Professional Documents
Culture Documents
1996/97
Contents
Message from the Managing Director, Power Systems Report Highlights Company Profile Quality of Supply Developments Company Targets System Performance 1996/97 Targeting Investments 1997/98 Capital Expenditure Analysis of System Performance 1996/97 Glossary of Terms How to Contact Us 2 3 3 4 10 11 17 19 22 23 25
Report highlights
Underlying CML per connected customer down 6.7% on 1995/6 to 61.9. Two periods of exceptionally severe weather add 47% to supply hours lost due to all the remaining unplanned incidents in 1996/7. Investment in Outage-Free working methods which allow work on live 11,000 volt overhead lines have avoided around 60,000 customer supply interruptions. Total outage time caused by planned work reduced by 55% since 1992/3. First installation of insulated 11,000 volt overhead lines completed. As a result of the December 96 storm, stronger overhead line construction specification to be piloted during 97/8. New incident recording and customer monitoring system introduced in April 97.
Company profile
ScottishPower distributes electricity to more than 1.8 million customers in 23,000 square kilometres stretching from Newporton-Tay and Helensburgh in the north to Stranraer and Holy Island in the south. This geographical area comprises contrasting topography from the denselypopulated industrial and urban areas of the Clyde/Forth Valley to the exposed and sparsely-populated areas of the Borders and Dumfries and Galloway. The map shows our four Regions and illustrates the differences in customer numbers and type of network used to provide supply.
Customers Overhead Network (km) Underground Network (km)
413,952 16,048km 573,777 12,359km 20,850km 675,983
CLYDE REGION
FORTH REGION
WESTERN REGION
13,823km
SOUTHERN REGION
140,353
Network Management
When an incident occurs on our network which disrupts the supply to customers, it is important that customers can contact us easily, advise us of their circumstances and obtain information about what action we are taking. Our Customer Service Centre now provides an improved 24 hour service, for customers to report problems with their supply on 0845 27 27 999. Calls to this Call Centre are dealt with quickly and efficiently to make sure that customers are given accurate up-to-date information. In January 1996, we opened a new Power Systems Management Centre (PSMC) in Hamilton at a cost of 5m to improve our efficiency and management of all incidents and planned work. Since then we have extended the system to our regional centres to allow us greater flexibility in managing our network. The PSMC includes a Control Room which uses a modern computerised network management system to control all network operations, and a Despatch Centre which provides dedicated staff to co-ordinate the activities of all our emergency staff. The duration of an outage depends on how quickly our field staff can rectify the problem, but more than 80% of our customers affected by incidents are now restored within three hours. To accelerate our supply restoration capacity we are investing 7m in distribution automation which will complete the fitting of remote control and alarm monitoring facilities at all 440 main substations. This work is on target to be completed by the end of 1998.
4
To improve our ability to accurately record incidents and identify those customers who suffer repeated interruptions to their supply, we are developing a new incident recording and customer monitoring system at a cost of more than 500,000. This system was implemented at the beginning of April 97 and will be enhanced during 1997 to improve our monitoring of the worst served areas.
Planned Work
ScottishPower and Manweb are leaders in the field of Outage-Free working and the Company integration has strengthened this experience. Special equipment and techniques have been developed to keep customers on supply while allowing us to conduct routine maintenance. This has resulted in a 55% drop in CML due to such planned interruptions, although we are conducting more maintenance. We now have 10 Outage-Free teams operating which have contributed to the significant reduction in CML shown on this graph.
Pre-Arranged CML per Connected Customer
Pre-Arranged CML
16 14 12 10 8 6 4 Pre-Arranged
92/3
93/4
95/6
96/7
Our market research tells us that customers see short-term interruptions to their supply as preferable to a longer time without supply. However we are aware that even a short interruption in supply is inconvenient. Modern electronic equipment often needs to be reset if it is unable to ride-through these short interruptions. Under European legislation manufacturers are working to make their equipment operate correctly during such supply interruptions. We aim to collect accurate statistics on the performance of our network and we are undertaking trials of equipment, similar to that shown here, which will provide us with the ability to monitor short-term interruptions. These Power Fail Monitors were installed last year as part of a programme to develop a reporting system. This work will continue during 1997/8 to ensure our information is accurate and reliable. Many circuits have measured no short interruptions and others have shown between 1 and 20 for the year. We wish to refine this work before reporting the results. We plan to provide an indication of the number of short term interruptions experienced by customers in our 1997/8 Quality of Supply Report.
