Billboard series

20mm and 23mm Pitch Series Signs

Billboard Installation Instructions


March 19, 2008

BEFORE YOU START . . . . . . . . . . . 3 UNLOADING AND LIFTING . . . . . . . . 8 MECHANICAL INSTALLATION . . . . . 13 ELECTRICAL INSTALLATION . . . . . 19 CONNECTIVITY . . . . . . . . . . . . . . 21 CAMERA . . . . . . . . . . . . . . . . . . . 25 LIGHT SENSORS . . . . . . . . . . . . . 28 TEMPERATURE PROBE . . . . . . . . . 32 POWER UP SEQUENCE . . . . . . . . 34 ROUTER SETTINGS . . . . . . . . . . . 35 PLAYER.INI FILE . . . . . . . . . . . . . 37 TECHNICAL SPECIFICATIONS . . . . 38

Dynamic outdoor advertising solutions

Part Number 1109610105 rev. A

Excite Billboard Installation Instructions

March 19, 2008

Copyright 2008 Adaptive Micro Systems LLC. All rights reserved. Adaptive Micro Systems 7840 North 86th Street Milwaukee, WI 53224 USA 414-357-2020 414-357-2029 (fax) http://www.adaptivedisplays.com

Adaptive is a registered trademark of Adaptive Micro Systems. Excite is a trademark of Adaptive Micro Systems. All other brand and product names are trademarks or registered trademarks of their respective companies.

The Billboard was shipped with the IP address provided before shipment or with Adaptives default IP address of 10.11.11.254. Adaptives default IP address must be changed during the installation. For instructions, see "Router Settings" on page 35 and "Player.ini File" on page 37. Adaptive recommends logging the new network settings below. Internet Service Provider: Public IP Address: IP Subnet Mask: Gateway IP Address: Primary DNS:

Excite Billboard Installation Instructions (pn 1109610105 rev. A)

Excite Billboard Installation Instructions - Before You Start

March 19, 2008

1.0 Before You Start


1.1 General Guidelines and Requirements Items required (not supplied by Adaptive) Crane requirements: 2-leg sling with minimum length of 20 feet. Lifting beam and slings required. A sling is required for each lifting hook on the Billboard. Cable / DSL modem or router. Internet service and dedicated network settings from an Internet Service Provider (ISP). Log these settings on page 2. Service personnel MUST have full access to all sides of the remote control cabinet on the catwalk after the installation is complete. Obstruction free space is required to fully open both cabinet doors, to access the load center, and service the air conditioning unit. Service personnel MUST have a safe and adequate space around the control cabinet to safely access the control cabinet contents. Review the following Review this manual for installation requirements and guidelines. Technical Specifications on page 38. Remote Control Cabinet Dimensions on page 39. Connectivity Diagram on page 40. Related documentation shipped with the Billboard and the remote control cabinet: 1112610101B Billboard Service Manual 20mm and 23mm Pitch Signs. 1112610103B Billboard Remote Control Cabinet Service Manual.

Sign painting or wrapping The sides and bottom of the Billboard may be painted or vinyl wrapped without affecting the product warranty. Painting or vinyl wrapping the top and/or the back of the Billboard will void the warranty. When painting the Billboard, follow the paint manufacturer's instructions for surface preparation of mill finish aluminum. Torque Specifications Unless otherwise noted, use the following torque specifications on all installation hardware: 3/8" fasteners 20 ft-lbs 1/2" fasteners 43 ft-lbs 5/8" fasteners 90 ft-lbs Apply Anti-Seize to all threaded hardware used in the installation process.

Excite Billboard Installation Instructions (pn 1109610105 rev. A)

Excite Billboard Installation Instructions - Before You Start

March 19, 2008

1.2

Mounting Requirements The Billboard must be installed onto a super-structure designed to withstand live loads and comply with all national and local codes. Live loads include loading from wind and seismic events. Because every Billboard installation is unique, there is no single procedure for mounting Excite Billboards. Sub-structure defined The top and bottom steel angles, aluminum windframe tubes, and steel mounting brackets on the back of the Billboard. Supplied with the Billboard. Super-structure defined Customer or installer supplied structure to which the Billboard is mounted. Superstructures must be approved by a qualified structural engineer. Super-structure design The design of a Billboards support structure depends on a number of factors: mounting methods, building codes, foundation, Billboard size, Billboard weight, Billboard height, wind loading, and seismic loading. The installer must ensure the installation complies with all national and local codes. All installations, super-structure designs, and connections must be designed and approved by a qualified structural engineer. Call Adaptive Micro Systems at 1-800558-7022 for contact information for structural engineering consultants. Drill holes as needed in the Billboards steel framework for fasteners. Drilling holes in any other area will void the Billboards warranty. When drilling holes, follow these guidelines: Connections must be analyzed by a structural engineer. Dissimilar metals must be isolated to avoid galvanic corrosion. Any area on the Billboards frame that had paint removed during mounting must be recoated with paint that is UL recognized to standard UL-1332, category DTOV2. Failure to repaint the area will result in accelerated corrosion of the Billboards structure. Adaptive Micro Systems is not responsible for any failure in the Billboards structure because of this. Failure to comply will void the Billboards warranty.

