Professional Documents
Culture Documents
Similarly, the scope of the project can be summarized below: Review of existing study, reports, standards and specifications Study of the topographical map along the road corridor Detailed engineering survey of the alignment and its corridor Conduct hydrological studies for cross-drainage works and propose suitable cross drainage structures List the various trees and other structures that needs removal during the upgrading of the road alignment To give preventive measures and appropriate solutions for critical sections To be familiar with the methodology behind the construction of low cost rural roads Better usage of local resources during soil stabilization and landslide protection Familiarity with rural road construction techniques alongside pavement constructions Preparation of working drawings of plan, profile, cross section of the road Preparation of quantity and cost estimates Preparation of survey and design reports Explore and recommend sources of basic road construction materials Using compendium of cadastral maps of the road with the plan of exiting road networks
1.3 Methodology
The methodology for alignment survey adopted for the completion of the project has been described below. However desk study was required to familiarize with the project which was carried out within the project group in the college premises that included the following: Study of various information regarding environment friendly roads Review of all available information, reports and documents pertaining to proposed alignment Careful study of topographical map and its interpretation Locating the alignment for the project But before a highway alignment is finalized in highway project, the engineering surveys are to be carried out. The surveys may be computed in four stages. The first three stages consider all possible alternate alignments keeping in view of the various requirement of
highway alignment. The fourth stage is meant for the detailed survey of the selected alignment. The four stages of the engineering surveys are: A. B. C. D. Map study Reconnaissance Preliminary survey Detailed survey
A. Map Study When the topographical map of the area is available, it will be easier to find out alternate path of the highway. In Nepal, topographic maps are available from the department of survey, Government of Nepal. Then, it is possible to suggest the likely routes of the road. The new maps are available in 1:25,000 to 1:50,000 scales. The main features like rivers, hills, and valley are carefully shown in colours in these maps. By the careful study of such maps, it is possible to have an idea of the several possible alternate routes so that the further details of these may be studied later at the site. The probable alignment can be located on the map from the following details available on the map. Alignment avoiding valleys, ponds or lakes When road has to cross a row of hills, possibility of crossing through a mountain pass Approximate location of bridge site for crossing rivers, avoiding bend of the river, if any. When a road is to be connected between two stations, one on the top and the other on the foot of the hill, then alternate routes can be suggested keeping in view the permissible gradient ; say the ruling gradient. Hence, from the map study, the alternate routes can also be suggested .It may also be possible from map study to drop a certain route in view of any unavoidable obstructions or undesirable ground, en route. Thus, map study gives a rough guidance of the routes necessary for the survey.
B. Reconnaissance It is the second stage of surveys for the highway location. A field survey party inspects a broad section of land along the proposed alternative routes of map in the field using simple
3
instruments like Abney level. All relevant details not available in the map are collected and noted down. Some of the details to be collected during reconnaissance are mentioned as follows: Valleys, ponds, lakes, marshy land, ridge, hills, permanent structures and other obstruction along the route, which are not available in the map study. Approximate value of gradient, length of gradient and radius of curves of alternative alignments. Number and types of cross drainage structures, maximum flood level and natural ground water level along the probable routes. Soil type along the routes from the field identification tests and observation of geological features Sources of construction materials, water and location of stone quarries. When the road passes through hilly or mountainous terrain, additional data regarding the geological formation, type of rocks, dip of strata, seepage flow etc may be observed so as to decide the stable and unstable sides of the hill for highway alignment. For the vast area or when terrain if difficult, reconnaissance may be done by aerial survey. From the details collected during the reconnaissance, the alignment proposed after map study may be altered or even changed completely for better design of road. C. Preliminary survey The main objectives of the preliminary survey are given as below: To survey the various alternate alignments proposed after the reconnaissance and to collect all necessary details of topography, drainage and soil. To compare the different proposals in view of the requirements of a good alignment. To finalize the best alignment from all considerations. D. Final Location and Detailed survey The alignment finalized after the preliminary surveys is to be first located on the field by establishing the centreline. Then, detailed survey should be carried out for collecting the necessary data for the preparation of plans and construction details for the highway project.
Benchmark Benchmark is a relatively permanent point of reference whose elevations with respect to some assumed datum is known. Plan It is the vertical projection of a map. It consists of North line Location of IPs and BMs with references The road centreline, formation width and right of way. Levelling It is a branch of surveying. The objective of levelling is to find the elevations of given points with respect to a given elevations or at a different elevations with respect to a given or assumed datum. Levelling deals with measurements in a vertical plane. For the purpose of road construction, the profile levelling is carried out to determine the R.L. of the centreline, located with driven pegs. The levelling determines the alignment of the road. Generally, the levelling is taken at the interval of 20m chainage.
B. Watershed Value Situated in Northern part of Kathmandu, Shivapuri Park is one of the primary sources of freshwater for Kathmandu valley. The park is bestowed with an abundance of streams/streamlets. The park provides over 40% of the drinking water to the Kathmandu valley. About 30 million litres of water per day is tapped from Bagmati, Syalmati, Bishnumati, Nagmati, Sangla, Mahadeva and Tusal Khola. There are reservoirs in Sundarijal to supply water to the Kathmandu valley and hence is the lifeline of the capital city. C. Flora and Fauna The park is in transition between sub tropical to temperate regions. There are more than 1250 species of flora. About 129 species of mushrooms have been reported. Pine, Oaks, Rhododendrons are the dominant vegetation of the park. The vegetation can be categorized into four types: Lower Mixed Hardwood Forest (1350-1500m) Chirpine Forests (1350-1600m) Oak Forest ( 2300-2372m) Upper Mixed Hardwood Forest (1500-2732m) Corresponding to rich floral diversity, Shivapuri Nagarjun National Park supports rich faunal diversity with number of protected, threatened and endemic species. It is an abode of a wide range of vertebrates. There are more than 22 species of mammals, out of which 5 species are protected list and includes the Pangolin and Leopard. Ghoral, Mongoose, Bats, Porcupine,Himalayan Black Bear, Barking Deer, Flying squirrel etc .
3.1 Geology
The alignment of the road section passes with various areas of Shivapuri- Nagarjun National Park. The project area if part of the hilly region in route to Chisapani trekking route situated at Nuwakot district .The soil composition was generally ordinary soil, soft- clay, hard soil with BMS (boulder mixed soil) and GMS(gravel mixed soil). In some areas there was the presence of soft rock and hard rock and due to backhoe excavation in certain portion of the route, there was significant presence of fill soil.
Development Committees under the co ordination of Department of Local Infrastructure Development and Agricultural Roads (DOLIDAR).
12
Optimum use o locally available materials in terms of labour an finances Generation of short term, off farm employment opportunities using labour based road construction and maintenance techniques.
