Professional Documents
Culture Documents
Summary
1
Project Scope
Risk Analysis
Conclusions
Project Scope
The Scope of Work of this thesis is summarized by following points:
Dual Subsea Completion State of Art analyze existing case history from all main subsea vendors. Prons and Cons of Dual subsea completion, compared with standard single subsea completion. Camilla 2 Eni case history and close out post job report analysis.
Risk analysis and Risk evaluation of Camilla 2 activity.
Summary
1
Project Scope
Risk Analysis
Conclusions
Multilayers Reservoir
(more than two zones completed)
Simultaneus production from all completed zones
8
Crossover 3 1/2" x 2 7/8" WD HV-1 Shrouded ON-OFF Type Choke Size 2 7/8" Wireline Plug 2-3/8" FJ Tubing Gravel Pack Packer with 3.25" Seal Bore Gravel Pack Closing Sleeve
Moulded Seal Unit size 3.25" Polished Bore size 3.25" Pup Joint Locator with Moulded Seal Units For 3.25" Seal Bore
Gravel Pack Packer with 3.25" Seal Bore Gravel Pack Closing Sleeve Gravel Pack Screen on 4" Base Pipe
Locator with Moulded Seal Units For 3.25" Seal Bore Permanent Type Seal Bore Packer
10
Horizontal Trees
Disadvantages Requires an additional BOP trip Requires a SSTT and landing string BOP may require modifications to accommodate IWOC's umbilical Higher bending loads on the wellhead system Potential leak paths below the BOP Well must be plugged prior to removing the tree Some concern with wireline plugs for vertical barriers Longer emergency disconnect time Cannot pull tree independent of the completion
Metal sealing gate valves for environmental barriers, not field installed like wire line plugs Allow monitoring of all down hole functions as standard
Allows workover without pulling tree or disconnecting flowlines Flow base typically not required Flexibility of design to accomodate natural flow, gas lift, water injection and ESP
Tubing intervention simpler as no wire line plugs need to be retrieved Installed CAPEX considered to be lower the horizontal tree
Tubing hanger seals in the casing that could be damaged during drilling operations Need to remove the tree for tubing work over
11
12
It is used with the horizontal xmas tree, it accomodates the crown plug. Some suppliers may replace the internal tree cap with a longer tubing hanger.
13
14
15
16
17
Aker: NO applications.
19
Summary
1
Project Scope
Risk Analysis
Conclusions
20
21
Short String
Long String
22
PTR = 23,6 mt on water level Water Depth = 85 mt Csg 30 @169 mt TVD Csg 133/8 @344 mt TVD Liner head 7 @955 mt TVD Csg 95/8 @1104 mt TVD Liner 7 @1477 mt TVD
23
lev. 1
lev. 2+3
24
25
26
27
BUDGET
42,0 71,0 6,5 30,0 6,0 36,5 4,0 3,0 21,5 1,0 5,0 79,0 127,0 13,5 147,0 20,0 10,0 2,0 12,0 0,0 0,0 0,0 0,0 0,0 0,0
FINAL BALANCE
32,0 154,0 4,0 23,0 5,5 80,0 2,5 16,0 2,5 16,5 65,0 80,5 10,5 128,0 9,5 8,5 3,5 20,0 4,5 6,5 2,0 5,0 39,5
%
-23,8% 116,9% -38,5% -23,3% -8,3% 119,2% -16,7% -25,6% 150,0% 230,0% -17,7% -36,6% -22,2% -12,9% -52,5% -15,0% -70,8%
% of total
4,5% 21,4% 0,6% 3,2% 0,8% 11,1% 0,3% 2,2% 0,3% 2,3% 9,0% 11,2% 1,5% 17,8% 1,3% 1,2% 0,5% 2,8% 0,6% 0,9% 0,3% 0,7% 5,5%
TOTAL (Hours)
637,0
719,0
12,9%
TOTAL (Days)
26,5
30,0
29
Summary
1
Project Scope
Risk Analysis
Conclusions
30
Risk Analysis
The Risk Analysis was developed with these hipotesys:
The completion operations were deducted from the Camilla 2 completion because it is the most recent well completed with dual string by Eni. There are very few subsea wells with dual string completion, and a lot of them are old, so it is difficult to find the informations about the operations and the related problems. Therefore the values of Probability and Impact for the operations were found out with the help of expertises.
