Professional Documents
Culture Documents
CS/APR 2007/QMT337
: : : :
INSTRUCTIONS TO CANDIDATES 1. This question paper consists of two (2) parts : PART A (5 Questions) PART B (5 Questions)
2. 3.
Answer ALL questions in the Answer Booklet. Answer to each question in PART B should start on a new page. Do not bring any material into the examination room unless permission is given by the invigilator. Please check to make sure that this examination pack consists of: i) ii) iii) iv) v) the Question Paper an Answer Booklet - provided by the Faculty a one - page Appendix (List of Formulae) a one - page Appendix (Standard Normal Table) a graph paper - provided by the Faculty
4.
CONFIDENTIAL
CONFIDENTIAL
CS/APR 2007/QMT337
QUESTION 1 a) b) State TWO (2) characteristics of a good model. (2 marks) Give TWO (2) advantages of using mathematical models in problem solving. (2 marks)
QUESTION 2 State whether each of the following statements is TRUE or FALSE . a) In project management, the variance of the project completion time is equal to the sum of the variances of all the activities in a project. (1 mark) The corner-point solution method in solving a linear programming problem will provide one, and only one, optimum. (1 mark) If the Economic Order Quantity assumptions are met and a company orders more than the economic order quantity, then total annual holding cost will be greater than the total annual ordering cost. (1 mark) Sequential decisions are best made using decision trees. (1 mark) e) Simulation models are designed to generate optimal solutions, which can then be applied to real-world situations. (1 mark)
b)
c)
d)
CONFIDENTIAL
CONFIDENTIAL
CS/APR 2007/QMT337
QUESTION 3 Solve the following linear programming problem using the graphical method. Maximize z = 3x + 2y
subject to :
2x-6y 5x + 4y x + 2y y x, y
12 40 12 6 0
(6 marks)
QUESTION 4 An inventory system at ABC Company has the following data: Annual demand Ordering cost per order Price per unit Annual carrying cost a) = = = = 120 units RM45 RM200 24% of the unit price
b)
A supplier offers a 5% discount on the unit price if at least 100 units are purchased at a time. Should ABC Company take the offer? (4 marks)
QUESTION 5 Use the random numbers 98, 09, 68 and 44 to generate four random observations for the following probability distribution.
; otherwise (5 marks)
CONFIDENTIAL
CONFIDENTIAL
CS/APR 2007/QMT337
QUESTION 1
a)
A publishing house publishes three weekly magazines - Daily Life, Agriculture Today and Surf's Up. Publication of one issue of each of the magazines requires the following amounts of production time and paper. Magazine Daily Life Agriculture Today Surf's Up Production (hour) 0.01 0.03 0^02 Paper (kg) 0.2 0.5 0.3
Each week the publisher has available 50 hours of production time and 3,000 kg of paper. Total circulation for all three magazines must exceed 5,000 issues per week if the company is to keep its advertisers. The selling price per issue is RM2.25 for Daily Life, RM4.00 for Agriculture Today, and RM1.50 for Surf's Up. Based on past sales, the publisher knows that the maximum weekly demand for Daily Life is 3,000 issues; for Agriculture Today, 2,000 issues; and for Surf's Up, 6,000 issues. The production manager wants to know the number of issues of each magazine to produce weekly in order to maximize total sales revenue. Formulate a linear programming model for this problem. (6 marks)
CONFIDENTIAL
CONFIDENTIAL
CS/APR 2007/QMT337
b)
A clothing shop makes suits and blazers. The three main resources used are material A, material B, and labor hours. The shop has developed the following linear programming model for determining the number of suits (x) and blazers (y) to make in order to maximize profits. Maximize P = 100x + 150y (profit, RM) subject to : 10x+ 4y s 160 x + y 20 10x + 2 0 y < 3 0 0 x, y 5 0 (material A, square meters) (material B, square meters) (labor hours)
The final simplex tableau for the above problem is given below: Basis
Si X X
y 0 0 1 0
Si
s2 -16 2 -1 50
S3
RHS 20 10 10 Q
0 1 0 0
1 0 0 0
y p
i)
ii)
State how much of each resource is used at the optimum production level. (2 marks)
iii)
Calculate the new profit if 2 extra square meters of material A and 2 extra labor hours were available. (1 mark) Formulate the dual problem and state its optimal solution. (4 marks)
