You are on page 1of 92

Report on the impact of unexploded

cluster submunitions in Serbia

Norwegian Peoples Aid


Regional ofce South East Europe

January 2009 Norwegian Peoples Aid, Regional office South East Europe, Kosovska 8/3 , 11ooo Beograde, Serbia in cooperation with Norwegian Peoples Aid, Storgt. 33A, 0028 Oslo, Norway www.npa.org.rs; www.npaid.org

Publisher

Norwegian Peoples Aid, Regional office South East Europe

Published by

Emil Jeremi

Report prepared by

Darvin Lisica, erif Bajri

Photographer Design

John Rodsted erif Bajri

Project team

Programme manager: Darvin Lisica Project manager: Mirko Milii, Surveyors: Rusmir Trumi, Stania uri, Neboja trbac, Goran Vladi, Sead Klii, Miroslav Pisarevi, Ervin Omeragi i Branislav Jovanovi Amela Bali, erif Bajri

Monitoring team

Contents
Acknowledgements ...............................................................................................................................8 Executive summary ...............................................................................................................................9 Timeframe and objectives of the General Survey .......................................................................9 Results of the cluster hazard assessment.......................................................................................9 Hazard and accidents caused by cluster contamination ...........................................................10 Risk behaviour................................................................................................................................10 Economic impact of cluster contamination ...............................................................................11 Size of risk area in Serbia ..............................................................................................................11 Introduction .........................................................................................................................................12 Terms of reference and methodology ...............................................................................................16 Terms of reference .........................................................................................................................16 Standard operating procedures ....................................................................................................18 Database ..........................................................................................................................................20 General assessment of the situation of unexploded cluster submunitions in Serbia .................24 Unexploded cluster submunition hazard in Serbia ...................................................................25 Unexploded cluster submunitions as cause of hazard.........................................................25 Assessment of extent and characteristics of suspected areas..............................................29 Suspected Areas: Status at the Beginning of Survey operations ..................................29 Procedure and Results of Exclusion of Suspected Areas through Land Cancellation ........................................................................................................................31 Suspected Area Contaminated by Cluster Submunitions Status at the Beginning of November 2008 ...........................................................................................34 What will be the final extent of risk areas for clearance in Serbia? ..............................36 Social and economic impact of unexploded cluster submunitions ..............................................39 Cluster submunitions accidents and incidents ..........................................................................40 Vulnerability analysis of the population at risk .........................................................................43 Affected Communities ............................................................................................................43 Age Structure ............................................................................................................................44 Entry of Population into Risk Areas ......................................................................................44 Analysis of blocked resources ......................................................................................................47 Reports on general survey of risk areas ............................................................................................50 Selection of priorities for clearance .............................................................................................52

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

Case studies ....................................................................................................................................56 Municipality Bujanovac .....................................................................................................56 Municipality of Preevo .....................................................................................................59 Municipality of Kurumlija ...............................................................................................61 Project quality managment ................................................................................................................63 General survey monitoring ..........................................................................................................63 General survey: Quality control .............................................................................................64 General survey results: Quality assurance ............................................................................64 Strategic assumptions and indicators................................................................................................69 Conclusions ..........................................................................................................................................71 Appendixes ...........................................................................................................................................72 Appendix A: Acronyms and terms used...........................................................................................72 Appendix B: Criteria for cancellation of land from the areas suspected of hazard of unexploded cluster submunitions ....................................................................................................77 Appendix C: Land use classification system ....................................................................................78 Appendix D: Data by districts, municipalities and settlements ....................................................79 Appendix E: Calculation of failure severity .....................................................................................84 Appendix F: Calculations of risk area for clearance .......................................................................86 Literature ..............................................................................................................................................90

List of tables
Table 1: Geo-coded entities...................................................................................................................................................... 23 Table 2: Cluster ordnance deployed by NATO forces in the Republic of Serbia ..............................................................27 Table 3: Estimate of the number of cluster ordnance used and remaining unexploded cluster submunitions ...........28 Table 4: Cluster submunitions, quantity per municipality..................................................................................................29 Table 5: Municipalities affected by unexploded cluster submunitions ............................................................................. 35 Table 6: Number of suspected areas with regard to hazard levels and blocked resources ..............................................48 Table 7: Extent of suspected areas with regard to hazard levels and blocked resources..................................................49 Table 8: Risk location priority matrix .................................................................................................................................... 52 Table 9: Matrix for identifying the level of hazard ............................................................................................................... 53 Table 10: Matrix for identifying environmental impact risk ............................................................................................... 53 Table 11: Data on threatened communities in the Municipality of Bujanovac ................................................................. 57 Table 12: Land blocked due to unexploded cluster submunitions contamination in the Municipality of Bujanovac in km2 ...................................................................................................................................................................... 58 Table 13: Data on threatened communities in the Municipality of Preevo .....................................................................59 Table 14: Land blocked due to unexploded cluster submunitions contamination in the Municipality of Preevo in km2 ......................................................................................................................................................................... 60 Table 15: Data on threatened communities in the Municipality of Kurumlija................................................................ 61 Table 16: Land blocked due to unexploded cluster submunitions contamination in the Municipality of Kurumlija in km2 .................................................................................................................................................................... 52 Table 17: Districts in Serbia affected by unexploded cluster submunitions ......................................................................79

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

Table 18: Settlements affected by unexploded cluster submunitions ................................................................................ 80 Table 19: Suspected area and the number of directly threatened inhabitants per threatened community................... 81 Table 20: Calculation of failure severity ................................................................................................................................82 Table 21: Scale for evaluation of the Failure Severity Degree .............................................................................................. 85 Table 22: Scale for evaluation of the Failure Occurrence Probability ................................................................................ 85 Table 23: Scale for evaluation of the Difficulty in Failure Detection.................................................................................. 85 Table 24: Calculation of risk area for clearance based on the magnitude and number of suspected areas ..................86 Table 25: Calculation of risk area for clearance based on land release rate by hazard levels ..........................................87 Table 26: Calculation of risk area for clearance based on the surveyed risk areas ...........................................................88 Table 27: Calculation of risk area for clearance options ...................................................................................................89

List of graphs
Graph 1: Extent of cancelled area, by cancellation criteria.................................................................................................. 32 Graph 2: Analysis of cancelled area in relation to previously assessed hazard levels ...................................................... 33 Graph 3: Analysis of cancelled area in relation to intended use of land............................................................................ 33 Graph 4: Share in the extent of suspected area per hazard level ........................................................................................ 35 Graph 5: Number of suspected areas and average extent by hazard level ........................................................................ 35 Graph 6: Unexploded cluster submunitions clearance, by year .........................................................................................39 Graph 7: Number of accidents and incidents, by year ........................................................................................................ 40 Graph 8: Number of accidents and incidents, by type of cluster submunitions .............................................................. 41 Graph 9: Cluster submunitions casualties ............................................................................................................................. 41 Graph 10: Exposure of local communities to the risk of unexploded cluster submunitions..........................................43 Graph 11: Age structure of the affected population ..............................................................................................................45 Graph 12: Entry into surveyed risk area identified groups ..............................................................................................45 Graph 13: Entry into surveyed risk area frequency and numbers .................................................................................. 46 Graph 14: Distance of the surveyed risk areas from nearest settlement/household ....................................................... 46 Graph 15: Relation of the number and extent of suspected areas, by blocked resources ................................................47 Graph 16: Time spent on preparing general survey reports ............................................................................................... 51 Graph 17: Share of risk areas, by vulnerability levels and potential benefit levels............................................................54 Graph 18: Share of risk areas by hazard levels and environmental impact levels............................................................. 55 Graph 19: Share of risk areas for clearance, by priority levels............................................................................................. 55 Graph 20: Ratio of failure frequency and their risk factor ................................................................................................. 66 Graph 21: Pareto chart of errors identified during the control of survey reports ............................................................67 Graph 22: Population structure in local communities where survey of individual risk areas was carried out ............82 Graph 23: Employment structure in affected communities ................................................................................................ 83

List of maps
Map 1: Areas of cluster ordnance deployment, according to data received from NATO ...............................................26 Map 2: Distribution of cluster-ordnance deployment zones in the territory of Serbia (without Kosovo) ...................30 Map 3: Classification of affected municipalities by size of suspected areas ...................................................................... 37

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

Map 4: Locations of accidents and incidents .......................................................................................................................42 Map 5: Municipality of Bujanovac..........................................................................................................................................56 Map 6: Map of risk areas, Bujanovac municipality ............................................................................................................. 58 Map 7: Municipality of Preevo ..............................................................................................................................................59 Map 8: Map of risk areas, Preevo municipality .................................................................................................................. 60 Map 9: Municipality of Kurumlija ........................................................................................................................................ 61 Map 10: Map of risk areas, Kurumlija municipality ...........................................................................................................62

List of figures
Figure 1: Organizational structure.......................................................................................................................................... 17 Figure 2: Flow Chart: Process of general survey of cluster-ordnance deployment areas ................................................ 21 Figure 3: Data Flow Chart for General Survey Database ....................................................................................................22 Figure 4: Position of the general assessment of the situation in planning for clearance of areas contaminated by unexploded ordnance in the Mine Action Centre of the Republic of Serbia Model ...................................................24

List of pictures
Collecting and processing data in field................................................................................................................................. 19 Cluster submunition found in Sjenica ................................................................................................................................... 25 Parts of cluster submunitions found in Kurumlija .............................................................................................................27 Urgent marking sings installed on acces road to suspected area ........................................................................................31 Part of cluster bomb found in Preevo ..................................................................................................................................36 Cluster submunition victim ................................................................................................................................................... 40 Parts of cluster submunitions found in Sjenica ....................................................................................................................44 Parts of cluster submunitions found in Bujanovac ..............................................................................................................45 Urgent marking sign installed by survey team during field activities ...............................................................................50 Household in suspected area ..................................................................................................................................................54 Populated area suspected to contain cluster submunitions ................................................................................................56

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

Acknowledgements
We wish to thank the Norwegian Ministry of Foreign Affairs for financing this project. Many thanks to photographer John Rodsted for taking the pictures for the survey report, and to Susan Hivik for language-editing the English version of the report. We are indebted to the Civil Protection in Serbia for providing us with necessary information on affected municipalities and areas, facilitating data collection in the field for our surveyors. We also thank the Serbian Mine Action Centre and its director, Petar Mihajlovi, for support and co-operation. Finally, we would like to stress that any shortcomings or omissions in this report are solely the responsibility of the NPA!

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

Executive summary

Timeframe and objectives of the General Survey


The general survey in Serbia was carried out by NPA between 9 November 2007 and 30 November 2008. The immediate objectives were to assist the Mine Action Centre and the Government of the Republic of Serbia in defining the scale of the problem, identify contaminated areas and assist in capacity building to enable the Mine Action Centre to manage operations of surveying and clearing areas contaminated by unexploded cluster submunitions. The long-term objective of the project has been to create a secure environment for the local population, free of hazards of unexploded cluster submunitions.

Results of the cluster hazard assessment


A detailed assessment of the characteristics of deployment zones was carried out in the third phase of the general survey. Survey reports were prepared, data mapping was conducted and the results were entered into the database. By the end of November 2008, the survey teams had prepared 100 reports. The total risk area covered by these reports is 8.3 km,2 which will necessitate multi-annual operations of clearance of unexploded cluster submunitions in Serbia. Each report on the general survey contains 313 items of data: thus, a total of 31,300 data entries have been recorded in the database. In addition, there are 100 sketch drawings of risk areas with coordinates of breakpoints, 100 drawings of the wider areas, 231 photographs of risk areas, 168 photographs of installed signs of emergency marking, 48 minutes of interviews conducted, and 100 orders/requests for general survey. The number of working hours spent on field operations, data processing and report preparation was 4,424, or an average of 44.24 hours for the preparation of each survey report. The results of the general survey show a total of 105 cluster ordnance deployment zones located in the territory of Serbia, in 15 municipalities. In these deployment zones, 196 cluster bomb units were used, containing 37,032 pieces of cluster submunitions. Immediately after deployment, the cluster submunitions and bomb remnants were typically collected by military, police and civil defence units. However, records on the removal of unexploded ordnance were not available to the survey teams of the NPA. It is estimated that there are still 2,547 pieces of unexploded cluster submunitions scattered in 105 deployment zones, or an average of 24.06 pieces of cluster submunitions per deployment zone. General survey field activities were completed by early November 2008. All results were processed and entered into the database. The database on the total suspected areas contains 390 polygons, in all 30.7 km2, with an average size of 0.079 km2 per polygon. It

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

was possible to reduce the total suspected area in comparison to the initial assessment of February 2008, for two reasons: (1) reduction in the number of deployment zones after cancellation of non-existent deployment zones of cluster ordnance, and cancellation of deployment zones of graphite cluster submunitions; and (2) more precise assessment and ensuing cancellation of some previously suspected areas. The distribution of suspected areas in relation to the level of assessed hazard was as expected. The lowest share consisted of areas categorized as representing an extremely high hazard. Suspected areas assessed as having higher hazard levels (extremely high, very high and high hazard) constituted 21.52% of the total, or 6.6 km.2

Hazard and accidents caused by cluster contamination


Accidents and incidents have been caused by four types of cluster submunitions: BLU 97, BLU 97 A/B, Mk-4 and Mk-118. Cluster submunitions of the type BLU 97 are the most frequent cause (46.6% of instances), followed by submunitions of the type Mk-4 (in 34.3% of cases). Accidents recorded to date have resulted in 191 victims: 31 fatalities (16.2%), and 160 persons injured (83.8%). The greatest number of casualties occurred during the 1999 deployment of NATO air forces: 27 fatalities, and 152 persons wounded. From the end of the NATO campaign until November 2008, there were an additional 12 casualties, four of them fatalities: three children and one farmer; whereas eight persons have been injured: two de-miners, one farmer and five children. The hazard of cluster submunitions is not evenly distributed, affecting 28 local communities (mesne zajednice) in 16 different municipalities in Serbia, and a total of 12 out of 30 districts. Some 162,000 people live in the affected local communities. According to the latest assessments, 88,000 are living in the immediate vicinity of suspected areas, and can thus be considered as exposed to daily risk.

Risk behaviour
Risk behaviour of the population was registered in 91.8% of the surveyed risk areas. In most cases (56.2%), such behaviour involved the entry of adults from affected settlements. (See Graph 12.) Children are second in the number of registered cases. They enter together with adult villagers (in 28% of the cases), and less frequently together with adults and other persons i.e. individuals not living in the affected communities. Those living in the affected local communities apparently do not feel directly vulnerable to cluster submunitions. They know that surface-level removal of unexploded cluster submunitions has been undertaken, and assume that what remains is mainly located underground. On the other hand, they do take certain precautions: children tend to enter suspected areas in the company of adults, and group entry is more common than individual entry. Entry into risk areas, proximity to settlements, and children as a vulnarable group are included in the criteria for selection of priorities for clearance of unexploded cluster submunitions.

10

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

Economic impact of cluster contamination


It is mostly agricultural land that is blocked due to the presence of unexploded cluster submunitions: 29.7% of the suspected locations relate to agricultural land, or 33.4% of the total area suspected. The second largest barrier caused by unexploded cluster submunitions is the impossibility of reconstructing the infrastructure of settlements and utility facilities (19.9% of the total suspected area). The third largest problem is the impossibility of renovating or restoring housing units (14.2%). Further significant blockage problems relate to the following categories of land use: forest exploitation and maintenance (8.8%), tourism development (9.6%), road communications (6.4%), and new industrial production (4.2%). The analysis confirms that the hazard of unexploded cluster submunitions in combination with blocked resources has a significant impact on the socioeconomic situation of the communities affected. The likelihood of fatalities has been reduced, but the number and frequency of incidents is such that the probability of activating unexploded submunitions will rise with the growing needs of the population to use the blocked land.

Size of risk area in Serbia


The extent of risk area still to be cleared of unexploded cluster submunitions in Serbia has been calculated to be approximately 15 km2 !

