You are on page 1of 13

MEGHALAYA ENERGY CORPORATION LIMITED

MYNTDU LESHKA H. E. PROJECT (3X42MW)


JAINTIA HILLS DISTRCT, MEGHALAYA

PROGRESS OF WORKS AS ON MARCH 2012


COMPLETION DATE: UNIT-I UNIT-II UNIT-III

November, 2011 March, 2012 September, 2012

Save Energy For Benefit of Self and Nation

BACKGROUND

ACTUAL STARTED DATE OF THE PROJECT ORIGINAL COST AS PER TEC ADDITION OF 3RD UNIT APPROVED REVISED COST AS PER 2009 REVISED COST AS PER 2010 SCHEDULE DATE OF COMPLETION

= OCTOBER, 2004 = 363.08 Cr. (2X42MW) = JANUARY, 2008 = 965.93 Cr. (3X42MW) = 1173.13 Cr. (3X42MW) = UNIT-I : NOVEMBER, 2011 = UNIT-II : MARCH, 2012 = UNIT-III : SEPTEMBER, 2012

TIME OF COMPLETION AS PER TEC ACTUAL = 5 YEARS = 7 YEARS

Save Energy For Benefit of Self and Nation

CAUSES OF DELAY
1. Target Completion period is 5 years is unrealistic and the delay is apparent. 2. Remoteness of site. a. Shortage of skilled man power. b. Slow reaction to construction materials. 3. Geological Condition. a. Delay in foundation excavation of Dam. b. Increase in quantity of concreting. 4. Seismological Condition a. New Dawki fault b. Delay in design. 5. Water Chemical Condition (Acidity) a. In view of acidity of river, special concrete, paints etc. had to be provided after some research and design works. 6. Heavy Rainfall (Cherrapunje Belt) a. Early rainfall b. Heavy rainfall causing flood. c. Less working time. As a result of Early and Heavy rainfall there has been many floodings in the work site but abnormal flooding had occurred on :a. 8th October, 2009 b. 20th May, 2011. 7. High head of the Project a. In view of High head, the machine RPM is fixed at 600. b. This result in high pressure etc. develop at the Power House which require utmost care and caution.

Save Energy For Benefit of Self and Nation

PHYSICAL PROGRESS OF WORKS OF THE


MYNTDU LESHKA HYDRO ELECTRIC PROJECT (3 X 42 MW) 1. ROAD The constructions of all road works connecting different sites in the Project are completed.

2. BUILDING The constructions of all buildings are completed, except for Permanent Building, Type-IV at Power House Colony where the works are in progress.

Save Energy For Benefit of Self and Nation

3. DAMSl. No 1 2 3 Particulars of Works Excavation Concreting Control Room Present Quantity 650000 332311 Balance Quantity Completed Finishing works Target date of completion completed -

Unit M3 M3

Completed 650000 331439.00

Completed except for finishing works.

Save Energy For Benefit of Self and Nation

4. SLUICE RADIAL GATES (DAM): Sl. No. 1 All gates completed, except 1(one). All hoisting arrangement completed. Particulars of Works Sluice Radial Gates Unit Nos. Present Quantity 7 Completed All Gates are completed and in operation from both individual control and remote control panel. Gate No.1 is presently used by stop log gate.

5. TUNNEL/SURGESHAFT Sl. No. 1 2 Particulars of Works HRT HPT INTAKE GATE SURGE SHAFT Unit M M No M Present Quantity 3313.46 314.00 1 85 Completed All works completed All works completed All works completed All works completed

Save Energy For Benefit of Self and Nation

Save Energy For Benefit of Self and Nation

6. VAVLE HOUSE & ERECTION OF BUTTERFLY VALVE Sl. No 1 2 3 Present Quantity 11250.00 698.50 Balance Quantity Target date of completion Completed Completed Completed

Particulars of Works Excavation Concreting. Erection of Butterfly Valve

Unit M3 M3 No.

Completed 11250.00 698.50

Units -I, II, & III are completed.

Save Energy For Benefit of Self and Nation

7. ANCHORS & SADDLES (3x42 MW) No. of Anchor Blocks: 10 Sl. No 1 2 Particulars of Works Excavation (channel) & (Anchors/Saddles) Concreting for Anchors & Saddles. Unit M3 M3 Present Quantity 116660.59 27384.993 Completed 116660.59 27384.993 Balance Quantity Target date of completion Completed Completed

8. PENSTOCK & PIPE LINER Sl. No 1 2 Particulars of Works Supply & Fabrication of Penstock Liner Erection of Penstock Liner Unit MT MT Present Quantity 3128.913 3128.913 Completed 3128.913 3128.913 Balance Quantity Target date of completion Completed Completed

Save Energy For Benefit of Self and Nation

9. POWER HOUSE (CIVIL) Civil works All Completed (For Unit- I & II). Remaining works (finishing): a. Railing b. Lighting c. Lifts

Sl. No. 1

Particulars of Works A. POWER HOUSE (i) General Excavation, Pit & Tail Race (ii) Concreting Sub-Structure (iii) Concreting SuperStructure (iv) Concreting of Tail Race Draft Tube Gate

Unit M3 M3 M3 M3 No.

Present Quantity

Completed

Balance Quantity

Target date of completion Completed

All works completed 22000.00 4050.00 20226.739 3 22000.00 4050.00 0 0

Completed Completed Completed -

20226.739 completed The erection work and installation of draft tube gate for all units is completed. (Hoisting arrangement is going on)

Save Energy For Benefit of Self and Nation

10. SWITCHYARD Erection of Equipment All completed. Cabling works All completed. Charging All completed. Sl. No 1 2 3 4 Particulars of Works Excavation Erection of structures equipment Inter connecting Line Cabling Testing Charging Unit M3 M3 Nos. Present Balance Completed Quantity Quantity 90997.38 90997.38 The erection work completed. Testing work is in progress Foundation completed, 7 Tower erection completed Completed Completed Completed Target date of completion Completed Completed Completed Completed Completed Completed

Save Energy For Benefit of Self and Nation

11. POWER HOUSE (ELECTRICAL) a. M/s. Shyama Power Erection of all Auxiliaries in Power House is completed. Testing of all equipments is in progress for Unit III. b. M/s Andritz Hydro Generation started on December 2011 for 1st Unit Auxiliaries Cabling & Termination in progress for Unit-III. c. M/s. Vijai Electricals Erection of Equipment for Unit-III in progress.

CONCLUSION: 1. The 1st Unit is in generation and as on date more than 16 mu of energy is generated. 2. Synchronization of Unit II started on 30th March 2012. 3. Target completion date for Unit III is September 2012.

Save Energy For Benefit of Self and Nation

Save Energy For Benefit of Self and Nation

You might also like