The analysis is qualitative and based on STAP-P-1-N-20913: Project Risk Management for Drilling, Completion and production Optimization Activities.
31
Risk Analysis
Completion execution phases:
Installation
Decommissioning
The Risk analysis was developed for Engineering & Procurement and Installation for the Single String and the Dual String with the mitigating actions for a risk reduction
32
Risk Analysis
N
Original Risk P I RL
Residual Risk
Mitigations
RL
Environment
Weather and sea conditions 1) B 2 M this could affect the real functioning system for the landing string and for drilling riser, so simulation could be aborted and not considered during the operations B 3 M
Rig
Availability 2) Market conditions: availability of the rig and costs: depend by the area of working, in case of mediterranean sea floating RIG are very poor, other areas permits to have RIG availability with different daily rate Mobilization on time: time to MOB/DEMOB and the travel Availability of specific equipment: Rig set for drilling activities C 5) Reliability (QA, HSE and maintenance) 4 M D C 4 4 M M plan activity where it is possible with the right completion schematic and based also on RIG availability on the markey plan the activity with right time in order to avoid any delay doublecheck before to commence the moving or before to sign the contract the availability of the completion tools on board, finalize right contract for completion activity (services) --D C 5 5 L L
3) Performance 4)
6)
---
Completion
7) Availability of the specific equipment rarely used by the oil companies: manufacturing line set for standard equipments Time to engineering: it takes more time because it is uncommon, personnel not skilled and new design Delivery & manufacturing: special items, like TH for dual string, are required and they have to be manufactured ad hoc Test and qualification (no common): procedure of testing and qualification are not defined by ISO and it could be written and agreed Orizontal vs vertical X-Tree ---> it is suggested to use horizontal XT where it is necessary to re-entry instead in shallow water it is possible to go with vertical XT. where few hydraulic lines and electrical lines are requested it is suggested to avoid vertical XT
plan the activity with right time in order to avoid any delay or consider the activity without Rig window availability but always on the market possibility to choose all standard equipments on the market and modify the completion goals based on the market proposal --action by company to control and check procedure of test
8)
B B B
3 4 2
M L M
B B B
5 4 4
L L L
9) 10) 11)
Evaluation prons and cons choose a horizontal vs vertical X-Tree fitting with dual subsea completion
33
Risk Analysis
N
Original Risk
Residual Risk
RL
Mitigations
RL
Environment
Weather and sea conditions 12) Strong heave ---> need of motion compensator to counter the movement
squall not considered, wave abnormal, strong wind more than 45 kn; possibility of investigation on environment conditions historycally
Rig
Availability 13) Truster functioning (DP) ---> it keeps the rig in the right position B 2 M --B 2 M
Performance
14) Motion compensator ---> if it does not work, it can append that the rig must stop the operations
---
Completion
15) Staff: generally the staff does not have the skills in this area, so special training and team building is requested 16) Space on deck rig number of reels: possibility to have few numers of reels 17) Running TH with landing string: dedicated landing string and umbilical for this operation 18) Shearability dual string completion in BOP: impossibility to shear two strings inside of BOP C C 2 4 H M organize few meeting between contractor and company in order to standardize the procedure avoid to run control lines more than SCSSV inside of downhole completion package define with landing string supplier and subsea vendor the best design and optimize with market availability. Optimize the plan in order to reduce delivery verify with RIG contractor possibility and new design C C 4 5 M L
C C
1 2 1 2 4 5
H H H H M L
C C C C C C
3 3 2 3 4 5
M M H M M L
agreed all personnel on procedures, operations meeting before to begin, perform during the day, to have all SPV on the rig floor
as point above analyze with subsea vendor best procedures and analyze methodology -----