3.3.2 Principles
An environmental friendly road is characterized by construction methods described by the green road concept. It has a relatively low initial design standard in terms of surface treatment and curvature of horizontal alignment in order to keep costs low. In fact, these roads are low-cost, low-volume, fair weathered earthen road. Generally constructed in villages they need to be integrated well into the present environmental conditions taking into consideration about the future implantations that might arise due to increase in traffic volume. Hence greater emphasis is given to the selection of a smooth longitudinal alignment that allows progressive upgrading in the future. A set of basic principles describes the concept mentioned above is listed below: 1) Political and Strategic Principles Participatory rural road network planning Preservation of the fragile mountain environment Optimum utilization of supportive natural processes 2) Technological and Technical Principles Promotion of appropriate labour based technology Application of labour intensive road construction methods 3) Organizational, Institutional and Administrative Principle Performance based work assignment methods Decentralized decision making, concern planning, road ownership etc 4) Social and Socio-Economic Principles Integration of local circumstances into implementation Self help promotion and local capacity building 5) Economic and Financial Principles Collective financial and public audit Sustainable maintenance
14
will ensure that the cut materials are used for fill on the valley side or low laying formation and will not be thrown down the slope. The typical cross sections of both green road cut-fill and conventional cut throw method differ in their modes of implementation. c. Use of Bio Engineering Techniques Soil bioengineering techniques is the use of vegetation alone or in conjunction with some small scale civil engineering structures to reduce the shallow seated erosion, and to stabilize the slope. It is an important part of environment friendly construction and is a preventive measure. Using this technique, the surrounding environment and landscape can be maintained so as to preserve the mountain ecology even during the construction phase. d. Proper Water Management To reduce the extra slope cutting and minimize the quantity of excavation, side drains are provided only along necessary places where water needs to be drained to the mountain side. Generally and outward slope of 5 % is provided for drainage purpose. Where possible the natural slope is used to disperse water towards the valley side in a controlled way. In places where water needs to be drained to the mountain side, proper side drains are provided to remove water as soon as possible. e. Phase Construction The construction of road in hills and mountains with fragile geology and difficult topography is done in phase wise. In total of three to four phases construction work completes. In the beginning, a track of 1 to 1.5 meter width is opened. Then gradually the track is opened to the required width by cutting on the hillside and filling on the valley side. Another phase of construction is only started after the track gets naturally compacted over one monsoon. Finally the road is completed with all necessary structures and applying soil bio engineering techniques to maintain sufficient vegetative coverage along the road side slopes to prevent slope failures and erosion. f. Labour Based Construction The construction is carried out through the use of local labour. As technology is labourintensive, no machines and heavy equipments will be used. The construction work is done during the slack agricultural season, usually during October to May. Thus it brings
16
employment opportunities to the local rural people who would otherwise migrate elsewhere to look for employment opportunities. g. Local Capacity Building Training is provided to various people at local level to build the capacity of the local people involved or intend to involve in the construction and maintenance of roads. Different types of training are required for different groups of stakeholders. Generally, training on management of construction works, supervision of works, accounting and other construction related works are provided prior to the construction of an environment friendly road. Further livelihood related income generating activities are also implemented in the project area forming various self-help groups among the project beneficiaries. h. Use of ordinary tools/equipments and other local resources In these road construction techniques, the construction works are generally accomplished through the use of ordinary tools and equipments which are easily available in the villages. Mostly hammer and chisel are used to break the rocks. Heating and drilling are also done in some areas where as blasting of rock is not allowed as it might cause unnecessary damage to the surrounding environment. No heavy equipment is used equipment is used to construct and materials are usually transported via wheel barrows. However, tractors with trailers are used to transport stones or sand over longer distances when necessary. Emphasis will be given on optimum use of local stones, gravel and plant materials those extracted during excavation and available nearby construction sites. As the materials at site are used in construction, the transportation of construction materials over a long distance is not required.
A decentralized approach with the involvement of different stakeholders is required to implement the design of these roads. However, the road department does not follow this approach rather it follows a system with a chain of command within the department.
3.6 Organization and Management The support for the construction of environment friendly roads consists of technical and social mobilization assistance. A principle behind technical support is that these technicians would live and work with the local people on-site. They would work directly with people building the road rather than preparing elaborate detailed drawings, designs and reports that few people read. The nature of technical and social mobilization support are as follows: Technical support can be provided by a local engineering consultancy firm that has engineers, overseers, sub-overseers, senior supervisors and social experienced this field Alternatively non-governmental organizations can be recruited if they have sufficient technical staff. Technical support for single project is provided either by an engineering consultancy firm or by an NGO but not mixed between these two. Technical support is provided during the construction period only and ceases once the road is complete, while support may be extended to help institute a proper maintenance system by training and system development, it is important to avoid dependency on technical support for recurrent activities The following pre-conditions are to be met prior to start of the project All parties involved in the project must agree to adopt the environment friendly principles Local people constructing roads using labour intensive methods Local representatives from a user committee which takes responsibility of construction and future maintenance( including local resource generation) The DDC and VDC agree to provide resources to the user committee to meet future maintenance and rehabilitation costs The DDC agrees to provide its technical manpower for the future maintenance and rehabilitation programmes
18
mobilizes
i. ii. iii.
A muster-roll system A lump sum piecework system Payments based on work measurement and valuation assigning contractors (i.e. with competitive bidding)
B. Organizational Set Up This system of site organization of labour has proved successful for supervision and quality control. C. Typical Working Period Labourers Work is undertaken for only six months of the year about 150 working days i. Higher altitude areas : the best off-farm working period avoiding the monsoon and winters are Oct-Nov and Feb-May ii. Lower Altitude Areas: The approximate working period to avoid the farming season , monsoon and heat is Nov- April In the monsoon season only Bio- Engineering activities and preventive maintenance work are undertaken Technical Team June- Oct: Planning, reporting, surveying and annual leave Oct- May: Field work at the site for lower altitude areas Jan-Feb: Site work in low altitudes or preparatory works at higher altitude Store and Site Management Experience has shown that the technical teams most effectively provide store management in the projects. Since the project is carried out using only local resources, user committee members also manage storekeeping with a view to minimize costs and the workers work in tandem to solve the arising problems in the site.
20
3.7
Social Arrangements
A. Social Mobilization Support
Self help promotion is provided by social mobilization support who are recruited by the consultant or the NGO whose assignment includes group mobilization tasks or additional work if portions of wages are pooled into savings and loan fund at the group level. As an expression of self-help local people and institutions contribute the following: Voluntary labour is contributed as a contribution in kind of fixed number of days per household per year in the off-farm season Land for road is contributed and obtained after compensation Local construction materials ( stone, gravel, sand , soil and planting materials ) are other forms of contributions Representatives serve on committees without salary, although they may receive allowances to meet expenses
B. Self-Help Local Level Capacity Building The major focus of environmental friendly roads is on local capacity building. Training efforts are integrated into the construction work. Experience has shown that trained people often provide an invaluable source of human resources for neighbouring districts and subsequent roads or other infrastructure projects, as well as for later maintenance, rehabilitation and upgrading works. C. Gender Issues This approach does not discriminate against women in wither work or wages instead encourages their involvement in the committees and training. Policies that require a certain involvement of women workers and it have been found to be advantageous for the local community. Sometimes separate women groups and women local supervisors make this kind of involvement socially more acceptable. This approach also recognizes areas of work where women perform better than men, and encourages women to be involved in those areas more than others. They are better in transporting stone, gravel, sand planting materials as well as collection transportation, supply of materials using spades assisting masons with wall construction. The income thus generated is further used to stabilize the economic status in the family.
