You are on page 1of 30

Document Number HG-Rig-011 Issued by, Rigging Department Approved by, Director

HaGun Institute

SCAFFOLDING RESPONSIBILITY PROCEDURE

1 SCAFFOLDING RESPONSIBILITY PROCEDURE


1.1 SECTION CONTENTS
This section provides general information and pertinent safety guidelines for single pole and independent pole wood scaffolds and tubular steel scaffolds which are needed for occasional Company work such as painting, insulating, maintenance work, pipefitting, etc. Refer to applicable code regulations for guidance in the use of other types of scaffolds.

1.2 GENERAL AND DESIGN REQUIREMENTS FOR SCAFFOLDING


1.2.1 GENERAL REQUIREMENTS FOR ALL SCAFFOLDING 1.2.1.1 Scaffolds are temporary, elevated platform structures which should be provided for all work that cannot be done safely from permanent or solid construction (minimum 20 inches wide), or cannot be done safely from ladders. 1.2.1.2 The erection and dismantling of scaffolds should be performed under the supervision and direction of a qualified person experienced with or trained in scaffold erection, dismantling, and use as well as knowledgeable about the hazards involved. 1.2.1.3 Personnel should not work on scaffolds during storms or high winds nor on scaffolds covered with ice or snow. 1.2.1.4 Some jurisdictions may require a permit for scaffold use.

1.2.2 GENERAL DESIGN REQUIREMENTS 1.2.2.1 Platform Footings


The footing or anchorage for scaffolds should be sound, rigid, and capable of carrying the maximum anticipated load without settling or displacement. Unstable objects such as boxes, loose bricks, concrete blocks, or scrap lumber should not be used to support or level scaffold or planks. The scaffold should be erected as near as possible to the building or structure. All poles should be set and maintained plumb for the full height of scaffold. Open sides and ends of working level 10 feet 0 inches or more above grade should be guarded by top rails, mid rails, and toe boards with a top of railing at 42 inches above the platform level. (Some jurisdictions may require guarding of open sides and ends of working levels 7 feet 6 inches or more above grade see Cal. Code of Regulations).

1.2.2.2 Guardrails and Toe boards

Revised: 0 Page 1 of 30 Date: 28 September 2012

Document Number HG-Rig-011 Issued by, Rigging Department Approved by, Director

HaGun Institute

SCAFFOLDING RESPONSIBILITY PROCEDURE Where personnel are required to work or pass under a scaffold platform, a screen (18 gage, -inch mesh or equivalent) should be installed between top rail and toe board of platform guardrail. Scaffolds and their components should be capable of supporting without failure at least four times the maximum intended load. A safe means of access such as a walkway, stair or fixed ladder should be provided to all scaffold platforms. A portable ladder may be used if securely attached to the scaffold. All ladders should extend 3 feet minimum above the platform deck or 12 inches above top rail for handhold during mounting and dismounting. Wooden planking should be scaffold grade as recognized by lumber industry standards. Where planking is lapped, each plank should lap its end supports by a minimum of 12 inches or secured from movement. Overlapping of planks at the unsupported end or overhang of planks is not permitted. Where the ends of planks about each other to form a flush floor, the abutted ends should be secured to separate bearers. Where planks rest on bearers, ends should extend minimum 6 inches, but not more than maximum 18 inches over end supports. Platform slopes should not exceed 2 inches in 10 feet.

1.2.2.3 Design Load


1.2.2.4 Access

1.2.2.5 Planking and Overlaps.

1.3

GENERAL REQUIREMENTS FOR WOOD POLE SCAFFOLDING


Scaffold lumber should be select grade as recognized by the lumber industry standards. Lumber should be inspected for defective or damaged pieces before and regularly during use, and substandard pieces should be replaced (see Figure 8.1, 8.2, and 8.3). When poles are spliced, their ends should be squared and fit squarely together. Splice plates should be at least 4 feet 0 inches in length and be the same width and have at least the cross sectional area of the poles being spliced. Splice plates should be provided on two adjacent sides and should overlap the abutted ends equally. Splice plates of other equivalent strength material may be used. Double-headed nails should not be used where projections create a hazard such as on guardrails. Also lubricated, wax-coated nails are not permitted.

