Status of Hydro Electric Projects under Execution

Sl. No Name of Project Executing Agency Date ofCEA clearance / Approval Capacity (MW) Broad Features Cost (original/latest) State Region Sector Status Commng. Schedule (original/ Now Ant. Broad Present Status As on 31.12.2009 Remarks

A. Projects as per 11th Plan Programme


Central Sector
1 Parbati-II NHPC 12.10.1999/11.09.2002 4x200 = 800 MW Broad Features : Dam 85m High, concrete gravity HRT- 6m x 31.52km S.Shaft-17m x 130m P.Shaft-2 x 3.5m x2133m P.House- Surface Turbine- Pelton Switchyard- 400 kV Cost: Original: 3919.59 Latest: 3954.00 H.P. NR CS Execution 2009-10 12th Plan Civil & HM works: awarded to M/s Patel SEW JV (Dam & part HRT) on 11.09.2002, M/s Himachal JV (HRT) on 11.09.2002, M/s Gammon (I) Ltd. (Power House, Pr. Shaft, Surge Shaft & part HRT) and M/s BJ_Techno-HAS(JV) (Jiwah Nallah) on 11.09.2002. Dam- Excavation completed. 132005 cum Dam & Inlet structure concreting out of 195977 cum completed. Head Race Tunnel- 26141 m excavation out of 31525m completed Total Overt lining: 10892 m excavation out of 31525m completed Feeder Tunnels (Jiwa Nalah): 3263 m exc.out of 4560m done. (Manihar-Pancha) 1802 m excavation completed out of 2252m. (Jigrai-Feeder) 632 m excavation completed out of 813m. Pressure Shafts- Inclined pressure shaft (left) Ferrule erection 406 m out of 1546m completed. Power House -Excavation completed and 8295 cum sub structure and super structure conc. completed out of 60000 cum. progress hampered due to PH back slope failure on 20/21st Feb., 2007. E&M works: awarded to M/s BHEL Ltd on 24.12.2002. Civil Works: awarded to M/s HCC Ltd. on 21.09.2005. Diversion Tunnel: Works completed & river diverted on 5.3.07. Dam Area: River bed excavation: 62414 cum completed out of 71000 cum. Dam concreting : 96396 cum completed out of 152346 cum. Head Race Tunnel- Excavation completed and 6552 m overt concreting completed out of 15995 m. Surge Shaft: 86 m excavation completed out of 97 m. Vertical Pressure Shaft: Excavation completed. Power House- Excavation completed. Tail Race Tunnel: Excavation almost completed. E&M works: awarded to M/s Alstom on 23.01.2007. HM works: awarded to M/s Om Metals SPML (JV) on 26.07.07. Civil works: Awarded to M/s Patel L&T Consortium & M/s Jager Gammon JV respectively on 15.12.2005. Diversion tunnel: River diverted on 14.03.07. Rockfill DamLeft bank excavation: Completed. Right bank excavation: Completed Rockfilling upto 1300 m: Completed. Rockfilling above 1300 m: 177900 cum completed out of 200000cum. Intake Structure: 6300 cum conc. completed out of 240000 cum. Head Race Tunnel: 7261 m excavation out of 7869m completed. Surge Shaft- Slashing completed. Power House: Benching completed. Tail Race Tunnel- TRT (Heading) excavation (U/S) completed and D/S 933 m out of 1094m completed. E&M works: awarded to M/s BHEL Ltd on 29.12.2006. EOT crane installed in service bay. HM works: awarded to M/s Om Metals SPML (JV) on 26.07.07. D&E works in progress. Gravity Dam: Excavation in Dam area completed. Excavation in Spillway area 107.41 lac cum out of 125 lac cum has been completed. Coffer Dam Filling: 11.35 lac cum filling completed out of 12 lac cum. -Slow progress of excavation of HRT due to poor geological strata especially in Face-4. For treatment of strata ahead of face-4 of HRT, work has been awarded to M/s Jager-Bau. Treatment of fault zone ahead of TBM face & modification of TBM has been taken up in consultation with M/s Jager Bau - Rock busting phenomena in Face-III in HRT. - Ban on use of aggregate by Hble High Court of H.P. -Slide in Power House area in April, 04 June, 06, & Feb, 07. - Labor agitation and stoppage of works for 3-4 months in June, 2006 - Washing away of coffer dam in July, 2007.

Chamera-III NHPC 10.10.2003/01.09.2005 3x77= 231 MW Broad Features : Dam 68m High, concrete gravity HRT- 6.5m x 15.9km S.Shaft-24m x 110m P.House-Uunderground Turbine- V.Francis Switchyard- 220 kV Cost: Original: 1405.63 Latest: 1584.00 Parbati-III NHPC 12.11.2003/09.11.2005 4x130 = 520 MW Broad Features : Dam 43m High, Rockfill HRT- 7.25m x 7.98km S.Shaft-20m x 114m P.Shaft-2 x 4.5m x345m P.House- Underground Turbine- V.Francis Switchyard- 400 kV Cost: Original: 2304.56 Latest: 2217.00

H.P. NR CS Execution 2010-11 2010-11

H.P. NR CS Execution 2010-11 2010-11

-Construction of Sainj Bypass road. -Poor geology in HRT - Delay in award of E&M works due to decision on participation of Chinese companies.

Kol Dam NTPC 30.6.2002/Oct.2002 4x200 = 800 MW Broad Features :

H.P. NR CS Execution

- Clay/earth filling of main dam. - Grouting of dam galleries. - Concreting of spillway. - Procurement of steel/conc.

Sl. No

Name of Project Executing Agency Date ofCEA clearance / Approval Capacity (MW) Broad Features Cost (original/latest) Dam 163m High, Rock & Gravell fill Penstock Tunnel: 4nos. 6.45m dia, 1600m long P.House- Surface Turbine- V. Francis Cost: Original: 4527.15 Latest: 4527.15

State Region Sector Status Commng. Schedule (original/ Now Ant. 2008-10 2011-12

Broad Present Status

Remarks

Ram Pur (SJVNL) SJVNL 16.12.2005/25.01.07 6x68.67= 412 Broad Features: HRT-10.5m x 15.08Km S.Shaft- 38m x 149m P.House- Surface Turbine- Francis Switchyard 400 kV Cost: Original: 2047.03 Latest: 2047.03 Uri-II NHPC 11.2.2004/1.9.2005 4x60 = 240 MW Broad Features : Dam 52m High, concrete gravity HRT- 8.4m x 4.27km S.Shaft-25m x 78m P.House- under.ground Turbine- V. Francis Switchyard 400 kV Cost: Original: 1724.79 Latest: 1725.00

H.P. NR CS Execution 2011-12 12th Plan

Main Dam: 60.61 lac cum filling completed out of 110 lac cum. Clay filling 10.61 lac cum out of 21 lac cum completed. Other materials filling 50.00 lac cum out of 89 lac cum completed. Spillway concreting: 1.69 lac cum concreting completed out of 4.16 lac cum. Power House-: 1.21 lac cum primary conc. out of 1.20 lac cum and 18000 cum secondary conc. Out of 26500 cum have been completed. Unit-1: Boxed up. Erection of draft tube for all units completed. Unit-2: Runner lowered. Stator assembly completed. Turbine erection in progress. Unit-3: Stator & rotor assembly in progress. Unit-4: Spiral casing welding completed. Penstock : Fabrication and erection of penstock liners completed. CCEA clearance obtained on 25.01.2007. Civil works awarded to Patel Gammons JV on 01.02.2007. LOI for E&M works issued to BHEL on 16.09.08 8.25 km out of 15.144 km HRT excavation has been completed. River cut & cover- River has been diverted to the original course. Main Surge Shaft (149 m): Pilot Hole excavation completed on 23.07.2008. Widening has been completed upto 92 m depth. Surface excavation for Pressure Shaft, valve house and Power house upto EL 847 m (18,04,000 cum): Balance excavation is 5000 cum. Service Bay # 1: Structure upto roof truss level completed. Fabrication of roof truss completed.

of spillway.

