwitchBoard 300mm2 3Core 300mm2 3Core 12751- 25500kW HT Customers SwitchBoard 25501- 38250kW (subject to SPPG approval)

Normally Open Bus Coupler 300mm


2

3Core

300mm

3Core

300mm

3Core

300mm

3Core

300mm

3Core

300mm

3Core

111


CERTIFICATE OF COMPLIANCE
Particulars of Electrical Installation

Appendix 37

Name of Consumer: ________________________________________________ Address of Installation: ______________________________________________ _________________________________________________________________ Electrical Installation Licence No. _________ MSS Account No. _____________

Approved load & Supply Voltage: _______________ kW ____________ Volts Generator(s) Installed: Operated in parallel with SP PowerAssets network. No. of generator: ________ Rating: _________ kVA Standby generator. No. of generator: ________ Rating: _________ kVA Not applicable Electrical Installation Design Certification I certify that the design of the above-mentioned electrical installation complies with the requirements of the Electricity (Electrical Installations) Regulations 2002 and the relevant Singapore Standard Code of Practice. With the certification of compliance by the LEW responsible for the installation work as shown below, I hereby request for the energisation of the supply line to the said electrical installation on _________________ (date).

Name & Signature of LEW responsible for design of electrical installation* Electrical Installation Inspection Certification

__________ Licence No.

_________ Date

I have supervised the work of the above-mentioned electrical installation and hereby certify that the electrical installation complies with the requirements of the Electricity (Electrical Installations) Regulations 2002 and the relevant Singapore Standard Code of Practice. I further certify that the technical requirements as stipulated by the person responsible for turning on the switchgear which controls the supply of electricity to the said electrical installation have been complied with.

Name & Signature of LEW responsible for electrical installation work*

__________ Licence No.

_________ Date

* The same LEW may perform both design and installation work for the electrical installation. Copy to: Market Support Services Licensee REF: E(EI)Reg5(2) 112

Appendix 38
STATEMENT OF TURN-ON OF ELECTRICITY
ELECTRICITY SUPPLY TO _____________________________________________________________
(Name of Applicant)

AT__________________________________________________________________________________
(Address of Installation)

ELECTRICAL INSTALLATION LICENCE NO : ______________________________________________ APPLICATION NUMBER : ______________________________________________________________ I agree that the above-mentioned electrical installation is suitable for connection to the electrical system. I certify that the supply line to the installation has been energised on
_______________________at ______________________.
(date) (time)

____________________________________ Name & Signature of SP PowerGrid officer SP PowerGrid Ltd As agent for and on behalf of SP PowerAssets Ltd

_____________ NRIC No.

____________ Date

I acknowledge that the supply line has been energised on the date and time as indicated above.

_______________________________________ Name & Signature of LEW requesting for energisation of supply line

________________ ____________ Licence No. Date

I acknowledge that the supply line has been energised on the date and time as indicated above and confirm that I will be responsible for the operation of this electrical installation hereafter.

_______________________________________ Name & Signature of LEW responsible for the operation of the electrical installation*

________________ ____________ Licence No. Date

I acknowledge that the supply line has been energised on the date and time as indicated above. ______________________________________ Name & Signature of Applicant or his representative ________________ _____________ NRIC / Passport No. Date

*Not Applicable for an electrical installation that is exempted from licensing Original Copy Pink Copy Yellow Copy Green Copy Blue Copy White (last) Copy SP PowerGrid Ltd LEW (Requesting) LEW (Operation) Applicant MSSL File

REF: E(EI) REG 5(4)

113

Appendix 39
REQUIREMENTS FOR DISTRIBUTED GENERATION FACILITY
The customer applying for distributed generation facility is required to obtain SPPAs approval and shall comply with the technical, safety & operational and commercial & legal requirements as follows: A) Technical Requirements 1 2 3 4 5 6 real and reactive power/voltage output and voltage and frequency response times must be within agreed limits not contribute to the voltage unbalance, voltage fluctuation and harmonic content specified for the transmission network ensure that there is no interference to SPPAs Equipment or any other directly or indirectly connected consumers ensure adequate partitioning of the exempt generation facility equipment from SPPAs equipment where required by SPPA, install harmonic filtering circuit at the incoming switchboard of the service connection in compliance with the harmonics standard LEW is required to submit fault level reports to SPPGs Distribution Planning Section. The distributed generation system shall limit their fault level contribution to the grid to a level acceptable to SPPG.