20) Orientation TH: it is the most difficult operation and it needs to be done with the motion compensator working 21) X-Tree installation: verify the procedures with contractors 22) Retrieving Wire Line Plugs/clean up/Well Test 23) Cap/protective frame installation
C C C C
34
Risk Analysis
N
Original Risk
Residual Risk
Mitigations
P I RL P I RL
Environment
Weather and sea conditions 1) Global Riser Analysis ---> simulation of RIH and installation of Landing String and Tbg string: poor data and uncertainties on the RIG, for the availability and for the RIG choice B 2 M this could affect the real functioning system for the landing string and for drilling riser, so simulation could be aborted and not considered during the operations B 3 M
Rig
Availability 2) Market conditions: availability of the rig and costs: depend by the area of working, in case of mediterranean sea floating RIG are very poor, other areas permits to have RIG availability with different daily rate Mobilization on time: time to MOB/DEMOB and the travel D 4 M plan activity where it is possible with the right completion schematic and based also on RIG availability on the markey plan the activity with right time in order to avoid any delay D 5 L
3)
Performance
4)
doublecheck before to commence the moving or before to sign the contract the availability of the completion tools on board, finalize right contract for completion activity (services)
-----
5) 6)
B B
4 4
L L
B B
4 4
L L
Completion
7) 8) 9) Availability on the market B Time to engineering Common test and qualification B B 4 5 4 L L L ----Evaluation prons and cons choose a horizontal vs vertical X-Tree fitting with dual subsea completion Take standard equipment on the market B B B 5 5 4 L L L
10) Horizontal vs vertical X-Tree ---> it is suggested to use horizontal XT where it is necessary to re-entry instead in shallow water it is possible to go with vertical XT. where few hydraulic lines and electrical lines are requested it is suggested to avoid vertical XT
35
Risk Analysis
N
Original Risk
Residual Risk
Mitigations
P I RL P I RL
Environment
Weather and sea conditions 11) Strong heave ---> need of motion compensator to counter the movement
C 3 M
squall not considered, wave abnormal, strong wind more than 45 kn; possibility of investigation on environment conditions historycally
Rig
Availability 12) Truster functioning (DP) ---> it keeps the rig in the right position B 2 M --B 2 M
Performance
13)
Motion compensator ---> if it does not work, it can append that the rig must stop the operations
---
Completion
14)
15)
B C
4 4
L M
--avoid to run control lines more than SCSSV inside of downhole completion package
B C
4 5
L L
16)
define with landing string supplier and subsea vendor the best design and optimize with market availability. Optimize the plan in order to reduce delivery verify Rig BOP bullettin (shear sub)
agreed all personnel on procedures, operations meeting before to begin, perform during the day, to have all SPV on the rig floor analyze with subsea vendor best procedures and analyze methodology -----
17)
18) 19) 20) 21)
C C D C C
4 3 4 4 5
M M M M L
C C D C C
5 4 5 4 5
L M L M L
36
Risk Analysis
The following matrix shows the differences between the risk associated to the single string and the dual string completion
Installation operations
37
Risk Analysis
The following matrix shows the risk reduction due to the mitigating actions taken
38
Summary
1
Project Scope
Risk Analysis
Conclusions
39
Conclusions
The following conclusions could be carried out:
A pre-enquiry with all major subsea vendors shows a poor case history of dual subsea completion with SSXT dual bore Actual market does not propose standard equipments for dual subsea completion and SSXT with dual bore. This condition affects the choice of subsea dual completion development
Risk analysis conducted on previous experience of ENI, shows major criticalities during operations compared with a single completion
Vertical XT is preferred to horizontal type to couple to dual subsea completion, but with all constrains of subsea applications
Acknowledgements
I would thank Eni E&P Division Management for permission to present this work and related results
and COMP colleagues for the technical support and needed assistance.
41