Slow progress of HRT due to poor geology.

Service Bay # 2: Erection of the crane beam upto EL 895 m completed. Fabrication of truss is in progress.
J&K NR CS Execution 2009-10 2010-11 Civil Works: awarded to M/s HCC Ltd., on 21.09.2005, The work has earlier been severely hampered due to devastation by earthquake on 08.10.2005. Diversion tunnel: River diverted in January, 2007. Dam- Excavation of right and left bank abutments and river bed excavation completed. 84562 cum concreting out of 95300 cum completed above RBL. Open Channel & Desilting Chamber: 22943 cum concreting out of 48994 cum completed. Head Race Tunnel: Heading excavation: Completed. Benching excavation: 4180 m out of 4233 m completed. Overt lining: from face-I, II & III is in progress. 3550 m completed out of 4233 m. Power House: Excavation completed and 10305 cum concreting out of 25000 cum completed. Surge Shaft excavation: 66 m out of 78 m completed. TRT Excavation: 3565 m heading excavation completed out of 3614 m and 3159 m benching excavation completed out of 3614 m. E&M works: Design & Engineering as well as fabrication works is in progress. Erection of DT liner in Unit-1, 2 & 3 completed. Erection of Spiral casing and Pit liner in Unit-1 has been completed. HM works: Work on erection of ferrule in Unit-2 is in progress. Ferrule erection in Unit-1 from SC to MIV has been completed. 1st stage & 2nd stage embedded parts is in progress. Civil works: awarded to M/s GIL-Srinivasa JV (Dam, HRT and Power House) on 08.09.2003 and M/s Patel Engg. (Tail Race and other works) on 08.09.2003. Dam- All works completed. De-silting Chambers: Completed. Head Race Tunnel- Excavation (10084 m) completed. HRT Lining: 10068.5 m lining completed out of 10084 m. Surface Power House- 36573 cum concreting including - Earthquake on 08.10.2005 - Flash flood in March, 2007 and washing away of coffer dams. -Massive slide on the right side of Dam in January, 08. -Widening of NH 1A by BRO. - Collapse of bridge being constructed in river Jhelum in Nov, 2008.

Sewa - II NHPC 18.10.2002/09.09.2003 3x40 = 120 MW Broad Features : Dam 53m High, concrete gravity HRT- 3.3m x 10.02km

J&K NR CS Execution 2007-08 2009-10 U#1: 01/10 U#2: 02/10

-Problem of labour union agitation. -Lack of resources with the contractor.

Sl. No

Name of Project Executing Agency Date ofCEA clearance / Approval Capacity (MW) Broad Features Cost (original/latest) P. House- Surface Turbine- Pelton Switchyard 132 kV Cost: Original: 665.46 Latest: 897.00 Chutak NHPC 23.04.2004/24.08.2006 4x11 = 44 MW Broad Features: Barrage- 5 bays, 47.5 long HRT- 5.9m x 4.370m S. Shaft- 19m x 59m P Shaft-3.25m x 37m (2 no) P.House- Underground Turbine- V. Francis Switchyard- 33 kV Cost: Original: 621.26 Latest: 802.00 Nimoo Bazgo NHPC 16,03.2006/24.08.2006 3x15 = 45 MW Broad Features: Dam 57.5m High, concrete gravity Spillway- 5 x 65m Penstock- 3 x 63mx3.3m P.House- Surface Turbine- V. Francis Switchyard- 33 kV Cost: Original: 611.01 Latest: 796.00 Koteshwar THDC 10.04.2000/ 4x100=400 Broad Features: Dam 97.5m High, concrete gravity P.House- Surface Turbine- V. Francis Cost: Original: 1301.56 Latest: 1301.56 (Under Revision)

State Region Sector Status Commng. Schedule (original/ Now Ant. U#3: 03/10

Broad Present Status

Remarks

J&K NR CS Execution 2010-11 2011-12

switchyard completed out of 36750cum. Unit #1 #2 & #3 Boxed up. E&M works: awarded to M/s BHEL on 23.06.2004. HM works: awarded to M/s Om Metals & Minerals Ltd. on 24.11.2004. Erection of all gates except SFT & surge shaft gates completed. Civil works: awarded to M/s HCC Ltd. on 23.09.2006. River diverted on 22.11.2007. Barrage: Excavation completed. Concreting upto crest level completed. HRT: Excavation and overt lining completed. Power House: Excavation completed and 1791 cum concreting completed out of 12000 cum. Pressure Shaft: Vertical excavation of PS-1 & PS-2completed. E&M works: awarded to M/s BHEL on 16.08.2007. Design & Engg. is in progress. EOT crane reached at site. HM works: Awarded to M/s PES Engineers Pvt. Ltd. on 28.07.2008.

-Extreme cold climate. - Delay in award of E&M works due to poor participation and re-tendering. - HM works package award delayed due to abnormal high price bid.

J&K NR CS Execution 2010-11 2011-12

Civil works: awarded to M/s HCC Ltd. on 23.09.2006. River diverted on 22.11.2007. Dam: Excavation: Completed. Concreting upto crest level: Completed and Power Dam concreting 31623 cum completed out of 45000 cum. Cellular Wall: Concreting completed. Power House: Excavation completed. 4574 cum concreting completed out of 30500 cum. E&M works: Awarded to M/s BHEL on 12.06.2007. Design & Engg. is in progress. Erection of EOT crane started. HM works: Awarded to M/s PES Engineers Pvt. Ltd. on 28.07.2008.

-Extreme cold climate. - Delay in award of E&M works due to poor participation and re-tendering. - HM works package award delayed due to abnormal high price bid.