B) Safety & Operational Requirements 1 provide an interlocking and inter-tripping facility for the service connection that meets SPPAs requirement fit exempt generation facility with reverse power relays to prevent export of power to the transmission system. However, this requirement will not apply in the event that EMA / EMC had given approval for the export of power to the transmission system not operate the exempt generation facility in islanding mode i.e., the embedded generator must isolate itself from the distribution network when there is a fault/tripping on the latter or the customers installation (non-islanding protection) provide a synchronizing facility at the incoming switchboard of its service connection and ensure that any output is always synchronized with the distribution network

C) Commercial & Legal Requirement The customer with an exempt generation facility shall 1 2 pay standby use of system charges or any other charges approved by the EMA indemnify SPPA i) for all losses and liabilities arising from any loss of synchronisation caused by any tripping or re-closing of any breakers in the transmission system and the exempt generation facility connected in parallel to the transmission system ; and ii) against losses to third parties caused by impedance, disruption degradation interference or failure of transmission services to third parties caused by the system or works carried out on the transmission system certify to SPPG that the exempt generation facility meet all conditions of the relevant legislation, regulation (including installation, fire and safety, noise and environment); conduct regular site tests and to notify the SPPG of the results allow SPPG to conduct inspection of, disconnect and enforce conditions in respect of the service connection if the exempt generation facility fails to meet any of the above requirements resolve, at its own expense all third party complaints concerning the exempt generation facility (e.g.complaints due to noise, or aesthetic reasons); and use the service connection to operate in parallel with its exempt generation facility at its own risk

3 4 5 6 7

114

Appendix 39.1 TERMS AND CONDITIONS FOR CAPPED CAPACITY SCHEME (CCS) 1 The Consumer shall at its own expense, install and maintain, in accordance with such requirements that Transmission Licensee may from time to time stipulate: 1.1 at the Consumers incoming switchboard (or at such other point that Transmission Licensee may specify), a Load Limiting Device (LLD), which will automatically disconnect the Service Connection from the Transmission System in the event (Event) that the Consumers intake from the Transmission System exceeds one hundred twenty percent (120%) of the Contracted Capacity (CC) continuously for more than ten (10) seconds. at the HT metering kiosk (or at such other point that Transmission Licensee may specify), a Load Monitoring Device (LMD) including all control cables for the LMD as well as metering accessories and telephone line(s) for Transmission Licensee to monitor the Consumers intake from the Transmission System.

1.2

Upon installation, all title, rights and interest in the LMD shall vest immediately in Transmission Licensee. However, the Consumer shall ensure that: 2.1 The LMD shall at all times be set and adjusted to the satisfaction of Transmission Licensee; No modification, reset or adjustment to the LMD is carried out without first obtaining Transmission Licensees approval; The testing, commissioning and subsequent annual testing of the LMD as well as any modification, reset or adjustment to the LMD approved by the Transmission Licensee is to be carried out by a Licensed Electrical Worker and in the presence of a representative from Transmission Licensee; The LMD is re-tested and re-commissioned as and when required at the discretion of Transmission Licensee; All test results are submitted to Transmission Licensee at such address as notified by Transmission Licensee within two (2) weeks of the testing; The telephone line(s) set up for Transmission Licensees remote data downloading from LMD shall be operational at all times; Transmission Licensee officers are granted unrestricted access to substation premises for on-site inspection and retrieval of data from the LMD; and The LMD is covered under a valid maintenance contract providing for relevant technical support and replacement parts to keep the LMD in good operational condition at all times.

2.2

2.3

2.4

2.5

2.6

2.7

2.8

The Transmission Licensee shall witness the testing of LMD at its own expense. All other expenses in connection with the testing of the LMD shall be borne by the Consumer.

The conversion to CCS shall be effective upon the following (the CCS Effective Date): 4.1 4.2 the Consumers compliance with Item 1 above; and the successful commissioning of the LLD and LMD.

In the event that the LLD fails to cap the power demand (kW) drawn from the network in the circumstances as described in Item 1.1, the Uncontracted Standby Capacity Charge (USCC) shall apply and be payable. USCC is a monthly charge payable in any month for the Uncontracted Standby Capacity utilised. The Uncontracted Standby Capacity is the peak power demand in kW drawn from the network exceeding 120% of CC, recorded from the time the power drawn exceeds 120% of CC to the time the power drawn falls below 120% of CC. This peak power demand is recorded by the LMD at single second intervals. The rate of USCC shall be the prevailing rate stated in the Transmission Service Rate Schedule. SPPA reserves the right to review the USCC rate applicable to the Consumer from time to time, such review to be subject to EMAs approval. The current rate for USCC is 5 times CC Charge for demand drawn exceeding 120% of CC. For each Event, as defined in Item 1.1 above, the Consumer is required to submit, within two weeks of the occurrence of the Event, a report to the Transmission Licensee on the causes of the occurrence. The report shall also include the Consumers followup actions to prevent similar Events from occurring. The Consumer shall ensure that multiple sources of Transmission System are not connected in parallel at any time, and that any switching between circuits is undertaken on black changeover or break before make basis. Transmission Licensee reserves the right to withdraw the CCS from the Consumer if the Consumer fails to comply with the terms and conditions applicable to the scheme, and to offer only the Summation Scheme (as outlined in Clause 12.14(a) of the CCA) to such Consumer.
In the event of a change in scheme for whatever reason, the Service Connection may

10

11

be disconnected temporarily to facilitate the installation of energy meters and other equipment for the purposes of the implementation of the Summation Scheme.

ii

Appendix 39.2 TERMS AND CONDITIONS FOR EXTENDED CAPPED CAPACITY SCHEME (ECCS) 1 The Consumer shall at its own expense, install and maintain, in accordance with such requirements that Transmission Licensee may from time to time stipulate: 1.1 at the Consumers incoming switchboard (or at such other point that Transmission Licensee may specify), a Load Limiting Device (LLD), which will automatically disconnect the Service Connection from the Transmission System on the happening of any one of the following events (Event): (a) when the Consumers intake from the Transmission System exceeds one hundred twenty percent (120%) of the Contracted Capacity (CC) continuously for more than one hundred (100) seconds; or when the Consumers intake exceeds two hundred percent (200%) of the CC continuously for more than ten (10) seconds.