Excite Billboard Installation Instructions (pn 1109610105 rev. A)

Excite Billboard Installation Instructions - Before You Start

March 19, 2008

1.3

Electrical Requirements Electrical installation must only be performed by a qualified electrician. Electrical connections must comply with all applicable national and local codes.
Notice: Drilling into the Billboard or the control cabinet will void the warranty. It is only acceptable to drill an entry hole into the J-Box located on the back of the Billboard for communication cables.

The following requirements MUST be followed or the warranty will be voided: All internal Billboard cabling must be properly connected and seated. All power wiring MUST be from circuit breaker-protected lines. Do NOT connect to a GFI-protected circuit. A two-pole disconnect device MUST be installed in the building wiring for each branch circuit supplying the Billboard and control cabinet. The Billboard and control cabinet MUST be properly grounded according to the applicable codes (for example, NEC Article 250 and 600, and IEEE 1100-1999). Bring power wiring directly into both the Billboard and the control cabinets load centers. Do NOT drill additional holes into the Billboard or the control cabinet for power wiring. All electrical connections MUST be watertight. Use minimum 80 C copper wire. Torque terminals are as follows:
Wire Gauge 2/0-6 8 10-14 Torque 120 in/lbs 40 in/lbs 35 in/lbs

Do NOT route power and communication wires in the same conduit. Separate conduits MUST be run for communication wires and for power wires. However, fiber optic wire may be run in the same conduit with power wires. If applicable, run separate communication conduits to each Billboard if more than one is installed.

Excite Billboard Installation Instructions (pn 1109610105 rev. A)

Excite Billboard Installation Instructions - Before You Start

March 19, 2008

Grounding Requirements
WARNING! Failure to properly ground the Billboard / control cabinet could result in elevated voltage from lightning entering the Billboard / control cabinet seeking a path to earth. The high voltage can result in electric shock, fires, and the destruction of the Billboard / control cabinet from lightning.

Properly grounding each Billboard / control cabinet is necessary because it is an essential means of preventing shock, shock hazards, and potential fire hazards. Refer to the laminated one page document Earth-grounding AlphaEclipse Signs attached to the outdoor ground lug located near the load center(s). Lightning strike protection A Billboard / control cabinet bonded to an earth ground has a means of dissipating the high voltage and current from a lightning strike. The resistance of the grounding electrode must be as low as possible. However, damage can still occur to a Billboard / control cabinets electronic equipment from lightning voltage transients. Though some surge protection is incorporated into a Billboard / control cabinet, to protect a Billboard / control cabinet from high-voltage lightning transients, surge protectors need to be installed in accordance with NEC Articles 280 and 285. 1.4 Safety High voltage Contact with high voltage may cause death or serious injury. Always disconnect power to unit prior to servicing. High leakage current and earth-grounding It is essential to earth-ground the Billboard and remote control cabinet before connecting the power source. Contacting signs that are not earth-grounded may cause death or serious injury. Do not use the Billboard or remote control cabinet ground-lugs for grounding installation equipment such as welding equipment. Safety equipment Anyone working at the Billboard installation site is required to have personal protection equipment (PPE) such as hard hats, safety glasses, gloves, harnesses, and other appropriate safety equipment. Other Other safety messages appear throughout this manual where appropriate.

Excite Billboard Installation Instructions (pn 1109610105 rev. A)

Excite Billboard Installation Instructions - Before You Start

March 19, 2008

1.5

Identifying your Billboard mounting option After the protective wrap is removed from the Billboard the following mounting options will be visible from the back of the Billboard. Hook without windframe mounting option

Clip with windframe mounting option

Tilt with windframe mounting option

Excite Billboard Installation Instructions (pn 1109610105 rev. A)

Excite Billboard Installation Instructions - Unloading and Lifting

March 19, 2008

2.0 Unloading and Lifting


2.1 Unload Billboard Equipment and Kits

STOP

Before doing anything else, open the control cabinet and ensure all cables are connected and seated properly. During shipping cable connections inside the control cabinet may become loose.

Remove and unpack the remote control cabinet Prepare the remote control cabinet for mounting. Prepare the installation location of the remote control cabinet. Refer to Remote Control Cabinet Dimensions on page 39 for dimensions. Remove the spare parts bin from the truck
WARNING! Possible fire hazard. Only weld the spare parts bin at the mounting feet. Welding the spare parts bin elsewhere may ignite a fire inside, causing damage to the spare parts equipment and/or possible burn injury.

Prepare the spare parts bin for mounting. Prepare the installation location of the spare parts bin. Spare parts bins vary in size and shape, therefore installation and mounting requirements need to be assessed at the installation site. A padlock (not supplied by Adaptive) is recommended to lock the spare parts bin.

