You are on page 1of 292

Information Technology and Communications Complex Saudi Arabia - Riyadh

MEP Design Verification Report Underground Services Final Report Report No. 1 Prepared for Drake & Scull International
January 14th, 2012
Rev 1

Quality Control Sheet

Project Location Client Att. Prepared by Contact person

ITCC- 18 Parcels Riyadh, KSA Drake & Scull International Mr. Saher Kamal, Project Director Jain Consultants International Ammar Nahya , CEO Amman/ 7th Circle beside Royal Jordanian H.Q. P.O. Box 143833 Amman 11814 Jordan Tel: +962-6-5857690 Fax: +962-6-5857035 Email: jordan@Jainengineering.com Drake & Scull International PO Box 15130 Riyadh 11444 Kingdom of Saudi Arabia Tel: +966 1 464 3037 Fax: +966 1 464 3375 Mr. Saher Kamal, Project Director

Submitted to

Contact person Document Register: Item DVR251011 Quality Control Log: Item DVR251011 Originator SIM, IMH Revision No. 1 Date

January 14 , 2012

th

Description MEP Design verification report #1

Reviewer AMH, IMH

Authorized By ASN

DVR 251011/109

P a g e | 2 / 292

Table of Contents

DVR 251011/109

P a g e | 3 / 292

TABLE OF CONTENTS

I. II.

III.

IV.

V. VI.

PROJECT INFORMATION ..................................................................................... 5 EXECUTIVE SUMMARY ........................................................................................ 5 A. INTRODUCTION ............................................................................................... 5 B. METHODOLOGY ............................................................................................... 6 C. SUMMARY OF FINDING S ............................................................................... 6 1. MECHANICAL ............................................................................................. 7 2. ELECTRICAL .............................................................................................. 8 RECOMMENDATIONS ........................................................................................... 9 A. MECHANICAL ................................................................................................... 9 B. ELECTRICAL ..................................................................................................... 9 DETAILED ANALYSIS ............................................................................................ 57 A. MECHANICAL ................................................................................................... 57 1. PUBLIC HEALTH......................................................................................... 57 2. HVAC .............................................................................................................. 173 3. FIRE FIGHTING ........................................................................................... 173 B. ELECTRICAL ..................................................................................................... 174 1. GROUNDING & LIGHTNING PROTECTION ........................................ 174 2. NORMAL & EMERGENCY LIGHTING .................................................. 202 3. POWER & LOW VOLTAGE DISTIBUTION ........................................... 202 4. IT NETWORK ............................................................................................... 202 5. FIRE ALARM & DETECTION ................................................................... 202 REFERENCE STANDARDS .................................................................................... 203 APPENDICES ..................................................................................................... 205

DVR 251011/109

P a g e | 4 / 292

I.

PROJECT INFORMATION
The project is located in the northern part of Riyadh at the intersection of Imam Saud Street and Takhasusi Street. The project consists of 13 buildings with a total built up area of 431,304 m2 divided into several building types of commercial and retail. The MEP design was done by Zuhair Fayez Partnership Consultants and the MEP contract was awarded to Drake & Scull International DSI. As a part of their contractual agreement, DSI is required to verify the MEP design for: 1- Validity 2- Constructability 3- Functionality DSI has signed a contract with Jain Engineering Consultants International to verify the MEP design and issue their results in stages to coincide with construction activities. Since the main contractor is near casting the lowest basement slab, it is important for DSI to verify design of services below that slab (Drainage, sump pits, groundingetc) and produce related shop drawings first.

II.

EXECUTIVE SUMMARY A. Introduction


The purpose of this report is to provide information regarding the design validation of the MEP systems for the Information Technology and Communications Complex (ITCC)- 18 Parcels Project in Riyadh, KSA. The design review was conducted to highlight any potential impact caused by the design on the construction activities of the project. The point of view expressed in this report is that of the author which is based on International Practices and Standards. It is no meant to be condemnatory or judgmental of the current design. The intention of this report is to highlight issues related to the progress of engineering works such as production of shop drawings and materials ordering. The design review was conducted on sample areas of the project for each discipline of the MEP systems as per the scope of work. This spot check is an indication of the general condition of the design and must not be taken as a complete list of design issues that might impact construction activities. The design reviewer reserves the right to highlight more issue should they arise in the future. The information presented in this report is based on the Issued for Construction (IFC) drawings, specifications and relevant calculations issued for the project. It must be noted that the review was done without altering any design parameters used by the original designer. The following is a summary of the design review for the underground MEP systems for all buildings. Supporting documents and more information may be found in subsequent sections (Underground services for this report means: All services

DVR 251011/109

P a g e | 5 / 292

running below the lowest slab in a building and do not include analysis of underground services running outside the building):

B. Methodology
A comprehensive review of IFC documents (MEP drawings, specifications and calculations) was carried out using the best up-to-date quality assurance procedures to identify best practice that should be used and current problems in the design that should be avoided. The verification also considers the requirements for installation, commissioning, operation and control and subsequent maintenance of systems selected at the design stage. The design verification process provides information on required design inputs, outputs and practical key design watch-points for MEP building services topics which will lead to improvements in the subsequent implementation of the design, and reduce the risk of problems occurring during installation, commissioning or system operation. This was expressed as a summary tables as shown in further pages. These tables are then followed by detailed analysis for the drawings or specifications. The analysis will include minor and major comments, inconsistency and contradiction between drawings and/or drawings against specifications, lack of coordination with other trades and ended by recommendations.

C. Summary of Findings
Tables (M.1-M.13 & E.1-E.13) provide a summary of the following: 1. Availability of design documents: The review included checking for completeness of design documents such as drawings, specifications, calculations, detailsetc 2. Consistency between design documents within the same discipline: The review included examination of level of consistency between design documents prior to checking against sample outputs 3. Coordination between design documents of an MEP discipline and other disciplines: The review included examination of coordination level between various disciplines such as between drainage and structural or grounding and structural 4. Compliance of design with International Standards and project requirements listed in the specifications: The review included examination of compliance level of the design with projects standards The following observations were noted for the systems reviewed namely Underground Services: 1. Some data are available for some buildings but not others, such as details drawings; we have assumed such data are typical to all buildings. 2. Some buildings designs were compliant with specifications requirements but others were not 3. Some designs that comply with specifications requirements were not compliant with International Standards listed in the same specifications

DVR 251011/109

P a g e | 6 / 292

4. Many of the designs did not comply with sample calculations outputs. The following is a summary of review result for Mechanical and Electrical disciplines: 1. Mechanical: a. HVAC (Not included in this report) b. Water (Only for underground services) The design does not contain any water tanks or pipes that shall impact underground services c. Waste and Soil Drainage (Only for underground services) The following is a summary of findings in regards to above system. More details, calculations and references may be found in subsequent sections: i. ii. iii. iv. In general, it appears that gravity pipe sizes are adequate and in some cases oversized which is acceptable In many cases, the forced flow discharge pipes are undersized (Up to 1000 Pa/m) There are many discrepancies in regards to sump pit sizes and depths between MEP floor plans, calculations and structural plans and sections Many sump pit sizes were underestimated. Detailed calculations were done and sizes on design drawings were found to be less than required either due to deep pipe falls, pump physical size or flow Sump pump calculations in many buildings were based on incorrect parameters. Such parameters include incorrect fixture units, rainfall intensities, areasetc Slopes of many pipes are not as per standards (UPC or IPC) In many cases where pipes are running in a raft slab, the long pipe run final elevation is close to raft bottom. This is an issue that a structural engineer must review and provide an opinion. Also, this shall impact pit depths Pipe connection between elevator drain to sump pit is not considering the low level of elevator drain connection. Also, flow from fire fighters elevator drain is not considered in pump sizing There are no sand traps at the entry of sump pits There are no information (size, capacity, calculationsetc) provided for grease trap in WH06. Location of grease trap is close to populated areas which is going to cause bad odors to transfer to restaurant and other areas. Also, the grease trap is not shown on structural drawings There is no service connection to grey water tank in WH06 shown on plans or riser diagrams. All drainage from above floors is directly connected to waste water network outside the building without any recycling. Note that the design includes a set of calculations for this tank.

v.

vi. vii.

viii.

ix. x.

xi.

DVR 251011/109

P a g e | 7 / 292

xii.

xiii.

xiv. xv.

In other buildings waste pipes are not connected to either external network or grey water tanks There are many discrepancies in regards to grey water tank size between calculations, plans and structural drawings (In KB01, calculated size was 102 m3 and on MEP plans is shown as 216 m3) All grey water tanks are oversized. In general, this is acceptable for other types of tanks. However, in a grey water system it is dangerous to store untreated water more than 72 hours (IPC). It was found that tanks were sized to store grey water for an average of 6-7 days Most of grey water tanks are not provided with vent, make up water, over flow or drain connections In IT01, the plumbing drawings indicate grey water tank below ground. However, the same tank is shown on structural drawings above ground

d. Storm Water Drainage (Only for underground services) The following is a summary of findings in regards to above system. More details, calculations and references may be found in subsequent sections: i. Rainfall intensity values and area calculations were found to be incorrect and inconsistent between buildings

e. Fire Fighting (Not included in this report) 2. Electrical: a. Grounding & Lightning Protection (For the complete system in all buildings) The following is a summary of findings in regards to above system. More details, calculations and references may be found in subsequent sections: i. ii. iii. Calculations for grounding and lightning systems were not provided with IFC documents In general, lightning system designed overall resistance is within standard required values Grounding conductor for main electrical equipment is over sized (Which is acceptable) in some buildings while in many other buildings it is undersized Telecommunication clean grounding is not provided in many buildings. This means that number of grounding pits must be increased Calculated Telecommunication grounding resistance (where provided) exceeds specification requirements. This means that number of grounding pits and/ or rods is underestimated General grounding for RMUs, transformers, generators, LV switchgears is not provided for many buildings Calculated grounding resistance for RMUs, transformers, generators, LV switchgears (where provided) exceeds specification requirements

iv. v.

vi. vii.

DVR 251011/109

P a g e | 8 / 292

viii. ix. x.

xi.

Available earth pits do not reflect the actual number of pits required for telecommunication, general and lightning grounding system There are inconsistency within system installation details provided on IFC design drawings Grounding rods within raft slabs (With a thickness of 0.7-1.3 meters) are shown to be 3.0 deep (Starting at 0.3 m below FFL). However, the standard calls for 3.0 m of rod length to be extended vertically into earth. Also, main ring electrode is shown on drawings to be installed 0.3 meters below FFL of raft. This means the ring electrode is going to be buried within raft. However, the specifications call for it to be 0.6 m below grade and the NFPA 780 calls for it to be in direct contact with earth at a depth of not less than 0.46 m. There are inconsistency between specifications and drawings in regards to rod sizes, burial depth of ring electrode, embedded conduit sizesetc

b. Normal & Emergency Lighting (Not included in this report) c. Power & Low Voltage Distribution(Not included in this report) d. Fire Alarm & Detection (Not included in this report) e. IT Network (Not included in this report)

III.

RECOMMENDATIONS
It is of the design reviewer opinion that underground services design requires revisions to be made prior to proceeding with production of shop drawings or site installations as follows: A. Mechanical: 1. Water System: No design revisions are required in relation to this system for underground services 2. Waste and Soil Drainage System: In general pipe network design requires minor revisions. However, sump pits, pumps, grey water system and rain water system require major revision. Calculations must be re-done and results must be coordinated with other disciplines such as structural, electrical power, architecturaletc B. Electrical: 1. Lighting and Grounding System: Calculations must be redone based on actual soil resistivity measurements done on site. Also, number of grounding pits, size and depth of rods, number of down conductors and general layout of system must be revised prior to producing shop drawings or start of installation on site

DVR 251011/109

P a g e | 9 / 292

Plumbing Drainage System Building KB 01-02 Verification Checklist Summary Checked Not Applicable Yes Yes Key Design Checks Compliance Not Applicable Partially Notes & Remarks

No

Final design report Owner/Operator requirement Check Foundation Type Check Drainage Pipe Encasement Check Sump Pit Flow Calculations Check Sump Pit Head Calculations Check Coordination Between Sump Pit & Structural Drawings Check Gray Water Tank Calculations Check Non-Potable Water Tank Calculations Check Consistency Between Drainage Plans, Riser Diagram & Calculations Check Coordination Between Gray Water System & Structual Drawings

No

Not provided Not provided Column Base


Table M.1

DVR 251011/109

P a g e | 10 / 292

Plumbing Drainage System Building KB 03 Verification Checklist Summary Checked Not Applicable Key Design Checks Compliance Not Applicable Partially Notes & Remarks

Yes

Yes

No

Final design report Owner/Operator requirement Check Foundation Type Check Drainage Pipe Encasement Check Sump Pit Flow Calculations Check Sump Pit Head Calculations Check Coordination Between Sump Pit & Structural Drawings Check Gray Water Tank Calculations Check Non-Potable Water Tank Calculations Check Consistency Between Drainage Plans, Riser Diagram & Calculations Check Coordination Between Gray Water System & Structual Drawings

No

Not provided Not provided Raft

Table M.2

DVR 251011/109

P a g e | 11 / 292

Plumbing Drainage System Building RD 03 Verification Checklist Summary Checked Not Applicable Yes Yes Key Design Checks Compliance Not Applicable Partially Notes & Remarks

No

Final design report Owner/Operator requirement Check Foundation Type Check Drainage Pipe Encasement Check Sump Pit Flow Calculations Check Sump Pit Head Calculations Check Coordination Between Sump Pit & Structural Drawings Check Gray Water Tank Calculations Check Non-Potable Water Tank Calculations Check Consistency Between Drainage Plans, Riser Diagram & Calculations Check Coordination Between Gray Water System & Structual Drawings

No

Not provided Not provided Column Base

Data is not Available, refer to detailed Analysis

Data is not Available, refer to detailed Analysis Data is not Available, refer to detailed Analysis

Table M.3

DVR 251011/109

P a g e | 12 / 292

Plumbing Drainage System Building RD 04 Verification Checklist Summary Checked Not Applicable Yes Yes Key Design Checks Compliance Not Applicable Partially Notes & Remarks

No

Final design report Owner/Operator requirement Check Foundation Type Check Drainage Pipe Encasement Check Sump Pit Flow Calculations Check Sump Pit Head Calculations Check Coordination Between Sump Pit & Structural Drawings Check Gray Water Tank Calculations Check Non-Potable Water Tank Calculations Check Consistency Between Drainage Plans, Riser Diagram & Calculations Check Coordination Between Gray Water System & Structual Drawings

No

Not provided Not provided Column Base

Data is not Available, refer to detailed Analysis

Data is not Available, refer to detailed Analysis

Table M.4

DVR 251011/109

P a g e | 13 / 292

Plumbing Drainage System Building WH 01-04 Verification Checklist Summary Checked Not Applicable Yes Yes Key Design Checks Compliance Not Applicable Partially Notes & Remarks

No

Final design report Owner/Operator requirement Check Foundation Type Check Drainage Pipe Encasement Check Sump Pit Flow Calculations Check Sump Pit Head Calculations Check Coordination Between Sump Pit & Structural Drawings Check Gray Water Tank Calculations Check Non-Potable Water Tank Calculations Check Consistency Between Drainage Plans, Riser Diagram & Calculations Check Coordination Between Gray Water System & Structual Drawings

No

Not provided Not provided Raft Foundation


Table M.5

DVR 251011/109

P a g e | 14 / 292

Plumbing Drainage System Building WH 05 Verification Checklist Summary Checked Not Applicable Key Design Checks Compliance Not Applicable Partially Notes & Remarks

Yes

Yes

No

Final design report Owner/Operator requirement Check Foundation Type Check Drainage Pipe Encasement Check Sump Pit Flow Calculations Check Sump Pit Head Calculations Check Coordination Between Sump Pit & Structural Drawings Check Gray Water Tank Calculations Check Non-Potable Water Tank Calculations Check Consistency Between Drainage Plans, Riser Diagram & Calculations Check Coordination Between Gray Water System & Structual Drawings

No

Not provided Not provided Raft Foundation


Table M.6

DVR 251011/109

P a g e | 15 / 292

Plumbing Drainage System Building WH 06 Verification Checklist Summary Checked Not Applicable Key Design Checks Compliance Not Applicable Partially Notes & Remarks

Yes

Yes

No

Final design report Owner/Operator requirement Check Foundation Type Check Drainage Pipe Encasement Check Sump Pit Flow Calculations Check Sump Pit Head Calculations Check Coordination Between Sump Pit & Structural Drawings Check Gray Water Tank Calculations Check Non-Potable Water Tank Calculations Check Consistency Between Drainage Plans, Riser Diagram & Calculations Check Coordination Between Gray Water System & Structual Drawings

No

Not provided Not provided Raft


Table M.7

DVR 251011/109

P a g e | 16 / 292

Plumbing Drainage System Building IT 01 Verification Checklist Summary Checked Not Applicable Key Design Checks Compliance Not Applicable Partially Notes & Remarks

Yes

Yes

No

Final design report Owner/Operator requirement Check Foundation Type Check Drainage Pipe Encasement Check Sump Pit Flow Calculations Check Sump Pit Head Calculations Check Coordination Between Sump Pit & Structural Drawings Check Gray Water Tank Calculations Check Non-Potable Water Tank Calculations Check Consistency Between Drainage Plans, Riser Diagram & Calculations Check Coordination Between Gray Water System & Structual Drawings

No

Not provided Not provided Column Base

Table M.8

DVR 251011/109

P a g e | 17 / 292

Plumbing Drainage System Building IT02 Verification Checklist Summary Checked Not Applicable Yes Yes Key Design Checks Compliance Not Applicable Partially Notes & Remarks

No

Final design report Owner/Operator requirement Check Foundation Type Check Drainage Pipe Encasement Check Sump Pit Flow Calculations Check Sump Pit Head Calculations Check Coordination Between Sump Pit & Structural Drawings Check Gray Water Tank Calculations Check Non-Potable Water Tank Calculations Check Consistency Between Drainage Plans, Riser Diagram & Calculations Check Coordination Between Gray Water System & Structual Drawings

No

Not provided Not provided Column Base

Data is not Available, refer to detailed Analysis Data is not Available, refer to detailed Analysis

Table M.9

DVR 251011/109

P a g e | 18 / 292

Plumbing Drainage System Building IT 03 Verification Checklist Summary Checked Not Applicable Key Design Checks Compliance Not Applicable Partially Notes & Remarks

Yes

Yes

No

Final design report Owner/Operator requirement Check Foundation Type Check Drainage Pipe Encasement Check Sump Pit Flow Calculations Check Sump Pit Head Calculations Check Coordination Between Sump Pit & Structural Drawings Check Gray Water Tank Calculations Check Non-Potable Water Tank Calculations Check Consistency Between Drainage Plans, Riser Diagram & Calculations Check Coordination Between Gray Water System & Structual Drawings

No

Not provided Not provided Column Base

Data is not Available, refer to detailed Analysis

Table M.10

DVR 251011/109

P a g e | 19 / 292

Plumbing Drainage System Building KB 04 Verification Checklist Summary Checked Not Applicable Yes Yes Key Design Checks Compliance Not Applicable Partially Notes & Remarks

No

Final design report Owner/Operator requirement Check Foundation Type Check Drainage Pipe Encasement Check Sump Pit Flow Calculations Check Sump Pit Head Calculations Check Coordination Between Sump Pit & Structural Drawings Check Consistency Between Drainage Plans, Riser Diagram & Calculations

No

Not provided Not provided Column Base

Table M.11

DVR 251011/109

P a g e | 20 / 292

Plumbing Drainage System Building KB 05 Verification Checklist Summary Checked Not Applicable Key Design Checks Compliance Not Applicable Partially Notes & Remarks

Yes

Yes

No

Final design report Owner/Operator requirement Check Foundation Type Check Drainage Pipe Encasement Check Sump Pit Flow Calculations Check Sump Pit Head Calculations Check Coordination Between Sump Pit & Structural Drawings Check Consistency Between Drainage Plans, Riser Diagram & Calculations

No

Not provided Not provided Column Base

Table M.12

DVR 251011/109

P a g e | 21 / 292

Plumbing Drainage System Building KB 06 Verification Checklist Summary Checked Not Applicable Key Design Checks Compliance Not Applicable Partially Notes & Remarks

Yes

Yes

No

Final design report Owner/Operator requirement Check Foundation Type Check Drainage Pipe Encasement Check Sump Pit Flow Calculations Check Sump Pit Head Calculations Check Coordination Between Sump Pit & Structural Drawings Check Consistency Between Drainage Plans, Riser Diagram & Calculations

No

Not provided Not provided Column Base

Table M.13

DVR 251011/109

P a g e | 22 / 292

Grounding & Lightning Protection Building KB 01-02 Verification Checklist Summary Checked Not Applicable Yes Yes Key Design Checks Compliance Not Applicable Partially Notes & Remarks

No

Final design report Owner/Operator requirement Soil resistivity measurement Check type of earthing system to be employed (such as TNS or TN-C-S) Check local electrical company requirements and electrical supply arrangements Check connections to other systems and determine any clean earth requirement Check earthing system calculations Check schematic of main earth bar and connections Check earth termination and space required Check electrical bonding details and provisions for other systems such as ceilings, catering equipment and raised floors Check relevant specification clauses Size of main earthing/equipotential bonding conductors Check consistency between electrical drawings Check consistency between specifications and drawings

No

Not provided Not provided Data not provided, refer to detailed analysis for assumptions

Refer to detailed analysis Data not provided, refer to detailed analysis and calculations Data not provided

Covered in the specifications only

Refer to detailed analysis Refer to detailed analysis and calculations Refer to detailed analysis Refer to detailed analysis