(b)

1.2

at the HT metering kiosk (or at such other point that Transmission Licensee may specify), a Load Monitoring Device (LMD) including all control cables for the LMD as well as metering accessories and telephone line(s) for Transmission Licensee to monitor the Consumers intake from the Transmission System.

Upon installation, all title, rights and interest in the LMD shall vest immediately in Transmission Licensee. However, the Consumer shall ensure that: 2.1 The LMD shall at all times be set and adjusted to the satisfaction of Transmission Licensee; No modification, reset or adjustment to the LMD is carried out without first obtaining Transmission Licensees approval; The testing, commissioning and subsequent annual testing of the LMD as well as any modification, reset or adjustment to the LMD approved by the Transmission Licensee is to be carried out by a Licensed Electrical Worker and in the presence of a representative from Transmission Licensee; The LMD is re-tested and re-commissioned as and when required at the discretion of Transmission Licensee; All test results are submitted to Transmission Licensee at such address as notified by Transmission Licensee within two (2) weeks of the testing; The telephone line(s) set up for Transmission Licensees remote data downloading from LMD shall be operational at all times; Transmission Licensee officers are granted unrestricted access to substation premises for on-site inspection and retrieval of data from the LMD; and The LMD is covered under a valid maintenance contract providing for relevant technical support and replacement parts to keep the LMD in good operational condition at all times.

2.2

2.3

2.4

2.5

2.6

2.7

2.8

The Transmission Licensee shall witness the testing of LMD at its own expense. All

iii

other expenses in connection with the testing of the LMD shall be borne by the Consumer. 4 The conversion to ECCS shall be effective upon the following (the ECCS Effective Date): 4.1 4.2 5 the Consumers compliance with Item 1 above; and the successful commissioning of the LLD and LMD.

In the event that the LLD fails to cap the power demand (kW) drawn from the network in the circumstances as described in Item 1.1, the Uncontracted Standby Capacity Charge (USCC) shall apply and be payable. The USCC is a monthly charge payable in any month for the Uncontracted Standby Capacity utilised. For the purposes of this ECCS, the term Uncontracted Standby Capacity shall mean the capacity by which the demand in kW drawn from the network: 6.1 exceeds 120% up to a level of 200% of the CC at the metered intake supply point for a duration of more than 100 seconds continuously; or exceeds 200% of the CC at the metered intake supply point for a duration of more than 10 seconds continuously,

6.2

in both cases, arising from a failure by the Consumer to cap the demand in kW drawn from the Transmission System. The definition of Uncontracted Standby Capacity as stated in the CCA is hereby superceded. 7 The rate of USCC shall be the prevailing rate stated in the Transmission Service Rate Schedule. SPPA reserves the right to review the USCC rate applicable to the Consumer from time to time, such review to be subject to EMAs approval. The current rate for USCC is: 7.1 7.2 8 5 times CC Charge for demand drawn exceeding 120% up to 200% of CC; and 12 times CC Charge for demand exceeding 200% of CC.

For each Event, as defined in Item 1.1 above, the Consumer is required to submit, within two weeks of the occurrence of the Event, a report to the Transmission Licensee on the causes of the occurrence. The report shall also include the Consumers followup actions to prevent similar Events from occurring. The Consumer shall ensure that multiple sources of Transmission System are not connected in parallel at any time, and that any switching between circuits is undertaken on black changeover or break before make basis. Transmission Licensee reserves the right to withdraw the ECCS from the Consumer if the Consumer fails to comply with the terms and conditions applicable to the scheme, and to offer only the Summation Scheme (as outlined in Clause 12.14(a) of the CCA) to such Consumer. The Consumer acknowledges and accepts that in the event of a change in scheme for whatever reason, the Service Connection may be disconnected temporarily to facilitate the installation of energy meters and other equipment for the purposes of the implementation of the Summation Scheme.