1.3.1 Lumber

1.3.2 Splices

1.3.3 Nailing

Revised: 0 Page 2 of 30 Date: 28 September 2012

Document Number HG-Rig-011 Issued by, Rigging Department Approved by, Director

HaGun Institute

SCAFFOLDING RESPONSIBILITY PROCEDURE All nails should be 8d or greater, should be driven full length or to the first head of double-headed nails, and should not be subjected to a straight pull. Ledgers should span pole space without splicing between poles. Ledgers should be reinforced by bearing blocks securely nailed to the side of pole to form a support for the ledger. Bearers should be sent on edge and long enough to project over the ledger at least 3 inches for proper support.
LIGHT DUTY 25 PSF 20' 2" x 4" 6' 5' 6' 2" x 6" 2" x 6" 7' 60' 4" x 4" 10' 5' 10' 2" x 10" 2" x 10" 7' MEDIUM DUTY 50 PSF 60' 4" x 4" 8' 5' 8' 2" x 10" 2" x 10" 7' HEAVY DUTY 75 PSF 60' 4" x 4" 7' 5' 7' 2" x 10" 2" x 10" 6'6"

1.3.4 Ledgers

1.3.5 Bearers

SCAFFOLD COMPONENT Maximum uniformly distributed load Maximum Height Pole Size Longitudinal pole spacing Scaffold width (single pole) Scaffold width (independent pole) Ledger size Bearer size Maximum vertical spacing Horizontal member (single pole) Dim "A" Figure 8.3 Maximum vertical spacing Horizontal member (independent pole) Dim "B" Figure 8.2 Diagonal & Cross Bracing

7'

7'

7'

4'6"

1" x 6"

1" x 6"

1" x 6"

2" x 4"

Dimensions are minimum nominal sizes and maximum allowable spacings. Table 1 Typical Wood Scaffold Specifications - Single Pole and Independent Pole

1.3.6 Full Diagonal Bracing


Full diagonal bracing should be installed across the entire face of scaffold in both directions to prevent movement parallel to the building wall and buckling. Braces should be spliced only at the poles.

Revised: 0 Page 3 of 30 Date: 28 September 2012

Document Number HG-Rig-011 Issued by, Rigging Department Approved by, Director

HaGun Institute

SCAFFOLDING RESPONSIBILITY PROCEDURE

1.3.7 Cross Bracing


Cross bracing should be provided between the inner and outer sets of poles in independent pole scaffolds. The free ends of pole scaffolds should be cross braced. Wood scaffold over 60 feet in height should be designed by a Civil Engineer registered within the appropriate jurisdiction. Scaffolds should not be built beyond reach of effective firefighting equipment. All scaffolds should be securely guyed or tied to the building or structure. Ties should be doubled 12 gage iron wire or equivalent and should not be more than 20 feet apart horizontally or vertically. Heavy duty scaffolds require ties every 15 feet horizontally or vertically.