Excite Billboard Installation Instructions (pn 1109610105 rev. A)

Excite Billboard Installation Instructions - Unloading and Lifting

March 19, 2008

2.2

Remove Billboard from Shipping Cradle


WARNING! The Billboard poses a crush hazard. Only use lifting hooks to lift the Billboard. Use all lifting hooks when lifting the Billboard. Failure to use all lifting hooks may cause the sign to buckle; potentially resulting in injury or equipment damage, and void the warranty. Crush hazard. Properly secure all equipment or kits before lifting. Notice: Adaptive recommends the use of control ropes attached to the lifting beam to prevent Billboard from spinning during lifting and mounting procedures. Do not lift remote control cabinet by the air conditioning unit, damage to the unit may occur or the weather tight seal may be broken.

1. Attach lifting beam and slings to all lifting hooks on top of the Billboard.
Lifting beam

Sling

Lifting hook

Excite Billboard Installation Instructions (pn 1109610105 rev. A)

Excite Billboard Installation Instructions - Unloading and Lifting

March 19, 2008

2. Remove all bolt hardware securing the Billboard to the shipping cradle. Hook without windframe mounting option
Shipping cradle stringer brackets attached to the Billboard frame.

Remove bolt hardware Shipping cradle

Clip or tilt with windframe mounting option


Do not remove the bolts that secure the shipping cradle bracket to the cradle. Shipping cradle brackets stay attached to the cradle frame. Remove this bolt

Billboard windframe Shipping cradle

Bolt hardware (not applicable to the tilt with windframe mounting option). Cradles hinged support bracket

Excite Billboard Installation Instructions (pn 1109610105 rev. A)

10

Excite Billboard Installation Instructions - Unloading and Lifting

March 19, 2008

3. Lift the Billboard to a vertical position and lift vertically off the shipping cradle.
WARNING! Keep the lifting apparatus taut and directly above the Billboard to prevent the Billboard from swinging forward away from the shipping cradle.

Hook without windrame mounting option

Clip or tilt with windframe mounting option

4. Suspend the Billboard just above the ground, over a working area.
Notice: Do not cut protective wrap from the front of the sign, damage to the driver boards LEDs may occur.

5. Remove the protective wrapping from the Billboard.


Excite Billboard Installation Instructions (pn 1109610105 rev. A) 11

Excite Billboard Installation Instructions - Unloading and Lifting

March 19, 2008

6. Prepare the Billboard for mounting. Hook without windframe mounting option Support the weight of the shipping cradle stringer, and remove the outside bolt hardware and the locking support brackets. Remove the shipping cradle stringers. Repeat the procedure on the remaining shipping cradle stringers.

Bolt hardware

Billboard support bracket Locking support bracket Shipping cradle stringer

Keep all hardware and brackets you will need them later.

Clip with windframe mounting option Loosen the three lower bolts on all the mounting brackets.

Billboard windframe stringer Bolts

Loosen bolts so they do not interfere when mounting the Billboard to the billboard head.

Tilt with windframe mounting option Do NOT remove metal shipping straps until the Billboard is lifted to the billboard head and ready for mounting.
Tilt option mounting hardware bag (one located at each tilt arm)

Adjustable turnbuckle

Tilt support bracket

Metal shipping strap

Excite Billboard Installation Instructions (pn 1109610105 rev. A)

12

Excite Billboard Installation Instructions - Mechanical Installation

March 19, 2008

3.0 Mechanical Installation


WARNING! Do NOT use lifting hooks to mount the Billboard. Remove lifting hooks from Billboard after installation. Notice: Adaptive recommends the use of control ropes attached to the lifting beam to prevent Billboard from spinning during lifting and mounting procedures.
Billboard mounting option Lift and Secure the Billboard Hook without Windframe Lift and Secure the Billboard Clip with Windframe Lift and Secure the Billboard Tilt with Windframe Page 13 14 15

3.1

Lift and Secure the Billboard Hook without Windframe 1. Lift the Billboard to the billboard head. 2. Align and lower the Billboard, verify all the support bracket slot openings engage with the billboard heads stringers.

Support bracket slot opening

3. Ensure Billboard is positioned evenly on the billboard head. DO NOT remove the lifting beam or slings, but allow the billboard head to support the weight of the Billboard. 4. Apply Anti-Seize to bolt threads or the bolts may break. 5. Attach locking support brackets and tighten all bolts to torque specification of 43ft-lbs.
Locking support bolt hardware

Billboard head stringer

Locking support bracket

6. Remove the slings and lifting beam. 7. Remove all lifting hooks from the top of the Billboard. 8. If applicable, repeat procedure for second Billboard; otherwise proceed to Lift and Secure the Remote Control Cabinet on page 18.
Excite Billboard Installation Instructions (pn 1109610105 rev. A) 13

Excite Billboard Installation Instructions - Mechanical Installation

March 19, 2008

3.2

Lift and Secure the Billboard Clip with Windframe 1. Lift the Billboard to the billboard head. 2. Align and lower the Billboard, verify the hanger mounting bracket openings engage with the billboard heads stringers.

Hanger mounting bracket opening

3. Ensure Billboard is positioned evenly on the billboard head. DO NOT remove the lifting beam or slings, but allow the Billboard head to support the weight of the Billboard. 4. If applicable adjust the hanger mounting brackets. Loosen the two upper bolts. Adjust the bracket up or down until it engages the billboard head stringer. Tighten upper bolts to a torque specification of 48ft-lbs.