120
4000
100
80
3000
60
2000
40
1000
20
91/2
92/3
93/4
94/5
95/6
96/7
91/2
92/3
93/4
94/5
95/6
96/7
Damage
Non-Damage
An example of the benefits we obtain from this targeted investment is shown in the graph. This shows that following the application of our overhead line protection policy to the 11,000 volt lines out of Dalbeattie primary substation in 1993/4, the level of customer hours supply lost due to non-damage incidents has fallen to less than 3.5% of its 1993/4 level.
By the end of 1996/7 we had installed this equipment on more than 190 circuits. Some of those which benefited from this equipment during 1996/7 are indicated on page 16 of this report. This program will be completed during 1997/8 with a further 50 circuits being targeted.
Slamannan
Aberlady Coldingham
Gifford Pathhead
Gordon St Boswells
Generators
Live working on 11,000 volt overhead lines will substantially reduce pre-arranged interruptions to customers supplies but some tasks are not possible to safely complete on live lines. Similarly there are other types of high voltage equipment, such as cables, transformers and switchgear which are not suitable for live working techniques. In these situations it may be possible to use a generator to maintain supply to customers while working safely on equipment. We plan to increase our use of generators in this way. We have developed techniques which allow generators to be used at high voltage without even a short interruption of customers supplies to allow the generator to be disconnected. This approach will allow us to maintain supplies to groups of customers affected by our rural upgrading programme.
process and service industry customers who are concerned about losing many hours of production because of these
supply disturbances which last less than one second. The ScottishPower area has one of the highest concentrations of
NUMBER OF DIPS
PCs are manufactured here, and we are addressing these customers' concerns by monitoring power quality. Our monitoring
DURATION
equipment produces power quality reports, showing the number, duration and severity of voltage depression, which we use to ensure we deliver high quality supplies and to assist customers in understanding their internal protection needs.
9
Company targets
Our strategic goal is to deliver excellent customer service and ensure a continuous improvement in the availability, reliability and security of supply. We have system performance targets to demonstrate this improvement, the most notable of which are: By 2000, to reduce total underlying CML per connected customer by 20% compared to 1991/2 to between 55 and 65 minutes. By 2000, to reduce total underlying customer interruptions to between 45 and 55 per 100 connected customers. By 2000, to target improvements to those customers who experience more than an average of three unplanned incidents in each separately protected section of HV network used to provide their supply. These company targets are consistent with regional performance in line with the tables below:
Availability
Customer Minutes Lost per Region Clyde Forth Western Southern connected customer by 2000 37-43 58-70 60-72 145-175
Security
Interruptions per 100 Region Clyde Forth Western Southern connected customers by 2000 32-36 55-65 47-55 105-125
This report shows that the underlying performance of our network is well on the way to achieving these targets. However, the unusually severe snow and ice storms of the previous two winters have masked the underlying improvement in our reported figures. We have described in this report the actions we are taking to achieve our targets and reduce the impact of future severe events. Through these efforts we expect the improvements to continue. We will however continue to review these targets to ensure our customers receive the highest possible quality of supply.
10
300
200
100
April 96
March 97
On the 6 November 1996 the Western region suffered from severe winds which gusted to more than 85 mph, amongst the worst for more than 20 years. These gales caused 188 incidents on our HV and EHV networks. On the 3 and 4 December 1996 southern Scotland was subjected to a severe snow and ice storm which caused extensive damage to our network. This caused 300 incidents on the HV and EHV systems and was centred on our Borders area as shown in the diagram overleaf. The damage caused to overhead lines by this storm was the worst that ScottishPower has ever experienced from a single event. The storm caused more than 400 wooden poles and steel towers to snap or buckle and conductors to break at 800 locations.
11
Stirling Edinburgh
Kilmarnock
The region's emergency plan was activated and at the peak of the storm more than 1000 staff, including 300 from Manweb and outside contractors were involved. Our contingency planning successfully allowed us to use these resources to restore the supplies to 40,000 customers affected by the storm. Despite all the efforts to restore supplies quickly during both these storms their combined effect was to add 26.7 CML to the company's performance, which represents 48% of the underlying CML performance for the whole year.
Availability
This graph clearly demonstrates the impact of the storms during 1996/7 which have been described earlier and which added 26.7 CML to the 1996/7 total. During 1995/6 severe lightning, wind and snow storms including the snow storm in Dumfries and Galloway during February, which triggered the Local Authority Emergency Plan, added 14.7 CML to the 1995/6 total. Availability
120 CML per Connected Customer 100 80 60 40 20 0
92/3
93/4
94/5
97/8
98/9
99/00
Over the past five years the underlying availability of supply due to unplanned interruptions, measured in CML, has improved by 33%. The underlying trend is shown in this graph by the 'weather corrected' line, which shows that we are on course to achieve our year 2000 target.