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

11

Introduction

n 3 December 2008, 94 states signed the Convention on Cluster Munitions (CCM) in Oslo, Norway. The Convention prohibits state parties from buying, selling, storing, using or transferring cluster munitions in the future. The CCM is expected to contribute to speeding up the process of clearing countries and territories affected by cluster munitions and to provide necessary assistance to victims both to the victims of cluster munition accidents, and to their families. Furthermore, stockpile destruction will be a priority: destroying millions of cluster submunitions so that they will never kill, hurt or maim innocent civilians during or after conflicts. The Convention on Cluster Munitions is a great achievement. It was possible due to fruitful co-operation between progressive countries, civil society organizations, relevant UN agencies, the ICRC and the Red Cross Movement working together within the Oslo Process aimed at banning cluster munitions. We hope and expect that the CCM will be adhered to also by states that do not sign the convention, as has been the case with the Mine Ban Treaty of 1997. The Oslo Process aimed at banning the indiscriminate weapon of cluster munitions was truly a success, producing a strong convention in less than two years. The CCM will enter into force six months after 30 states have ratified it. It grants to affected states 10 years to clear their own territories of cluster bombs. However, it is important to point out that the Convention itself cannot solve anything: it is merely a tool for solving the problems related to cluster bombs for affected people and states in the longer term. One prerequisite for solving the problem of cluster contamination is identifying and understanding the nature of the issue. Without data collection on affected communities, assessment of the number of people and communities threatened by cluster munitions, how they live with the threat, how they earn a living and how the threat affects them, and without collecting and systematizing this information, it is not possible to solve the problems of the individual communities or the states affected by cluster munitions. Systematic and efficient removal of unexploded cluster submunitions remaining after the activities of NATO forces on the territory of Serbia depends on a clear understanding of the level of hazard and socio-economic impacts of the problem today. These issues had not been sufficiently investigated previously, and the reliability of earlier assessments was not acceptable to the Mine Action Centre of the Republic of Serbia. This meant that conditions have not been in place for the preparation of a comprehensive strategy for dealing with this problem. The NPA started planning the general survey of areas suspected to be contaminated with cluster munitions in Serbia at the end of 2006. The Standard Operation Procedures were drafted by NPA Mine Action Programme Manager in Bosnia and Herzegovina Darvin Lisica, and project implementation started in Novem-

12

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

ber 2007. The project has been planned, implemented and monitored in a regional co-operation involving the NPA humanitarian mine action programme in Bosnia-Herzegovina, the Serbian Mine Action Centre, and the NPA regional office for southeast Europe in Belgrade. The project had three phases: (1) project preparation, (2) preliminary assessment of the situation regarding unexploded cluster submunitions, and (3) on-the-ground survey and general assessment of areas of cluster ordnance deployment. The preparatory phase started at the end of 2006 and lasted until project implementation began in November 2007. Work in this phase included preparing project documents, drafting standard operating procedures for the general survey, selection of personnel and their material and professional preparations, and accreditation with the Mine Action Centre of the Republic of Serbia. Phase two, preliminary assessment of the situation related to areas contaminated with unexploded cluster submunitions, lasted from the beginning of the project in November 2007 until mid-February of 2008. It started with logistical preparations and seven-day training of personnel. During this phase, the first part of the general survey was completed identification of areas suspected to contain unexploded cluster submunitions. During this period the team entered into the database a total of 1,241 records of data collected and 1,039 records of data assessed, which served as the basis for the later field activities of the general survey. Phase three, survey in the field and general assessment of the situation of unexploded cluster submunitions in Serbia, lasted from mid-February till mid-November 2008. The office was relocated from id in northern Serbia to Mladenovac in central Serbia in order to obtain better operating conditions, closer to the areas of cluster ordnance deployment. During this phase, the work of survey teams focused on surveying suspected areas, in line with the priorities of the Mine Action Centre. This phase included the collection of additional data in the field, measuring of hazardous areas, risk assessment, as well as cancelling from the list of suspected areas land that was found beyond any doubt not to contain any unexploded cluster submunitions. A general assessment provides necessary input to the strategic as well as operational planning of activities leading to the elimination of unexploded cluster submunitions. It enables the relevant authorities to make informed choices regarding priority setting, so that, for example, areas where cluster munitions pose a real risk to the local population are given priority over remote, uninhabitated areas. Without data on the nature and scope of the hazard posed by cluster munitions it is not possible to set the right priorities, as long as the baseline data for priority setting are lacking. As such, a general assessment is a necessary precondition for efficient use of limited resources for clearance. A general assessment also facilitates good communication between operators and donors, as it provides baseline data on the nature and scope of the risk. Such information is critical to relevant state institutions as well as to other stakeholders, for solving the problem in a cost-effective and timely manner. As such, the general assessment facilitates a clearer selection of priorities and hence efficient clearance, better communication with donors and international organizations, and provides baseline data on the scope of the problem, so that progress can be measured and reports related to commitments to relevant international agreements can be produced. The general assessment includes an evaluation of the hazard of unexploded cluster submunitions and an assessment of their socio-economic impacts. Continuation of the general survey to accompany the clearance process is necessary, so that the remaining suspected areas can be analysed in detail and the necessary documents be prepared. Continuation of the project has been secured in 2009, with funds from the US State Department

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

13

through the International Trust Fund for Demining and Victims Assistance. With greater interest on the part of all stakeholders for resolving the unexploded cluster submunitions problem in Serbia, the need for prioritizing clearance tasks will also increase. A clear and transparent system for determining priorities should be put in place as part of the national policy of mine action, including uniform prioritization criteria, to be followed by relevant state authorities and other bodies or organizations involved in the process. Regular measures of warning the population and marking suspected areas need to be undertaken, to prevent misperceptions as to the absence or presence of unexploded cluster submunitions. Removal of the threat is the only long-term solution to the problem. That will produce the following results: (1) increase in general safety, (2) reduction of risk, especially for people living in contact with risk areas, (3) increase in the number of users of land now blocked, as indicated by the employment structure in the threatened local communities. No International Mine Action Standards (IMAS) exist on general survey of areas contaminated with cluster munitions. For state parties to the CCM, surveys must be conducted in order to solve the problems in their respective countries. Without information about the type and character of the threats posed by cluster munitions, it is not possible to make a plan for solving the problem. The CCM specifies that affected states are to have cleared their territories of cluster munitions within ten years of ratifying the Convention. Clearly, there is an urgent need for International Mine Action Standards regulating the survey of areas suspected to be contaminated with cluster munitions. A survey should form the basis for priority setting of clearance of affected areas, and hence is a prerequisite for solving the problem in affected states and territories. It is our hope that the work carried out by the NPA in Serbia can serve as a basis for the development of IMAS standards for cluster survey, thereby providing affected states with this vital tool as soon as possible. Developing instruments for monitoring in connection with the Convention on Cluster Munitions represents a challenge regarding the compliance of state parties to the Convention. One basis for a future monitoring system could be provided by the experience gained by the International Campaign to Ban Landmines related to monitoring compliance with the Mine Ban Treaty through the yearly publication Landmine Monitor. However, that monitoring system relates to antipersonnel landmines and not cluster munitions, and is as such not compatible with the requirements of the CCM. We hope that the concept and indicators developed by the NPA in this report may prove useful in the process of developing a monitoring system for states affected by cluster munitions, and their compliance to the Convention. This relates particularly to defining the scope of the problem in affected states, as a baseline for measuring progress in munitions clearance. Finally, a note to the reader: this General Survey Report is intended for various target groups. We hope and expect that it will be of interest to practitioners on the ground in affected areas, as well as to national mine action authorities, donors, academics, journalists, policy-makers and others. The report is of technical character that lies in the nature of the matter. On the other hand, we do not foresee that the technical form of the report should be a challenge to readers less familiar with the terminology or the methodology used. Work on a general survey is necessarily of a technical character, involving the development of standard operating procedures and their implementation. We believe that practitioners or operators can learn from the work done in Serbia, so we have chosen to publish the survey report in its present technical form. Practitioners, including operators and mine action authorities like national mine action centres, might

14

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

want to focus on the Terms of reference and methodology (16-24) and the chapter General assessment of the situation of unexploded cluster munitions in Serbia (24-39). Furthermore, this group of readers might find useful the section on Project quality management (63-69). Donors and policy-makers may be especially interested in Social and economic impact of unexploded cluster munitions (39-41) and Reports on general survey of risk areas (50-62). Journalists will probably find the chapter on Social and economic impact of unexploded cluster munitions (39-49) of greatest relevance!

Belgrade, February 2009 Emil Jeremi Regional Director

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

15

Terms of reference and methodology

rganized activities related to the clearance of mines and explosive remnants of war in the Republic of Serbia have been underway since 2001. The focus has been on systemic solutions to the problem of minefields in the border area with the Republic of Croatia, in order to heighten security, promote cross-border mobility and prevent illegal cross-border activities. Most of these priority activities regarding mine clearance have now been realized, so the state authorities of the Republic of Serbia may be expected to shift the focus of mine action to the removal of other types of explosive remnants of war primarily the clearance of areas contaminated by unexploded cluster submunitions. The systematic and efficient removal of unexploded cluster submunitions remaining after the activities of NATO forces in the territory of Serbia depends on adequate understanding of the level of hazard and social/economic impacts of the problem today. These issues had not been sufficiently investigated, and the reliability of previous assessments was not acceptable to the Mine Action Centre of the Republic of Serbia.1 Consequently, the conditions have not been in place for the preparation of a comprehensive strategy for dealing with this problem. In 2007, Norwegian Peoples Aid (NPA) took on the task of performing a survey and assessing the situation related to remaining cluster submunitions in Serbia. The terms of reference were accepted in October 2007, and the financial assistance was provided by the Royal Norwegian Ministry of Foreign Affairs.

Terms of reference
The Cluster Survey Project in Serbia was carried out between 9 November 2007 and 30 November 2008. The long-term objectives were to create a secure environment for the local population, free of hazards of unexploded cluster submunitions; to assist the Mine Action Centre and the Government of the Republic of Serbia in defining the scale of the problem, identifying contaminated areas; and to assist in capacity building to enable the Mine Action Centre to manage the operations of surveying and clearing the areas contaminated by unexploded cluster submunitions. The immediate objective of the project was to prepare a general assessment of the situation regarding unexploded cluster submunitions including the identification of areas suspected of cluster submunitions hazard, collecting data in the field, performing risk assessment and preparation of project documents for the operations of clearing, reducing or marking of hazardous areas. It was undertaken as a project of regional cooperation in Southeast Europe. The NPA Mine Action Programme in Bosnia and Herzegovina agreed to take on responsibility for this project due to its many years of
1 A similar survey has not been planned for the territory of Kososvo, where the removal of landmines and other unexploded ordnance is under the purview of the UNMIK and not the Mine Action Centre of the Republic of Serbia.

16

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

experience in general surveying. This programme has supported the activities of the Mine Action Centre in Bosnia and Herzegovina with seven survey teams with capacity for general surveying of areas contaminated with mines and explosive remnants of war (ERW) since 2005. Realization of the project included personnel from Bosnia and Herzegovina and Serbia. Ten persons were directly engaged. In addition to the project manager, from the NPA Mine Action Programme in Bosnia and Herzegovina four surveyors with several years of experience were selected to serve as survey team leaders. An additional six persons were employed in Serbia: a liaison assistant for threatened communities, a logistician and 4 surveyors with no previous experience in general surveying.

FIGURE 1
Regional Director for Southeast Europe

Organizational structure

Finanace and Administration: Regional Office Southeastern Europe: (Serbia)

Mine Action Program Manager in Bosnia and Herzegovina (Bosnia and Herzegovina)

Logistics officer (Serbia)

Database Consultant (Serbia)

Project Manager / Operation Manager (Bosnia and Herzegovina)

Monitoring Team: Operations Manager and Planning and reporting officer (Bosnia and Herzegovina)

Project Manager Assisstant for liaison with the community (Serbia)

Leader of Survey Team 1 (Bosnia and Herzegovina) Surveyor (Serbia)

Leader of Survey Team 2 (Bosnia and Herzegovina) Surveyor (Serbia)

Leader of Survey Team 3 (Bosnia and Herzegovina) Surveyor (Serbia)

Leader of Survey Team 4 (Bosnia and Herzegovina) Surveyor (Serbia)

Monitoring of all activities was carried out by the Demining Programme Manager, along with the monitoring team and under the supervision of the NPA Regional Director for Southeastern Europe. The Monitoring Team consisted of the operations manager and the planning/ reporting officer from the NPA Mine Action Programme in Bosnia and Herzegovina, all with experience in managing survey projects and quality management. Logistics and financial assistance to the project were arranged through the NPA Regional Office in Belgrade. A consultant for the general survey database was also engaged in Serbia. The project had three phases: (1) project preparation, (2) preliminary assessment of the situation regarding unexploded cluster submunitions in Serbia, and (3) on-the-ground survey and general assessment of the situation of unexploded cluster submunitions in Serbia.

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

17

The preparatory phase started at the end of 2006 and lasted until the actual project began in November 2007. Work in this phase included preparing project documents, drafting standard operating procedures (SOPs) for the general survey of the area of cluster ordnance deployment, selection of personnel and their material and professional preparations, and accreditation with the Mine Action Centre of the Republic of Serbia. In addition, cooperation was also arranged with the Serbian Ministry of Defence Civilian Defence Sector, municipal authorities and representatives of communities at risk. Phase two, preliminary assessment of the situation related to unexploded cluster submunitions, lasted from the beginning of the project in November 2007 until mid-February of 2008. It started with logistical preparations and seven-day training of personnel. Logistical preparations included transport of vehicles and some of the equipment from Bosnia and Herzegovina and procurement of the remaining equipment in Serbia, and establishing an office in the territory of Serbia, in id. The seven-day training of personnel focused on cluster submunitions information, survey methodology according to approved SOPs, use of measurement instruments in the field, and data processing and work on the database. During this phase, the first part of general survey was completed identification of areas suspected to contain unexploded cluster submunitions. This work started on 10 December 2007 and lasted until 7 February 2008. This meant 34 working days in all: six days for processing the available data, 19 days for collecting additional data in the field by questionnaires and mapping, and nine days for data analysis and preparing the preliminary assessment. During this period the team entered into the database a total of 1,241 records of data collected and 1,039 records of data assessed, which served as the basis for the later field activities of the general survey. Phase three survey in the field and general assessment of the situation of unexploded cluster submunitions in Serbia lasted from mid-February till mid-November 2008. The office was relocated from id to Mladenovac in order to obtain better operating conditions. During this last phase the work of survey teams focused on surveying suspected areas, in line with the priorities of the Mine Action Centre of the Republic of Serbia. This phase included the collection of additional data in the field, measuring of hazardous areas, risk assessment, deleting from the suspected areas list land that was found beyond any doubt not to present a danger of unexploded cluster submunitions, report preparation, data mapping, and entering data into the database. Sufficient levels of accuracy and quantity of data were ensured for the detailed risk assessment from the micro-location level to the general assessment of the situation of unexploded cluster submunitions in Serbia (excluding Kosovo). The results obtained were entered into the database. On the basis of such data, clearance tasks will be planned and strategic assumptions and indicators determined: thus favourable conditions will be created for efficient future operations and strategic planning under the Mine Action Centre of the Republic of Serbia.

Standard operating procedures


General survey of locations with unexploded cluster submunitions involves a process of assessment of hazard, extent, form and characteristics of suspected areas, from the level of micro-locations to general assessment at the national level. This assessment was based on data collection and process-

18

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

ing and identifying hazards of unexNormative framework of standard operating procedures for general ploded cluster submunitions, without survey of the areas affected by cluster ordnances: applying technical methods for their 1) ISO 9001:2000, Quality Management Systems Requirements removal. The objective of general sur2) ISO 9004:2000, Guidelines for Performance Improvements vey is to identify the level of priorities 3) ISO 14001:1996, Environmental Management Systems and operating conditions necessary 4) ISO/IEC 51:1999, Safety Aspects Guidelines for their inclusion for the successful planning and orgain standards nizing of the removal of unexploded 5) AS/NZS 4360:1999, Risk Management cluster submunitions through hazard 6) IMAS 04.10:2003, Glossary of Mine Action Terms, Definitions and assessment and environmental impact Abbreviations assessment. This involved the follow7) IMAS 10.10:2001, Safety and Occupational Health ing elements: (1) collecting, sorting 8) IMAS 08.10:2003, General Mine Action Assessment and processing available data on identified suspected locations and supplementing the database as necessary; (2) carrying out the previous assessment of scope and impact of the problem related to the remaining cluster submunitions for the country and individual local communities; (3) planning, organizing and implementing the field collection of new data, performing hazard assessment and identifying priorities for clearance and all other activities to reduce the risk of unexploded cluster submunitions; (4) preparing project documents for clearance and other activities to reduce the risk of unexploded cluster submunitions; and (5) enabling more precise short-term and long-term planning in terms of time periods and scheduling. Standard operating procedures for general survey are formed as a process-oriented activity based on the requirements of the beneficiaries vulnerable individuals and groups, as well as potential users of land that is contaminated or suspected of being contaminated by unexploded cluster submunitions. The basic process of general survey of areas of cluster ordnance deployment consists of three sub-processes: (1) identification of areas suspected of cluster ordnance hazards, (2) on-site activities of general survey, and (3) risk assessment and project design. Collecting and Identification of areas suspected of cluster ordnance processing data hazards is the first sub-process of general survey, during in field which all available data are analysed, without any additional field collection of data. Hazard is assessed from the levels of local communities to the general hazard assessment for the country. At the local community level, the perimeters, area and other characteristics of suspected areas are defined, for later use in the preparation and organization of general survey field activities. In addition, these data, statistically processed and sorted by higherlevel administrative areas, are used to complement the general assessment of mine action. Identification of areas suspected of cluster ordnance hazard involves six process steps: (1) collection and processing of available data, (2) sorting the documents collected, estimating their quality and entering them into the database, (3)

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

19

classifying information by micro-location and mapping, (4) comparative analysis of data and the reconstruction of cluster-ordnance deployment zones, (5) mapping the areas suspected of cluster ordnance hazards, and (6) monitoring of process and results. Field activities are the second sub-process of general survey. The collection and processing of missing data is performed as well as detailed measurements related to the area where a hazard of unexploded cluster submunitions has been identified. This work is performed at each individual location by the survey team, in line with the priorities and plan of the national mine action body. It consists of five process steps: (1) analysis of missing data, (2) preparation for field visits, (3) collecting data in the field and control of their quality, (4) corections of deployment zone and cancellation of hazard-free land from the list of suspected areas, and (5) topographic measurements at hazardous locations. Risk assessment of unexploded cluster submunitions and preparing terms of reference for clearance (including technical survey and marking) constitutes the third sub-process of the general survey. The scale of the problem is assessed (risk magnitude), as well as the priorities and plan for managing the risk at given locations contaminated by unexploded cluster submunitions. This involves four process steps: (1) identification and characterization of affected population groups, (2) risk evaluation and priority-setting, (3) assessment of operating conditions for clearing risk areas, and (4) preparing clearance tasks for risk areas. The results of the general survey process represent input for the process of risk management, which may involve clearance, reduction, marking of contaminated area or/and education of the local population. The results of the risk management process, like the satisfaction of direct and indirect users of the land released to them for use, will depend on the quality of general survey management, the quality of its results and the selection of priorities. The flow chart of the general survey process (see Figure 2) shows that normative requirements in these SOPs are maximized, with clear inputs and outputs from the sub-process and process steps. This was necessary to enable testing the quality of the process, including the objective and subjective capacities of the survey teams. It is also a flexible process that can be used for surveys elsewhere, whether in its entirety or in individual sub-processes and process steps. Testing during the survey in Serbia confirmed its applicability and contributed to improving the final version of SOPs accepted by the Mine Action Centre as relevant for future general survey activities in Serbia.

Database
Data collected during the general survey are kept in three model data repositories: (1) the archives, where all collected and generated documents are sorted by basic administrative units, and within them, by data type; (2) the relational database, where all data on surveyed risk areas are organized in a manner that provides for easier manipulation of the data, generation of necessary reports and creation of terms of reference for clearance; (3) the file-based data repository, where geo-coded spatial data are kept in files easy to view and process with software intended for manipulating spatial data. The archives consists of data collected and reports on the general survey of the area where cluster ordnance was deployed. The total number of reports on accidents collected is 24, number of reports on military and police removal is 23, there are 13 reports on clearance and found cluster ordnance, and 76

20

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

FIGURE 2
Identification of areas suspected of cluster ordnance hazard Available data collecting and processing Sorting collected documents, their quality assurance and entering into database Classification of information per microlocations and mapping Data comparative analysis and reconstruction of deployment zones GPS data on cluster ordnance deployment, database and archives, data from local communities, previous surveys, data from armed forces, police and civil defence, data from other sources

Map of situation with cluster submunition remnants Area not suspected General assessment of the situation with remnants of cluster submunitions

Suspected area identification criteria


Yes

No

Mapping the areas suspected of cluster ordnance hazard

Suspected area

Database of areas suspected of cluster ordnance hazard

Process and results monitoring

General survey field activities Missing data analysis

Preparation for field visits Interview report, questionnaire, data collected by observation (photographs, drawings, descriptions)

Collecting data in the field and quality control of these data Corections of deoloyment zones and cancelling suspected areas

Criteria for cancelling suspected areas


Yes

No

Cancelled area

Topographic measurement at hazardous locations

Risk area

Risk assessment and creating terms of reference Identification and characterisation of affected population groups Priority list

Risk estimation and priority setting General survey report General survey database Project task for clearance Clearance database

Assessment of operating conditions for clearance of risk areas

Producing clearance tasks for risk areas

Project for donors

Start of clearance of cluster submunitions risk areas

questionnaires. The archives contain 100 survey reports, along with accompanying documents, maps and cadastral maps of areas intended for clearing unexploded cluster submunitions, photographs of markings emplaced and risk areas, interviews, etc.