DVR 251011/109

P a g e | 23 / 292

Grounding & Lightning Protection Building KB 01-02 Verification Checklist Summary Checked Not Applicable Yes Yes Key Design Checks Compliance Not Applicable Partially Notes & Remarks

No

Checking arrangement and location of earth pits (such as coordination with other trades (structural, Architectural and mechanical)) Check the use of transient earth clamps for clamping different earthing systems to prevent transient disturbances Provide main equipotential bonding (required for lightning protection, structure, incoming services, heating and ventilation). Provide supplementary bonding conductors to exposed and extraneous metal work such as trunking trays, ceiling grid and raised access floors Check that removable links for testing are specified. Check that test link location is coordinated with Architect Check for provision of protective earth and clean earth bars at each switchroom and riser location Consider whether dedicated earths are necessary (for example telecommunications and electronic systems) Check air terminals are considered with correct size and location Check roof strike termination network is considered with correct conductor size and location

No

Refer to detailed analysis

Refer to detailed analysis

Covered in the specifications only

Covered in the details only Refer to detailed analysis

Refer to detailed analysis

Refer to detailed analysis

DVR 251011/109

P a g e | 24 / 292

Grounding & Lightning Protection Building KB 01-02 Verification Checklist Summary Checked Not Applicable Yes Yes Key Design Checks Compliance Not Applicable Partially Notes & Remarks

No

Check down coductors are considered with correct conductor size and spacing

No

Table E.1

Refer to detailed analysis

DVR 251011/109

P a g e | 25 / 292

Grounding & Lightning Protection Building KB-03 Verification Checklist Summary Checked Not Applicable Key Design Checks Compliance Not Applicable Partially Notes & Remarks

Yes

Yes

No

Final design report Owner/Operator requirement Soil resistivity measurement Check type of earthing system to be employed (such as TNS or TN-C-S) Check local electrical company requirements and electrical supply arrangements Check connections to other systems and determine any clean earth requirement Check earthing system calculations Check schematic of main earth bar and connections Check earth termination and space required Check electrical bonding details and provisions for other systems such as ceilings, catering equipment and raised floors Check relevant specification clauses Size of main earthing/equipotential bonding conductors Check consistency between electrical drawings Check consistency between specifications and drawings

No

Not provided Not provided Data not provided, refer to detailed analysis for assumptions

Refer to detailed analysis Data not provided, refer to detailed analysis and calculations Data not provided

Covered in the specifications only

Refer to detailed analysis Refer to detailed analysis and calculations Refer to detailed analysis Refer to detailed analysis

DVR 251011/109

P a g e | 26 / 292

Grounding & Lightning Protection Building KB-03 Verification Checklist Summary Checked Not Applicable Key Design Checks Compliance Not Applicable Partially Notes & Remarks

Yes

Yes

No

Checking arrangement and location of earth pits (such as coordination with other trades (structural, Architectural and mechanical)) Check the use of transient earth clamps for clamping different earthing systems to prevent transient disturbances Provide main equipotential bonding (required for lightning protection, structure, incoming services, heating and ventilation). Provide supplementary bonding conductors to exposed and extraneous metal work such as trunking trays, ceiling grid and raised access floors Check that removable links for testing are specified. Check that test link location is coordinated with Architect Check for provision of protective earth and clean earth bars at each switchroom and riser location Consider whether dedicated earths are necessary (for example telecommunications and electronic systems) Check air terminals are considered with correct size and location Check roof strike termination network is considered with correct conductor size and location Check down coductors are considered with correct conductor size and spacing

No

Refer to detailed analysis

Refer to detailed analysis

Refer to detailed analysis

Covered in the specifications only

Covered in the details only Refer to detailed analysis

Refer to detailed analysis

Refer to detailed analysis

DVR 251011/109

P a g e | 27 / 292

Grounding & Lightning Protection Building KB-03 Verification Checklist Summary Checked Not Applicable Key Design Checks Compliance Not Applicable Partially Notes & Remarks

Yes

Yes

No

Table E.2

DVR 251011/109

No

P a g e | 28 / 292

Grounding & Lightning Protection Building RD-03 Verification Checklist Summary Checked Not Applicable Key Design Checks Compliance Not Applicable Partially Notes & Remarks

Yes

Yes

No

Final design report Owner/Operator requirement Soil resistivity measurement Check type of earthing system to be employed (such as TNS or TN-C-S) Check local electrical company requirements and electrical supply arrangements Check connections to other systems and determine any clean earth requirement Check earthing system calculations Check schematic of main earth bar and connections Check earth termination and space required Check electrical bonding details and provisions for other systems such as ceilings, catering equipment and raised floors Check relevant specification clauses Size of main earthing/equipotential bonding conductors Check consistency between electrical drawings

No

Not provided Not provided

Data not provided, refer to detailed analysis for assumptions


Refer to detailed analysis Data not provided, refer to detailed analysis and calculations Data not provided

Covered in the specifications only

Refer to detailed analysis Refer to detailed analysis and calculations Refer to detailed analysis

DVR 251011/109

P a g e | 29 / 292

Grounding & Lightning Protection Building RD-03 Verification Checklist Summary Checked Not Applicable Key Design Checks Compliance Not Applicable Partially Notes & Remarks

Yes

Yes

No

Check consistency between specifications and drawings Checking arrangement and location of earth pits (such as coordination with other trades (structural, Architectural and mechanical)) Check the use of transient earth clamps for clamping different earthing systems to prevent transient disturbances Provide main equipotential bonding (required for lightning protection, structure, incoming services, heating and ventilation). Provide supplementary bonding conductors to exposed and extraneous metal work such as trunking trays, ceiling grid and raised access floors Check that removable links for testing are specified. Check that test link location is coordinated with Architect Check for provision of protective earth and clean earth bars at each switchroom and riser location Consider whether dedicated earths are necessary (for example telecommunications and electronic systems) Check air terminals are considered with correct size and location

No

Refer to detailed analysis

Refer to detailed analysis

Refer to detailed analysis

Refer to detailed analysis

Covered in the specifications only

Covered in the details only Refer to detailed analysis

Refer to detailed analysis

Refer to detailed analysis

Refer to detailed analysis

DVR 251011/109

P a g e | 30 / 292

Grounding & Lightning Protection Building RD-03 Verification Checklist Summary Checked Not Applicable Key Design Checks Compliance Not Applicable Partially Notes & Remarks

Yes

Yes

No

Check roof strike termination network is considered with correct conductor size and location Check down coductors are considered with correct conductor size and spacing

No

Refer to detailed analysis

Table E.3

DVR 251011/109

P a g e | 31 / 292

Grounding & Lightning Protection Building RD-04 Verification Checklist Summary Checked Not Applicable Yes Yes Key Design Checks Compliance Not Applicable Partially Notes & Remarks

No

Final design report Owner/Operator requirement Soil resistivity measurement Check type of earthing system to be employed (such as TNS or TN-C-S) Check local electrical company requirements and electrical supply arrangements Check connections to other systems and determine any clean earth requirement Check earthing system calculations Check schematic of main earth bar and connections Check earth termination and space required Check electrical bonding details and provisions for other systems such as ceilings, catering equipment and raised floors Check relevant specification clauses Size of main earthing/equipotential bonding conductors Check consistency between electrical drawings Check consistency between specifications and drawings

No

Not provided Not provided

Data not provided, refer to detailed analysis for assumptions


Refer to detailed analysis Data not provided, refer to detailed analysis and calculations Data not provided

Covered in the specifications only

Refer to detailed analysis Refer to detailed analysis and calculations Refer to detailed analysis Refer to detailed analysis

DVR 251011/109

P a g e | 32 / 292

Grounding & Lightning Protection Building RD-04 Verification Checklist Summary Checked Not Applicable Yes Yes Key Design Checks Compliance Not Applicable Partially Notes & Remarks

No

Checking arrangement and location of earth pits (such as coordination with other trades (structural, Architectural and mechanical)) Check the use of transient earth clamps for clamping different earthing systems to prevent transient disturbances Provide main equipotential bonding (required for lightning protection, structure, incoming services, heating and ventilation). Provide supplementary bonding conductors to exposed and extraneous metal work such as trunking trays, ceiling grid and raised access floors Check that removable links for testing are specified. Check that test link location is coordinated with Architect Check for provision of protective earth and clean earth bars at each switchroom and riser location Consider whether dedicated earths are necessary (for example telecommunications and electronic systems) Check air terminals are considered with correct size and location Check roof strike termination network is considered with correct conductor size and location

No

Refer to detailed analysis

Refer to detailed analysis

Refer to detailed analysis

Covered in the specifications only

Covered in the details only Refer to detailed analysis

Refer to detailed analysis

Refer to detailed analysis

Refer to detailed analysis

DVR 251011/109

P a g e | 33 / 292

Grounding & Lightning Protection Building RD-04 Verification Checklist Summary Checked Not Applicable Yes Yes Key Design Checks Compliance Not Applicable Partially Notes & Remarks

No

Check down coductors are considered with correct conductor size and spacing

No

Refer to detailed analysis

Table E.4

DVR 251011/109

P a g e | 34 / 292

Grounding & Lightning Protection Building WH 01-04 Verification Checklist Summary Checked Not Applicable Key Design Checks Compliance Not Applicable Partially Notes & Remarks

Yes

Yes

No

Final design report Owner/Operator requirement Soil resistivity measurement Check type of earthing system to be employed (such as TNS or TN-C-S) Check local electrical company requirements and electrical supply arrangements Check connections to other systems and determine any clean earth requirement Check earthing system calculations Check schematic of main earth bar and connections Check earth termination and space required Check electrical bonding details and provisions for other systems such as ceilings, catering equipment and raised floors Check relevant specification clauses Size of main earthing/equipotential bonding conductors Check consistency between electrical drawings Check consistency between specifications and drawings

No

Not provided Not provided Data not provided, refer to detailed analysis for assumptions

Refer to detailed analysis Data not provided, refer to detailed analysis and calculations Data not provided

Covered in the specifications only

Refer to detailed analysis Refer to detailed analysis and calculations Refer to detailed analysis Refer to detailed analysis

DVR 251011/109

P a g e | 35 / 292

Grounding & Lightning Protection Building WH 01-04 Verification Checklist Summary Checked Not Applicable Key Design Checks Compliance Not Applicable Partially Notes & Remarks

Yes

Yes

No

Checking arrangement and location of earth pits (such as coordination with other trades (structural, Architectural and mechanical)) Check the use of transient earth clamps for clamping different earthing systems to prevent transient disturbances Provide main equipotential bonding (required for lightning protection, structure, incoming services, heating and ventilation). Provide supplementary bonding conductors to exposed and extraneous metal work such as trunking trays, ceiling grid and raised access floors Check that removable links for testing are specified. Check that test link location is coordinated with Architect Check for provision of protective earth and clean earth bars at each switchroom and riser location Consider whether dedicated earths are necessary (for example telecommunications and electronic systems) Check air terminals are considered with correct size and location Check roof strike termination network is considered with correct conductor size and location

No

Refer to detailed analysis

Refer to detailed analysis

Refer to detailed analysis

Covered in the specifications only

Covered in the details only Refer to detailed analysis

Refer to detailed analysis

Refer to detailed analysis

Refer to detailed analysis

DVR 251011/109

P a g e | 36 / 292

Grounding & Lightning Protection Building WH 01-04 Verification Checklist Summary Checked Not Applicable Key Design Checks Compliance Not Applicable Partially Notes & Remarks

Yes

Yes

No

Check down coductors are considered with correct conductor size and spacing

Table E.5

No

DVR 251011/109

P a g e | 37 / 292

Grounding & Lightning Protection Building WH-05 Verification Checklist Summary Checked Not Applicable Key Design Checks Compliance Not Applicable Partially Notes & Remarks

Yes

Yes

No

Final design report Owner/Operator requirement Soil resistivity measurement Check type of earthing system to be employed (such as TNS or TN-C-S) Check local electrical company requirements and electrical supply arrangements Check connections to other systems and determine any clean earth requirement Check earthing system calculations Check schematic of main earth bar and connections Check earth termination and space required Check electrical bonding details and provisions for other systems such as ceilings, catering equipment and raised floors Check relevant specification clauses Size of main earthing/equipotential bonding conductors Check consistency between electrical drawings Check consistency between specifications and drawings Checking arrangement and location of earth pits (such as coordination with other trades (structural, Architectural and mechanical))

No

Not provided Not provided Data not provided, refer to detailed analysis for assumptions

Refer to detailed analysis Data not provided, refer to detailed analysis and calculations Data not provided

Covered in the specifications only

Refer to detailed analysis Refer to detailed analysis and calculations Refer to detailed analysis Refer to detailed analysis

Refer to detailed analysis

DVR 251011/109

P a g e | 38 / 292

Grounding & Lightning Protection Building WH-05 Verification Checklist Summary Checked Not Applicable Key Design Checks Compliance Not Applicable Partially Notes & Remarks

Yes

Yes

No

Check the use of transient earth clamps for clamping different earthing systems to prevent transient disturbances Provide main equipotential bonding (required for lightning protection, structure, incoming services, heating and ventilation). Provide supplementary bonding conductors to exposed and extraneous metal work such as trunking trays, ceiling grid and raised access floors Check that removable links for testing are specified. Check that test link location is coordinated with Architect Check for provision of protective earth and clean earth bars at each switchroom and riser location Consider whether dedicated earths are necessary (for example telecommunications and electronic systems) Check air terminals are considered with correct size and location Check roof strike termination network is considered with correct conductor size and location Check down coductors are considered with correct conductor size and spacing

No

Refer to detailed analysis

Covered in the specifications only

Covered in the details only Refer to detailed analysis

Refer to detailed analysis

Refer to detailed analysis

Refer to detailed analysis

Table E.6

DVR 251011/109

P a g e | 39 / 292

Grounding & Lightning Protection Building WH-06 Verification Checklist Summary Checked Not Applicable Key Design Checks Compliance Not Applicable Partially Notes & Remarks

Yes

Yes

No

Final design report Owner/Operator requirement Soil resistivity measurement Check type of earthing system to be employed (such as TNS or TN-C-S) Check local electrical company requirements and electrical supply arrangements Check connections to other systems and determine any clean earth requirement Check earthing system calculations Check schematic of main earth bar and connections Check earth termination and space required Check electrical bonding details and provisions for other systems such as ceilings, catering equipment and raised floors Check relevant specification clauses Size of main earthing/equipotential bonding conductors Check consistency between electrical drawings Check consistency between specifications and drawings

No

Not provided Not provided

Data not provided, refer to detailed analysis for assumptions


Refer to detailed analysis Data not provided, refer to detailed analysis and calculations Data not provided

Covered in the specifications only

Refer to detailed analysis

Refer to detailed analysis Refer to detailed analysis

DVR 251011/109

P a g e | 40 / 292

Grounding & Lightning Protection Building WH-06 Verification Checklist Summary Checked Not Applicable Key Design Checks Compliance Not Applicable Partially Notes & Remarks

Yes

Yes

No

Checking arrangement and location of earth pits (such as coordination with other trades (structural, Architectural and mechanical)) Check the use of transient earth clamps for clamping different earthing systems to prevent transient disturbances Provide main equipotential bonding (required for lightning protection, structure, incoming services, heating and ventilation). Provide supplementary bonding conductors to exposed and extraneous metal work such as trunking trays, ceiling grid and raised access floors Check that removable links for testing are specified. Check that test link location is coordinated with Architect Check for provision of protective earth and clean earth bars at each switchroom and riser location Consider whether dedicated earths are necessary (for example telecommunications and electronic systems) Check air terminals are considered with correct size and location Check roof strike termination network is considered with correct conductor size and location

No

Refer to detailed analysis

Refer to detailed analysis

Covered in the specifications only

Covered in the details only Refer to detailed analysis

Refer to detailed analysis

Refer to detailed analysis

Refer to detailed analysis

DVR 251011/109

P a g e | 41 / 292

Grounding & Lightning Protection Building WH-06 Verification Checklist Summary Checked Not Applicable Key Design Checks Compliance Not Applicable Partially Notes & Remarks

Yes

Yes

No

Check down coductors are considered with correct conductor size and spacing

No

Table E.7

DVR 251011/109

P a g e | 42 / 292

Grounding & Lightning Protection Building IT-01 Verification Checklist Summary Checked Not Applicable Key Design Checks Compliance Not Applicable Partially Notes & Remarks

Yes

Yes

No

Final design report Owner/Operator requirement Soil resistivity measurement Check type of earthing system to be employed (such as TNS or TN-C-S) Check local electrical company requirements and electrical supply arrangements Check connections to other systems and determine any clean earth requirement Check earthing system calculations Check schematic of main earth bar and connections Check earth termination and space required Check electrical bonding details and provisions for other systems such as ceilings, catering equipment and raised floors Check relevant specification clauses Size of main earthing/equipotential bonding conductors Check consistency between electrical drawings Check consistency between specifications and drawings Checking arrangement and location of earth pits (such as coordination with other trades (structural, Architectural and mechanical))

No

Not provided Not provided Data not provided, refer to detailed analysis for assumptions

Refer to detailed analysis Data not provided, refer to detailed analysis and calculations Data not provided

Covered in the specifications only

Refer to detailed analysis Refer to detailed analysis and calculations Refer to detailed analysis Refer to detailed analysis

Refer to detailed analysis

DVR 251011/109

P a g e | 43 / 292

Grounding & Lightning Protection Building IT-01 Verification Checklist Summary Checked Not Applicable Key Design Checks Compliance Not Applicable Partially Notes & Remarks

Yes

Yes

No

Check the use of transient earth clamps for clamping different earthing systems to prevent transient disturbances Provide main equipotential bonding (required for lightning protection, structure, incoming services, heating and ventilation). Provide supplementary bonding conductors to exposed and extraneous metal work such as trunking trays, ceiling grid and raised access floors Check that removable links for testing are specified. Check that test link location is coordinated with Architect Check for provision of protective earth and clean earth bars at each switchroom and riser location Consider whether dedicated earths are necessary (for example telecommunications and electronic systems) Check air terminals are considered with correct size and location Check roof strike termination network is considered with correct conductor size and location Check down coductors are considered with correct conductor size and spacing

No

Refer to detailed analysis

Refer to detailed analysis

Covered in the specifications only

Covered in the details only Refer to detailed analysis

Refer to detailed analysis

Refer to detailed analysis

Refer to detailed analysis

Table E.8

DVR 251011/109

P a g e | 44 / 292

Grounding & Lightning Protection Building IT-02 Verification Checklist Summary Checked Not Applicable Key Design Checks Compliance Not Applicable Partially Notes & Remarks

Yes

Yes

No

Final design report Owner/Operator requirement Soil resistivity measurement Check type of earthing system to be employed (such as TNS or TN-C-S) Check local electrical company requirements and electrical supply arrangements Check connections to other systems and determine any clean earth requirement Check earthing system calculations Check schematic of main earth bar and connections Check earth termination and space required Check electrical bonding details and provisions for other systems such as ceilings, catering equipment and raised floors Check relevant specification clauses Size of main earthing/equipotential bonding conductors Check consistency between electrical drawings Check consistency between specifications and drawings

No

Not provided Not provided Data not provided, refer to detailed analysis for assumptions

Refer to detailed analysis Data not provided, refer to detailed analysis and calculations Data not provided

Covered in the specifications only

Refer to detailed analysis Refer to detailed analysis and calculations Refer to detailed analysis Refer to detailed analysis

DVR 251011/109

P a g e | 45 / 292

Grounding & Lightning Protection Building IT-02 Verification Checklist Summary Checked Not Applicable Key Design Checks Compliance Not Applicable Partially Notes & Remarks

Yes

Yes

No

Checking arrangement and location of earth pits (such as coordination with other trades (structural, Architectural and mechanical)) Check the use of transient earth clamps for clamping different earthing systems to prevent transient disturbances Provide main equipotential bonding (required for lightning protection, structure, incoming services, heating and ventilation). Provide supplementary bonding conductors to exposed and extraneous metal work such as trunking trays, ceiling grid and raised access floors Check that removable links for testing are specified. Check that test link location is coordinated with Architect Check for provision of protective earth and clean earth bars at each switchroom and riser location Consider whether dedicated earths are necessary (for example telecommunications and electronic systems) Check air terminals are considered with correct size and location

No

Refer to detailed analysis

Refer to detailed analysis

Refer to detailed analysis

Covered in the specifications only

Covered in the details only Refer to detailed analysis

Refer to detailed analysis

Refer to detailed analysis

DVR 251011/109

P a g e | 46 / 292

Grounding & Lightning Protection Building IT-02 Verification Checklist Summary Checked Not Applicable Key Design Checks Compliance Not Applicable Partially Notes & Remarks

Yes

Yes

No

Check roof strike termination network is considered with correct conductor size and location Check down coductors are considered with correct conductor size and spacing


Refer to detailed analysis

Table E.9

DVR 251011/109

No

P a g e | 47 / 292

Grounding & Lightning Protection Building IT-03 Verification Checklist Summary Checked Not Applicable Key Design Checks Compliance Not Applicable Partially Notes & Remarks

Yes

Yes

No

Final design report Owner/Operator requirement Soil resistivity measurement Check type of earthing system to be employed (such as TNS or TN-C-S) Check local electrical company requirements and electrical supply arrangements Check connections to other systems and determine any clean earth requirement Check earthing system calculations Check schematic of main earth bar and connections Check earth termination and space required Check electrical bonding details and provisions for other systems such as ceilings, catering equipment and raised floors Check relevant specification clauses Size of main earthing/equipotential bonding conductors Check consistency between electrical drawings Check consistency between specifications and drawings Checking arrangement and location of earth pits (such as coordination with other trades (structural, Architectural and

