You are on page 1of 47

National Cyclone Risk Mitigation Project (NCRMP) Revenue (DM) Department Government of Andhra Pradesh

Third Party Quality Audit(TPQA)


in Joint Venture with

MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

INDEX

1.0

Project Background

2.0 3.0 4.0 5.0

Third Party Quality Audit Consultant Review meetings and Major Events of this Month Status of TPQA Visits Progress of NCRMP works

3 3 4 5

6.0 7.0

District wise status of tests conducted by TPQA Details of Audit Reports Submitted during this Month

26 27

8.0

Observations of Submitted Reports

28

9.0

Details of Social & Environmental Reports Submitted in this Month

36

10.0

Non Compliance Reports(NCRs) Submitted During this month

36

1|Page

MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

1.0 Project Background


Andhra Pradesh (AP) state has one of the longest coastal belts in India. Out of 67,362 Km of road network in the state, the nine coastal districts cover 26,000 km of road length. Every year during the period of April-May and September-December, cyclonic situations set in to the Bay of Bengal. With the recent changes in climatic conditions, the catastrophic events are increasing resulting in very devastating cyclones like Laila, Jal etc where the loss is enormous. In the 97 years ranging from 1892 to 1989, there were as many as 67 cyclones within the State. It is essential to provide safe residential accommodation to the vulnerable population during any eventuality or disaster due to natural calamities such as cyclones and associated tidal waves and storm surges. The project is formulated based on experiences of Government of Andhra Pradesh in mitigating such disasters during the past and also keeping in view the existing facilities available in the project area in Andhra Pradesh. The Government of India has applied for a credit of US$ 255 Million equivalent from the International Development Association (IDA) toward the cost of National Cyclone Risk Mitigation Project (NCRMP), and it intends to apply the proceeds to payments for goods, works, related services and consulting services under this Project. National Cyclone Risk Mitigation Project (NCRMP) Project Implementation Unit (PIU), Andhra Pradesh, headquartered at Hyderabad has invited the consultants to submit proposals for providing the consultancy services for Third Party Quality Audit for 9 coastal districts namely Srikakulam, Vijayanagaram, Visakhapatnam, East Godavari, West Godavari, Krishna, Guntur, Prakasam and Nellore. The project Construction of Multipurpose Cyclone Shelters, Roads to Cyclone Shelters, Roads to habitations and Roads & Bridges under NCRMP is funded by International Development Association and received through Government of India. This consultancy is envisaged to audit the quality of works being implemented by various line departments working under PIU. The number of works under progress / for which agreements are concluded in each district is shown in the table below.
No. of works(Under Concluded Agreements) No. of works under Progress RHB RCS MPCS Bridges Roads (R&B) No. of works not started

District

RHB

RCS

MPCS

Bridges

Roads (R&B)

Total

Srikakulam Vizianagaram Visakhapatnam East Godavari West Godavari Krishna Guntur Prakasham Nellore

6 8 2 10 5 3 14 16

8 6 8 3 12 7 8

7 3 2 -

4 2 2 1 -

1 1 -

19 3 21 13 10 8 17 24 24

6 8 2 2 3 2 13 16

4 5 6 2 4 6

5 -

3 2 2 1

1 1 -

5 0 3 5 8 3 13 6 2

2|Page

MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

30 25 20 15 10 5 0 No. of works not started Works Under Progress

2.0

Third Party Quality Audit Consultant.

To provide Consulting Services of Third Party Quality Auditor for Construction of Multipurpose Cyclone Shelters, Roads to Cyclone Shelters, Roads to habitations, and Roads and Bridges under NCRMP in 9 coastal districts The Commissioner for Disaster Management & Project Director, Project Implementation Unit (PIU) NCRMP has selected Egis International in JV with Egis India Consulting Engineers (I) Pvt. Ltd. On 31 May2011, the Contract for Consultancy Service was signed between The Commissioner for Disaster Management & Project Director, Project Implementation Unit (PIU) NCRMP and the Egis International in JV with Egis India Consulting Engineers (I) Pvt. Ltd. 3.0 Review Meetings and Major Activities of this month
st

The Major activities of this month are as follows. The modified Quality Assurance Plan in 3 volumes duly attending the remarks pointed out by the World Bank. Necessary modifications are also carried out based on discussions during TPQA review meeting held on 05-11-2011. 1. 2. Volume 1 Contains Introduction, Quality Assurance Plans, Check Lists and Q.C Formats. Volume 2 Contains Quality Control Test Procedures.

3. Volume 3 Contains Technical Presentations.

3|Page

MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

4.0

Status of TPQA Visits:

The following table shows the details of TPQA visits to sites in respective districts.

District Srikakulam Vizianagaram Vishakhapatnam East Godavari West Godavari Krishna Guntur Prakasam Nellore

Total Number of Visits Up to Oct.'2011 82 45 61 64 75 45 68 94 98 In Nov.'2011 19 4 19 39 35 31 24 29 11 Up to Nov.'2011 101 49 80 103 110 76 92 123 109

No. of Visits by TPQA

4|Page

MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

5.0

Progress of NCRMP works:

The district wise progress of works is shown below. The works in the West Godavari are not started and the works in Krishna District has just started. At many places the first milestone is completed but works are not started. The line departments are to analyze the reasons for the slow progress and if necessary penalty for the slow progress as per the agreement conditions should be imposed.

Third Party Quality Audit by Egis India consulting services Summary of Activities Agreements for Packages Communicated PR
1 2 3 4 5 6 7 8 9 Srikakulam Vizianagaram Visakhapatnam East Godavari West Godavari Krishna Guntur Prakasham Nellore Total 5 0 13 4 3 4 6 11 16 62

S.No.

District

Status of works Progress


14 3 18 8 2 5 4 18 22 94

R&B
5 3 0 0 0 0 2 1 0 11

Not Started
5 0 3 5 8 3 13 6 2 45 73 139

Total Packages for which Agreements are received Total Number of works in the above packages

5|Page

MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Status of works in Srikakulam District up to 30.11.2011


Category Packages allotted under Phase - 1 Names of works under each package Road from DPN R&B road to Uddandapalem NCRMP/BW/AP/RHB/PRED/01/Santhabommali/003 Road from K. Umilada Junction to Koduru (Link Road) Road from Borubhadra, Malagam to Kollipadu via Seepuram, Gantapeta RHB NCRMP/B-W/AP/RHB/PRED/01/Polaki/006 Road from R&B road Mobagam to Duubakavanipeta via Gajapathinagaram Road from Talasamudram to Dola Regulator Road from R&B road Edulavalasa - Killam to Jonnam via Talasamudram Construction of bridge at Km 11/6-8 of NH-5 to Patnavanipeta Connecting Sundarapalem Construction of Minor Bridge at Km 12/2-4 of NH-5 to Surampeta Road via Naruva, Mentada Agreement No. / Date /2010-11, Dt. 30.04.2011 /2010-11, Dt. 30.04.2011 /2010-11, Dt. 30.04.2011 /2010-11, Dt. 30.04.2011 /2010-11, Dt. 30.04.2011 /2011-12, Dt. 30.04.2011 DHS 30.04.11 30.04.11 DFC 30.04.12 30.04.12 Progress up to 30.11.2011 First Milestone i.e. Earthwork & Cd works &GSB First Milestone i.e. Earthwork & Cd works &GSB First Milestone i.e. Earthwork & Cd works &GSB First Milestone i.e. Earthwork & Cd works &GSB First Milestone i.e. Earthwork & Cd works &GSB First Milestone i.e. Earthwork & Cd works &GSB First Milestone i.e. Foundation up to well capping Second Milestone i.e. Completion up to below the deck slab.

30.04.11

30.04.12

30.04.11

30.04.12

30.04.11

30.04.12

NCRMP/B-W/AP/RHB/PRED/01/Polaki/005

30.04.11

31.01.12

NCRMP/B-W/ AP/Br/R&B/01/ Patnavanipeta/001 Bridges NCRMP/B-W/AP/Br/R&B/01/ Surampeta/003

46/2011, Dt. 17.12.2010

17.12.10

17.06.12

45/20102011,Dt17.12.2010

17.12.10

17.03.12

6|Page

MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

NCRMP/B-W/AP/Br/R&B/01/Bendigadda/004

Construction of High level bridge across Bendigadda at KM 4/10 of Pundi-Parlakimidi road in Srikakulam Dt, A.P. Improvements NaupadaVenkatapuram road from 0/0to15/0km Road from NP road to URK Puram Road from Deppuru, Bahadapalli road to Onkuluru to Cyclone Shelter Road from R & B Road to Devunthalada Road from Pollada to Komarthalada to Cyclone Shelter Road from Koyyam R & B Road to Moosavanipeta Road from Mentada to Dovupeta

1/2010,Dt.11.11.2010

11.11.10

11.05.12

First Milestone i.e Foundation upto well caping Second mile stone i.e.WMM,Shoulders E/W,pipe culverts,GSB,R/W E/W,pipe culverts,GSB,R/W E/W,pipe culverts,GSB,R/W E/W,pipe culverts,GSB,R/W E/W,pipe culverts,GSB. E/W,pipe culverts,GSB. E/W,pipe culverts,GSB.