10

Uttaranch al NR CS Execution 2005-06 2010-11

11

Loharinagpala NTPC 11.08.2004/June, 2006 4x150 = 600 MW Broad Features :

Uttaranch al NR CS Execution

Civil Works: Dam- Excavation completed & 464.47 Th. Cum concreting out of total quantity of 534 Th. Cum completed. Power Intake: Excavation completed. 69.56 Th. Cum concreting out of total quantity of 75 Th. Cum completed. Stilling Basin: Excavation completed. 103.59 Th. Cum concreting out of total quantity of 120Th. Cum completed. Power House: Excavation completed. Concreting: 128.31 Th. cum out of 185 Th. cum completed. Tail Race Channel- Total excavation 825 Th cum, completed 775 Th cum. Balance to be done from Jan, 10 to June, 10. E&M Works: Erection of E&M equipment are being done with Mobile Tower crane. EOT Crane: EOT crane commissioned upto Unit-1 area. Unit Erection: U-1: Erection of spiral casing completed. U-2: Erection of spiral casing is in progress. U-3: Erection of spiral casing completed. U-4: Erection of Stay ring is in progress. Switchyard: Erection of tower completed. Erection of equipment is in progress. H&M works: The fabrication of penstock steel liners completed. Erection of penstocks is nearing completion. Head Race Tunnel works awarded in July, 2006 to M/s Patel Engg. Barrage and Desilting arrangement package awarded in July, 2006 to M/s HCC, Mumbai. Power House and Penstock works awarded in Sept.,06 to M/s Patel Engg. Hydro-mechanical package awarded in Aug., 07 to M/s Texmaco Ltd. E&M works

- Delay in Diversion tunnel works. - Initial R&R problem affected progress of works. - Slow progress by Contractor. - Due to poor geology, slope failure above Power House & Intake Area affected progress. - Breakdown of Rotomec system affected progress of works. As per latest commissioning i.e. December, 2011, works are progressing more or less as per schedule.

- Delay in forest clearance for approach road to Helgu adit. - Slow progress due to slide zone in approach road area to Gunagu adit.

Sl. No

Name of Project Executing Agency Date ofCEA clearance / Approval Capacity (MW) Broad Features Cost (original/latest) Barrage4 bays of 15m HRT- 6m x 13.85km P.Shaft-2x 4m x 500m P.House- underground Turbine- V.Pelton Cost: Original: 2895.104 Latest: 2895.104

State Region Sector Status Commng. Schedule (original/ Now Ant. 2011-12 12th Plan

Broad Present Status

Remarks

12

Tapovan Vishnugad NTPC 11.08.2004/Nov, 2006 4x130 = 520 MW Broad Features : Barrage5 bays of 12m HRT- 5.4m x 11.97km P.House- underground Turbine- V.Pelton Cost: Original: 2810.84 Latest: 2978.48

Uttaranch al NR CS Execution 2011-12 12th Plan

13

Teesta Low Dam-III NHPC 25.06.2002/30.10.2003 4x33 = 132 MW Broad Features : Barrage 140m Height Penstock-4x 7m x 50m P.House- Surface Turbine- Kaplan Swutchyard 220 kV Cost: Original: 768.92 Latest: 1279.40

W.B. ER CS Execution. 2006-07 2010-11

14

Teesta Low Dam-IV NHPC 23.12.2003/30.09.2005 4x40 = 160 MW Broad Features : Dam 45m High, concrete gravity Penstock-4x7m x45m P.House- Surface Turbine- Kaplan Swutchyard 220 kV Cost: Original: 1061.38

W.B.. ER CS Execution 2009-10 2011-12

awarded to M/s Voith Siemens in January, 2008. Work of Barrage & Desilting chamber under progress, River diverted on 14.12.2008 and 2.08 lac cum out of 2.40 lac cum excavation of barrage completed. Excavation of adit, main access tunnel in progress. Excavation of adit to TRT completed. Gunagu adit work 262 m completed. MAT works upto 327 m completed. Work in intermediate adit to pressure shaft completed. Excavation of switchyard 66602 cum completed. 2084 m HRT completed. Surge shaft excavation 30370 cum completed. Work held up due to agitation by environmentalists. Head Race Tunnel work awarded in Nov., 2006. Barrage & Desilting Chamber package awarded in January, 2007. P.H. & penstock package awarded in May, 2007. E&M works awarded to M/s BHEL in January, 2008. 400 KV GIS awarded to M/s AREVA T&D Ltd. in July, 2008. HRT from Intake D/s excavation 1327.00 m out of 3012.30m, U/S excavation 190 m out of 241.4 m and HRT by TBM 1733.00 m out of 8618.6 m completed. Excavation of Desilting Chamber under progress and 16.15 lakh m3 out of 18.50 lakh m3 completed. Excavation of main access tunnel and Ventilation Tunnel completed. In TRT 25000 cum out of 45000 cum open exc. & 7.2 m out of 730 m have been completed. Adit to surge shaft bottom completed. Excavation in switchyard is completed. Surge shaft excavation: Surge shaft widening 13.50 m out of 144.3 m completed. Civil works: Awarded to M/s Patel Engg. Ltd. on 28.10.2003. Dam Cellular wall concreting: 63333 cum concreting completed out of 67315 cum. Barrage- Barrage Blocks III to VII: Excavation & concreting Completed. Intake Structure - Concreting completed. Penstock Excavation completed and erection is in progress. Power House- Excavation completed (307067 cum). 91071 cum conc. completed out of 96957 cum. Tail Race channel: 817996cum excavation out of 835000 cum completed. E&M work: Supply of major components almost completed at site. Draft tube erection for all Units completed and earthmat work is in progress. EOT crane erection in all units completed. Scroll case in all units completed. Installation of testing device & hydrotest of U#1,2 & 3 completed. Erection of auxiallaries in all units under progress. Assembling of rotor in U#1 completed. Installation of Turbine guide apparatus, Runner Shaft, TGBT Shaft seat U#1&2 is under progress. HM work: Design/Drawings and Fabrication of various Components is in progress. Erection of Penstocks is completed. Erection of radial gate in bay IV 55% completed. Erection of 2nd stage EP of intake service gate 1&2 completed. 65% of Erection of Intake service gate 1&2 and 21% Erection of Intake stoplog gate 1&2 completed. ET&C of spillway stoplog Bay S-6 & S-7 under progress and 66% completed. Civil works: awarded to M/s HCC on 19.01.2006. 1 stage river diversion achieved on 30.01.2007. Excavation of Dam Spillway: 106087 cum completed out of 922047 cum. Concreting in spillway glacis and piers: 99806cum completed out of 135754 cum. Cellular wall: Excavation & concreting completed. Power House: 70280cum concreting completed out of 130281 cum. Tail Race Channel: 603617 cum excavation completed out of 636325 cum. E&M works: awarded to M/s BHEL on 09.05.07. Design/Engg. is in progress.
st

- Work suspended since 20.02.2009 due to agitation by environmentalist Prof. G.D. Aggarwal.

- Delay in HRT work due to late procurement/ deployment of TBM by civil contractor about 20 months. - Slow progress of barrage & desilting chamber. - Surge shaft work hindered due to poor geology.

-Delay in forest clearance -Slope failure in Power House and Intake area. - Frequent interruption of works by local people and stoppage of works due to GJM agitation. - Flash floods in the year 2007 & May, 2009.

-Delay in forest clearance - Frequent interruption of works by local people and stoppage of works due to GJM agitation. - Flash floods in the year 2007& May, 2009.

Sl. No

Name of Project Executing Agency Date ofCEA clearance / Approval Capacity (MW) Broad Features Cost (original/latest) Latest: 1061.00

State Region Sector Status Commng. Schedule (original/ Now Ant.