10

11

iv

Appendix 40
LIST OF STANDARDS
IEC Standards
IEC 60044-1 IEC 60044-1-am1 IEC 60044-2 IEC 60044-6 IEC 60060-1 IEC 60060-2 IEC 60060-2-am1 IEC 60076-1 IEC 60076-2 IEC 60076-3 IEC 60076-5 IEC 60076-8 IEC 60076-10 IEC 60099-4 IEC 60137 IEC 60141-1 (1996-12) Ed. 1.0 Instrument transformers - Part 1 : Current transformers (2000-07) Ed. 1.0 Amendment 1 (2000-11) Consol. Ed. 1.1 (incl. am1) Instrument transformers - Part 2 : Inductive voltage transformers (1992-03) Ed. 1.0 Instrument transformers - Part 6 : Requirements for protective current transformers for transient performance (1989-11) Ed. 2.0 High-voltage test techniques - Part 1 : General definitions and test requirements (1994-11) Ed. 2.0 High-voltage test techniques - Part 2 : Measuring systems (1996-03) Ed. 2.0 Amendment No.2 to IEC 60-2 (2000-04) Consol. Ed. 2.1 (incl. am1) Power transformers - Part 1 : General (1993-04) Ed. 2.0 Power transformers - Part 2 : Temperature rise (2000-03) Ed. 2.0 Power transformers - Part 3 : Insulation levels, dielectric tests and external clearances in air (2000-07) Ed. 2.0 Power transformers - Part 5 : Ability to withstand short circuit (1997-11) Ed. 1.0 Power transformers - Part 8 : Application guide (2001-05) Ed. 1.0 Power transformers - Part 10 : Determination of sound levels (2001-12) Consol. Ed. 1.2 (incl. am1 + am2) Surge arresters - Part 4 : Metal-oxide surge arresters without gaps for a.c. systems (1995-12) Ed. 4.0 Insulating bushings for alternating voltages above 1000V (1993-09) Ed. 3.0 Tests on oil-filled and gas-pressure cables and their accessories Part 1 : Oil-filled, paper or polypropylene paper laminate insulated, metalsheathed cables and accessories for alternating voltages up to and including 500kV (1995-02) Ed. 3.0 Amendment No.1 (1998-08) Ed. 3.0 Amendment No.2 (1978-01) Ed. 2.0 Conductors of insulated cables (1993-01) Ed. 2.0 Amendment No.1 (1966-01) Ed. 1.0 Impulse tests on cables and their accessories (1989-06) Ed. 2.0 Electrical relays Part 3: Single input energizing quantity measuring relays with dependent or independent time (2000-12) Ed. 2.0 Electrical relays Part 5: Insulation coordination for measuring relays and protection equipment Requirements and tests (1988-12) Ed. 2.0 Electrical relays Part 6: Measuring relays and protection equipment (1990-10) Ed. 2.0 Electrical relays Part 8: Thermal electrical relays (1980-01) Ed. 1.0 Electrical relays Part 12: Directional relays and power relays with two input energizing quantities (1980-01) Ed. 1.0 Electrical relays Part 13: Biased (percentage) differential relays (1981-01) Ed. 1.0 Electrical relays Part 14: Endurance tests for electrical relay contacts Preferred values for contact loads (1982-01) Ed. 1.0 Electrical relays Part 16: Impedance measuring relays (1983-01) Ed. 1.0 Electrical relays Part 19: Sectional specification: Electromechanical all-or-nothing relays of assessed quality (1994-10) Ed. 1.0 Electrical relays Part 23: Contact performance (2001-05) Ed. 1.0 Electrical relays Part 24: Common format for transient data exchange (COMTRADE) for power systems (1990-03) Ed. 3.0 Characteristics of indoor and outdoor post insulators for systems with nominal voltages greater than 1000V

IEC 60141-1-am1 IEC 60141-1-am2 IEC 60228 IEC 60228-am1 IEC 60230 IEC 60255-3 IEC 60255-5 IEC 60255-6 IEC 60255-8 IEC 60255-12 IEC 60255-13 IEC 60255-14 IEC 60255-16 IEC 60255-19 IEC 60255-23 IEC 60255-24 IEC 60273