Roads

NCRMP/B-W/AP/RD/R&B/01/Nowpada/006)

43/2010-11,17.12.2010 G.O.Rt.No.451, Dt. 06.04.2011 G.O.Rt.No.451, Dt. 06.04.2011 G.O.Rt.No.451, Dt. 06.04.2011 G.O.Rt.No.451, Dt. 06.04.2011 G.O.Rt.No.451, Dt. 06.04.2011 G.O.Rt.No.451, Dt. 06.04.2011 G.O.Rt.No.451, Dt. 06.04.2011 G.O.Rt.No.451, Dt. 06.04.2011

17.12.10

17.03.12

06.04.11

29.09.12

06.04.11

29.09.12

NCRMP/BW/AP/RCS/PRED/01/V.Kotturui/002

06.04.11

29.09.12

RCS

06.04.11

29.09.12

30.04.11 30.04.11 30.04.11

07.05.12 07.05.12 07.05.12

NCRMP/B-W/AP/RCS/PRED/01/Etcherla/005

Road from Kotcherela road to Kollibhemavaram & Cyclone Shelter Road from Kotcherla road to Pathesundrapalem

30.04.11

07.05.12

E/W,pipe culverts,GSB.

7|Page

MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Status of works in Vizianagaram District up to 30.11.2011 Category Packages allotted under Phase - 1 Names of works under each package
Construction of Minor Bridge at Km. 7/2 near Puligadda of Konada Ramatheertham R&B Road to Konathalapalem via Yerukonda, Pasupam, Kollayavalasa (Z.P. Road) Construction of Minor Bridge at Km 15/2 near Chakaligedda of Konada Ramatheertham R&B road to Konatalapalem (via) Yerukonda, Pasupam, Kollayavalasa (ZP Road) Improvements to Road from Konada Ramatheertham (R&B) Road to Konathalapalem (Via) Pasupam, Yerukonda, Kollayavalasa from Km 12/0 to 16/5 (Km 0/0 to 4/0 i.e. up to NH-5 crossing)

Agreement No./ Date

DHS

DFC

Progress up to 30.11.2011

NCRMP/ B-W/ AP/ Br/ R&B/ 02/ Puligadda/ 007 Bridges NCRMP/ B-W/ AP/ Br/ R&B/ 02/ Chakaligadda / 008

31/2010-201 Dt. 1.12.2010

01.12.10

31.05.12

40.72% of work completed

34/2010-2011 Dt. 8.12.2010

08.12.10

07.06.12

74.57% of work completed

Road (R&B)

NCRMP/BW/AP/RD/R&B/ 02/ Konada/009

33/2010-201 Dt. 8.12.2010

08.12.10

07.03.12

95% of work completed

8|Page

MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Status of works in Visakhapatnam District up to 30.11.2011 Category Packages allotted under Phase - 1 Names of works under each package
Road from Vempadu to Patimeeda NCRMP/B-W/AP/RHB/PRED/03/Nakkapalli/001 Road from R&B road to Mulaparra up to Beach end Road from R&B B.P Kallalu to Matchvanipalem Road from R & B road to Pothu Rajannapalem NCRMP/B-W/AP/RHB/PRED/03/Paravada/004 Road from R & B road to Jalaripeta /2010-11, Dt. 28.03.2011 28.03.22 28.12.11

Agreement No. / Date


/2010-11, Dt. 11.01.2011

DHS

DFC

Progress up to 30.11.2011
Third Milestone i.e Road furniture & Shoulders work are in progress Third Milestone i.e Shoulders work are in progress For Second Milestone i.e WBM Gr-III is in progress For Second Milestone i.e WBM Gr-III is in progress Collection of B.T material is started for Third Milestone i.e B.T & Shoulders ..etc work Third Milestone i.e Road furniture & Shoulders work are in progrress Third Milestone i.e Road furniture & Shoulders work are in progrress Third Milestone i.e Road furniture & Shoulders work are in progress Third Milestone i.e Shoulders work are in progress For Second Milestone i.e WBM Gr-III is in progress For Second Milestone i.e WBM Gr-III is in progress

11.01.11

11.01.12

/2010-11, Dt. 11.01.2011

11.01.11

27.10.11

NCRMP/BW/AP/RHB/PRED/03/Anandapuram/003

/2010-11, Dt. 10.03.2011 /2010-11, Dt. 28.03.2011

10.03.11

09.12.11

RHB

28.03.11

27.12.11

NCRMP/B-W/AP/RHB/PRED/03/Rambilli/006 NCRMP/BW/AP/RHB/PRED/03/Atchutapuram/007

Road from R & B road to Venkayyapalem

/2010-11, Dt. 11.01.2011

11.01.11

11.10.11

Road from R&B road to Ava- Somavaram

/2011-12, Dt. 27.04.2011

27.04.11

26.01.12

9|Page

MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Road from R&B Road to Avarajam

/2011-12, Dt. 27.04.2011

27.04.11

26.01.12

Collection of B.T material is started for Third Milestone i.e B.T & Shoulders ..etc work

Status of works in Visakhapatnam District up to 30.11.2011 Category Packages allotted under Phase - 1
NCRMP/B-W/AP/RCS/PRED/03/ Anandapuram/001

Names of works under each package


Road from NH-5 to Ramarayadupalem

Agreement No. / Date


/2010-11, Dt. 15.09.2011

DHS

DFC

Progress up to 30.11.2011
1st Milestone i.e WBM Grade- II is in progress. 1st Milestone i.e CD works are completed & WBM GradeII is in progress. Ready to started 1st Milestone i.e CD works and WBM Grade- II is in progress. Earth work widening is in progress. Earth work widening is in progress.

15.09.11

14.06.12

Road from R&B road to Krishnampalem

/2010-11, Dt. 15.09.2011

15.09.11

14.09.12

NCRMP/B-W/AP/RCS/PRED/03/ Rambilli/002 RCS

Road from R & B road to Kattubolu to Marripalem

/2010-11, Dt. 15.09.2011

15.09.11

14.09.12

Road from R & B road to Rajakoduru

/2010-11, Dt. 15.09.2011

15.09.11

14.09.12

NCRMP/B-W/AP/RCS/PRED/03/ Nakkapalli/003

Road from R & B road to Pedateenarla to Chinateenarla Road from Upamaka Rajayyapeta R & B road to Janakayyapeta

/2010-11, Dt. 15.09.2011

15.09.11

14.06.12

/2010-11, Dt. 15.09.2011

15.09.11

14.06.12

10 | P a g e

MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Status of works in Visakhapatnam District up to 30.11.2011

Category

Packages allotted under Phase - 1

Names of works under each package Construction of cyclone shelter at Gajapathi Nagaram

Agreement No. / Date

Milestone Completion Dates First Second Third

Progress w.r.t. milestone up to 30.11.2011

/2011-12, Dt. 03.10.2011

02.02.12

02.06.12

02.10.12

Not to be started

NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/003 Construction of cyclone shelter at Ratnayampeta Construction of cyclone shelter at Patimeeda Construction of cyclone shelter at Moolaparra /2011-12, Dt. 03.10.2011 /2011-12, Dt. 03.10.2011 /2011-12, Dt. 03.10.2011 02.02.12 02.06.12 02.10.12 E/W for foundation work is in progress

02.03.12

02.08.12

02.01.13

Not to be started

NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002 MPCS

02.03.12

02.08.12

02.01.13

E/W for foundation work is in progress

Construction of cyclone shelter at Bangarampeta

/2011-12, Dt. 03.10.2011

02.03.12

02.08.12

02.01.13

Foundation PCC work is in progress

NCRMP/B-W/AP/MPCS/PRED/03/Rambillii/004

Construction of cyclone shelter at Venkayyapalem

/2011-12, Dt. 03.10.2011

02.01.12

02.04.12

02.07.12

Earth work excavation is in progress

NCRMP/B-W/AP/MPCS/PRED/03/Parawada/001

Construction of cyclone shelter at Tikkavanipalem

/2011-12, Dt. 07.10.2011

06.01.12

06.04.12

06.07.12

Earth work excavation is in progress

11 | P a g e

MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Status of works in East Godavari District up to 30.11.2011


Category Packages allotted under Phase - I Names of works under each package
Road from PR roads to Dasarivanipeta and to Cyclone Shelter

Agreement No. / Date

Mile stones

Remarks

First
/2011-12 Dt:27.04.2011 30-11-2011

Second
30-11-2011

Third
20-01-2012
Work stopped due to land acquisition problem In between chainage Km.1.400 to Km.2.280 Work stopped due to land acquisition problem Pipe Culverts completed in Km :0/2 & 1/6 Culverts completed in Km:0/2 & WBM Gr. iii Layer work is in progress in between chainage Km.1.100 to Km. 1.775 Jungle clearance & Np3 600 mm dia pipe Culvert Completed in Km. 0/2 Jungle clearance & Np3 600 mm dia pipe Culvert Completed in Km. 0/2 Work stopped due to land acquisition problem In between chainage Km.1.400 to Km.2.280 Work stopped due to land acquisition problem Pipe Culverts completed in Km :0/2 & 1/6

NCRMP/B-W /AP/RHB/PRED/04/Katrenikona/003

NCRMP/B-W /RCS/PRED/04/Karapa/001

Approach Road to cyclone Shelter at Adavipudi

2011-12 Dt:20.05.2011

30-11-2011

31-10-2011

31-01-2012

RHB (2 ) RCS (8) MPCS (3)