Flow Chart: Process of general survey of cluster-ordnance deployment areas

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

21

The logics of SOPs was incorporated into the relational database. The data flow chart (see Figure 3) for the general survey database presents the procedure of creating clearance tasks for risk areas and entering data into the database. All activities, data and data flows presented in the chart are defined by SOPs. The activity of Hazard Assessment has the input data necessary for hazard assessment: data on incidents and accidents and the consequences thereof, data on cluster-ordnance deployment zones, and estimation of probability of presence of cluster submunitions. These data were entered into the database, and serve as the basis for assessing the level of hazard. Input data for the activity Environmental Impact Assessment are: General Data on Community, Data on Deployment Impact, Data on Level of Threat to Population, and Data on Potential Benefits after Clearance. The level of environmental impact is assessed on the basis of these data. The activity Priority Identification has input data that are the outputs of the previous two activities: Level of Hazard in Risk Area and Level of Environmental Impact. On the basis of these inputs, the priority level is identified. Assessment of Operating Conditions involves the input data on soil properties, on climate conditions, on liaison officers, and descriptions of the risk area. The activity Assessment of Additional Activities employs input data generated by previous activities: priority level, data on accidents/victims and assessment of the need for additional activities. The data generated in previous activities are used for preparing the necessary reports. All data necessary for statistical analyses, generation of survey reports and preparation of project documents for unexploded cluster submunitions clearance are contained in the relational database.

FIGURE 3
SOP Data on accidents/victims Data on cluster ordnance deployment zone Data on removing cluster ordnance Estimation of probability of presence of cluster ordnance

HAZARD ASSESSMENT A1

Hazard assessment data Hazard level in risk area

Environmental impact data

Data base on general survey of cluster ordnance deployment area

General data on the community Data on deployment impact Estimation of threat to population Estimation of potential benefits

ENVIRONMENT AL IMPACT ASSESSMENT A2

Data on victims Level of environmental impact Data on additional activities Data on priority level

IDENTIFICATIO N OF PRIORITY LEVEL A3


Priority level

Data on operating conditions Data on additional activities Data on priority level

Soil properties Climate conditions Data on liaison officers Risk area description

OPERATING CONDITIONS ASSESSMENT A4

Data on operating conditions

Data on environmental impact

Data on hazard assessment

ADDITIONAL ACTIVITIES
Assessment of need for additional activities

A5

REPORT GENERATION
DBMS

Report on GS Clearance Project Clearance tasks

A6

Data Flow Chart for General Survey Database

22

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

Large items, like photographs, are referenced within the base by hyperlinks. They are then placed in a folder with accompanying documents, for practical reasons. The file-based repository stores spatial data, as well as geo-coded topographic and cadastral maps of the locations where the survey was performed. The data in this repository may be classified as raster data and vector data. The raster data are: geo-coded topographic maps at the scale of 1:25,000, cadastral maps at the scale of 1:1,000, and geographic maps of Serbia at the scales of 1:200,000 and 1:300,000. Topographic and cadastral maps are geo-coded only for the area of the locations under survey. The vector data consist of geo-coded spatial data collected or generated during the general survey. The files represent the entities that, in addition to geographic location, have some other defining attributes. In total, the files contain 30,114 entered data describing the entities. (See Table 1.)

TABLE 1
Entity Number of Attributes Number of Records Number of Data Entriesered

Military and police clearance Accidents Depleted uranium NATO GIS cluster 4 GIS cluster 3 Original data GIS cluster 2 GIS cluster 1 Clearance found Clearance Questionnaire suspected area Questionnaire ERW Excluded area Assessed Data Settlement Suspected area Deployment zone Risk area Operating Data Access road Marking Incidents Total

7 13 8 13 15 16 13 9 12 9 9 9 8 10 13 14 6 10 13
207

23 24 11 217 312 48 143 211 13 120 123 600 72 392 105 100 32 168 50
2,764

161 312 88 2,821 4,680 768 1,859 1,899 156 1,080 1,107 5,400 576 3,920 1,365 1,400 192 1.680 650
30,114

Geo-coded entities

The original and assessed data are the geo-coded input data collected during the first sub-process of the general survey (identification of areas suspected of cluster ordnance hazard), supplemented during the ensuing sub-processes. The original data are geo-coded data obtained from the data source of the general survey, whereas the assessed data are the result of the work of general survey teams evaluating the location and characteristics of cluster-ordnance deployment zones and suspected areas. The operating data class includes the geo-coded data on risk areas, access lanes and installed signs warning of the immediate proximity of areas suspected of unexploded cluster submunitions hazard!

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

23

4
T
FIGURE 4
Position of the general assessment of the situation in planning for clearance of areas contaminated by unexploded ordnance in the Mine Action Centre of the Republic of Serbia Model

General assessment of the situation of unexploded cluster submunitions in Serbia

he objective of the situation assessment is to provide as exact as possible a picture of the consequences of cluster ordnance deployment in the territory of Serbia. The general assessment enables the following: successful strategic and operational planning of the activities leading to the elimination of unexploded cluster submunitions; clearer selection of priorities and efficient clearance; better communication with donors and international organizations; status updating and information on observing the commitments undertaken by international agreements.

GENERAL ASSESSMENT OF THE SITUATION WITH UNEXPLODED CLUSTER SUBMUNITIONS IN SERBIA

HAZARD ASSESSMENT

GENERAL SURVEY

NEEDS OF AFFECTED COMMUNITIES IN SERBIA

ASSESSMENT OF SOCIAL AND ECONOMIC IMPACT

PREPARING CLEARANCE TASKS FOR RISK AREAS

SELECTION OF CLEARANCE PRIORITIES GOVERNMENT OF THE REPUBLIC OF SERBIA

INTERNATIONAL AGREEMENTS

STRATEGIC PLANNING

CLEARANCE OPERATING PLAN

CLEARANCE OF AREAS CONTAMINATED BY UNEXPLODED CLUSTER SUBMUNITIONS

The general assessment includes an evaluation of the hazard of unexploded cluster submunitions and an assessment of their social and economic impacts. Along with the appraisal of operating capacities for clearance it forms the general assessment for actions against landmines and other explosive remnants of war, including cluster submunitions. International mine action standards set such an assessment as a requirement to be met by affected countries.1
1 Requirements under International Mine Action Standards, IMAS 08.10:2003, General Mine Action Assessment, http://www.mineactionstandards.org/IMAS_archive/Final/ IMAS_0810.pdf.

24

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

Unexploded cluster submunition hazard in Serbia


In considering its problems with unexploded ordnance, a affected country starts with hazard assessment. The task of this assessment is to identify the cause of the problem through its manifestations in the field, then to identify hazardous areas and all related circumstances where people, property or the environment may be exposed to hazard. The assessment of hazard related to unexploded cluster submunitions in Serbia included the following: identification and reconstruction of cluster-ordnance deployment zones, assessment of the extent and characteristics of hazardous areas, estimation of the hazard level and assessment of risk areas for clearance. The assessment of the extent and characteristics of hazardous areas was carried out at two qualitatively different levels. It included an assessment Cluster submunition found in of suspected areas and the assessment of Sjenica risk areas for clearance. Suspected areas are those for which, from the analysis of available information, there are clear indications or reasonable suspicion of the presence of unexploded ordnance. The number, quality and accuracy of the defined characteristics of the suspected areas are selected in such a manner so as to enable an objective assessment of the hazard, from the level of the affected community to the level of the entire country. This area is the smallest unit for planning the tasks of the general survey during which additional collection of data and identification of risk areas for clearance took place. The survey of risk areas is undertaken in line with the priorities of the state authorities. For each individual risk area, the hazard of explosive ordnance was assessed, detailed measurements were carried out, soil properties and operating conditions for clearance were identified, and the current negative impact and potential benefits for the land after removal of the hazard of unexploded cluster submunitions were evaluated. An assessment of suspected areas was carried out for the territory of Serbia, except for Kosovo, where mine and ERW clearance lies under the purview of UNMIK. In February 2008, the preliminary hazard assessment was performed, as a necessary first step in general survey activities. November 2008 saw the completion of the assessment of the hazard of unexploded cluster submunitions in Serbia, aimed at enabling efficient strategic and operational planning, a transparent system for priority identification, and assisting the Serbian state authorities in presenting the problem more clearly to donors and relevant international organizations.

Unexploded cluster submunitions as cause of hazard


Identification and reconstruction of cluster-ordnance deployment zones were carried out based on the data obtained from available sources, and by collecting and verifying data in the field. The state authorities of the Republic of Serbia had received some data on the areas of cluster ordnance deployment from NATO Headquarters. However, the data on deployment zones proved incomplete, containing only the coordinates of the deployment locations and the number of ordnances deployed, without any particulars as to which type(s)

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

25

MAP 1

Areas of cluster ordnance deployment, according to data received from NATO

26

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

of ordnance had been used. Data were submitted for 217 deployment zones, as follows: 142 deployment zones in Kosovo, 3 deployment zones in Vojvodina and 70 deployment zones in central Serbia. (See Map 1.) The coordinates for two deployment zones were outside the territory of Serbia. The Serbian Mine Action Centre provided data on previous surveys and records of earlier clearances, and prepared the terms of reference. Data on accidents and incidents caused by cluster submunitions were also used as a source for identifying deployment zones.1

TABLE 2
Dispenser Cluster Ordnance Type Submunitions Type Diameter (m) Length (m) Mass (kg) Cluster Submunitions Quantity per Bomb Failure Rate Failure Rate per Manufacturer % Average Empirical Failure Rate % Maximum Expected Failure Rate (%)

AGM-154/A CBU-87/B CBU-94 CBU 99 A/B BL 755

BLU 97 BLU - 97 A/B BLU - 114/B Mk - 118 MK1, MK4

2,698 0,397 0,406 0,42

4,07 2,33 2,06 2,45

484 430 460 264

154 202 166 247 147

5,00% 5,00% 5,00% 5,00% 5,00% 11,80% 8,00%

30,00% 30,00% 30,00% 30,00% 30,00%

All these data were not sufficient for the reconstruction of deployment zones, so the survey teams of the NPA had to perform additional field collection and verification through questionnaires and on-site visits. The teams collected data by filling in questionnaires for each affected municipality and by visiting 76 cluster-ordnance deployment areas in order to get an overview of the situation. On the basis of available data and time-constrained field activities, the survey teams were able to reconstruct the location and extent of deployment zones, identify which cluster ordnance had been used and in which numbers, and estimate the quantity of unexploded cluster submunitions. At that time it was estimated that NATO forces had deployed five types of cluster bomb units with a total of seven types of cluster submunitions. It was assessed that there were a maximum of 177 deployment zones, in which 298 cluster bomb units were used. A more detailed assessment of Parts of cluster submunideployment zone characteristics was tions found in carried out in the second phase of Kurumlija the general survey. After new data had been collected and existing data had been verified in the field, it was possible to cancel 98 deployment zones, since they were found to be deployment zones not of cluster ordnance, but of other bombs or cluster ordnance without explosive
1 Data on incidents and accidents from the study prepared by the Norwegian Peoples Aid on the consequences of NATO activities in the territory of the Federal Republic of Yugoslavia in 1999. Yellow Killers were a starting point for identifying locations of cluster submunitions deployment.

Cluster ordnance deployed by NATO forces in the Republic of Serbia

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

27

payloads. Furthermore, during the general survey field activities, 26 new deployment zones were identified. The latest results of the general survey show that, in all, 105 cluster-ordnance deployment zones have been located in the territory of Serbia, in 15 municipalities. In these deployment zones, 196 cluster bomb units were used, containing 37,032 pieces of cluster submunitions. (See Table 3.)

TABLE 3
Cluster Ordnance Type Number of Identified Deployment Zones Number of Ordnance Projected Munitions Type Number of Munitions Projected Assessed Number of Unexploded Cluster Submunitions

AGM 154/A CBU 87 CBU 87 CBU 99 RBL 755 RBL 755

4 61 9 5 2 24
105

6 82 42 14 2 50
196

BLU 97 BLU 97 BLU 97 A/B Mk-118 Mk-1 Mk-4

882 16,564 8,484 3,458 294 7,350


37,032

112 1,061 644 290 21 419


2,547

Estimate of the number of cluster ordnance used Immediately after deployment, the cluster submunitions and bomb remnants were coland remaining unexploded cluster lected by military, police and civil defence units. However, records on the removal of unexsubmunitions

ploded ordnance were not available to the survey teams of the NPA. By collecting additional data in the field, the survey teams found that removal by military and police forces had been undertaken at 24 locations, and that approximately 990 pieces of unexploded cluster submunitions of various types had been removed from these locations. Although this removal operation certainly reduced the probability of casualties, the hazard has remained: local farmers have since come across more cluster submunitions and remnants of cluster bombs. Thus it may be assumed that the collection of unexploded ordnance was undertaken in haste, mostly of unexploded ordnance visible on the surface, without applying international standards for ERW clearance. Most ordnance was collected in 1999. Since then, it has mainly been a case of spot clearance of unexploded ordnance, as reported by civilians. Clearance operations carried out in line with international standards are now underway, supervised by the Serbian Mine Action Centre. During the clearance operations 226 pieces of unexploded cluster submunitions were removed and destroyed, 56.19% of which were found on the surface, and 43.81% at depths of 10 to 50 cm. The survey teams assessed the remaining unexploded cluster submunitions for each deployment zone separately, taking into account the assessment of the failure rate and the data on removal of cluster submunitions to date. It is estimated that there are still 2,547 pieces of unexploded cluster submunitions scattered in 105 deployment zones, which means an average of 24.06 pieces of cluster submunitions per deployment zone. The largest number of unexploded cluster submunitions in the territory of Serbia has been identified in Ni and in six municipalities in the south of the country. It has been assessed that in the territory of the Ni municipality of Crveni Krst there are 800 pieces, or

28

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

31.41% of the total amount of unexploded cluster submunitions. For the municipalities of Bujanovac, Kurumlija, Preevo, Sjenica, Kraljevo and Brus, it has been assessed that there are 1,424 pieces, or 55.91% of the total amount of unexploded cluster submunitions. The remaining unexploded cluster submunitions are located in the territories of eight other municipalities.

TABLE 4
Assessed Number of Unexploded Submunitions Pieces %

Municipality

Number of Zones

Number of Cluster Ordnance Projected

Kni Raka Sopot Leposavi Vladimirci Stara Pazova Gadin Han Mediana Brus Kraljevo Sjenica Preevo Bujanovac Kurumljija Crveni Krst
Total

2 2 1 2 1 1 1 6 10 13 11 12 14 13 16
105

2 2 1 2 2 2 1 6 10 13 11 16 36 34 58
196

24 30 32 35 42 46 50 64 116 141 155 192 302 518 800


2547

0.94% 1.18% 1.26% 1.37% 1.65% 1.81% 1.96% 2.51% 4.55% 5.54% 6.09% 7.54% 11.86% 20.34% 31.41%
100.00%

Assessment of extent and characteristics of suspected areas


Suspected Areas: Status at the Beginning of Survey operations
The characteristics of the suspected areas1 were assessed on the basis of the reconstructed deployment zones, other data collected, and sketch drawings made by the survey teams during field visits. Each suspected area is a vector polygon with its perimeters defined in the map on the scale of 1:25,000. The perimeters of each suspected area were defined on the basis of the assessed hazard level, land-use, and topographic characteristics of the land. During December 2007 and January 2008, NPA survey teams processed and entered into the database drawings of 790 sites with a total area of 77.13 km2. Areas with graphite munitions deployment are not considered to be a hazard for the population. There were a total of 60 such identified sites, with an overall area of 7.02 km2. Accordingly, it was assessed that 720 sites are suspected of unexploded cluster submunitions hazard, some 70.11 km2 in total. Suspected areas were classified into five hazard levels: extremely high hazard (7 suspected areas), very high hazard (15), high hazard (154), middle hazard (307) and low hazard (247).
1 Suspected area characteristics: suspected area parameters, suspected area extent, being part of a certain administrative unit, level of hazard and intended use of land. The hazard level is identified in line with the matrix provided in the General Survey Standard Operating Procedures. The intended use of land indicates which resources are blocked, identified on the basis of the classification system of land use approved by the Serbian Mine Action Centre.

Cluster submunitions, quantity per municipality

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

29

MAP 2

Distribution of cluster-ordnance deployment zones in the territory of Serbia (without Kosovo)

30

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

The initial status of the suspectUrgent marking sings ed area changed during the generinstalled on acces road to al survey field activities carried out suspected area from February till November 2008. Changes in the shape and number of polygons and the extent and characteristics of the suspected areas resulted from adjustments and more precise defining of the characteristics of the deployment zone, or a higher number of smaller suspected areas due to a more precise definition of their characteristics. However, their extent did not exceed the number of 937 polygons and the area of 78.1 km2. This is the largest possible suspected area identified in Serbia for remnants of cluster submunitions, prior to any cancellation of the land due to additional new data.