Upper bolt hardware (torque specifications 48ft-lbs)

Adjust up or down

Billboard head stringer

5. Apply Anti-Seize to bolt threads or the bolts may break. Tighten lower bolt hardware to a torque specification of 20ft-lbs.
Lower hanger bolt hardware (torque specifications 20ft-lbs)

Billboard head stringer

6. Remove the slings and lifting beam.


Excite Billboard Installation Instructions (pn 1109610105 rev. A) 14

Excite Billboard Installation Instructions - Mechanical Installation

March 19, 2008

7. Remove all lifting hooks from the top of the Billboard. 8. If applicable, repeat procedure for second Billboard; otherwise proceed to Lift and Secure the Remote Control Cabinet on page 18. 3.3 Lift and Secure the Billboard Tilt with Windframe 1. Lift the Billboard to the billboard head. 2. Position the tilt support brackets. Remove the metal shipping straps from the top most tilt support brackets. Lower the tilt support brackets onto the billboard head stringer, straddling the Ibeam. Place the adjustable turnbuckle in an upward position, and loosen the turnbuckle so final Billboard adjustments can be made. Lower the billboard until the next level of tilt support brackets can be released clearing the billboard stringer above.

Billboard head stringer

Tilt support bracket (straddle the billboard heads I-beam)

Billboard head I-beam

3. Set tilt angle and temporarily secure the tilt support brackets. Using a ratchet device, draw the bottom of the billboard toward the billboard head. Attach the device to the billboards windframe not to the Billboard. The first notch on the tilt support bracket is for a 7 degree tilt and the second notch is for a 10 degree tilt. The bottom bracket has only one notch.
7 degree tilt notch

10 degree tilt notch

Excite Billboard Installation Instructions (pn 1109610105 rev. A)

15

Excite Billboard Installation Instructions - Mechanical Installation

March 19, 2008

Apply Anti-Seize to bolt threads or the bolts may break. Insert bolt hardware and tighten.

Billboard head I-beam

Insert bolt hardware

4. Start with the bottom row of brackets and attach the mounting strap assemblies to the adjustable turnbuckles. Connect and secure the mounting strap assembly to the turnbuckle.

Insert bolt hardware

Strap assembly

Loosened turnbuckle

Excite Billboard Installation Instructions (pn 1109610105 rev. A)

16

Excite Billboard Installation Instructions - Mechanical Installation

March 19, 2008

Place one strap on each side of the billboard heads I-beam. Connect opposite end of the strap assembly to the back of the tilt support bracket. Tighten turnbuckles to straighten out the strap assemblies; do NOT overtighten, final adjustments will be made after the lifting beam is removed.

Strap assembly hardware

Strap assemblies

Turnbuckle

5. Using a masons line, verify straightness of sign. Adjust the turnbuckles to align billboard face and to adjust loading. 6. DO NOT remove the lifting beam or slings, but allow the Billboard head to support the weight of the Billboard. 7. Remove the slings and lifting beam. 8. Remove all lifting hooks from the top of the Billboard and any wood shipping braces. 9. If applicable, repeat procedure for second Billboard; otherwise proceed to Lift and Secure the Remote Control Cabinet on page 18.

Excite Billboard Installation Instructions (pn 1109610105 rev. A)

17

Excite Billboard Installation Instructions - Mechanical Installation

March 19, 2008

3.4

Lift and Secure the Remote Control Cabinet For more detailed specifications regarding the control cabinet refer to Remote Control Cabinet Dimensions on page 39.
Notice: Do not lift remote control cabinet by the air conditioning unit, damage to the unit may occur or the weather tight seal may be broken.

1. Lift control cabinet to billboard head or your designated area. 2. Ensure both cabinet doors open fully, and you have complete access to the load center and the air conditioning unit before proceeding.

A W T
Excite Billboard Installation Instructions (pn 1109610105 rev. A)

3. Secure control cabinet to billboard head or your designated area.

18

Excite Billboard Installation Instructions - Electrical Installation

March 19, 2008

4.0 Electrical Installation


Electrical installation must only be performed by a qualified electrician. Electrical connections must comply with all applicable national and local codes.
WARNING! Hazardous voltage! Contact with high voltage may cause death or serious injury. Always disconnect main power to unit prior to servicing.

4.1

Wire and Ground the Billboard For Billboard power requirements refer toTechnical Specifications on page 38. 1. Route incoming power conduit into the Billboard load center. 2. Connect incoming power to the main lugs in the load center.