NCRMP/B-W /AP/RHB/PRED/04/Karapa/001/

Road from Gurajanapalli to Bandulavaripalem Road from R&B Road to P.Chodipallipeta CS

2011-12 Dt:27.04.2011

30-09-2011

31-10-2011

31-01-2012

NCRMP/B-W /AP/RCS/PRED/04/Thondangi/004

2011-12 Dt:07.09.2011

3 months

3 months

3 months

NCRMP/B-W /AP/RCS/PRED/04/Thondangi/004

Road from R&B Road to K.Chodipallipeta CS

/2011-12 Dt:07.09.2011

3 months

3 months

3 months

NCRMP/B-W /AP/RCS/PRED/04/Thondangi/004

Road from R&B Road to Hukumpeta CS

/2011-12 Dt:07.09.2011

3 months

3 months

3 months

12 | P a g e

MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

NCRMP/B-W /AP/RCS/PRED/04/Thondangi/004

Road from R&B Road to Gaddipeta CS

/2011-12 Dt:07.09.2011

3 months

3 months

3 months

Jungle clearance is in progress

NCRMP/B-W /AP/RCS/PRED/04/Thondangi/004

Road from R&B Road to Danavaipeta CS

/2011-12 Dt:07.09.2011

3 months

3 months

3 months

Jungle clearance is in progress

NCRMP/B-W /AP/RCS/PRED/04/Thondangi/004/

Road from R&B Road to G.Musalayyapeta CS

2011-12 Dt:07.09.2011

3 months

3 months

3 months

To be started

NCRMP/BW/AP/RCS/PRED/04/Uppalaguptam/003

Road from R&B Road to Chinaraghavulapeta Cyclone Shelter Construction of Cyclone Shelter at Pedaraghavulapeta of Uppalaguptam Mandal E.G.Dt. Construction of Cyclone Shelter at Laxamanudupadu inThondangi

/2011-12 Dt: 23.09.2011

3 months/ 22.11.2011

3 months 22.06.2011

-----------

Not yet Started

NCRMP/BW/AP/MPCS/PRED/04/Uppalaguptam/002

/2011-12 Dt:17.10.2011

3 months 16.01.2012

3 months 16.04.2012

3 months 16.07.2012

Not yet Started

NCRMP/B-W /AP/MPCS/PRED/04/Thondangi/004

/2011-12 Dt:07.09.2011

Not yet Started

NCRMP/B-W /AP/MPCS/PRED/04/Thondangi/004

Construction of Cyclone Shelter at Avulamanda

/2011-12 Dt:07.09.2011

Not yet Started

13 | P a g e

MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Status of works in West Godavari District up to 30.11.2011 Category Packages allotted under Phase - 1 Names of works under each package
Road from NH 214 A at Ranga Statue center to Harijanawada of Kalipatnam (E) (Mogalthuru Mandal W.G.Dist.) R&B road at Panchayat Office to Pulaparthivarithota via Badava (Mogalthuru Mandal W.G.Dist.) Mogalthuru Vempa R&B Road at Uchintha Kalava Bridge to Gogulamma Harijanapeta (Mogalthuru Mandal W.G.Dist.)

Agreement No. / Date

DHS

DFC

Progress up to 30.11.2011
Works not started

NCRMP/B-W/AP/RHB/ PRED/05/Mogalthuru/001

/2011-12 , Dt. 27.04.2011

27.04.11

26.07.2012

GrII and GSB 595 mts Completed, 2 culverts completed Works not started

From Narsapur Mogalthuru R&B road to Dayadaldaspeta via Venkateswara Swamy temple (Mogalthuru Mandal W.G.Dist.) RHB Road from NH 214 A road to Harijanapeta of Kothota (Mogalthuru Mandal W.G.Dist.) R&B Road to Indira nagar (via) Pochamma temple (Narsapur Mandal W.G.Dist.) Road from R&B road to Pedalanka (Narsapur Mandal W.G.Dist.) Road from LB Cheria CC road to Chillapalem of LB Cheria (Narsapur Mandal W.G.Dist.) From A-U R&B Road to Satyanarayanapuram, (Kalla Mandal W.G.Dist.) From A-U R&B Road to Mekaladibba

CC Road completed

NCRMP/B-W/AP/RHB/ PRED/05/Narsapur/002

/2011-12 , Dt. 09.05.2011

09.05.11

08.05.2012

Works not started

NCRMP/B-W/AP/RHB/ PRED/05/Kalla/003

/2011-12 , Dt. 26.05.2011

26.05.11

25.02.2012

Works not started

14 | P a g e

MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Status of works in Krishna District up to 30.11.2011 Category Packages allotted under Phase 1
NCRMP/BW/AP/RHB/PRED/06/Machipatnam/001

Names of works under each package


Road connecting R&B road through Gantalammapalem

Agreement No. / Date


/2011-12 Dt.27.4.2011

DHS

DFC

27.04.11

26.01.2012

GSB work in progress and Pipe culvert excavation work in progress Jungle clearance and earth work in progress

Progress up to 30.11.2011

Road from R & B Road to B.V Thota NCRMP/BW/AP/RHB/PRED/06/Machipatnam/002 Road from Potlapalem Z.P road to Chikativanipalem RHB Road from Intheru R&B Road to Rangaraopet /2011-12 Dt.27.4.2011 27.04.11 26.01.2012

Jungle clearance and earth work in progress Jungle clearance and earth work in progress Jungle clearance and earth work in progress. Material collected (sand) and Gravel. Pipe culvert construction work in progress

NCRMP/BW/AP/RHB/PRED/06/Kruthivennu/003

Road from R&B road to Cyclone Shelter at Chandala

/2011-12 Dt.27.4.2011

27.04.11

26.01.2012

15 | P a g e

MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Status of works in Krishna Districts up to 30.11.2011 Milestone Completion Dates Category Packages allotted under Phase - 1 Names of works Agreement No. under each / Date package First Second Third Progress w.r.t. milestone up to 30.11.2011

Remarks

Road from Bhogireddipalli R&B Road to Ramakhandam

/2011-12/ Dt.02.09.2011

01.12.2011

01.03.12

01.06.12

5%

Jungle clearance work in progress

RCS

NCRMP/B-W /AP/RCS/PRED/06/Machipatnam/001

Road from R&B Road Chinnapuram to Gundupalem

/201112/27.04.2011

01.12.2011

01.03.12

01.06.12

10%

GSB work in progress

Road from Potlapalem Z.P road to Pothepalli.

/2011-12/ Dt.02.09.2011

01.12.2011

01.03.12

01.06.12

10%

Jungle clearance work in progress and leaves taken

16 | P a g e

MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Status of works in GUNTUR District up to 30.11.2011 Category Packages allotted under Phase - 1
NCRMP/BW/AP/RHB/PRED/07/KARLAPAL EM/001 RHB NCRMP/BW/AP/PRED/07/Nagaram/002

Names of works under each package


R/f Ganapavaram R&B Road to Kesavapuri ST colony

Agreement No./ Date


7/2011-2012 27.04.2011

DHS
27.04.11

DFC
26.01.2012

Progress up to 30.11.2011
2nd milestone completed ,Work yet to be start CC Road completed, Earth Work is in progress. Earth Work is in Progress. Total cost of project is Rs 330.00 lakhs, total amount of 1st, 2nd mile stone is Rs 2,05,33,000.00 , Up to 30.11.2011 Work done is 2,10,00,000.00 Total cost of project is Rs 370.00 lakhs, total amount of 1st, 2nd mile stone is Rs 1,91,98,882.00 Up to 30.11.2011 Work done is Rs 2,80,00,000.00

R/f R&B Road to Mohammad Alipalem 8/2011-2012 27.04.2011 27.04.11 26.4.2012

R/f R&B Road to Katuivaripalem.

NCRMP/BW/AP/Br/R&B/07/Bapatla/010

Reconstruction of High level Bridge @Km5/2 of Bapatla-Suryalanka Road across Perali drain in Guntur

79/2010-2011 1.12.2010

01.12.10

31.5.2012

Bridges Reconstruction of High level Bridge @Km2/4 of Bapatla-Pandurangapuram Road across Perali drain in Guntur

NCRMP/BW/AP/Br/R&B/07/Bapatla/011

78/2010-2011 1.12.2010

01.12.10

31.5.2012

17 | P a g e

MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Status of works in GUNTUR District up to 30.11.2011 Category Packages allotted under Phase - 1 Names of works under each Agreement No. / package Date
Road from R&B Road to Mandevaripalem Road from R&B Road Alluru to Yadavapalem Road from Ganapavaram R & B road to Pedamarpuvaripalem Road from R & B Road to Chinapuluguvaripalem NCRMP/BW/AP/RCS/PRED/07/KarlaPalem/002 Road from R & B road to Yaramvaripalem Road from R & B road to Pedagollapalem Cyclone Shelter Pedagollapalem PR Road to Bonthagorlapalem Road from R&B Road to Gurunadhanagar Road from R&B Road to Adavala H/O Bavajipalem /2010-11 Dt.01.11.2011 /2010-11 Dt.01.11.2011 /2010-11 Dt.01.11.2011 /2010-11 Dt.01.11.2011 /2010-11 Dt.01.11.2011 /2010-11 Dt.01.11.2011 /2010-11 Dt.01.11.2011 /2010-11 Dt. 17.10.2011 /2010-11 Dt. 17.10.2011