No

Not provided Not provided

Data not provided, refer to detailed analysis for assumptions

Refer to detailed analysis Data not provided, refer to detailed analysis and calculations Data not provided

Covered in the specifications only

Refer to detailed analysis Refer to detailed analysis and calculations Refer to detailed analysis Refer to detailed analysis

Refer to detailed analysis

DVR 251011/109

P a g e | 48 / 292

Grounding & Lightning Protection Building IT-03 Verification Checklist Summary Checked Not Applicable Key Design Checks Compliance Not Applicable Partially Notes & Remarks

Yes

Yes

No

mechanical)) Check the use of transient earth clamps for clamping different earthing systems to prevent transient disturbances Provide main equipotential bonding (required for lightning protection, structure, incoming services, heating and ventilation). Provide supplementary bonding conductors to exposed and extraneous metal work such as trunking trays, ceiling grid and raised access floors Check that removable links for testing are specified. Check that test link location is coordinated with Architect Check for provision of protective earth and clean earth bars at each switchroom and riser location Consider whether dedicated earths are necessary (for example telecommunications and electronic systems) Check air terminals are considered with correct size and location Check roof strike termination network is considered with correct conductor size and location Check down coductors are considered with correct conductor size and spacing

No

Refer to detailed analysis

Refer to detailed analysis

Covered in the specifications only

Covered in the details only Refer to detailed analysis

Refer to detailed analysis

Refer to detailed analysis

Table E.10

DVR 251011/109

P a g e | 49 / 292

Grounding & Lightning Protection Building KB-04 Verification Checklist Summary Checked Not Applicable Yes Yes Key Design Checks Compliance Not Applicable Partially Notes & Remarks

No

Final design report Owner/Operator requirement Soil resistivity measurement Check type of earthing system to be employed (such as TNS or TN-C-S) Check local electrical company requirements and electrical supply arrangements Check connections to other systems and determine any clean earth requirement Check earthing system calculations Check schematic of main earth bar and connections Check earth termination and space required Check electrical bonding details and provisions for other systems such as ceilings, catering equipment and raised floors Check relevant specification clauses Size of main earthing/equipotential bonding conductors Check consistency between electrical drawings Check consistency between specifications and drawings Checking arrangement and location of earth pits (such as coordination with other trades (structural, Architectural and

No

Not provided Not provided Data not provided, refer to detailed analysis for assumptions

Refer to detailed analysis Data not provided, refer to detailed analysis and calculations Data not provided

Covered in the specifications only

Refer to detailed analysis Refer to detailed analysis and calculations Refer to detailed analysis Refer to detailed analysis

Refer to detailed analysis

DVR 251011/109

P a g e | 50 / 292

Grounding & Lightning Protection Building KB-04 Verification Checklist Summary Checked Not Applicable Yes Yes Key Design Checks Compliance Not Applicable Partially Notes & Remarks

No

mechanical)) Check the use of transient earth clamps for clamping different earthing systems to prevent transient disturbances Provide main equipotential bonding (required for lightning protection, structure, incoming services, heating and ventilation). Provide supplementary bonding conductors to exposed and extraneous metal work such as trunking trays, ceiling grid and raised access floors Check that removable links for testing are specified. Check that test link location is coordinated with Architect Check for provision of protective earth and clean earth bars at each switchroom and riser location Consider whether dedicated earths are necessary (for example telecommunications and electronic systems) Check air terminals are considered with correct size and location Check roof strike termination network is considered with correct conductor size and location Check down coductors are considered with correct conductor size and spacing

No

Refer to detailed analysis

Covered in the specifications only

Covered in the details only Refer to detailed analysis

Refer to detailed analysis

Table E.11

DVR 251011/109

P a g e | 51 / 292

Grounding & Lightning Protection Building KB-05 Verification Checklist Summary Checked Not Applicable Key Design Checks Compliance Not Applicable Partially Notes & Remarks

Yes

Yes

No

Final design report Owner/Operator requirement Soil resistivity measurement Check type of earthing system to be employed (such as TNS or TN-C-S) Check local electrical company requirements and electrical supply arrangements Check connections to other systems and determine any clean earth requirement Check earthing system calculations Check schematic of main earth bar and connections Check earth termination and space required Check electrical bonding details and provisions for other systems such as ceilings, catering equipment and raised floors Check relevant specification clauses Size of main earthing/equipotential bonding conductors Check consistency between electrical drawings Check consistency between specifications and drawings Checking arrangement and location of earth pits (such as coordination with other trades

No

Not provided Not provided

Data not provided, refer to detailed analysis for assumptions


Refer to detailed analysis Data not provided, refer to detailed analysis and calculations Data not provided

Covered in the specifications only

Refer to detailed analysis Refer to detailed analysis and calculations Refer to detailed analysis Refer to detailed analysis Refer to detailed analysis

DVR 251011/109

P a g e | 52 / 292

Grounding & Lightning Protection Building KB-05 Verification Checklist Summary Checked Not Applicable Key Design Checks Compliance Not Applicable Partially Notes & Remarks

Yes

Yes

No

(structural, Architectural and mechanical)) Check the use of transient earth clamps for clamping different earthing systems to prevent transient disturbances Provide main equipotential bonding (required for lightning protection, structure, incoming services, heating and ventilation). Provide supplementary bonding conductors to exposed and extraneous metal work such as trunking trays, ceiling grid and raised access floors Check that removable links for testing are specified. Check that test link location is coordinated with Architect Check for provision of protective earth and clean earth bars at each switchroom and riser location Consider whether dedicated earths are necessary (for example telecommunications and electronic systems) Check air terminals are considered with correct size and location Check roof strike termination network is considered with correct conductor size and location Check down coductors are considered with correct conductor size and spacing

No

Refer to detailed analysis

Refer to detailed analysis

Covered in the specifications only

Covered in the details only Refer to detailed analysis

Refer to detailed analysis

Refer to detailed analysis

Refer to detailed analysis

Table E.12

DVR 251011/109

P a g e | 53 / 292

Grounding & Lightning Protection Building KB-06 Verification Checklist Summary Checked Not Applicable Key Design Checks Compliance Not Applicable Partially Notes & Remarks

Yes

Yes

No

Final design report Owner/Operator requirement Soil resistivity measurement Check type of earthing system to be employed (such as TNS or TN-C-S) Check local electrical company requirements and electrical supply arrangements Check connections to other systems and determine any clean earth requirement Check earthing system calculations Check schematic of main earth bar and connections Check earth termination and space required Check electrical bonding details and provisions for other systems such as ceilings, catering equipment and raised floors Check relevant specification clauses Size of main earthing/equipotential bonding conductors Check consistency between electrical drawings

No

Not provided Not provided

Data not provided, refer to detailed analysis for assumptions


Refer to detailed analysis Data not provided, refer to detailed analysis and calculations Data not provided

Covered in the specifications only

Refer to detailed analysis Refer to detailed analysis and calculations Refer to detailed analysis

DVR 251011/109

P a g e | 54 / 292

Grounding & Lightning Protection Building KB-06 Verification Checklist Summary Checked Not Applicable Key Design Checks Compliance Not Applicable Partially Notes & Remarks

Yes

Yes

No

Check consistency between specifications and drawings Checking arrangement and location of earth pits (such as coordination with other trades (structural, Architectural and mechanical)) Check the use of transient earth clamps for clamping different earthing systems to prevent transient disturbances Provide main equipotential bonding (required for lightning protection, structure, incoming services, heating and ventilation). Provide supplementary bonding conductors to exposed and extraneous metal work such as trunking trays, ceiling grid and raised access floors Check that removable links for testing are specified. Check that test link location is coordinated with Architect Check for provision of protective earth and clean earth bars at each switchroom and riser location Consider whether dedicated earths are necessary (for example telecommunications and electronic systems) Check air terminals are considered with correct size and location

No

Refer to detailed analysis

Refer to detailed analysis

Refer to detailed analysis

Refer to detailed analysis

Covered in the specifications only

Covered in the details only Refer to detailed analysis

Refer to detailed analysis

Refer to detailed analysis

DVR 251011/109

P a g e | 55 / 292

Grounding & Lightning Protection Building KB-06 Verification Checklist Summary Checked Not Applicable Key Design Checks Compliance Not Applicable Partially Notes & Remarks

Yes

Yes

No

Check roof strike termination network is considered with correct conductor size and location Check down coductors are considered with correct conductor size and spacing

No

Table E.13

DVR 251011/109

P a g e | 56 / 292

IV.

DETAILED ANALYSIS A. MECHANICAL


1. Public health Below is the detailed analysis related to plumbing drainage system considering the methodology specified above:

a. BUILDING.(KB01&02)
Underground piping, submersible pumps and pits, gray water concrete tank and related calculations have been reviewed. I. DESIGN PARAMETERS:

The followings table shows the design parameters used in the IFC design documents and those extracted through the design review process Table M.14 : Design parameters Item Parking drain Fixtures Units AHU & FCU Fixtures Units Floor Drain Fixtures Units Slope of Drainage piping (100 & 150 mm Diameters) Rainfall intensity WC Flush flow rate Number of persons per m2 IFC Design Value Reference 21 UPC 2 UPC 2 UPC Not Indicated 758 mm/hr Not Indicated Not Indicated Not Indicated UPC Required Parameters Reference UPC2 UPC3 UPC3 IPC4 UPC5 UPC6

Value 8 2 2 1%

50 mm/hr 6.1 liter (1.6 gallon/flush) 14

Water consumption ratio per 5% shower Water consumption ratio per Not Plumbing Engineering 32% Indicated toilet flushing Servicing Design Water consumption ratio per Not Guide- The Institute of 20% Indicated Plumbing 20027 Laundry Water consumption ratio per Not 15% Indicated kitchen Water consumption ratio per Not 9% Indicated basin 1. IFC design indicates parking floor drain to have 2 FU. However, since pipe connection is 4 UPC calls for 8 FU to be used in calculations. 2. Refer to Appendix A, PageA.3 3. Refer to Appendix A, PageA.2 4. Refer to appendix A, Page A.11

DVR 251011/109

P a g e | 57 / 292

Table M.14 : Design parameters Item


5. 6. 7. 8.

IFC Design Value Reference

Required Parameters Value Reference

Refer to Appendix A, Page A.5 Refer to Appendix A, Page A.1 Refer to Appendix A, Page A.4 Rainfall intensity used by the designer varies for different buildings. It is recommended to use 50 mm/hr II. SUMP PITS & SUBMERSIBLE PUMPS (DSP-1): 1. Submersible pump-1 (DSP-1) has been reviewed as an example for others in the same building. Results of this review indicate that same issues are found in other areas within the same building 2. IFC Design plans(Drainage), IFC calculations, IFC risers, IFC structural drawings and sections have been reviewed, the following table shows the results:

Table M.15 ; DSP-1 Design data as per IFC Design Drawings & Calculations Output from design review
IFC Mechanical Drawings Plan 3rd Basement Master Floor Plumbing Plan (P-101) Drawings reference Ground Floor Master Plumbing Plan (P-116) Riser IFC Calculations IFC Structural Drawings Plan Sections Design Review Output

Sanitary Sewer System Riser Diagram (P401)

Calculations J09-07800

Master FoundAtion Plan (S101)

Sections & Details ( S-201)

N/A

Foundation Type Location Encasement for Drainage Pipe Under ground 3 Basement Grids (A&5)
rd

Column Base (Footing) 3rd Basement Grids (A&5) Shown

N/A

N/A

Not shown 2 pumps Flow = 2.6 L/s each Head = 1.2 Bar

Shown

Should be indicated on Plumbing drawings 2 pumps, flow = 2.2 L/s each Head = 2.0 Bar IFC Pumps accepted

Pump Data

Not provided

Not available

DVR 251011/109

P a g e | 58 / 292

Table M.15 ; DSP-1 Design data as per IFC Design Drawings & Calculations Output from design review
IFC Mechanical Drawings Plan 1.0 x 1.0x1.6 m3 Riser Not provided IFC Calculations IFC Structural Drawings Plan 1.0 m x 1.0 m Depth is not available Sections 1.8 x 1.8 x 2.4 m3 Design Review Output

Pit Size

Not available

1.3 x 1.3 x 2.0 m3

Pump discharge pipe size (Forced Flow)

100 mm

Not provided

Not provided

100 mm

Sump pit Service Mechanical Drawings Plan Parking drains Included Riser Included Not Included Calculations Plan N/A Structural Sections N/A Should be indicated on riser diagram and considered in calculations Should be included in plans, riser and calculations Should be shown on plans, riser and calculations Design Review Output

Elevator Pit Condensate drain

Not Included

Not Included Not Included

Not Included

N/A

N/A

Not Included

Not Included

N/A

N/A

Red: Not Acceptable, Orange: Partially, Green: Acceptable

3.

Description of above findings: a. Pump Flow rate: i. In the same discipline there is discrepancy in the Tag numbers between risers, calculations and plans. Same mismatching found with other disciplines like structural ii. It is required to drain the elevator pit with a separate pump set or with a floor drain connected to sump pit. iii. Flow of condensate drain from FCUs & AHUs is not considered in design calculations and not shown on plans or risers

4. Pump Head: Calculations are not included in IFC design for pump head 5. Pit Size: a. Modified calculations based on the above will change pit size b. Duplex Pump sizes are not taken into consideration c. Effective volume is not properly calculated d. Pit depth is less than required (Waste pipe invert level connected to sump pit is not taken into consideration) e. Elevator pit is not taken into consideration in sizing the pit depth

DVR 251011/109

P a g e | 59 / 292

f. No sand trap is provided at waste pipe connected to sump pit 6. Sample calculations:Below is a sample calculation for DSP-1 a. Flow Rate calculations: Consists of all waste water connected into sump pit-1 including: i. Parking drains ii. Condensate drains iii. Floor drains The following table shows flow of connected fixtures to DSP-1 done by design reviewer (IFC Design does not contain similar calculations): Table M.16 : Connected Fixtures to DSP-1 Fixture Parking Drains AHU & FCU Floor Drain Total Fixtures units Total Fixtures Flow Rate* Diversity (All systems shall not work together in any case) Total Flow Number 10 6 6 D.F.U.V Total 264 12 12 104 70 GPM (4.4 L/s) 75% 52.5 GPM (3.3 L/s) Unit 8 2 2 -

Reference for converting D.F.U.V to flow rate is NBS Monograph, Fig 3-3 NBS Monograph 31, Designflow curves for plumbing-drainage systems. Refer to Appendix A, Page A.15 b. Pump head calculations done by design reviewer (IFC design does not contain similar calculations): The below table shows pump head calculations for DSP-1 Table M.17 : Pump Head Calculations Static Head m Pipe Size mm Pipe Equivalent Length m Head Loss According to pipe size mm/m Fluid Velocity m/s Residual Pressure m Safety Factor Total pressure m.H2o (Bar) 20(2.0)

14 100 20 6 0.8 4 10% Head loss data & fluid velocity figures with respect to pipe size and flow are as per ASHRAE Fundamentals 2005 chapter 36, Pipe Sizing Refer to Appendix A, Page A.6

DVR 251011/109

P a g e | 60 / 292

c. Pump Selection: The below table shows pump selection and configuration Table M.18: Pump selection Pump Type No. Total Flow Pump Flow/each (66% of total flow) Pump Head Submersible waste water pump 2 Pumps (Duplex) 3.3 (52.5) 2.2 (35) 2.0 (20)

L/s (GPM) L/s (GPM) Bar (m H2O)

Pump diameter* mm 405 Pump Height* mm 770 Pump Length* mm 795 Configuration Lead-lag Reference for pump data from Grundfos Pumps; Refer to Appendix A, Page A.16 d. Pit sizing: The below table shows pit sizing calculations: Table M.19: Pit sizing Total Pump Flow GPM (L/s) in Gal. Gal/ft. ft. ft. in ft. ft. (m) 52.5 (3.3) 50 208 105 2.0 3.3 6.0 1.0 6.8 (2.0)

Basin Diameter Draw Down volume Capacity of fluid per ft. Draw Down Height Depth of lowest level incoming piping Difference between inlet pipe and high water level Minimum depth at the bottom of the basin Sump pit Height Min. pit size should be 1.3 x 1.3x 2.0 (3.4 m3) Procedure for sizing pit is described in Handbook of Mechanical Engineering Calculations; Part 3 Environmental Control; Section 15 Plumbing and Drainage for Buildings and Other Structures. Refer to Appendix A, Pages A.8, A.9, A.10

DVR 251011/109

P a g e | 61 / 292

7. Comparison: The following table shows a comparison between IFC and Design review output for DSP-1

Table M.20: Comparison between IFC and Design review output IFC No calculations Indicated. Flow on plans is 2.6 L/s for each pump No calculations Indicated. Head on plans is 1.2 Bar 1.6 m Not provided III. Design review output According to building flow requirement described in sample calculations (connected fixtures) Total Pump flow = 3.3 L/s (52.5 gpm) divided into 2 pumps 66% of total flow each Pump Flow = 2.2 L/s (35 GPM) each According to system head requirement, static head and discharge pipe size and routing Pump Head = 2.0 Bar Minimum depth shall not be less than 2.0 m Should be provided to block sand particles from entering and accumulating inside the pit

Pump flow rate calculations

Pump Head Pit depth Sand Trap

GRAY WATER TANK:

Table M.21 ; Gray water tank data as per IFC Design Drawings & Calculations output from design review Structure Plan
3rd BASEMENT MASTER FLOOR PLUMBING PLAN (P-101)

Calculations

Riser

Design Review Output

Drawing Reference

GROUND FLOOR MASTER PLUMBING PLAN (P-116)

Calculation J09-07800

Sanitary sewer system riser diagram (P-401)

Master foundation plan S 101 Water Tank Sections S 202

N/A

Grey Water Tank Size NonPotable Water Tank Size Location

Discrepancy on Plans, two capacities are available 216m3 & 270m3 Discrepancy on Plans, two capacities are available 216m3 & 270m3 Basement-3 Above Ground

200 m3

N/A

Tank indicated but size not considered

58.5 m3

200 m3

Not Shown Basement-3 Above Ground

Shown but the tank height is not indicated Basement-3 Above Ground

58.5 m3

N/A

Matching

DVR 251011/109

P a g e | 62 / 292

Table M.21 ; Gray water tank data as per IFC Design Drawings & Calculations output from design review Structure Plan Access Panel Overflow Vent Drain Make up water & backflow preventer Cat ladder Level of incoming waste line Not provided Not Provided Not Provided Provided Calculations N/A N/A N/A N/A Riser N/A Not Provided Not Provided Not Provided Not Provided N/A Not Provided N/A N/A N/A Design Review Output Should be provided Should be provided Should be provided Should be provided Should be provided Should be provided Should be taken into consideration

Not Provided

N/A

N/A

Not Provided Cannot be determined. No waste pipe connected to tank

N/A

Not Provided

N/A

Not Shown

N/A

Red: Not Acceptable, Orange: Partially, Green: Acceptable

1.

Description: a. Gray water tank is sized based on incorrect design parameters b. No waste pipe is connected to gray water tank, therefore, tank effective volume cannot be determined c. On plumbing plans, two capacities are provided for gray water and non-potable water tanks, 216m3 &270 m3 d. Calculation of Gray water tank capacity is not taking the incoming pipe level into consideration. Sample Calculations: The below is a sample calculations for sizing of gray water systems

2.

Table M.22; Gray Water Tank Size Verification Building Floor Area m2 m2 Persons

Total Area: Per person Area requirement--> (as per IPC code) Total no. of users (persons) ----------> OPTION-1 Assuming each person will use the WC a day WC Flow rate per flush

32,160 14 2,298

2.00 times 6.10 Liters

DVR 251011/109

P a g e | 63 / 292

Table M.22; Gray Water Tank Size Verification Water requirement per day for flushing No. of persons x no. of flushes x 6.1 liters

32,982 32.98

liters m3

OPTION-2 As per IPC Code Daily water demand for Office application Water requirement = persons x water demand ----->

45.00 121,654

liters/person liters

As per IPC Code, Water consumption ratio for appliances is as follows: Shower & Bath Toilet flushing Laundry Kitchen Basin Therefore, flushing water requirement ---> 38,929 38.93 Gray Water System (Collection tank plus treated tank) Capacity as per calculations ----> Gray water tank capacity = 58.5 m3 Non-Potable water tank capacity = 58.5 m3 Gray Water Tank Capacity as per IFC ----> 216.00

5% 32% 20% 15% 9% liters m3

39X3 Days 117 m3

m3

Comparison of IFC Capacities with Calculated Capacities


Tank Capacity (M3) as per Calculation No. of Days Holding based on IFC

Daily Requirement (m3)

38.9

5.55

3.

From above table, number of storage days is exceeding the 3 days allowable by the standard (IPC) Comparison:

4.

The below table shows a comparison between IFC and Design review output

DVR 251011/109

P a g e | 64 / 292

Table M.23: Gray Water System Comparison IFC Design review output 216 m3 Gray water tank sizes are overestimated. Correct system size is 117 m3 divided by two tanks 58.5 m3 each Should be taken into consideration and deducted from tank total height

Tank size

AS per plan size is 216 m3 or 270m3 As per calculation size is 102 m3

Level of incoming waste pipe

Not taken into consideration Cannot be identified since no waste pipe is connected to tank

DVR 251011/109

P a g e | 65 / 292

IV.