Procedure and Results of Exclusion of Suspected Areas through Land Cancellation


During the field part of the survey, which was the second sub-process of the general survey, the teams assessed all the data collected, the situation on the ground and the defined risk areas. These data were compared with the initial assessment of the suspected area in the cluster-ordnance deployment zone under survey. The survey teams focused on the following questions: (1) Whether the data collected during the field visit confirm the previously collected data, or if they are different, and why; (2) To which extent the data collected influence the accuracy of the previous assessment of the deployment zone characteristics and whether it is possible to carry out correction of the deployment zone, (3) To which extent the data collected influence the characteristics of the suspected areas in the deployment zone, and which of the characteristics may be changed; (4) Whether a part of the suspected area may be cancelled (i.e. removed from the list of suspected hazard sites) due to change in the deployment zone characteristics or use of the land. The collection of new data and the checking of facts resulted in a more accurate assessment of the situation in the micro-location under survey. The survey teams were able to assess more objectively the position and characteristics of the adjacent suspected areas. Such assessments generally led to the cancellation of certain parts of the suspected areas, as it could be positively determined that they presented no hazard. The re-assessment of the deployment zone and its suspected areas was undertaken in the manner described in the sub-process of identifying areas suspected of hazards of cluster ordnance. Land was cancelled if one of the criteria for the cancellation of land from the area suspected of cluster ordnance hazard was met.1 The land thus cancelled was deleted from the records in the database for the relevant suspected area and, using identical perimeters, was entered into the database of cancelled land. This enabled monitoring of the timeframe and control of the land cancellation procedure. In the period from February to November 2008, cancellation of land from the suspected area was undertaken in 593 cases. The size of the areas cancelled was 47.4 km2, or 60.67% of the area previously
1 See Appendix B: Criteria for cancellation of land from area suspected of cluster ordnance hazards, 82. page

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

31

defined as suspected. In the greatest number of cases, 282, land was cancelled because only graphite munitions had been used, or other types of air ordnance that do not carry cluster munitions (Criterion C9). Such data were specially processed so as to enable any hazard of ordnance to be removed by methods different from clearing unexploded cluster submunitions. The total size of the cancelled area, under this criterion, was 24.5 km2. The second largest cancelled area (14.6 km2) was directly related to a more precise defining of the deployment zone parameters (Criterion C10). Those are areas which are not in use because of suspicion of cluster submunitions on the part of the civilian population, and which are at a distance from the nearest deployment zone of at least half the longer axis, and where no traces of cluster munitions deployment have been found. Cancellation took place in 133 such cases. The third largest cancelled area (7.2 km2) was related to land-use (Criterion C8): farmland outside the deployment zone which had been cultivated for at least two years without finding any traces of cluster munitions deployment. Cancellation was possible in 72 such cases. Cancellations under other criteria were negligible in comparison with those above. The average size of each cancelled area was 0.080 km2.

GRAPH 1
Extent of cancelled area, by cancellation criteria

Cancelled Area (km) 25 20 15 10 5 0 km C1 0.274 C2 0.176 C3 0.011 C4 0.023 C5 0.007 C6 0.505 C7 C8 C9 C10

0.029 7.271 24.526 14.616 Criterion for cancellation of suspected area

The analysis of cancelled area in relation to the hazard and intended use of land confirms earlier assumptions that the rate of land release was in connection with the previously assessed hazard and the intended use of land. In accordance with earlier forecasts, there were most cancellations in connection with suspected areas of low and medium levels of hazard. For suspected areas with low hazard level, there were 187 cancellations (total size 17.5 km2), and for suspected areas of medium hazard level, 211 cancellations (14.4 km2). However, the highest cancellation rate 62.48% was for suspected areas with a high priority level. This is not in line with the previous assumption that the release rates for suspected areas of extremely high, very high and high levels of hazard would be significantly less than for the remaining two, lower, levels. The explanation should be sought in the initial caution exercised by the survey teams: lacking sufficient input data for hazard assessment during the preliminary assessment, they opted for a higher level of hazard in borderline cases. The areas categorized as representing a high level of hazard were mostly located on the outside perimeters of the deployment zone. During the second phase, the survey teams made the relatively largest number of adjustments in relation to these, partly cancelling

32

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

them, and partly lowering their priority level. In 60 cases, a total area of 7 km2 was cancelled since it referred to deployment zones where only graphite submunitions had been used.

GRAPH 2
Area km 35 30 25 20 15 10 28.60% 5 0 Extremely high 4.50% Very high High Medium Cancelled area Remaining suspected area Land release rate 62.48% 55.11%
Analysis of Land release rate (%) cancelled area in 100.00% 100.00% relation to previ90.00% ously assessed 80.00% hazard levels 70.00% 60.00% 58.71% 50.00% 40.00% 30.00% 20.00% 10.00% 0.00% Low Graphite submunitions Previously assesed hazard level

As to the structure of the cancelled land areas, land intended for agriculture, exploitation and maintenance of forests and reconstruction of infrastructure and utility facilities was predominant. Agricultural land (Criterion N11) totalling 19.8 km2 was cancelled in 250 instances; land intended for forest exploitation and maintenance (Criterion N01) totalling 13.3 km2 was cancelled in 165 instances; and land intended for reconstruction of infrastructure of settlements and utility facilities (Criterion N12) totalling 5.8 km2 was cancelled in 69 instances. Important cancellations also took place regarding land intended for the development of tourism (Criterion N02), reconstruction of power distribution system and other electrical power facilities (Criterion N10) and the regulation of rivers and reconstruction of canals and embankments (Criterion N07).

GRAPH 3
100.00% 83.13% 90.65%

Area km 35 30 25 20 15 10

52.17%

65.92%

Cancelled area Renaining suspected area Land release rate

0.00%

0.00%

0 N01 N02

N03

N04

N05

N06

0.00%

N07

N08

N09

Analysis of Land release rate (%) cancelled area 100.00% in relation to 90.00% intended use of land 80.00% 70.00% 60.00% 50.00% 40.00% 30.00% 20.00% 10.00% 0.00% N10 N11 N12 N13 N14 Previously assessed intended use of land

32.01%

48.90%

0.06%

0.37%

14.45%

67.34%

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

33

Suspected Area Contaminated by Cluster Submunitions Status at the Beginning of November 2008
The field activities of the general survey, including the collection of additional data in the field, measurements, recording data and the mapping thereof, were of twofold importance. Firstly, they enabled an evaluation of the situation and the preparation of project documents for risk areas of priority for clearance. Secondly, they ensured sufficient data for a more precise assessment of the total suspected area and its reduction after non-hazardous portions had been cancelled. By early November 2008, general survey field activities were completed. All the results were processed and entered into the database. The database on the total suspected area contains 390 polygons, in all 30.7 km2, with an average size of 0.079 km2. The total suspected area could be reduced in comparison to the initial assessment of February that year for two reasons: (1) reduction in the number of deployment zones after cancellation of non-existent deployment zones of cluster ordnance, and deployment zones of graphite cluster submunitions; and (2) more precise assessment and ensuing cancellation of previously suspected area. The distribution of suspected areas in relation to the level of assessed hazard was as expected. The lowest share consisted of areas categorized as representing an extremely high hazard. Suspected areas assessed as having higher hazard levels (extremely high, very high and high hazard) constituted 21.52% of the total, or 6.6 km2. (See Graphs 4 and 5.) These are areas located within a deployment zone. Such areas are not expected to see any additional significant cancellations as the general survey continues, and they will be treated by measures for clearing unexploded cluster submunitions. The share of higher hazard levels in the total number of 390 suspected areas stands at 17.18 %.

GRAPH 4
Extremely high 0.627 2% Very high 1.139 4% Low 12.366 40% High 4.852 16%

Share in the extent of suspected area per hazard level

Medium 11.766 38%

34

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

GRAPH 5
Number of suspected areas 200 180 160 140 120 100 80 60 40 20 0 0.105 0.110
Number of susAverage magnitude of suspected area km pected areas and 186 0.120

137 0.090 0.063

0.100 0.080

average extent by hazard level

Number of suspected areas Suspected area average magnitude km 6

0.067 44 17

0.060 0.040 0.020 0.000

Extremely high

Very high

High

Medium

Low Hazard level

The hazard of cluster submunitions is not evenly distributed, affecting 28 local communities (mesne zajednice) from 16 different municipalities in Serbia, and a total of 12 out of 30 districts. Currently the largest suspected area is in the districts of Niavski, Zlatiborski and Raki. (See Appendix D: Status of Suspected Areas by Districts, Municipalities and Settlements.).

TABLE 5
Suspected Areas Status Extremely High Municipalities Hazard No. km2 Very High Hazard No. km2 High Hazard No. km
2

Medium Hazard No. km


2

Low Hazard No. km


2

Total No. km2 %

Crveni Krst Sjenica Medijana Kraljevo Kursumlija Brus Stara Pazova Bujanovac Leposavic Knic Presevo Raska Vladimirci Sopot Cacak Gadzin Han

2 1

0.104 0.052

13

1.597

0.190 2 6 1 4 1 0.297 0.271 0.106 0.194 0.115

8 2 8 2 7 1 1 1 1

1.035 0.397 0.646 0.173 0.611 0.118 0.054 0.106 0.115


4.852

0.035

0.209

28 39 67 10 3 9 3 3 7 1 1 3 3 5 4
186

2.658 3.364 2.099 0.393 0.340 0.774 0.228 0.238 0.675 0.092 0.044 0.259 0.116 0.289 0.195
11.766

29 9 19 20 5 6 5 4 17 1 3 7 4 5 3
137

2.115 0.982 1.971 2.989 0.511 0.594 0.828 0.488 0.705 0.003 0.334 0.373 0.242 0.128 0.105
12.366

0.193

72 49 86 30 18 17 10 14 11 21 15 7 12 6 10 8
390

6.474 4.398 4.070 3.382 2.078 1.764 1.353 1.189 1.164 1.077 1.061 0.711 0.658 0.541 0.416 0.415

21.05% 14.30% 13.23% 11.00% 6.76% 5.74% 4.40% 3.87% 3.78% 3.50% 3.45% 2.31% 2.14% 1.76% 1.35% 1.35%

0.627

17

1.139

44

30.751 100.00%

Municipalities affected by unexploded cluster submunitions


Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

35

Part of cluster bomb found in Preevo

Crveni Krst, Sjenica, Medijana and Kraljevo are municipalities with the largest suspected areas, totalling 18.3 km2 in size, or 59.59% of the total current suspected area in Serbia. However, the picture is somewhat different if suspected areas of higher hazard levels (extremely high, very high and high hazard), are taken into account, as 73.93% of such areas (4.8 km2) are located in four municipalities: Crveni Krst, Kurumlija, Preevo and Bujanovac. If a more profound evaluation of the priorities in view of the hazard level is undertaken, it may be concluded that the suspected area of extremely high hazard is recorded only in the municipalities of Bujanovac, Kurumlija, Preevo and Sopot. If the very high level of hazard is added to the extreme level, then the municipalities of Preevo, Bujanovac and Stara Pazova head the list of suspected areas, with 56.97% of the total. This brief analysis shows that in the selection of priorities it is necessary to evaluate the level of hazard by comparing individual locations within an affected community; similarly, communities or municipalities may be ranked internally.

What will be the final extent of risk areas for clearance in Serbia?
The most difficult assessment of all concerns the final extent of the risk areas to be fully treated by international-standard procedures of cluster ordnance clearance. A statistical analysis was undertaken that included: calculation of risk areas based on the extent and number of suspected areas, calculation of the risk areas based on the land release rate according to hazard levels, calculation of risk areas for clearance based on the surveyed risk areas, and calculation of risk areas based on the deployment zones. The calculation of risk areas based on the extent of suspected areas starts from the latest status of the suspected areas on 1 November 2008 and the structure of the land cancelled until this date. (See Table 24, page 84.) By using the release-rate indicators1 and the cancellation structure, the structure of suspected areas could be projected and the extent of the suspected areas assessed. Similarly, calculations based on the number of locations were performed, using the indicators of average extent of suspected areas and number of areas, in addition to the land release rate. It had been assumed that areas where partial land cancellation had been undertaken would not significantly alter in extent. Using this method, it was assessed that the final risk areas for clearance would be slightly larger than 5 km2. The weakness of this calculation is that it started on the basis of the indicators for previous reductions of suspected areas, without taking into account that such land release rate may not be achieved for two reasons: because the number of completely cancelled areas would be dramatically reduced, and because the release rate is inversely proportional to the level of precision of assessed data. This assessment is conservative and may not be valid as a result for the entire suspected area.
1 Land release rate is the percentage of land cancelled in relation to the size of the suspected areas.

36

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

MAP 3

Classification of affected municipalities by size of suspected areas

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

37

Instead, it should be considered as an indicator of the final extent of higher-level risk areas. The calculation of risk areas based on the results of land cancellation per hazard levels was based also on the latest status of the suspected areas, but here the structure of cancelled areas was analysed in relation to the priority level. (See Table 25, page 85.) It was assumed that the land release rate, expressed by hazard levels, would remain the same in future surveys of suspected areas. In addition to the average assessment, the upper and lower limits were calculated for a standard deviation of the release rate. In this case the lower assessed limit proved to be similar to the previous calculation based on the surveyed area structure. The average assessment of 13.7 km2 represented 44.69% of the latest assessed suspected area, or 17.58% of the initial assessment for the extent of the suspected area. That is less in comparison with indicators in other countries in the Western Balkans where similar general surveys have been undertaken: these surveys have shown the rate of reduction of the suspected area to the risk area for clearance to be between 20% and 25%. The third calculation of the risk area for clearance, based on the surveyed risk areas, is similar to the previous one, but it takes into account the surveyed risk area planned for clearance. It involves 93 polygons with a total risk area of 8.1 km2, where no additional land cancellations are expected. This area was not included in the calculation of the average release rate, but was added to the final assessment of the clearance area. The lower assessed limit of the suspected area of 12.5 km2 is slightly less than the average assessed area in the previous case. The average assessed limit of 18 km2 is 23.03% of the initial assessment of the extent of the suspected area, and the upper assessed limit of 23.5 km2 is 30.07% of this. Calculations of risk areas based on deployment zones were carried out for the reconstructed dimensions of 105 deployment zones. The average size of a deployment zone is 114,779 m2. Their total common area is 12 km2, which is in accordance with the lower limit of risk area in the previous calculation. This is acceptable from the perspective of assessing the risk area, which will always be larger than the cluster-ordnance deployment zone. Scattering makes it is impossible to determine the outer perimeters of a cluster-ordnance deployment zone precisely, so an additional safety belt is cleared around the assessed deployment zone. According to the current rules in Serbia, a safety belt of 100 metres is to be cleared from the outermost cluster submunitions found. Including this safety belt zone in the calculation as a safety ring around the deployment zone yields an assessment of 24.5 km2. By reducing this area by 3 km2, which is the area cleared of cluster submunitions between 2003 and 2007, the result is that the area of 21.5 km2 as the upper assessed limit below which is the final risk area for clearance. This upper limit may be further reduced due to overlapping of deployment zones. The average value according to this calculation is 15 km2. Since the risk area is always larger than the deployment zone for a given safety belt, it may be concluded that the area to be cleared of cluster ordnance will not be smaller than 15 km2. This analysis shows that the third and the fourth calculations are consistent in their results, and the first and second calculations imply certain trends in the reduction of the suspected areas. The calculation based on the deployment zone indicated the extent of the risk areas to be between 15 km2 and 21.5 km2. That will serve as a framework for in-depth assessment based on the third calculation. The following assumptions are crucial for the analysis of the final assessment:

38

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

1. During future land cancellation, the standard dispersal of the results will be smaller, or the results will be grouped around the average land release rate. 2. The release rate for suspected areas with high hazard level will decrease; with areas of extremely high and very high levels of hazard there probably will not be further cancellations due to the procedures of data processing involved. 3. Release rates for suspected areas of lower levels of hazard will rise, approaching 100% for the low hazard level as conditions for cancellation are created during clearance. 4. For 28 existing suspected areas (total area of 2 km2) land cancellation has been performed, and further reductions should not be expected. The release rate does not apply to this area, and it is added into the final calculation of the clearance area. The final analysis provides for two options for the assumptions given (See Table 25, page 85.). It may be predicted that the extent of the risk area still to be cleared from unexploded cluster submunitions in Serbia is between 15 km2 and 16 km2. Given the current average area clearance of 0.682 km2 a year, clearance of cluster-ordnance deployment zone will take about 23 years to complete. (See Graph 6.) It is clear that more resources must be allocated to clearance in order to solve the problem of unexploded cluster munitions in Serbia within a reasonable time-frame.

GRAPH 6
Number of cluster submunitions found
100 90 80 70 60 50 40 30 20 10 0 2003 2004 Cleared area (km) cluster submuni1.200 tions clearance,
by year Unexploded

Cleared area Cluster sumbmunitions found

1.000 0.800 0.600 0.400 0.200 0.000

2005

2006

2007

2008

Year

Social and economic impact of unexploded cluster submunitions


The assessment of social and economic impact of unexploded cluster submunitions is the other part of the general assessment of the situation. It starts from the hazard as the source of risk, being more complex and dynamic. Its results are more short-term, contingent upon changes in the environment caused primarily by human activities and changes in nature.

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

39

Cluster submunition victim

The assessment of socio-economic impact undertaken here involves the following elements: (1) analysis of accidents and incidents to date; (2) vulnerable analysis of the population at risk; and (3) analysis of blocked resources. These provide the information necessary for selecting priorities for clearance of unexploded cluster submunitions in Serbia.

Cluster submunitions accidents and incidents


Data on accidents and incidents caused by cluster submunitions were collected in all the phases of the general survey. In all, 73 such were recorded: 21 instances of accidents, and 52 incidents without harmful effects to human life and health. At the beginning of the survey there were data on 20 accidents and one incident caused by cluster submunitions. With regard to this initial situation, the survey teams found data on one more accident and 51 incidents. (See Graph 7.) These data were mapped and used in the assessment of hazards from unexploded cluster submunitions. The most recent accident took place in 2005 in the industrial zone of Ni, and the most recent incident happened in 2008 in the settlement of Reljan, in Preevo municipality. Accidents and incidents were caused by four types of cluster submunitions: BLU 97, BLU 97 A/B and Mk-4 and Mk-118. Cluster submunitions of type BLU 97 were the most frequent cause (46.6% of instances), followed by submunitions of type Mk-4 (in 34.3% of cases). (See Graph 8.)

GRAPH 7
Number of accidents/incidents 20 15 10 5 0 Accidents Incidents
Number of accidents and incidents, by year

1999 17 16

2000 2 9

2001 1 4

2002 0 10

2003 0 1

2004 0 1

2005 1 3

2006 0 2

2007 0 4

2008 0 2 Year

40

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

GRAPH 8
Number of accidents/incidents 25 20 15 10 5 0 BLU 97A/B BLU 97 Mk-4 Mk-118 Cluster submunitions type Incidents Accidents
Number of accidents and incidents, by type of cluster submunitions

The accidents recorded to date have resulted in 191 victims: 31 fatalities (16.2%), and 160 persons injured (83.8%). The largest number of casualties occurred during the 1999 deployment of NATO air forces: 27 fatalities, and 152 persons wounded. From the end of the NATO campaign until November 2008, there were an additional 12 casualties, 4 of them fatalities: 3 children and one farmer died, whereas 8 persons have been injured: 2 deminers, 1 farmer and 5 children . Casualties were caused by three types of cluster submunitions: BLU 97A/B, BLU 97 and Mk-4. Most casualties were caused by BLU 97 A/B cluster submunitions during the NATO deployment to Ni. For casualties after the NATO deployment, the share of all types of submunitions is evenly distributed.