iv)
CONFIDENTIAL
CONFIDENTIAL
CS/APR 2007/QMT337
QUESTION 2
Computers Unlimited sells microcomputers to universities and colleges. The firm is able to supply the universities with computers from the following warehouses. Distribution Warehouse 1. Puchong 2. Tangkak 3. Grik Supply (No. of Computers) 420 610 340
Four universities have ordered microcomputers as follows. University A. Universiti Industri Malaysia (UIM) B. Universiti Pembangunan Malaysia (UPM) C. Universiti Cyberjaya (UC) D. Universiti Sentral Malaysia (USM) Demand (No. of Computers) 520 250 400 380
The shipping and installation costs (RM) per microcomputer from each distributor to each university are as follows: To From 1 2 3 A 22 15 28 8 17 35 21 C 30 20 16 D 18 25 14
a)
b)
Solve the above transportation problem. Calculate the the minimum total cost. (11 marks)
c)
CONFIDENTIAL
CONFIDENTIAL
CS/APR 2007/QMT337
QUESTION 3 The promoter of a pop concert in Ipoh must perform the activities shown in the table below before the concert can be held. Immediate Predecessor A A A B C C C D, H E, G F, 1 Duration (days) Optimistic Most Likely Pessimistic 12 8 10 3 3 10 6 8
6
Activities A B C D E F G H 1
J
6 3 20 7 9 7 16
11
15 3 30 8 16 8 18
12 8
8
10 6 1
7 2
a)
b)
Determine the critical path and the project completion time. (2 marks)
c)
Find the earliest completion time for each of the following activities:
i) ii) Activity E Activity F
(2 marks) d) The promoter wants a 92.92% chance of completing all preparations in time for a rehearsal. How far ahead of the scheduled rehearsal date should he begin working on the project? (4 marks)
CONFIDENTIAL
CONFIDENTIAL
CS/APR 2007/QMT337
QUESTION 4 The Semporna Manufacturing Company must decide whether to purchase a component from a supplier or manufacture the component at its plant in Melaka. If demand is high, Semporna Manufacturing could profitably manufacture the component. However, if demand is low, its unit manufacturing cost would be high due to underutilization of equipment. The following table shows the projected profit (RM'OOO) for Semporna Manufacturing's make-orbuy decision. Demand Decision Alternative Manufacture component Purchase component Low (L)
-20
20
The company estimates the probabilities of low and high demand at 0.45 and 0.55, respectively. Semporna Manufacturing is considering conducting a market research to study the potential demand for the component. The study is expected to report either favourable (F) or unfavourable (U) conditions. The reliability of the study is given below. P(F|L) = 0.10 a) P(F I H) = 0.60
Use a decision tree to recommend the optimal strategy for Semporna Manufacturing. (14 marks)
b)
How much is the market research information worth to Semporna Manufacturing? (1 mark)
CONFIDENTIAL
CONFIDENTIAL
CS/APR 2007/QMT337
QUESTION 5
The Iskandaria Manufacturing Company manufactures a component that has to be processed by one of two drill presses. The components are lined up in a single line and are worked on by either of the two drill presses as they become available. The components arrive at a rate of 100 per hour. Each press can process 60 units per hour. The company estimates that it costs RM2 for each hour a component spends in the queuing system. The cost of operating a press is RM6.30 an hour. Although at present, the company has 2 drill presses, the company is considering whether to install a third drill press. Make a comparison of the total hourly costs incurred by the company by operating 2 drill presses and 3 drill presses. Advise the company as to how many drill presses the company should operate. (15 marks)
CONFIDENTIAL
CONFIDENTIAL
APPENDIX 1
CS/APR 2007/QMT337
2. 3. 4.
Total inventory cost, TC = C o + C h + DP Reorder point, ROP = DL Bayes'Theorem, P(A|B) = P(B | A)P(A) P(B|A)P(A) + P(B|A)P(A)
5.
M z nil
III.
IV.
ri
^(k)sf 1 "I
_pj
s!d-Pr
v. vi.
= L,4
W
'=T
vii.
Po
n<s
Pn = <
Pn
n>s
i.
L= -
.-A.
iv.
W
W=
A. -
.-A.
q =
v.
P =
CONFIDENTIAL
CONFIDENTIAL
APPENDIX 2
CS/APR 2007/QMT337
Normal Curve Areas : P(Z >z) [Standard Normal Probability in right-hand tail]
z
00 01 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 1.9 2.0 2.1 2.2 2.3 2.4 2.5 2.6 2.7 2.8 2.9 30 3.5 4.0 4.5 5.0
00135 000 233 000 031 7 000 003 40 000 000 287
CONFIDENTIAL