You are on page 1of 8

E2-E3/Civil

Rev date: 01-04-2011

E2-E3: CIVIL

CHAPTER-8 QUALITY ASSURANCE IN BUILDING WORKS

BSNL India

For Internal Circulation Only

Page: 1

E2-E3/Civil

Rev date: 01-04-2011

Quality Assurance in Building Works


Quality Assurance Unit, in general shall exercise the role for management of quality Systems and procedures to achieve and sustain quality of works executed by BSNL Civil Wing and to offer necessary guidance to the field units in this regard. QA &TA Cell (Quality Assurance & Technical Audit cell) at the Head Quarters of BSNL has two Executive Engineers & four Sub divisional Engineers. They function under the control of DGM(C) & PGM(BW) Major Functions To deal with the policy issues pertaining to total quality management system for Civil Wing. To deal with the recommendations of the Technical committee. To update the system on the basis of feedback from Quality Assurance Teams at Zonal Level and to issue guidelines/instructions To lay down procedures, norms/guidelines for periodic inspection. To keep itself update with modern testing equipment & methods and to update the information. To review the performance of new building materials and techniques introduced from time to time. To conduct field inspection of works to assess the effectiveness of the quality assurance procedures. To carry out investigations and enquires with regard to quality related aspects. To lay down the specifications in respect of items which are not specified in CPWD specification A) Documents/Registers to be made available to QATA Tender opening register Works/tender file Copy of PE Copy of DE MRJ Copy of agreement/NIT Soil investigation recomm B) Quality Assurance Aids Field staff should be equipped with

BSNL India

For Internal Circulation Only

Page: 2

E2-E3/Civil

Rev date: 01-04-2011

(a) Copy of agreement (b) Latest CPWD specifications along with upto date correction slips (c) Copy of (I) Preliminary estimate (II) Detailed estimate (III) Details of measurement (d) Inspection report of senior officers and zonal QATA cell C) Drawings to be available at site (I) Approved architectural drawings (II) Structural drawings (III) Municipal approval of the project. (IV) Site development plan. (V) Terrace plan detailed. (VI) Drainage plan of compound. (VII) Toilet plans with pipe system. D) Testing facilities to be available at site Field lab should be well equipped with: a) Standard Tool Kit. b) Level, Theodolite. c) Cube mould(required nos.). d) Slump Cone e) Standard Sieves. f) Graduated cylinders, weighing balance. g) Cube testing machine (calibrated) etc. h) Removal of defects Timely notice should be issued to the Contractor/ agency along with the list of defects/ damages observed by EE/ SE at site and recorded in site order book for rectification. In case of failure to rectify defects/ damages, whether action under relevant clause should be initiated. Hindrance Register Is hindrance register to be recorded by AE and reviewed by EE/SE. Timely Provisional Extension to be issued. Entries to be in chronological order. Overlapping period should be calculated To signed by agency on start and completion of hindrance

BSNL India

For Internal Circulation Only

Page: 3

E2-E3/Civil

Rev date: 01-04-2011

Soil Investigation Report Whether soil investigation done. Give brief detail with recommended net bearing capacity of soil and depth of foundation). Whether recommendations of the report has been incorporated in the design. Suitability of water for construction (a) What is source of water. (b) All Mandatory tests prescribed in the CPWD Specifications have been done and approved by Engineer-in-Charge of work before construction (c) Has water been tested subsequently (i.e., after an interval of three months) and found fit for use in the work? 6.0 Technical Audit 6.1 Pe Sanction Memo No (a) Amounting to (b) Corresponding provisions Detailed Estimate (a) Technically sanctioned by (b) Amount of technically sanctioned Estimate 6.2 Tender (i) Call no/ published on website (ii) No of tenders received (iii) Work awarded to lowest (iv) Authority accepting the tender (v) Market rate justification of tender (vi) Clause 12 percentage on applicable

schedule

Tender Documents Properly page numbered Agreement on stamp paper Conditions modified during negotiation. Any observations during scrutiny which needs incorporation. All columns needs to be filled. Rebate needs to be accounted. Agreement not signed by the agency/EE. Sources to be filled properly.