3. Connect the ground lug, located near the load center on the back of the Billboard, to an earth-ground rod.

Ground lug

4. If applicable, repeat procedure for second Billboard or load center.

Excite Billboard Installation Instructions (pn 1109610105 rev. A)

19

Excite Billboard Installation Instructions - Electrical Installation

March 19, 2008

4.2

Wire and Ground the Remote Control Cabinet If a temporary power source is used such as a generator, you may need to adjust the power sensitivity adjustment dial (located on the back of the UPS inside the control cabinet) for normal sign operation. 1. Route incoming power conduit into the control cabinets load center. 2. Connect incoming power to the main lugs in the load center.
TO MINIMUM 30A 120/240VAC, 4-WIRE SERVICE
G L1 L2 N

LOAD CENTER
G 20 20

TO CP13 RECEPTACLE

CP14 LIGHT

120VAC CP12 AC UNIT N L1 G 120VAC

CP13 RECEPTACLE G N L1 120VAC L2

3. Connect the ground lug, located near the load center on the control cabinet, to an earth-ground rod.
Load center

Ground lug

Excite Billboard Installation Instructions (pn 1109610105 rev. A)

TO CP13 RECEPTACLE

REMOTE CONTROL CABINET - POWER

20

Excite Billboard Installation Instructions - Connectivity

March 19, 2008

5.0 Connectivity
5.1 Remote Control Cabinet Components Only one remote control cabinet is required, even in dual (Master / Master) Billboard configurations. However, each Billboard does require a dedicated PC controller, USB to RS485 adapter, network adapter (PoE for camera), and Fiber / DVI converter to operate independently. These components will be labeled with a #1 or #2 for quick identification. All other components inside the cabinet are shared by either Billboard without conflict.
Inside view of remote control cabinet (dual Billboard configuration).

Network shelf KVM switch (Keyboard, Video, and Mouse switch)

PC controller board

UPS

Top view of Network shelf (dual Billboard configuration).

Cable / DSL modem (customer supplied) USB to RS485 adapters

Network router Network adapters (PoE)

Fiber / DVI converter

Excite Billboard Installation Instructions (pn 1109610105 rev. A)

21

Excite Billboard Installation Instructions - Connectivity

March 19, 2008

5.2

Connect the Cable / DSL Modem 1. Place the Cable / DSL modem (customer provided) on the top shelf in the control cabinet. 2. Route the Internet service cable conduit into one of the openings on the bottom of the control cabinet. The cable conduit entry point must have a water tight seal. 3. Connect the Cable / DSL modem to the Internet port on the Network router.
Inside view of remote control cabinet

Network router Network (top) shelf

UPS

4. Plug the Cable / DSL modems power cable into the open receptacle in LOAD 3 on the back of the UPS.
UPS rear view

Plug Cable / DSL modem into this receptacle.

Excite Billboard Installation Instructions (pn 1109610105 rev. A)

22

Excite Billboard Installation Instructions - Connectivity

March 19, 2008

5.3

Connect Fiber Optic and RS485 For dual Billboard installations determine which Billboard will be considered #1 and #2. Ensure the control cabinet components labeled with #1 or #2 are routed to the appropriate Billboard.
Notice: Do not use excessive force when connecting the fiber optic cabling or damage to the connectors or the converter ports may occur, resulting in garbled messages appearing on the Billboard.

1. Remove the cover on the J-Box. 2. Install weather tight conduit from the remote control cabinet to the J-Box on the back of the Billboard (lower right side). 3. Drill a hole in the J-Box for the conduit containing the fiber optic and RS485 cables. 4. Route the fiber optic and RS485 cables through the conduit from the remote control cabinet into the J-Box. Note: Any extra cable slack can be coiled and stored in the bottom of the control cabinet. 5. At the Billboard, connect the fiber optic cable to the fiber optic converter, matching the cables to the numbered ports. The fiber ends will click into place on the converter.
Inside view of J-Box

RS485 terminal block

Match labels on fiber optic cables to the numbers on the converter.

6. Connect the RS485 wires to the RS485 terminal block inside the J-Box.
RS485 terminal block

1 2 3 4 5

+RS485 - BLACK -RS485 - RED RS485 wires routed from the control cabinet. SHIELD / BARE

Excite Billboard Installation Instructions (pn 1109610105 rev. A)

1 2 3 4 5

23

Excite Billboard Installation Instructions - Connectivity

March 19, 2008

7. Secure the cover back onto the J-Box. 8. Inside the control cabinet, connect the RS485 wires to the USB to RS485 adapter. Route the RS485 wires to the USB to RS485 adapter on the top shelf of the control cabinet and cut to length. Strip 3/8" of insulation off the ends of the RS485 wires. Connect the RS485 wires to the pinout shown in the following diagram.

SHIELD / BARE (Pin 5) +RS485 - BLACK (Pin 2) -RS485 - RED (Pin 1)

9. Inside the control cabinet, connect the fiber optic cable to the fiber optic converter (on the top shelf of the control cabinet), matching the cables to the numbered ports.

Match labels on fiber optic cables to the numbers on the converter.

10. If applicable, repeat procedure for second Billboard.

Excite Billboard Installation Instructions (pn 1109610105 rev. A)

24

Excite Billboard Installation Instructions - Camera

March 19, 2008

6.0 Camera

6.1

Assemble Camera Mount Assembly 1. Attach camera mount assembly to the 8-foot tube (A). 2. Attach Ethernet cable to camera. 3. Weather proof the cable to camera connection with silicone. 4. Run cable through the tube (B). 5. Install tube section (C) to the billboard head. Mount to the bottom of the billboard head, catwalk, or on the side of the toe kick.