RECOMMENDATIONS:

Further to the design review study and analysis, and as per the above sample calculation for sump pits and gray water tanks for KB01&02 building, the following can be concluded: 1. It is recommended to use the correct design parameters in calculating the pump flow rate and to take condensate drain and elevator pits drain into consideration. 2. The pump head data for submersible pumps is found to be insufficient to reflect the true case and setting of the underground drainage system. It is recommended to use the correct design parameters in calculating the pump head and to take actual equivalent length, pipe friction loss and safety factors into consideration. 3. The pit size is found to be insufficient with respect to the fixtures and drainage points connected to it. It is recommended to take the level of incoming waste pipes and the size of submersible pumps into consideration when sizing the pit. 4. Gray water system is oversized. It is recommended to size the gray water tank for no more than 3 days (72 Hours) divided by two tanks, collection and treated tanks as per IPC. Refer to Appendix A, A.18 5. No waste pipe is connected to gray water tank. It is required to make clear routing of waste risers and pipes to gray water tank. 6. It is required to provide gray water tank with makeup water line with backflow preventer to avoid pump dry run. 7. It is required to provide the gray water tank with overflow, vent with insect screen, access panel and cat ladder for maintenance

DVR 251011/109

P a g e | 66 / 292

b. BUILDING (KB03)
Underground piping, submersible pumps and pits, gray water concrete tank and related calculations have been reviewed.

I.

DESIGN PARAMETERS:

The followings table shows the design parameters used in the IFC design documents and those extracted through the design review process

Table M.24 : Design parameters Item Parking drain Fixtures Units AHU & FCU Fixtures Units Floor Drain Fixtures Units Slope of Drainage piping (100 & 150 mm Diameters) Rainfall intensity WC Flush flow rate Number of persons per m2 IFC Design Value Reference 1 2 UPC 2 UPC 2 UPC Not Indicated Not Indicated Not Indicated Not Indicated Not Indicated UPC Required Parameters Reference UPC2 UPC3 UPC3 IPC4 UPC5 UPC6

Value 8 2 2 1%

50 mm/hr 6.1 liter (1.6 gallon/flush) 14

Water consumption ratio per 5% shower Water consumption ratio per Not Plumbing Engineering 32% Indicated toilet flushing Servicing Design Water consumption ratio per Not Guide- The Institute of 20% Indicated Plumbing 20027 Laundry Water consumption ratio per Not 15% Indicated kitchen Water consumption ratio per Not 9% Indicated basin 1. IFC design indicates parking floor drain to have 2 FU. However, since pipe connection is 4 UPC calls for 8 FU to be used in calculations. 2. Refer to Appendix A, PageA.3 3. Refer to Appendix A, PageA.2 4. Refer to appendix A, Page A.11 5. Refer to Appendix A, Page A.5 6. Refer to Appendix A, Page A.1 7. Refer to Appendix A, Page A.4 8. Rainfall intensity used by the designer varies for different buildings. It is recommended to use 50 mm/hr

DVR 251011/109

P a g e | 67 / 292

II.

SUMP PITS & SUBMERSIBLE PUMPS (SP-1): 1. Submersible pump-1 (SP-1) has been reviewed as an example for others in the same building. Results of this review indicate that same issues are found in other areas within the same building 2. IFC Design plans(Drainage), IFC calculations, IFC risers, IFC structural drawings and sections have been reviewed, the following table shows the results:

Table M.25: SP-1 Design data as per IFC Design Drawings & Calculations Output from design review
Mechanical Drawings Plan 4th Basement Master Floor Plumbing Plan (P-101) Drawings reference Ground Floor Master Plumbing Plan (P-110) Riser Calculations Structure Plan Sections Design Review Output

Riser Diagram Of Sewer, Waste & Vent Distribution System (101r-P002)

ITCC-18 Parcels Knowledge Business Corporate Office Building KB03 (Plumbing Calculations)

Foundation & 4th Basement Master Framing Plan

Sections & Details ( S-301)

N/A

Foundation Type Location Encasement for Drainage Pipe Under ground 4th Basement Grids (B&3) -

1200mm Raft Foundation 4th Basement Grids (B&3) N/A Should be indicated on Plumbing drawings 2 pumps 3.27 L/s each Head = 2.1 Bar IFC Pumps accepted

Not shown

Not shown

Not shown

Not shown

Not shown

Pump Data

Not shown

Total Flow = 5.61 L/s Head = 2.0 Bar

Flow = 5.61 L/s Head = 2.0 Bar

Pit Size Pump discharge pipe size (Forced Flow)

1.54 m x 1.54 m Depth is not available

N/A

1.0 x 1.0 x 1.5 m

1.54 m x 1.54 m Depth is not available

1.0 x 1.0 x 1.5 m

1.3x1.3x2.5 m3

75 mm

100 mm

DVR 251011/109

P a g e | 68 / 292

Table M.25: SP-1 Design data as per IFC Design Drawings & Calculations Output from design review
Mechanical Drawings Plan Riser Calculations Structure Plan Sections Design Review Output

SUMP PIT SERVICE Mechanical Drawings Plan Riser Parking drains Included Included Calculations Structure Plan Sections N/A N/A Design Review Output Should be indicated on riser diagram & Calculations Should be indicated on riser diagram & Calculations Should be indicated on riser diagram & Calculations Should be indicated on riser diagram

Included

Elevator Pit

Included

Not Included

Not Included

N/A

N/A

Rain water

Included

Not Included

Not Included

N/A

N/A

Condensate drain

Included

Not Included

Included

N/A

N/A

Red: Not Acceptable, Orange: Partially, Green: Acceptable

3.

Description of above findings: a. Pump Flow rate: i. In the same discipline there is discrepancy in the Tag numbers between risers, calculations and plans. Same mismatching found with other disciplines like structural ii. Pump flow rate is based on incorrect design parameters. However, pump flow/head of IFC drawing are enough iii. Flow of condensate drain from FCUs & AHUs is not considered in design calculations and not shown on plans or risers iv. Rain water from exposed ramp area is not considered in calculations.

DVR 251011/109

P a g e | 69 / 292

4. Pump Head: The following table shows IFC design data calculations and analysis; Table M.26: IFC Design Head Calculations Head Loss According Fluid Residual Safety Total pressure to pipe Velocity Pressure Factor size psi mm psi mm/m m/s m psi m. H2o (Bar) 20 75 14.5 17.3 1.2 2 2.9 20 (2.0) Head loss data & fluid velocity figures with respect to pipe size and flow are as per ASHRAE Fundamentals 2005 chapter 36, Pipe Sizing Refer to Appendix A, Page A.6 a. Based on new flow rate as per design review output, the above data are subject to change. b. Forced drain discharge pipe has very high values for pressure drop and velocity; diameter should be increased to 100 mm. 5. Pit Size: a. Modified calculations based on the above will change pit size. b. Duplex Pump sizes are not taken into consideration. c. Effective volume is not properly calculated. d. Pit depth is less than required (Waste pipe connected to sump pit is not taken into consideration) e. Elevator pit is not taken into consideration in sizing the pit depth. f. No sand trap is provided at waste pipe connected to sump pit. 6. Sample of calculation:Below is a sample calculation for SP-1 Static Head Pipe Size Pipe Friction loss a. Flow Rate calculations: Consists of all waste water connected to sump pit-1 including: i. Rain water ii. Parking drains iii. Condensate drains iv. Floor drains The following table shows rain water calculations as per UPC, done by design reviewer (IFC Design does not contain similar calculations): Table M.27: Rain water calculations
Exposed Ramp Area (m2) 100 Ground floor master plumbing plan (p-121) Rainfall Intensity (mm/hr) 50 1. As per 18 parcel group B calculations 2. AS per ITCC project Package 1&2 Flow Rate (L/s) 1.4

Reference

DVR 251011/109

P a g e | 70 / 292

The following table shows flow of connected fixtures to SP-1 done by design reviewer (IFC Design does not contain similar calculations): Table M.28 : Connected Fixtures to SP-1 Fixture Number Unit 8 2 D.F.U.V

Total Parking Drain 15 120 AHU & FCU 20 40 Floor Drain Total DFU 160 Total Fixtures Flow Rate 82 GPM (5.2 L/s) Reference for converting D.F.U.V to flow rate is NBS Monograph, Fig 3-3 NBS Monograph 31, Design-flow curves for plumbing-drainage systems. Refer to Appendix A, Page A.15 The following table shows total pump flow

Table M.29: Pump Total Flow Rain water Flow Fixture Flow Diversity* Total Pump Flow L/s L/s L/s (gpm) 75% 1.4 5.2 4.95 (78.5) *: Flow diversity of 75 % is considered since it is highly unlikely that all systems shall work together b. Pump head calculations; The below table shows pump head calculations for SP-1, done by design reviewer (IFC Design does not contain similar calculations): Table M.30 : Pump Head Calculations Static Head m 14 Pipe Size mm Pipe Equivalent Length m Head Loss According to pipe size mm/m Fluid Velocity m/s Residual Pressure m Safety Factor Total pressure

m. H2o (Bar) 100 95 14.5 1.26 4 10% 21(2.1) *: Head loss data & fluid velocity figures with respect to pipe size and flow are as per ASHRAE Fundamentals 2005 chapter 36, Pipe Sizing Refer to Appendix A, Page A.6

c. Pump Selection: The below table shows pump selection and configuration; done by design reviewer (IFC Design does not contain similar calculations):

DVR 251011/109

P a g e | 71 / 292

Table M.31 : Pump selection Pump Type No. Total Pump Flow Pump Flow Each 66% of total Flow Pump Head

Submersible waste water pump 2 Pumps (Duplex) L/s (GPM) L/s (GPM) Bar (m H2O) 4.95 (78.5) 3.3 (52) 2.1 (21)

Pump diameter* mm 405 Pump Height* mm 770 Pump Length* mm 795 Configuration Lead-lag *Reference for pump data from Grundfos Pumps; Refer to Appendix A, Page A.16 d. Pit sizing: The below table shows pit sizing calculations: Table M.32: Pit sizing Pump Flow GPM (L/s) in Gal. Gal/ft. ft. 78.5 (4.95) 50 311 105 2.96

Basin Diameter Draw Down volume Capacity of fluid per ft. Draw Down Height Depth of lowest level incoming ft. 3.75 piping Difference between inlet pipe and in 6.0 high water level Minimum depth at the bottom of the ft. 1.0 basin Sump pit Height ft. (m) 8.21 (2.5) Min. pit size should be 1.3 x 1.3x2.5 (4.3 m3) Procedure for sizing pit is described in Handbook of Mechanical Engineering Calculations; Part 3 Environmental Control; Section 15 Plumbing and Drainage for Buildings and Other Structures. Refer to Appendix A, Pages A.8, A.9, A.10

DVR 251011/109

P a g e | 72 / 292

7. Comparison: The following table shows a comparison between IFC and Design review output for SP-1

Table M.33 : Comparison between IFC and Design review output Pump flow rate calculations IFC IFC is using connected fixtures units taking PD and FU as 2 IFC is not taking rain water calculations into consideration. 2.0 1.5 m Not considered Design review output According to building flow requirement described in sample calculations ( Rain water and connected fixtures) Total Pump flow = 4.95 L/s (78.5 gpm) According to system head requirement, static head and discharge pipe size and routing Pump Head = 2.1 Bar Minimum depth shall not be less than 2.5 m Should be considered in calculations to find the lowest waste incoming pipe connected to SP-1 Should be provided to block sand particles from entering and accumulating inside the pit

Pump Head Pit depth Elevator Pit 1 Sand Trap 2

Not provided

1. Refer to Appendix A, Page A.7 2. Refer to Appendix A, Page A.13 III. GRAY WATER TANK:

The following table shows the results for grey water system review

Table M.34: Gray Water Tank design data as per mechanical, structural IFC drawings and calculations Design Review Output

Plan
4th Basement Master Floor Plumbing PLAN (P-101) Ground Floor Master Plumbing Plan (P-110)

Calculations
Itcc-18 Parcels Knowledge Business Corporation Office Building KB03 (Plumbing Calculations)

Riser

Structure

Drawing Reference

Typ. Riser Diagram Water, Sewer ,Waste & Vent Distribution System (101R-P002)

Foundation & 4th Basement Master Framing Plane

Gray water Tank Size Non-Potable Water Tank

36 m3 150 m3

36 m3 196 m3

N/A N/A

N/A

22 m3 22 m3

Shown but the tank height is

DVR 251011/109

P a g e | 73 / 292

Table M.34: Gray Water Tank design data as per mechanical, structural IFC drawings and calculations Design Review Output Matching

Plan Size Location Access Panel Overflow Vent Drain Make up water & backflow preventer Cat ladder Level of incoming waste line Basement-4 Above Ground Upper above Floor Not Provided Not Provided Not Provided

Calculations

Riser

Structure not indicated.

N/A N/A N/A N/A N/A

Basement-4, Above Ground N/A Provided Not Provided Provided

Basement-4, Above Ground Not Provided Provided N/A N/A

Not Provided

N/A

Not Provided

N/A

Should be provided Should be provided Should be provided Should be provided Should be provided

Not Provided +1800

N/A N/A

Not Provided N/A

Not Provided N/A

Should be provided Should be taken into consideration

Red: Not Acceptable, Orange: Partially, Green: Acceptable

1.

Description: a. Actual tank size is different than that in calculations and plans ( level of incoming waste pipe is not taken into considerations) b. Tank is not provided with ladder below tank access panel. c. Tank is not provided with overflow, vent & drain. d. Tank is not provided with makeup water line. e. Trench is located over Gray water tank footing, needs confirmation from structural engineer. f. Gray water tank sizing: The following table shows gray water tank effective volume as per IFC drainage plans and structural drawings: g. Effective volume is 26 m3 as per IFC and this is below required as per calculations (36m3)

DVR 251011/109

P a g e | 74 / 292

Table M.35: Gray Water Tank Effective Volume Gray water tank as per IFC design calculations Given tank area Tank height Depth of lowest level incoming piping Difference between inlet pipe and high water level Effective height Effective volume 2. Sample Calculations:

m3 m2 m m m m m3

36 15.8 2.35 1.8 0.15 1.65 26

The below is a sample calculations for sizing of gray water systems

Table M.36 : Gray Water Tank Size Verification Total Area: Per person Area requirement--> (as per IPC code) Total no. of users (persons) ----------> OPTION-1 Assuming each person will use the WC a day Quantity of flushed water per flushing Water requirement per day for flushing No. of persons x no. of flushes x 6.1 liters OPTION-2 As per IPC Code Daily water demand for Office application Water requirement = persons x water demand -----> 14,443.00 14 1,032 Building Floor Area m2 m2 Persons

2.00 times 6.10 Liters 12,586 12.59 liters m3

45.00 46,424

liters/person liters

As per IPC Code, Water consumption ratio for appliances is as follows: Shower & Bath Toilet flushing Laundry Kitchen Basin So, Flushing water requirement ---> 14,856

5% 32% 20% 15% 9% liters 14.86 m3

Gray Water System (Collection tank plus treated tank) Capacity as per calculations ----> Gray water tank capacity = 22 m3 Non-Potable water tank capacity = 22 m3 Gray Water Tank Capacity as per IFC ---->

14.68 X3 Days = 44 m3 m3

36.00

DVR 251011/109

P a g e | 75 / 292

Comparison of IFC Capacities with Calculated Capacities


Tank Capacity (M3) as per Calculation

Daily Requirement (m3) 14.9

No. of Days Holding 2.42

3.

Comparison:

The below table shows a comparison between IFC and Design review output

Table M.37 : Gray Water System Comparison IFC Design review output Gray water system total size is 44 m3, reserve for 72 hours, divided by two tanks; gray water collection and treated tank 22 m3 each. Level of incoming waste pipe Pipe level is 1800 mm measured from tank bottom level Should be taken into consideration and deducted from tank total height

Tank size

AS per IFC PG plans and calculations, tank size is 36m3

Not taken into consideration

DVR 251011/109

P a g e | 76 / 292

IV.

RECOMMENDATIONS:

Further to the design review study and analysis, and as per the above sample calculation for sump pits and gray water tanks for KB03 building, we conclude the following: 1. The discharge pipe from submersible pump is having high pressure loss and fluid velocity, it is recommended to resize the pipe according to the allowable pressure loss and velocity parameters. 2. Pit sizing: The level of lowest invert level incoming waste pipe is not taken into consideration when sizing the pit depth. Also, the size of duplex pumps should be given more attention in sizing the pit to verify if the current size fits for two submersible pumps. 3. The pit size is found to be insufficient with respect to the fixtures and drainage points connected to it. It is recommended to take the level of incoming waste pipes and the size of submersible pumps into consideration when sizing the pit. 4. Gray water tank is oversized. It is recommended to size the gray water tank for no more than 3 days (72 Hours), as per IPC. 5. It is required to provide gray water tank with makeup water line with backflow preventer to avoid pump dry run. 6. It is required to provide the gray water tank with overflow, vent with insect screen, and access panel and cat ladder for maintenance

DVR 251011/109

P a g e | 77 / 292

c. BUILDING (RD-03)
Underground piping, submersible pumps and pits, gray water concrete tank and related calculations have been reviewed.

I.

DESIGN PARAMETERS:

The followings table shows the design parameters used in the IFC design documents and those extracted through the design review process Table M.38 : Design parameters Item Parking drain Fixtures Units AHU & FCU Fixtures Units Floor Drain Fixtures Units Slope of Drainage piping (100 & 150 mm Diameters) Rainfall intensity WC Flush flow rate Number of persons per m2 IFC Design Value Reference 21 UPC 2 UPC 2 UPC Not Indicated 100 mm/hr8 Not Indicated Not Indicated Not Indicated UPC Required Parameters Value Reference 8 UPC2 2 UPC3 2 UPC3 1% 50 mm/hr 6.1 liter (1.6 gallon/flush) 14 IPC4 UPC5 UPC6

Water consumption ratio per 5% shower Water consumption ratio per Not Plumbing Engineering 32% Indicated toilet flushing Servicing Design Water consumption ratio per Not Guide- The Institute of 20% Indicated Plumbing 20027 Laundry Water consumption ratio per Not 15% Indicated kitchen Water consumption ratio per Not 9% Indicated basin 1. IFC design indicates parking floor drain to have 2 FU. However, since pipe connection is 4 UPC calls for 8 FU to be used in calculations. 2. Refer to Appendix A, PageA.3 3. Refer to Appendix A, PageA.2 4. Refer to appendix A, Page A.11 5. Refer to Appendix A, Page A.5 6. Refer to Appendix A, Page A.1 7. Refer to Appendix A, Page A.4 8. Rainfall intensity used by the designer varies for different buildings. It is recommended to use 50 mm/hr

DVR 251011/109

P a g e | 78 / 292

II.

SUMP PITS & SUBMERSIBLE PUMPS (SP-1) 1. Submersible pump-1 (SP-1) has been reviewed as an example for others in the same building. Results of this review indicate that same issues are found in other areas within the same building 2. IFC Design plans(Drainage), IFC calculations, IFC risers, IFC structural drawings and sections have been reviewed, the following table shows the results:

Table M.39: SP-1 Design data as per IFC Design Drawings & Calculations Output from design review
Mechanical Drawings Plan Riser 4th basement master floor plumbing plan (PG-101) Ground floor plumbing plan (P-105) Calculations Plan Structure Sections Design Review Output

Drawings reference

Water drainage, waste & vent Schematic riser diagram PG 402

18-parcles RD-04 (plumbing calculations)

4th basement Foundation Master floor plan (S-101)

Foundation schedule & detail S 201

Foundatio n Type 4th Basement Grids (D & 01)

Column base (footings) 4th Basement Grids (D &01)

Location

Shown and miss matches with structural plan, height size was referred to PG(in which not found)

Encaseme nt for Drainage Pipe Under ground

Not shown

Shown Without sizing

Should be shown

Pump Data

Not available

Not available

Total Flow = 6.3 L/s Head = not available

2 pumps Flow =2.65 L/s Head = 2.2 Bar IFC Pumps are accepted 1.4x1.4x1.9 m3

Pit Size

1.4 m x 1.2 m Depth is not available

Not available

1.2 x 1.2 x 1.2 m

1.4 m x 1.2 m Depth is not available

1.8 x 1.8 (depth is not available refer to PG)

DVR 251011/109

P a g e | 79 / 292

Table M.39: SP-1 Design data as per IFC Design Drawings & Calculations Output from design review
Mechanical Drawings Plan Riser Calculations Plan Sump pit Service Mechanical Drawings Plan Riser Parking drains Elevator Pit Rain water Condensat e drain Included Not Included Calculations Plan Not Included N/A Structure Sections N/A Design Review Output ok Should be included in plans and riser Should be included Should be included Structure Sections Design Review Output

Not Included

Not Included

Not Included

N/A

N/A

Included

Not Included

Included

N/A

N/A

Not Included

Not Included

Not Included

N/A

N/A

Red: Not Acceptable, Orange: Partially, Green: Acceptable

3. Description: a. Pump Flow rate i. In the same discipline there is discrepancy in the Tag numbers miss matching with riser, calculation, and plans, and same mismatching with other disciplines like structural. ii. Pump flow rate is based on incorrect design parameters where only rain water flow is considered while connected fixtures to sump pit are not considered. iii. No pump head calculation founded on IFC design calculation. 4. Pump Head: Calculations are not included in IFC design for pump head 5. Pit Size: a. Modified calculations based on the above will change pit size. b. Duplex Pump sizes are not taken into consideration. c. Effective volume is not properly calculated. d. Pit depth is less than required (Waste pipe connected to sump pit is not taken into consideration) e. Elevator pit is not taken into consideration in sizing the pit depth. f. No sand trap is provided at waste pipe connected to sump pit.