115

Appendix 40
LIST OF STANDARDS
IEC Standards continued
IEC 60186 IEC 60287-1-1 IEC 60287-1-2 IEC 60287-2-1 IEC 60287-2-2 IEC 60287-3-1 IEC 60287-3-2 IEC 60287-3-2-am1 IEC 60289 IEC 60298 IEC 60332-1 IEC 60354 IEC 60376 IEC 60502-1 Voltage Transformers (2001-11) Consol. Ed. 1.2 (incl. am1 + am2) Electric cables - Calculation of the current rating Part 1-1: Current rating equations (100% load factor) and calculation of losses General (1993-12) Ed. 1.0 Electric cables - Calculation of the current rating Part 1: Current rating equations (100% load factor) and calculations of losses Section 2: Sheath eddy current loss factors for two circuits in flat formation (2001-11) Consol. Ed. 1.0 (incl. am1) Electric cables - Calculation of the current rating Part 2-1: Thermal resistance Calculation of the thermal resistance (1995-05) Ed. 1.0 Electric cables - Calculation of the current rating Part 2: Thermal resistance Section 2: A method for calculating reduction factors for groups of cables in free air, protected from solar radiation (1999-05) Consol. Ed. 1.1 (incl. am1) Electric cables - Calculation of the current rating Part 3-1: Sections on operating conditions Reference operating conditions and selection of cable type (1995-07) Ed. 1.0 Electric cables - Calculation of the current rating Part 3: Sections on operating conditions Section 2: Economic optimization of power cable size (1996-10) Ed. 1.0 Amendment No.1 to IEC 287-3-2 (1988-05) Ed. 2.0 Reactors (1990-12) Ed. 3.0 A.C. metal-enclosed switchgear and controlgear for rated voltages above 1kV and up to and including 52kV (1993-04) Ed. 3.0 Tests on electric cables under fire conditions - Part 1 : Test on a single vertical insulated wire or cable (1991-10) Ed. 2.0 Loading guide for oil-immersed power transformers (1971-01) Ed. 1.0 Specification and acceptance of new sulphur hexafluoride (1998-11) Consol. Ed. 1.1 (incl. am1) Power cables with extruded insulation and their accessories for rated voltages from 1kV(Um = 1,2kV) up to 30kV (Um = 36kV) - Part 1 : Cables for rated voltages of 1kV (Um = 1,2kV) and 3kV (Um = 3,6kV) (1990-10) Ed. 3.0 Gas-insulated metal-enclosed switchgear for rated voltages of 72.5kV and above (1994-11) Ed. 3.0 Amendment No.1 (1988-03) Ed. 2.0 Class 0.5, 1 and 2 alternating-current watthour meters (2001-02) Consol. Ed. 2.1 (incl. am1) Degrees of protection provided by enclosures (IP Code) (2001-10) Consol. Ed. 1.2 (incl. am1 + am2) Sound level meters (1999-10) Ed. 2.0 Insulators Tests on indoor post insulators of organic material for systems with nominal voltages greater than 1000V up to but not including 300kV (1992-06) Ed. 2.0 Alternating current static watt-hour meters for active energy (classes 0,2 S and 0,5 S) (2001-05) Consol. Ed. 2.1 (incl. am1) Common specifications for high-voltage switchgear and controlgear standards (1982-01) Ed. 1.0 Guide to the lightning impulse and switching impulse testing of power transformers and reactors (2001-07) Consol. Ed. 2.1 (incl. am1) Common test methods for insulating and sheathing materials of electric cables and optical cables - Part 1-1 : Methods for general application Measurement of thickness and overall dimensions - Tests for determining the mechanical properties (1999-02) Ed. 2.0 Power cables with extruded insulation and their accessories for rated voltages above 30kV (Um = 36kV) up to 150kV (Um = 170kV) - Test methods and requirements

IEC 60517 IEC 60517-am1 IEC 60521 IEC 60529 IEC 60651 IEC 60660 IEC 60687 IEC 60694 IEC 60722 IEC 60811-1-1

IEC 60840

116

Appendix 40
LIST OF STANDARDS
IEC Standards
IEC 60859 IEC 60885-1 IEC 60885-2 IEC 60885-3 IEC 60947-1 IEC 60947-7-1 IEC 61000-4-2 IEC 61036 IEC 62098 IEC 62271-100 IEC 62271-102 IEC 60068 IEC 60068-1-am1 IEC 60068-2-3 IEC 60068-2-11 IEC 60068-2-11 IEC 60068-2-30 IEC 60068-2-30-am1 IEC 60068-2-67 IEC 60068-3-4 IEC 60068-4 IEC 60068-4-am1 IEC 60068-4-am2 IEC 61000-1-1 IEC 61000-1-2 IEC 62067 (1999-07) Ed. 2.0 Cable connections for gas-insulated metal-enclosed switchgear for rated voltages of 72.5kV and above - Fluid-filled and extruded insulation cables - Fluid-filled and dry type cable-terminations (1987-03) Ed. 1.0 Electrical test methods for electric cables. Part 1: Electrical tests for cables, cords and wires for voltages up to and including 450-750V (1987-03) Ed. 1.0 Electrical test methods for electric cables. Part 2: Partial discharge tests (1988-07) Ed. 1.0 Electrical test methods for electric cables. Part 3: Tests methods for partial discharge measurements on lengths of extruded power cables (2001-12) Consol. Ed. 3.2 (incl. am1 + am2) Low-voltage switchgear and controlgear - Part 1 : General rules (1999-08) Consol. Ed. 1.1 (incl. am1) Low-voltage switchgear and controlgear Part 7 : Ancillary equipment - Section 1 : Terminal blocks for copper conductors (2001-04) Consol. Ed. 1.2 (incl. am1 + am2) Electromagnetic compatibility (EMC) Part 4-2 : Testing and measurement techniques Electrostatic discharge immunity test (2000-09) Consol. Ed. 2.1 (incl. am1) Alternating current static watt-hour meters for active energy (classes 1 and 2) (2000-11) Ed. 1.0 Evaluation methods for microprocessor based instruments (2001-05) Ed. 1.0 High-voltage switchgear and controlgear - Part 100 : Highvoltage alternating-current circuit-breakers (2001-12) Ed. 1.0 High-voltage switchgear and controlgear - Part 102 : Highvoltage alternating-current disconnectors and earthing switches (1988-06) Environmental testing. Part 1: General and guidance (1992-04) Amendment No. 1 (1969-01) Environmental testing - Part 2: Tests. Tests Ca: Damp heat, steady state. (1981-01) Environmental testing - Part 2: Tests. Tests Ka: Salt Mist. (1999-12) Corrigendum 1. (1980-01) Environmental testing - Part 2: Tests. Tests Db and guidance: Damp heat, cyclic (12 + 12-hour cycle) (1985-08) Amendment No. 1 (1995-12) Environmental testing Part 2: Tests Test Cy: Damp heat, steady state, accelerated test primarily intended for components. (2001-08) Environmental testing Part 3-4: Supporting documentation and guidance Damp heat tests (1987-09) Environmental testing. Part 4: Information for specification writers Test Summaries (1992-02) Amendment No. 1 (1994-03) Amendment No. 2 (1992-05) Electromagnetic compatibility (EMC) Part 1: General Section 1: Application and interpretation of fundamental definitions and terms. (2001-06) Electromagnetic compatibility (EMC) Part 1-2: General Methodology for the achievement of the functional safety of electrical and electronic equipment with regard to electromagnetic phenomena. (2001-10) Power cables with extruded insulation and their accessories for rated voltages above 150kV (Um = 170kV) up to 500kV (Um = 550kV) Test methods and requirements

