You are on page 1of 4

PROGRESS REPORT

WAVE PIERCE CATAMARAN "QUICK SILVER"


" ONE WEEKLY REPORT "
Site:PT. CAPUTRA MITRA SEJATI Shipyard & Shipbuilder
Day/Date: Wednesday, 11/07/2012
Progress no : 019/CMS/WPC-QS/VII/2012
No

Description

Project Engineering & Site Preparation


1 Pleminary Project
1.1.1
Design Drawing
1.1.2
Material Spesification Approval
1.1.3
Working procedure, WPS and Welder Certificate
2 Detail Drawing
3 Yard Preparation
1.3.1
Rig Arrangement
1.3.2
Tool and Equipment
1.3.3
Man power

II Order / Procurement
1 Hull Construction
2.1.1
Marine Alluminium Plate
2.1.2
Piping, Fitting, And Accessories
2 Vessel Equipment
2.2.1
Propulsion
- Main Engine
- Gear box
2.2.2
Water Jet
2.2.3
Cardin Shaft
2.2.4
Main Engine Exhaust
2.2.5
Auxiliary Exhaust
2.2.6
Electrical Supply (Generator)
2.2.7
Winch Anchor
2.2.8
Freight Davit
2.2.9
Cathodic Protection (alluminium anode and anti fouling coat)
2.2.10 Air Conditioning
2.2.11 Pumps
3 Electrical System and Electrical Equipment
2.3.1
Cable
2.3.2
Distribution Panel (415 V , 220V and 24 V Dc)
2.3.3
Electrical Accessories
Batteries
Shore Power
FORM/CMS-PPC-PPC/002. Rev.00

Required

Working
Week

Unit

8
5
7
48

Completed (each)

Progress

TOTAL
(total progress x
required)

0.00%
0.00%
0.00%
0.02%

98.75%
98.50%
100.00%
98.75%

0.99%
0.49%
0.50%
0.99%

0.01%
0.01%
0.00%
0.01%

50.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%

0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%

100.00%
100.00%
100.00%
0.00%
0.00%
0.00%
100.00%
0.00%
0.00%
25.00%
0.00%
0.00%
50.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%

0.33%
0.33%
0.33%
0.00%
0.00%
0.00%
8.50%
0.00%
0.00%
3.34%
0.00%
0.00%
4.61%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%

0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
1.50%
0.00%
10.01%
0.00%
0.00%
4.61%
2.02%
0.28%
0.63%
1.26%
0.96%
1.26%
0.08%
2.75%
0.69%

0.00%
0.00%
0.00%

0.00%
0.00%
0.00%

0.00%
0.00%
0.00%

0.00%
0.00%
0.00%

1.13%
3.00%
0.19%

of total

Prev

Weeks
Weeks
Weeks
Weeks

1.00%
0.50%
0.50%
1.00%

98.75%
98.50%
100.00%
96.75%

2
2
2

Weeks
Weeks
Weeks

0.33%
0.33%
0.33%

100.00%
100.00%
100.00%

10
3

Weeks
Weeks

8.50%
1.50%

100.00%
0.00%

Weeks

13.34%

25.00%

4
4
4
4
4
4
4
4
2
1

Weeks
Weeks
Weeks
Weeks
Weeks
Weeks
Weeks
Weeks
Weeks
Weeks

9.22%
2.02%
0.28%
0.63%
1.26%
0.96%
1.26%
0.08%
2.75%
0.69%

1
3
1

Weeks
Weeks
Weeks

1.13%
3.00%
0.19%

Actual

Week

Progress

2.00%

Total

Remaining

1 of 4

PROGRESS REPORT
WAVE PIERCE CATAMARAN "QUICK SILVER"
" ONE WEEKLY REPORT "
Site:PT. CAPUTRA MITRA SEJATI Shipyard & Shipbuilder
Day/Date: Wednesday, 11/07/2012
Progress no : 019/CMS/WPC-QS/VII/2012
No

Description

2.3.4
2.3.5
2.3.6
2.3.7
2.3.8
2.3.9
2.3.10

Lighting
Power Outlet
Navigation
Alarm System
Crew Intercom
CCTV
PA/Audio System
TV System
Fire and Safety Equipment