1.3.8 Height Limitations


1.3.9 Securing

Revised: 0 Page 4 of 30 Date: 28 September 2012

Document Number HG-Rig-011 Issued by, Rigging Department Approved by, Director

HaGun Institute

SCAFFOLDING RESPONSIBILITY PROCEDURE

Figure 1

Wood Independent Pole Scaffold

Revised: 0 Page 5 of 30 Date: 28 September 2012

Document Number HG-Rig-011 Issued by, Rigging Department Approved by, Director

HaGun Institute

SCAFFOLDING RESPONSIBILITY PROCEDURE

Figure 2

Wood Single Pole Scaffold

Revised: 0 Page 6 of 30 Date: 28 September 2012

Document Number HG-Rig-011 Issued by, Rigging Department Approved by, Director

HaGun Institute

SCAFFOLDING RESPONSIBILITY PROCEDURE

1.4 TUBULAR STEEL SCAFFOLDING AND STAGING


1.4.1 Material
Staging pieces such as poles, ledgers, bearers, ribbons, and braces should be 2 inches nominal OD tube steel or other material of equivalent strength. Tube lox staging material may be used. All staging pieces should extend inch minimum through couplings to prevent crimping of ends. Bearers should be at least 4 inches, but not more than 12 inches longer than the pole spacing. Tubular steel scaffolds exceeding the maximum heights listed in specification (Figure 3) should be designed by a Civil Engineer registered within the appropriate jurisdiction. Scaffolds should not be built beyond reach of effective firefighting equipment. Intermediate rest platforms should be provided for climbing to levels where the change in elevation is greater than 30 feet. Rest and intermediate platforms should be fully planked, equipped with guardrail and toe board, and should not be used for storage of material or as an additional working platform. Staging should be tied securely to structures or equipment to prevent tipping over. Ties should be doubled 12 gage iron wire or equivalent and not be spaced more than 30 feet horizontally or 26 feet vertically. The ties should be as close as possible to the top working platform. TCC clamps with staging pieces may be used instead of tie-wires to stabilize staging (Figure 13) The full height of all staging should be braced. Both the front and back of longitudinal staging faces should be braced. Diagonal bracing should be installed at approximately a 45 angle from near the base of the first post upward to the extreme top of the scaffold. Repeat at the base of every fifth longitudinal post. Similarly diagonal bracing should be installed from the base of the last extending back and upward toward the first post (see Figures 8.5, 8.6, and 8.7 for details). Cross bracing should be installed across the width of the scaffold at least every third set of posts horizontally and every fourth ribbon vertically (see Figures 2 and 5 for details).
TYPE STANDARD MEDIUM DUTY HEAVY DUTY

1.4.2 Bearers

1.4.3 Height Limitations


1.4.4 Securing

1.4.5 Diagonal Bracing


1.4.6 Cross Bracing

Revised: 0 Page 7 of 30 Date: 28 September 2012

Document Number HG-Rig-011 Issued by, Rigging Department Approved by, Director

HaGun Institute
Inspection, Painting Exchangers Dismantling Refractor Refractory Insulating, Welding Cleaning Pipefitting y Work Work and Pipefitting 25 50 50 50 70 300 10' 320 8' 350 8' 375 6' 350 6'6" Other Special 70 450 6'

SCAFFOLDING RESPONSIBILITY PROCEDURE


Application

DISTRIBUTED LOAD LBS./SQ.FT. CONCENTRATED LOADS/LBS. POST SPACING LENGTHWISE DIM "A" SEE FIG. 8.5 POST SPACING LENGTHWISE DIM "A" SEE FIG. 8.5 MAXIMUM NUMBER OF LOADED/WORKING PLATFORMS ADDITIONAL PLANKED LEVEL (NOT FOR STORAGE OR WORK) MAXIMUM HEIGHT

6'

5'

4'

5'

6'

4'

125'

125'

91'

125'

78'

125'

Table 2 Typical Tubular Steel Scaffold Specifications

1.5 TYPICAL SCAFFOLDING ERECTION ARRANGEMENTS


Suggested Erection Arrangements and Nomenclature (see following pages) Figure 3 Figure 4 Figure 5 Figure 6 Figure 7 Figure 8 Figure 9 Figure 10 Figure 11 Figure 12 Typical Bracing Requirements Typical Tubular Steel Nomenclatures Typical Tubular Steel Diagonal Bracing Typical Tubular Steel Cross Bracing Typical Front and Side Access Scaffold Ladders Typical Tubular Steel Platform Staging and Ladder Typical Tubular Steel Footing Connections Typical Tubular Steel Connectors and Coupler Typical Tubular Steel Planking Details Typical Tubular Steel Tie and Clamp Details