DHS

DFC

Progress up to 31.10.2011

NCRMP/B-W/AP/RCS/PRED/07/P Palem/001

01.11.11

31.07.2012

Not yet started

01.11.11

31.07.2012

Not yet started

01.11.11

31.10.2012

Not yet started

01.11.11

31.10.2011

Not yet started

RCS

01.11.11

31.10.2011

Not yet started

01.11.11

31.10.201

Not yet started

01.11.11

31.10.201

Not yet started

NCRMP/BW/AP/RCS/PRED/07/Nizampatnam/003

17.10.11

16.07.12

Work to be Grounded

17.10.11

16.07.12

Work to be Grounded

18 | P a g e

MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Road from R&B Road to Atlavaripalem Road from R&B Road to Hanumanthanagar Road from R & B road to Adarsanagar

/2010-11 Dt. 17.10.2011

17.10.11

16.07.12

Work to be Grounded

NCRMP/BW/AP/RCS/PRED/07/Bapatla/004

2010-11 Dt13.10.2011

Not yet started 13.10.11 12.07.2012 Not yet started

19 | P a g e

MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Status of works in Prakasam District up to 31.10.2011 Category Packages allotted under Phase - 1
NCRMP/B-W/AP/Br/R&B/08/ Kanaparthi/012

Names of works under each package


Construction of High level Bridge at Km 16/10 of Naguluppalapadu Kanaparthi road in Prakasam District Road from Pakala ZP Road to Atlavaripalem Cyclone shelter

Agreement No. / Date

DHS

DFC

Progress up to 31.10.2011
piers raised up to bed block & Abutment filter media working progress cc road completed & pipe culvert is in progress CC road laying progress, work not resumed not started C.D work is in progress,Gsb to bedone earth work widening progress,Gsb to bedone

BRIDGES

76/2010-11 Dated 1/12/2010

01.12.10

31.5.12

NCRMP/BW/AP/RHB/PRED/08/S.Konda/001

Road from R&B Road to Somarajupalli Road from R&B road to Narravaripalem

RHB

Road from NH5 to Mulaguntapadu Road from R&B road to Chalivendradibba NCRMP/BW/AP/RHB/PRED/08/S.Konda/002 Road from Pakala R&B road to Mosanaladinne Road from R&B road to Binginapalli Harijanawada Cyclone Shelter

NCRMP/BW/AP/RHB/PRED/08/S.Konda/001 Dated 10/02/2011 NCRMP/BW/AP/RHB/PRED/08/S.Konda/001 Dated 10/02/2011 NCRMP/BW/AP/RHB/PRED/08/S.Konda/001 Dated 10/02/2011 NCRMP/BW/AP/RHB/PRED/08/S.Konda/002 dated 10/02/2011 NCRMP/BW/AP/RHB/PRED/08/S.Konda/002 dated -10/02/2011 NCRMP/BW/AP/RHB/PRED/08/S.Konda/002 dated 10/02/2011 NCRMP/BW/AP/RHB/PRED/08/S.Konda/002 dated 10/02/2011

10.02.11 10.02.11 10.02.11 10.02.11 10.02.11

9.2.12 9.2.12 9.2.12 10.02.12 10.02.12

10.02.11

10.02.12

10.02.11

10.02.12

Work not Resumed

20 | P a g e

MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Status of works in Prakasam District up to 31.10.2011 Category Packages allotted under Phase - Names of works under 1 each package
NCRMP/BW/AP/RHB/PRED/08/Kothapatnam/00 3

Agreement No. / Date


NCRMP/BW/AP/RHB/PRED/08/Kothapatnam/003 Dated 27/04/2011

DHS
27.04.11

DFC

Road from R&B Road Allur to M T Raju colony

RHB

NCRMP/BRoad from KEM R&B Road W/AP/RHB/PRED/08/Kothapatnam/004 to Sankuvarigunta NCRMP/BDated 27/04/2011 W/AP/RHB/PRED/08/Kothapatnam/00 Road from KEM R & B NCRMP/B4 Road to Pullareddypalem W/AP/RHB/PRED/08/Kothapatnam/004 Dated 27/04/2011 Road from MC Road to NCRMP/BNCRMP/BSubbarayudu Satram W/AP/RHB/PRED/08/Ulavapadu/07 W/AP/RHB/PRED/08/Ulavapadu/07 dated 27/04/2011 NCRMP/BNCRMP/BRoad from R&B road Tettu W/AP/RHB/PRED/08/Ulavapadu/08 W/AP/RHB/PRED/08/Ulavapadu/08 to Ramayapatnam dated 27/04/2011 NCRMP/BW/AP/RHB/PRED/08/Tangutur/09 NCRMP/BW/AP/RHB/PRED/08/Tangutur/10 NCRMP/BRoad from R&B road Pellur W/AP/RHB/PRED/08/Tangutur/09 dated to Vasepallipadu 16/03/2011 Road from R&B road to Kesupalem NCRMP/BW/AP/RHB/PRED/08/Tangutur/10 dated 16/03/2011

CC road compleetd, Gsb progress material approval 27.04.12 shall be taken from competent authority. 27.04.12 27.04.12 27.04.12 27.04.12 WBM Gr-III progress WBM Gr-III progress Gsb progress WBM Gr-II progress

Progress up to 31.10.2011

27.04.11 27.04.11 27.04.11 27.04.11

16.03.11

CC road compleetd,Gsb progress material approval 16.03.12 shall be taken from competent authority.C.D work is in progress 16.03.12 Gsb progress

16.03.11

21 | P a g e

MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Status of works in Prakasam District up to 30.11.2011


Category Packages allotted under Phase -I Names of works under each package
Road from R&B road to vijayanagar colony cyclone shelter Road from NH road to Challareddypalem NCRMP/BW/AP/RCS/PRED/08/Vetapalem/001 Road from R&B road to jeevaraksh nagar colony cyclone shelter Road from R&B road to Ramnagar colony cyclone shelter Road from R&B road to cyclone shelter at Mankenavaripalem Road from R&B Road to Keertivaripalem cyclone shelter NCRMP/BW/AP/RCS/PRED/08/Chirala/002 Road from R&B Road to Devinutala cyclone shelter of chirala mandal in prakasam district. NCRMP/BW/AP/RCS/PRED/08/Vetapalem/00 1 dated 2011/12 dated 30.09.2011 29.01.201 2 29.05.201 2

Agreement No. / Date

Mile stones

Remarks

First

Second

Third
cc road completed & Grade-II work is in progress Grade-III progress cc road work is in progress

29.09.2012

not started

RCS

not started

not started NCRMP/BW/AP/RCS/PRED/08/Chirala/002 dated 27.08.2011

cc road laid 260 m out of 800 m work is not resumed.

22 | P a g e

MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Status of works in Prakasam District up to 31.10.2011 Names of works under each package
Chakicherla cyclone shelter in Ulavapadu Mandal Prakasam District MPCS Kanaparthy cyclone shelter in Nagulappapadu Mandal Prakasam District Not furnished

Category

Packages allotted under Phase - 1

Agreement No. / Date


Not furnished

DHS

DFC

Progress up to 31.10.2011

Foundation concrete work is in progress. Foundation concrete work is in progress.

23 | P a g e

MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Status of works in Nellore District up to 30.11.2011 Category Packages allotted under Phase - 1 Names of works under each package
Road from NH 5 to Sambasivapuram 34/2010-11, Dt. NCRMP/B-W/AP/RHB/PRED/09/Bogole/001 Road from 9/6 of Zuvvaladinne R&B Road to 19.01.2011 11/0 of Zuvvaladinne R&B via Venkideshpalem (Venkideshpalem) NCRMP/B-W/AP/RHB/PRED/09/Bogole/002 Road from 1/6 of Zuvvaladinne R&B road to / 2010 - 11, Dt. Tellagunta 07.02.2011 Road from R&B road to Muttembake Via Pittuvanipalli Road from R&B Chittamur to Soma Samudram Road from K.T R&B Road to Alliguntapalem Road from Km 5/8 of Chennayapalem Road 32/2010-11, Dt. to Gummadi Bandala 17.01.2011 Road from Pedapattapupalem R&B road to Chennayapalem H. Wada NCRMP/BW/AP/RHB/PRED/09/Vidavalur/005 NCRMP/BW/AP/RHB/PRED/09/Muthukur/006 NCRMP/BW/AP/RHB/PRED/09/V.Chalam/007 Road from R&B Road Alaganipadu to Vavilla / 2011 - 12, Dt. Road from R&B road Kancharapalem HW to 27.04.2011 Alaganipadu Road from R&B Road to PatuvariKandriga Survepalli Pudiparthi Road to Srikanth Colony Road from R & B Road to Edagali Kandriga /2010-11 Dt.25.04.2011 / 2011 - 12, Dt. 27.04.2011 19.01.11 19.4.12 WBM Gr-III is in Progress 07.02.11 06.11.11 WBM Gr-II Completed GSB Completed 18.01.11 18.4.12 GSB Completed BT is in progress 17.01.11 27.4.12 BT Completed Side Earth in progress CC Road completed 27.04.11 27.7.12 Side Earth is in Progress BT Completed WBM Gr_III Completed WBM Gr.II Completed