III Construction & Installation


1 Kell Laying
2 Hull Construction (Bottom, Double bottom, Side, Bhd and Frame)
3.2.1
Cutting and Nesting
3.2.2
Fit up and Assmebly
3.2.3
Welding and Finishing
3 Main Deck Construction (Shell and Frame)
3.3.1
Cutting and Nesting
3.3.2
Fit up and Assmebly
3.3.3
Welding and Finishing
4 Superstructure (Shell, Deck and Frame)
3.4.1
Cutting and Nesting
3.4.2
Fit up and Assmebly
3.4.3
Welding and Finishing
5 Out Fitting
3.5.1
Fender
3.5.2
Engine Bearer
3.5.3
Sewage and Fwt Tank
3.5.4
Engine Cashing
3.5.5
Daily Tank
3.5.6
Engine Removal Hatch
3.5.7
Man Hole
3.5.8
Hand Railling and Walkways
3.5.9
Engine Room Floor
3.5.10 Rescue Boat Davit
3.5.11 Acces Ladder
FORM/CMS-PPC-PPC/002. Rev.00

Required

Completed (each)

Progress

TOTAL
(total progress x
required)

0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%

0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%

0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%

0.75%
0.30%
0.15%
0.15%
0.19%
0.15%
1.50%

100.00%
100.00%
99.00%

0.00%
0.00%
0.00%

100.00%
100.00%
99.00%

2.00%
4.00%
1.98%

0.00%
0.00%
0.02%

1.00%
2.00%
1.00%

100.00%
99.00%
88.00%

2.50%

0.00%
0.00%
0.03%

100.00%
99.00%
90.50%

1.00%
1.98%
0.91%

0.00%
0.02%
0.10%

Weeks
Weeks
Weeks

1.00%
2.00%
1.00%

98.50%
56.00%
5.00%

0.25%
15.00%
2.50%

0.00%
0.30%
0.03%

98.75%
71.00%
7.50%

0.99%
1.42%
0.08%

0.01%
0.58%
0.93%

Weeks
Weeks
Weeks
Weeks
Weeks
Weeks
Weeks
Weeks
Weeks
Weeks
Weeks

0.24%
0.30%
0.30%
0.18%
0.24%
0.18%
0.18%
0.12%
0.45%
0.45%
0.24%

30.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
0.00%
0.00%
0.00%
80.00%

0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%

30.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
0.00%
0.00%
0.00%
80.00%

0.07%
0.30%
0.30%
0.18%
0.24%
0.18%
0.18%
0.00%
0.00%
0.00%
0.19%

0.17%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.12%
0.45%
0.45%
0.05%

Working
Week

Unit

1
1
1
1
1
1
1

Weeks
Weeks
Weeks
Weeks
Weeks
Weeks
Weeks

0.75%
0.30%
0.15%
0.15%
0.19%
0.15%
1.50%

0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%

5
16
10

Weeks
Weeks
Weeks

2.00%
4.00%
2.00%

5
13
10

Weeks
Weeks
Weeks

5
12
8
8
5
5
4
3
3
2
3
6
4
4

of total

Prev

Week

Actual
Progress

Total

Remaining

2 of 4

PROGRESS REPORT
WAVE PIERCE CATAMARAN "QUICK SILVER"
" ONE WEEKLY REPORT "
Site:PT. CAPUTRA MITRA SEJATI Shipyard & Shipbuilder
Day/Date: Wednesday, 11/07/2012
Progress no : 019/CMS/WPC-QS/VII/2012
No

Description

10

3.5.12 Bulwark
3.5.13 Air Conditioner Ducting
3.5.14 Deck Crane
3.5.15 Pillar interior
3.5.16 Watertigh Door and Window
3.5.17 Pump Foundation
3.5.18 Bollards
3.5.19 Mast Navigation
3.5.20 Chain Locker, Hawse Pipe & Winch Anchor Found.
Piping System
3.6.1
Bilge System
3.6.2
Sullage System
3.6.3
Fire and Hydrant System
3.6.4
Filling, Sounding and Air Pipe System
3.6.5
Fresh Water System
3.6.6
Hydraulic System
3.6.7
Fuel System
3.6.8
Cooling System
Machinery and Propulsion
3.7.1
Main Engine and gear Box
3.7.2
Shafting
3.7.3
Electrical Suppy (Generator)
3.7.4
Water Jet
3.7.5
Main and Aux. Engine Exhaust
Electrical and Navigation Installation
3.8.1
Installation Cable and Support
3.8.2
Installation Panel and Accessories
3.8.3
Navigation Installation
Interior and Finishing
3.9.1
Deck Covering
3.9.2
Ceilling
3.9.3
Seat Installation
3.9.4
Pilot House
3.9.5
Kiosk/Servery
3.9.6
Painting AF
Safety Sign and Equipment