Excite Billboard Installation Instructions (pn 1109610105 rev. A)

25

Excite Billboard Installation Instructions - Camera

March 19, 2008

6.2

Lift Camera Pole

A B C

1. Lift the tube / camera assembly (A and B) up to the billboard head near tube (C) that was previously mounted. 2. Run the Ethernet cable through this tube (C). 3. Slide the tube / camera assembly (A and B) into the mounted tube (C) and attach the hardware to keep the tubes firmly in position. 4. Position the camera angle so it views the complete Billboard face and tighten hardware to keep it from moving. 6.3 Connect the Camera to the Remote Control Cabinet Locate the plastic bag inside the control cabinet that contains two reducer washers and one strain relief connector (two sets will be available for dual Billboard configurations). 1. Place the rubber enclosure gasket and reducer washer (protruding side up) onto the feedthru body. Insert the compression gasket and install the compression nut but do not tighten.
Reducer washer (protruding side up) Rubber enclosure gasket

Feedthru body

Compression gasket

Compression nut

Excite Billboard Installation Instructions (pn 1109610105 rev. A)

26

Excite Billboard Installation Instructions - Camera

March 19, 2008

2. From underneath the control cabinet, insert the feedthru body into one of the conduit openings. 3. On the inside of the control cabinet, place the protruding side of the reducer washer down over the feedthru body, and install the enclosure nut onto the feedthru body.
Notice: Do not use the compression nut to tighten the assembly, damage to the threads may occur.

4. Hold the feedthru body and hand tighten the enclosure nut.
Enclosure nut Reducer washer (protruding side down)

Hold here when tightening the assembly

Control cabinet footing

Connect the Ethernet cable 1. Route the Ethernet cable from the camera to the remote control cabinet. 2. Route the RJ45 connector of the Ethernet cable from the camera through the compression nut, compression gasket, and feedthru body into the control cabinet.
Outdoor Ethernet cable

3. On the top shelf of the control cabinet, connect the RJ45 connector to the camera port on the network adapter (PoE injector), leaving a little slack inside the control cabinet.

Camera port

4. Tighten the compression nut until the compression gasket is tight around the cable. It is tight enough when you pull on the cable and it doesnt move. To improve the seal around the Ethernet cable, wrap the cable with electrical tape or a short length of tubing. 5. If applicable, repeat procedure for second Billboard camera.
Excite Billboard Installation Instructions (pn 1109610105 rev. A) 27

Excite Billboard Installation Instructions - Light Sensors

March 19, 2008

7.0 Light Sensors


7.1 Assemble Light Sensors 1. Position the first light sensor on the light sensor assembly. 2. Insert screws into the holes (6 per sensor) and tighten.

3. Attach the second light sensor in the same manner.

Excite Billboard Installation Instructions (pn 1109610105 rev. A)

28

Excite Billboard Installation Instructions - Light Sensors

March 19, 2008

7.2

Mount the Light Sensor Assembly 1. Mount the light sensor assembly. Attach the assembly to an I-beam in a location that receives similar light as the Billboard. Mount the light sensor assembly just above the top of the Billboard. Mount the light sensor assembly with the light sensors facing in an East / West direction.

Excite Billboard Installation Instructions (pn 1109610105 rev. A)

29

Excite Billboard Installation Instructions - Light Sensors

March 19, 2008

Sample light sensors mounted facing East / West directions.

Notice the light sensor assembly barely extends above the Billboard so it will not be visible from a distance.

Excite Billboard Installation Instructions (pn 1109610105 rev. A)

30

Excite Billboard Installation Instructions - Light Sensors

March 19, 2008

7.3

Connect Light Sensors to Billboard 1. Connect the cables from the light sensors to the panel mount connectors on the back of the Billboard.

2. Line up the connectors and gently push the light sensor connector into one of the connectors on the back of the Billboard. Note: The light sensors can be connected to any one of the three ports on the back of the Billboard. The other port is for the temperature probe. 3. Turn and push in the locking sealer in a clockwise direction. 4. Once the sealer goes in, turn 1/2 turn clockwise. 5. Repeat the process for the second light sensor. 6. If applicable repeat procedure for the second Billboard.

Excite Billboard Installation Instructions (pn 1109610105 rev. A)

31

Excite Billboard Installation Instructions - Temperature Probe

March 19, 2008

8.0 Temperature Probe


8.1 Mount the Temperature Probe
Bendable mounting plate Mounting holes Conduit holes

Temperature probe vents point downward

25ft cable and connector

Mount the temperature probe with the vents pointing down in a location where it can record the ambient temperature and is NOT in direct sun light. NOTE:If possible, mount the temperature probe to the billboard head just beneath the Billboard but NOT in direct sun light, and never mount directly to the Billboard.

Excite Billboard Installation Instructions (pn 1109610105 rev. A)

32

Excite Billboard Installation Instructions - Temperature Probe

March 19, 2008

8.2

Connect the Temperature Probe to the Billboard 1. Connect the temperature probe cable to the panel mount connectors on the back of the Billboard.