117

Appendix 40
LIST OF STANDARDS
British Standards
BS EN 60051-1 (1999) [IEC 60051-1(1997)] BS 89-2 (1990) [IEC 60051-2 (1984)] BS 89-3 (1990) [IEC 60051-3 (1984)] BS 89-4 (1990) [IEC 60051-4 (1984)] BS 89-5 (1990) [IEC 60051-5 (1985)] BS 89-9 (1990) [IEC 60051-9 (1988)] BS 148 (1998) BS 159 (1992) BS EN 60076-1 (1997) BS 171-5 (1978) [IEC 60076-5 (1976)] BS EN 60060-2 (1995) BS 3938 (1973) BS 3941 (1975) BS EN 60214 (1998) BS 5207(1975) BS 5209 (1975) Direct acting indicating analogue electrical measuring instruments and their accessories. Definitions and general requirements common for all parts. Direct acting indicating analogue electrical measuring instruments and their accessories. Specification for special requirements for ammeters and voltmeters Direct acting indicating analogue electrical measuring instruments and their accessories. Specification for special requirements for wattmeters and varmeters. Direct acting indicating analogue electrical measuring instruments and their accessories. Specification for special requirements for frequency meters. Direct acting indicating analogue electrical measuring instruments and their accessories. Specification for special requirements for phase meters, power factor meters and synchroscopes. Direct acting indicating analogue electrical measuring instruments and their accessories. Recommended test methods. Specification for unused and reclaimed mineral insulating oils for transformers and switchgear. Specification for high-voltage busbars and busbar connections. Power transformers. General Power transformers. Specification for ability to withstand short circuit. High-voltage testing techniques. Measuring systems

Specification for current transformers Specification for voltage transformers On-load tap changers Specification for sulphur hexafluoride for electrical equipment Code of practice for the testing of sulphur hexafluoride taken from electrical equipment BS 5311(1996) High-voltage alternating-current circuit-breakers BS EN 60947-4-1 (1992) Specification for low-voltage switchgear and controlgear. Contactors and motorstarters. Electromechanical contactors and motor-starters BS 5685-1(1979) Electricity meters. Specification for class 0.5, 1 and 2 single-phase and polyphase, single rate and multi-rate watt-hour meters. BS 5685-2 (1986) Electricity meters. Specification for single-phase coin operated prepayment flat rate and two-part tariff watt-hour meters of class 2 and fixed charge collectors of class 2. BS 5685-3 (1986) Electricity meters. Specification for meters having class 1 electro-mechanical maximum demand indicators. BS 5685-4 (1986) Electricity meters. Specification for class 3 var-hour meters. BS 5685-5 (1987) Electricity meters. Specification for input and output switching or logic arrangements for multi-rate registers for electricity meters. BS 5685-8 (1991) Electricity meters. Specification for impulse operated multiple registers for use with induction electricity meters. BS 5730 (2001) Monitoring and maintenance guide for mineral insulating oils in electrical equipment. BS 5992-1(1980) Electrical relays. Specification for contact performance of electrical relays [IEC 60255-0-20 (1974)] BS 6231(1998) Specification for PVC-insulated cables for switchgear and controlgear wiring. BS EN 60044-2 (1999) Instrument transformers. Inductive voltage transformers [IEC 60044-2 (1997)]

118

Appendix 40
LIST OF STANDARDS
Singapore Standards
SS 318 (1987) SS 404 (1997) SS 404 (1997) SS 404 (2001) SS 404 (2001) SS 404 (2000) SS 443 (1998) SS ISO 9000 (2000) SS ISO 9001 (2000) SS ISO 9004 (2000) CP 5 (1998) CP 10 (1993) CP 16 (1991) CP 19 (2000) CP 31 (1996) CP 33 (1996) Current transformers for measurement and protection Power transformers Part 1: General Power transformers Part 2: Temperature rise Power transformers Part 3: Insulation levels and dielectric tests and external clearances in air Power transformers Part 5: Ability to withstand short circuit Power transformers Part 8: Application guide Part 1: Power cables with extruded insulation and their accessories for rated voltages from 1kV (Um = 1.2kV) up to 30kV (Um = 36kV) Cables for rated voltages of 1kV (Um = 1.2kV) and 3kV (Um = 3.6kV) Quality management systems Fundamentals and vocabulary Quality management systems Requirements Quality management systems Guidelines for performance improvements Code of practice for electrical installations Code of practice for the installation and servicing of electrical fire alarm systems Code of practice for earthing Code of practice for the installation and maintenance of emergency lighting and power supply systems in buildings Code of practice for installation, operation, maintenance, performance and constructional requirements of mains failure standby generating systems Code of practice for lightning protection

