Professional Documents
Culture Documents
Equipment
BAY 220 kv S'halli line 220 kv Malur line 150MVA TR01 HV 150MVA TR02 HV 150MVA TR01 MV 150MVA TR02 MV 31.5MVA TR01 HV 31.5MVA TR02 HV 66KV BUS COUPLER 66KV LINE1(CESSNA-1) 66KV LINE2(CESSNA-2) 66KV LINE3(DB HALLI) 66KV LINE4(PRIMAL) 66KV LINE5(KB HALLI)
IR test Done Done Done Done Done Done Done Done Done Done Done Done Done Done
Contact Resistance Timing test Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done
PD operation
Local Done Done Done Done Done Done Done Done Done Done Done Done Done Done
Remote
Circuit breaker
Note:
1. Observed air leakage at 220kv S'halli line breaker the same has been rectified by CGL representative. 2. Observed Gas leakage at 66kv line.4 line breaker the same has been rectified by CGL representative. 3. Spring charge indication flag missing in 66/11kv Tr-1 breaker 4. Continuous Spring charging motor trouble of 66Kv tr1 bkr have been attended by CGL person.
Equipment
BAY
IR test Done Done Done Done Done Done Done Done Done Done Done Done Done Done
Polarity Done Done Done Done Done Done Done Done Done Done Done Done Done
Knee pt vg Done Done Done Done Done Done Done Done Done Done Done Done Done Done
Tandelta Done Done Done Done Done Done Done Done Done Done Done Done Done Done
Ratio test Done Done Done Done Done Done Done Done Done Done Done
Remarks
220 kv S'halli line 220 kv Malur line 150MVA TR01 HV 150MVA TR02 HV 150MVA TR01 MV 150MVA TR02 MV 31.5MVA TR01 HV Current Transformer 31.5MVA TR02 HV 66KV BUS COUPLER 66KV LINE1(CESSNA-1) 66KV LINE2(CESSNA-2) 66KV LINE3(DB HALLI) 66KV LINE4(PRIMAL) 66KV LINE5(KB HALLI)
Note:
1. Metering core cable of 66kv line1 found faulty the same has been replaced. 2.Terminals S1 and S2 have been shorted at ct terminal of 66kv line4 ct, the same has to got repaired. 3. Ct's of 66kv line 1,line2,line3 have been repaired by KAPCO representative at site. 4. vermin proofing to be done for all Ct terminal box and marshalling box.
Equipment
BAY 220 kv S'halli line 220 kv Malur line 150MVA TR01 HV 150MVA TR02 HV 150MVA TR01 MV 150MVA TR02 MV 31.5MVA TR01 HV 31.5MVA TR02 HV 66KV BUS COUPLER 66KV LINE1(CESSNA-1) 66KV LINE2(CESSNA-2) 66KV LINE3(DB HALLI) 66KV LINE4(PRIMAL) 66KV LINE5(KB HALLI) BUSBAR panel
Backup relays Done Done Done Done Done Done Done Done Done Done Done Done Done Done
Distance/Diff
BCU
Busbar CSC150
86/LBB Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done
Overfluxin g/REFR
REMARKS
Panels
Done Done Done Done Done Done Done Done Done Done
Done
Note:
1. Faulty power cord of tr1 OCR relay have been rplaced by OCR of spare twin feeder relay. 2.Error of Distance relay of line-4 was not within tolerance. 3. Naming of fusecutouts to be done in 66kv line1 panel is to be done.
Equipment
BAY Feeder-1 Feeder-2 Feeder-3 Feeder-4 Feeder-5 Feeder-6 Feeder-7 Feeder-8 Feeder-9 Feeder-10 Feeder-11 Feeder-12 Feeder-13 Feeder-14 Feeder-15 Feeder-16 Bank1 Bank2 Buscoupler Bus to GND
IR test Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done
Contact Resistance Timing test Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done
BCU Status
Local Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done
Remote
86 tripping Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Faulty
Remarks
Circuit breaker
Note:
1. feeder-1 relay case 9,10 terminal corroded. 2. 86 relay of buscoupler found faulty. 3. Cable to be laid from annunciator panel to 66/11kv tranformer panel. 4
Equipment
BAY Feeder-1 Feeder-2 Feeder-3 Feeder-4 Feeder-5 Feeder-6 Feeder-7 Feeder-8 Feeder-9 Feeder-10 Feeder-11 Feeder-12 Feeder-13 Feeder-14 Feeder-15 Feeder-16 Bank1 Bank2 Buscoupler Bus to GND
IR test Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done
Polarity Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done
Ratio Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done
BCU Status
Remarks
Circuit breaker
Note:
1.Remote trip and protection trip not extended from SAS panel of bank1 and 2. 2. feeder-1 relay case 9,10 terminal corroded. 3. 86 relay of buscoupler found faulty. 4. Cable to be laid from annunciator panel to 66/11kv tranformer panel.
Equipment
BAY 220 kv S'halli line CVT 220 kv Malur line CVT 220 kv BUS PT 66KV BUS PT1 66KV BUS PT1 11KV BANK1 PT 11KV BANK2 PT
POLARITY
RATIO
TANDELTA Done
CVT/POTENTIAL TRANSFORMER
Done Done
Done
Note:
1. Oil leakage observed at r ph cvt of malur line. 2. inter panel PT wiring to be extended for 66kv and 220 kv line
Pending works 1. LA insulation resistance to be done. 2. Contact resitance of 66 kv bus isolators 89A ,89B and 220kv isolator is to checked. 3.220kv line distance relays have to be checked. 4.Remote operations of breakers have to be checked. 4. Battery cells yet to be commissioned. 5. DG set yet to be commisioned. 6.PC tests on transformer. 7.SAS setup to be done.