Professional Documents
Culture Documents
Utility options
Heat Fuel PROCESS Electricity Electricity Heat Cogen Plant Fuel SHP Electricity Power Plant Fuel Cogeneration
BOILER
Heat
Cogeneration Concept
Boiler 90% Power plant 40% Where is the scope for improvement? Cogeneration- Simultaneous generation of heat and power (motive power or electricity) CHP- Total Energy Second Law of Thermodynamics Concept of Exergy
Evaluation Criteria
Relative Fuel Savings Rf Fuel savings over separate heat & power generation Rf = ( Fnc Fc) / Fnc Fnc = Fboiler + Fpower plant Fuel Chargeable to Power (FCP) The incremental fuel in cogeneration is charged to the power generation. FCP =( Fc Fboiler)/ W kg of oil/kWh, kJ/kWh, Nm3 gas/kWh, kg of bagasse/kWh
Cogeneration Concept
Process boiler , sat steam at 180 C 90% (1st law eff) Tu= 180+273 =453 K, T0 = 300 K II=Qu(1- T0 / Tu)/ Qin (for fuel 1.0) =0.9(1-300/453) =0.3 (30%) Increase generation temperature to 400 C and pass through an expansion turbine
is = h1-h2 h1-h2i
2 2i Specific Entropy s
Example Problem
A process boiler generates 25T/hour of saturated steam at 10 bar absolute. The fuel used is LSHS. The boiler efficiency is 90%. The power requirement of the industry is 2.5 MW. Evaluate the viability of using a high pressure boiler generating steam at 50 bar 400 C and a back pressure turbine
Power
C Air
Steam to Process
Suppl Fuel
Stack
Cogeneration
Self generated electricity in Chemical 42% of total elec, 86% from cogeneration plants Average price only 57% of grid price Purchased electricity declining (-0.4%), self generated elec increasing at 21.3% per year Evaluate viability of Cogeneration If heat/power loads small-Cogeneration for group of industries
Operating Strategy
Standalone/ Isolated Grid Interconnection
Parallel with Grid Only Buying from grid Buying and Selling to Grid
5 8 T /h r
F eed w ater
4 .5 T /h r B O IL E R
0 .5 T /h r
2 7 T /h r
2 6 T /h r
PRDS
BA G A SSE 0 .5 T /h r M IL L IN G
PRDS
6 a ta
~ P ro cess
2 .5 M W STEA M T U R B IN E
2 a ta
F la s h e d C o n d e n sa te
P ro cess
S c h e m a tic o f ty p ic a l 2 5 0 0 tc d S u g a r fa c to r y
Options
A- Replace mill turbines by motors + power turbine by efficient motor B- New Boiler 43 ata 480 C + additional TG C- HP Boiler 65 ata 480 C + additional TG D C+ replace mill turbines with TG E similar to D but with condensing extraction turbine
B O IL E R F e e d w a te r
75 TPH , 65 a ta , 4 8 0 O C
STEA M T U R B IN E 13 M W 9 .5 M W P ow er export
BA G A SSE
( A lt e r n a t e f u e l) ~
PR O C ESS 2 a ta 2 a ta
CO NDENSER
Condenser
6 a ta 4 .5 T P H
1 .0 M W M ill d r iv e s
BFP PR O C ESS
2 .5 M W C a p tiv e lo a d
P R O P O S E D P L A N T C O N F IG U R A T IO N : O P T IO N 2
Comparison of Options
Case A B C D E Output 5.4 MW Export 1.9 MW kWh export /tc 18 48 41 69 91
Constraints
Equipment Characteristics Min/Max Process Steam & Electricity Loads Grid Interconnection
Objective Function
Minimise annual operating cost (Maximise revenue)
WHRB-1
G
Gas turbine -1
20 MW
Supp. Firing LSHS 5.6 T/h WHRB-2 136 T/h Grid 7.52 MW Process Load, 60 MW
Gas turbine -2
20 MW
BUS SHP Steam 100 bar,500o C 117.1 T/h 60.6 T/h Process Load,150 T/h 76.2 T/h ST
12.5 MW
G4
Process Load,125 T/h PRDS-1 PRDS-2 HP Steam 41b,400 oC MP Steam 20b, 300 oC
20 T/h
Process Load
40 T/h
40 T/h
16.2 T/h
LP Steam 5. 5 b, 180 oC
Deaerator
Feed water 426.5 T/h
25 20 15 10 5 0
21.6
flat tariff
17.6
TOU tariff
peak period demand 11 MW 0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Time hours
40 30 20 10 0
flat tariff
TOU tariff
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Time hours
Summing Up
Even in industries with cogen Retrofits for additional power generation Sugar 2500 tcd plant can generate 9.5 MW surplus by using high pressure boilers Grid Agreement Parallel, Buying/Selling Optimal operating strategy can result in significant savings Significant potential in process industries
Thank You