Broad Present Status

Remarks

15

Subansiri Lower NHPC 07.06.2001/09.09.03 8x250= 2000 MW Broad Features : Dam 116m High, concrete gravity HRT- 8 x 9.5m x 1145m P.Shaft-8x 9.7m x2153m P.House- Surface Turbine- Francis Switchyard 400 kV Cost: Original: 6285.33 Latest: 7452.00

Ar.P/Assa m NER CS Execution 2010-11 12th Plan

16

Kameng NEEPCO 02 12 2004 /4x150 = 600 MW Broad Features: Dam :Bichom-75m High, 247.3m long. Tenga 25.0 High, 103m long. HRT- 6.7m dia, 14.477km. High Pressure Tunnel (HPT)Total length 3.64 km Surge Shaft: 25m dia, 70m H Penstock- 2x 4m P.House- semi-U/G Turbine- Francis Cost: Original: 2496.90 Latest: 2496.90

Ar. Pradesh NER CS Execution 2009-10 12th Plan

HM works: awarded to M/s Om Metals on 10.05.2007. Design/Engg. is in progress. Civil works: awarded to M/s BGS-SGS-Soma JV (Dam/Barrage and HRT) on 19.12.2003 and M/s L&T Ltd. (Power House & Tail Race works) on 19.12.2003. Diversion tunnel: River diverted on 25.12.2007. Inlet Structure- Excavation completed. Dam Foundation excavation: 154011 cum completed out of 173000 cum. Dam concreting upto EL 108m: 67587 cum completed out of 1350000 cum. Reconstruction of U/S and D/S coffer dam and dykes: Completed. Intake Structure: 34441 cum concreting completed out of 260000 cum. Head Race Tunnel (I-VI & VIII): 3753 m excavation completed out of 7124 m. Surge Tunnels (8 nos.): Surge Chamber has been modified to 8 nos. surge tunnel. Pressure ShaftHorizontal Pressure Shaft: 1053 RM excavation out of 1429 RM completed. Surface Power House: Excavation: Completed. Concreting: 45465 cum out of 360000 cum completed. E&M Works: Awarded to M/s Alstom Ltd on 11.02.2005. HM Package: Awarded to M/s Texmaco on 19.06.2006. Bichom Dam: Excavation (including intake) (R) 359960/495000 cum and Concreting 3302/ 328341 cum completed.

- Signing of MoU with State Governments. - Washing away of coffer dam in the year 2008. - Slope failure of power house in January, 2008. Change of surge shaft to surge tunnels. Works awarded to M/s L&T Ltd. - Law & Order problem.

Tenga Dam: Excavation 67870/102000 cum and Concreting 650/63000 cum completed. HRT: Excavation: 6925.66/14527.50m completed. FaceII, III, VI & VII critical, work slow due to bad Geology. Surge Shaft: Open excavation and boring completed, Lining: 28.2/70m completed. HPT: Boring completed & excavation works in progress. Power House & TRT: Excavation 997000/1050000 cum completed. Concreting 6991.61/30600 cum completed. HM Works & Penstock: Design and fabrication of penstock steel liner and HM works are in progress. Electro-mechanical works: BHEL mobilized at site & D/T liner received at site.

- Change in Crest level from EL 755m to EL 735m, length of dam increased from 247.3m to 264.15m. Also, Diversion arrangement modified. - Subsequently delay in construction drawings from consultant i.e. SMEC. - Slow progress in Dam & HRT due to various reasons ie. Bad geology, heavy seepage, in adequate machinery at site etc. - Work suffered due to flash flood in Oct. 08.

State Sector
17 Uhl-III, Beas Valley Power Corporation Ltd. (HPSEB) 19.09.02 / (TEC -2x50 MW) 3x33.3 =100 MW (Revised vide HPSEB letter dt. 19.01.07. Broad Features: HRT-4.15m x 8.47 km S.Shaft- 13m x 57m Penstock- 3.4m x 1860m P.House- Surface Turbine- V. Francis Cost: H.P. NR SS Execution 2006-07 12th Plan Neri Khad works (Trench weir, Intake Structures, Water conductor system upto Khuddar Reservoir): 43089 cum excavation and 985.5 cum concreting completed by previous contractor. Work rescinded on 21.05.08. Fresh award given to M/s CCPL on 25.10.2008. New contractor has started the work. 25173 cum out of 52161 cum excavation and 6430 cum out of 16142 cum concreting completed. Rana Khad Works (Trench weir, Intake Structures, Water conductor system upto Khuddar Reservoir): 69690 cum out of 91848 cum excavation and 12096 cum out of 17891 cum concreting completed. Aqueduct over Rand Khad: 18313 cum out of 18300 cum excavation and 2237 cum out of 2900 cum concreting completed. Out of 651 MT steel, 310.5MT has been erected. Storage Reservoir: 39440 cum out of 60145 cum excavation and Slow progress of civil works, particularly HRT (which is critical) due to poor geology, difficult area, inadequate mobilization by contractor, etc. Contract for Package-I & Package-V cancelled and fresh awards placed.

Sl. No

Name of Project Executing Agency Date ofCEA clearance / Approval Capacity (MW) Broad Features Cost (original/latest) Original: 431.56 Latest: 431.56

State Region Sector Status Commng. Schedule (original/ Now Ant.

Broad Present Status

Remarks

18

19

20

Swara Kuddu H.P. Power Corpn. Ltd. HPSEB Clearance: 10.11.2004 3x37= 111 MW Broad Features: Diversion Structure: 10.45m high Piano Key Weir. HRT- D-Shaped, 5m dia, 11.145Km long. Power House- Under ground Turbine- 500 rpm vertical francis. Switchyard: 220 Kv. Cost: Original: 558.53 (03/03) Latest: 721.71 (02/08) Priyadarshini Jurala APGENCO 24 07 02 6x39= 234 Broad Features : Barrage 27.8m Height P.House- Surface Turbine- Bulb Cost: Original: 547 Latest: 547 Nagarujana Sagar TR APGENCO 17 01 05 2x25=50 Broad Features: Dam 29.5m High Spillway- 21nos gate Penstock- 2x 5.35m P.House- Surface Turbine- V. Kaplan Cost: Original: 357.63 Latest: 464.70 Lower Jurala APGENCO, A.P. TEC in July 2007 6x40=240 (120 MW likely to slip) Broad Features: Intake: 18 vents (3 vents for each unit) 4.7m width, P.House- Surface,

H.P. NR SS Execution 2010-11 12th Plan

15407 cum out of 37596 cum concreting completed. HRT: 6856.5 m out of 9258.5 m excavation completed by previous contractor. Contract was cancelled due to slow progress. Fresh award given to M/s CCPL on 30.09.2008. 659m out of 2402 m excavation completed and balance is 1743m. Penstock: U/G excavation completed and open excavation (148524 cum out of 155000 cum) is in progress. 24099 cum out of 31622 cum concreting completed. Out of 3900 MT Steel Plates, 2575 MT has been erected. Power House and Tail Race: 26267 out of 31500 cum excavation completed and 3945 cum out of 10105 cum concreting completed. Award for E&M equipments placed on 15.02.2007 to BHEL. Package I (Diversion structure, intake and desilting chambers) Awarded to M/s Patel Engg. Ltd., Mumbai, on 25.08.2009. HRT works (PackageII) awarded in June, 07. 2603 m out of 11145 m excavation of HRT completed. Excavation of all the Adits completed. Package III (Power House Complex) awarded in February, 2009. Excavation of MAT, cable tunnel cum constt adit to PH and pilot hole to top of PH cavern has been completed. Excavation of 163.29 m adit to valve chamber & 102 m adit to bottom of Pressure shaft and 10925 cum surge shaft has been completed. Award of contract for E&M Package (Package-IV) has been signed on 27.2.2009 with JV of M/s VA Tech Hydro India Pvt Ltd & M/s VA Tech EMF Pvt Ltd with effective date as 13.3.2009. Stipulated period for completion is 38 months i.e. completion by May, 2012.