Revised: 0 Page 8 of 30 Date: 28 September 2012

Document Number HG-Rig-011 Issued by, Rigging Department Approved by, Director

HaGun Institute

SCAFFOLDING RESPONSIBILITY PROCEDURE

Figure 3

Typical Bracing Requirements

Revised: 0 Page 9 of 30 Date: 28 September 2012

Document Number HG-Rig-011 Issued by, Rigging Department Approved by, Director

HaGun Institute

SCAFFOLDING RESPONSIBILITY PROCEDURE

Figure 4

Typical Tubular Steel Nomenclature

Revised: 0 Page 10 of 30 Date: 28 September 2012

Document Number HG-Rig-011 Issued by, Rigging Department Approved by, Director

HaGun Institute

SCAFFOLDING RESPONSIBILITY PROCEDURE

Figure 5

Typical Tubular Steel Diagonal Bracing

Revised: 0 Page 11 of 30 Date: 28 September 2012

Document Number HG-Rig-011 Issued by, Rigging Department Approved by, Director

HaGun Institute

SCAFFOLDING RESPONSIBILITY PROCEDURE

Figure 6

Typical Tubular Steel Cross Bracing: Across Width of Scaffold

Revised: 0 Page 12 of 30 Date: 28 September 2012

Document Number HG-Rig-011 Issued by, Rigging Department Approved by, Director

HaGun Institute

SCAFFOLDING RESPONSIBILITY PROCEDURE

Figure 7

Typical Front and Side Access Scaffold Ladders

Revised: 0 Page 13 of 30 Date: 28 September 2012

Document Number HG-Rig-011 Issued by, Rigging Department Approved by, Director

HaGun Institute

SCAFFOLDING RESPONSIBILITY PROCEDURE

Figure 8

Typical Tubular Steel Platform Staging and Ladder

Revised: 0 Page 14 of 30 Date: 28 September 2012

Document Number HG-Rig-011 Issued by, Rigging Department Approved by, Director

HaGun Institute

SCAFFOLDING RESPONSIBILITY PROCEDURE

Figure 9

Typical Tubular Steel Footing Connections

Revised: 0 Page 15 of 30 Date: 28 September 2012

Document Number HG-Rig-011 Issued by, Rigging Department Approved by, Director

HaGun Institute

SCAFFOLDING RESPONSIBILITY PROCEDURE

Figure 10

Typical Tubular Steel Connectors and Coupler

Revised: 0 Page 16 of 30 Date: 28 September 2012

Document Number HG-Rig-011 Issued by, Rigging Department Approved by, Director

HaGun Institute

SCAFFOLDING RESPONSIBILITY PROCEDURE

Figure 11

Typical Tubular Steel Planking Details

Revised: 0 Page 17 of 30 Date: 28 September 2012

Document Number HG-Rig-011 Issued by, Rigging Department Approved by, Director

HaGun Institute

SCAFFOLDING RESPONSIBILITY PROCEDURE

Figure 12

Typical Tubular Steel Tie and Clamp Details

Revised: 0 Page 18 of 30 Date: 28 September 2012

Document Number HG-Rig-011 Issued by, Rigging Department Approved by, Director

HaGun Institute

SCAFFOLDING RESPONSIBILITY PROCEDURE

1.6 NOTES AND REFERENCES


OTHER GUIDES A10.8-1988 ANSI Standard Construction and Demolition Operations --- Scaffolding --- Safety Requirements

1.7 SECTION CONTENTS


This section provides basic rigging information for the safe use of slings. Rigging requires careful evaluation because of the wide variety of safety factors which must be considered in each case. These factors include, but are not limited to: size and type of sling, the method of fastening, sheaves, sprockets, and drums, condition of equipment or material, size and shape of load, type of attachment, the lifting environment, weather and atmospheric conditions. Some serious hazards result from overloading, improper hitching or slinging which allow the load to drop or slip; obstructing free movement of loaded sling; and using equipment for a purpose not intended or designed.