21
water management structures prepared beforehand are used. Most important is that the road follows a smooth longitudinal gradient with an average of 7% and a maximum of 12%. The horizontal alignment generally follows the natural contour, but can be gradually improved in the major rehabilitation works later on. After selecting the optimum alignment, the minimum requirement for a technical survey works is the following: Longitudinal alignment setting is done with Abney Level or levelling instrument, staff and measuring tapes. Road Centreline Pegs are fixed at intervals of 20m,and the cross slope at each peg point is measured as in line with the road alignment and corresponding chainages & bench Marks are established at intervals of 500m. A local plant availability survey is conducted at certain intervals to identify suitable plants, which could be later used for bioengineering purposes. A land-use survey (forest, agricultural land, pasture land, rock cliffs, etc.) and a soil survey (earth, gravel, rock, conglomerate, etc.) are carried out. Simple and robust survey instruments are to be used for survey and construction supervision works. Some of the most essential instruments are listed here as follows: Measurement tapes of different lengths (5m, 30m, 100m, etc.) Ranging Rods Abney Level Magnetic Compass Camera Engineering Level with Horizontal Compass and Circle Staffs Plumb Bobs Theodolite Total Station Instrument (if applicable) A typical Design Report would consist of the following: Longitudinal Profile of the Road Alignment (1:1000 Horizontal and 1:100 Vertical) Horizontal Plan of the road on an existing topographical map (1:25000 or 1:50000) Cross Sections at given intervals and typical cross sections of varying mountain slopes. Detailed cross Sections at critical areas including layout plan in contour maps, if necessary, especially at switchbacks.
23
Typical type designs of structural works, such as retaining walls and water management structures. Estimate of quantity and cost of different work items, preferably for each construction phase, and finally number of skilled and unskilled labour person. Days Required (Please refer to Annex G for work specifications and work norms) Quantity and cost of construction materials to be procured from outside (cement, gabion wires, etc.)
24
Careful, gradual formation of the road platform as a terrace, and its road slopes through a phase-wise widening process that allows natural stabilization. Actually taking advantage of heavy monsoon rains to promote controlled natural compaction and settlement of back-filled material Using flexible, or soft, retaining structures that are less prone to failure due to often unpredictable unstable foundations and slopes.
all relevant stakeholders. Relevant studies (economic, environmental, and social) will be required to sufficiently justify the needs for upgrading. DORs concepts of staged construction are as follows: Stage I: Fair weather Earthen Road is the first construction stage- a low cost, low volume, fair weathered, single lane earthen road with necessary bypasses Stage II: Gravel Road is the second stage of construction designed to a higher volume of traffic. The road geometrics are improved, the surface is gravelled and the cross sections are improved by widening as well as by providing better retaining and water management structures. Stage III: All weather Bituminous Road is the final stage of construction. The road is finally bought to all- weathered road with bituminous surface with further improved curves, culverts and bridges and better provision of retaining and water management structures.
26
B. Labour- Based Construction It utilizes labour based construction methods where the local labour resource is utilized during the slack period. These human resources can be properly utilized if the local people are mobilized for construction activities during the off-farm season. C. Rock Cutting Techniques Environment Friendly Road Concept does not support the blasting of rocks, as hard rocks are often encountered in the mid-hills of Nepal. Blasting of rocks can disturb the fragile mountain slope stability and the natural sub surface water drainage system. Blasting of rocks increases the risk of landslides tremendously during the monsoon. Many landslides are developed along the road at the sections if blasting is done during construction. i. Chiselling and Hammering
For soft rocks such as sandstone and schist, which crumble generally into pieces, cutting can be done manually by chiselling and hammering. Kingpin chisel would be the most appropriate for this purpose which can also be done is case of less hard medium rocks. ii. Heating and Breaking
Medium rocks such as limestone and dolomite can be broken down into pieces by heating and breaking. Rocks are heated by using fire woods, after heating for a few hours water is poured into it, which will develop cracks on the rocks. Simple tools such as crowbar, chisel and hammer can be then used to finally break the rocks. D. Haulage and Transportation of Excavated Materials Haulage and transportation of construction materials is one of the most important road construction activities. Better management could increase the construction speed as well as efficiency. Some of the methods adopted are listed below Manual Haulage Haulage by Wheel barrows Transportation by vehicles i.e. tractor trailers in accessible areas
27
E. Construction Materials A re-utilization of locally available natural resources obtained from excavation is strongly recommended which is economic and environment friendly. However, it needs proper know-how and management skills. Excavated soils, rocks and top-soil and vegetation are the primary construction materials which are listed below: Excavated stones can be used for horizontal as well as longitudinal back filling works; excess soil is used for widening the roads at passing zones, gullies and switchbacks Stone can be used for construction of dry stone masonry walls and gabion walls along with water management structures. The stone obtained from excavation are to be slacked along the road and re-used later for these structures. Gravel can be used for spot surface improvement of critical(steep, moist etc) road sections Vegetation and topsoil can be used for turfing and re-vegetation of the hill slopes. Local people are generally familiar with the local construction materials and with their knowledge and skill the road construction is cheaper but also makes the roads easily maintainable. Hence this concept envisages the use of locally available indigenous skills and knowledge for the construction procedure. F. Use of flexible Retaining and Cross Drainage Structures Construction of flexible soft structures compared to the conventional hard structures such as cement concrete is promoted, as foundation of such structures can adjust themselves to the instability of mountain slope. These soft structures can be listed as follows: Dry stone masonry retaining wall up to maximum 3m height Gabion retaining wall up to maximum 10 m height Composite walls with gabion at bottom and dry stone wall at top Gabion check dams for gully control works Dry stone masonry side drains Catch drains and French drains for road slope drainage Dry stone causeways with stone soiling Dry stone rip rap or stone pitching for slope protection Dry stone skipper culverts i.e. truncated culverts
28
Hume pipe culverts as cross drainage structures in combination with dry stone walls Vented floodway with Hume pipes Flexible soft structures are preferred over the concrete structures because, they are: Comparatively cheap as locally available materials and skills are used Relatively easy to construct as locally trained workmanship can be developed Easy to maintain as the local manpower can use construction for the maintenance works the skills learned during the
G. Natural Compaction Use of natural rain for compaction purposes is recommended. With environment friendly road utilizes natural means than the mechanical one. Construction activities are carried out during the dry season and the road is allowed to settle down over the monsoon period after each construction phase. Monsoon rains compact and stabilize the fill material. This process makes optimum use of available natural forces that makes the road cost-effective. Ramming is also required, if a strong foundation is needed for retaining structures. However, manual compaction methods, such as ramming can be applied, if Critical road sections are encountered Speedy construction is needed Enough funds are available
H. Tools and Equipments This technique supports the promotion and use of locally available tools, primarily agricultural tools, suited to the labourers for their day to day works and environment. Appropriate hand tools are used and simple tools such as spade, axes etc can also be purchased from local blacksmiths. Other tools such as good quality shovels, picks etc can be procured from the local market. The tools must be of good quality and be supplied in sufficient quantity to achieve speedy construction and maximum efficiency. Appropriate and robust pneumatic wheel barrows are required for transporting the construction materials.
29
4.2.2Geometric Design
Considering design speed, the existing road geometry etc design standard is adopted.
some special locations that are not connecting by the direct routes, and some time to avoid geological features that are unsuitable for the construction of road. However, due consideration should be given while introducing the curves, the effect it will bring and other factors. Several studies have been carried out to investigate the effects of curves. The studies have showed higher accident rate in the curve section than tangent, and the rate of accident increases as the radius of curvatures is decreased. Vehicle operating costs are higher in the curvilinear nature of the alignment. The essence of curve also increases the total construction cost. However, roads are sager with some curves rather than only straight ones, as the attention of the driver is enhanced by the presence of the curves. The journey time substantially increases in the rods with low radius curves. Finally, design speed and topography have high deciding roles in the provision of curves. More undulated and rugged terrain requires more curves. A horizontal cure serves for change in direction to the centreline of a road and safe turning to the vehicles in horizontal plane.
force, which cuses it to slide outwrd, away from the centre of curvature.