Slow progress of HRT due to poor geology. The stipulated period for completion of Package-III is 39 months after award of contract i.e. completion by June, 2012. The stipulated period for completion of Package-IV is 38 months after award of contract i.e. completion by April, 2012. As the excavation of major civil works are still in initial stages and award of Package-I is yet to be placed, the project is likely to slip to 12th Plan. - The unit is getting delayed due to single shift working by Chinese personnel. - Visa renewable problem of Chinese working personnel at site.

Power House - Power House concreting in progress. Unit #1- Commissioned on 28.03.2008. COD on 18.08.2008. Unit #2- Commissioned on 31.08.2008. COD on 11.09.2008. Unit #3- Commissioned on 27.06.2009. Unit #4 Erection of turbine completed. 2006-07 Unit 5 #6- Erection & generator is in progress. Erection of stay 2007-11 cone & match cover completed. Due to return of Chinese U# 4: 11/09 personnel from site as per direction of local Administration, the U# 5: 03/10 commissioning of Units may be delayed further. U#6: 07/10 A.P. SR SS Execution 2008-09 2010-11 Civil works awarded on 9.5.2005. E&M works awarded to M/s BHEL on 3.5.2006. Main Dam: Excavation at dam area is almost completed. Concreting is in progress. P.H. Civil works: Excavation completed in PH area. Column raising in service bay is in progress. Nose pier for both units erected. Fixing of draft tube pipe for Unit-I & II is completed. EOT crane is erected. Concreting is in progress. Tail Race: H&M works re-awarded to Gtv-PES Jt. venture on 11.5.2009. Due to unprecedented floods on 01.10.2009, all activities at site are stopped. The dewatering process/muck removal at site is underway.

A.P. SR SS Execution

- Construction of dam. - Delay in Award of HM works.

21

AP SR SS Execution 2011-12 2011-13

Works for construction of weirs was awarded to M/s Patel Engg. and the work commenced in November, 2008. Excavation works for approach channel, intake pool, power house pit, tail race pool and channel was awarded to M/s Ramakrishna Reddy, Hyderabad in November, 2007 and are under progress. About 81% excavation works completed. Works for construction of power house civil works including switchyard, gates etc was awarded on 04.07.2009. Due to unprecedented floods on 01.10.2009, excavation works were

- Three units are programmed for commissioning by March, 2012. - Due to delay in award of E&M works, erection of unit is the area of concern.

Sl. No

Name of Project Executing Agency Date ofCEA clearance / Approval Capacity (MW) Broad Features Cost (original/latest) Turbine- Bulb Design Head- 20m SWYD- 220 kV Cost: Original: 908.34 Latest: 908.34 Pulichintala APGENCO 120 MW (4x30 MW) 25.04.2007 Broad Features: Design Head: 24 M Power House: Surface Turbine : V. Kaplan Annual Energy: 220 MU Cost: Original: 380 Crs.(PL 0607) Latest: 380 Crs.(PL-0607) Kuttiyadi Addl. Extn KSEB 15.7.97 2x50 = 100 Broad Features: HRT- 3m x 666m S. Shaft- 5m x 75m Penstock- 2x 2.05mx2144m P.House- Surface Turbine- Pelton Swyd- 110 kV Cost: Original: 220.50 Latest: 168.28 Pallivasal KSEB 2x30= 60 MW Broad Features: HRT: 3.50m X 3396m Surge Shaft: 7.0m X 49m Pressure Shaft: 2.50m X 1019.20m Penstock: 2.00mX1161.20m Power House: Surface Turbine : Pelton S.Yard: 220kV Single bus Cost: Original: 242.95 + US$ 57M Bhawani Kattalai Barrage-II 11.6.99 2x15 = 30 Broad Features: Barrage 22 gates P.House- Surface Turbine- Bulb Cost: Original: 99.15 Latest: 400.59 Bhawani Kattalai

State Region Sector Status Commng. Schedule (original/ Now Ant.

Broad Present Status

Remarks

stopped. The works would be taken up after receding of floods. LOA for E&M works earlier placed on M/s CMEC, China is January, 2008 was cancelled and re-awarded to M/s Alsthom Project India Ltd. in May, 2008.

22

A.P. SR SS Execution 2010-11 2011-12

Dam is under construction by Irrigation Department, Govt. of A.P. The works for dam construction were awarded to M/s SCLCR18G JV. Progress/Total Qty: Concreting 32 lakh cum/68 lakh cum. The excavation of power house completed and tail race channel excavation is in progress. (81%) The E&M works have been awarded to M/s BHEL in May, 2007. Materials are being received progressively at site. Pier nose for all units erected. Fabrication of spiral casing segments for all units completed at site. Due to unprecedented flood on 02.10.2009, all project area has been inundated. Works will be taken up after receding of floods. Intake, HRT, Surge shaft civil works completed. Penstock (surface)Penstock track excavating is almost completed. Erection of steel liner is in progress. Concreting of 22/28 anchor blocks completed. About 1819 m penstock erection out of 2114 m completed. Unit Erection: Boxing up of both units is nearing completion. Transmission Line: Work for 14.5 Km multi-circuit line from Kakkayam to Patthiper started in November, 2008. For 25.23 km D/C line Patthiper to Vadkora, tree cutting in undisputed portion is in progress.

- Lack of co-ordination between APGENCO and Irrigation Deptt. - E&M works need to be expedited.

23

Kerala SR SS Execution 2006-07 2010-11

- Late forest clearances delayed penstock works. - Erection of penstock is critical.

24

Kerala SR SS Execution 2010-11 12th plan

Contract has been awarded for construction of the project on turnkey basis to consortium of M/s ESSAR DEC CPPL. Progress/Total Qty: Intake structure excavation 28398/33492 cum. HRT excavation 697/3396 m. Pressure Shaft excavation : 519/1062 m. Surface penstock excavation 50636/118400 cum. P.H. excavation : 48998/64408 cum.

- Works are getting affected due to poor maintenance of machineries by contractor. - Land acquisition problem for penstock. - Slow progress of civil works.

25

Tamil Nadu SR SS Execution

2006-07 2011-12

26

Tamil

Power House Works divided in three packages. (Barrage works, PH civil works, and E&M works). PH civil package and E&M works awarded in February, 2006. LOI issued for barrage civil works on 12.04.2007. The excavation of barrage and Power House completed. Concreting of barrage 85462 cum completed. Sub-structure concreting of P.H. 75982/81850 cum and concreting (unit-wise) 26980/37559 cum have been completed. In TRT, 2735 cum concreting out of 3950 cum has been completed. E&M Works: (i) Erection of Draft tube liner for both the units completed. (ii) Erection of stay ring for both the units completed. Power House Works divided in three packages. (Barrage works,

- Erection of unit is critical.

