You are on page 1of 5

Steps Site selection Update about wind issued energy permits

Duration (expected time we need) Min Real

Costs Man Efforts (salary in men/months) 0.5

2w

3w

Tour of potential sites and collect information in the field of local residents and local administration First preliminary selection of interesting projects Meetings with preliminary project owners Preliminary study for choosen locations (planned two locations), having in mind owner conditions, status of permits and documentation, wind data, infrastructure, local installers, agriculture lands, nature protection issues... Establishing legal entity or buy an existing If we will establish new one Change in designation of land (if agriculture) Loans and financial issues Legal issues regarding the land, projects etc. Possible additional metering of wind Design conditions Obtaining conditions for grid connection and protection of network Feasibility study Investment project Technical and working plans Building perimitions Preliminary grid connection study Grid connection contract Priviledged producer status Preliminary contract of selling electricity Grid connection build Network access Providing funding Buliding contracts Building activities

4w

6w

2w 4w

3w 6w

1 2

0.5 2

4w

4w

1w 4w 2w 2w 50w 4w 4w 8w 10w 10w 12w 8w 2w 2w 2w 10w 1w ? 8w 4w 4w 150w 8w 5w 10w 16w 16w 16w 10w 3w 3w 3w 20w 1w

0.25

Site supervision Assembly of wind system (and PV) Testing and preliminary test production Techical inspection of the system Usage permit Final connection and production

Costs Remarks Other costs Energy ministry - Republic and Province Some kind of spy activities in order to dicover the truth, check political situation, who is involved from local poilticnas and how.... Very sensitive and necessery Report to the investor Travel, Auxiliary How to buy location, energy permit, possible wind measurement results Include possibility to make combined wind/PV installation on the sam location - Report to investor Steps have to be repeated if PV cannont be inplemented at the same site

Kalkulacija cene za pregovore sa Mr. Polsky 6 meseci 12 men/month 28.75

Travel

Travel, Auxiliary

26 weeks 40 hour/week

2 men

Investor issue Lawyer costs Preparing for the build of wind park Building and commisionong Issues related to renewable status and connection

From this point new company will take all activities. Our role in new company would be discussed and negotiated, or we can keep only consultant status (who knows). If we will stay as consultants, we will need two man inside.

Building and commisionong

kulacija cene za pregovore sa Mr. Polsky 2 coveka men/month 30 EUR/h

1200

2400

62400

You might also like