31
Where the coefficient of lateral friction or side friction factor, g is the acceleration due to gravity, M is the mass of the vehicle. The quantity neglected. If = ( + ) Where is the centrifugal acceleration? If v m/s is replaced V Km/h and g = 9.81 m/s2
+ +
This is known as minimum radius equation. If design speed and super elevation Are known it enables the minimum radius to be determined for an acceptable level of side friction (and of drive comfort). later friction ( = 0) 127 = ( + 0) The maximum super elevation is obtained without taking into account the coefficient of
= ( + )
In this case, the driver does not require adjusting the steering wheel. The minimum super- elevation is obtained in the case if taking into account the full value of the coefficient of later friction. 127 =
In some countries super elevation are normally provided only for balance about 45 percent of radial force in order to give the driver comfort and from the recognition that a stationary or slow moving vehicle tends to slide toward the inside of the curve in abnormal coldish conditions.
32
When a vehicle traverses a horizontal curve, the centrifugal force act as horizontal outward through the centre of gravity of the vehicle, the centrifugal force developed depends on the radius of the horizontal curves. The super elevation that is provided should not be less than the camber from the surface because of the drainage point of view hence a minimum super elevation of 4% is adopted for rural black topped road. The danger over from normal section to super elevation section should be achieved gradually over the full length the transition curves so that the design elevation is available in tangent and balanced on the circular curve. The super elevation is introduced by raising the outer edge or the pavement at a specified rate by rotation the pavement about centre line. As the traffic was observes s mixed so for this condition 75% of design speed is taken and the friction is neglected. The formula for super elevation has reduced, = + V = design speed in m/sec and g = 9.81 m/sec2
33
Where, T = tangent length E = Apex distance L= Length of curve R= Radius of curve in meter =Deflection angle in degree
180
= extra widening = number of traffic lanes = length of wheel base (6.1m) =design speed (30 km/h) =radius of curve
Since in the proposed road no transition curve is provided to third of the extra width should be achieved on the tangent portion before the start of the circular curve and one third on the circular. Road is located in the hilly terrain, the entire widening should be done inside of the curve. Due to drainage consideration and other constrains, it is necessary to provide widening equally both sides of the road. The adopted EW is tabulated as below.
34
And L = 2S Where L S A
=length of curve in m =sight distance in m =algebraic difference of approach grades in percent and
Height of eye = 1.2 meter Height of lowest objective visible = 0.15 meter
=2
(1.5 + 0.035 )
>
35
4.3.8 Gradient
The gradients are provided as minimum so as possible considering present surface land and are within the limit value given in Nepal Road Standards. The main problems that consultant faced during design of this road is to maintain the existing road gradient.
Where S.S.D. = Stopping sight distance V T F V T F =Design speed in Km/h = Total Reaction Times 2.5 sec
=Coefficient of friction form 0.42 at minimum =Design speed in km/h =Total reaction times 2.5 sec =Coefficient of friction from 0.42 at uniformly distributed. Friction coefficient of 0.4
Overtaking sight distances are calculated from the formula given by O.S.D = 0.2798Vbt+0.2798 VbT+2S+0.2798VT Where, Vb = Speed of overtaken vehicle, Km/h
36
t T S A
=reaction time of driver = 2.5 sec = =spacing of vehicle = (0.7Vb+6) =Acceleration km/h/sec
4.3.10Lateral clearance
As per N.R.S for culverts, the full roadway width will be the width including width of shoulders. There were no crossings requiring minor and major bridges.
CHAPTER-5
: DESIGN ELEMENTS
5.1
Horizontal Alignment
A change in the direction is required in roadway alignment due to existing road and topography of the terrain. The design standards for various elements given earlier chapter have been adopted throughout.
5.2
Horizontal Curves
The different elements of horizontal curves were designed using equations that are already given above. As far as possible, large radii were adopted on the curves, where the minimum radius of the curve adopted is 12 m. Most of the curves are having radius around 20 m. A list with the design parameters are presented in the drawings and list with its design parameters are presented in the appendices.
X=
Horizontal distance
5.5 DRAINAGE
General The durability of road pavement and sub-grade as a whole depends on the proper drainage management. Collection, transportation and disposal of surface water originating on or near of the right of way or, flowing in stream crossing or, bordering that Right of way, involves the need of proper drainage system in order to keep the sub-grade material free from excessive moisture. Drainage system and other road structures would be needed to achieve stable road formation and to protect the existing and designed slopes from erosion.
Adequate protection works (bioengineering measures) are suggested for erosion control in side slopes of road.
5.6
Retaining Structures:
Retaining walls are structures to support backfill and surcharge load form the fill section of the road. Normally, it is constructed on the valley side along hill roads. Breast walls are similar structures constructed along the hillside.
39
Retaining and breast walls are not normally intended to stabilize slop failures but are meant to support active or passive earth pressure from the assumed failure wedge above the base of the wall. Retaining and breast walls are constructed for the following purposes: To minimize the volume of excavation and to achieve cut and fill balanced sections. To support the road completely or partially in fill. To stabilize fill slopes (e.g. tipping areas) and cut slopes. To support the toe of a weak slope. To prevent erosion on steep sloping cut faces as revetments.
As a retaining and support structure in weak foundations, wet soils, high groundwater, high seepage pressure areas etc. To retain the road completely or partially in fill when the height of fill exceeds 3.5 m. To strengthen and regulate natural slope drainage systems, water flow areas etc as protection works around drainage outlets. Protection to unstable slopes such as slope movement due to creep, landslide etc. The general principles adopted in design and construction: All wires used in gabion boxes should have galvanized zinc coating. To achieve monolithic design and strength, all gabions should be firmly wired together with continuous lacing at the edges, with double loops at each binding place. This is done mostly before the filling. Erection of gabion walls should start only after inspection and acceptance of the foundation. Permanent dampness must be avoided during the construction period, as well as thereafter. Use of larger size, hammer dressed, tabular stones, staggered joints, proper bonding and interlocking between the stones must be ensured. During the filling of the stones, bracing wire should be fixed at one-third and twothird height in the box. The mountainside walls should generally tilted at 1:3(H: V) whilst the base or foundation of wall must be inclined 4:1 inwards. No tilt should be provided for gabion structures used in and around drainage outlets. The rear of gabions structures are used in wet and weak soil, the rear face should be curtained with geo-textile fabric to retain the fine particles allowing the water to percolate. For low-cost roads, walls constructed in dry masonry and gabion is far the most common since the bulk of material is available locally. In order to secure the river banks and to minimize the earthworks, number of retaining structures is suggested. Stone masonry walls are provided at different chainages. The specification of gabion walls is as suggested by DOR design standards. The stone masonry structures are suggested as retaining as well as breast walls in difficult points where gabion and dry masonry walls are not possible to construct.
41
Since the road is designed to cater for fair weather access only, this study did not consider the design of any bridges and is assumed that any stream or river crossing would be by means of ford. If required, the typical drawings will be produced.