- Erection of unit is critical.

Sl. No

Name of Project Executing Agency Date ofCEA clearance / Approval Capacity (MW) Broad Features Cost (original/latest) Barrage-III 27.03.02 2x15 = 30 Broad Features: Barrage 22 gates P.House- Surface Turbine- Bulb Cost: Original: 99.75 Latest: 398.60

State Region Sector Status Commng. Schedule (original/ Now Ant. Nadu SR SS Execution 2006-07 2011-12

Broad Present Status

Remarks

27

Myntdu, MeSEB 20.09.99/ 2x42+1x42 = 126 Broad Features: Dam 63m High HRT- 3316.46mx3.4m dia Power House- Surface Turbine- V. Francis Cost: Original: 363.1 Latest: 671.29

Meghalaya NER SS Execution 2006-07 2010-11

28

New Umtru MeSEB, 2x20=40 Broad Features: Diversion Structur-Gated structure (FRL-130.1m, MDDL-123.3m) HRT- 5m dia, 750m long P.House- Deep Set SWYD- 132 kV Cost: 194.3 Cr. 194.3 Cr.

Meghalay a NER 2011-12 2011-12

PH civil works, and E&M works). PH civil package & barrage civil works awarded in Feb & Oct. 2006 respectively. E&M works awarded in November, 2006. Dam & Dykes/Barrage excavation & concreting of Phase-I (piers 1 to 5) completed, phase-II (piers 6 to 10) yet to be started and Phase-III (Piers 11 to 15) excavation completed and concreting 8717 cum out of 9840 cum completed. HRT open channel excavation 25870 cum out of 26670 cum and concreting 6715 cum out of 7500 cum completed. Sub-structure concreting of P.H. 79561/81850 cum and turbine pit concreting 19594/37850 cum completed. In TRT 2575 cum concrete lining out of 3950 cum completed. E&M Works: (i) Erection of Draft tube liner for both the units completed. (ii) Erection of stay ring for Unit # 1 is completed. Main Dam: Excavation completed and 326301 out of 332311 cum concreting completed. HRT & HPT: Completed. Surge Shaft: Works completed. Surface Penstock: Excavation completed. 19904 cum out of 27385 cum concreting completed. Power House: Excavation completed. 17226.437/18362 cum substructure and 2490.35/4050 cum super structure concreting completed. E&M: Works under advance stage. Erection of unit-I has been taken up. HM works: Erection of Radial gates is underway and 3nos out of 7 gates erected.. Tail Race: Excavation completed. 5756.820/6331 cum lining completed. Civil works awarded to M/s ITD Cementation (India) Ltd. in Dec. 2007. Work resumed 5th Dec. 2008. Order for HM works has been placed to M/s SEW Texmaco in January, 2009. E&M works awarded to VA Tech Hydro (ANDRITZ) in Feb. 2009. Surge shaft: Open excavation completed and balance boring work of surge shaft 6800 cum yet to be taken. Dam & Intake final drawings are under securitization & expected to be received in Dec. 2009.

Due to heavy rain & sudden flood occurred on 8th Oct.09, which had affected the progress of works.

Although, works have been started / awarded recently, considering the smaller unit size and comparably lesser civil works, the units can be commissioned in the 11th plan, with extra efforts by the project authorities.

Private
29 Allain Duhangan AD Hydro Power Ltd 20.08.02/Nov. 2006 (FC) 2x96=192 Broad Features: BarrageHRT- x 3.7 km x 4.6 km P.Shaft- 2.8m x 1750m P.House- underground Turbine- Pelton Cost: Original: 922.35 Latest: 922.35 Karcham Wangtoo Jaypee Karcham Hydro Power Ltd. 31.03.2003/30.3.2006 (FC) 4x250=1000 Broad Features : H.P. NR PS Execution 2007-08 2010-11 Financial closure : Achieved on 21.11.2005 HRT: Excavation of Allain HRT have been completed. Out of 4220 m of boring of Duhangan HRT, 2981 m has been completed. Conc. 2817 m /4099 m done. Tail Race Access Tunnel : Excavation and overt lining completed. Gates erected. Power House: Excavation and concreting completed. EOT crane is in operation. Transformer : All works completed. E&M: Both units boxed up. Switchyard: All major works completed. Transmission Lines: Erection, Tower erection 508/580, Stringing 66 km out of 175 km completed. Excavation and concreting in Allain barrage, desilting chambers and intermediate reservoir is completed. Financial closure achieved on 30.3.2006. Design, engineering, procurement & construction contract awarded to M/s JAL on 09.07.2003. LOI for E&M works issued on 30.10.2007 in favour of Voith-Siemens Adritz VA Tech Hydro Karcham Wangtoo Consortium. River diversion completed on 11.04.2007. Main Dam: 963959 cum out of 1081500 cum excavation and -Slow progress in Face-V & VI of Allain HRT due to poor geological condition. Transmission works are lagging behind the schedule.

30

H.P. NR PS Execution 2008-09 2011-12

Sl. No

Name of Project Executing Agency Date ofCEA clearance / Approval Capacity (MW) Broad Features Cost (original/latest) Dam 98m Height HRT- 10.48m x 17.2km P.Shaft-4x 4.7m x291m P.House- underground Turbine- Francis Cost: Original: 5909.59 Latest: 5909.59

State Region Sector Status Commng. Schedule (original/ Now Ant.

Broad Present Status

Remarks

31

32

33

Budhil Lanco Green Power Pvt Ltd 1.06.2005/ Jan, 06 (FC) 2x35=70 MW Broad Features: Dam-58m High HRT-4m x 6028m P.House- underground Turbine- V. Francis Cost: Original: 418.80 Latest: 418.80 Malana-II Everest Power Pvt. Ltd. 15.10.2004 by HP Govt./ 2x50=100 MW Broad Features: Dam 45.5m High HRT- 3m x 4.874 km S. Shaft- 6m x 90m P. Shaft- 2.5m x 666m P.House- underground Turbine- Pelton Cost: Original: 598.00 Latest: 598.00 Sorang Himachal Sorang Power corporation Ltd. June, 2006/ 2x50= 100 MW

H.P. NR PS Execution 2008-09 2010-11

411117 cum concreting out of 502800 cum completed. Intake: Excavation of intake tunnel completed. 318m overt and 150m invert lining out of 1558m of intake tunnel completed. HRT: Heading excavation completed and 12299 m benching & 6344 m overt lining out of 16925m HRT completed. Power House: Both the EOT cranes are in operation and unit erection is in progress. TRT: Heading excavation completed and 1196 m out of 1255 m benching has been done. Financial closure achieved in March, 2006. All works awarded and are under progress River diversion works completed. Dam : Excavation completed and concreting of 27447 cum out of 50000 cum also completed. HRT: Out of 6.27 km of boring, 5.794 km has been completed and 1016 m concreting has also been completed. Power House: Excavation completed. EOT crane is in operation. Stator & rotor formation is in progress. E&M Works: Works awarded to M/s Dongfong Electric Corporation Limited, China. 80% supply completed.