GRAPH 9
Number of casaulties 150 100 50 0 Fatalities Wounded

Cluster submunitions casualties

BLU 97A/B 15 143

BLU 97 2 12

Mk-4 14 5 Cluster submunitions type

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

41

MAP 4

Locations of accidents and incidents

42

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

Vulnerability analysis of the population at risk


Affected Communities
The survey found that 28 local communities (mesne zajednice) are affected by unexploded cluster submunitions. In these communities there are about 162,000 inhabitants. According to the current assessment, 88,000 people live in the immediate vicinity of a suspected area, and can thus can be said to be exposed to daily risk. Of these, a full 66.1% live in the settlement of Duvanite in Ni. (See Table 18, page 78.) On average there are 2,881 directly affected inhabitants for each affected local community (mesne zajednice). However, if Duvanite is excluded from the assessment, the average for the other communities falls to 1,125 inhabitants. The risks of exposure to unexploded ordnance are not evenly distributed. Graph 10, showing the exposure of local communities to the risk of unexploded ordnance, combines two parameters of risk exposure: (1) share of those directly threatened among the population of the local community, and (2) share of the suspected area within the threatened local community. The graph clearly shows that the affected communities are concentrated into three groups. The first group covers three communities Merdare, Duvanite and Medoevac where both parameters are higher than elsewhere. Group two consists of 7 communities Butranje, 12. Februar, Reljan, Strezovce, ibnica, Belo Brdo and Donji Komren which are represented in the upper part of the graph due to their larger share of directly threatened population, but with a relatively smaller suspected area. The remaining communities are grouped around low values, below 20% under both of the parameters, except for Laevci, which has the relatively largest suspected area but also a minimal number of persons directly threatened. These conclusions may serve as a point of reference for selecting priorities in planning clearance operations for unexploded cluster submunitions.

GRAPH 10
Percentage of population directly at risk in affekted communities
100.00% 90.00% 80.00% 70.00% 12 Februar Reljan ibnica Belo Brdo Medoevac 30.00% 20.00% Donji Komren Lisina Bogdanovac Vapa Gare 10.00% Svinjite Ravnite KaradnikBumbarevo brdo Jalovik Vojka Bapsko Polje Guncati Cedovo Jastrebac Samaila 0.00%Bresnica 0.00% 5.00% 10.00% 15.00% Duvanite Butranje Merdare

60.00% Strezovce 50.00% 40.00%

Sjenica 20.00% 25.00% 30.00% 35.00% 40.00% 45.00%

Laevci 50.00%

Percentage of territory defined as suspected areas in affected communities


Exposure of local communities to the risk of unexploded cluster submunitions

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

43

Age Structure
The population structure of the threatened communities was analysed on the basis of data for all 22 threatened communities where individual risk areas were surveyed. There is an almost even distribution of all age categories if the overall population in threatened communities is taken into account. However, the average share of age groups per threatened communities is a more realistic indicator, since it eliminates the effect of communities with an especially high number of inhabitants, like Duvanite. Then the structure moves in the direction of the older population groups, to 37.9% for those over 60 years of age. (See Graph 11.) Age structure per threatened local communities is not evenly distributed. The elderly dominate in the communities of Merdare, Reljan, Gare and Jastrebac, whereas young people up to 19 years of age have a larger share in Butranje, Strezovce, Sjenica, Vojka, Vapa and Bumbarevo Brdo. (See Graph 21 in Appendix D.)

GRAPH 11
Age structure of the affected population

13.4% 15.8% 10.1%

As regards average age structure per threatened communities

19.9% 37.9%

As regards the total number of inhabitants 14.2% in threatened communities 23.4%

17.6% 26.7%

21.1%

Up to 14 15-35 years of age 25-39 years of age 40-59 years of age Over 60

Parts of cluster submunitions found in Sjenica

Entry of Population into Risk Areas


Risk behaviour of the population was registered in 91.8% surveyed risk areas. In most cases (56.2%), such behaviour involved the entry of adults from threatened settlements. (See Graph 12.) Children are second in the number of registered cases. They enter together with adult villagers (in 28% of the cases), and less frequently together with adults and

44

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

other persons i.e. individuals not living in the threatened communities. The correlation between the frequency and numbers of entry into risk area indicates that there are two dominant types of behaviour concerning entry to risk areas. (See Graph 13.) In most cases it was individual and occasional entry of villagers into the risk area. The other dominant type is daily entry of groups of villagers into the risk area.

GRAPH 12
Entry into surveyed risk area identified groups

28.1%

13.5%

1.1% 1.1% Adult villagers Adults and children Adults and children, others Others Unknown

56.2%

The behaviour of the population is influenced by the distance of the households from the risk areas (Graph 14). In 29.2% of all cases, the risk area is in the immediate vicinity of the houses. In 50% Parts of cluster of the cases the distance is up to 300 metres, and in 69.8 submunitions % cases the distance is up to one kilometre from the risk found in Bujanovac area. Thus, in most cases the population is living near the source of hazard of unexploded cluster submunitions. Conclusion of the analysis indicates that people in affected communities seem to underestimate threat posed by unexploded cluster submunitions. They assume that surface-level removal of unexploded cluster submunitions has been undertaken, and that what remains is mainly located underground. On the other hand, they do take certain precautions: children tend to enter the suspected area in the company of adults, and group entry is preferred over individual entry. Entry into risk areas, proximity to settlements, and children as a vulnerable group are included in the criteria for selection of priorities for clearance of unexploded cluster submunitions.

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

45

GRAPH 13
Entry into surveyed risk area frequency and numbers

Number of risk areas 35 30 25 20 15 10 5 0 up Gro

ily Da ca Oc

Gro

up a

a vidu indi nd

l ivi Ind dua l n Unk own

y nll sia

ry Ve e rar ly n k Un w no

In groups or individualy

Frequency of entry into risk area

GRAPH 14
Distance of the surveyed risk areas from nearest settlement/ household

12.5% 29.2%

16.7% 0-5 meters 6-100 meters 101- 300 meters 301-1000 meters 1001-2000 meters Over 2000 meters

8.3%

19.8% 13.5%

46

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

Analysis of blocked resources


One of the parameters used in assessing a suspected area is determining the predominant intended use of the land not being used, or which natural or other resources are blocked in the suspected area. The intended use of land was determined in line with the classification system approved by the Serbian Mine Action Centre. (See Appendix C.) As shown in Graph 15, it is mostly agricultural land that is blocked due to the presence of unexploded cluster submunitions hazards: 29.7% of the suspected locations relate to agricultural land, or 33.4% of the total areas suspected. The second largest barrier due to unexploded cluster submunitions is the impossibility of reconstructing the infrastructure of settlements and utility facilities, representing 19.9% of the total suspected area. The third largest problem is the impossibility of renovating or restoring housing units, at 14.2%. Further significant reasons for blocking relate to the following categories of land use: forest exploitation and maintenance (8.8%), tourism development (9.6%), road communications (6.4%), and new industrial production (4.2%). The remaining categories of land use have individual shares of less than 1.5% of the total suspected area. The employment structure of threatened local communities is dominated by agriculture, hunting and fishing. Especially prevalent are the following business activities: processing industry, commerce, traffic and communications, public administration and construction engineering. (See Graph 22 in Appendix D.) Clearly, the structure of blocked resources is reflected in these activities.

GRAPH 15
Number of suspected areas 120 100 80 60 40 20 0 N 01 N 02 N 03 N 04 N 05 N 06 N 07 N 08 N 09 N 10 N 11 N 12 N 13 N 14 Number of suspected areas Magnitude of suspected areas Magnitude of suspected areas (km) number and ex12.000 tent of suspected 10.000 8.000 6.000 4.000 2.000 0.000 Blocked resources
Relation of the

areas, by blocked resources

However, blocked agricultural land is for the most part (7.7 km2 out of 10.3 km2 of the suspected total) of only low or medium hazard, being located on the outside perimeters of the deployment zone. The share of areas of low and medium hazard is similar with regard to blocked reconstruction of settlement infrastructure (5 km2 out of 6.1 km2 of the suspected area) and housing units (3.9 km2 out of 4.4 km2 of the suspected area). (See detailed calculations in Tables 6 and 7.) Since the rate of cancellation of suspected areas is generally higher in low hazard areas, the share of higher levels of hazard (extremely high, very high and high hazard) can be expected to be greater

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

47

in the final risk area for clearance. If we look at the extent of the suspected area only for the higher levels of hazard, the sequence in the structure of blocked land is somewhat different. The share of blocked agricultural land remains dominant, and then the blocked resources follow in this order: reconstruction of settlement infrastructure, forest exploitation and maintenance, road communication lines, development of tourism, and reconstruction of housing facilities. The analysis of blocked resources confirms that the hazard of unexploded cluster submunitions in combination with blocked resources has a significant impact on the socio-economic situation of the communities affected. The likelihood of fatalities has been reduced, but the number and frequency of incidents is such that the probability of activating unexploded submunitions will rise with the growing needs of the population to use the blocked land. The structure of blocked land for higher levels of hazard indicates another possible hazard. Any potential use of areas contaminated by unexploded cluster submunitions, prior to clearance, involves the disturbance of soil whether agriculture is the main potential activity, or other land-uses predominate. Regular measures of warning the population and marking suspected areas need to be undertaken, to prevent misperceptions as to the absence/presence of unexploded cluster submunitions. The positive effects of the removal of unexploded cluster submunitions will be reflected in the following: (1) increase in general safety, (2) reduction of risk, especially for people living in contact with risk areas, (3) increase in the number of users of land now blocked, as indicated by the employment structure in the affected local communities!

TABLE 6
Structure of resources blocked due to presence of unexploded cluster submunitions Extremely high hazard Very high hazard High hazard Medium hazard Low hazard Total 39 23 1 7 17 0 0 4 22 2 116 65 90 4 390 100,00% %

Forest exploitation and maintenance Tourism development Employment incentives Reconstruction of educational, religious and cultural facilities Passability of transport communications Construction of communications facilities River regulations, reconstruction of canals and embankments Water supply Starting industry production Reconstruction of power transmission lines and power facilities Restoring agricultural land use Reconstruction of settlement infrastructure and utilities Reconstruction of housing units Other
Total %

1 0 0 0 0 0 0 0 0 0 3 0 1 1
6 1,54%

3 0 0 1 0 0 0 0 0 1 7 2 0 3
17 4,36%

7 3 0 0 5 0 0 0 1 0 17 8 3 0
44 11,28%

13 12 0 4 8 0 0 2 8 1 43 27 68 0
186 47,69%

15 8 1 2 4 0 0 2 13 0 46 28 18 0
137 35,13%

10,00% 5,90% 0,26% 1,79% 4,36% 0,00% 0,00% 1,03% 5,64% 0,51% 29,74% 16,67% 23,08% 1,03%
100,00%

Number of suspected areas with regard to hazard levels and blocked resources

48

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

TABLE 7
Structure of resources blocked due to presence of unexploded cluster submunitions Extremely high hazard Very high hazard High hazard Medium hazard Low hazard

Total

Forest exploitation and maintenance Tourism development Employment incentives Reconstruction of educational, religious and cultural facilities Passability of transport communications Construction of communications facilities River regulations, reconstruction of canals and embankments Water supply Starting industry production Reconstruction of power transmission lines and power facilities Restoring agricultural land use Reconstruction of settlement infrastructure and utilities Reconstruction of housing units Other
Total %

0,057 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,000 0,402 0,000 0,133 0,035
0,627 2,04%

0,120 0,000 0,000 0,001 0,000 0,000 0,000 0,000 0,000 0,149 0,563 0,155 0,000 0,152
1,140 3,71%

0,739 0,515 0,000 0,000 0,610 0,000 0,000 0,000 0,057 0,000 1,648 0,961 0,323 0,000
4,853 15,78%

0,899 1,240 0,000 0,319 0,907 0,000 0,000 0,080 0,543 0,098 3,014 2,345 2,320 0,000
11,765 38,26%

0,884 1,202 0,094 0,091 0,446 0,000 0,000 0,097 0,678 0,000 4,645 2,650 1,581 0,000
12,368 40,22%

2,699 2,957 0,094 0,411 1,963 0,000 0,000 0,177 1,278 0,247 10,272 6,111 4,357 0,187 30,753 100,00%

8,78% 9,62% 0,30% 1,34% 6,38% 0,00% 0,00% 0,57% 4,15% 0,80% 33,40% 19,87% 14,17% 0,61% 100,00%

Extent of suspected areas with regard to hazard levels and blocked resources

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

49

5
P

Reports on general survey of risk areas

reparation of the general survey report is the first step in generating the clearance tasks for risk areas. These reports represent the sum of information collected from a range of sources by applying various methods of data collection: questionnaires, interviews, observations and measurements. The general survey report is a standardized form where the data and the results of data processing are entered in the form of estimates, descriptions, coordinates and other records. The structure of the general survey report is based on the general survey process, thus reminding the survey teams of the requirements to be met during survey activities. Integral to the report on general survey are minutes of interviews, photographs, and sketch drawings of the risk area. The main parts of the survey report are as follows: general data on the areas surveyed, hazard assessment, environmental impact assessment, and assessment of operating conditions for clearance. Hazard assessment contains information on accidents, victims, deployment zone characteristics, and previous activities of removal of unexploded cluster submunitions and other unexploded ordnance. On the basis of this information, the survey team assesses the level of hazard in each risk area. Environmental impact assessment involves general data on the community where the risk area is located, data on the consequences of cluster submunitions deployment in the community, assessments of the population vulnerability and estimates of the potential benefits of clearance. On the basis of all these elements, the survey team prepares an assessment of the environmental impacts of the risk. The assessment of operating conditions includes data on characteristics of the risk-area land, prevailing local climate conditions, contact information on persons from the local community, information on each location in relation to the wider area, as well as a description of the risk area covered by the report, and additional activities Urgent marking sign installed identified by the survey team to be by survey team taken in addition to clearance. during field activities By the end of November 2008, the survey teams had prepared 100 reports. The total risk area covered by these reports is 8.3 km2. This is sufficient for multi-annual operations of clearance of unexploded cluster submunitions in Serbia. Each report on the general survey

50

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

contains 313 pieces of data, which means that a total of 31,300 data entries have been recorded in the database. In addition, there are 100 sketch drawings of risk areas with coordinates of breakpoints, 100 drawings of the wider area, 231 photographs of risk areas, 168 photographs of installed signs of emergency marking, 48 minutes of interviews, and 100 orders/requests for general survey. The number of working hours spent on field operations, data processing and report preparation was 4,424, or an average of 44.24 hours for the preparation of each survey report. Bearing in mind the activities, the distribution of time is as expected, apart from the time spent on trips to survey locations and return. (See Graph 16.) The general survey reports are integral parts of the project documentation on unexploded

GRAPH 16
Hours per report 16 14 12 10 8 6 4 2 0 13 10 7 4 9
Time spent on preparing general survey reports

Working hours spent on Working hours spent on Working hours spent on Working hours spent on Working hours spent on entering data into the survey location preparing the survey and travelling to the location preparing reports and accompanying documents data base and preparing and back analysis of documentation project documents Activity

cluster submunitions clearance prepared by the Serbian Mine Action Centre. Based on these reports, this Centre prepares other project documents: proposals for donnors, clearance tasks, and other relevant documents.

Selection of priorities for clearance


Fundamental elements in identifying priorities for clearance are the nature of risk, risk source (expressed through hazard of unexploded cluster submunitions), and the environmental impact. The matrix for identifying priorities for risk areas is generated by combining the hazard level scale and the environmental impact scale for risk. In order to survey the areas contaminated by unexploded cluster submunitions in Serbia, a matrix with nine levels of priority was prepared for ranking risk locations. This matrix was constructed on the basis of five levels of hazard and five levels of environmental impact assessed during the survey. Levels of hazard within the matrix are classified as: extremely high hazard (EH), very high hazard (VH), high hazard (H), medium hazard (M) and low hazard (L).

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

51

TABLE 8
Risk location priority matrix
Priority level for risk areas EH EH VH Environemental impact level H M L VH Hazard level H M L

1 2 3 4 5

2 3 4 5 6

3 4 5 6 7

4 5 6 7 8

5 6 7 8 9

Hazard as a source of risk is described on the basis of the position and characteristics of the risk area in question. The level of hazard is identified on the basis of data on consequences of accidents/ incidents and the assessed probability of the presence of unexploded cluster submunitions in the risk area. The matrix for estimating the level of hazard has been generated by combining the scale of consequences of accidents/incidents caused by unexploded cluster submunitions and the scale of probability of presence of unexploded cluster submunitions in the suspected area. The consequences of accident/incidents caused by cluster submunitions to date have been classified according to the following scale: 1) accident with fatal consequence or wounding of one or more persons 2) incident with animal casualties 3) incident without consequences for people or animals 4) no incidents The probability of presence of unexploded cluster submunitions in the suspected area has been determined in accordance with the following scale and relevant cumulative criteria: 1) Almost certain presence of unexploded cluster submunitions. Criteria to be met: a. data indicating that the area lies within the zone of scattering of cluster submunitions, the area is not in use, or that b. during use of the area, cluster submunitions or other remnants indicating the deployment of cluster ordnance have been found. 2) Highly probable presence of unexploded cluster submunitions. Criteria: a. data indicating that the area lies within the zone of scattering of cluster submunitions, the area is not in use, there have been some activities on partial removal of unexploded cluster submunitions without application of international standards or expert monitoring of the competent body. 3) Low probability of presence of unexploded cluster submunitions. Criteria: a. area contiguous with the zone of scattering of cluster submunitions, the area is not in use, or b. data indicating that the area lies within the zone of scattering of cluster submunitions, the area is in use, there have been some activities on partial removal of unexploded cluster submunitions without application of international standards or expert monitoring of the competent body. 4) No probability of presence of unexploded cluster submunitions. Criteria:

52

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

TABLE 9
Consequences of accidents/incidents to date Matrix for hazard level Death or injury Death or injury Incidnts without to persons to animals consequences No incidents

Matrix for level of hazard

Almost certain Probability of presence High probable of unexploded cluster Low probability submunitions Not probabile

EH VH M

EH H M

VH M L

H M L L

a. area is not in use, due to the suspicion of unexploded cluster submunitions hazard. Levels of hazard within the matrix are classified as: extremely high hazard (EH), very high hazard (VH), high hazard (H), medium hazard (M) and low hazard (L). The environmental impact of the risk of unexploded cluster submunitions has been estimated by comparing adverse circumstances and potential possibilities. Adverse circumstances are expressed by the level of vulnerability of the population, and potential possibilities by the expected benefits of clearing areas currently contaminated by unexploded cluster submunitions. The vulnerability level of the population in relation to a given risk area has been determined in accordance with the following scale: 1) High vulnerability level. Criteria: daily presence of the population in the immediate vicinity of the risk area, or multiple entries into the risk area, or definite information that children move about in the immediate vicinity of the risk area. 2) Medium vulnerability level. Criteria: population occasionally present in the vicinity of the risk area, or no population present in the immediate vicinity of the risk area. 3) Low vulnerability level. Criteria: no definite information on the presence of population in the vicinity of the suspected area, or population rarely present. The potential benefits of clearance have been defined by the affected communities themselves, based on the criteria identified by the relevant authorities. In principle, the criteria are grouped according to their importance, where category one is of highest importance. The environmental impact matrix has been generated by combining these two scales. Also here, the levels of environmental impact are classified as extremely high impact (EH), very high impact (VH), high impact (H), medium impact (M), and low impact (L).