Where, Q= Runoff in m3/s A= Area of catchment in hector C=co-efficient of run-off I= Rainfall intensity
43
B. Hydraulic analysis Once the design discharge is determined then hydraulic analysis is done. The side drains are designed based on principle through open channels. Select longitudinal slope of channels, which is parallel to the road profile. Select type of lining from which value of n and permissible V is obtained. Equate, Q=A x V Q=A x (R2/3 x S1/2)/n For the rectangular section, select economical section as, R=D/2, B=2 x D Solve equation (1) to get B and D Calculate V by V= (R2/3 x S1/2)/n for the design section which should be within the permissible limit otherwise change lining material and redesign the section. Where, V=velocity of flow n= Mannings roughness coefficient A=Area P=wetted perimeter R=Hydraulic radius =A/P S= Longitudinal bed slope of channel (1)
44
Conversation of natural drainage patterns along the road alignment is one of the major considerations that should be made during the design and construction of the draining structure. Water accumulation and concentrated on road surface is a major threat to earth road as it causes rutting, formation of ditches etc. A fundamental technique applied in water management is to ensure that rain water is evenly distributed off the road surface, towards the valley side. This has been achieved by providing the road surface with an outward cross slope with an outward cross slope thereby rainwater to accumulate of the road surface as shown in the typical drawings. Since the road is designed as a low cost, side-drain construction is discouraged in the design as these drains often are blocked and the water finds its way to the road surface, causing major damage to the road. Drains have been proposed along sections with excess water from the hillside, or at the sections with steep gradient (>5%) or switchbacks. Drains have also been proposed along sections where settlements exist. A. Cross Falls The road surface is generally provided with 4% outcross slope to allow the surface runoff to disperse gently toward valley, along the complete length of the road thereby reducing the possibility of erosion. The super-elevations are provided according to the requirement of the curves and drains are provided according to the slopes of the road section if necessary. B. Side Drains Side drains are for the drainage of the surface water these are provided on the both side of the road to drain off the surface water from the Carriageway. The longitudinal slope of drain is made parallel to the longitudinal slope of the alignment.
45
At locations where road profile gradient is greater than 5%, rainwater may flow longitudinally along the road, scouring weak surfaces and forming a gully along the road. In such cases, drains are provided to guide the nearest cross drainage structure or gully. They are generally earthen drains with dry masonry scour checks, spaced at a difference of 5 m to 15 m depending on the longitudinal gradient. Outlets to side drains are designed in such a manner that scouring by the water flow is prevented. At switchbacks, where the cross slope is reversed towards the hillside, drains are constructed and water from the drain is crossed over to the valley side through a causeway. A road alignment consisting of a stack of switchbacks is set out in such a manner that the water diverted from the road uphill does not fall on the road downhill. In exceptional case with steep gradient and highly are erosive soil, side drains will be lined. C. Sub-surface Drains Hillside slopes with excessive water seepage are provided with sub-surface drains along the hillside of the road. The subsurface drain (50 cm * 50 cm) consists of filter material (40 mm single size aggregate) enclosed by geo-textile fabric. The water from the sub-surface drain is discharged at intervals of 30 m along the length of the road. D. Cross Drainage Structure The cross drainage structures proposed for construction on rural roads are limited to dry stone Selection of the type of cross-drainage structures depends on the flow characteristics (discharge, sediment load etc), local topography, access to the site and availability of materials. DOR design standards will be followed for design of small bridges and RCC slab culverts. E. Dry Stone Causeways These are very commonly used cross drainage structure in hill roads. They are built across non-perennial streams, khola etc, where sediment loads are high or where excessive debris is expected. The advantage of the dry stone causeway is that it is cheap and offers least resistance to the natural water flow and flood material. They are unsuitable for perennial streams with high water levels and gorges.
46
F. Vented Causeway These are built across perennial streams where the average water discharge is high. They are provided with vents to discharge dry season flows. Hydraulic considerations need to be taken into account in determining the number and size of the openings during the design. Concrete pipes (minimum diameter of 900 mm) are preferred where sediment loads are not excessive. G. Box Culverts Masonry box culverts are preferred in narrow valleys or gorges that are relatively deep and where massive flood and sediment movement is expected. Their selection also depends on the availability of adequate stones in the vicinity. Hydraulic design criteria need to be taken into considerations in the design of box culverts. H. Irrigation Water Crossings These are minor structures used to discharge irrigation water from one side of the road to the other. However, such crossings also come in use while discharging small quantities of rain water where required. I. Pipe Culverts Topography is the main criterion that determines pie culvert considerations in place of
stone pitched causeway. Pipe culverts are proposed in areas where the discharge is concentrated. Vehicular access to the construction site is necessary for transportation of the pipe.
47
denote both the barriers and fences throughout this technical note. This technical note will help to determine the safety barriers as dictated by site conditions. The different systems of safety barriers can use: A. Semi-rigid System Steel beam barrier Gabion barrier B. Rigid Systems Random-rubble masonry barrier, Plum-concrete barrier R.C.C barrier Barrier Recommended Use a) Steel beam barrier: High speed roads; where space is limited b) Gabion barrier: General use but not in towns c) Random rubble masonry barrier: Alternate to other barriers on bridge approaches d) Plum Concrete Barrier: Alternate to gabion barrier where a more permanent looking structure is required slower speeds e) R.C.C barrier: Narrow medians; where space is limited; where it is essential that the vehicles to stopped Gabion Barrier is recommended for this road section because Gabion barriers are very effective and at the same time are economic, easy to construct and maintain. However, they do not look neat and modem like other types. Gabion safety barriers are useful against all run-off-road type accidents. They have proved to be effective in stopping large vehicles, including loaded trucks.
48
Design considerations The slope gradient and length of cut slope should be determined on the basis of the geological, hydro geological conditions and soil parameters. The cut slope gradient should be between 1:0.3(V: H) and 1:1.5 depending on subsurface conditions and other characteristic. Berms of 1 to 4 m width should construct at interval of 5 to 10 m in the vertical direction (height). Attention shall be paid to the geological condition of the slope prior to cutting of slope. The gradient of the cut slope should be based on the results of the investigation and as approved by the engineer. In designing a cut slope, the following geological conditions should be considered with the utmost care.
a) Colluvial Deposit Slope Colluviums such as talus and debris flow deposits, being poorly consolidated, usually form a slope with a critical angle of stability. When excavated, the cut slope formed will become unstable. Therefore a wide berm near the boundary between the bedrock and the upper Colluvial deposit should be designed.
b) Erosive Sandy Soil Sandy soils, such as decomposed granite, pit sand or terrace gravel are easily eroded by surface water, which may result shallow collapse.
c) Erodible Soft Rocks Cut slopes in soft rocks such as mudstone and tuff with low degree of solidification becomes unstable after the completion of cutting because of the weak internal shear strength of the rock and stress release.
d) Fissured Rock Slope The stability of fissured rock slopes is governed by the degree of fissure development and their distribution. As a rule, cutting and removal of soil mass should be performed from upper to lower portion to maintain the slope stability. Cutting work should be carried out during dry season. The final cut slopes should be treated with adequate drainages, slope protection works and/or bioengineering works to increase stability against effects of rainfall and infiltration of water.
49
Protection of the cut slope and its foot should be considered in order to prevent erosion and instabilities. Slopes must be protected by means of walls and resisting structures if it is unavoidable to implement steeper slope gradient than the standard gradient. Proper cutting work is effective to safeguard the probable cut slopes for different soil characteristics are shown in Table.
Recommended Standard Slope Gradient for Cut Slopes Soil Classification Hard Rock Soft Rock Sand Not dense(loose), poorly graded Sandy Soil Dense, or well graded Not dense(loose) Less than 5 m 5 10 m Less than 5m 5 10 m 1:0.81:1.0 1:1.01:1.2 1:1.01:1.2 1:1.21:15 Cutting Height Slope Gradient 1:0.31:0.8 1:0.51:1.2
6.2 Introduction
EIA is defined as a process to ensure that potentially significant environmental impacts are satisfactorily assessed and taken into account in the planning, design and implementation phase. Further, EIA can also be defined as Systematic Identification and Evaluation of Potential Impacts (effects) of proposed projects, Plan, Programs or legislative actions relative to the physical, biological, socio economic and cultural component of the total environment. The main objective of this EIA study is to have the systematic identification and evaluation of potential impacts on the environment during the construction and operation phase of the road projects. EIA also gives response for a more effective compliance of new projects with
51
approve environmental standard making it more environmental friendly and better researched design to reduce the constructional and operational cost. Further EIA study examines the significance of the environment implication, recommends the preservative and mitigation measures on physical, biological and socio economic conditions, including environmental implication of the proposed projects. Types of impacts to be covered in EIA The EIA process is expected to identify and assess impacts upon the environment as defined below: A) Receiving Environmental Media Changes in air quality Changes in water quality Changes in ambient levels of noise and vibration Changes in the quantity of land available for different purposes and in the quality of land.