DVR 251011/109

P a g e | 80 / 292

6. Sample of calculation:Below is a sample calculation for SP-1 a. Flow Rate calculations: Consists of all waste water connected to sump pit-1 including: i. Rain water ii. Parking & Floor drains The following table shows rain water calculations as per UPC, done by design reviewer (IFC Design does not contain similar calculations): Table M.40: Rain water calculations
Exposed Ramp Area (m2) 200 Ground Floor Master Plumbing Plan (PG-105) Rainfall Intensity (mm/hr) 50 1. As per 18 parcel group B calculations 2. AS per ITCC project Package 1&2 Flow Rate (L/s) 2.7

Reference

The following table shows flow of connected fixtures to SP-1 done by design reviewer (IFC Design does not contain similar calculations): Table M.41: Connected Fixtures to SP-1 Fixture Number D.F.U.V

Unit Total Parking Drain 4 8 24 Floor Drains 2 2 4 Total 28 Fixtures Flow Rate 40 GPM (2.6 L/s) Reference for converting D.F.U.V to flow rate is NBS Monograph, Fig 3-3 NBS Monograph 31, Design-flow curves for plumbing-drainage systems. Refer to Appendix A, Page A.15 The following table shows total pump flow Table M.42: Pump Total Flow Rain water Flow Fixture Flow Diversity * Total Pump Flow L/s L/s L/s (gpm) 75% 2.7 2.6 4.0 (63.5) *: 75% diversity is considered since it is highly unlikely that all systems shall work together

DVR 251011/109

P a g e | 81 / 292

b. Pump head calculations; The below table shows pump head calculations for SP-1 Table M.43 : Pump Head Calculations Pipe Head Loss Total Fluid Residual Safety Equivalent According to pressure Velocity Pressure Factor Length pipe size m mm m mm/m m/s m m. H2o (Bar) 15.6 100 25 7.5 0.85 4 10% 21 (2.1) Head loss data & fluid velocity figures with respect to pipe size and flow are as per ASHRAE Fundamentals 2005 chapter 36, Pipe Sizing Refer to Appendix A, Page A.6 Static Head Pipe Size c. Pump Selection: The below table shows pump selection and configuration Table M.44 : Pump Selection Pump Type No. Total Pump Flow Pump Flow/each 66% of total flow Pump Head Submersible waste water pump 2 Pumps (Duplex) L/s (GPM) L/s (GPM) Bar (m H2O) 4.0 (63.5) 2.65 (42) 2.1 (21)

Pump diameter* mm 405 Pump Height* mm 770 Pump Length* mm 795 Configuration Lead-lag Reference for pump data from Grundfos Pumps; Refer to Appendix A, Page A.16 d. Pit sizing: The below table shows pit sizing calculations: Table M.45: Pit Sizing Pump Flow Basin Diameter Draw Down volume Capacity of fluid per ft. Draw Down Height Depth of lowest level incoming piping Difference between inlet pipe and high water level GPM (L/s) in Gal. Gal/ft. ft. ft. in 63.5 (4.0) 54 255 123 2.1 2.6 6.0

DVR 251011/109

P a g e | 82 / 292

Minimum depth at the bottom of the ft. 1.0 basin Sump pit Height ft. (m) 6.2 (1.9) Min. pit size should be 1.4 x 1.4 x 1.9 (3.75 m3) Procedure for sizing pit is described in Handbook of Mechanical Engineering Calculations; Part 3 Environmental Control; Section 15 Plumbing and Drainage for Buildings and Other Structures. Refer to Appendix A, Pages A.8, A.9, A.10 7. Comparison: The following table shows a comparison between IFC and Design review output

Table M.46: Comparison between IFC and Design review output Pump flow rate calculations IFC IFC is using rain water calculation but with incorrect area. IFC is not taking gray water overflow into consideration. 1.5 m Not considered Not provided Design review output According to building flow requirement described in sample calculations ( Rain water and connected fixtures, gray water overflow) Total Pump flow = 4.0 L/s (63.5 gpm) 2 Pumps 66% of total flow Minimum depth shall not be less than 1.9 m Should be considered in calculations to find the lowest waste incoming pipe connected to SP-1 Should be provided to block sand particles from entering and accumulating inside the pit

Pit depth Elevator Pit 1 Sand Trap 2

1. Refer to Appendix A, Page A.7 2. Refer to Appendix A, Page A.13

III.

GRAY WATER TANK:

Table M.47: Gray water tank data as per IFC Design Drawings & Calculations output from design
review

Plan
4th Basement Master Floor Plumbing Plan (PG-101) Ground Floor Plumbing Plan (P-105)

Calculations

Riser

Structure

Design review output

Drawing Reference

18-Parcles RD-04 (Plumbing Calculations)

Water Drainage, Waste & Vent Schematic Riser Diagram PG 402

4th Basement Foundation Floor Plan Master (10 & 2) (S-101)

Gray Water Tank size NonPotable

Not provided No tank is available

Not provided Not provided

Not provided Not provided

Not provided Not provided

11 m3 11 m3

DVR 251011/109

P a g e | 83 / 292

Table M.47: Gray water tank data as per IFC Design Drawings & Calculations output from design
review

Plan Water Tank Size Location Access Panel Overflow Vent Drain Make up water & backflow preventer Cat ladder Level of incoming waste line Basement-4, above Ground Not provided Provided Provided Not Provided

Calculations

Riser

Structure

Design review output

N/A N/A N/A N/A N/A

Basement-4, above Ground N/A Provided Provided Not Provided

Basement-4, Above Ground Not Provided N/A N/A N/A

Matching Should be provided Should be provided Should be provided Should be provided Should be provided

Provided

N/A

Provided

N/A

Not Provided +2230

Not Provided N/A

Not Provided N/A

Not Provided N/A

Should be provided Should be taken into consideration

Red: Not Acceptable, Orange: Partially, Green: Acceptable

1.

Description: a. There are no reference for any calculation for gray water tank or non-potable water tank capacity and size. b. Gray water system is not divided into two tanks; gray collection and treated water c. Actual tank size is different than that in calculations and plans ( Level of incoming waste pipe is not taken into considerations) d. Tank is not provided with ladder below tank access panel. e. Tank is not provided with makeup water line. f. Tank trench is located at tank bottom footing & needs confirmation from structural engineer. g. Gray water tank sizing: the following table shows gray water tank effective volume as per drainage plans and structural drawings:

Table M.48: Gray Water Tank Effective Volume Tank Volume as Per IFC design calculations Given tank area Tank height m3 m2 m Not available 16.3 2.93

DVR 251011/109

P a g e | 84 / 292

Depth of lowest level incoming piping Difference between inlet pipe and high water level Effective height Effective volume

m m m m3

2.23 0.15 2.1 34.23

h. Effective volume is 34.23 m3 as per IFC. i. There is no size for Gray water tank indicated on plans or calculations.

2.

Sample Calculations:

The below is a sample calculations for sizing of gray water systems Table M.49 : Gray Water Tank Size Verification Building Floor Area m2 m2 Persons

Total Area: Per person Area requirement--> (as per IPC code) Total no. of users (persons) ---------->

7,153.00 14 511

OPTION-1 Assuming each person will use the WC a day Quantity of flushed water per flushing Water requirement per day for flushing No. of persons x no. of flushes x 6.1 liters 2.00 times 6.10 Liters 6,233 6.23 liters m3

OPTION-2 As per IPC Code Daily water demand for Office application Water requirement = persons x water demand ----->

45.00 22,992

liters/person liters

As per IPC Code, Water consumption ratio for appliances is as follows: Shower & Bath Toilet flushing Laundry Kitchen Basin So, Flushing water requirement ---> 7,357 7.36 Gray Water System (Collection tank plus treated tank) Capacity as per calculations ----> Gray water tank capacity = 11 m3

5% 32% 20% 15% 9% liters m3

7.36X3 Days 117 m3 = 22 Not Available m3

DVR 251011/109

P a g e | 85 / 292

Non-Potable water tank capacity = 11 m3 Gray Water Tank Capacity as per IFC ---->

3.

Comparison; The below table shows a comparison between IFC and Design review output

Table M.50: Non Potable Water Tank Comparison IFC AS per IFC PG plans and calculations, tank is not sized, however effective volume has been calculated using mechanical & structural drawings and found to be 34.23 m3 Design review output AS per structural drawings, effective tank size is 34 m3 Gray water system total size is 22 m3, reserve for 72 hours, divided by two tanks; gray water collection and treated tank 11 m3 each. Pipe level is 2330 mm measured from tank bottom level Should be taken into consideration and deducted from tank total height Location should be coordinated with structural gray water tank footing. Tank should be split into two tanks, gray water collection tank & treated water tank.

Tank size

Level of incoming waste pipe

Not taken into consideration

Trench location ( serving gray water) Tank partition

Located above gray water tank footing

One partition

DVR 251011/109

P a g e | 86 / 292

IV.

RECOMMENDATIONS:

Further to the design review study and analysis, and as per the above sample calculation for sump pits and gray water tanks for RD03 building, the following can be concluded:

1. There is no reference to any calculations indicating the submersible pump head, the head is also not indicated on plans and risers. It is recommended to provide all data on plans, risers and calculations. 2. Pit sizing: The level of lowest invert level incoming waste pipe is not taken into consideration when sizing the pit depth. Also, the size of duplex pumps should be given more attention in sizing the pit to verify if the current size fits for two submersible pumps. 3. The pit size is found to be insufficient with respect to the fixtures and drainage points connected to it. It is recommended to take the level of incoming waste pipes and the size of submersible pumps into consideration when sizing the pit. 4. It is required to provide gray water tank with makeup water line with backflow preventer to avoid pump dry run.

5. It is required to provide the gray water tank with overflow, vent with insect screen, and access panel and cat ladder for maintenance. 6. It is required to coordinate the tank trench location with structural engineering to avoid trench in tank footing. 7. It is required to separate the tank into two partitions, one for gray water collection and the other for treated water.

DVR 251011/109

P a g e | 87 / 292

d. BUILDING (RD-04)
Underground piping, submersible pumps and pits, gray water concrete tank and related calculations have been reviewed.

I.

DESIGN PARAMETERS:

The followings table shows the design parameters used in the IFC design documents and those extracted through the design review process Table M.51: Design parameters Item Parking drain Fixtures Units AHU & FCU Fixtures Units Floor Drain Fixtures Units Slope of Drainage piping (100 & 150 mm Diameters) Rainfall intensity WC Flush flow rate Number of persons per m2 IFC Design Value Reference 21 UPC 2 UPC 2 UPC Not Indicated 100 mm/hr8 Not Indicated Not Indicated Not Indicated UPC Required Parameters Value Reference 8 UPC2 2 UPC3 2 UPC3 1% 50 mm/hr 6.1 liter (1.6 gallon/flush) 14 IPC4 UPC5 UPC6

Water consumption ratio per 5% shower Water consumption ratio per Not Plumbing Engineering 32% Indicated toilet flushing Servicing Design Water consumption ratio per Not Guide- The Institute of 20% Indicated Plumbing 20027 Laundry Water consumption ratio per Not 15% Indicated kitchen Water consumption ratio per Not 9% Indicated basin 1. IFC design indicates parking floor drain to have 2 FU. However, since pipe connection is 4 UPC calls for 8 FU to be used in calculations. 2. Refer to Appendix A, PageA.3 3. Refer to Appendix A, PageA.2 4. Refer to appendix A, Page A.11 5. Refer to Appendix A, Page A.5 6. Refer to Appendix A, Page A.1 7. Refer to Appendix A, Page A.4 8. Rainfall intensity used by the designer varies for different buildings. It is recommended to use 50 mm/hr

DVR 251011/109

P a g e | 88 / 292

II.

SUMP PITS & SUBMERSIBLE PUMPS (SP-2) 1. Submersible pump-2 (SP-2) has been reviewed as an example for others in the same building. Results of this review indicate that same issues are found in other areas within the same building 2. IFC Design plans(Drainage), IFC calculations, IFC risers, IFC structural drawings and sections have been reviewed, the following table shows the results:

Table M.52: SP-2 Design data as per IFC Design Drawings & Calculations Output from design review
Mechanical Drawings Plan Riser 4th basement Drainage, floor waste & plumbing plan vent (PG-101) Schematic riser Ground floor diagram plumbing plan (PG- 402) (P-104) Calculations Structure Plan Sections 4th basement Foundation Master floor plan (S-101) Foundation schedule & detail (S- 201) Design Review Output

Drawings reference

18-parcles RD-04 (Plumbing Calculations)

Foundation Type Location Encasement for Drainage Pipe Under ground 4th Basement Grids (D & 10) Not shown -

Column base (footing) 4th Basement Grids (D &10) Shown Should be indicated on Plumbing drawings 2 pumps 4.16 L/s Each Head = 2.2 Bar IFC pumps are accepted

Shown

Pump Data

Not shown

Not shown

Total Flow = 6.3 L/s Head = not available

Pump discharge pipe size (Forced Flow) Pit Size

75 mm 1.4 m x 1.2 m Depth is not available

Not shown 1.4 m x 1.2 m Depth is not available

100 mm
1.8 x 1.8 x 2.25 m3

N/A

1.2 x 1.2 x 1.2 m Sump pit Service

1.3x1.3x2.4 m3

Mechanical Drawings Plan Riser Parking drains Elevator Pit Rain water Condensate drain Included Not Included Not Included Not Included Not Included Not Included Not Included Not Included

Calculations Not Included Not Included Included Not Included

Structure Plan Sections N/A N/A N/A N/A N/A N/A N/A N/A

Design Review Output Should be included Should be included Should be included Should be included

Red: Not Acceptable, Orange: Partially, Green: Acceptable

DVR 251011/109

P a g e | 89 / 292

3. Description: a. Pump Flow rate; i. In the same discipline there is discrepancy in the Tag numbers miss matching with riser, calculation, and plans, and same mismatching with other disciplines like structural. ii. Pump flow rate is based on incorrect design parameters where only rain water flow is considered while connected fixtures to sump pit are not considered. iii. It is required to drain the elevator pit with a separate pump set or with a floor drain connected to sump pit. iv. Flow of condensate drain from FCUs & AHUs is not considered in design calculations and not shown on plans or risers 4. Pump Head: a. No calculations for pump head are provided on IFC calculations b. Based on new flow rate as per design review output, the above data are subject to change. c. Forced drain discharge pipe has very high values for pressure drop & velocity; diameter should be increased to 100 mm. 5. Pit Size: a. b. c. d. e. f. No size is indicated on sump pit on IFC plumbing plans No calculations for pit size on IFC documents Modified calculations based on the above will change pit size. Duplex Pump sizes are not taken into consideration. Effective volume is not properly calculated. Pit depth is less than required (Waste pipe connected to sump pit is not taken into consideration) g. Elevator pit is not taken into consideration in sizing the pit depth. h. No sand trap is provided at waste pipe connected to sump pit. 6. Sample of calculation:Below is a sample calculation for SP-2 a. Flow Rate calculations: Consists of all waste water connected to SP-2 including: i. Rain water ii. Parking drains iii. Gray water tank overflow The following table shows rain water calculations as per UPC; done by design reviewer (IFC Design does not contain similar calculations):

DVR 251011/109

P a g e | 90 / 292

Table M.52: Rain water calculations


Exposed Ramp Area (m2) 150 Ground floor master plumbing plan (P-121) Rainfall Intensity (mm/hr) 50 1. As per 18 parcel group B calculations 2. As per ITCC project Package 1&2 Flow Rate (L/s) 2.1

Reference

The following table shows flow of gray water tank connected to SP-2, done by design reviewer (IFC Design does not contain similar calculations): Table M.53: Flow of Gray water tank overflow & Drain to SP-2 Tank size 50 m3 Drain time 6 hours Flow 2.3 L/s

The following table shows flow of connected fixtures to SP-2 Table M.54: Connected Fixtures to SP-2 Fixture Number Unit 8 2 2 D.F.U.V

Total Parking Drain 6 48 AHU & FCU 1 2 Floor Drains 2 4 Total 54 Total Fixtures Flow Rate 50 GPM (3.15) Reference for converting D.F.U.V to flow rate is NBS Monograph, Fig 3-3 NBS Monograph 31, Design-flow curves for plumbing-drainage systems. Refer to Appendix A, Page A.15 The following table shows total pump flow Table M.55: Pump Total Flow Gray water tank overflow Rain water Flow Fixture Flow Diversity* Total Pump Flow L/S (gpm) L/s L/s L/s (gpm) 75 % 2.3 (36.5) 2.1 (33.3) 3.5 (55.5) 5.9 (94) *: 75% Diversity is considered since it is highly unlikely that all systems shall work together

DVR 251011/109

P a g e | 91 / 292

b. Pump head calculations; The below table shows pump head calculations for SP-2 Table M.56: Pump Head Calculations Static Head m Pipe Size mm Pipe Equivalent Length m Head Loss According to pipe size mm/m Fluid Velocity m/s Residual Pressure m Safety Factor Total pressure m. H2o (Bar) 21 (2.1)

15.7 100 25 15 1.2 4 10% Head loss data & fluid velocity figures with respect to pipe size and flow are as per ASHRAE Fundamentals 2005 chapter 36, Pipe Sizing Refer to Appendix A, Page A.6 c. Pump Selection: The below table shows pump selection and configuration Table M.57: Pump selection Pump Type No. Total Pump Flow Each pump flow 66% of total pump flow Pump Head

Submersible waste water pump 2 Pumps (Duplex) L/s (GPM) L/s (GPM) Bar (m H2O) 5.9 (94) 3.89 (62) 2.1 (21)

Pump diameter* mm 405 Pump Height* mm 770 Pump Length* mm 795 Configuration Lead-lag Reference for pump data from Grundfos Pumps; Refer to Appendix A, Page A.16 d. Pit sizing: The below table shows pit sizing calculations: Table M.58: Pit sizing Pump Flow Basin Diameter Draw Down volume Capacity of fluid per ft. Draw Down Height Depth of lowest level incoming piping Difference between inlet pipe and high water level Minimum depth at the bottom of the basin GPM (L/s) in Gal. Gal/ft. ft. ft. in ft. 94 (5.9) 50 372 105 3.5 2.9 6.0 1.0

DVR 251011/109

P a g e | 92 / 292

Table M.58: Pit sizing Sump pit Height ft. (m) 7.9 (2.4) 3 Min. pit size should be 1.3 x 1.3 x 2.4 (4.0 m ) Procedure for sizing pit is described in Handbook of Mechanical Engineering Calculations; Part 3 Environmental Control; Section 15 Plumbing and Drainage for Buildings and Other Structures. Refer to Appendix A, Pages A.8, A.9, A.10 7. Comparison: The following table shows a comparison between IFC and Design review output for SP-2 Table M.59: Comparison between IFC and Design review output IFC IFC is using rain water calculation but with incorrect area. IFC is using connected fixtures units taking PD and FU as 2 IFC is not taking gray water overflow into consideration. 1.0 m Not considered Not provided Design review output According to building flow requirement described in sample calculations ( Rain water and connected fixtures, gray water overflow) Total Pump flow = 5.9 L/s (94 gpm) IFC pumps are accepted Minimum depth shall not be less than 2.4 m Should be considered in calculations to find the lowest waste incoming pipe connected to SP-1 Should be provided to block sand particles from entering and accumulating inside the pit

Pump flow rate calculations

Pit depth Elevator Pit 1 Sand Trap 2

1. Refer to Appendix A, Page A.7 2. Refer to Appendix A, Page A.13 III. GRAY WATER TANK:

Table M.60: Gray water System data as per IFC Design Drawings & Calculations output from design review Plan
4th basement floor plumbing plan (PG-101)

Calculations

Riser

Structure
4th basement Foundation Master floor plan (S-101) Foundation schedule & detail (S- 201)

Design review output

Drawing Reference

Ground floor plumbing plan (P-104)

18-parcles RD-04 (plumbing calculations)

Drainage, waste & vent Schematic riser diagram PG 402

DVR 251011/109

P a g e | 93 / 292

Table M.60: Gray water System data as per IFC Design Drawings & Calculations output from design review Plan Gray Water Tank Size Non-Potable Water Tank Size Location Access Panel Overflow Vent Drain Make up water & backflow preventer Cat ladder Level of incoming waste line Not Provided No tank is available Basement-4, Above Ground Not Provided Not Provided Provided Not Provided Provided Not Provided +2330 Calculations 32 m3 Not provided N/A N/A N/A N/A N/A N/A N/A N/A Riser 50 m3 Not provided Basement-4, Above Ground N/A Not Provided Not Provided Not Provided Provided Not Provided N/A Structure
Not provided

Design review output


16 m3 16 m3

Not provided Basement-4, Above Ground Not provided N/A N/A N/A N/A Not Provided N/A

Matching Should be provided Should be provided Should be provided Should be provided Should be provided Should be provided Should be taken into consideration

Red: Not Acceptable, Orange: Partially, Green: Acceptable

1.

Description: a. Gray water system is not divided into two tanks; gray collection and treated water b. Actual tank size is different than that in calculations and plans c. ( Level of incoming waste pipe is not taken into considerations) d. Tank is not provided with ladder below tank access panel. e. Tank is not provided with overflow, vent & drain. f. Tank trench is located at tank bottom footing & needs confirmation from structural engineer. g. Gray water tank sizing: the following table shows gray water tank effective volume as per drainage IFC plans and structural drawings h. Effective volume is 105 m3 as per IFC and this is not matching calculations (32m3)

DVR 251011/109

P a g e | 94 / 292

Table M. 61 Gray Water Tank Effective Volume Tank Volume as Per IFC design calculations Given tank area Tank height Depth of lowest level incoming piping Difference between inlet pipe and high water level Effective height Effective volume m3 m2 m m m m m3 32 48.2 2.6 2.33 0.15 2.18 105

2.