Agreement No. / Date

DHS

DFC

Progress up to 30.11.2011
WBM Gr-II Completed

NCRMP/BW/AP/RHB/PRED/09/Chittamur/003 RHB

2010-11Dt 18.01.2011

NCRMP/B-W/AP/RHB/PRED/09/Kavali/004

RHB

25.04.11

25.1.2012

27.04.11

27.4.2012

24 | P a g e

MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

NCRMP/B-W/AP/RHB/PRED/09/Allur/009

Road from R&B Road Allur to Galidibbalu (via) Chukavanidibba Road from R&B Road to A.S. Puram Road from GD road to Vavillapalem Road from R&B road Kappaladoruvu to Bandlapalem H.Wada Road from Katuivaripalem R&B Road to Vellapalm

/2010-11 Dt. 24.01.2011 201011Dt10.05.2011 /2010-11 Dt. 21.04.2011 /2010-11Dt 23.05.2011

24.01.11

24.4.2012

GSB is Completed Earth work in embankment Earth work in embankment WBM-Gr-III Jungle clearance is in progress GSB is in progress Construction of culvert is in progress

NCRMP/B-W/AP/RCS/PRED/09/Kota/001 NCRMP/BW/AP/RCS/PRED/09/Muthukur/002 RCS NCRMP/B-W/AP/RCS/PRED/09/Chillakur/004 NCRMP/BW/AP/RCS/PRED/09/T.P.Gudur/005 NCRMP/BW/AP/RCS/PRED/09/DV.Satram/008

10.05.11

10.2.2012

21.04.11

21.1.2012

23.05.2011 17.05.2011 09.05.2011

23.2.2012 17.2.2012 9.2.2012

Road from 7/2 M.C road to Venkannapalem 2011-10 Dt Pattapupalem 17.05.2011 Road from R&B road to Sullurpeta Mallam to /2010-11 Dated Berjengalapalli cyclone shelter 9.05.2011

25 | P a g e

MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

6.0 District wise status of tests conducted by TPQA: Apart from monitoring the tests being conducted by the implementation team (contractors & Line department) at various stages, the Third party Quality Audit team also conducted tests to confirm its compliance with the standards. These tests are carried out in the site itself and in some cases samples are collected and testing done in outside laboratories. The details of tests conducted in the field till end of September 2011 are presented.

Summary of QC Tests - Up to 30.11.2011 S.No.


1 2 3 4 5 6 7 8 9

District
Srikakulam Vizianagaram Visakhapatnam East Godavari West Godavari Krishna Guntur Prakasham Nellore Total

Total No. Tests Done


174 159 250 119 11 3 173 259 240

Total no. of Tests Passed


156 156 244 119 11 2 173 257 236

Failed
18 3 6 0 0 1 0 2 4

1388

1354

34

The works in West Godavari and Krishna Districts were just started

26 | P a g e

MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

7.0 Details of Audit Reports Submitted During this Month:


S.NO District Package Number Name of work For the work Road from R&B Road to Kesupalem in Tangatur Mandal Road from R&B Road to Allur to M.T.Raju colony in Kothapatnam mandal in Prakasham district. Construction of HLB in Km 16/10 of Naguluppapadu-Kanaparthy road in Prakasam district Road from Pakala ZP Road to Aulavaripalem Cyclone Shelter The Work from KEM R&B Road TO Pullareddypalem village Kothhapatnam mandal. Road from R&B Road Tettu to Ramayapatnam in Ulavapadu Mandal The Work from KEM R&B Road TO Sankuvarigunta village Kothhapatnam mandal. Road from R&B Road to Somarajupalli The Work Road from M.C Road to Subbarayadu Satram in Ulavapadu Mandal Road from R&B Road Pellur to Vasepallipadu - Tangur (M)

1 2 3 4 5 6 7 8 9 10

Prakasham Prakasham Prakasham Prakasham Prakasham Prakasham Prakasham Prakasham Prakasham Prakasham

NCRMP / B-W /AP/RHB/ PRED / 08 / Tangatur/10 NCRMP/BW/AP/RHB/PRED/08/KOTHAPATNAM/003 NCRMP/B-W/AP/Br/R&B/08/Kanaparthy/012 NCRMP/BW/AP/RHB/PRED/08/Singarayakonda/001 NCRMP/BW/AP/RHB/PRED/08/KOTHAPATNAM/004 NCRMP / B-W /AP/RHB/ PRED / 08 / Ulavapadu/008 NCRMP/BW/AP/RHB/PRED/08/KOTHAPATNAM/004 NCRMP/B-W/AP/RHB/PRED/08/S.Konda/001 NCRMP / B-W /AP/RHB/ PRED / 08 / Ulavapadu/007 NCRMP / B-W /AP/RHB/ PRED / 08 / Tangutur/09

27 | P a g e

MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

8.0

Observations in the submitted reports: For the work Road from R&B Road to Kesupalem in Tangatur Mandal
35.76 % value of the work is completed. Works to be done as per Milestone: Mile stone 1 to the end of Dt: 18.07.11- Earthwork, CD Works . Mile stone 2 to the end of Dt: 18.10.11- WBM Gr-II, Gr-III and CD works. Mile stone 3 to the end of Dt: 18.01.12- BT, CC Pavement and Road furniture. Widening work is in progress. The field officers are requested to provide the material test reports to TPQA Staff for verification and to conduct the field tests. The field officers are requested to use only approved material for embankment as per IRC-36. IRC-36-1970 Para 9 states that I) When an existing embankment is to be widened, and its slopes are steeper than 4:1, horizontal benches of up to 600mm width shall be cut in to the old slope for ensuring adequate bond with the fresh embankment material to be added. The material obtained from cutting of the benches could be utilized in the widening of the embankment. However, when the existing slope against which the freshly material is to be placed in flatter than 4:1, the slope surface may only be ploughed or scarified instead of resorting to benching. II) The layers of the widened embankment shall be compacted to requirements of Para 7.12 and 7.14 of IRC-36. In such cases where the width of the widened portion is insufficient to permit the use of usual wider rollers, compaction may be carried out with the help of tandem/sheep foot roller or other approved plant. Construction of Piped causes way and CD works are in Progress. Rcc NP3 1000mm dia Pipes received at the site. The MTC of NP3 1000 mm dia pipes are not furnished. The field officers are requested to supply the same for verification The field officers are requested to follow the IRC-36 specifications during filling around and over the culverts. As per IRC 36, Para 8, The filling around and over culverts and other structures in the embankment area shall be carried out independently of the work on the main embankment. The embankment shall be brought up simultaneously in equal layers on each side of the structure, so as to avoid displacement and unequal pressure. ii) The soil in such cases shall be deposited in layers not exceeding 150mm in loose thickness and compacted thoroughly to the requirements of Para 7.14. When it may be impracticable to use power rollers or other heavy equipment, The compaction shall be carried out by mechanical tampers or by other approved methods. GSB material samples were collected by the TPQA and field officers and sent for necessary tests. The test results are awaited. Shoulder construction is in progress. The field officers are requested to follow the IRC 36 specifications, the code states that Shoulder construction should be so organised as to keep pace with the construction of different layers of the pavement. Q.C Lab is not established at site work. It is suggested to provide Q.C lab and conduct regular test and maintain registers.

Name of Work:
1. 2.

3.

4. 5. 6.

7. 8. 9.

Name of Work:
1. 2.

Road from R&B Road to Allur to M.T.Raju colony in Kothapatnam Mandal in Prakasham district.
8.77% value of the work is completed. Works to be done as per Milestone: Mile stone 1 to the end of Dt: 26.08.11- Earthwork, CD Works and GSB. Mile stone 2 to the end of Dt: 26.12.11- WBM Gr-II, Gr-III and Shoulders. Mile stone 3 to the end of Dt: 26.04.12- BT,CC Pavement and Road furniture. Widening work is in progress. The field officers are requested to provide the material test reports to TPQA Staff for verification and to conduct the field tests. The field officers are requested to use only approved material for embankment as per IRC-36. IRC-36-1970 Para 9 states that 1. When an existing embankment is to be widened, and its slopes are steeper than 4:1, horizontal

3.

28 | P a g e

MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

4.

5. 6. 7.

8. 9. 10.