FORM/CMS-PPC-PPC/002. Rev.00

Required

Completed (each)

Progress

TOTAL
(total progress x
required)

0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%

40.00%
0.00%
0.00%
0.00%
0.00%
0.00%
25.00%
0.00%
91.00%

0.24%
0.00%
0.00%
0.00%
0.00%
0.00%
0.03%
0.00%
0.27%

0.36%
0.90%
0.60%
0.12%
0.12%
0.24%
0.09%
0.12%
0.03%

0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%

0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%

0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%

0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%

0.60%
0.45%
1.20%
0.45%
0.30%
0.90%
1.20%
0.90%

1.50%
0.90%
1.20%
1.50%
0.90%

0.00%
0.00%
0.00%
0.00%
0.00%

0.00%
0.00%
0.00%
0.00%
0.00%

0.00%
0.00%
0.00%
0.00%
0.00%

0.00%
0.00%
0.00%
0.00%
0.00%

1.50%
0.90%
1.20%
1.50%
0.90%

Weeks
Weeks
Weeks

2.00%
1.20%
0.80%

0.00%
0.00%
0.00%

0.00%
0.00%
0.00%

0.00%
0.00%
0.00%

0.00%
0.00%
0.00%

2.00%
1.20%
0.80%

Weeks
Weeks
Weeks
Weeks
Weeks
Weeks

0.30%
0.40%
0.30%
0.30%
0.30%
0.40%

0.00%
0.00%
0.00%
0.00%
0.00%
0.00%

0.00%
0.00%
0.00%
0.00%
0.00%
0.00%

0.00%
0.00%
0.00%
0.00%
0.00%
0.00%

0.00%
0.00%
0.00%
0.00%
0.00%
0.00%

0.30%
0.40%
0.30%
0.30%
0.30%
0.40%

Working
Week

Unit

3
5
3
3
4
3
3
3
4

Weeks
Weeks
Weeks
Weeks
Weeks
Weeks
Weeks
Weeks
Weeks

0.60%
0.90%
0.60%
0.12%
0.12%
0.24%
0.12%
0.12%
0.30%

40.00%
0.00%
0.00%
0.00%
0.00%
0.00%
25.00%
0.00%
91.00%

6
5
5
5
5
5
5
4

Weeks
Weeks
Weeks
Weeks
Weeks
Weeks
Weeks
Weeks

0.60%
0.45%
1.20%
0.45%
0.30%
0.90%
1.20%
0.90%

4
4
4
4
4

Weeks
Weeks
Weeks
Weeks
Weeks

9
8
6
13
13
4
4
4
4

of total

Prev

Week

Actual
Progress

Total

Remaining

3 of 4

PROGRESS REPORT
WAVE PIERCE CATAMARAN "QUICK SILVER"
" ONE WEEKLY REPORT "
Site:PT. CAPUTRA MITRA SEJATI Shipyard & Shipbuilder
Day/Date: Wednesday, 11/07/2012
Progress no : 019/CMS/WPC-QS/VII/2012
No

Description

IV Inspection, Test & Dossier (certifocate by Hubla and Class)


accordance with the inspection test plan approved by the class
V

Required

Completed (each)

Working
Week

Unit

55

Weeks

3.00%

0.00%

2
2

Weeks
Weeks

1.05%
1.95%

0.00%
0.00%

of total

Prev

Week

Actual

Progress

TOTAL
(total progress x
required)

0.00%

0.00%

0.00%

3.00%

0.00%
0.00%

0.00%
0.00%

0.00%
0.00%

1.05%
1.95%

Progress

Total

Remaining

Launching

VI Trial
1 Dock Trial
2 Sea Trial
VII Acceptance

100.00%
Distribution Laporan
Nama

Instansi

Suralaya, 11 Juli 2012


Prepared,

Checked,

Putra Is Dewata
Staff PPC

M. Iqbal Kurniawan
Ka. Dept PPC

FORM/CMS-PPC-PPC/002. Rev.00

0.37%

Jabatan

Safety Meeting
Safety Meeting's Topic

Approved,
PT. CAPUTRA MITRA SEJATI

Approved,
PT. Caputra Bumi Bahari

M. Ghufron
Project Manager

36.95%

63.05%

Kriss Pramono
Project Leader Builder

4 of 4

You might also like