H.P. NR PS Execution 2008-09 2010-11

Financial closure on 03.08.2006. Dam: Excavation of dam completed and 68500/86000 cum concreting done. HRT: Out of 4.952 km of boring, 4.708 km has been completed and lining is in progress. Power House: All major civil works for both the units is complete. EOT crane is in operation. Pressure Shaft: Horizontal & top limb pressure shaft completed and 52.5/303m vertical Pressure Shaft bottom limb ferrule erection completed. E&M Works: Works awarded to M/s Abir Const. Private Ltd. on 18.10.2006. Supply of TG sets completed. Both the units are boxed up and dry test is in progress. Financial closure achieved in June, 2007. Civil & HM works awarded to NCC Maytas SSJV consortium in June, 2007. E &M works awarded to M/s Voith Siemens in June, 2007. All infrastructure works including bridge completed. Excavation of Power house is completed. Boring of main access tunnel, Adit to HRT and Adit to crown of PH cavern has been completed. 81% excavation of transformer cavern completed. 123 m boring of HRT has been completed Land Forest & Pvt. Land acquisition is in progress. - Order for civil works awarded to M/s NCC-GVKPL consortium on 11.06.07. - LOA for E&M works issued to M/s BHEL in April,2007. - HM works awarded to M/s Precision Infratech Limited. - Financial closure achieved on 3.8.2007. Progress/Total Quantity of various Activities: - Diversion tunnel and NH-54 Road realignment completed. - Construction of coffer dam near Power House completed. - Dam excavation on Right Flank upto EL550 m (100%) completed. Left Flank excavation EL 550 m (99%) and excavation below EL 550 m (100%) completed. - HRT excavation 96% completed. - Power Channel excavation 58% & concreting 13% completed. - Power House excavation completed. P.H. Concreting: (i) Unit # 1, 1st stage 100% completed. (ii) Unit # 2, 1st stage 75% completed.

Dam & HRT works critical due to poor geology. Delay in acquisition of land for Sub Station area. Delay in completion of Transmission line from Chhaur sub-station to Nalagarh which is common to Allain Duhangan HE project and also being constructed by ADHPL.

H.P. NR PS Execution 2012-13 2011-12

Difficult area, accessibility and availability of working period.

34

Shrinagar GVK Industries Ltd. 14/06/2000/ FC 4x82.5=330 Broad Features: Dam 66.5m High, concrete gravity HRT- 13m x 889m Penstock-4x 5.6m x 114m P.House- Surface Turbine- Francis Cost: Original: 1699.12 Latest: 2069.00

Uttarakha nd NR PS Execution 2005-06 2011-12

- Lease deed for forest land is yet to be executed. - Permission yet to be obtained for purchase of : i) Additional private land of 9.28 Ha through negotiations. ii) Additional Government land to an extent of 17.089 Ha on lease. - AHPCL is not in a position to take up the construction of Main Dam as raising of this structure would submerge the Dhari Devi Temple.

Sl. No

Name of Project Executing Agency Date ofCEA clearance / Approval Capacity (MW) Broad Features Cost (original/latest)

State Region Sector Status Commng. Schedule (original/ Now Ant.

Broad Present Status

Remarks

(iii) Unit #3, 1st stage 6.2% completed. (iv) Unit #4, 1st stage 16.3% completed. (v) Assembly bay concreting 95% completed. (vi) Forebay concreting 50% completed. 35 Maheshwar, SMHPCL 30 12 96/ 29.9.2006 (FC) 10x40= 400 Broad Features: Dam-535m High, concrete gravity P.Shaft-10x7.82m x 52m P.House- Surface Turbine- Kaplan Cost: Original: 1569.27 Latest: 2449.20 M. P. WR PS Execution 2001-02 2011-12 (a) Spillway: 100% excavation completed. 93.3% concreting completed. (4.55 lacs cum out of 4.88 lace cum) (b) Power Dam: Excavation completed for all blocks. Concreting is taken up in all 10 blocks and for blocks 44 to 42 completed. 99.3% concreting completed. (2.1 lac cum out of 2.12 lac cum). (c) Power House: Excavation work completed for all 10 units and concreting work is in progress. 76.2% concreting completed. (1.49 lac cum out of 1.95 lac cum) Unloading, storage bay & service bay & roof trusses works completed. Pier nose lines for all 10 units erected. E&M works: 2 nos. 115/30/10T EOT crane delivered, installed & commissioned. Unit Erection: Unit #10: Scroll case erected and concreted. Unit #9: Stay ring erection is being taken up. Unit #8: Stay ring erected. Unit #7: Stay ring pedestal casting in progress. Unit #6: Draft tube knee lines concreting in progress. Unit #4: Draft tube knee lines concreting in progress. Unit #3: Draft tube knee lines welding in progress. HM Works: Out of 27 nos. of radial gates, 15 gates erected. Financial closure achieved on 14.03.2007 Civil works: awarded to M/s SEW & PRASAD (JV) Hyderabad on 09.03.2006. Rongli Dam: All excavation works completed Overall concreting 34075/36000 cum completed. All dam concreting works are likely to be completed by Dec. 09. Rongli Intake 6836/7500 cum completed. Rangpo Dam Excavation about 81384/10,000 cum completed and concreting of 15171 cum completed. Intake excavation 4727/5400 cum completed. Surge Tank: Excavation 13573/15000 cum completed. HRT: 5962/7937cum excavation completed. Invert concreting 485m completed. Overt concreting 191.8 m completed. BF Valve: Excavation completed. Pressure Shaft: Excavation almost completed. Fabrication of steel liners completed (328m).Erection of steel liner 146/328 m completed.. H&M works: awarded to M/s PES Engineers Pvt. Ltd on 11.12.07. Erection works in various phases of completion. Power House: Excavation completed. Concreting work in progress. Erection of Unit 1 & 2 draft tube completed. EOT crane is in operation. Unit-1& 2 spiral casing placed. Switchyard 11/132 kV: Excavation of switchyard & side by side concreting of footing is in progress. Financial closure achieved on 14.08.2007. State clearance to the project accorded on 18th July 2005. TEC from CEA accorded on 12.05.2006. Environment and Forest clearance have been obtained. Private and Forest land acquisition has been completed. LOA for turnkey execution of the project placed on the EPC consortium led by M/s Navayuga Engineering Company, Hyderabad and AIPL on 18.04.2007 and contract agreement signed on 12.09.2007. Flushing Tunnel 91% of heading excavation completed. HRT 6.5/13.86 km excavation completed. Excavation of all the access tunnels to the Machine Hall, GIS hall & TRI completed. Cash flow problem and related issue of delievery of E&M equipment by BHEL.

36

Chujachen Gati Infrastructure Ltd, Secunderabad 30.11.2004 (State Govt.)/ 2x49.5= 99 MW Broad Features: Dam Rampo- 48.5m High Rongli- 41m High HRTRampo-3.3m x 2578m Rongli-3.5m x 2256m Common-5.2m x 3225m S. Shaft-12m x 104m P.House- Surface Turbine- V. Francis Cost: Original: 448.76 Latest: 651.50

Sikkim ER PS Execution 2009-10 2010-11

.Slow progress in some stretches of HRT. Flash flood on 16.04.2009 washing away Rangpo coffer dam. .