11. 12. 13. 14. 15.

benches of up to 600mm width shall be cut in to the old slope for ensuring adequate bond with the fresh embankment material to be added. The material obtained from cutting of the benches could be utilized in the widening of the embankment. However, when the existing slope against which the freshly material is to be placed in flatter than 4:1, the slope surface may only be ploughed or scarified instead of resorting to benching. 2. The layers of the widened embankment shall be compacted to requirements of Para 7.12 and 7.14 of IRC-36. In such cases where the width of the widened portion is insufficient to permit the use of usual wider rollers, compaction may be carried out with the help of tandem/sheep foot roller or other approved plant. Clause -1501 of MORD states that (i) Contraction joints shall be mechanically sawn joints spaced 2.5 m to 3.75 m. Length of panel in the direction of traffic shall not be less than the width of the pavement. Joints shall be cut when the pavement is neither too soft nor too hard and is able to bear the weight of the machine and crew. Normally it may vary from 8 to 12 hours depending on weather conditions. (ii) Construction joints shall be butt joints and placed after a days work is over or when work is suspended for more than 30 minutes. (iii) Expansion joints shall be provided near bridges and slab culverts and consist of a bitumen impregnated joint/ premoulded synthetic joint filler board, about 20 mm thick, and dowel bars. The quality control tests should be conducted as per IRC SP-11, Maintain QC record and the same shall be produced to QA wing for verification. QC laboratory is not provided at site. The line deportment is requested to take necessary action and see that the Quality lab is established at site at an early stage. As per the agreement condition the GSB material is well graded material (stone aggregate9.5 mm to 4.75 mm size of gravel 66% and sand of size < 2.36mm @34%) is to be used for construction. But the contractor procured the quarry waste material from Chimakurthi granite quarry instead of the above said material, the same material is collected for testing for its suitability like CBR, PI the result are found CBR value is 23 which is more than the required value of 20 and PI is NP which is less than 6.The field officers are requested to get the prior approval before proceeding further from the Engineer in Charge. CD work in KM 0/600 and 0/800 with 600mm dia NP3 pipe culvert work is in progress. The pipe laying work is completed further work has to be taken up. The field officers are requested to provide the MTCs of pipes for verification. For CD work in KM 1/10 with 600mm dia NP3 pipe culvert, earth work is in progress. Further work has to be taken up. The field officers are requested to provide the MTCs of pipes for verification. The field officers are requested to follow the IRC-36 specifications during filling around and over the culverts. As per IRC 36, Para 8, The filling around and over culverts and other structures in the embankment area shall be carried out independently of the work on the main embankment. The embankment shall be brought up simultaneously in equal layers on each side of the structure, so as to avoid displacement and unequal pressure. II) The soil in such cases shall be deposited in layers not exceeding 150mm in loose thickness and compacted thoroughly to the requirements of Para 7.14. When it may be impracticable to use power rollers or other heavy equipment, The compaction shall be carried out by mechanical tampers or by other approved methods. Shoulders need to be taken up simultaneously with the GSB laying work, for better compaction at edges also. Shoulders are to be taken up In between KM 0/350 to 1/0, & 3/65 to 3/80 Km and HM stones are not available on the the road stretch. The field officers are requested to provide the same. Cautionary sign boards at necessary points and village name boards are not provided. The project informatory boards with all details were not provided as per aggregement.The same shall be provided as per the guidelines given by PIU, NCRMP.

Name of Work:
1. 2. 3.

Construction of HLB in Km 16/10 of Naguluppapadu- Kanaparthy road in Prakasam district

42.8% of Work is completed. Milestone-I Up to 31.05.2011 : Completion of foundation up to sill level, and found completed within the mile stone Milestone2 up to 31.12.2011: Completion up to below the deck slab. Completed.

29 | P a g e

MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

4. 5. 6. 7. 8. 9. 10. 11.

Milestone3 up to 31.05.2012 : Completion of entire work including approaches The alignment is verified and found fairly tallying with the approved drawing. Piers and Abutments and bed block Concrete work completed. Centering work for deck Slab has to be taken up. Non destructive test conducted for Piers and Abutments with Rebound hammer by Site Engineers on 12.09.2011 and the results are varying from 24 N/mm2 to 33 N/mm2. The field officers are also requested to apply cement slurry to the steel bars so as to protect from rusting. The field officers are also requested to get the samples of cement tested from every consignment, conduct all the required tests on cement such as cube strength, initial setting time, Final setting time, consistency, soundness etc. The reinforcement steel shall be neatly stored on wooden blocks, racks or platforms above the ground in clean and suitably marked to facilitate inspection and identification as per Cl.1603 of MORTH The width of filter media is verified and found between o.6m to 0.65m.The field officers are requested to provide the test reports for back fill material for verification. The back fill material shall conform the Cl.710.1.4 of IRC 78.It is observed that the construction of filter material is not as per cl.710.1.4 of IRC 78.The field officers are requested to rectify the same as pre IRC-78. TPQA Site Engineers have conducted tests for the input materials like Coarse aggregate, fine aggregate and water at site and the result found within the specified limits. The informatory & identification of semi reflective sign boards with all details were not provided as per agreement. The same may be provided immediately at site.. Project Name board with details are not provided at site. It shall be provided as per specifications. The field officers are requested to provide the invoices bills of the materials like cement, steel for verification The replica are received from the Executive Engineer wide Letter No. 3467/E.E.(R&B)/ATO/2011 Dated 03-09-2011 for the previous observations. Safety measures for workers such as helmets, gum shoes, jackets etc., are to be provided by the contractor as per 5.2 of agreement clause

12. 13. 14. 15. 16. 17.

Name of Work:
1. 2. 3. 4.

Construction of HLB in Km 16/10 of Naguluppapadu-Kanaparthy road in Prakasam district

88.48 % value of the work is completed. C.C.Road is completed. In between stretches 0/350 to 1/0, Curing is in Progress. Cores will be taken to verify depth and compressive strength after 28 days of laying. i) Construction of joints shall be mechanically sawn joints spaced 2.5 m to 3.75 m (ii) length of the panel in the direction of traffic shall not be less than the width of the pavement. (iii) Joints shall be cut when the pavement is neither too soft nor too hard and able to bear the weight of the machine and crew. Normally it may vary from 8 to 12 hrs depending on weather conditions Construction joints shall be butt joints and placed after a days work is over or when work is suspended for more than 30 minutes Expantion joints shall be provided near bridges and slab culverts and consists of a bitumen impregnated joints/ premoulded synthetic joints filler board about 20 mm thick, and dowel bars (i) After completion of the finishing operations, the surface of the pavement shall be covered with wet Hessain cloth, burlap or jute mats. They shall be maintained fully wetted and in position for 24 hrs (ii) Upon the removal of the wet covering out the end of 24 hrs, the slab shall be thoroughly wetted and cured by ponding or sprinklers. Widening work is in progress. The field officers are requested to provide the material test reports to TPQA Staff for verification and to conduct the field tests. The field officers are requested to use only approved material for embankment as perIRC-36. IRC-36-1970 Para 9 states that i) When an existing embankment is to be widened, and its slopes are steeper than 4:1, horizontal benches of up to 600mm width shall be cut in to the old slope for ensuring adequate bond with the fresh embankment material to be added. The material obtained from cutting of the benches could be utilized in the widening of the embankment. However, when the existing slope against which the freshly material is to be placed in flatter than 4:1, the slope surface may only be ploughed or

5. 6.

7.

30 | P a g e

MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

8. 9. 10.

scarified instead of resorting to benching. ii) The layers of the widened embankment shall be compacted to requirements of Para 7.12 and 7.14 of IRC-36. In such cases where the width of the widened portion is insufficient to permit the use of usual wider rollers, compaction may be carried out with the help of tandem/sheep foot roller or other approved plant. For GSB material, The field officer collected the soil samples and sent to Engineering college laboratory for conducting tests like. 1) Maximum dry density and OMC, 2) Liquid limit and Plastic limit, 3) Free swell index. The test results are awaited. The quality control tests should be conducted as per IRC SP-11, Maintain QC record and the same shall be produced to QA wing for verification. Q.C Lab is not established at site work. It is suggested to provide Q.C lab and conduct regular test and maintain registers.

Name of Work:
1. 2.

The Work from KEM R&B Road TO Pullareddypalem village Kothhapatnam mandal.
6.67 % of the work is completed. Works to be done as per Milestone: (Two works in this package) Mile stone 1 to the end of Dt: 26.08.11- Earthwork, CD Works and GSB. Mile stone 2 to the end of Dt: 26.12.11- WBM Gr-II, Gr-III and Shoulders. Mile stone 3 to the end of Dt: 26.04.12- BT and Road furniture. Widening work is in progress. The field officers are requested to provide the material test reports to TPQA Staff for verification and to conduct the field tests. The field officers are requested to use only approved material for embankment as per IRC-36. IRC-36-1970 Para 9 states that i) When an existing embankment is to be widened, and its slopes are steeper than 4:1, horizontal benches of up to 600mm width shall be cut in to the old slope for ensuring adequate bond with the fresh embankment material to be added. The material obtained from cutting of the benches could be utilized in the widening of the embankment. However, when the existing slope against which the freshly material is to be placed in flatter than 4:1, the slope surface may only be ploughed or scarified instead of resorting to benching. ii) The layers of the widened embankment shall be compacted to requirements of Para 7.12 and 7.14 of IRC-36. In such cases where the width of the widened portion is insufficient to permit the use of usual wider rollers, compaction may be carried out with the help of tandem/sheep foot roller or other approved plant. The contractor procured the quarry waste material from Chimakurthi granite quarry, the same material is collected for testing for its suitability like CBR and PI, the result are found CBR value is 23 which is more than the required value of 20 and PI is NP which is less than 6.As per clause 401.4 and 408 this material is suitable for sub grade construction. However the usage of this material requires deviation approval from the competent authority. The field officers are requested to get the prior approval before proceeding further from the Engineer in Charge. Shoulder formation has to be done simultaneously with the GSB,WBM GrII and Gr III Earth work excavation is completed for CD work at KM 1/100 and 1/600.Further work has to be taken up. Km and HM stones are not available on the the road stretch. The field officers are requested to provide the same. Cautionary sign boards at necessary points and village name boards are not provided. The quality control tests should be conducted as per IRC SP-11, Maintain QC record and the same shall be produced to QA wing for verification. QC laboratory is not provided at site. The line deportment is requested to take necessary action and see that the Quality lab is established at site at an early stage.

3.

4.