Other Standards
IEEE C37.09 ANSI C37.09 (1999) IEEE 32 (1972) ISO 7-2 (2000) AEIC CS2 (1997) AEIC CS4 (1993) ASTM B187 (2000) ASTM B3 (2001) Test procedure for A.C high-voltage circuit breakers rated on a symmetrical current basis Neutral grounding devices, req term and test procedures Pipe threads where pressure-tight joints are made on the threads Part 2: Verification by means of limit gauges Impregnated paper and laminated paper polypropylyne insulated cable highpressure-pipe type Impregnated-paper-insulated-low and medium pressure self-contained liquid filled cable Standard specification for copper bar, bus-bar, rod and shapes Standard specification for soft or annealed copper wire

119

Appendix 41
FORM CS/12
To: SP Services Ltd Fax No: 6823 8289

APPLICATION FOR ELECTRICAL INSTALLATION INSPECTION (UP TO 45KVA) I/We hereby request an appointment to inspect the electrical installation at the premises with SP Services Account No : (Please tick or fill in the appropriate boxes) An application for electricity supply service has been submitted earlier and approved. SP Services Application Reference No is:

OR
This is a new application. Form CS/5, together with Certificate of Compliance (COC), is enclosed. (Please note that CS/3 form is required for supply connection from Landlords Electrical Installation). Type of Meter Required: Singlephase Three phase Yes No new meter required No

Removal of old meter(s) :

*Preferred Dates : 1 ___________ (in order of preference) 2 ___________ 3 ___________

Morning Morning Morning

Afternoon Afternoon Afternoon

Remarks: ___________________________________________________________________ (*Your preferred dates shall be from the third working day onwards. If you do not give us your preferred date(s), we shall provide you with the earliest available appointment date & time. ) Signature : Licensed Electrical Worker : Telephone/ Handphone No : FAX NO : Pager No : _________________________________________________________________________________ Please note the following: 1. 2. 3. 4. For applications received before 3pm, it will be processed on the same day. For applications received after 3pm, it will be processed on the following business day. The granting of an appointment on the preferred date is at SP Services discretion and subject to availability. It is important that you provide us with your contact number and fax number. All applications are to be accompanied by Certificate of Compliance (COC). 120

09/06/2005

Appendix 42

APPLICATION FOR CONTESTABILITY STATUS

Name of Consumer (company):

Existing Electricity Account No : (if applicable)


(the Consumer)

Company Registration No:

Official Premises Address where supply is required:


(the Premises)

Mailing Address: (if different from the Premises) Contact Person:


* Requested Date of contestability:

Fax No: Contact Tel: E-mail:

1. I wish to apply to be a contestable consumer with respect to the premises stated above (the Premises) 2. In accordance with the Electricity (Contestable Consumers) Regulations 2003 or such further amendments thereto, I confirm that the Premises is a non-residential premises. 3. The phone number of the phone line connected to my meters for the purpose of remote meter reading is _____________. 4. I agree that my application for contestability is subject to my compliance with paragraph 3 above and that SP Services shall not be liable for any inconvenience, loss, expense and damage that may be incurred or suffered as a result of a delay or postponement of my compliance or non-compliance of paragraph 3 provided always that such delay, postponement or non-compliance is not caused by SP Services or is within its reasonable control. 5. If my application as a contestable consumer is approved, I agree to open an account with you for Market Support Services and to pay a Security Deposit for an amount declared and in the form approved by you within the time period stipulated by you. 6. I agree to be bound by the Conditions of Service (a copy which will be given to me), which shall take effect when I open an account with you for Market Support Services after being classified as a contestable consumer.

SIGNATURE: NAME: DATE:

COMPANY STAMP: DESIGNATION:

* Note :

(a) You shall be classified as a contestable consumer from such date as may be notified by SP Services Ltd and approved by the Authority. (b) This form should reach SP Services Ltd at least 12 business days before the Requested Date of contestability

SP Services Ltd 111 Somerset Road #06-05 Singapore Power Building Singapore 238164 Tel : 1800- 2338000 Website: www.mssl.com.sg Email: aboutmssl@singaporepower.com.sg Fax: 6820 6800

Updated 15 April 2005

121

Appendix 43

APPLICATION TO OPEN A MARKET SUPPORT SERVICES ACCOUNT


MSSL A/C No.
(For Official Use)

Name of Consumer (company):


(the Consumer)

Company Registration No:

Official Premises Address where supply is required :


(the Premises)

Mailing Address: (if different from the Premises)

Fax No: Contact Tel: E-mail:

Contact Person:

* Requested Date of Account Activation: (must be at least 12 business days from date of application)

Tick where appropriate


1. 2. 3.