Sample Calculations:

The below is a sample calculations for sizing of gray water systems

Table M.62 : Gray Water Tank Size Verification Building Floor Area m2 m2 Persons

Total Area: Per person Area requirement--> (as per IPC code) Total no. of users (persons) ----------> OPTION-1 Assuming each person will use the WC a day Quantity of flushed water per flushing Water requirement per day for flushing No. of persons x no. of flushes x 6.1 liters OPTION-2 As per IPC Code Daily water demand for Office application Water requirement = persons x water demand ----->

10,257.00 14 733

2.00 times 6.10 Liters 8,938 8.94 liters m3

45.00 32,969

liters/person liters

As per IPC Code, Water consumption ratio for appliances is as follows: Shower & Bath 5% Toilet flushing 32% Laundry 20% Kitchen 15% Basin 9% So, Flushing water requirement ---> 10,550 liters 10.55 m3 Gray Water System (Collection tank plus treated 10.55X3 Days tank) Capacity as per calculations ----> = 32 m3 Gray water tank capacity = 16 m3 Non-Potable water tank capacity = 16 m3

DVR 251011/109

P a g e | 95 / 292

Table M.62 : Gray Water Tank Size Verification Gray Water Tank Capacity as per IFC ----> 50.00 m3

Comparison of IFC Capacities with Calculated Capacities


Tank Capacity (M3) as per Calculation Daily Requirement (m3) 10.55 No. of Days Holding 4.7

3.

From above table, number of storage days is exceeding the 3 days allowable by the standard (IPC) Comparison:

4.

The below table shows a comparison between IFC and Design review output

Table M.63: Non Potable Water Tank Comparison IFC As per IFC PG calculations, tank size is 32 m3 Tank size As per IFC PG riser, tank size is 50 m3 Design review output As per structural drawings, effective tank size is 105 m3 Tank size needs confirmation from supplier 105 m3, 50 m3 and 32 m3 gray water tank sizes is overestimated Correct system size is 32 m3 divided into 2 tanks 16 m3 each. Pipe level is 2330 mm measured from tank bottom level Should be taken into consideration and deducted from tank total height Location should be coordinated with structural gray water tank footing. Tank should be split into two tanks, gray water collection tank & treated water tank.

Level of incoming waste pipe Not taken into consideration

Trench location ( serving gray water) Tank partition

Located above gray water tank footing One partition

DVR 251011/109

P a g e | 96 / 292

IV.

RECOMMENDATIONS:

Further to the design review study and analysis, and as per the above sample calculation for sump pits and gray water tanks for RD04 building, the following can be concluded:

1. Submersible pump data are not shown on plans and riser. 2. There is no reference to any calculations indicating the submersible pump head, the head is also not indicated on plans and risers. 3. The discharge pipe from submersible pump is having high pressure loss and fluid velocity, it is recommended to resize the pipe according to the allowable pressure loss and velocity parameters. 4. Pit sizing: The level of lowest invert level incoming waste pipe is not taken into consideration when sizing the pit depth. Also, the size of duplex pumps should be given more attention in sizing the pit to verify if the current size fits for two submersible pumps. 5. The pit size is found to be insufficient with respect to the fixtures and drainage points connected to it. It is recommended to take the level of incoming waste pipes and the size of submersible pumps into consideration when sizing the pit. 6. Gray water tank is oversized. It is recommended to size the gray water tank for 1 no more than 3 days (72 Hours), as per IPC.

7. It is required to provide the gray water tank with overflow, vent with insect screen, and access panel and cat ladder for maintenance. 8. It is required to coordinate the tank trench location with structural engineering to avoid trench in tank footing. 9. It is required to separate the tank into two partitions, one for gray water collection and the other for treated water.

DVR 251011/109

P a g e | 97 / 292

e. BUILDING (WH01-04)
Underground piping, submersible pumps and pits, gray water concrete tank and related calculations have been reviewed.

I.

DESIGN PARAMETERS:

The followings table shows the design parameters used in the IFC design documents and those extracted through the design review process

Table M.64 : Design parameters Item Parking drain Fixtures Units AHU & FCU Fixtures Units Floor Drain Fixtures Units Slope of Drainage piping (100 & 150 mm Diameters) Rainfall intensity WC Flush flow rate Number of persons per m2 IFC Design Value Reference 1 2 UPC 2 UPC 2 UPC Not Indicated 32 mm/hr8 Not Indicated Not Indicated Not Indicated UPC Required Parameters Value Reference 8 UPC2 2 UPC3 2 UPC3 1% 50 mm/hr 6.1 liter (1.6 gallon/flush) 14 IPC4 UPC5 UPC6

Water consumption ratio per 5% shower Water consumption ratio per Not Plumbing Engineering 32% Indicated toilet flushing Servicing Design Water consumption ratio per Not Guide- The Institute of 20% Indicated Plumbing 20027 Laundry Water consumption ratio per Not 15% Indicated kitchen Water consumption ratio per Not 9% Indicated basin 1. IFC design indicates parking floor drain to have 2 FU. However, since pipe connection is 4 UPC calls for 8 FU to be used in calculations. 2. Refer to Appendix A, PageA.3 3. Refer to Appendix A, PageA.2 4. Refer to appendix A, Page A.11 5. Refer to Appendix A, Page A.5 6. Refer to Appendix A, Page A.1 7. Refer to Appendix A, Page A.4 8. Rainfall intensity used by the designer varies for different buildings. It is recommended to use 50 mm/hr

DVR 251011/109

P a g e | 98 / 292

II.

SUMP PITS & SUBMERSIBLE PUMPS (SP-1): 1. Submersible pump-1 (SP-1) has been reviewed as an example for others in the same building. Results of this review indicate that same issues are found in other areas within the same building 2. IFC Design plans(Drainage), IFC calculations, IFC risers, IFC structural drawings and sections have been reviewed, the following table shows the results:

Table M.65 ; SP-1 Design data as per IFC Design Drawings & Calculations Output from design review
Mechanical Drawings Plan 4th Basement Master Floor Plumbing Plan (P-101) Drawings reference Ground floor master plumbing plan (P-121) Riser Calculations Plan Structure Sections Design Review Output

Typ. Riser diagram water, sewer, waste & vent distribution system (101RP002)

Itcc-18 parcels Service offices & virtual building WH01-04 (plumbing calculations)

Foundation plan (S-106)

Sections & details ( S-301)

Foundation Type Location Encasement for Drainage Pipe Under ground 4th Basement Grids (G&14) Not shown -

1300mm Raft Foundation 4th Basement Grids (G&14) Not shown -

Not shown

Not shown

Not shown 2 Pumps 3.4 L/s each Head = 2 bar IFC pumps are accepted

Pump Data

Total Flow = 5.36 L/s Head = 2.0 Bar

Not shown

Total Flow = 5.34 L/s Head = 2.0 Bar

Pump discharge pipe size (Forced Flow) Pit Size

50 mm

100 mm

1.0 m x 1.0 m Depth is not available

N/A

1.0 x 1.0 x 1.5 m

1.54 m x 1.54 m Depth is not available

1.0 x 1.0 x 1.5 m

1.3x1.3x2.4 m3

DVR 251011/109

P a g e | 99 / 292

Table M.65 ; SP-1 Design data as per IFC Design Drawings & Calculations Output from design review
Mechanical Drawings Plan Riser Calculations Plan Structure Sections Design Review Output

Sump pit Service

Mechanical Drawings Plan Parking drains Included Riser Included

Calculations Plan Included N/A

Structure Sections N/A

Design Review Output O.K Should be included in calculations and riser Should be included Should be included

Elevator Pit

Included

Not Included Not Included Not Included

Not Included

N/A

N/A

Rain water Condensate drain

Included Included

Not Included Included

N/A N/A

N/A N/A

Red: Not Acceptable, Orange: Partially, Green: Acceptable


3.

Description of above findings: a. Pump Flow rate: i. In the same discipline there is discrepancy in the Tag numbers between risers, calculations and plans. Same mismatching found with other disciplines like structural

4. Pump Head: a. Forced drain discharge pipe has very high values for pressure drop and velocity; diameter should be increased to 100 mm. The following table shows design data calculations and analysis;

Table m.66: Design Head Calculations Pipe Head Loss Fluid Residual Safety Total pressure Friction According Velocity Pressure Factor loss to pipe size psi mm psi mm/m m/s m psi m. H2o (Bar) 20 50 3 108 2.5 2 2.9 20 (2.0) Head loss data & fluid velocity figures with respect to pipe size and flow are as per ASHRAE Fundamentals 2005 chapter 36, Pipe Sizing Refer to Appendix A, Page A.6 Static Head Pipe Size

DVR 251011/109

P a g e | 100 / 292

5. Pit Size: a. b. c. d. Modified calculations based on the above will change pit size. Duplex Pump sizes are not taken into consideration. Effective volume is not properly calculated. Pit depth is less than required (Waste pipe connected to sump pit is not taken into consideration) e. Elevator pit is not taken into consideration in sizing the pit depth. f. No sand trap is provided at waste pipe connected to sump pit. 6. Sample of calculation:Below is a sample calculation for SP-1 a. Flow Rate calculations: Consists of all waste water pouring into sump pit-1 including: i. Rain water ii. Parking drains iii. Condensate drains iv. Floor drains

The following table shows rain water calculations as per UPC, done by design reviewer (IFC Design does not contain similar calculations): Table M.67; Rain water calculations
Exposed Ramp Area (m2) 150 Ground Floor Master Plumbing Plan (P-121) Rainfall Intensity (mm/hr) 50 1. As per 18 parcel group B calculations 2. AS per ITCC project Package 1&2 Flow Rate (L/s)

Reference

2.0

The following table shows flow of connected fixtures to SP-1 Table M.68: Connected Fixtures to SP-1 Fixture Number D.F.U.V

Unit Total Parking Drain 13 8 104 AHU & FCU 8 2 16 Floor Drain 3 2 6 Total 126 Fixtures Flow Rate* 76 GPM (4.8) Reference for converting D.F.U.V to flow rate is NBS Monograph, Fig 3-3 NBS Monograph 31, Designflow curves for plumbing-drainage systems. Refer to Appendix A, Page A.15

DVR 251011/109

P a g e | 101 / 292

The following table shows total pump flow Table M.69: Pump Total Flow Rain water Flow Fixture Flow Diversity* Total Pump Flow L/s L/s L/s (gpm) 75% 2.0 (32) 4.8 (76) 5.1 (81) *: 75% diversity has been considered since it is highly unlikely for all system to work together b. Pump head calculations; The below table shows pump head calculations for SP-1 Table M.70: Pump Head Calculations Pipe Head Loss Total Fluid Residual Safety Equivalent According to pressure Velocity Pressure Factor Length pipe size m mm m mm/m m/s m m. H2o (Bar) 14 100 95 16.6 1.4 4 10% 21(2.1) Head loss data & fluid velocity figures with respect to pipe size and flow are as per ASHRAE Fundamentals 2005 chapter 36, Pipe Sizing Refer to Appendix A, Page A.6 Static Head Pipe Size c. Pump Selection The below table shows pump selection and configuration Table M.71: Pump selection Pump Type No. Total Pump Flow Each pump flow 66% of total flow Pump Head Submersible waste water pump 2 Pumps (Duplex) L/s (GPM) L/s (GPM) Bar (m H2O) 5.1 (81) 3.4 (54) 2.1 (21) 405 770 795 Lead-lag

Pump diameter* mm Pump Height* mm Pump Length* mm Configuration Reference for pump data from Grundfos Pumps; Refer to Appendix A, Page A.16 IFC pumps are accepted

DVR 251011/109

P a g e | 102 / 292

d. Pit sizing: The below table shows pit sizing calculations: Table M.72: Pit sizing Pump Flow GPM (L/s) in Gal. Gal/ft. ft. ft. 81 (5.1) 50 321 105 3.0 3.3

Basin Diameter Draw Down volume Capacity of fluid per ft. Draw Down Height Depth of lowest level incoming piping Difference between inlet pipe and high water in 6.0 level Minimum depth at the bottom of the basin ft. 1.0 Sump pit Height ft. (m) 7.8 (2.4) Min. pit size should be 1.3 x 1.3x2.4 (4.0 m3) Procedure for sizing pit is described in Handbook of Mechanical Engineering Calculations; Part 3 Environmental Control; Section 15 Plumbing and Drainage for Buildings and Other Structures. Refer to Appendix A, Pages A.8, A.9, A.10 7. Comparison: The following table shows a comparison between IFC and Design review output for SP-1

Table M.73: Comparison between IFC and Design review output Pump flow rate calculations IFC IFC is using connected fixtures units taking PD and FU as 2 IFC is not taking rain water calculations into consideration. 1.5 m Not considered in calculations and pit depth Not provided Design review output According to building flow requirement described in sample calculations ( Rain water and connected fixtures) Total Pump flow = 5.1 L/s (81 gpm) Each pump sized 66% of total flow IFC pumps are accepted Minimum depth shall not be less than 2.4 m Should be considered in calculations to find the lowest waste incoming pipe connected to SP-1 Should be provided to block sand particles from entering and accumulating inside the pit

Pit depth Elevator Pit 1 Sand Trap 2

1. Refer to Appendix A, Page A.7 2. Refer to Appendix A, Page A.13

DVR 251011/109

P a g e | 103 / 292

III.

GRAY WATER TANK:

Table M.74 ; Gray water tank data as per IFC Design Drawings & Calculations output from design review Design Plan Calculations Riser Structure review output
4th Basement Master Floor Plumbing Plan (P-101) ITCC-18 parcels Service offices & virtual building WH01-04 (Plumbing calculations) Typ. Riser diagram water, sewer, waste & vent distribution system (101R-P002) Foundation plan (S-106) Sections & details ( S-301)

Drawing Reference

Ground Floor Master Plumbing Plan (P-121)

Grey Water Tank Size Non-Potable Water Tank Size Location

31.4 m3 Shown but the tank height is not available Basement-4 Above Ground

31 m3 129 m3

N/A N/A Basement-4, Above Ground N/A

N/A

58.5 m3 58.5 m3

N/A

Shown but the tank height is not available Basement-4, Above Ground Not Provided

O.K Should be provided on structural drawings Should be provided Should be provided Should be provided Should be provided

Access Panel

Upper

N/A

Overflow Vent Drain Make up water & backflow preventer Cat ladder Level of incoming waste line

Not Provided Not Provided Not Provided

N/A N/A N/A

Not Provided Not Provided Not Provided

N/A N/A N/A

Not Provided

N/A

Not Provided

N/A

Not Provided +2000

N/A Not considered

Not Provided N/A

Not Provided N/A

Should be provided Should be taken into consideration

Red: Not Acceptable, Orange: Partially, Green: Acceptable

1. Description: a. Actual tank size is different than that in calculations and plans ( Level of incoming waste pipe is not taken into considerations) b. Tank is not provided with ladder below tank access panel. c. Tank is not provided with overflow, vent & drain. d. Tank is not provided with makeup water line. e. Tank trench is located at tank bottom footing & needs confirmation from structural engineer.

DVR 251011/109

P a g e | 104 / 292

f. Gray water tank sizing: the following table shows gray water tank effective volume as per drainage plans and structural drawings: Table M.75; Gray Water Tank Effective Volume Tank Volume as Per IFC design calculations m3 Given tank area m2 Tank height m Depth of lowest level incoming piping m Difference between inlet pipe and high water level m Effective height m Effective volume m3 Effective volume is 20.25 m3 as per IFC and this is below required as per calculations (31 m3) 2. Sample Calculations The below is a sample calculations for sizing of gray water system Table M.76 : Gray Water Tank Size Verification Building Floor Area m2 m2 Persons 31 13.5 2.35 1.65 0.15 1.5 20.25

Total Area: Per person Area requirement--> (as per IPC code) Total no. of users (persons) ----------> OPTION-1 Assuming each person will use the WC a day Quantity of flushed water per flushing Water requirement per day for flushing No. of persons x no. of flushes x 6.1 liters OPTION-2 As per IPC Code Daily water demand for Office application Water requirement = persons x water demand ----->

37,848.00 14 2,703

2.00 times 6.10 Liters 32,982 32.98 liters m3

45.00 121,654

liters/person liters

As per IPC Code, Water consumption ratio for appliances is as follows: Shower & Bath Toilet flushing Laundry Kitchen Basin So, Flushing water requirement ---> 38,929 38.93 Gray Water System (Collection tank plus treated tank) Capacity as per calculations ---->

5% 32% 20% 15% 9% liters m3

39X3 Days= 117 m3

DVR 251011/109

P a g e | 105 / 292

Table M.76 : Gray Water Tank Size Verification Gray water tank capacity = 58.5 m3 Non-Potable water tank capacity = 58.5 m3 Gray Water Tank Capacity as per IFC ----> 31.00 m3

Comparison of IFC Capacities with Calculated Capacities


Tank Capacity (M3) as per Calculation

Daily Requirement (m3) 38.9

No. of Days Holding 0.80

3. Comparison: The below table shows a comparison between IFC and Design review output

Table m.77: Gray Water Tank Comparison IFC Design review output As per structural drawings, effective tank size is 20.25m3 Correct system size is 117 m3 divided by two tanks 58.5 m3 each Pipe level is 1650 mm measured from tank bottom level Should be taken into consideration and deducted from tank total height

Tank size

AS per IFC PG plans and calculations, tank size is 31m3

Level of incoming waste pipe

Not taken into consideration

DVR 251011/109

P a g e | 106 / 292

IV.

RECOMMENDATIONS:

Further to the design review study and analysis, and as per the above sample calculation for sump pits and gray water tanks for WH-01-04 building, we conclude the following: 1. There is no reference to any calculations indicating the submersible pump head, the head is also not indicated on plans and risers. 2. The discharge pipe from submersible pump is having high pressure loss and fluid velocity, it is recommended to resize the pipe according to the allowable pressure loss and velocity parameters. 3. Pit sizing: The level of lowest invert level incoming waste pipe is not taken into consideration when sizing the pit depth. Also, the size of duplex pumps should be given more attention in sizing the pit to verify if the current size fits for two submersible pumps. 4. The pit size is found to be insufficient with respect to the fixtures and drainage points connected to it. It is recommended to take the level of incoming waste pipes and the size of submersible pumps into consideration when sizing the pit.

5. It is required to provide gray water tank with makeup water line with backflow preventer to avoid pump dry run. 6. It is required to provide the gray water tank with overflow, vent with insect screen, and access panel and cat ladder for maintenance. 7. It is required to take the level of lowest invert level incoming waste pipe into consideration when sizing the gray water tank. 8. Sump pit located beside non-potable water tank does not contain submersible pump and there is no reference in calculation for the mentioned pit.

DVR 251011/109

P a g e | 107 / 292

f. BUILDING(WH-05)
Underground piping, submersible pumps and pits, gray water concrete tank and related calculations have been reviewed.

I.

DESIGN PARAMETERS:

The followings table shows the design parameters used in the IFC design documents and those extracted through the design review process Table M.78 : Design parameters Item Parking drain Fixtures Units AHU & FCU Fixtures Units Floor Drain Fixtures Units Slope of Drainage piping (100 & 150 mm Diameters) Rainfall intensity WC Flush flow rate Number of persons per m2 IFC Design Value Reference 21 UPC 2 UPC 2 UPC Not Indicated Not Indicated Not Indicated Not Indicated Not Indicated UPC Required Parameters Reference UPC2 UPC3 UPC3 IPC4 UPC5 UPC6

Value 8 2 2 1% 50 mm/hr

6.1 liter (1.6 gallon/flush) 14

Water consumption ratio per 5% shower Water consumption ratio per Not Plumbing Engineering 32% Indicated toilet flushing Servicing Design Water consumption ratio per Not Guide- The Institute of 20% Indicated Plumbing 20027 Laundry Water consumption ratio per Not 15% Indicated kitchen Water consumption ratio per Not 9% Indicated basin 1. IFC design indicates parking floor drain to have 2 FU. However, since pipe connection is 4 UPC calls for 8 FU to be used in calculations. 2. Refer to Appendix A, PageA.3 3. Refer to Appendix A, PageA.2 4. Refer to appendix A, Page A.11 5. Refer to Appendix A, Page A.5 6. Refer to Appendix A, Page A.1 7. Refer to Appendix A, Page A.4 8. Rainfall intensity used by the designer varies for different buildings. It is recommended to use 50 mm/hr

DVR 251011/109

P a g e | 108 / 292

II.