TABLE 10
Vulnerability population level Environmental impact risk matrix High Category 1 Potential benefits level Category 2 Category 3 Medium Low

Matrix for identifying environmental impact risk

EH H M

VH M M

H M L

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

53

Household in suspected area

For all risk areas surveyed by the NPA in Serbia, the level of priority was determined as described above. As for hazard levels, survey teams assessed them in the suspected area first, later confirming them during the detailed survey of the suspected area and their conversion into risk areas. The distribution of risk areas per hazard levels for the areas surveyed so far is normal. Medium-level hazard has the maximum share, and from there the values decrease on both sides. (See Graph 18.)

GRAPH 17
Share of risk Share in surveyed risk area (%) areas, by vulner94.73% ability levels and 100.00% potential benefit 90.00% levels 80.00% 70.07% 70.00%

Vulnerability level Potential benefit level

60.00% 50.00% 40.00% 30.00% 20.00% 10.00% 0.00% High vulnerability/Category 1 Medium vulnerability/Category 2 Low vulnerability/Category 3 5.27% 0.00% 0.00% 29.93%

Vulnerability level/Categories of potential benefits

Regarding the threat-level assessment, high level of threat dominates, with 70.07% of the surveyed areas. This could have been expected, since the activities of the survey teams were directly precisely at the most hazardous locations, and in those communities where assessments indicated highest vulnerability for the population. Almost all locations belong to category 1 of potential benefits, because there are no clearly elaborated criteria on the basis of which risk areas may be categorized in relation to this characteristic. These criteria need to be determined by the competent bodies as soon as possible, as only then will the system for identifying priorities be fully effective. (See Graph 17.) Level of environmental impact was estimated on the basis of the estimation of the vulnerability level, and of potential benefits of clearance. Since the results of both these evaluations are in the upper parts of the scale, the distribution of risk areas in terms of environmental impact level is also located in the upper part of the scale. Thus the normal distribution of

54

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

risk area otherwise characteristic of hazard assessment is missing. The share of extremely high environmental impact is at the maximum, and then decreases sharply down the scale to the medium level of environmental impact, which has the smallest share. No areas with low environmental impact were identified. (See Graph 18.) The share of risk areas by priority levels indicates a regular distribution of risk areas, with the maximum at the fourth level of priority. (See Graph 19.) Due to the results obtained for environmental impact assessment, there was a slight but not significant shift toward higher priority levels. This confirms that the effect of particular factors influencing the identification of priorities is sufficiently balanced, and that the system is capable of compensating for extreme values.

GRAPH 18
Share in risk area (%)
80.00% 70.00% 60.00% 50.00% 40.00% 30.00% 20.00% 10.00% 0.00% Extremely high Very high High Medium Low 5.81% 7.74% 3.65% 1.62% 6.31% 0.00% 27.60% 36.84% 43.30% 67.13%
Share of risk areas by Hazard level hazard levels and environmental Environmental impact level impact levels

Environmental impact level

GRAPH 19
Share in risk area (%)
40.00% 35.00% 30.00% 25.00% 20.00% 15.00% 10.00% 5.00% 0.00% 1 2 3 4 5 6 7 8 9 8.00% 5.96% 1.14% 1.04% 0.00% 0.00% 17.68% 29.86% 36.33%
Share of risk areas for clearance, by priority levels

Priority levels

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

55

Populated area suspected to contain cluster submunitions

This analysis has shown how important it is to have a system for defining priorities in making planning decisions. This is crucial for operational planning. Along with the growing interest in resolving the problems of unexploded cluster submunitions in Serbia, the need to set priorities among clearance tasks will also increase. Donors wish to see priorities set in a clear and transparent manner, the users want to have a fair and just order for resolving their problems, and the government wishes to channel clearance activities into legal and normative frameworks. Another important reason for identifying priorities is that, under conditions where financial and other resources are not sufficient, as is the case in Serbia, available funds should be directed to where they will yield the most positive effects for the people. The Serbian Mine Action Centre has approved implementation of this model for prioritizing as part of the NPA standard operating procedures. The next step is to make identifying priorities part of the national policy for mine action, including uniform criteria for prioritization, to be followed by all state authorities and other bodies or organizations involved.

Case studies Municipality Bujanovac


The municipality of Bujanovac is situated in the south of Serbia. It borders on the municipalities of Preevo, Gnjilane, Kosovska Kamenica, Vranje and Trgovite to the west, north and east, and to the south with the Republic of Macedonia. Its area covers 462 km2. According to the latest census (2002), the population of Bujanovac was 12.011.
Municipality of Bujanovac

56

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

During the 1999 bombing, NATO aircraft deployed cluster ordnance and other ordnance against positions of the Serbian military located in this area. After the war, areas contaminated by unexploded cluster submunitions remained in four local communities of the municipality: Jastrebac, Karadnik, Bogdanovac and Svinjite. Immediately after bombing, military and civil defence personnel carried out surface removal of unexploded cluster submunitions. However, a certain quantity of cluster submunitions that remained hidden in the vegetation or underground could not be detected by surface removal. The total area of affected local communities in the municipality of Bujanovac is about 17 km2 and has (according to the 2002 census) 1,259 inhabitants. Most of the population earn a livelihood from agriculture and forest exploitation.

TABLE 11
Settlement Area of the Community Number of Inhabitants Number of Households Number in workforce Workers in agriculture

Bogdanovac Jastrebac Karadnik Svinjite


Total

17 5 12 10
44

101 19 455 103


678

33 19 107 35
194

47 7 164 38
256

24 7 27 24
82

Data on threatened communities in the Municipality of Bujanovac

Since the end of the NATO bombing there have been three victims to date in this municipality: two fatalities and one wounded person. In ten cases, members of the local population have found cluster submunitions during agricultural activities, hunting, herding cattle, etc. The first accident involving unexploded cluster submunitions took place on 6 August 1999, and involved two children. One child was killed, the other wounded. At the accident site, ten more pieces of cluster submunitions were found. On 18 July 2001, a boy was killed by cluster submunitions under unknown circumstances. Probably he or someone else passing through the area where cluster ordnance had been deployed found the cluster ordnance, took it outside the risk area, and activated it. In 2001, 2002 and 2007 there were six incidents recorded involving the finding of cluster ordnance. In all, 30 additional pieces were found: three in 2001, seven pieces in 2002, and 20 pieces in 2007. At the end of 2007 and the beginning of 2008, the NPA started its general survey of areas of cluster ordnance deployment in Serbia, assessing the hazards, extent, shape and characteristics of the suspected areas. On the basis of the NATO data on cluster submunition deployment, data on accidents, removal by military and police forces, and questionnaires completed by informants assigned by the local government, 17 cluster-ordnance deployment zone were identified. It was assessed that there were 361 pieces of cluster submunitions: 110 pieces of BLU 97 and 251 pieces of Mk-4. The initial suspected area in the municipality of Bujanovac measured 7.5 km2. After existing data had been analysed, new data collected and compared against the situation in the field, certain parts of suspected areas could be cancelled, as it could be positively determined that there was no hazard. Thus the suspected or risk area was more precisely defined. By the end of the survey of all suspected areas within the municipality, the extent of total risk area in Bujanovac was reduced to 1.8 km2, with agricultural land and forest predominating.
Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

57

TABLE 12
Land blocked due to unexploded cluster submunitions contamination in the Municipality of Bujanovac in km2
Settlement Agricultural Land Forest Industrial land Other Total

Svinjiste Karadnik Bogdanovac Jastrebac


Total

0.175 0.056 0.051 0.245


0.527

0 0 0.102 0.323
0.425

0 0.183 0 0
0.183

0 0 0.153 0
0.153

0.175 0.239 0.306 0.568


1.288

MAP 6
Map of risk areas, Bujanovac municipality

Risk areas, Bujanovac municipality

58

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

Municipality of Preevo
The municipality of Preevo is located in the south of Serbia. Its geographic area covers 252 km2. According to the latest census (2002), there are 13,426 inhabitants. The municipality borders on the municipalities of Gnjilane and Bujanovac to the west and to the east, and on the Republic of Macedonia in the south.
Municipality of Preevo

Three local communities, Butranje, Reljan and Strezovice, have problems with remnants of unexploded cluster submunitions after the NATO bombings of 1999. After deployment, military and police personnel performed surface removal of unexploded cluster submunitions, but not of submunitions that had penetrated the soil or remained hidden in dense undergrowth. The total area of threatened local communities in the municipality of Preevo is about 38 km2. According to the 2002 census, the population of these local communities is 2,599, most of whom earn a

TABLE 13 Preevo
Settlement Area of the Local Community Population Number of Households
Number in workforce Workers in agriculture

Optina

Bustranje Reljan Strezovce


Total

10 19 9
38

872 692 995


2559

201 174 284


659

284 231 266


781

175 125 158


458

Data on threatened communities in the Municipality of Preevo

livelihood from agriculture and forest exploitation. From the NATO bombing and till September 2008, in the territory of this municipality, 11 persons have been victims of cluster submunitions remnants: eight killed and three wounded. On 15 April 1999, during the NATO bombing, seven soldiers of the Serbian military were killed in the local community of Reljan. On 27 July 1999, one boy was killed and two were injured in the local community of Butranje, when a boy activated the cluster ordnance he was playing with together with his friends. In May 2008

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

59

there was another incident in Butranje: in the course of farming activities, a villager found three pieces of unexploded cluster submunitions remnants. 12 deployment zones were reconstructed. The initial suspected area was 4.295 km2. Later on, during the second phase of the general survey, detailed assessments of suspected areas were undertaken. After existing data had been analysed, new data collected and compared against the situation in the field, certain parts of the suspected areas were found not to be hazardous and could be cancelled, so the suspected or risk area was more precisely defined. The total risk area in the municipality of Preevo was reduced to 1 km2.

TABLE 14
Land blocked Settlement due to unexploded cluster Bustranje submunitions contamination in Reljan the Municipality of Preevo in km2 Strezovce
Total Agricultural Land Forest Industrial land Other Total

0,258 0,681 0,067


1,006

0 0 0,052
0,052

0 0 0
0

0 0 0
0

0,258 0,681 0,119


1,058

MAP 7
Map of risk areas, Preevo municipality

Risk areas, Preevo municipality


60

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

Municipality of Kurumlija
The municipality of Kurumlija is located in the south of Serbia. To the west it borders on the municipality of Podujevo, to the north it borders on the municipalities of Brus and Blace, and to the east and west the municipalities of Prokuplje and Medveda. There is only one threatened community in the municipality of Kurumlija: Merdare, in the south-west. Merdare covers an area of 6 km2, and has a population of 139, according to the 2002 census.
Municipality of Kurumlija

During the 1999 bombing, NATO aircraft deployed cluster and other ordnance in this local community. Immediately after the bombing, military and the civil defence personnel carried out surface removal of unexploded cluster submunitions, but also here a certain quantity remained hidden in the vegetation or under the surface.

TABLE 15
Settlement Area of the Local Community Population Number of Households
Number in workforce Workers in agriculture

Merdare
Ukupno

6
6

139
139

52
52

41
41

5
5

Data on threatened communities in the Municipality of Kurumlija

During the NATO deployment on 11 April 1999, there were seven victims: five killed and two wounded in Merdare. Concerning unexploded cluster submunitions, there have been no casualties after the NATO bombing, except for one incident where an animal was killed. Additionally, there were four more incidents where unexploded cluster submunitions were found, in 1999 and 2000. The initial suspected area was 2.7 km2. After existing data had been analysed, new data col-

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

61

lected and compared against the situation in the field, certain parts of suspected areas where it was clear that there was no hazard were cancelled, also here enabling more precise identification of the suspected or risk area. The total risk area in the municipality of Kurumlija was reduced to 2 km2 much of which is covered in trees. A special problem in this local community is the large risk area located in courtyards and homesteads !

TABLE 16
Land blocked Settlement due to unexploded cluster Merdare submunitions contamination in Total the Municipality of Kurumlija in km2
Agricultural Land Forest Industrial land Other Total

0,274
0,274

1,406
1,406 0

0,397
0,397

2,077
2,077

MAP 8
Map of risk areas, Kurumlija municipality

Risk areas, Kurumlija municipality

62

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

6
T

Project quality managment

he general survey of the cluster-ordnance deployment areas in Serbia is one project of the NPA that has employede a regional approach to mine action in Southeast Europe. The project was carried out by the NPA Mine Action Programme from Bosnia and Herzegovina. On 23 October 2007, NPA applied to the Serbian Mine Action Centre for approval of standard operating procedures for mine action and general survey of the cluster-ordnance deployment areas and accreditation for performing humanitarian demining and survey in the territory of Serbia. Following the completed accreditation procedure, the Serbian Mine Action Centre granted approval for the NPA Mine Action Programme from Bosnia and Herzegovina to carry out the following operations: de-mining of mine fields; de-mining/clearance of land and facilities from unexploded ordnance; and general survey of areas of cluster bomb deployment. This permission was valid for one year, from 5 November 2007 till 5 November 2008. The Serbian Mine Action Centre assisted the NPA in establishing cooperation with other state authorities, above all with the Administration for Emergency Situations of the Ministry of Defence, Republic of Serbia. As early as 12 December 2007 the head of the Administration for Emergency Situations sent a letter to district departments for emergency situations, instructing these departments to establish cooperation with the NPA survey teams and enable them to collect data in the field. Following completion of the project, the NPA delivered to the Serbian Mine Action Centre the database and archives containing the sorted documents generated during the survey or received from other data sources.

General survey monitoring


Monitoring of the general survey of the cluster-ordnance deployment areas in the Republic of Serbia was the task of the management of the NPA and a special team for survey monitoring. The activities of the Regional Director of the NPA for Southeast Europe and the Programme Manager of the Mine Action Programme in Bosnia and Herzegovina were directed at ensuring realization of the planned project objectives and terms of reference. The special team for survey monitoring consisted of the head of operations and the planning and reporting officer from the NPA Mine Action Programme in Bosnia and Herzegovina. The overall objective of the monitoring was to ensure consistent implementation of SOPs and the verification of processes and sub-processes for input and output data. The monitoring was carried out through two basic activities: (1) general survey quality control, and (2) quality assurance of general survey input data and final outcomes.

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

63

General survey: Quality control


General survey quality control involved (1) supervision the activities of survey teams, and (2) realization of planned project objectives. The activities of survey teams in adhering to the SOPs was continuously followed by the monitoring team through inspections or control of documents delivered. Inspection included: (1) control of compliance of the survey team activities with the prescribed procedures, (2) checking database entries, and (3) checking the accuracy of measurements. The Regional Director and the Programme Manager inspected the teams from time to time, and continuously monitored the schedule of realization of the tasks planned. During the first sub-process identification of areas suspected of cluster ordnance hazard the verification of first entries into the database and the mapping thereof were undertaken. It was determined that the survey teams had not been transforming the coordinates into the coordinate system used by the relevant national body for mine action. Additional training of the teams was then carried out, and all data previously entered and coded were re-entered. Such verification was a regular activity and was carried out every fifteen days until the end of phase two of the project. It involved all the entries into the database. Any errors detected were removed. The second phase of the project, involved field work of the general survey including risk assessment and production of relevant documents. Each of the survey teams was subject to several days inspection of activities, during which time any omissions identified in relation to database entries, or in relation to the preparation of survey reports as part of project documents for the clearance of the risk areas, were rectified. Since the testing of the database was carried out in parallel and under actual operating conditions, on three occasions it was necessary to adapt the base to the requirements of the process. During the control of the preparation of project documents, it was found that the quality of three survey reports, 3.1% of the total number of reports prepared, failed to meet the requirements set by the standard operating procedures. All three reports were withdrawn, and the order was given for the survey to be carried out again. Otherwise, there were no other significant errors in the preparation of project documents that would affect the final result. The general conclusion of the quality control is that the survey teams observed the SOPs for general survey and that all the tasks as planned by general survey project in Serbia were completed. The errors that occurred were not permanent and did not affect project results. Some difficulties in obtaining cadastral maps slowed down the project to a certain extent, during phase two. However, by investing additional effort the survey teams managed to overcome this problem, so there were no significant deviations from the schedule.

General survey results: Quality assurance


Quality assurance included the following: (1) input data quality control by failure modes and effects analysis method (FMEA) in combination with the Pareto priority method; (2) SOP testing; (3) general survey results verification by statistical analysis of random samples. The FMEA method was selected because it enables the identification of weaknesses in the general survey process and their reflection on the final results. Thus a preventive identification of

64

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

problems, before they can adversely affect the results, was made possible. The combination of this method with the priority method allowed the focus on the causes of errors with greatest potential effects on final quality. Random sample statistical analysis was used for evaluating the accuracy of the assessed parameters of the cluster-ordnance deployment zone, or of the risk area. On the basis of the appropriate random sample of cluster-ordnance deployment zones and a sample of completed reports on the general survey, the critical parameters were verified: (1) hazard level, (2) environmental impact level, (3) priority level, and (4) intended use of land. Testing of standard operating procedures for the general survey of the cluster-ordnance deployment area was carried out twice: (1) at the beginning of phase one of the project, and (2) at the beginning of phase two of the general survey of cluster-ordnance deployment area. The first testing showed that SOPs enabled the realization of the first sub-process of the general survey, resulting in identification of the suspected areas. The second testing was carried out on the first ten reports prepared on the risk area survey. FMEA employed during this testing led to the conclusion that certain amendments would have to be introduced to improve the SOPs in the procedure for assessment of hazard level and for cancelling of land previously part of the suspected area. In the former case this involved improving the criteria for assessing the probability of the presence of unexploded cluster submunitions in a suspected area. In the latter case it involved SOP amendment: there was a process step carried out in practice (adjustment of deployment zone characteristics and cancelling land from suspected areas) which had not been described in the standard operating procedures. The necessary amendments were introduced by the Programme Manager and analysed together with members of the general survey team and the monitoring team. These modifications to the SOPs were accepted by the Serbian Mine Action Centre. Verification of the general survey results included evaluation of the work of the teams in determining the deployment zone parameters and the control of general survey reports. Analysis of assessed cluster-ordnance deployment zone parameters was carried out on the random sample of the deployment zone. The quality of input data, the accuracy of cluster-ordnance deployment zone parameters and compliance with the criteria under the SOPs were evaluated. The checking was carried out on a simple random sample without repetition. The sample was selected from the 177 deployment zones identified during the previous assessment of the situation of unexploded cluster ordnance, and consisted of 62 cluster-ordnance deployment zones.1 The results of the analysis showed that for 12 deployment zones, 17.4% of the selected sample, no irregularities were found. As for 39 deployment zones (62.9% of the sample), minor adjustments were necessary to the parameters assessed. In 17 cases (27.4% of the sample), adjustments of the deployment zone centre were made, and in 12 cases (17.4% of the sample), adjustments of the dimensions and directions of the deployment zone locations were made. The mentioned mistakes were the cause of the errors in defining suspected areas. Most often they resulted in an increase in the dimensions of the suspected area and inaccuracies in defining their shape. For 24 deployment zones included in the random sample, it was found that they did not in fact exist at all, as they had been projected on the basis of incorrect input data on cluster-ordnance deployment zones. The direct consequence of these earlier errors was the later cancellation of the suspected area. Analysis of failure modes was carried out by the Pareto chart. Four causes of incorrect assessment of the deployment zone parameters were identified: (1) insufficient quantity and quality of available data for reconstruction of the deployment zone, (2) incorrect input data from NATO other types of ordnance
1 The size of random sample was identified for the confidence level of 95% and interval of +/- 10%.