2. Line up the connectors and gently push the temperature probe connector into one of the connectors on the back of the Billboard. Note: The temperature probe can be connected to any one of the three ports on the back of the Billboard. 3. Turn and push in the locking sealer in a clockwise direction. 4. Once the sealer goes in, turn 1/2 turn clockwise. 5. If applicable, repeat procedure for second Billboard.

Excite Billboard Installation Instructions (pn 1109610105 rev. A)

33

Excite Billboard Installation Instructions - Power Up Sequence

March 19, 2008

9.0 Power Up Sequence


WARNING! Hazardous voltage may be present in cabinet. Contact with high voltage may cause death or serious injury. Always disconnect power to equipment prior to servicing.

The Billboard must be powered on and off in a specific order to prevent garbled messages and other display abnormalities. The Billboard is powered on and off in the same sequence. To power the sign on: 1. Power on the load center on the back of the sign. 2. Power on the load center on the remote control cabinet. Ensure all control cabinet components are powered on. To power the sign off: Always exit all operating software programs before removing power from the remote control cabinet. 1. Power off the load center on the back of the sign. 2. Power off the load center on the remote control cabinet. 3. Press and hold the ON/OFF/STANDBY button on the UPS to disable the back up battery system.

Excite Billboard Installation Instructions (pn 1109610105 rev. A)

34

Excite Billboard Installation Instructions - Router Settings

March 19, 2008

10.0 Router Settings


To communicate with the Billboard, the Network settings on the router and PC Controllers must match the dedicated IP address you received from your Internet Service Provider (ISP) and logged on page 2. If the new IP address was given to Adaptive prior to the shipment of the Billboard this procedure can be skipped. 10.1 Changing the Router Settings 1. If applicable, unlock the LCD monitor keyboard drawer (KVM). 2. Pull the front handle and slide unit out until it stops. 3. Lift handle up to open the LCD monitor keyboard drawer. 4. Press the power on button (A). 5. Press the number 7 selection button to access the PC Controller 1 desktop.
Drawer handle Drawer lock

Flip monitor open

ON/OFF button

#7 Selection button (PC Controller 1)

#8 Selection button (PC Controller 2)

6. Open a browser in Internet Explorer and type http://192.168.0.100 in the browser address bar and click Enter. A login appears, type admin for the login and password. 7. Click the Basic Settings link under the Setup section of the main menu.

Excite Billboard Installation Instructions (pn 1109610105 rev. A)

35

Excite Billboard Installation Instructions - Router Settings

March 19, 2008

8. Fill in the Network routers Basic Settings as shown in the following diagram:

Select No.

Select Use Static IP Address. Enter * IP Address Enter * IP Subnet Mask Enter * Gateway IP Address Select Use These DNS Servers. Enter * Primary DNS address

Click Apply to save your settings * Provided by your Internet Service Provider.

Excite Billboard Installation Instructions (pn 1109610105 rev. A)

36

Excite Billboard Installation Instructions - Player.ini File

March 19, 2008

11.0 Player.ini File


To communicate with the Billboard(s), the IP Address (provided by the Internet Service Provider) must be updated in both PC controllers player.ini files. If the new IP address was given to Adaptive prior to the shipment of the Billboard this procedure can be skipped. 11.1 Changing the Player.ini.file 1. Pull out the LCD monitor keyboard drawer and press the power on button. 2. Press the number 7 selection button to access the PC Controller 1 desktop. 3. Select Start > My Computer > Hard Disk > User > Config and double click the player.ini file. The following information will appear on your screen: [Settings] model=AlphaEclipse Excite drawlostframes=0 rows=144 columns=448 dotpitch=20 palette=RGB colordepth=24 driverx=16 drivery=16 serialnumber= hwport+COM3: ftpport=40003 pasvaddress=10.11.11.254 pasvport=40100 pasvrange=50 lightsensors=2 tempsensors=1

Change the IP Address after the equal sign to match the IP Address provided to you by your Internet Service Provider.

4. Click Save. 5. If installing dual Billboards press the number 8 selection button and repeat Steps 3 - 4 for PC controller 2.

Excite Billboard Installation Instructions (pn 1109610105 rev. A)

37

Excite Billboard Installation Instructions - Technical Specifications

March 19, 2008

12.0 Technical Specifications


The most current specifications are maintained on Adaptives website www.adaptivedisplays.com. 12.1 20mm Billboard Specifications
Height Rows Cols Ft 144 144 144 160 176 176 176 208 432 448 528 336 352 608 736 720 9 9 9 10 11 11 11 13 In 6 6 6 6 6 6 6 6 Ft 28 30 36 22 24 40 48 48 In 6 6 Hooks 2800 2900 3400 2500 2800 4700 5600 6400 Width Sign weight with mounting options (pounds) Clips / Windframe 3400 3500 4100 2900 3300 5500 6600 7600 230VAC Number of Power Power Tilt / Total current Entries Entry A Windframe REQ (Amp) (Amp) 3800 3900 4500 3200 3600 6000 7200 8400 1 1 1 1 1 2 2 2 69 72 85 61 69 119 144 167 69 72 85 61 69 64.9 78.5 89.9