I wish to apply to open an account for Market Support Services (MSS) for the above premises (the Premises). I confirm that I am a contestable consumer and have been notified by Energy Market Authority/SP Services through the Contestability Notice dated ______________. (Please attach the Contestability Notice). I will make arrangement to turn on the supply of electricity to the electrical installation of my premises on ________ (date), and I will send a confirmation to notify you of any changes. I confirm that I intend to move-in/take-over a contestable premises currently taking high tension supply. Contract Capacity : _________________ Contract Expiry date : _________________ I agree that my move-in/take-over of the premises is subject to the corresponding move-out of the existing consumer of the premises and I agree that SP Services shall not be liable for any inconvenience, loss, expense and damage that may be incurred or suffered as a result of a delay, postponement or cancellation of such move-out by the existing consumer, provided always that such delay, postponement or cancellation is not caused by SP Services or is within its reasonable control.
I agree that I will be billed from 00:00hrs on the date of move in/take over and up to 23:59hrs on the date I move out of the Premises.

4.

I intend to purchase my electricity supply from :


An Electricity Retailer Please specify Retailer Name :

Billing Option: * Split / Consolidated (delete appropriately)

Indirectly from the wholesale electricity market through SP Services Ltd


Directly from the wholesale electricity market

5. 6.

I agree to pay a Security Deposit for an amount declared and in the form approved by you within the time period stipulated by you or before the supply at the premises has been turned on, whichever is earlier. I agree to be bound by the Conditions of Service (a copy of which has been given to me) which shall take effect when this application is approved.

SIGNATURE:
NAME:

COMPANY STAMP: DESIGNATION:

DATE:

SP Services Ltd 111 Somerset Road #06-05 Singapore Power Building Singapore 238164 Tel : 1800- 2338000 Website: www.mssl.com.sg Email: aboutmssl@singaporepower.com.sg Fax: 6820 6800

Updated 15 April 2005

122

Appendix 44
COMPLETION CERTIFICATE FOR MODIFICATION OF SMALL ELECTRICAL INSTALLATION
To: SP Services Ltd 111 Somerset Rd #06-05 Singapore Power Building Singapore 238164

MODIFICATION TO ELECTRICAL INSTALLATION AT ____________________________ __________________________________________________________________________________________


(Address of installation)

MSSL Account No. : ____________________________________________________________ in the name of : ______________________________________________________________

I, ______________________________ certify that the modification to the above-mentioned electrical installation has been inspected and tested by me in accordance with Singapore Standard CP5: Code of Practice for Electrical Installations, and that to the best of my knowledge and belief the modification summarized below complies with the said Singapore Standard CP5 and the relevant Regulations. Description
Lighting points 13 Amp socket outlets 15 Amp socket outlets Heater Isolator Others (please specify)

Quantity

The said modification has been connected to the supply of electricity on ____________. The existing supply line is adequate for the after diversity maximum demand of the above-mentioned electrical installation. 2. I append below the result of my inspection and test:
Incoming supply MCB / Cutout size Revenue meter no RCCB rating Phase to Phase insulation Phase to Earth insulation Neutral to Earth insulation RCCB test satisfactory Polarity check satisfactory Earth fault loop impedance Date of inspection/test : : : : : : : : : : : SP PowerAssets Network / Third party electrical installation Amp Amp/30mA sensitivity Mohm Mohm Mohm Yes/No Yes/No ohm _________________

________________________________________
Name & signature of Licensed Electrical Worker cc Consumer

____________
Licence No.

____________
Date

REF: E(EI)Reg7(1) 201003

123

Appendix 45
FORM E
To:

CERTIFICATE OF FITNESS OF RESIDENTIAL UNIT


Application No. ____________________

Deputy Director, Installation Branch SP Services Ltd 111 Somerset Road #06-01 Singapore Power Building Singapore 238164

PROJECT:

AT APARTMENT BLOCK No. DATE OF TEST: Type/Total No. of Units MCB Rating

STREET NAME: POSTAL DISTRICT: /( units) /( units)

Others Details of Electrical Installation

MCB Type (Before & after Revenue Meter) Service Cable Size RCCB Rating / Sensitivity Cooker / Oven Point Water Heater Point 15A Socket Outlet 13A Socket Outlet Fan Point Lamp Point 20A isolator SPN 20A isolator TPN 30A isolator SPN 30A isolator TPN Others Unit Nos.

I hereby declare that I have supervised the installation, inspected and tested the electrical installation of the residential units(s) in accordance with the relevant Regulations and Code of Practice.

I hereby certify that the electrical installation of the residential unit(s) has been designed in accordance with the relevant Regulations and Code of Practice.

________________________________________ Signature/Name/Licence No. of LEW responsible for electrical installation work*

_____________________________________________ Signature/Name/Licence No. of LEW responsible for design of electrical installation*

*The same LEW may perform both design and installation work for the electrical installation.