1.8 GENERAL REQUIREMENTS FOR RIGGING


1.8.1 SAFE USE OF SLINGS 1.8.1.1 Safe Operating Practice:
Slings that are damaged or defective should not be used. Slings should not be shortened with knots or bolts or other makeshift devices. Sling legs should not be kinked. Slings should not be loaded in excess of their rated capacities. Slings used in a basket hitch should have the loads balanced to prevent slippage. Slings should be securely attached to their loads. Slings should be padded or protected from the sharp edges of their loads. Suspended loads should be kept clear of all obstructions. All personnel should be kept clear of loads about to be lifted and of suspended loads. Hands or fingers should not be placed between the sling and its load while the sling is being tightened around the load. Shock loading is prohibited. A sling should not be pulled from under a load when the load is resting on the sling. Slings should be stored where they will not be damaged by extreme heat, corrosion, being run over, or being kinked.

Revised: 0 Page 19 of 30 Date: 28 September 2012

Document Number HG-Rig-011 Issued by, Rigging Department Approved by, Director

HaGun Institute

SCAFFOLDING RESPONSIBILITY PROCEDURE

1.8.2 TYPES OF SLINGS


Slings are available in alloy steel chain, wire rope with fiber core or steel rope core, metal mesh, natural or synthetic fiber rope, or synthetic wedding. Slings should be used in accordance with manufacturers recommendations and regulatory requirements.

1.8.3 RATED CAPACITY OF SLINGS


Care must be exercised when using tables and charts for slings. The units of measurements need to be noted in each case. Rated capacity may need to be reduced because of the configuration of attachment to load. Rated capacity may need to be reduced because of non-vertical load angel. Rated capacity may need to be reduced because of high or low operating temperatures. Rated capacity may need to be reduced because of end connection and splices. Rated capacity, where there is more than one leg, applies only where the load is distributed evenly between legs. Typical Rigging Arrangements (see following pages) Figure 1 Wire Ropes and Wire Rope Slings Table of Rated Capacities in Tons (2,000 lbs.) Figure 2 Other Wire Rope and Wire Rope Slings Table of Rated Capacities in Tons (2,000 lbs.) Figure 3 Manila Ropes and Manila Rope Slings Table of Rated Capacities in Lbs. Figure 4 Manila Rope and Tackle Table of Rated Capacities in Lbs. Figure 5 Wire Rope Connections Figure 6 Stresses of Lines on Inclined Planes Figure 7 Weights of Materials for Approximating Rigging Loads.

Revised: 0 Page 20 of 30 Date: 28 September 2012

Document Number HG-Rig-011 Issued by, Rigging Department Approved by, Director

HaGun Institute

SCAFFOLDING RESPONSIBILITY PROCEDURE

Figure 13 Wire

Rope Slings Table of Rated Capacities in Tons (2000 lbs.)

Revised: 0 Page 21 of 30 Date: 28 September 2012

Document Number HG-Rig-011 Issued by, Rigging Department Approved by, Director

HaGun Institute

SCAFFOLDING RESPONSIBILITY PROCEDURE

Figure 14 Other

Wire Rope and Wire Rope Slings Table of Rated Capacities in Tons (2000 lbs.)

Revised: 0 Page 22 of 30 Date: 28 September 2012

Document Number HG-Rig-011 Issued by, Rigging Department Approved by, Director

HaGun Institute

SCAFFOLDING RESPONSIBILITY PROCEDURE

Figure 15

Manila Ropes and Manila Rope Slings Table of Rated Capacities in lbs.

Revised: 0 Page 23 of 30 Date: 28 September 2012

Document Number HG-Rig-011 Issued by, Rigging Department Approved by, Director

HaGun Institute

SCAFFOLDING RESPONSIBILITY PROCEDURE

Figure 16 Manila

Rope and Tackle Table of Rated capacities in Lbs.

1. 2. 3. 4.

Tables are based on the use of new manila rope and tackle that is in good condition. If sisal rope is used, values in tables should be reduced by one third. Tackle values allow for one snatch block, snatching lead line to engine spool. When using more than one snatch block, add one extra part for each additional snatch block in addition to the number of parts shown for the weight to lift.

