220KV VIKAS TECH PARK

Equipment

BAY 220 kv S'halli line 220 kv Malur line 150MVA TR01 HV 150MVA TR02 HV 150MVA TR01 MV 150MVA TR02 MV 31.5MVA TR01 HV 31.5MVA TR02 HV 66KV BUS COUPLER 66KV LINE1(CESSNA-1) 66KV LINE2(CESSNA-2) 66KV LINE3(DB HALLI) 66KV LINE4(PRIMAL) 66KV LINE5(KB HALLI)

IR test Done Done Done Done Done Done Done Done Done Done Done Done Done Done

Contact Resistance Timing test Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done

PD operation

Local Done Done Done Done Done Done Done Done Done Done Done Done Done Done

Remote

BCU Status Remarks

Circuit breaker

Note:

1. Observed air leakage at 220kv S'halli line breaker the same has been rectified by CGL representative. 2. Observed Gas leakage at 66kv line.4 line breaker the same has been rectified by CGL representative. 3. Spring charge indication flag missing in 66/11kv Tr-1 breaker 4. Continuous Spring charging motor trouble of 66Kv tr1 bkr have been attended by CGL person.

220KV VIKAS TECH PARK

Equipment

BAY

IR test Done Done Done Done Done Done Done Done Done Done Done Done Done Done

Polarity Done Done Done Done Done Done Done Done Done Done Done Done Done

Knee pt vg Done Done Done Done Done Done Done Done Done Done Done Done Done Done

Tandelta Done Done Done Done Done Done Done Done Done Done Done Done Done Done

Ratio test Done Done Done Done Done Done Done Done Done Done Done

Remarks

220 kv S'halli line 220 kv Malur line 150MVA TR01 HV 150MVA TR02 HV 150MVA TR01 MV 150MVA TR02 MV 31.5MVA TR01 HV Current Transformer 31.5MVA TR02 HV 66KV BUS COUPLER 66KV LINE1(CESSNA-1) 66KV LINE2(CESSNA-2) 66KV LINE3(DB HALLI) 66KV LINE4(PRIMAL) 66KV LINE5(KB HALLI)

Overcurrent relay faulty B ph CT fauly Done

Note:

1. Metering core cable of 66kv line1 found faulty the same has been replaced. 2.Terminals S1 and S2 have been shorted at ct terminal of 66kv line4 ct, the same has to got repaired. 3. Ct's of 66kv line 1,line2,line3 have been repaired by KAPCO representative at site. 4. vermin proofing to be done for all Ct terminal box and marshalling box.

220KV VIKAS TECH PARK

Equipment

BAY 220 kv S'halli line 220 kv Malur line 150MVA TR01 HV 150MVA TR02 HV 150MVA TR01 MV 150MVA TR02 MV 31.5MVA TR01 HV 31.5MVA TR02 HV 66KV BUS COUPLER 66KV LINE1(CESSNA-1) 66KV LINE2(CESSNA-2) 66KV LINE3(DB HALLI) 66KV LINE4(PRIMAL) 66KV LINE5(KB HALLI) BUSBAR panel

Backup relays Done Done Done Done Done Done Done Done Done Done Done Done Done Done

Distance/Diff

BCU

Busbar CSC150

86/LBB Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done

Overfluxin g/REFR

REMARKS

Panels

Done Done Done Done Done Done Done Done Done Done

Done

Note:

1. Faulty power cord of tr1 OCR relay have been rplaced by OCR of spare twin feeder relay. 2.Error of Distance relay of line-4 was not within tolerance. 3. Naming of fusecutouts to be done in 66kv line1 panel is to be done.

220KV VIKAS TECH PARK

Equipment

BAY Feeder-1 Feeder-2 Feeder-3 Feeder-4 Feeder-5 Feeder-6 Feeder-7 Feeder-8 Feeder-9 Feeder-10 Feeder-11 Feeder-12 Feeder-13 Feeder-14 Feeder-15 Feeder-16 Bank1 Bank2 Buscoupler Bus to GND

IR test Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done

Contact Resistance Timing test Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done

BCU Status

Local Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done

Remote

86 tripping Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Faulty

Remarks

Circuit breaker

Note:

1. feeder-1 relay case 9,10 terminal corroded. 2. 86 relay of buscoupler found faulty. 3. Cable to be laid from annunciator panel to 66/11kv tranformer panel. 4

220KV VIKAS TECH PARK

Equipment

BAY Feeder-1 Feeder-2 Feeder-3 Feeder-4 Feeder-5 Feeder-6 Feeder-7 Feeder-8 Feeder-9 Feeder-10 Feeder-11 Feeder-12 Feeder-13 Feeder-14 Feeder-15 Feeder-16 Bank1 Bank2 Buscoupler Bus to GND

IR test Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done

Polarity Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done

Ratio Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done Done

BCU Status

Remarks Case to be changed

Remarks

Circuit breaker

Wiring pending Wiring pending 86 faulty Bus to be cleaned

Note:

1.Remote trip and protection trip not extended from SAS panel of bank1 and 2. 2. feeder-1 relay case 9,10 terminal corroded. 3. 86 relay of buscoupler found faulty. 4. Cable to be laid from annunciator panel to 66/11kv tranformer panel.

220KV VIKAS TECH PARK

Equipment

BAY 220 kv S'halli line CVT 220 kv Malur line CVT 220 kv BUS PT 66KV BUS PT1 66KV BUS PT1 11KV BANK1 PT 11KV BANK2 PT

IR TEST Done Done Done Done Done Done

POLARITY

RATIO

TANDELTA Done

REMARKS OIL LEAKAGE

CVT/POTENTIAL TRANSFORMER

Done Done

Done

Note:

1. Oil leakage observed at r ph cvt of malur line. 2. inter panel PT wiring to be extended for 66kv and 220 kv line

Pending works 1. LA insulation resistance to be done. 2. Contact resitance of 66 kv bus isolators 89A ,89B and 220kv isolator is to checked. 3.220kv line distance relays have to be checked. 4.Remote operations of breakers have to be checked. 4. Battery cells yet to be commissioned. 5. DG set yet to be commisioned. 6.PC tests on transformer. 7.SAS setup to be done.