B) Living Receptor Changes in the level of human mortality and morbidity, changes in the amenity value of the environment for leisure and recreational use, change in human use values. Changes in the damage levels to fauna and flora and natural ecosystem with consequential effects on species diversity and abundance, and on agriculture and forestry
C) Built Environment Changes in the damage level to individual building and in the quality of the environment
52
Information required to be collected during impact identification i. What is the feature of the proposed project (site location, project size, project design features and pollution control mechanism? ii. What alternatives to the preferred project have been considered and have any reasonable alternatives have been investigated iii. iv. v. Have all components of the project been investigated? Have all phases of the project been satisfactorily taken into account? Have all impact generating activities associated with each aspect of project investigated?
EIA activities Screening Scoping and TOR Identification of issues Impact investigation
3. Feasibility stage
EIA activities carried out Alternative analysis Impact prediction Impact Evaluation Mitigation measures and monitoring programs Environmental Manage mental Plan
Project viability and authorization based on EIA and technical and economic
5. Design phase Detailed survey Detailed design Tender document 6. Project Implementation Construction Operation 7. Post construction
EIA recommendation Incorporation Design work needs to adapt to the EIA results Use of mitigation measures and monitoring schemes Environmental auditing
53
Methodology selection is a part of impact study. Portion of several methodologies can be used for certain prerequisite activity. More complex and sophisticated identification technique are not widely used and that they can have practical shortcomings. Methods listed can be modified, adopted, extended or simplified to meet the needs of a particular EIA. 1. Adhoc Method Only suggest broad areas and general nature of possible impacts. 2. Checklist method Ranges from simple listing of environmental factors to descriptive approaches Four broad categories of checklist in use are: simple checklist Descriptive checklist scaling weighing Checklist Scaling weighing Checklist
3. Matrix Methods It combines the use of two checklists Project characteristics in one axis and environmental factors in other axis. 4. Network Method 5. GIS Method 6. Cause and Effect Method
54
education area may also promote understanding on the value of health and education facilities through exchange of information and experience. 5. Reduced in project time and cost 6. Nepal is underdeveloped country and has about 60% of the total area covered in the mountainous ranges. Until now a lot of areas are beyond the road transportation facilities, due to lack of nation budget. So, this project is under slow transition strategy. This requires low budget & entire work is labour based. This project uses local material and local labour, hence reducing much more cost. 7. Increase in Flora and Fauna Low cost and flexible structures are used in this road and bio engineering works are applied for slope stabilization. So the flora and fauna will be increased, which also helps the wildlife to move across the road alignment easily. 8. Sight distance can be increased due to cutting of slope for stability. It also helps to increase night visibility that corresponds to decease in road accidents, creating extra width.
56
at the downhill if a concentrate flow is left unattended. Hence it is recommended that the cross drainage outlets must channelize to the confirmed natural drain. 3. Effect on drinking water pipe system the source of water supply system been located at most of the outlet structures of the drainage, which is providing domestic drinking facilities for local people. These are likely to affect by construction of road. 4. Effect on social services sector Education and drinking water facilities developed with due consideration on the local population. It may also increase number of students and education quality may be degraded if physical facilities qualified teachers are not increased as per requirements. 5. Mitigation Measures Application of the design standards and specification on effective implication of the proposed mitigation measures would minimize the adverse impacts of the project on the environment. The mitigation measures to be employed for avoiding the landslide are as follows: Provide adequate catch drains to drain out surface runoff water as quickly as possible Do not disturb the uphill slopes at the active slide area and the gabion wall or masonry wall should support road. Excessive cut should be avoided and road component should be balancing depth as far as possible. Provide the pocket walls at the uphill of the road where the rock fall is expected. Provide vegetation covers on the cut slope area by bioengineering measures. The indigenous plants including grass having good soil binding properties and investigate it with engineering application. forest clearing is recommended for road formation width only carries out compensatory plantation Provide adequate compensation for loss of agricultural land, agricultural procedures. Relocate affected infrastructure facilities. Dispose the spoil at designated location and provide bioengineering give green development
57
58
59
Water management is an essential factor in controlling slope stability. Suitable drainage system drainage system is the most important factor for the safety of both natural and artificial slopes. Quick and effective drainage of surface and spring water, and lowering of ground water table are basic methods for stabilizing slopes. In most of the cases Earthwork comprising of Cutting unstable portion of a slope at top and Embankment in the toe part of the landslide can stabilize the slope Combination of water Management and Earthworks shall be considered as primary control measures. Restrain measures such as retaining wall and structures like gabion wall and stone masonry can stabilize the slope when failure scale is small and or when the movement of landslide is low. Bioengineering shall be considered in every case of slope failures. Proper application of bioengineering contributes to basic stabilization of the slope and reduction of negative environmental impact. In large scale slope failures, monitoring and control measures should be planned and applied prior to implementation of restrain measures.
60
D. Anchor Works Supporting the unstable slope by application by application of rock bolts, soil nails, and ground anchors. E. Wall and Resisting structures Supporting the slope by construction of retaining walls and similar structures. F. Gully protection work Protection or reduction of the damages from slope failures by wire net and catch wall. Series of suitable check (Sabo) dams are applied to check the Debris Flow. G. Pile Work Site Clearance defines clearing and grubbing shall be carried out prior to earthwork. It also affected the environment and social structures. The work includes the removal and disposal of objects such as, trees, bushes, shrubs stumps, rubbishes and other obstacles to work.