BSNL India

For Internal Circulation Only

Page: 4

E2-E3/Civil

Rev date: 01-04-2011

6.3 Deviations Whether deviation in quantities noticed? If so (i) Whether EE has examined the reasons for deviations (ii) Whether EE has forwarded the case to next higher authority for its approval 6.5 Extra/Substituted Items (a) Is justification of items proper (b) Sanction of competent authority (c) Any minus extra item paid (Examine the criterion for such items). 6.6 Substandard Items (a) Whether notice was issued under relevant clause of agreement (b) Whether approval of competent authority taken for acceptance of substandard work Part rates Whether part rate paid Whether rates held back are adequate Insurance/bank guarantee of documents and safe custody of materials for which secured advance has been given Percentage of test check by AE/EE has been Whether any tender / work order issued for the completion of the work in addition to the main agreement (E) Site Records Register should be issued by division office under the signature of EE. Site order book Should be reviewed by EE/SE. AE/ JE to take action on the aspects pointed out by EE/SE and record compliance in site order book. Cement register - Cement register to checked by AE/EE periodically and record the observations with date invariably. - Details of cement received should be entered with brand name, source of receipt, date of manufacture. - Brief description of all works carried out in cement issued for a days work should be given.

BSNL India

For Internal Circulation Only

Page: 5

E2-E3/Civil

Rev date: 01-04-2011

Steel Register Register to checked by AE/EE periodically and record the observations with date invariably. -Details of steel received should be entered with brand name, source of receipt. -Unit weights to measured and recorded. (samples to be kept), payment to be done accordingly. Testing Test Registers Test registers to be maintained in the standard format. To be reviewed by SE/EE with date. Field tests should be recorded properly. General Observations Checking of floor slope.(specifically in bath, WC, kitchen, terrace and balcony) ISI marked materials/fittings etc to be used at site. Testing of plumbing systems/SW line. Quality and testing of materials/ products 1) Mandatory tests not done to required number. 2) Field test not done or not entered in register. 3) Extension of time not given to agreement. 4) Sanction of work charged to main AA&ES without provision. 5)Secured Advance without insurance. 6)Part rates not sufficient e.g in steel windows ,shuttering to be removed etc. 7)Development plan, plan of compound not available. 8)Level of site not taken before start of work. 9)Payments made for leveling of site and jungle clearance. 10)Water test not carried out before start of work. 11)Payment/ measurements of earth work of excavation not done as per spec. 12)Use of wooden ballies in centering and shuttering. 13) Casting of slab without leaving space for rain water pipes. 14) Columns reinforcements bars not embedded in terrace slab / beams. 15) Last landing of staircase casted at slab level. 16) Stair case waist slab thickness not uniform / as per drawing. 17)Brick on edge at plinth, roof slab not done. 18)Hoop iron bars in half brick work missing or not regular. 19)Kota stone thickness in fooling and stair case not proper.

BSNL India

For Internal Circulation Only

Page: 6

E2-E3/Civil

Rev date: 01-04-2011

20) Shaft side beams of toilet casted above slab level without leaving hole for pipes to pass. 21)Traps are not as per specifications. 22) Hacking of RCC surface not done. 23) Reinforcement placing at stair case not proper. 24Steel door hinges not ISI marked and not of proper thickness. 25)Use of MS screws in Aluminum work instead of brass/steel screws. 26)Construction of Septic tanks with excess capacity. 27)Lead joint in plumbing not as per items. 28)Terrazzo tile not ISI. 29) Thickness of glass in windows not proper.

BSNL India

For Internal Circulation Only

Page: 7

E2-E3/Civil

Rev date: 01-04-2011

Questions:1. Briefly discuss about major functions of QATA? 2. Please elaborate the documents/registers required to be made available to the QATA wing on inspection. 3. What are the quality assurance aids at site? Please mention briefly. 4. What is substandard item? Please mention provisions about this item. 5. Please write brief notes on cement register and steel register. 6. Write down at least ten check lists/points about quality assurance and testing of materials which QATA generally inspects at site. 7. What are the various drawings which should be available at site of work? 8. What are the various testing facilities which should be available at site? 9. What is the checklist to ascertain the suitability of water for construction purposes? 10. What are part rates of items? When and where part rates of items are paid? 11. What is site order book? Who maintains it? What are the provisions about its inspection/checking by senior officers?

BSNL India

For Internal Circulation Only

Page: 8

You might also like