5. 6. 7. 8. 9. 10.

Name of Work: 1. 2.

Road from R&B Road Tettu to Ramayapatnam in Ulavapadu Mandal


96.00 % value of the work is completed. Shoulder works are in progress. Works to be done as per Milestone: Mile stone 1 to the end of Dt: 26.08.11- Earthwork, CD Works and GSB.

31 | P a g e

MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

3. 4. 5. 6.

7. 8. 9.
10. 11. 12. 13. 14. 15.

16.

Mile stone 2 to the end of Dt: 26.12.11- WBM Gr-II, Gr-III and Shoulders . Mile stone 3 to the end of Dt: 26.04.12- BT and Road furniture. The formation widths and Earthen shoulder widths are verified from Km 5/150 to Km 5/4 and at some locations shoulders have slipped and the same shall be rectified. CC road in between stretches Km 4/471 to Km 5/080. The width of the road verified as 5.5 meters out of estimate width 3.75 meters. The field officers are requested to furnish the reasons for change in the width of the road. The WBM GRADE -II thickness are verified and is tallying with the approved Drawing, the reports are enclosed in annexure-2 The BT road completed in between stretches Km 3/0 to Km 4/368.The thickness are verified and is tallying with the approved Estimate. The reports are enclosed in Annexure-II. The BT extraction test for Combined OGPC and SEAL COAT test conducted and the percentage of Binder content in the Combined OGPC and SEAL COAT observed as 4.2% to 4.4%. Hence satisfactory. The reports are enclosed in Annexure-III and Annexure-IV The granular shoulder work is in progress. The relative compaction test to be done. The CC road completed in between stretches Km 4/4 to Km 5/67. The compressive strength at the age of 28 days test conducted and the values are in between range 32.00N/mm2 to 34.66 N/mm2, for M-30 Grade of concrete. Concrete cores are taken from the cc road randomly in between stretches Km 4/4 to Km 5/67, to find the thickness and strength of the CC road. The Avg.thickness of cores are observed as 195 mm to 223 mm. The compressive strength of cores are tested, the average compressive strength of core is in between 26.08 N/mm2 to 27.13 N/mm2. The minimum Avg. values of compressive strength of core should be 85% of Grade of concrete (M30=30.00 N/mm2) i.e. 25.5 N/mm2. Hence satisfactory 1000mm dia eight rows culvert, 600mm dia single row culvert in village portion, 2 vents of 2.0 mts span RCC slab culvert, and Side drains in village portion are completed and the physical measurements are verified and are tallying with the approved drawing. White wash to be done to parapet walls of the existing culverts for the clear visibility of vehicular traffic. The widths of Shoulders are found Narrow at Bucking hum canal bridge between Km 5/150 to Km 5/4. it is suggested to provide extra width. MORD Specifications and IRC: SP-62-2004, Guidelines for the construction and design of Cement Concrete roads for low volume roads, need to be followed in cutting and spacing of joints and curing the CC road as mentioned below. (i) Construction of joints shall be mechanically sawn joints spaced 2.5 m to 3.75 m (ii) length of the panel in the direction of traffic shall not be less then the width of the pavement. (iii) Joints shall be cut when the pavement is neither too soft nor to hard and able to bear the weight of the machine and crew. Normally it may vary from 8 to 12 hrs depending on weather conditions Construction joints shall be butt joints and placed after a days work is over or when work is suspended for more than 30 minutes

Name of Work:
1. 2.

The Work from KEM R&B Road TO Sankuvarigunta village Kothhapatnam mandal.
28.47% of the work is completed. Works to be done as per Milestone: (Two works in this Package) Mile stone 1 to the end of Dt: 26.08.11- Earthwork, CD Works and GSB. Mile stone 2 to the end of Dt: 26.12.11- WBM Gr-II, Gr-III and Shoulders. Mile stone 3 to the end of Dt: 26.04.12- BT and Road furniture. Widening work is in progress. The field officers are requested to provide the material test reports to TPQA Staff for verification and to conduct the field tests. The field officers are requested to use only approved material for embankment as per IRC-36. IRC-36-1970 Para 9 states that i) When an existing embankment is to be widened, and its slopes are steeper than 4:1, horizontal benches of up to 600mm width shall be cut in to the old slope for ensuring adequate bond with the fresh embankment material to be added. The material obtained from cutting of the benches could be utilized in the widening of the embankment. However, when the existing slope against

3.

32 | P a g e

MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

4. 5.

6.

7. 8. 9.

10. 11.

12.

13. 14. 15. 16. 17.

which the freshly material is to be placed in flatter than 4:1, the slope surface may only be ploughed or scarified instead of resorting to benching. ii) The layers of the widened embankment shall be compacted to requirements of Para 7.12 and 7.14 of IRC-36. In such cases where the width of the widened portion is insufficient to permit the use of usual wider rollers, compaction may be carried out with the help of tandem/sheep foot roller or other approved plant. C.C Road completed in between stretches 1/400 to 1/500 Km. It is observed that the groves are not cut as per MORD specification MORD Specifications and IRC: SP-62-2004, Guidelines for the construction and design of Cement Concrete roads for low volume roads, need to be followed in cutting and spacing of joints and curing the CC road as mentioned below. (i) Construction of joints shall be mechanically sawn joints spaced 2.5 m to 3.75 m (ii) Length of the panel in the direction of traffic shall not be less than the width of the pavement. (iii) Joints shall be cut when the pavement is neither too soft nor too hard and able to bear the weight of the machine and crew. Normally it may vary from 8 to 12 hrs depending on weather conditions (iv) Expantion joints shall be provided near bridges and slab culverts and consists of a bitumen impregnated joints/ premoulded synthetic joints filler board about 20 mm thick, and dowel bars (v) After completion of the finishing operations, the surface of the pavement shall be covered with wet Hessain cloth, burlap or jute mats. They shall be maintained fully wetted and in position for 24 hrs (vi) Upon the removal of the wet covering out the end of 24 hrs, the slab shall be thoroughly wetted and cured by ponding or sprinklers. Two sets of cubes are tested for 7 days compressive strength at laboratory and the average value of 2 one set is 26.52 N/mmand average value of another set is 26.61 N/mm . And one set of cubes tested for 28days strength produced an average compressive strength of 31.70 N/mm for M-30 grade concrete. Approximate Compressive strength of C.C.Road is tested with Rebound hammer on 06.10.2011 and the results are varying from 32 N/mm2 to 38 N/mm2. Cores will be taken to verify depth and compressive strength after 28 days of laying. The contractor procured the quarry waste material from Chimakurthi granite quarry, the same material is collected for testing for its suitability like CBR and PI, the result are found CBR value is 23 which is more than the required value of 20 and PI is NP which is less than 6. As per clause 401 and 408 this material is suitable for sub grade construction. However the usage of this material requires deviation approval from the competent authority. The field officers are requested to get the prior approval before proceeding further from the Engineer in Charge. The thickness for GSB and WBM Gr II are verified at random and found fairly tallying with the estimated thickness. WBM Gr II work completed in between KM 0/000 to KM1/340, WBM GrII Work has to be taken up. a. SHOULDER construction work is in progress, the field officers are requested to follow the specification of IRC36. It specifies that the shoulder construction should be so organized as to keep pace with the construction of different layers of the pavement The field officers are requested to follow the IRC-36 specifications during filling around and over the culverts. As per IRC 36, Para 8, The filling around and over culverts and other structures in the embankment area shall be carried out independently of the work on the main embankment. The embankment shall be brought up simultaneously in equal layers on each side of the structure, so as to avoid displacement and unequal pressure. i) The soil in such cases shall be deposited in layers not exceeding 150mm in loose thickness and compacted thoroughly to the requirements of Para 7.14. When it may be impracticable to use power rollers or other heavy equipment, The compaction shall be carried out by mechanical tampers or by other approved methods. As per agreement 5.2 Clause Environment Management Plan not followed at site. It is suggested to follow them. Km and HM stones are not available on the the road stretch. The field officers are requested to provide the same. Cautionary sign boards at necessary points and village name boards are not provided. The project informatory boards with all details were not provided as per aggregement.The same shall be provided as per the guidelines given by PIU, NCRMP. The quality control tests should be conducted as per IRC SP-11, Maintain QC record and the same shall be produced to QA wing for verification.

33 | P a g e

MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

18.

QC laboratory is not provided at site. The line deportment is requested to take necessary action and see that the Quality lab is established at site at an early stage.

Name of Work:
1. 2. 3. 4.