SUMP PITS & SUBMERSIBLE PUMPS (SP-1): 1. Submersible pump-1 (SP-1) has been reviewed as an example for others in the same building. Results of this review indicate that same issues are found in other areas within the same building 2. IFC Design plans(Drainage), IFC calculations, IFC risers, IFC structural drawings and sections have been reviewed, the following table shows the results:

Table M.79 ; SP-1 Design data as per IFC Design Drawings & Calculations Output from design review
Mechanical Drawings Plan 4th Basement Floor Plumbing Plan (P-101) Drawings reference Ground Floor Plumbing Plan (P-104) Riser Calculations Structure Plan Sections Design Review Output

Typ. Riser Diagram Water, Sewer, Waste & Vent Distribution System (101R-P002)

WHITE (WH-05) (Plumbing Design Calculations)

Foundation Plan (S-102)

Sections & Details ( S-302)

Foundation Type Location Encasement for Drainage Pipe Under ground 4th Basement Grids (D & 6) N/A

900mm Raft Foundation 4th Basement Grids (D & 6) Not shown

N/A

N/A

Not shown

N/A

N/A

Not shown

Pump Data

Total Flow = 4.73 L/s Head = 2.1 Bar

Total Flow = 4.73 L/s Head = 2.1 Bar

Total Flow = 4.73 L/s Head = 2.1 Bar

N/A

N/A

Should be shown 2 pumps flow 3.3 L/s Each Head 2 bar IFC pumps are accepted

Pump discharge pipe size (Forced Flow) Pit Size

75 mm

100 mm

0.8 m x 0.8 m Depth is not available

N/A

1.0 x 1.0 x 1.0 m

0.8 m x 0.8 m Depth is not available

1.2 x 1.2 x 1.5 m3

1.3x1.3x2.5 m3

DVR 251011/109

P a g e | 109 / 292

Table M.79 ; SP-1 Design data as per IFC Design Drawings & Calculations Output from design review
Mechanical Drawings Plan Riser Calculations Structure Plan Sections Design Review Output

Sump Pit Service

Mechanical Drawings Plan Parking drains Elevator Pit Rain water Condensate drain Gray Water Over Flow Included Included Included Included Not Included Riser Included Included Not Included Not Included Not Included

Calculations Plan Included Not Included Not Included Not Included Not Included N/A N/A N/A N/A N/A

Structure Sections N/A N/A N/A N/A N/A

Design Review Output O.K. Should be included Should be included Should be included Should be included

Calculation was performed based on sump pit connected fixtures. Red: Not Acceptable, Orange: Partially, Green: Acceptable

3. Description: a. Pump Flow rate i. In the same discipline there is discrepancy in the Tag numbers miss matching with riser, calculation, and plans, and same mismatching with other disciplines like structural. ii. Pump flow rate is based on incorrect design parameters where only rain water flow is considered while connected fixtures to sump pit are not considered. 4. Pump Head:

Table m.80: Design Head Calculations Head Loss Static Pipe Fluid Residual Total pressure Accordin Safety Factor Head Size Velocity Pressure g to pipe size psi mm psi mm/m m/s m psi m. H2o (Bar) 16.5 75 2 13.02 0.9906 2.9 20 (2.1) Head loss data & fluid velocity figures with respect to pipe size and flow are as per ASHRAE Fundamentals 2005 chapter 36, Pipe Sizing Refer to Appendix A, Page A.6 Pipe Frictio n loss

DVR 251011/109

P a g e | 110 / 292

The following table shows design data calculations and analysis; 5. Pit Size: a. Modified calculations based on the above will change pit size. b. Duplex Pump sizes are not taken into consideration. c. Effective volume is not properly calculated. d. Pit depth is less than required (Waste pipe connected to sump pit is not taken into consideration) e. Elevator pit is not taken into consideration in sizing the pit depth. f. No sand trap is provided at waste pipe connected to sump pit. g. Pit location: Pit is located inside shaft and there is no access. 6. Sample of calculation:Below is a sample calculation for SP-1 a. Flow Rate calculations: Consists of all waste water pouring into sump pit-1 including: i. Rain water ii. Parking drains iii. Condensate drains iv. Floor drains

The following table shows rain water calculations as per UPC

Table M.81: Rain water calculations


Exposed Ramp Area (m2) 150 Ground Floor Master Plumbing Plan (P-121) Rainfall Intensity (mm/hr) 50 As per 18 parcel group B calculations As per ITCC project Package 1&2 1. Flow Rate (L/s) 2.0

Reference

2.

The following table shows flow of connected fixtures to SP-1 Table M.82: Connected Fixtures to SP-1 Fixture Number D.F.U.V

Unit Total Parking Drain 10 8 80 AHU & FCU 19 2 38 Floor Drain 0 Total DFU 118 Fixtures Flow Rate 74 GPM (4.6) Reference for converting D.F.U.V to flow rate is NBS Monograph, Fig 3-3 NBS Monograph 31, Design-flow curves for plumbing-drainage systems. Refer to Appendix A, Page A.15

DVR 251011/109

P a g e | 111 / 292

The following table shows total pump flow Table M.83: Pump Total Flow Rain water Flow L/s 2.0 Fixture Flow L/s 4.6 Diversity 75 % Total Pump Flow L/s (gpm) 4.95 (78.5)

b. Pump head calculations; The below table shows pump head calculations for SP-1 Table M.84: Pump Head Calculations Static Head m Pipe Size mm Pipe Equivalent Length m Head Loss According to pipe size mm/m Fluid Velocity m/s Residual Pressure m Safety Factor Total pressure

m. H2o (Bar) 14 100 63.75 11.93 1.13 4 10% 21 (2.1) Head loss data & fluid velocity figures with respect to pipe size and flow are as per ASHRAE Fundamentals 2005 chapter 36, Pipe Sizing Refer to Appendix A, Page A.6 c. Pump Selection: The below table shows pump selection and configuration

Table M.85: Pump selection Pump Type No. Total Pump Flow Each pump flow 66% of total flow Pump Head Submersible waste water pump 2 Pumps (Duplex) L/s (GPM) L/s (GPM) Bar (m H2O) 4.95 (78.5) 3.3 (52.5) 2.1 (21)

Pump diameter* mm 405 Pump Height* mm 770 Pump Length* mm 795 Configuration Lead-lag *: Reference for pump data from Grundfos Pumps; Refer to Appendix A, Page A.16

DVR 251011/109

P a g e | 112 / 292

d. Pit sizing: The below table shows pit sizing calculations: Table M.86: Pit sizing Pump Flow GPM (L/s) in Gal. Gal/ft. ft. ft. in ft. ft. (m) 78.5 (4.95) 50 311 105 3.0 3.8 6.0 1.0 8.3 (2.5)

Basin Diameter Draw Down volume Capacity of fluid per ft. Draw Down Height Depth of lowest level incoming piping Difference between inlet pipe and high water level Minimum depth at the bottom of the basin Sump pit Height Min. pit size should be 1.3 x 1.3 x 2.5 (4.25 m3) Procedure for sizing pit is described in Handbook of Mechanical Engineering Calculations; Part 3 Environmental Control; Section 15 Plumbing and Drainage for Buildings and Other Structures. Refer to Appendix A, Pages A.8, A.9, A.10

7. Comparison: The following table shows a comparison between IFC and Design review output

Table M.87: Comparison between IFC and Design review output IFC Pump flow rate calculations IFC is using connected fixtures units taking PD and FU as 2 IFC is not taking rain water calculations into consideration. 1.0 m Not considered Not provided Design review output According to building flow requirement described in sample calculations ( Rain water and connected fixtures) Total Pump flow =4.95 L/s (78.5 gpm) Each pump is sized based on 66% of total flow IFC pumps are accepted Minimum depth shall not be less than 2.5 m Should be considered in calculations to find the lowest waste incoming pipe connected to SP-1 Should be provided to block sand particles from entering and accumulating inside the pit

Pit depth Elevator Pit 1 Sand Trap 2

1. Refer to Appendix A, Page A.7 2. Refer to Appendix A, Page A.13

DVR 251011/109

P a g e | 113 / 292

III.

GRAY WATER TANK:

Table M.88: Gray water tank design data as per mechanical, structural IFC drawings and calculations Plan
4th Basement Floor Plumbing Plan (P-101) Ground Floor Plumbing Plan P-104

Calculations
White (WH-05) (Plumbing Design Calculations)

Riser
Typ. Riser Diagram Water, Sewer, Waste & Vent Distribution System 101R-P002 Not Provided

Structure

Design review output

Drawing Reference

Sections

& Details ( S-302)

Grey Water Tank Size Non-Potable Water Tank Size Location Access Panel Overflow Vent Drain Make up water & backflow preventer Cat ladder Level of incoming waste line

Not Provided

13 m3 30 m3

Not Provided

12.1 m3 12.1 m3

Shown, but tank height is not indicated Basement-4, Above Ground Side Not Provided Not Provided Not Provided Provided Without BFP Not Provided +2550

N/A Basement-4, Above Ground N/A Not Provided Not Provided Not Provided Not Provided Not Provided N/A

N/A N/A N/A N/A N/A N/A N/A Not considered

Shown, but tank height is not indicated Basement-4, Above Ground Not Provided N/A N/A N/A N/A Not Provided N/A

Matching Should be provided Should be provided Should be provided Should be provided Should be provided Should be provided Should be taken into consideration

1.

Description: a. Actual tank size is different than that in calculations and plans ( Level of incoming waste pipe is not taken into considerations) b. Tank is not provided with ladder below tank access panel. c. Tank is not provided with overflow, vent & drain. d. Tank is not provided with makeup water line. e. The following table shows gray water tank effective volume as per drainage plans and structural drawings: f. Effective volume is 38.4 m3 as per IFC and this not matching as per required by calculations (13m3)

DVR 251011/109

P a g e | 114 / 292

Table M.89 Gray Water Tank Effective Volume Tank Volume as Per IFC design calculations Given tank area Tank height Depth of lowest level incoming piping Difference between inlet pipe and high water level Effective height Effective volume m3 m2 m m m m m3 13 16 3.5 2.55 0.15 2.4 38.4

2.

Sample calculations: The below is a sample calculations for sizing of gray water systems

Table M.90 : Gray Water Tank Size Verification 7,866.00 14 562 Building Floor Area m2 m2 Persons

Per person Area requirement--> (as per IPC code) Total no. of users (persons) ----------> OPTION-1 Assuming each person will use the WC a day Quantity of flushed water per flushing Water requirement per day for flushing No. of persons x no. of flushes x 6.1 liters OPTION-2 As per IPC Code Daily water demand for Office application Water requirement = persons x water demand ----->

2.00 times 6.10 Liters 6,855 6.85 liters m3

45.00 25,284

liters/person liters

As per IPC Code, Water consumption ratio for appliances is as follows: Shower & Bath Toilet flushing Laundry Kitchen Basin So, Flushing water requirement ---> Gray Water System (Collection tank plus treated tank) Capacity as per calculations ----> Gray water tank capacity = 12.1 m3 Non-Potable water tank capacity = 12.1 m3 Gray Water Tank Capacity as per IFC ---->

5% 32% 20% 15% 9%

8,091 liters 8.09 m3 8.09X3 Days= 24.27 m3

13

m3

DVR 251011/109

P a g e | 115 / 292

Table M.90 : Gray Water Tank Size Verification

Comparison of IFC Capacities with Calculated Capacities


Tank Capacity (M3) as per Calculation

Daily Requirement (m3) 8.1

No. of Days Holding 1.61

3.

Comparison: The below table shows a comparison between IFC and Design review output

Table M.91: Non Potable Water Tank Comparison IFC AS per IFC PG plans and calculations, tank size is 13m3

Design review output As per structural drawings, effective tank size is 38.4m3 Correct system size is 24.27 m3 divided by two tanks 12.1 m3 each

Tank size

Level of incoming waste pipe Not taken into consideration

Pipe level is 2250 mm measured from tank bottom level Should be taken into consideration and deducted from tank total height Location should be coordinated with structural gray water tank footing.

Trench location ( serving gray water)

Located above gray water tank footing

DVR 251011/109

P a g e | 116 / 292

IV.

RECOMMENDATIONS:

Further to the design review study and analysis, and as per the above sample calculation for sump pits and gray water tanks for WH05 building, the following can be concluded: 1. The discharge pipe from submersible pump is having high pressure loss and fluid velocity, it is recommended to resize the pipe according to the allowable pressure loss and velocity parameters. 2. Pit sizing: The level of lowest invert level incoming waste pipe is not taken into consideration when sizing the pit depth. Also, the size of duplex pumps should be given more attention in sizing the pit to verify if the current size fits for two submersible pumps. 3. Sump pit is located inside shaft without access, it is required to provide an access for pump setup and maintenance 4. The pit size is found to be insufficient with respect to the fixtures and drainage points connected to it. It is recommended to take the level of incoming waste pipes and the size of submersible pumps into consideration when sizing the pit. 5. It is required to provide gray water tank with makeup water line with backflow preventer to avoid pump dry run. 6. It is required to provide the gray water tank with overflow, vent with insect screen, and access panel and cat ladder for maintenance. 7. It is required to coordinate the tank trench location with structural engineering to avoid trench in tank footing.

DVR 251011/109

P a g e | 117 / 292

g. BUILDING(WH-06)
Underground piping, submersible pumps and pits, gray water concrete tank and related calculations have been reviewed. I. DESIGN PARAMETERS: The followings table shows the design parameters used in the IFC design documents and those extracted through the design review process
Table M.92 : Design parameters

Item Parking drain Fixtures Units AHU & FCU Fixtures Units Water Closet (Flush valve type Staff/Public use) DFU Floor Drain Fixtures Units Lavatory (Staff/Public use) DFU Commercial Kitchen Sink Slope of Drainage piping (100 & 150 mm Diameters) Rainfall intensity WC Flush flow rate

IFC Design Value Reference 21 UPC 2 UPC UPC Not Indicated Not Indicated Not Indicated Not Indicated Not Indicated 32 mm/hr8 Not Indicated UPC UPC UPC UPC -

Required Parameters Value Reference 8 UPC2 2 UPC3 6 UPC3 2 2 3 1% 50 mm/hr 6.1 liter (1.6 gallon/flush) 14 UPC3 UPC3 UPC3 IPC4 UPC5 UPC6

Number of persons per m2 Not Indicated Water consumption ratio per Not Indicated 5% shower Water consumption ratio per Not Indicated 32% Plumbing Engineering toilet flushing Servicing Design Water consumption ratio per Not Indicated Guide- The Institute of 20% Laundry Plumbing 20027 Water consumption ratio per Not Indicated 15% kitchen Water consumption ratio per Not Indicated 9% basin 1. IFC design indicates parking floor drain to have 2 FU. However, since pipe connection is 4 UPC calls for 8 FU to be used in calculations. 2. Refer to Appendix A, PageA.3 3. Refer to Appendix A, PageA.2 4. Refer to appendix A, Page A.11 5. Refer to Appendix A, Page A.5 6. Refer to Appendix A, Page A.1 7. Refer to Appendix A, Page A.4, 8. Rainfall intensity used by the designer varies for different buildings. It is recommended to use 50 mm/hr

DVR 251011/109

P a g e | 118 / 292

II. SUMP PITS & SUBMERSIBLE PUMPS (SP-1): 1. Submersible pump-1 (SP-1) has been reviewed as an example for others in the same building. Results of this review indicate that same issues are found in other areas within the same building IFC Design plans(Drainage), IFC calculations, IFC risers, IFC structural drawings and sections have been reviewed, the following table shows the results:

2.

Table M.93 ; SP-1 Design data as per IFC Design Drawings & Calculations Output from design review Mechanical Drawings Plan Riser Basement Floor Sewer, Waste & Plumbing Vent Plan Distribution (P-101) System (P-307) Calculations Plan ITCC-18 Parcels Restaurant Building WH-06 (Plumbing Calculations) Structure Sections Design Review Output

Drawings reference

Foundations (S-102)

Sections & Details ( S-303)

Foundation Type 1st Basement Grids (A & 8)

700mm Thickness Raft Foundation 1st Basement Grids (A & 8)

Location

N/A

N/A

Encasemen t for Drainage Pipe Under ground

Not shown

N/A

N/A

Not shown

Not shown

Pump Data

Flow = 5.16 L/s Head = 1.5 Bar

Flow = 5.16 L/s Head = 2.1 Bar

Tag. numbers not matching with plan and riser

N/A

N/A

2 pumps 2.5 L/s each Head = 1.1 Bar IFC Pumps are accepted

Pump discharge pipe size (Forced Flow) Pit Size

100 mm

100 mm

0.9 m x 0.9 m Depth is not available

N/A

1.0 x 1.0 x 1.0 m

0.9 m x 0.9 m Depth is not available

1.3 x 1.3 x 1.2 m3

1.3 x 1.3x1.85 m3

Sump pit Service

Mechanical Drawings Plan Riser Wet areas at basement 1

Calculations Plan

Structure Sections Calculations are not taking all connected fixtures into consideration

Included

Included

Not All Included

N/A

N/A

DVR 251011/109

P a g e | 119 / 292

Table M.93 ; SP-1 Design data as per IFC Design Drawings & Calculations Output from design review Mechanical Drawings Plan Riser Condensate drain Not Included Not Included Calculations Plan Not Included N/A Structure Sections N/A Design Review Output Should be included

Calculation was performed based on connected fixtures to sump pit Red: Not Acceptable, Orange: Partially, Green: Acceptable 3.

Description of above findings: a. Pump Flow rate: iii. In the same discipline there is discrepancy in the Tag numbers miss matching with riser, calculation, and plans, and same mismatching with other disciplines like structural. iv. Kitchen sinks are not taken into consideration in flow calculations Pump Head:

4.

The following table shows design data calculations and analysis;

Table M.94: Design Head Calculations Residu Pipe Fluid al Safety Total pressure Static Head Size Velocity Pressu Factor re psi mm psi mm/m m/s m psi m. H2o (Bar) 7.5 100 7.5 7.2 0.673 3 15 (1.5) *: Head loss data & fluid velocity figures with respect to pipe size and flow are as per ASHRAE Fundamentals 2005 chapter 36, Pipe Sizing Refer to Appendix A, Page A.6 Pipe Friction loss Head Loss According to pipe size Based on new flow rate as per design review output, the above data are subject to change. 5. Pit Size: a. Modified calculations based on the above will change pit size. b. Duplex Pump sizes are not taken into consideration. c. Effective volume is not properly calculated. d. Pit depth is less than required (Waste pipe connected to sump pit is not taken into consideration) e. Elevator pit is not taken into consideration in sizing the pit depth. f. No sand trap is provided at waste pipe connected to sump pit.

6.

Grease Trap: a. No calculations in IFC for grease trap capacity and grease retention time b. Grease trap size is not identified in IFC.

DVR 251011/109

P a g e | 120 / 292

c. Grease trap is located at corridor and close to food preparation areas. This will affect the smell of the area especially during maintenance. d. Location of grease trap is not coordinated with building structure. 7. Sample of calculation:Below is a sample calculation for SP-1

a. Flow Rate calculations: Consists of all waste water connected to sump pit-1 including: i. Condensate drains ii. Floor drains from wet areas located at 1st basement. iii. The following table shows flow of connected fixtures to SP-1 Table M.95: Connected Fixtures to SP-1 Fixture WC LAVATORY SHOWER AHU & FCU FLOOR DRAIN COMMERCIAL SINK Total FU Fixtures Flow rate Number 3 4 3 5 24 22 Unit 6 2 2 2 2 3 D.F.U.V

Total 18 8 6 10 48 66 156 80 GPM (5.0 L/s) 75 %: Since it is highly unlikely that all systems shall operate Diversity together Total Flow Rate 60 GPM (3.75 L/s) Reference for converting D.F.U.V to flow rate is NBS Monograph, Fig 3-3 NBS Monograph 31, Design-flow curves for plumbing-drainage systems. Refer to Appendix A, Page A.15

DVR 251011/109

P a g e | 121 / 292

b. Pump head calculations; The below table shows pump head calculations for SP-1 Table M.96: Pump Head Calculations Static Head m 5 Pipe Head Loss Fluid Residual Safety Total pressure Equivalent According to Velocity Pressure Factor Length pipe size mm m mm/m m/s m m. H2o (Bar) 75 13 22 132 4 10% 11 (1.1) *: Head loss data & fluid velocity figures with respect to pipe size and flow are as per ASHRAE Fundamentals 2005 chapter 36, Pipe Sizing Refer to Appendix A, Page A.6 c. Pump Selection; The below table shows pump selection and configuration Pipe Size

Table M.97: Pump selection Pump Type No. Total Pump Flow Each pump flow (66% of total flow) Pump Head Submersible waste water pump 2 Pumps (Duplex) L/s (GPM) L/s (GPM) Bar (m H2O) 3.75 (60) 2.5 (40) 1.1 (11) 405 770 795 Lead-lag

Pump diameter* mm Pump Height* mm Pump Length* mm Configuration Reference for pump data from Grundfos Pumps; Refer to Appendix A, Page A.16 d. Pit sizing: The below table shows pit sizing calculations: Table M.98: Pit sizing Pump Flow GPM (L/s) in Gal. Gal/ft. ft. ft. in ft. ft. (m)

Basin Diameter Draw Down volume Capacity of fluid per ft. Draw Down Height Depth of lowest level incoming piping Difference between inlet pipe and high water level Minimum depth at the bottom of the basin Sump pit Height Min. pit size should be 1.3 x 1.3 x 1.85 (3.2 m3) Procedure for sizing pit is described in Handbook of Mechanical Engineering Calculations; Part 3 Environmental Control; Section 15 Plumbing and Drainage for Buildings and Other Structures. Refer to Appendix A, Pages A.8, A.9, A.10

60 (3.75) 50 238 105 2.3 2.5 6.0 1.0 6 (1.85)

DVR 251011/109

P a g e | 122 / 292

8.

Comparison:

The following table shows a comparison between IFC and design review output Table M.99 : Comparison between IFC and design review output IFC IFC calculations are based on incorrect design parameters 1.0 m Not considered Not provided DESIGN REVIEW OUTPUT According to building flow requirement described in sample calculations ( Rain water and connected fixtures) Total Pump flow = 3.75 L/s (60 gpm) 2 pumps, each pump 66% of total flow Minimum depth shall not be less than 1.85 m Should be considered in calculations to find the lowest waste incoming pipe connected to SP-1 Should be provided to block sand particles from entering and accumulating inside the pit

Pump flow rate calculations

Pit depth Elevator Pit 1 Sand Trap 2

1. Refer to Appendix A, Page A.7 2. Refer to Appendix A, Page A.13 III. Gray Water Tank:

Table M.100 ; Gray water tank data as per IFC Design Drawings & Calculations output from design review Plan
Basement Floor Plumbing Plan (P-101)

Calculations
Itcc-18 Parcels Restaurant Building WH_06 Plumbing Calculation

Riser
Sewer, Waste & Vent Distribution System P-307

Structure
Sections

Design review output

Drawing Reference Grey Water Tank Size NonPotable Water Tank Size Location Access Panel Overflow Vent Drain

& Details ( S-303)

Not Provided

10 m3

Not Provided

Not Provided Shown but the height is not indicated Basement-1, Above Ground Not Provided N/A N/A N/A

4.35 m3

Not Provided Basement-1 Above Ground Above Not Provided Not Provided Not Provided

30 m3

N/A

4.35 m3

N/A N/A N/A N/A N/A

Basement-1 Above Ground N/A Not Provided Not Provided Not Provided

Matching Should be provided Should be provided Should be provided Should be provided

DVR 251011/109

P a g e | 123 / 292

Table M.100 ; Gray water tank data as per IFC Design Drawings & Calculations output from design review Plan Make up water & backflow preventer Cat ladder Level of incoming waste line Provided Without BFP Not Provided N/A Calculations Riser Structure Design review output Should be provided Should be provided Should be taken into consideration

N/A

Not Provided

N/A

N/A Not considered

N/A N/A

Not Provided N/A

1.