61
CHAPTER: 7 BIO-ENGINEERING
7.1 Background
Nepal is a country with approximately 86% land covered by the sloppy area. From these slopes, there is a tremendous amount of soil being eroded every year. For example, from the natural 240 Mm3 of soil is eroded every year. Likewise, 2.87 ton /year/ha in the Northern Himalayan Forest Area, careless construction of Mountain Roads, 400 700 m3 of landslide occur per km/year construction of mountain roads, 3000-9000m3 of landslide occur during the construction of road, 150 ton/year/ha in the poorly constructed areas of roads. Nepal has been investing its huge amount of resources to stabilize such roadside slopes. Generally Conventional retaining structures (masonry, concrete or gabion walls) are constructed to reinstate such slopes. The cost of such walls is increasing every year due to increased cost of construction materials. On the other hand, Nepal is very rich in natural resources. There are varieties of species of plants in Nepal, which can be used in Bio engineering purpose. Bio engineering involves using living plant material to build structures that reduce, prevent or repair erosion. The basic idea is to harness the natural properties of vegetation to stabilize soil, while well designed structures prevent the slope from failing and allow the plants time to establish. Plants roots bind and anchor soils. Bio engineering covers the use of vegetation for bio engineering techniques to study vegetation problems (e.g. the mechanical behaviour of plant roots, anchorage). Bio engineering techniques are not new; they were used in China (as long ago as 28BC) for constructing and repairing dikes. European, Celtics and Roman people have also practiced various bio engineering techniques. Today, a resurgence of this old knowledge is occurring. With proper design, there are May advantages to bio engineering techniques over conventional hard structures they can be more effective for controlling erosion; They are aesthetically pleasing; They are usually self maintain and less expensive;
62
Furthermore, while human made structures such as concrete walls break down over time, bio engineering structures grow stronger as plants mature. Bio engineering offers the engineer a new set of tools, but does not normally replace the use of civil engineering structures. In the context of upland slope protection and erosion reduction, bio engineering in co coordination with civil engineering structures can be the best solution. Bio engineering utilizes live plant parts to provide soil reinforcement and prevent surface erosion. Fascines, Brush layers etc are bio engineering techniques that use stems or branch parts of living plants as soil reinforcing and stabilizing materials. Crib walls etc are bio engineering techniques that use porous structures with opening through which vegetative cuttings are inserted and established. As vegetation becomes established, roots invade and permeate the slope, binding it together into a unified coherent mass. Over time, the structural elements diminish in importance as the vegetation increase in strength and functionality. Bio engineering techniques is very effective method in mountainous country like Nepal, providing a low cost solution to the problem of landslides and soil erosion in geologically weak and fragile areas maximizing the use of locally available materials and resource making the entire process less expensive is another advantage
7.2 Introduction
Bio engineering is the use of living vegetation, either alone or in conjunction with civil engineering structures and non living plant materials to reduce shallow seated instability and erosion on slope. It can be use to protect almost all slopes against erosion. It decreases the instances of shallow planar sliding and can be used to improve surface drainage and reduce slumping. Problems on Slope:i. ii. iii. iv. v. vi. Materials roll down the slope Encounter of water with slope Loose state of materials Tendency of outward and downward movement of slope materials slip of overlying strata accumulation of water
63
Bio engineering systems work by fulfilling the engineering functions for the protection and stabilization of slopes. the engineering function to be performed for the solution of the problems on slope are catching debris, armouring (cover) the surface, reinforcing the soil, anchoring the surface layer, supporting the slope and draining the material.
64
The main engineering functions of structures, with examples of civil and bio engineering structures Function Civil engineering technique Catch Catch walls Bio Engineering Technique Contour grass lines or brush layers Catch fences Shrubs and large bamboo clumps Armor Revetments Mixed plant storey giving complete cover Surface rendering Grass Carpet Jute netting with planted grass Reinforce Reinforced earth Densely rooting grasses, shrubs and trees Soil nailing Most vegetation structures Anchor Rock anchors Deeply rooting trees Wire bolster cylinder and planted shrubs or trees Jute netting with planted grass Combination of soil anchors and deeply Soil anchors Support Retaining walls Prop walls Drain Masonry surface drains Down slope and diagonal vegetation lines Large trees and large Rooting trees Retaking wall with Catch wall with dense shrubs Catch wall with bamboo clumps Vegetated stone pitching Combination of Both
bamboo clumps large bamboo clumps Planted above Herringbone pattern wire bolster cylinders and angled grass lines
65
66
100 80 60 40 20 0 0
Time (yrs)
Choosing a Bio Engineering Technique Slope angle >450 Slope length >15 met Material drainage Good Site moisture Damp Previous / potential problems Erosion Slumping Functions required Armor, reinforce drain Armor reinforce Drain, armor reinforce Techniques Diagonal grass lines
Contour grass lines down slope grass lines and vegetated stone pitched rills or 2. chevron grass lines and vegetated stone pitched rills Diagonal grass lines 1.
Dry
Erosion, slumping
<15 meters
Good
Any
Erosion
1. 2.
Poor
Damp
Slumping erosion
1.
2. 3. 300 - 450 >15 meters Good Any Erosion Armor reinforce catch 1.
2.
3.
Poor
Any
Slumping Erosion 67
Dram
1.
Diagonal grass lines or jute netting and planted grass jute netting and randomly planted grass or Contour grass tines or Diagonal grass lines horizontal bolster cylinders ad shrub/ tree planting or down slope grass lines and vegetated stone pitched rills or Site grass seeding, mulch and wide jute netting Herringbone
armor reinforce 2.
<15 meters
Good
Any
Erosion
1. 2. 3. 4. 5.
Poor
Any
Slumping Erosion
1. 2. 3.
4.
5.
bolster cylinders and shrub / tree planting or Another drainage system and shrub/ tree Brush layers of woody cutting or contour grass lines or contour fascines or Palisades of woody cutting site grass seeding, mulch jute-net Diagonal grass lines or diagonal brush layers or Herringbone fascines and shrub/tree planting or herringbone bolster cylinders and shrub/tree planting or Another drainage system and shrub/tree planting Site seeding of grass and shrub/tree planting or shrub/tree planting Diagonal lines of grass and shrubs/trees or shrub/tree
<300
Any
Good
Any
Erosion
Armor catch
1.
2. Poor Any Slumping Erosion Drain armor catch Turfing and shrub/tree planting 1.
1.
2.
68
Special Conditions Any Any Any Any Planar sliding, shear failure Reinforce, anchor Site seeding of shrubs/small trees
>300
Any
Debris fall
Reinforce, anchor
Good
Erosion
Armor
Poor
Any
Erosion, slumping
Armor drain
Site seeding shrubs/small 1 trees Jute netting and randomly planted grass Diagonal lines of grass and shrubs/ trees
Any gully
Erosion(major)
1. 2. 3.
Bioengineering in Nepal
The concept of bio engineering in road construction was introduced in Nepal 40 years ago with roadside plantations in a US assisted project on the Dhangadhi Dadelduhra highway in western Nepal. It was later applied in the Lamosangu Jiri highway in the countrys central hills region, built with Swiss assistance. Bio engineering in the modern sense was first introduced on massive scale with the involvement of the UK based Transport Research Laboratory on the eastern Dharan Dhankuta highway, supported by the British government. They then facilitated the transfer of the technology to Nepali institutions and professionals. Now the DoR. is paving the way for the bio engineering of roadside slopes. The department of roads, through several donor assisted projects had conducted experiments on Bio engineering case studies in the history of Nepal such as: a) Dharan- Dhankuta road (1988) b) Dhankuta Hill road (1990)
69
depending upon whether the road is solely local or forms a link in a longer road, or is a part of a road system. The World Bank has listed economic criteria and social service as the two primary aspects for evaluating the influence area. The method used in the determination of influence area for the proposed road project is through the area of influence of road , relative to the provision of basic social services, may be defined as the area contained within the The proposed project will be spiral cord for the transportation of human and goods of Mulkharka to Chisapani hilly areas of Kathmandu and Nuwakot district respectively. With the above mentioned criteria, the following Village is found to be within the direct influence of the proposed road. V.D.C and District 1. Sundarijal V.D.C. (Mulkharka Village) Kathmandu District 2. Chisapani V.D.C (Chisapani Village) Nuwakot District
70
73
74
Hospital
Financial Institutions
75
76
Sample Calculation:
C = co-efficient of run-off = 0.15 i = Intensity of rainfall = 78.2 mm/day A = area of catchment (in hectares) Q =
(m3/s)
Section 1 2 3 4 5
77
DRAINAGE CALCULATION
Wetted Perimeter (P) = ( + 2 ) Hydraulic Radius (R) = A/P A = 0.03 m2 P = 20.49 m R = 0.0612 m V = 1.64 m/s Q = 0.049 m3/s B 0.2 0.2 0.3 0.25 0.25 0.25 H 0.15 0.2 0.1 0.15 0.1 0.12 A 0.03 0.04 0.03 0.0375 0.025 0.03 P 0.5 0.6 0.5 0.55 0.45 0.49 R 0.060 0.067 0.060 0.068 0.056 0.061 V 1.62 1.74 1.62 1.77 1.54 1.64 Q 0.049 0.070 0.049 0.066 0.039 0.049
78
79
readjustment of longitudinal gradient damaged by run-offs. Spot gravelling and stone soiling are undertaken C. Cyclic Maintenance: carried out in cycles of about 5-7 years but is hardly practiced D. Emergency Maintenance: carried out after extraordinary landslides and is important to avoid further damage to drainage systems.