Road from R&B Road to Somarajupalli


26.35 % value of the work is completed. Shoulder works are not in progress. C.C.Road 300 meters length is completed. In between stretches 1/076 to 1/376 Km, Curing is in progress. Cores will be taken to verify depth and compressive strength after 28 days of laying. MORD Specifications and IRC: SP-62-2004, Guidelines for the construction and design of Cement Concrete roads for low volume roads, need to be followed in cutting and spacing of joints and curing the CC road as mentioned below. (i) Construction of joints shall be mechanically sawn joints spaced 2.5 m to 3.75 m (ii) Length of the panel in the direction of traffic shall not be less than the width of the pavement. (iii) Joints shall be cut when the pavement is neither too soft nor to hard and able to bear the weight of the machine and crew. Normally it may vary from 8 to 12 hrs depending on weather conditions. Construction joints shall be butt joints and placed after a days work is over or when work is suspended for more than 30 minutes Expantion joints shall be provided near bridges and slab culverts and consists of a bitumen impregnated joints/ premoulded synthetic joints filler board about 20 mm thick, and dowel bars Longitudinal joints shall be provided for two lane road and shall be saw cut (i) After completion of the finishing operations, the surface of the pavement shall be covered with wet Hessain cloth, burlap or jute mats. They shall be maintained fully wetted and in position for 24 hrs. (ii) upon the removal of the wet covering out the end of 24 hrs, the slab shall be thoroughly wetted and cured by ponding or sprinklers. For GSB material, The field officer collected the soil samples and sent to Engineering college laboratory for conducting tests like. 1) Maximum dry density and OMC, 2) Liquid limit and Plastic limit, The test results are awaited. The quality control tests should be conducted as per IRC SP-11, and requested the field officers to Maintain QC record and the same shall be produced to QA wing for verification. Q.C Lab is not established at site work. It is suggested to provide Q.C lab and conduct regular test and maintain registers.

5.

6. 7. 8.

Name of Work:
1. 2.

The Work Road from M.C Road to Subbarayadu Satram in Ulavapadu Mandal
20.00 % value of the work is completed. Works to be done as per Milestone: Mile stone 1 to the end of Dt: 26.08.11- Earthwork, CD Works and GSB. Mile stone 2 to the end of Dt: 26.12.11- WBM Gr-II,& Gr-III. Mile stone 3 to the end of Dt: 26.04.12- BT, shoulders and Road furniture. The 600mm dia single row pipe culvert (2 No's) constructed at stretches Km 1/6 and km 3/2. The 600mm dia double row culvert ( 3 No's) constructed at stretches Km 2/4,Km 2/8,& Km 4/2. The 600mm dia Triple row culvert (2 No's) constructed at stretches Km 3/0,& Km 3/4. i) The field officers are requested to follow the IRC-36 specifications during filling around and over the culverts. As per IRC 36, Para 8, The filling around and over culverts and other structures in the embankment area shall be carried out independently of the work on the main embankment. The embankment shall be brought up simultaneously in equal layers on each side of the structure, so as to avoid displacement and unequal pressure. ii) The soil in such cases shall be deposited in layers not exceeding 150mm in loose thickness and compacted thoroughly to the requirements of Para 7.14. When it may be impracticable to use power rollers or other heavy equipment, The compaction shall be carried out by mechanical tampers or by other approved methods.

3.

34 | P a g e

MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

4.

5. 6. 7. 8. 9. 10.

Widening work is in progress. The field officers are requested to provide the material test reports to TPQA Staff for verification and to conduct the field tests. The field officers are requested to use only approved material for embankment as per IRC-36. IRC-36-1970 Para 9 states that i) When an existing embankment is to be widened, and its slopes are steeper than 4:1, horizontal benches of up to 600mm width shall be cut in to the old slope for ensuring adequate bond with the fresh embankment material to be added. The material obtained from cutting of the benches could be utilized in the widening of the embankment. However, when the existing slope against which the freshly material is to be placed in flatter than 4:1, the slope surface may only be ploughed or scarified instead of resorting to benching. ii) The layers of the widened embankment shall be compacted to requirements of Para 7.12 and 7.14 of IRC-36. In such cases where the width of the widened portion is insufficient to permit the use of usual wider rollers, compaction may be carried out with the help of tandem/sheep foot roller or other approved plant GSB samples collected and sent to laboratory for necessary tests. Awaiting for result Project Name board with details are not provided at site. It is suggested to provide them as per specifications. White wash to be done to parapet walls of the existing culverts for the clear visibility of vehicular traffic. As per agreement 5.2 Clause Environment Management Plan not followed at site. It is suggested to follow them. The quality control tests should be conducted as per IRC SP-11, Maintain QC record and the same shall be produced to QA wing for verification. QC laboratory is not provided at site. The line deportment is requested to take necessary action and see that the Quality lab is established at site at an early stage.

Name of Work:
1. 2.

Road from R&B Road Pellur to Vasepallipadu - Tangur (M)


57.60% of work is completed. Works to be done as per Milestone: Mile stone 1 to the end of Dt: 16.07.11- Earthwork, CD Works and GSB. Mile stone 2 to the end of Dt: 16.11.11- WBM Gr-II, Gr-III and Shoulders. Mile stone 3 to the end of Dt: 16.03.12- BT and Road furniture. Cc road completed in between KM 0/258.50 to 0/434.50 Km, and between KM 4/800 to 5/100 Approximate Compressive strength of C.C.Road is tested with Rebound hammer on 29.09.2011 and the results are varying from 26 N/mm2 to 32 N/mm2. 8No.s of Cores are taken to verify the thickness and compressive strength .The average thickness observed as 198mm to 223mm MORD Specifications and IRC: SP-62-2004, Guidelines for the construction and design of Cement Concrete roads for low volume roads, need to be followed in cutting and spacing of joints and curing the CC road as mentioned below. Field officer have stated that curing has been done on the next day of laying the concrete, however MORD(IRC;SP-62-2004) Specifications stipulates the following regarding curing of C.C.Road. After completion of the finishing operations, the surface of the concrete shall be covered with wet Hessain cloth, burlap or jute mats. They shall be maintained fully wetted and in position for 24 hrs upon the removal of the wet covering out the end of 24 hrs, the slab shall be thoroughly wetted and cured by ponding or sprinklers. Construction joints shall be butt joints and placed after a days work is over or when work is suspended for more than 30 minutes Expantion joints shall be provided near bridges and slab culverts and consists of a bitumen impregnated joints/ premoulded synthetic joints filler board about 20 mm thick, and dowel bars Longitudinal joints shall be provided for two lane road and shall be saw cut After minimum 28 days after casting the concrete pavement ,joints groove at contraction joint shall be widened to a 10 mm width and to a depth 18 to 20mmand shall be sealed The contractor procured the quarry waste material from Chimakurthi granite quarry, the same material is collected for testing for its suitability like CBR and PI, the result are found CBR value is 23 which is more than the required value of 20 and PI is NP which is less than 6.As per clause 401 and 408 this material is suitable for sub grade construction. However the usage of this material requires deviation

3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14.

35 | P a g e

MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

15.

approval from the competent authority. The field officers are requested to get the prior approval before proceeding further from the Engineer in Charge. As per agreement 5.2 Clause Environment Management Plan not followed at site. It is suggested to follow them.

9.0 Details of Social & Environmental Reports Submitted in this Month: S. No.
1 2 3 4 5 6 7 8 9 10 11 12

Package No.
NCRMP/BW/AP/MPCS/PRED/03/Nakkapalli/002 NCRMP/B-W/AP/RCS/PRED/03/Rambilli/002 NCRMP/BW/AP/MPCS/PRED/03/Nakkapalli/002 NCRMP/B-W/AP/RCS/PRED/03/Rambilli/002 NCRMP/BW/AP/RCS/PRED/03/Anandapuram/001 NCRMP/BW/AP/MPCS/PRED/03/Payakaraopeta/003 NCRMP/BW/AP/MPCS/PRED/O8/N.G.Padu/003 NCRMP/B-W/AP/Br/R&B/O8/Kanaparthy/012 NCRMP/BW/AP/RCS/PRED/O8/Cheerala/002 NCRMP/B-W/AP/Br/R&B/O7/Bapatla/010 NCRMP/B-W/AP/Br/R&B/O7/Perali/011 NCRMP/BW/AP/RHB/PRED/O7/Nagaram/002

Name of the work


Construction of cyclone shelter at Bangarampeta Road from R & B road to Krishnampalem. Construction of cyclone shelter at Patimeeda Road from R & B road to Rajakoduru. Road from NH-5 to Ramarayadupalem Construction of cyclone shelter at Ratnayampeta Kanaparthy Cyclone shelter Construction of HLB @ Km.16/10 of Naguluppapadu-Kanaparthy Road Road from R&B Road to Devinutula cyclone shelter Reconstruction of HLB at Km. 5/2 of Bapatla-Suryalanka Road Reconstruction of HLB at Km. 2/4 of Bapatla-Pandurangapuram across Perali Drain Road from Ganapavaram R&B Road to Mohammad Alipalem

District
Visakhapatnam Visakhapatnam Visakhapatnam Visakhapatnam Visakhapatnam Visakhapatnam Prakasam Prakasam Prakasam Guntur Guntur Guntur

10.0 Non Compliance Reports (NCRs) Submitted in this Month: S.No


1

District
Nellore

Package No
NCRMP/B-W/AP/RHB/PRED/09/Kavali/004

Name of Work
Road from KT R&B road to Alliguntalapalem. Road from 5/8 of Chennayapalem Road to Gummadi bandla. Providing BT surface to the road from Survepalli-Pudiparthi Road to Srikanth Colony. Providing BT surface to the road from R & B Road to Edagali Kandriga.

Nellore

NCRMP/B-W/AP/RHB/PRED/09/Kavali/004 NCRMP/BW/AP/RHB/PRED/09/V.Chalam/007 NCRMP/BW/AP/RHB/PRED/09/V.Chalam/007

Nellore

Nellore

36 | P a g e

National Cyclone Risk Mitigation Project (NCRMP) Revenue (DM) Department Government of Andhra Pradesh

Third Party Quality Audit


in joint venture

You might also like