SCOPE OF ACTIVITY The safe and effective use of BRP Road Patches for road maintenance purposes. NOTE: Additional site/job specific risk assessment via Safe Work Method Statement (SWMS) or Job Safety Analysis (JSA) will be required in most circumstances.
PPE Required
JOB STEPS
STEP 1 - PREPARATION
Responsibil ity
Project Requirements
PPE possibly required
Set up traffic management as per traffic authority requirements. Sweep application area free from all loose particles. Ensure area is dry and not polluted with oil, grease, diesel etc. (Pic 1) Mark out the area to be sealed with chalk etc. Note the BRP Road Patch should extend 100mm beyond the edge of the defect or area requiring sealing. (Pic 2) Size/shape the BRP Road Patch to match the marked out area by perforating the paper side with a Serrated Tracing Wheel. (Pic 3) Fold the sheet together on the stone side to create an open joint and then pull the sheets apart along the open joint. Observe safe manual handling techniques. 2 Supervisor Equipment: Chalk/Marking paint or like Measuring tape Broom for Sweeping Brush/Broom for Emulsion Application A perforating tool also known as a Serrated Tracing Wheel Emulsion CRS Cationic Grade Sand Appropriate amount for task Spill kit (Appropriate size liquids stored) Disposal Bags Parent: 1/6
Version: 1.0
Date : 16/02/2012
JOB STEPS STEP 2 - ADHESION Agitate the emulsion (shake the container), to ensure it is mixed well. Apply the emulsion evenly to the marked out area (Pic 5,6,7) & the back of the Road Patch (Pic 4) using a block brush, broom or Roller. Ensure coverage is even, leaving no uncovered areas or puddles of emulsion. Check the edges to ensure that they are evenly covered. Allow the emulsion to break on the pavement & the back of the Road Patch i.e. emulsion turns from brown to black and becomes very tacky. Ensure gloves and eye protection is worn during application.
Responsibili ty Worker
Version: 1.0
Date : 16/02/2012
Parent: 2/6
JOB STEPS
Responsibili ty
7
STEP 3 - POSITION
Place the first Road Patch onto the emulsion treated area paper side down, aggregate side upwards. If further Patches are required simply butt the edges of the BRP Road Patch tightly together by pushing (kneading) the BRP Road Patch with a foot to ensure a neat/tight fit. Do not overlap the BRP Road Patches at the joins. Repeat the process until all the patches have been placed. Observe safe manual handling techniques. Worker
Version: 1.0
Date : 16/02/2012
Parent: 3/6
Responsibili ty
Apply a small quantity of emulsion to the edges and joints using a brush (Pic 9). Blind the edges and joints with crusher dust or sand (Pic 10)
Worker
Roll over the Road Patch with a rubber tyred vehicle (Pic 11) Ensure the full width of the BRP Road Patch surface is rolled using the number of passes recommended in below. Ensure no contaminants enter drains or water courses. Any spillage must be cleaned immediately. Remove traffic management equipment and open the road to traffic. Worker/plant/vehicle interaction be aware of surroundings at all times Worker
Version: 1.0
Date : 16/02/2012
Parent: 4/6
JOB STEPS
Responsibili ty
Version: 1.0
Date : 16/02/2012
Parent: 5/6
Version: 1.0
Date : 16/02/2012
Parent: 6/6