37

Teesta-III Teesta Urja Ltd. (TUL) 12.05.2006 6x200=1200MW Broad Features: Dam-Concrete with chute spillway 60m high. HRT- 7.5m dia, 13.325Km long. Press. Shaft- 3nos. 3.8m dia. Power House- Under

Sikkim ER PS Execution 2011-12 2011-13

As per contract , the commissioning of three units is in 2011-12 and other three units in 2012-13. Project authorities have intimated that all the six units would be commissioned during 11th plan (from August, 2011 to January, 2012.) Considering the present pace of civil works & mobilization done

10

Sl. No

Name of Project Executing Agency Date ofCEA clearance / Approval Capacity (MW) Broad Features Cost (original/latest) ground Turbine- Pelton Cost: Original: 5705.55 Crs. Latest: 5705.55 Crs.

State Region Sector Status Commng. Schedule (original/ Now Ant.

Broad Present Status

Remarks

TRT: 55% excavation completed. The electro-mechanical works have been awarded to consortium led by M/s VA tech Hydro and the contract has been signed on 18.10.2007. Diversion tunnel: Excavation of 937/957 m completed. HRT: Adits: Inlet Adit to Diversion Tunnel, Intermediate Adit to Diversion Tunnel, Zero Adit to Intake, Adit to flushing tunnel, Adit to desilting basin, Adit to Power House top, Adit 2,3,4 & 5 to HRT completed. 2731 cum/14019m excavation completed Pressure shaft: Inclined portion 91/417m and PS-2 38/417 m completed. Power House: MAT 387/572 m completed. TRT: 1030/1083 m excavation completed.

at site, it is possible to commission the units as per the revised schedule, indicated by the project authorities provided no major geological surprises / bottlenecks are encountered.

B. Projects likely to give benefits beyond 11th Plan


38 Central Kishanganga (NHPC), J&K 20.07.07 3x110 330 J&K NR CS Execution 2016-17 2016-17 Infrastructure works are under progress. Revised CCEA approval accorded in December, 2008. Turnkey execution of the project awarded to M/s Kishanganga Consortium with HCC ld. As lead partner, M/s Halcow group ltd., UK as partner and M/s SELI SJZA Italy, M/s BHEL, M/s DSD NOELL Gmbll Germany & M/s PES engineers Pvt. Ltd. As subcontractor on 22.01.2009. Construction of platform for TBM is in progress. Exploratory drilling at Dam, power house & pressure shaft are under progress. Project under construction. Civil works awarded.

39

Pare M/s NEEPCO 2x55 = 110 MW

Ar. P NER CS Execution 12th Plan

40

State Kashang-I H.P. Power Corpn. Ltd. 65 MW

H.P. NR SS Execution 12th Plan 12th Plan Kerala SR SS Execution

Civil & HM works awarded to M/s HCC Ltd. in February, 2009 and effective date for commencement of works is 09.04.2009. Bids for Package-II (E&M works for Stage-I, II & III) opened on 11.08.2009 and are being evaluated.

41

Thottiyar KSEB 40 MW

Construction works started.

12th Plan
42 Private Tidong-I M/s Nuziveedu Seeds 100 MW

12th Plan

43

Phata Byung

M/s Lanco 06.10.2008 2x38 MW = 76 MW Broad Features: Dam 26m high HRT- 3.2 m dia & 9.38 km length Pressure Shaft: 2.5m dia, 662.25 m length

H.P. NR PS Execution 12th Plan 12th Plan Uttarakhand NR PS Execution 12th Plan 12th Plan

Civil works awarded in November, 2008.

Project under construction Work awarded on 14.02.2008 as EPC contract to M/s Lanco Infratech Ltd. With a construction period of 36 months.

11

Sl. No

Name of Project Executing Agency Date ofCEA clearance / Approval Capacity (MW) Broad Features Cost (original/latest)

State Region Sector Status Commng. Schedule (original/ Now Ant. Sikkim ER PS Execution 2012-13 12th Plan

Broad Present Status

Remarks

Turbine Frances
44 Teesta-VI LANCO 27.12.2006 4x125= 500 MW Cost: Original: 3283.08 Latest : 3283.08 Broad Features: Barrage: 34.27m high HRT- 2nos,13.7km long Pressure shaft: 4nos. 5.4m dia. 130m av length, 13.325Km long. TRT: 4nos 250m av length, 8.5m dia. Power House- Under ground Turbine- Francis Rangit-IV Jal Power corp. Ltd. 06.07.2007 3x40= 120 MW Cost: Original: 726.17 Crs. Latest : 726.17 Crs. Broad Features: Dam: Concrte gravity 44m high .HRT :6.5km long 6.4m dia Power House : Surface Turbine: Francis HRT- 2nos,13.7km long Pressure shaft: 4nos. 5.4m dia. 130m av length, 13.325Km long. TRT: 4nos 250m av length, 8.5m dia. Power House- Under ground Turbine- Francis 46 Jorethang Loop M/s DANS Energy 96 MW (2x48 = 96 MW) Sikkim ER PS Execution 12th Plan 12th Plan Financial closure has been achieved in July, 2007. Infrastructure works such as roads and bridges are in progress. Land acquisition is in process. Excavation works of Adits (1+2+3+4+4A+HRT-2) 14865/2447447 completed. Surge Tank Excavation 42050/278183 completed. In power house complex Excavation of Main access Tunnel, ventilation Tunnel, Adit to Tranformer cavern, cable tunnel and Adit to BFV chamber completed. Excavation of Pilot Tunnel of Power house cavern transformer cavern & BFV chamber is going on and progress of 102m, 63m and 13m has been achieved. In adit to Pressure shaft Bottom & top 150m & 39m progress has been achieved. In surge shaft 29830 cum open excavation completed and shot- crete is in progress. In the HRT, Adit-IV completed upto HRT-I & 15m progress achieved from face-8 in the main HRT. Portal development work is in progress for Adit-I & Adit-II. In Adit-III & Adit IVA 61m & 41m progress achieved.

45

Sikkim ER PS Execution 2012-13 12th Plan

Financial closure yet to be achieved. Work for construction of Head Race Tunnel is awarded to M/s Coastal Projects Pvt. Ltd. on 22.11.2007. Dam & Intake work has been awarded on 01.02.08. E&M work under process of award. Dam & Intake works: Excavation of Adit to Intake Chamber is in progress. Excavation of road diversion tunnel has been completed. HRT: Adit-1 excavation completed & Adit-II excavation completed and HRT excavation started. (240 m/6488 m). Construction Power and infrastructure works such as roads are in progress. Power House: Civil works awarded on 23.05.2008. E&M Works: LOI placed on 28.08.09 to M/S ANDRITZ & Balance of Plant (E&M) has been issued on 14.08.2009.

Financial closure is expected shortly..

Civil & E&M works awarded. LOI issues by Govt. of Sikkim on 01.03.2005. Entire civil and HM works awarded to M/s SEW Construction Ltd on 2nd March, 2008. E&M works awarded to M/s Alstom Project India Ltd. on 26th May, 2008.