81
We used SMART ROAD software for design and analysis of the road section along with upgrading the existing alignment. The salient features of the software are described below.
It works either as a companion to other civil design software (AutoCAD) or as an independent standalone system. It includes functions for data collection, terrain modelling, contouring, volumes, profiles, sections and road design. Changes made in one window are instantaneously reflected in adjoining windows. Operating as a standalone program in Microsoft Windows (Win 2000, XP, VISTA, and WIN 7) Smart Road allows you to interactively design a road. Entire development process which also includes rigorous testing has been performed in consultation with leading road engineers working with the software.
With Smart Road one can design all types of Roads in Nepal as well as in other countries. It is a full Plan; Profile & Cross section based road designing software which provides all the data and necessary drawings ready to print with proper sheet management functions.
Smart Road supports both Baseline survey method (DTM) and Centreline survey method in a single package. All the design parameters can be given by the user according to the requirement of the individual's project. It allows user to work with Plan, Profile and Crosssection simultaneously in a single window and has the facility of importing & exporting various types of design data from CSV file and Active Excel Application. Smart Road is fully equipped with the powerful functionalities such as design of Horizontal alignment, Vertical alignment, Cross-section etc. Users can customize structures (drains, walls, cross
82
drain structures) according to their requirement and can also customize drawing templates for the printing.
Profile 1. Extensive Parameters display option in profile such as design level, ground level, cut-fill, soil type, side drains and super elevations 2. Chainage and Reduced Level (RL) reflection at mouse point in Drawing Window. 3. Real time reflection of vertical alignment with grade during VIP node movement 4. Possibility of locating the relative cross section and plan from profile window 5. Automatic vertical curve fitting at the time of insertion of VIP node 6. Real time reflection of design level in x-section. Cross Section 1. Automatic update from the horizontal and vertical alignment 2. A large number of drawing and measurement tools. 3. Custom cut-fill lines, cut fill area, drains, walls etc. 4. Cross drainage structures with typical drawings 5. Prompt update of cross section along with the changes made in any parameter with preview 6. Automatic Area calculation 7. Easy placement of structure (in Range also) 8. Centreline shift 9. Editing the ground feature.
83
DTM/Terrain/3D 1. DTM Bundled in a single package of a software copy 2. Exhaustive terrain consistency` and validity analysis and repair 3. Very fast constrained triangulation and contour generation. 4. 3D View of existing terrain with user controlled viewing angles. 5. Profile & X-section generation at desired interval. 6. 3D inspection as well as editing capabilities similar to horizontal alignment. 7. Easy placement of Break lines, surface details, boundaries. AutoCAD DTM 1. Recently added User Friendly feature. 2. Compatible with the AutoCAD version of 2004 or Higher. 3. Generation of Plan, Boundary, Break line, Triangulation, Contour can be done easily. 4. Editing the alignment using the user friendly features of AutoCAD. 5. Generation of Tin Surface data. 6. Feature of importing the Details, and required Layers from AutoCAD Drawing. 7. Feature of importing the Tin Surface data compatible for designing the road in Smart Road. Calculation/ Printing / Plotter 1. Recently added User Friendly feature. 2. Compatible with the AutoCAD version of 2004 or Higher. 3. Generation of Plan, Boundary, Break line, Triangulation, Contour can be done easily. 4. Editing the alignment using the user friendly features of AutoCAD. 5. Generation of Tin Surface data.
Hairpin bend design In SMART ROAD with inputs of only three curves radii, the alignment can be smoothened, simultaneously introducing suitable super elevation and extra widening.
84
12.1 Summary
The total estimated construction cost for Upgrading Sundarijal Chisapani Road Section is summarized in the table below which does not include compensation for building the road. S. No 1 Road Name Sundarijal Chisapani Road Package 1 Length 2.3 km Cost Estimate See Annex For Details
12.3 Earthwork
The quantity of earthwork is calculated as per attached earthwork quantity sheet and given in Annex
85
86
LIMITATIONS
The project work was completed amid many difficult circumstances some which were unavoidable due to the weather conditions. The main being our work being undertaken during the monsoon season as our work was hampered by constant intervals of erratic rainfall pattern in the watershed area also the work was delayed by faulty batteries in the total station instrument. Due to the steep topography and undulation of the project area it was very difficult to work at the site. Due to the previously laid track and alignment we were not able to choose the suitable alignment rather follow the current alignment there were many places where design was compromised due to the national park rules and limitations that strictly stated not to harm the ecology of the park. Hence, the concept of environment friendly road was utilized during various phases of the design procedure. Although faced my numerous constraints, the warm hospitality of the local people during our week long stay in the project area was very much appreciable. During the survey procedure, heavy rainfall and subsequent mud flows in the alignment area caused difficulties however our group worked as a team during the difficult time and completed the task assigned in the stipulated time. Some of the constraints are listed below: Budget limitations Steep topography Alignment limitation Instrument malfunction Time frame to complete the tasks Lodging area far from the project area Existing road crossed by numerous small streams Heavy rainfall followed by blocked roads and mud flows
87
CONCLUSION
The main task in the project was to improve the existing alignment and also fix new alignment in some places. The site condition, longitudinal gradient and accessibility were considered while selecting the alignment. The alignment was taken avoiding the cultivable land as far as possible the existing trail has been followed. The gradient was fixed from 7-12 % and in exceptional case only 12% gradient was exceeded. Standards set by DoLIDAR and NRS has been followed for the design of effective, economic and safe road. Mass balancing which is of the major motive of the environment friendly road concept was also involved. The small scale civil engineering structures such as retaining wall, gabion wall etc in integration with bio-engineering were suggested as per the site requirement. The suitable cross drainage and longitudinal cross drain structures were proposed as per the site condition. Environment Impact Assessment has also been considered and provision of roadside development program such as slope stabilization methods were also implemented in the road design procedure. The upgrading of Sundarijal Chisapani Road Section including cost estimate for road construction works was done and this report includes all detail works of survey and design of the various elements of the road section.
88
BIBILIOGRAPHY
Khanna ,Dr S.K. and Justo,Dr C.E.G. ,2001-Eight Edition ,Highway Engineering. Roorkee: Nem Chand & Bros publication . Agor, R., 1996- Eight Edition, A Textbook of Survey And Leveling. New Delhi: Khanna Publishers. Punmia,Dr B.C.,1985- Third Edition , Introductory Irrigation Engineering .New Delhi : Standard Publishers Distributors. Howell, John, 1999, Roadside Bioengineering: Reference Manual. Kathmandu: DoR Publication. Nepal Rural Road Standard,2055,DoR. Nepal Road Standard, 2045- First Revision. Manual for Survey, Investigation and Preparation of Road Project, 2001. New Delhi : IRC Publication. Work Norms for labour based constructions work of agricultural and rural
roads,1999,DoLIDAR Publication. Technical Specifications for labour based constructions work of agricultural and rural roads,1999,DoLIDAR Publication. District Rate ,FY 067/068, Kathmandu Final Year Project on Green Road by 2062 Batch Department of National Park and Wildlife Conservation www.dnpwc.gov.np
89