Professional Documents
Culture Documents
DEFINITION
In construction, underpinning is the process of strengthening and stabilizing the foundation of an existing building or other structure. (Wikipedia) Underpinning is the process of modifying an existing foundation system by extending it to or into subsurface strata that is deeper and more stable than the near surface soil that support the existing foundation system.
PURPOSES OF UNDERPINNING
To transfer load carried by an existing foundation from its present bearing level to a new level at a lower depth. To replace an existing weak foundation. To allow the adjacent ground level to be lowered. To provide vertical support that is not present in the existing design. To prevent/arrest the settlement of a foundation.
FUNCTIONS OF UNDERPINNING
Remedy for : Uneven loading Unequal existence of subsoil Cohesive soil settlement Deterioration of foundation concrete
Cohesive soil settlement
TRADITIONAL UNDERPINNING
RESIN INJECTION
TYPES OF UNDERPINNING
PERMEATION GROUTING
METHODS OF UNDERPINNING
1. TRADITIONAL UNDERPINNING
same issues as traditional underpinning but the walls must be strong enough to span over the heads of the concrete pile caps which are cast onto the jack pile heads after the hydraulic jacks have been removed. It is used for depths deeper than 1.5m.
3. PERMEATION GROUTING
This is where bores are drilled down into the foundation and floors and a liquid or grout is pressure pumped into the ground. The grout fills all voids and spaces underground and makes the ground more solid and closer to solid footing which means that the foundations are more solid. This is a cheaper way to underpin and has been extremely successful, again it is highly useful where the site is difficult to access or has limited space for maneuver.
Pit Underpinning.mp4 Underpinning, Residential Division.mp4
Pile and beam : Using this system requires that a min-pile must be installed on either side of the affected wall. After the piles have been installed, then brickwork is removed below the wall and reinforced concrete needle beam is used to connect the piles and support the wall. Augered piles or case driven piles can be used with this method of underpinning Piled raft : It is used when the whole structure need to be underpinned. Piles are placed at determined locations by loading conditions, then pocket below footings are broken, and reinforced needle beam are placed to bear the walls load. A ring beam is then built to link all needles and the structure is poured with concrete.
Factors in selecting plants & equipments. Scope of work : Big or small area to underpin Type of underpinning works Method of underpinning works
EXAMPLES
Pit underpinning and soil nailing to allow excavation for a new hospital addition in Rochester. - Hand excavation
Pynford stools
MEASUREMENT
Section H H.1. GENERAL 1. Given as a section in BQ 2. Location and work extent and particulars of existing structure to be underpinned - Shown on drawing under clause B.3.1 - Shown on further drawings which shall accompany BQ 3. Information of the ground, given in accordance with D.1 4. Should state: - limit of length in operation - number of sections contractor may be permitted to undertake at one time. 5. Given separately and so described: - If carried out from both sides OR - If carried out from one side only OR - If carried out from within an existing building 6. Curved underpinning shall be so described
SMM2
WORKS H.2 EXCAVATION 1. Item, stating any particulars: temporary supports to work to be underpinned 2. Excavation, accordance with clauses D.9-10, subject to: - excavate prelim, trenches down to the level of the base of existing foundations -excavate below the level of the base of the existing foundation shall be so described 3. If cutting away projecting foundations, it shall be in metres, stating: - number of courses of footings - dimension of concrete to be removed 4. If prepare the underside of existing work to receive the pinning up of the new, it shall be in metres, stating: -width of existing work
H.3.DISPOSAL OF WATER - Given accordance with clauses D.15-16 H.4.EARTHWORK SUPPORT 1. Given in accordance with clauses D.13-D.14 subject to : So described - Earthwork support to preliminary trenches - Earthwork support below the level of existing foundations base H.5.CONCRETE, BRICKWORK AND ASPHALT -Accordance with the rules of the applicable work sections.
SPECIFICATION
CONCRETE
2.0 3.0 Material s used : shall comply with Malaysian Standard (MS) and with the approval of S.O Classification of concrete mixes - Concrete mix 3.1, 3.2 - Concrete Grade 3.3.2 Concrete Compressive Strength Tests and Compliance - All sampling, curing and testing of concrete, fresh or hardened, shall be
carried out in accordance with MS 26 and the relevant Parts of BS 1881 4.1
4.0
Production of concrete (workmanship) Construction of concrete - In situ /precast Steel Reinforcement Formwork - Design and construction (workmanship) - Classes of formwork 8.2.2, 8.2.3
PILING
Piling shall fulfil General Requirements as per section B.1 (PWD Specs) State the type of pile used, all piles shall comply with S.O approval and MS or BS. Workmanship, and the production of piles shall be state. Elements that are being stressed for piling are : - Marking, Handling and storage of piles - Tolerance in Pile Dimensions - Length Of piles - Pitching and Driving of Piles - Lengthening Piles
Pile shall be tested in accordance to SECTION B.5, fulfilling the General requirement of the PILE TESTING : - Type of test necessary 1.1 - Safety Precautions 1.2 Together with the other relevant steps to be taken such as : - Supervision 3.0 - Reaction system 4.0 - Testing equipment 5.0
ESTIMATING