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

65

(not cluster ordnance) had been deployed at some locations, (3) imprecise data collected by the survey teams from local-level sources, and (4) incorrect input data from NATO there had been no deployment in some locations. In 18 cases it was found that the general survey teams did not have all input data, or that the quality of their input data was insufficient for identifying the deployment zone parameters, so they had reconstructed the deployment zone on the basis of knowledge and experiences. In 17 cases, the data received from NATO referred to the deployment of other (non-cluster) ordnance; in four cases of data supplied by NATO, the deployment zones proved non-existent. In 14 cases it was determined that the local data sources did not have correct information. During phase two of the general survey, these errors and irregularities were removed and additional information was collected. Then precise measurement was undertaken, and the data and the reconstruction of all deployment zones in the database were checked. By the FMEA method, the mistakes identified were analysed, and their risk factor was determined. Its value was determined on the basis of the previously defined scale for the level of failure, the probability of failure incidence, and the difficulty of discovering the failure.(See table 20, page 82.) The highest values of the risk factor related to failures where the cause was incorrect data from NATO (cluster-ordnance deployment zone and the suspected area are not present at all). In the analysis of failure modes it was found that 33.08% of the input data from NATO did not refer to cluster ordnance, but to other types of ordnance that had been used in these locations; moreover, 7.55% of the NATO data were totally incorrect, since there had been no NATO deployment at the coordinates indicated. During phase one of the survey, the teams were not able to check all input data due to time limitations and winter weather conditions. Quality assurance of phase two of the general survey was carried out for 20 selected general survey reports. In all 10,400 data items were examined, out of which 6,260 in the relational base (20% of

GRAPH 20
Ratio of failure Risk factor frequency and their risk factor 450
400 350
Erroneous assessment of deployment zone parameters

Erroneous assessment of priority level Erroneous assessment of probability of cluster submunitions presence

300 250 200 150

Erroneous assessment of hazard Erroneous assessment of level Access Base not in accordance environmental impact Erroneous assessment of threat with the amendments to the Drawing not in accordance with to population 100 Two intended uses of land SOP the SOP recorded Report form not in accordance Photographs not filed in project 50 Superficial or deficient rationale with the SOP documents Incomplete data 0 0 2 4 6 8 10 12 14 16 18 20

Incorrect entry into the base

Failure Classification

all items entered into this database), and 4,140 geo-coded data (13.75% of all entries into the files with geo-coded data). Special attention was paid to the accuracy of the assessment of risk area parameters:

66

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

hazard level, environmental impact level, priority level and intended use of land. These parameters were selected because incorrect assessment here could be expected to have the greatest impact on the final output, reports on the general survey of cluster-ordnance deployment areas. In all 14 different errors were identified, found in 129 instances. All were analysed by the FMEA (See Appendix E: Calculation of failure severity) method in combination with the priority method. The severity of failure was determined under the FMEA method as the product of frequency of failure and its risk factor (Ibid.) A Pareto chart was drawn up, showing that the failures with the greatest impact on the final results were the following: wrong assessment of priority level, wrong assessment of hazard level, and wrong assessment of the probability of the presence of cluster submunitions (Graph 21). Their cumulative share in the severity of failures is 84%. In addition, a high level of risk factor was represented by the wrong assessment of environmental impact, but its incidence was low, so it had no significant impact on the overall results. Other errors had no direct consequences for the end result. However, correcting them required additional efforts from the survey teams. All the mistakes identified were discussed with the survey teams and remedied. Of the total controlled data, errors were found in 1% cases, and in only 0.42% cases they were errors with any significant impact on the results, according to the Pareto chart. Error analysis of the selected sample of 20 survey reports showed that the monitoring team had appropriately determined the priorities in the quality control of the results for three parameters: priority level, hazard level and environmental impact level. As the probability of the presence of cluster submunitions is a parameter for determining the levels of hazard and priority, the three errors mentioned above are interrelated. Thus the high position of the presence of cluster submunitions in the Pareto chart is not surprising. From the qualitative part of the analysis it became clear that determining priorities is the critical process step in the general survey, and that control here should be a focal activity of internal monitoring. Quantitative analysis showed that the incidence of failures of 1% in relation to the overall number of data is low, and acceptable in terms of quality assurance of the final results.

GRAPH 21
Failure severity (risk factor x incidence)
7000 6000 5000 4000 3000 2000 1000 0
Erroneous assessment of priority level Erroneous assessment of hazard level Erroneous assessment of environmental impact Report form not in accordance with the SOP Erroneous assessment of probability of cluster submunitions presence Access Base not in accordance with the amendments to the SOP Erroneous assessment of threat to population Incorrect entry into the base Superficial or deficient rationale Two intended uses of land recorded Drawing not in accordance with the SOP Incomplete data Photographs not filed in project documents Erroneous assessment of deployment zone parameters

100.00% 90.00% 80.00% 70.00% 60.00% 50.00% 40.00% 30.00% 20.00% 10.00% 0.00%

Failure Classification
Pareto chart of errors identified during the control of survey reports

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

67

It may be concluded that the monitoring of the general survey fulfilled its function. The critical points in the general survey process were determined: in the first sub-process, the quality of input data; in the second and third sub-process, hazard assessment and identifying priorities, respectively. On the whole, the monitoring contributed to the improvement of the general survey process, the quality of work carried out by the survey teams, and the reliability of results obtained through the general survey!

68

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

7
T

Strategic assumptions and indicators

he one year of work on the survey, the data collected and the results of the general assessment of the situation have enabled the NPA to define certain strategic assumptions that are the preconditions for successful resolution of the problem of unexploded cluster submunitions in Serbia. Strategic assumptions and their indicators are part of the strategic and operating planning that lies within the purview of the Serbian Mine Action Centre. 1. strategic assumption: In the territory of Serbia, 105 deployment zones of cluster ordnance containing explosive submunitions were identified. It was determined that 196 pieces of cluster ordnance were deployed in these zones (five different types of bombs and other missiles). These deployment zones are not evenly distributed across the Republic. 2. strategic assumption: Almost in all deployment zones, units from the military, police and civil defence had removed unexploded ordnance from the surface, but hazards remained hidden underground. This has made the identification of unexploded cluster submunitions more difficult, and increases the extent of areas for clearance. It is estimated there are still 24.06 cluster submunitions to be removed per deployment zone, giving a total of 2,647 unexploded cluster submunitions in the territory of Serbia (excluding Kosovo). 3. strategic assumption: By November 2008, 390 polygons had been identified, the area suspected of cluster submunitions hazard being 30.7 km2. The average extent of the suspected area is 0.079 km2. This area has formed the basis for the general assessment of the situation concerning unexploded cluster submunitions in Serbia and for projecting future activities related to survey and clearance. The detailed survey will define all the elements necessary for planning clearance assignments, and aid the decision on possible cancellation of parts of the land found not to contain any remnants of unexploded cluster submunitions. 4. strategic assumption: The extent of risk area to be cleared of unexploded cluster submunitions in Serbia has been assessed at 15 km2 to 16 km2. The area surveyed so far is about 8 km2, or 26.7% of the currently suspected total. Continuation of the general survey to accompany the clearance process is necessary for the remaining suspected area to be analysed in detail and for the necessary documents to be prepared. 5. strategic assumption: Given current assessments of the number of unexploded cluster submunitions and the risk area for clearance, the average number of unexploded cluster submunitions per area unit is 171 pieces/km2 of the risk area. It is the success indicator for designing clearance assignments. The average number of cluster submunitions found in the cleared areas in previous years is 74 pcs/ km2 of the cleared area. 6. strategic assumption: According to the Convention on Cluster Munitions, the clearance of unexploded cluster submunitions is to be completed in the course of 10 years. It is ex-

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

69

pected that the Republic of Serbia will join this Convention and that the Convention will enter into effect at the beginning of 2010. This means that the obligation of clearing unexploded cluster submunitions will have to be met by 2020. Given the average to date of 0.682 km2 of cleared area annually, it would take about 23 years to complete clearance of the cluster-ordnance deployment zones. In order to honour its international commitments, Serbia will need to undertake measures to increase the average cleared area to 1.5 1.6 km2 a year. 7. strategic assumption: The survey found that 28 local communities were affected by unexploded cluster submunitions. The assessment of their exposure to the cluster submunitions risk may serve as guide for prioritizing in planning the operations of unexploded cluster submunitions clearance. 8. strategic assumption: About 162,000 people live in the affected local communities. According to current assessments, 88,000 are living in the immediate vicinity of suspected areas, and can thus be considered as exposed to daily risk. Inhabitants of the affected local communities do not feel directly endangered by cluster submunitions, but they do undertake certain precautionary measures, mostly with regard to children, who generally enter the suspected area only in the company of adults; in addition, group entry is preferred to individual entry into the suspected area. The vicinity, entry into the risk area, and children as a threatened group were included in the criteria for selecting priorities for clearance of unexploded cluster submunitions. 9. strategic assumption: In addition to agricultural land as a blocked resource, the largest negative impact is the impact of the impossibility of reconstructing settlement infrastructure, forest exploitation and maintenance, road communication lines, tourism development and housing facilities. Those are also criteria to serve as the basis for the state authorities of Serbia in defining potential benefits as one of the elements for assessing clearance priority. 10. strategic assumption: With greater interest on the part of all stakeholders for resolving the unexploded cluster submunitions problem in Serbia, the need for prioritizing clearance tasks will also increase. A clear and transparent system for determining priorities should be put in place as part of the national policy of mine action, including uniform prioritization criteria, to be followed by all state authorities and other bodies or organizations involved in the process!

70

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

Conclusions
The Cluster Survey in Serbia project started on 9 November 2007, and implementation continued until 30 November 2008. It was carried out as a project of regional cooperation in Southeast Europe. The Mine Action Programme of the NPA in Bosnia and Herzegovina took on responsibility for this project because of its years of experience with general survey. Implementation of the project involved staff from Bosnia and Herzegovina and from Serbia. The Serbian surveyors were trained for independent work in the future, as assistance to the Serbian Mine Action Centre. The project was carried out in three phases: (1) project preparation, (2) preliminary assessment of the situation of unexploded cluster submunitions, and (3) on-the-ground survey and general assessment of areas of cluster ordnance deployment. The general assessment of the situation included assessment of unexploded cluster submunitions hazards and of their socio-economic impact. According to the latest results of the general survey, 105 cluster-ordnance deployment zones are located in the territory of Serbia, in 15 municipalities. Into these deployment zones, 196 cluster ordnances had been fired, involving a total of 37,032 pieces of cluster submunitions. The area suspected of unexploded cluster submunitions was identified. The database of suspected areas contains 390 polygons of the total area of 30.7 km2. Analysis of blocked resources confirmed that the hazard of unexploded cluster submunitions, in combination with the blockage of resources, seriously affects the local socio-economic situation. The general assessment showed that removal of unexploded cluster submunitions will have positive impacts, as follows: (1) improvement of general safety, (2) reduction of risk, especially for the population living in contact with risk areas, (3) increase in the number of the users of currently blocked land, as indicated by the employment structure of threatened local communities. Monitoring of all activities was carried out by the Mine Action Programme Manager, together with the special team for monitoring, and with monitoring by the NPA Southeast Europe Regional Director. Such monitoring contributed to improving the general survey process, the quality of the work done by the survey teams and the reliability of the results obtained. The Serbian Mine Action Centre has taken over the general survey database along with all the documents collected, for use in future surveys and preparing terms of reference for clearance tasks!

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

71

Appendixes
Appendix A: Acronyms and terms used
ACRONYM AS/NZS CCM DESCRIPTION Australian and New Zealand Standard Convention on Cluster Munitions UN Convention on Prohibitions or Restrictions on the Use of Certain Conventional CCW Weapons Which May be Deemed to be Excessively Injurious or to Have Indiscriminate Effects, which came into effect in 1983 (abbreviated: the Convention on Conventional Weapons). ERW IMAS ISO/IEC NPA UXO Glossary OECD SOP UN UN MA Policy Explosive remnants of war International Mine Action Standards International Organization for Standardization Norwegian Peoples Aid Unexploded ordnance Glossary of Key Terms in Evaluation and Results Based Management, OECD, Development Co-operation Directorate, 2002. Standard operating procedures United Nations Mine Action and Effective Coordination: The United Nations Inter-Agency Policy

72

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

TERMS accident accreditation

DEFINITION undesired event resulting in harm the procedure by which a de-mining organisation is formally recognised as competent and able to plan, manage and operationally conduct mine action activities safely, effectively and efficiently individuals, groups or organizations, whether targeted or not, which benefit,

SOURCE IMAS 04.10 IMAS 4.10

beneficiaries

directly or indirectly, from development interventions related terms: target groups an expendable aircraft store consisting of a dispenser and submunitions; a bomb containing and dispensing submunitions that may be mines (antipersonnel or anti-tank), penetration (runway cratering) bomblets, fragmentation bomblets, etc. air bombs, ballistic and artillery missiles projected from ground and air, serving to transport and scatter cluster sub-munitions any munition that, to perform its task, separates from a parent munition, mines or munitions that form part of a cluster bomb unit (CBU), artillery shell or missile payload outcome of an event expressed qualitatively or quantitatively, which has

Glossary OECD

cluster bomb unit CBU

IMAS 04.10

cluster ordnance

cluster submunition

IMAS 04.10

consequence

turned into a loss, harm, setback or gain; may be a series of possible outcomes related to the event process of identifying, predicting, evaluating and reducing the biophysical, social and other relevant environmental impacts of mine actions to be undertaken an incident or situation occurring in a particular place at a particular point in time situation made up of particular set of circumstances conventional munitions containing explosives, with the exception of mines,

AS/NZS 4360:1999

environmental impact assessment

IMAS 04.10

event

AS/NZS 4360:1999 ISO 73:2002

explosive ordnance explosive remnants of war frequency

booby traps and other devices as defined in Protocol II of the CCW Conven- CCW Protocol V tion as amended on May 3, 1996 unexploded ordnance and abandoned explosive ordnance incidence of an event expressed as a number of occurrences of an event in a given period of time CCW Protocol V AS/NZS 4360:1999

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

73

TERMS

DEFINITION process for obtaining a comprehensive inventory of all reported and/or suspected locations of mine or ERW contamination, the quantities and types of explosive hazards, and information on local soil characteristics, vegetation and climate; assessment of the scale and impact of the landmine and ERW problem on the individual, community and country injury or damage to human health, or damage to property or the environment event where hazardous situation results in damage combines the process of hazard identification and hazard level assessment circumstances where people, property or environment are exposed to one or more hazards an event that gives rise to an accident or has the potential to lead to an accident use of products, processes or services in line with the information prepared by the supplier used as a qualitative description of probability or incidence emplacement of a measure or combination of measures to identify the position of a hazard or the boundary of a hazardous area munition designed to be placed under, on or near the ground or other sur-

SOURCE

general mine action assessment

IMAS 04.10

harm harmful event hazard assessment hazardous situation incident intended use likelihood marking

ISO 51:1999 ISO 51:1999

ISO 51:1999

ISO 51:1999 AS/NZS 4360:1999 IMAS 04.10

mine

face area, to be exploded by the presence, proximity or contact of a person or IMAS 04.10. a vehicle Mine action comprises five complementary groups of activities: 1. 2. mine risk education humanitarian de-mining, incl. the following: mine clearance

mine action

survey mapping marking 3. 4. 5. landmine victim assistance, rehabilitation and reintegration stockpile destruction advocacy

IMAS 04.10

74

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

TERMS

DEFINITION includes technical survey, mapping, marking, clearance, post-clearance

SOURCE UN MA Policy

mine and ERW clearance documentation, relating mine action to the community and the delivery and acceptance of cleared land monitor to check, supervise, critically review or record progress in an activity, action or system, on a specified basis, in order to identify changes likelihood of a particular event or outcome, measured as a relation of a particular event or outcome to the total number of potential events or outprobability comes; probability is expressed as a number between 0 and 1, where 0 indicates an impossible event or outcome, and 1 indicates that an event or outcome is certain protective measures risk risk acceptance risk analysis measures to reduce risk combination of probability of an event and its consequences communicated decision that the consequences and potential of certain risk systematic use of information to identify sources and to estimate risk; provides a basis for risk evaluation, risk treatment and risk acceptance area for which hazard of mines and/or ERW has been assessed, for which risk area detailed measurements have been undertaken and characteristics of the land determined, as well as the negative impact and potential benefits after clearance risk assessment risk communication overall process including risk analysis and risk evaluation exchange or sharing of information on risk between decision-makers and other stakeholders part of risk management involving the implementation of policies, stanrisk control risk criteria risk estimation risk identification risk reduction dards, procedures and physical modifications to eliminate or minimize harmful risk requirements to be met in assessing risk significance process used for determining values for probability and consequences process of finding, listing and characterizing elements of risk selective implementation of appropriate techniques and management principles for reducing the likelihood of an event or its consequences, or both

AS/NZS 4360:1999

AS/NZS 4360:1999

ISO 51:1999 ISO 73:2002 AS/NZS 4360:1999 ISO 73:2002

ISO 51:1999 ISO 73:2002

AS/NZS 4360:1999 ISO 73:2002 ISO 73:2002 ISO 73:2002 AS/NZS 4360:1999

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

75

TERMS safety stakeholders

DEFINITION absence of unacceptable risk the persons and organizations that may influence, be influenced by, or observe that they may be influenced, by decisions or activities the individuals, groups or organizations that may influence, be influenced by, or observe that they will by influenced by risk

SOURCE ISO 51:1999 AS/NZS 4360:1999 ISO 73:2002

suspected area

area d efined on the basis of analysis of available information on potential hazard of mines and ERW, representing the basis for general survey operations.

technical survey tolerable risk unexploded ordnance

detailed topographic and technical examination of known or justifiably suspected risk areas identified as such during the general survey risk accepted within the given context and based on the current social values explosive ordnance that has been primed, fused, armed or otherwise prepared for use or used; it may have been fired, dropped, launched or projected but has remained unexploded, through malfunction or design or for any other reason

modified as regards IMAS 04.10 ISO 51:1999 IMAS 04.10.

unexploded ordnance victim

(similar Protocol V CCW) an individual who has suffered harm as a result of an accident and/or the de- IMAS 04.10 pendants of a mine casualty

76

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

Appendix B: Criteria for cancellation of land from the areas suspected of hazard of unexploded cluster submunitions
CODE C1 CRITERIA /DESCRIPTION Asphalt or concrete road surface without any visible major damage. Surface of macadam roads that are used regularly or occasionally, without visible major damage to hard layer. Surfaces with asphalt or concrete sub-layer in place before cluster ordnance deployment, except for places damaged by explosive ordnance deployment. Areas where agricultural works have been carried out after bombing, to depths of more than 50 cm. Areas where new construction structures, now in use, have been erected.