Revised: 0 Page 24 of 30 Date: 28 September 2012

Document Number HG-Rig-011 Issued by, Rigging Department Approved by, Director

HaGun Institute

SCAFFOLDING RESPONSIBILITY PROCEDURE

Figure 17

Wire Rope Connections

The rated capacity of slings must be reduced according to the percent efficiency of the end connections.

Revised: 0 Page 25 of 30 Date: 28 September 2012

Document Number HG-Rig-011 Issued by, Rigging Department Approved by, Director

HaGun Institute

SCAFFOLDING RESPONSIBILITY PROCEDURE

Figure 18

Stress of Lines on inclined Planes

Revised: 0 Page 26 of 30 Date: 28 September 2012

Document Number HG-Rig-011 Issued by, Rigging Department Approved by, Director

HaGun Institute

SCAFFOLDING RESPONSIBILITY PROCEDURE


WEIGHT OF STEEL PLATE THICKNESS IN INCHES 3/8 1/2 5/8 3/4 7/8 1 POUNDS PER SQ. FOOT 15.3 20.4 25.5 30.6 35.7 40.8 SQ. FEET PER TON 131 98 79 65 56 49 THICKNESS IN INCHES 1 - 1/8 1 - 1/4 1 - 3/8 1 - 1/2 1 - 3/4 2 POUNDS PER SQ. FOOT 45.9 51.0 56.1 61.2 71.4 81.6 SQ. FEET PER TON 44 39 35.7 32 28 24

MATERIAL

APPROXIMATE WEIGHT PER CU. FOOT, IN POUNDS

Aluminium _____________________________________________________________ 166 Asphalt ________________________________________________________________ 81 Brass ________________________________________________________________ 524 Brick (common) (3 Tons Per Thousand) _____________________________________ 120 Bronze _______________________________________________________________ 534 Concrete (4050 Lbs. Per Cu. Yg.) __________________________________________ 150 Copper _______________________________________________________________ 537 Crushed Rock _______________________________________ (2565 Lbs. Per Cu. Yd.) 95 Dry Earth, Loose _____________________________________ (2052 Lbs. Per Cu. Yd.) 76 Iron Casting __________________________________________________________ 450 Lead _________________________________________________________________ 708 Lumber, Fir, Spruce (2666 Lbs. Per 1000 Bd. Ft.) _______________________________ 32 Lumber, Oak (5166 Lbs. Per 1000 Bd. Ft) _____________________________________ 62 Portland Cement (376 Lbs. Per Barrel) _______________________________________ 94 Steel _________________________________________________________________ 490 Water _______________________________________________________________ 62.5

Table 1.1 Weights of Materials for Approximating Rigging Loads

Revised: 0 Page 27 of 30 Date: 28 September 2012

Document Number HG-Rig-011 Issued by, Rigging Department Approved by, Director

HaGun Institute

SCAFFOLDING RESPONSIBILITY PROCEDURE

1.8.4 HAND SIGNALS


Common Used Hand Signals Figure 7 Crane Swinging Beam Hand Signals

Figure 7 Crane Swinging Beam Hand Signals (pt. 1/3)

Revised: 0 Page 28 of 30 Date: 28 September 2012

Document Number HG-Rig-011 Issued by, Rigging Department Approved by, Director

HaGun Institute

SCAFFOLDING RESPONSIBILITY PROCEDURE

Figure 7 Crane Swinging Beam Hand Signals (pt. 2/3)

Revised: 0 Page 29 of 30 Date: 28 September 2012

Document Number HG-Rig-011 Issued by, Rigging Department Approved by, Director

HaGun Institute

SCAFFOLDING RESPONSIBILITY PROCEDURE

Figure 7 Crane Swinging Beam Hand Signals (pt. 3/3)

Revised: 0 Page 30 of 30 Date: 28 September 2012

You might also like