12
Security
Over the past five years the impact on security of supply from unplanned interruptions, measured in CI, has improved by 29%. The graph shows we are on course to achieve our year 2000 target. Security
CI per 100 Connected Customers 100 80 Total All Faults Pre-Arranged Target Weather Corrected 60
40
20
92/3
93/4
94/5
97/8
98/9
99/00
Quality of Service
As soon as we are aware that an incident has occurred which disrupts supply to customers we respond as quickly as possible. To help us monitor our speed of response we record the time it takes to restore supply to each customer and we have a target to restore 80% of supplies within three hours and 99% of supplies within 24 hours. During 1996/7 we exceeded both of these targets by restoring 80.6% of all supplies within three hours and 99.1% of all supplies within 24 hours.
Voltage Complaints
(See also Table 4 on page 22 of this report) Domestic customers make up the majority of our 1.8 million customers and receive their supply at 230V. European legislation requires this voltage to be between minus 6% (216.2V) and plus 10% (253V). We design our networks to maintain supply within this band under normal circumstances. However, due to increasing load on our network for example, customers may complain to us about voltage problems. Last year we investigated 1005 complaints, found 521 were valid and took action to rectify the problem. To ensure we rectify these problems quickly we have a target to rectify 95% of verified voltage complaints within six months. During 1996/7 we exceeded this target by rectifying 513 voltage complaints, equal to 98.5%, within six months.
13
Availability
The vast majority of ScottishPowers' customers, 1.66 million or 92%, reside in either the Clyde, Forth or Western regions. These customers experience an availability of supply which is better than that received by the average customer in the UK.
100
Clyde
Forth
Western
Southern
The graph shows that the supply reliability of the remaining 140,000 ScottishPower customers, who reside in Southern region, is extremely dependent upon the weather. In 1996/7 the storms in November and December accounted for more than 70% of the total CML during the whole year. The underlying performance of the network in Southern region is close to the national average and the improvement due to our continued efforts and investment can be seen. As a result of the storms we have experienced, and their unacceptable impact on the performance of our network, we are taking action to construct overhead lines which are more resilient in extreme conditions. The work we are undertaking was described on page 8 of this report.
14
Security
In general, our rural customers are those who are least well served. This is demonstrated by the figures for our Southern region which serves predominantly rural communities. It is for this reason that the majority of our investments which are specifically aimed at improving the quality of the supply we provide, are targeted at our rural area. Again the impact of the storms is highlighted in the above figures together with the national average. It is clear that the vast majority of ScottishPower customers experience a supply reliability significantly better than the national average.
Regional Unplanned CI
CI per 100 Connected Customers 200 95/6 150 96/7 Storm Contribution 100 1995/6 National Average
50
Clyde
Forth
Western
Southern
20
Clyde
Forth
Western
Southern
15
Craig Port William Rebuild overhead line + protection St. Boswells 33kV primary automation
16
36.6%
LV Incidents
24.2% 11.8%
HVU/G Incidents HV Rest Incidents
Pre-arranged
0.8% Transmission
EHV Incidents
17
4 3 6
6 3 16 3 6 14 8
Overhead protection policy Overhead protection policy Line rebuild Overhead protection policy Line rebuild Line rebuild Line rebuild
4 5 2
Line rebuild & overhead protection policy Overhead protection policy Overhead protection policy
7 3 18 5 7 2 6
Line rebuild and refurbishment Line rebuild Line rebuild Overhead protection policy Overehad protection policy Overhead protection policy Overhead protection policy
18
Capital expenditure
Actual & planned investment for five year period 1995/6 1999/2000
In October 1995 OFFER announced that, in setting ScottishPower's Price Control, they had assumed it would be necessary to spend 431.8m on the Distribution network during the five years 1995/6 to 1999/2000. OFFERs Published Price Control Assumptions m (1996/7 Prices)
Load Related Non-Load Related Total 233 198.8 431.8
We are currently spending more on quality improvement initiatives than allowed by OFFER in the Price Control Review and our future investment plans will deliver further service enhancements to our customers. A range of efficiency improvements have already been delivered and further savings are planned for the future; Improved procurement by taking advantage of market opportunities. Cost reduction through introduction of new designs, materials and techniques. Implementation of new Information Technology systems providing more detailed operational information about our network assets and enabling more effective prioritisation and targeting of investment. Improved work management systems and working practices. Against this background of cost savings, ScottishPower's latest capital expenditure projections are: ScottishPowers Network Capital Expenditure (1996/7) Prices)