C2

C3

C4

C5

C6

Areas with reconstructed construction structures where roofs have been replaced, and are in use. Agricultural areas in deployment zone, where ploughing has been carried out to depths of 30 cm and more, which have been cultivated for at least two years and where no traces of cluster submunitions deployment have been found. Agricultural areas outside a deployment zone, which have been calculated for a minimum period of two years and where no traces of cluster submunitions deployment have been found. Areas where, according to available data on cluster ordnance deployment, only graphite munitions were used, or other types of air ordnance. Areas not in use because of suspicion of cluster submunitions, and where the distance from the closest deployment zone of cluster ordnance is at least half of the longer axis, and where no traces of cluster submunitions deployment have been found.

C7

C8

C9

C10

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

77

Appendix C: Land use classification system

CODE N01 N02 N03 N04 N05 N06 N07 N08 N09 N10 N11 N12 N13 N14 Forest exploitation and maintenance Tourism development Employment incentives

INTENDED USE

Reconstruction of educational, religious and cultural facilities Transport communications (roads, railways, bridges, ports) Construction of communications facilities River facilities, reconstruction of canals and embankments Water supply New industrial production Reconstruction of power transmission lines and other power facilities Restoring agricultural land use Reconstruction of settlement infrastructure and utilities Reconstruction of housing units Other

78

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

Appendix D: Data by districts, municipalities and settlements


District km2 Niavski Zlatiborski Raki Pinjski Topliki Rasinski Sremski Kososvsko-mitrovaki umadijski Mavanski Grad Beograd Moraviki Total 10.959 4.398 4.093 2.251 2.078 1.764 1.353 1.164 1.077 0.658 0.541 0.416 30,751 Suspected Area Status % 35.64% 14.30% 13.31% 7.32% 6.76% 5.74% 4.40% 3.78% 3.50% 2.14% 1.76% 1.35% 100% Districts in Serbia affected by unexploded cluster submunitions

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

79

Settlements affected by unexploded cluster submunitions 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28

Settlement

Municipality

Suspected Area Status km2 % 13.54% 13.23% 9.03% 7.53% 6.76% 5.74% 5.67% 5.63% 4.40% 3.78% 2.31% 2.23% 2.14% 1.89% 1.88% 1.85% 1.76% 1.62% 1.40% 1.35% 1.35% 1.11% 0.99% 0.84% 0.57% 0.57% 0.45% 0.39% 100.00%

Medosevac Medijana Ladjevci Sjenica Merdare Ravniste Vapa 12 Februar Vojka Belo Brdo LIsina Reljan Jalovik Donji Komren Bumbarevo brdo Jastrebac Sibnica Guncati Samaila Bresnica Gare Cedovo Bogdanovac Bustranje Svinjiste Bapsko Polje Karadnik Strezovce

Crveni Krst Mediana Kraljevo Sjenica Kurumlija Brus Sjenica Crveni Krst Stara Pazova Leposavi Raka Preevo Vladimirci Crveni Krst Kni Bujanovac Sopot Kni Kraljevo Cacak Gadin Han Sjenica Bujanovac Preevo Bujanovac Kraljevo Bujanovac Preevo

4.1638 4.0695 2.7772 2.3144 2.0776 1.7643 1.7429 1.7302 1.3526 1.1637 0.7112 0.6845 0.6582 0.5802 0.5796 0.5686 0.5410 0.4970 0.4304 0.4165 0.4150 0.3409 0.3058 0.2580 0.1754 0.1739 0.1396 0.1188 30.7507

80

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

Number of Directly Settlement Municipality Suspected Area (km )


2

Number of Directly Threatened Inhabitants per km2 of suspected area

Threatened Inhabitants

Suspected area and the number of directly threatened inhabitants per threatened community

12 Februar Bapsko polje Belo Brdo Bogdanovac Bresnica Bumbarevo brdo Butranje Cedovo Donji komren Duvanite Gare Guncati Jalovik Jastrbac Karadnik Laevci Lisina Medoevac Merdare Ravnite Reljan Samaila Sibnica Sjenica Strezovce Svinjite Vapa Vojka Total

Crveni Krst Kraljevo Leposavi Bujanovac aak Kni Preevo Sjenica Crveni Krst Medijana Gadin Han Kni Vladimirci Bujanovac Bujanovac Kraljevo Raka Crveni Krst Kurumlija Brus Preevo Kraljevo Sopot Sjenica Preevo Bujanovac Sjenica Stara Pazova

1.7302 0.1739 1.1637 0.3058 0.4165 0.5796 0.2580 0.3409 0.5802 4.0695 0.4150 0.4970 0.6582 0.5686 0.1396 2.7772 0.7112 4.1638 2.0776 1.7643 0.6845 0.4304 0.5410 2.3144 0.1188 0.1754 1.7429 1.3526 30.7508

23,500 10 500 15 8 50 785

13,582,2 57,5 429,7 49,1 19,2 86,3 3,042,6 0,0

1,750 58,600 7 30 200

3,016,2 14,399,8 16,9 60,4 303,9 0,0

40 5 10 950 139 10 456 15 350 300 650 10 30 200 88,620

286,5 1,8 14,1 228,2 66,9 5,7 666,2 34,9 647,0 129,6 5,471,4 57,0 17,2 147,9 2,881,9

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

81

Share in Population Structure (%)


100%

0-4 years 20-24 years 40-44 years 60-64 years

5-9 years 25-29 years 45-49 years 65-69 years

10-14 years 30-34 years 50-54 years 70-74 years

15-19 years 35-39 years 55-59 years 75-79 years

80%

60%

40%

20%

0% Bresnica Bapsko Polje Duvanite Ravnite Guncati Merdare Sjenica Strezovce Laevci Vapa Gare Butranje Jalovik Belo Brdo Lisina 12. Februar Bumbarevo Brdo Bogdanovac Jastrebac Sibnica Reljan Vojka

Affected communities

Population structure in local communities where survey of individual risk areas was carried out

82

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

10.00%

12.00%

14.00%

16.00%

18.00%

20.00%

0.00% Agriculture, hunting and forestry 4.33% 48.76% 0.00% Fishing 0.01% Mining Process industry 17.13% 2.06% 2.64% 3.82% 6.48% 5.60% 14.93% 1.11% 2.78% 4.56% 7.56% 0.45% 1.93% 1.00% 3.46% 4.94% 9.13% 3.02% 8.24% 3.19% 11.73% 1.60% 3.35% 0.03% 0.02% Agriculture House building Commerce Hotels and restaurants Infrastructure Finanncial institutions Real estate State administration Education Health sector Other service provision Private households 13.54% 0.46% 0.10%

2.00%

4.00%

6.00%

8.00%

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

Employee structure - average percentage for affected communities

Employee structure share in the total number of employees in the affected communities

83
Employment structure in affected communities
Unknown

Other organisations and 0.01% 0.02% bodies 5.83% 6.14%

Appendix E: Calculation of failure severity


Calculation of failure severity Failure Description Total Number of Failures Risk Factor Failure Severity =Number of Failures x Risk Factor

Erroneous assessment of priority level Erroneous assessment of hazard level Erroneous assessment of probability of cluster ordnance presence Drawing not in accordance with the SOP Erroneous assessment of threat to population level Erroneous assessment of environmental impact Erroneous assessment of deployment zone parameters Report form not in accordance with the SOP Access Base not in accordance with the amendments to the SOP Incorrect entry into the base Two intended uses of land entered Superficial or deficient rationale Incomplete data Photographs not filed in project documents

16 14 11 10 6 3 8 18 18 15 2 11 10 3

405 225 225 50 75 100 35 10 10 5 30 5 5 10

6480 3150 2475 500 450 300 280 180 180 75 60 55 50 30

84

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

Failure Severity Degree Very slight failures that do not affect the quality of the report. The failure will not affect the correct assessment of priority. Slight failures that affect assessments. A failure may influence a slight degradation in priority assessment. Medium failure of erroneous assessment. Significantly affects priority determination. Severe failures of erroneous assessment which result in a completely wrong idea of the priority level. Extremely severe failure, where the failure involves potential consequences related to safety. 1 2,3 4,5,6 7, 8, 9 10

Scale for evaluation of the Failure Severity Degree

Failure Occurrence Probability Very low probability Low probability of failure occurrence Medium probability of failure occurrence High probability of failure occurrence Extremely high probability of failure occurrence. Failure occurrence almost certain 1 2,3 4,5,6 7, 8, 9 10

Scale for evaluation of the Failure Occurrence Probability

Difficulty in Failure Detection Low probability that the failure will remain undetected. Failure is obvious. Low probability that the failure will remain undetected. 100% control. Medium probability that the failure will be detected. Random sample control. High probability that a report with failure will be accepted. Sporadic control. Extremely high probability that a report with failure will be accepted. Failure difficult to detect. 1 2,3 4,5,6 7,8,9 10

Scale for evaluation of the Difficulty in Failure Detection

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

85

Appendix F: Calculations of risk area for clearance


CALCULATION BASED ON NUMBER CALCULATION BASED ON SURVEYED AREA STRUCTURE OF AREAS (NUMBER OF LOCATIONS %, AVERAGE MAGNITUDE OF AREA) ASSESSMENT OF (km2) CANCELLATION STALAND RELEASED NUMBER OF LOAREA CATIONS Area Share (km2) dents 100 % cancellation Partial cancellation 8.63% <100% TOTAL 100.00% 344 100.00% 27.575 25.566 2.009 27.575 25.543 2.032 30 8.53% 2.353 14.61% 91.37% 314 91.47% 25.222 100.00% 25.222 of inciShare (km2) Number Release rate Cancelled area TUS PROJECTED SUSPECTED AREA ASSESSMENT OF RELEASED LAND

NUMBER OF AREAS

AREA Release rate

PECTED AREA AND RE-

AVERAGE LOCATION MAGNITUDE

AREA FOR CLEARANCE

PROJECTED SUSPECTED

0.000

25.195

100.00%

25.195

Cancelled area (km2)

0.000

SUSPECTED AREA 0.344 2.009 2.380 14.61% 0.348 2.032

WITHOUT LAND CAN-

344

27,575

0,080

CELLATION

SUSPECTED AREA No cancellations 100.00% 46 100.00% 3.176 0.00% 0.000 3.176 3.176 0.00% 0.000 3.176

WITH PARTIAL LAND

46

3,176

0,069

CANCELLATION 5.185 5.208

TOTAL REMAINING

390

30,751

0,079

SUSPECTED AREA

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

Calculation of risk area for clearance based on the magnitude and number of suspected areas

AREA FOR CLEARANCE

LEASE RATE

AREA (km2)

86

ASSESSMENT OF AREA

FOR CLEARANCE BASED

ON THE PROJECTED

STRUCTURE OF SUS-

DEVIATION (%)

AREA BASED ON LAND RELEASE RESULTS BY HAZARD LEVELS HAZARD LEVELS EXTREMELY HIGH VERY HIGH HIGH MEDIUM LOW TOTAL

RELEASE RATE STANDARD

AVERAGE RELEASE RATE

NUMBER OF LOCATIONS

SUSPECTED AREA (km2)

ASSESSMENT OF RISK

ASSESSMENT FOR CANCELLED AREA (km )


2

ASSESSED AREA FOR CLEARANCE (km2)

(%)

UPPER (Sd+) 0.493 0.469 4.064 9.560 10.060 24.648

AVERAGE 0.179 0.051 3.032 6.485 7.261 17.008

LOWER (Sd-) -0.135 -0.367 1.999 3.409 4.461 9.368

LOWER

AVERAGE

UPPER

6 17 44 186 137 390

0.627 1.139 4.852 11.766 12.366 30.751

28.60% 4.50% 62.48% 55.11% 58.71%

50.06% 36.72% 21.28% 26.14% 22.64%

0.134 0.669 0.788 2.206 2.306 6.103

0.448 1.088 1.821 5.281 5.106 13.743

0.762 1.506 2.853 8.357 7.905 21.383

Calculation of risk area for clearance based on land release rate by hazard levels

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

87

AREA (km2)

AREA (km2)

AREA (km2)

UPPER

LOWER

AVERAGE RELEASE RATE (%)

AVERAGE

LOWER

NUMBER OF LOCA

EXTREMELY HIGH 0.628 2.988 3.511 0.511 8.109 297 22.642 18.247 132 11.855 58.71% 22.64% 9.645 144 8.255 55.11% 26.14% 6.707 15 1.865 62.48% 21.28% 1.562 1.165 4.550 6.961 12.743 5 0.511 4.50% 36.72% 0.211 0.023

NUMBER OF LOCATIONS

0.627

NUMBER OF LOCATIONS

0.471

0.156

28.60%

50.06%

RELEASE RATE STANDARD DEVIA-

0.123

0.045

-0.033 -0.165 0.768 2.392 4.277 7.238

0.505 0.928 3.290 5.058 2.722 12.504

0.583 1.116 3.687 7.216 5.406 18.008

AVERAGE

0.661 1.304 4.084 9.374 8.090 23.512

VERY HIGH

17

1.139

12

HIGH 5

44

4.852

29

MEDIUM

186

11.766

42

LOW

137

12.366

TOTAL

390

30.751

93

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009 ASSESSMENT FOR CANCELLED AREA (km2) TION (%) CLEARANCE (km2) ASSESSED AREA FOR AREA UPPER

88
REMAINING SUSPECTED

ASSESSMENT OF

SUSPECTED

CLEARANCE AREA

RISK AREA

AREA (km2)

BASED ON SURVEYED

RISK AREAS

HAZARD LEVELS

Calculation of risk area for clearance based on the surveyed risk areas

REMAINREMAINING ASSESSMENT SUSPECTED AVERAGE RERISK AREA LEASE RATE (%) OUT CAN(km2) CANCELLATION CELLATION CELLED AREA AREA WITH ANCE AREA (km2) AREA WITHFOR CANPECTED ASSESSED CLEARING SUS-

ASSESSMENT OF CLEAR-

SUSPECTED

ANCE AREA BASED ON

AREA

SURVEYED RISK AREAS

OPTION 1

OPTION 1

OPTION 2

OPTION 2

OPTION 1

AREA (km2)

AREA (km2)

AREA (km2)

NUMBER OF LOCATIONS

NUMBER OF LOCATIONS

NUMBER OF LOCATIONS

EXTREMELY HIGH 12 29 42 5 100.00% 14.769 9.982 93 8.109 269 20.608 0.511 118 11.091 90.00% 11.091 15.593 3.511 132 7.504 60.00% 60.00% 4.502 4.502 2.988 15 1.780 16.00% 0.00% 0.285 0.000 0 12 14 28 0.628 4 0.234 0.00% 0.00% 0.000 0.000 1

0.627

0.471

0.000

0.00%

0.00%

0.000

0.000

NUMBER OF LOCATIONS

0.156 0.277 0.085 0.751 0.764 2.034

AREA (km2)

0.627 1.139 4.568 7.263 2.385 15.982

0.627 1.139 4.853 7.263 1.275 15.158

VERY HIGH

17

1.139

HIGH

44

4.852

MEDIUM

186

11.766

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009 OPTION 2

HAZARD LEVELS

LOW

137

12.366

TOTAL

390

30.751

Calculation of risk area for clearance options

89

Literature
1. AS/NZS 4360:1999, Risk Management 2. Circle of impact: The Fatal Footprint oc Cluster Munitions on People and Communities, Handicap International, Brussels, May 2007, 172 pages 3. Explosive remnanats of war and mines other than anti-personnel mines, Global survey 20032004, Landmine action, London, 2005., 172 pages 4. Foreseeable harm, The use and impact of cluster munitions in Lebanon: 2006, Landmine action, London, 2006., 52 pages 5. Humanitarian, Military, technical and legal chalenges of cluster munition, ICRC, 88 pages 6. IMAS 04.10:2003, Glossary of Mine Action Terms, Definitions and Abbreviations 7. IMAS 08.10:2003, General Mine Action Assessment 8. IMAS 10.10:2001, Safety and Occupational Health 9. ISO 14001:1996, Environmental Management Systems 10. ISO 9001:2000, Quality Management Systems Requirements 11. ISO 9004:2000, Guidelines for Performance Improvements 12. ISO/IEC VODI 51:1999, Safety Aspects Guidelines for their inclusion in standards 13. Lisica Darvin: Standard operating procedures for general survey of the areas affected by cluster ordnances 14. Lisica Darvin: Risk managment in mine action planning, Norvegian peoples Aid, Sarajevo, 2006., 251 pages 15. M85, An analysis of reliability, Norwegian peoples Aid, 2007., 63 pages 16. Yellow killers, The impact of cluster munitions in Serbia and Montenegro, Norwegian Peoples Aid, Belgrade, 2007., 72 pages

90

Norwegian Peoples Aid, Report on impact of unexploded cluster submunitions in Serbia, 2009

Report on the impact of unexploded cluster submunitons in Serbia

Project funded by the Norwegian Ministry of Foreign Affairs

You might also like