Power Entry B (Amp) 54.1 65.5 77.1

12.2 23mm Billboard Specifications


Height Rows Cols Ft 128 128 128 144 144 144 144 176 384 400 464 288 304 480 670 624 9 9 9 11 11 11 11 13 In 6 6 6 Ft 29 30 35 22 23 36 48 47 In Hooks 2900 2900 3400 2400 2500 3800 5100 6000 Width Sign weight with mounting options (pounds) Clips / Windframe 3500 3500 4200 2800 3000 4500 6000 7200 230VAC Number of Power Power Tilt / Entries Total current Entry A Windframe REQ (Amp) (Amp) 3900 3900 4700 3100 3300 5000 6600 8200 1 1 1 1 1 2 2 2 75 79 91 64 67 106 140 167 75 79 91 64 67 58.9 77.8 91.1

Power Entry B (Amp) 47.1 62.2 75.9

12.3 RS485 Hub block diagram

RS-485 Hub
5VDC in Sign RS-232 PC Controller RS-485 RS-485 RS-485 Turbo Distribution Board in Sign RS-485 Temperature Probe Light Sensor Light Sensor

Excite Billboard Installation Instructions (pn 1109610105 rev. A)

38

Excite Billboard Installation Instructions - Technical Specifications

March 19, 2008

12.4 Remote Control Cabinet Dimensions


All dimensions shown are in inches.
5X 6.10

6.31 2X 10.50 4X 3.25

2X 10.50

5X 1.375 HOLE FOR 1 " CONDUIT FITTINGS

2X 2.19

6X

.52

3X 2.75

3X 19.50

8.84 39.38

10.00

8.85

14.75 30.16 24.00

9.91 3.50 10.00 3.94 25.00 7.59 12.50 27.69 7.60

GROUND LUG FOR CUSTOMER SUPPLIED EARTH GROUND

4.00 1.73 3.80 22.66 17.40 25.00 70.32 22.66

Excite Billboard Installation Instructions (pn 1109610105 rev. A)

39

Excite Billboard Installation Instructions - Technical Specifications

March 19, 2008

12.5 Connectivity Diagram

Billboard Remote Control Cabinet


Internet Service Provider (ISP) Modem Customer Supplied ISP IN
Power From UPS Unswitched

Router

Ethernet IN

POE 1

To Camera

KVM Switch
Power From UPS Unswitched

Fiber optic Transmitter KVM Cable DVI Cable

To Fiber Optic Receiver

USB Cable

USB to 485 Converter

To "J" Box RS-485

PC1
Power to PC2

USB Cable

Power to Router

Envirosense USB Cable


Door Switches

UPS

Excite Billboard Installation Instructions (pn 1109610105 rev. A)

40

Excite Billboard Installation Instructions - Technical Specifications

March 19, 2008

Sign
Light Sensor 1 Light Sensor 2

Camera 1 Turbo
Located in bottom sign enclosure

RS-485 HUB
Mounted on back of Sign

J Box
Mounted on back of sign

Fiber Optic Cable

RS-485 Cable

Excite Billboard Installation Instructions (pn 1109610105 rev. A)

Fib R e er O c e pt ive ic r

Temp Probe

41

Excite Billboard Installation Instructions - Technical Specifications

March 19, 2008

Billboard Remote Control Cabinet


Internet Service Provider (ISP) Modem Customer Supplied ISP IN
Power From UPS Unswitched

Router

Ethernet IN

POE 1

To Camera Sign 1

KVM Switch
Power From UPS Unswitched Power From UPS Unswitched

POE 2

To Camera Sign 2

Fiber optic Transmitter KVM Cable DVI Cable

To Fiber Optic Receiver Sign 1

USB Cable

USB to 485 Converter

To "J" Box RS-485 Sign 1 To Fiber Optic Receiver Sign 2

PC1
KVM Cable USB Cable Fiber optic Transmitter DVI Cable

USB Cable

USB to 485 Converter

To "J" Box RS-485 Sign 2

PC2
Power to PC2 Power to PC1 Power to Router

Envirosense USB Cable


Door Switches

UPS

Excite Billboard Installation Instructions (pn 1109610105 rev. A)

42

Excite Billboard Installation Instructions - Technical Specifications

March 19, 2008

Sign 1
Light Sensor 1 Temp Probe Light Sensor 2

Sign 2

Camera 1 Turbo
Located in bottom sign enclosure

Light Sensor 1

J Box
Mounted on back of sign

Turbo
Located in bottom sign enclosure

RS-485 HUB
Mounted on back of Sign

J Box Fiber Optic Cable


Mounted on back of sign

RS-485 Cable Fiber Optic Cable

RS-485 Cable

Excite Billboard Installation Instructions (pn 1109610105 rev. A)

Fib Re er O c e pt ive ic r

Camera 2

Temp Probe

Fib R e er O c e pt ive ic r

Mounted on back of Sign

Light Sensor 2
43

RS-485 HUB