Actual 1995/6 m Load Related Non-Load Related Total 44.6 39 83.6 1996/7 m 42.1 37.5 79.6 Planned 1997/8 m 50.1 36.7 86.8 1998/9-1999/00 m 90.5 70.4 160.9 Total m 227.3 183.6 410.9
19
20
A representative selection of the major projects (each with expenditure in excess of 100k) completed during 1996/7 and planned for 1997/8 are shown in Tables 1 & 2. Table 1 Examples of Major Projects completed during 1996/7
Region Clyde Forth Forth Southern Southern Southern Southern Southern Western Project Description Replacement of 11kV switchgear at Acredyke primary substation New housing development at Seafield, Kirkcaldy Replacement of 11kV switchgear & overhead line at New Inn, Kettlebridge Refurbishment of Dumfries GSP Penpont 33 kV overhead line Rebuild of Gatehouse Tongland 33 kV overhead line Replacement of 11kV switchgear at Newton Stewart primary substation Extension to Dumfries GSP, 33 kV substation Connection of a 21MW Windfarm at Gallowrigg Replacement of 11kV switchgear at Girvan primary substation
Gallowrigg Windfarm
21
Table 3 - Availability No. of Supply Minutes Lost per connected customer due to:a) Distribution faults LV (Inc. Services) HV Overhead HV Underground HV Other HV Total EHV Transmission Total faults b) Planned outages Total from all causes (a) + (b) Correction for extreme weather events 42.1 1.5 43.6 0.4 68.5 4.7 73.2 12.9 60.3 82.6 3.5 86.1 21.0 65.1 305.7 38.6 344.3 214.9 129.4 11.4 1.5 22.9 5.0 29.4 1.3 7.5 23.0 23.3 11.8 58.1 2.9 12.3 29.2 18.1 12.7 60.0 10.3 5.0 213.7 16.4 19.5 249.7 51.0 9.7 32.4 21.4 10.4 64.3 7.8 0.7 82.5 6.1 88.6 26.7 61.9
Total corrected for extreme weather events43.2 Table 4 - Voltage Complaints Verified Voltage complaints per 10,000 connected customers 0.89
4.16
3.21
3.99
2.89
Notes for tables 2 and 3: 132kV faults aggregated at Company level. Weather correction = 6/11/96 and 3-4/12/96 replaced by an average day.
22
Glossary of Terms
Availability A measure of the time the supply is not available, generally expressed as the average number of minutes per connected customer the supply is NOT available. CHL CI Customer Hours Lost Customer Interruptions, generally expressed as the average number of customer interruptions per 100 connected customers. CML Customer Minutes Lost, generally expressed as the average number of minutes per connected customer the supply is NOT available. Extra High Voltage (EHV) Nominally operating at greater than 22,000 volts but less than 132,000 volts. This usually refers to 33,000 volts. High Voltage (HV) Nominally operating at greater than 1000 volts but less than 22,000 volts. This usually refers to 11,000 volts. Incident An event which causes an uncontrolled flow of electrical current, followed by supply disconnection. Kilovolt (kV) Non-damage incident 1000 volts An incident which causes no permanent damage to equipment and therefore requires no repairs to be undertaken. Outage Free Methods of undertaking work on 11,000 volt equipment without interrupting supplies to customers. Overhead protection The use of electronically controlled links together with automated switches to restore supplies following an incident and, where necessary, disconnect damaged equipment leaving the minimum number of customers without supply. Pre-arranged This term is used to refer to planned interruptions in supplies to customers which are notified to the affected customers at least two days in advance.
23
Refurbishment
A planned replacement or renewal of existing equipment as it reaches the end of its useful life.
Security
A measure of the number of supply interruptions, generally expressed as the number of supply interruptions per 100 customers.
Short interruptions
Interruptions to customers supplies which last less than 60 seconds. Their duration is typically about 10 seconds.
Substation
Switchgear
Automatic or manual mechanical devices for controlling the flow of electrical energy into a circuit or item of equipment.
Underlying performance
A measure of the performance of the system which excludes the affects of identifiable severe events.
Voltage Dip
A sudden sag in the voltage, typically in the range 10% to 30% of the sinusoidal voltage.
24
How to contact us
If you have any questions or comments following your study of this report please write to the Regional Manager at your local regional office. ScottishPower plc Clyde Region St Vincent Crescent Glasgow G3 8LT ScottishPower plc Western Region Leven Street Motherwell ML1 2RA
CLYDE REGION
FORTH REGION
WESTERN REGION
SOUTHERN REGION
25
Scottish Power plc, Registered Office, 1 Atlantic Quay, Glasgow G2 8SP. Registered in Scotland No. 117120
CH
A RT
ER
ARK