Description: a. There are no waste pipes connected to gray water tank, all above grade waste pipes are directed outside building and connected to sewage network. b. Gray water tank is over sized in IFC calculations c. Actual effective tank size is different than that in calculations and plans d. Tank is not provided with ladder below tank access panel.

2.

Sample Calculations: The below is a sample calculations for sizing of gray water systems

Table M.101 : Gray Water Tank Size Verification Total Area: Per person Area requirement--> (as per IPC code) Total no. of users (persons) ----------> OPTION-1 Assuming each person will use the WC a day Quantity of flushed water per flushing Water requirement per day for flushing No. of persons x no. of flushes x 6.1 liters OPTION-2 As per IPC Code Daily water demand for Office application Water requirement = persons x water demand -----> 2,817.00 14 201 Building Floor Area m2 m2 Persons

2.00 times 6.10 Liters 2,455 2.45 liters m3

45.00 9,055

liters/person liters

As per IPC Code, Water consumption ratio for appliances is as follows: Shower & Bath Toilet flushing Laundry Kitchen

5% 32% 20% 15%

DVR 251011/109

P a g e | 124 / 292

Table M.101 : Gray Water Tank Size Verification Basin So, Flushing water requirement --->

2,897 2.90

9% liters m3

Gray Water System (Collection tank plus treated tank) Capacity as per calculations ----> Gray water tank capacity = 4.35 m3 Non-Potable water tank capacity = 4.35 m3 Gray Water Tank Capacity as per IFC ---->

2.9X3 Days 8.7 m3

10

m3

Comparison of IFC Capacities with Calculated Capacities


Tank Capacity (M3) as per Calculation

Daily Requirement (m3) 2.9

No. of Days Holding 3.45

3.

comparison: The below table shows a comparison between IFC and design review output

Table M.102: Non Potable Water Tank Comparison IFC Tank size AS per IFC PG plans and calculations, tank size is 10m3 Design review output Tank is not provided with waste line Correct system capacity is 8.7 m3 divided by 2 tanks 4.35 m3 each

DVR 251011/109

P a g e | 125 / 292

IV. RECOMMENDATIONS: Further to the design review study and analysis, and as per the above sample calculation for sump pits and gray water tanks for WH06 building, we conclude the following: 1. Pit sizing: The level of lowest invert level incoming waste pipe is not taken into consideration when sizing the pit depth. Also, the size of duplex pumps should be given more attention in sizing the pit to verify if the current size fits for two submersible pumps. 2. The pit size is found to be insufficient with respect to the fixtures and drainage points connected to it. It is recommended to take the level of incoming waste pipes and the size of submersible pumps into consideration when sizing the pit. 3. No calculations in IFC for grease trap capacity and grease retention time. It is recommended to calculate and select grease trap based on commercial kitchen sinks flow 4. Grease trap is located at corridor and close food preparation areas. This will affect the smell of the area especially during maintenance. Relocate grease trap away from populated areas or within an enclosed room

5. Location of grease trap is not coordinated with building structure. It is recommended to coordinate the location and size of grease trap with structural engineer 6. There is no waste pipe connected to gray water tank, all waste stacks above ground are connected to sewage network and directed outside building. 7. Gray water tank is oversized. It is recommended to size the gray water tank for no more than 3 days (72 Hours), as per IPC. 8. It is required to provide gray water tank with makeup water line with backflow preventer to avoid pump dry run. 9. It is required to provide the gray water tank with overflow, vent with insect screen, and access panel and cat ladder for maintenance.

DVR 251011/109

P a g e | 126 / 292

h. BUILDING ( IT 01)
Underground piping, submersible pumps and pits, gray water concrete tank and related calculations have been reviewed. I. DESIGN PARAMETERS: The followings table shows the design parameters used in the IFC design documents and those extracted through the design review process

Table M.103: Design parameters Item Parking drain Fixtures Units AHU & FCU Fixtures Units Floor Drain Fixtures Units Slope of Drainage piping (100 & 150 mm Diameters) Rainfall intensity WC Flush flow rate Number of persons per m2 IFC Design Value Reference 1 2 UPC 2 UPC 2 UPC Not Indicated 758 mm/hr Not Indicated Not Indicated Not Indicated UPC Required Parameters Reference UPC2 UPC3 UPC3 IPC4 UPC5 UPC6

Value 8 2 2 1%

50 mm/hr 6.1 liter (1.6 gallon/flush) 14

Water consumption ratio per 5% shower Water consumption ratio per Not Plumbing Engineering 32% Indicated toilet flushing Servicing Design Water consumption ratio per Not Guide- The Institute of 20% Indicated Plumbing 20027 Laundry Water consumption ratio per Not 15% Indicated kitchen Water consumption ratio per Not 9% Indicated basin 1. IFC design indicates parking floor drain to have 2 FU. However, since pipe connection is 4 UPC calls for 8 FU to be used in calculations. 2. Refer to Appendix A, PageA.3 3. Refer to Appendix A, PageA.2 4. Refer to appendix A, Page A.11 5. Refer to Appendix A, Page A.5 6. Refer to Appendix A, Page A.1 7. Refer to Appendix A, Page A.4 8. Rainfall intensity used by the designer varies for different buildings. It is recommended to use 50 mm/hr

DVR 251011/109

P a g e | 127 / 292

II. SUMP PITS & SUBMERSIBLE PUMPS (SP-1): 1. Submersible pump-1 (SP-1) has been reviewed as an example for others in the same building. Results of this review indicate that same issues are found in other areas within the same building 2. IFC Design plans(Drainage), IFC calculations, IFC risers, IFC structural drawings and sections have been reviewed, the following table shows the results: Table M.104 ; SP-1 Design data as per IFC Design Drawings & Calculations Output from design review
IFC Mechanical Drawings Plan 3rd Basement Master Floor Plumbing Plan (P-101) Drawings reference Ground Floor Master Plumbing Plan (P-121) Riser IFC Calculations IFC Structure Plan Sections Design Review Output

Typ. Riser Diagram Water, Sewer, Waste & Vent Distribution System (P118)

It 01 Calcs -3 (Plumbing Design Calculations)

3rd Basement Foundation Master Plan (S-101)

Foundation & Schedule & Details ( S-201)

N/A

Foundation Type Location 3RD Basement Grids (G&14) -

Column Base (Footings) 3RD Basement Grids (G&14)

Shown and miss matches with structural plan, height size was referred to PG (in which not found)

N/A

Encasement for Drainage Pipe Under ground

Not shown

Shown without sizing

Should be indicated on Plumbing drawings

Pump Data

Flow = 15.77 L/s Head = 1.5 Bar

Flow = 15.77 L/s Head = 1.5 Bar

Tag. Numbers not matching with plan and riser (assuming SP1 in plan = typ. to 2 & 3)

2 pumps 7.1 L/s each Head 2 bar IFC pumps are accepted

Pump discharge pipe size (Forced Flow) Pit Size

100 mm

100 mm
1.55 x 1.55 x 1.5 m 1.25 m x 1.25 m Depth is not The pit shown in the

1.25 m x 1.25 m

N/A

1.8x1.8x2.65

DVR 251011/109

P a g e | 128 / 292

Table M.104 ; SP-1 Design data as per IFC Design Drawings & Calculations Output from design review
IFC Mechanical Drawings Plan Depth is not available Riser IFC Calculations IFC Structure Plan available Sections structural is general to be taken actual size from PG drawings Design Review Output

m3

Sump pit Service Mechanical Drawings Plan Riser Parking drains Included Included Calculations Plan Not Included N/A Structure Sections N/A Should be indicated on riser diagram Should be indicated on plans & riser diagram Should be indicated Should be indicated on riser diagram & calculations Should be indicated on riser diagram

Elevator Pit

Not Included Included

Not Included

Not Included

N/A

N/A

Rain water Condensate drain

Included

Not Included

N/A

N/A

Included

Not Included

Not Included

N/A

N/A

Gray Water Over Flow

Included

Included

Not Included

N/A

N/A

Calculation was performed based on fire fighting demand Red: Not Acceptable, Orange: Partially, Green: Acceptable

3. Description: a. Pump Flow rate: i. In the same discipline there is discrepancy in the Tag numbers miss matching with riser, calculation, and plan, and same mismatching with other disciplines like structural. ii. IFC calculations are based on fire fighting demand as 500 gpm divided by 2 pits (250 gpm each), this demand is over estimated

DVR 251011/109

P a g e | 129 / 292

4. Pump Head: The following table shows IFC design data calculations and analysis; Table M.105: Design Head Calculations Residu al Safety Total pressure Pressu Factor re mm psi mm/m m/s m psi m. H2o (Bar) 100 6 31* 1.9* 5 15 (1.5) *: Head loss data & fluid velocity figures with respect to pipe size and flow are as per ASHRAE Fundamentals 2005 chapter 36, Pipe Sizing Refer to Appendix A, Page A.6 Pipe Friction loss Head Loss According to pipe size Fluid Velocity 5. Pit Size: a. Modified calculations based on the above will change pit size b. Duplex Pump sizes are not taken into consideration c. Effective volume is not properly calculated d. Pit depth is less than required (elevator pits are not taken into consideration). 6. Sample of calculation:Below is a sample calculation for SP-1 a. Flow Rate calculations: Based on fire sprinklers operation over the sump pit as per the following assumption i. Sprinkler fire hazard in parking area is ordinary-1 ii. Flow Density for Ordinary-1 hazard is 0.15 gpm/ft2 iii. Area of sprinkler operations is 1500 ft2 iv. The following table shows the calculations

Static Head psi 16.5

Pipe Size

Table M.106 Sump Pump Flow Calculations Flow density (gpm/ft2) 0.15 Area of sprinkler operation (ft2) 1500 Total Pump flow (gpm) [L/s] 225 [14.2 L/s]

DVR 251011/109

P a g e | 130 / 292

b. Pump head calculations; The below table shows pump head calculations for SP-1: Table M.107: Pump Head Calculations Static Head m 14 Pipe Size Pipe Head Loss Fluid Residual Safety Total pressure Equivalent According to Velocity Pressure Factor Length pipe size mm m mm/m m/s m m. H2o (Bar) 100 30 7* 0.85* 4 10% 20 (2.0) *: Head loss data & fluid velocity figures with respect to pipe size and flow are as per ASHRAE Fundamentals 2005 chapter 36, Pipe Sizing Refer to Appendix A, Page A.6 c. Pump Selection: The below table shows pump selection and configuration: Table M.108: Pump selection Pump Type No. Total Pump Flow Each Pump Flow Pump Head Submersible waste water pump 2 Pumps (Duplex) L/s (GPM) L/s (GPM) Bar (m H2O) 14.2 (225) 7.1 (112.5) 2.0 (20)

Pump diameter* mm 405 Pump Height* mm 770 Pump Length* mm 795 Configuration Lead-lag *: Reference for pump data from Grundfos Pumps; Refer to Appendix A, Page A.16 IFC Pumps are accepted d. Pit sizing: The below table shows pit sizing calculations: Table M.109: Pit sizing Pump Flow Basin Diameter Draw Down volume Capacity of fluid per ft. Draw Down Height Depth of lowest level incoming piping Difference between inlet pipe and high water level GPM (L/s) in Gal. Gal/ft. ft. ft. in 225 (14.2) 72 891 212 4.2 3 6.0

DVR 251011/109

P a g e | 131 / 292

Minimum depth at the bottom of the ft. 1.0 basin Sump pit Height ft. (m) 8.7 (2.65) Min. pit size should be 1.8 x 1.8x2.65 (8.6 m3) Procedure for sizing pit is described in Handbook of Mechanical Engineering Calculations; Part 3 Environmental Control; Section 15 Plumbing and Drainage for Buildings and Other Structures. Refer to Appendix A, Pages A.8, A.9, A.10 7. Comparison: The following table shows a comparison between IFC and design review output

Table M.110: Comparison between IFC and Design review output Pump flow rate calculations IFC IFC is using fire fighting demand as 500 gpm divided by 2 pits (250 gpm each) 500 gpm fire demand is over estimated. According to ground floor (P110) it is free discharge, and not reflected and coordinated in site utilities plan (XP101) 1.5 m Design review output Same method is used based on 0.15 gpm/ft2 flow density and 1500 ft2 area Total pump flow 14.2 L/s Each pump sized based on 50% of total flow

Forced flow outlet discharge

Forced discharge flow shall be connected to the soil net work through brake manhole, in addition to that rain water should be connected to storm water system

Pit depth Elevator Pit 1 Sand Trap 2

Minimum depth shall not be less than 2.65 m Should be considered in calculations to find Not considered the lowest waste incoming pipe connected to SP-1 Should be provided to block sand particles Not provided from entering and accumulating inside the pit 1. Refer to Appendix A, Page A.7 2. Refer to Appendix A, Page A.13

DVR 251011/109

P a g e | 132 / 292

III. Gray Water Tank:

Table M.111; Gray water tank data as per IFC Design Drawings & Calculations output from design review Design Review Output

Plan
rd

Calculations

Riser
Typ. Riser Diagram Water, Sewer, Waste & Vent Distribution System (P118)

Structure
3rd Basement Foundation Master Plan (S-101)

Drawing Reference

3 Basement Master Floor Plumbing Plan (P-101)

It 01 Calcs -3 (Plumbing Design Calculations)

Foundation & Schedule & Details ( S-201) Not available


22.2 m3

Grey Water Tank Size NonPotable Water Tank Size Location Access Panel Overflow Vent Drain Make up water & backflow preventer Cat ladder Level of incoming waste line

85 m3 No tank is available on plans Basement-3 Under Ground Above Provided Not Provided Provided Provided Not Provided +2000

85 m3 No tank is available on calculations N/A N/A N/A N/A N/A N/A

Not available

Not available

Not available

22.2 m3

Basement-3, Above Ground N/A Provided Not Provided Provided Not Provided

Basement-3, Above Ground Not Provided Provided N/A N/A N/A

Not matching should be indicated. Should be provided. Matching. Should be provided. Matching. Should be provided. Should be provided. Should be taken into consideration.

Not Provided N/A

Not Provided N/A

Not Provided N/A

Red: Not Acceptable, Orange: Partially, Green: Acceptable

1.

Description: a. PG plan drawing shows non potable water tank underground, but PG riser, and structural section shows the tank above ground. b. Gray water tank is over sized and have to be divided into to two tanks, one for Raw water and the other for treated water c. Actual tank size is different than that in calculations and plans ( Level of incoming waste pipe is not taken into considerations) d. Tank is not provided with ladder below tank access panel.

DVR 251011/109

P a g e | 133 / 292

e. Gray water tank sizing: The following table shows gray water tank effective volume as per drainage plans and structural drawings f. Effective volume is 63 m3 as per IFC and this is below required as per calculations (85m3)

Table M.112: Gray Water Tank Effective Volume Given tank area Tank height Depth of lowest level incoming piping Difference between inlet pipe and high water level Effective height Effective volume m2 m m m m m3 30 2.93 2.25 0.15 2.1 63

2.

Sample calculations: The below is a sample calculations for sizing of gray water systems

Table M.113: Gray Water Tank Size Verification Building Floor Area m2 m2 Persons

Total Area: Per person Area requirement--> (as per IPC code) Total no. of users (persons) ----------> OPTION-1 Assuming each person will use the WC a day Quantity of flushed water per flushing Water requirement per day for flushing No. of persons x no. of flushes x 6.1 liters OPTION-2 As per IPC Code Daily water demand for Office application Water requirement = persons x water demand ---->

9798 14 700

2.00 times 6.10 Liters 8,538.26 8.54 liters m3

45.00 31,493.57

liters/person liters

As per Plumbing Engineering Servicing Design Guide, Water consumption ratio for appliances is as follows: Shower & Bath 5% Toilet flushing 32% Laundry 20% Kitchen 15% Basin 9%

DVR 251011/109

P a g e | 134 / 292

So, Flushing water requirement --->

14,856

liters

Gray Water System (Collection tank plus treated tank) Capacity as per calculations ----> Gray water tank capacity = 22.2 m3 Non-Potable water tank capacity = 22.2 m3 Gray Water Tank Capacity as per IFC ----> 85 m3

14.8 m3 14.8 X3 Days 44.4 m3

Comparison of IFC Capacities with Calculated Capacities


Tank Capacity (M3) as per Calculation

Daily Requirement (m3) 14.8

No. of Days Holding 5.7

3.

Comparison: The below table shows a comparison between IFC and Design review output

Table M.114: Non Potable Water Tank Comparison IFC Tank size As per IFC PG plans and calculations, tank size is 85m3 Tank Partition One partition As per PG drawings tank is located U/G As per Structural drawings, tank is located above ground Design review output AS per structural drawings, effective tank size is 63m3 85 m3 and 63 m3 gray water tank sizes are overestimated Tank should be split into two tanks, gray water collection tank and treated water tank Tank location must be identified Assumption for tank location above ground has been considered in calculations. Pipe level is 2250 mm measured from tank bottom level Should be taken into consideration and deducted from tank total

Tank location

Level of incoming waste pipe Not taken into consideration

DVR 251011/109

P a g e | 135 / 292

height Trench location ( serving gray water) Located above gray water tank footing Location should be coordinated with structural gray water tank footing.

IV. RECOMMENDATIONS: Further to the design review study and analysis, and as per the above sample calculation for sump pits and gray water tanks for IT 01 building, the following can be concluded:

1. The discharge pipe from submersible pump is having high pressure loss and fluid velocity, it is recommended to resize the pipe according to the allowable pressure loss and velocity parameters. 2. Pit sizing: The level of lowest invert level incoming waste pipe is not taken into consideration when sizing the pit depth. Also, the size of duplex pumps should be given more attention in sizing the pit to verify if the current size fits for two submersible pumps. 3. The pit size is found to be insufficient with respect to the fixtures and drainage points connected to it. It is recommended to take the level of incoming waste pipes and the size of submersible pumps into consideration when sizing the pit. 4. Gray water tank is oversized. It is recommended to size the gray water tank for 1 day water reserve and no more than 3day (72 Hours), as per IPC. 5. It is required to provide gray water tank with makeup water line with backflow preventer to avoid pump dry run. 6. It is required to provide the gray water tank with overflow, vent with insect screen, and access panel and cat ladder for maintenance.

DVR 251011/109

P a g e | 136 / 292

i. BUILDING ( IT 02)
Underground piping, submersible pumps and pits, gray water concrete tank and related calculations have been reviewed.

I.

DESIGN PARAMETERS:

The followings table shows the design parameters used in the IFC design documents and those extracted through the design review process Table M.115 : Design parameters Item Parking drain Fixtures Units AHU & FCU Fixtures Units Floor Drain Fixtures Units Slope of Drainage piping (100 & 150 mm Diameters) Rainfall intensity WC Flush flow rate Number of persons per m2 IFC Design Value Reference 21 2 2 Not Indicated 75 mm/hr8 Not Indicated Not Indicated Not Indicated UPC UPC UPC UPC Required Parameters Reference UPC2 UPC3 UPC3 IPC4 UPC5 UPC6

Value 8 2 2 1%

50 mm/hr 6.1 liter (1.6 gallon/flush) 14

Water consumption ratio 5% per shower Water consumption ratio Not Plumbing Engineering 32% Indicated per toilet flushing Servicing Design Water consumption ratio Not Guide- The Institute of 20% Indicated Plumbing 20027 per Laundry Water consumption ratio Not 15% Indicated per kitchen Water consumption ratio Not 9% Indicated per basin 1. IFC design indicates parking floor drain to have 2 FU. However, since pipe connection is 4 UPC calls for 8 FU to be used in calculations. 2. Refer to Appendix A, PageA.3 3. Refer to Appendix A, PageA.2 4. Refer to appendix A, Page A.11 5. Refer to Appendix A, Page A.5 6. Refer to Appendix A, Page A.1 7. Refer to Appendix A, Page A.4 8. Rainfall intensity used by the designer varies for different buildings. It is recommended to use 50 mm/hr

DVR 251011/109

P a g e | 137 / 292

II.

SUMP PITS & SUBMERSIBLE PUMPS (SP-2): 1. Submersible pump-2 (SP-2) has been reviewed as an example for others in the same building. Results of this review indicate that same issues are found in other areas within the same building 2. IFC Design plans(Drainage), IFC calculations, IFC risers, IFC structural drawings and sections have been reviewed, the following table shows the results:

Table M.116: SP-2 design data as per mechanical, structural drawings and calculations
Mechanical Drawings Plan 3rd Basement Master Floor Plumbing Plan (P-101) Drawings reference Ground Floor Master Plumbing Plan (P-110) Riser Calculations Plan Structure Sections Design Review Output

N/A

It 02 Calcs -3 (Plumbing Design Calculations)

3rd Basement Foundation Master Plan (S-101)

Foundation & Schedule & Details ( S-201)

N/A

Foundation Type Location 3RD Basement Grids (01 & F,G) N/A

Column Base (Footings) 3RD Basement Grids (01 & F,G)

N/A

Shown, but height size was referred to PG (in which not found)

N/A Should be indicated on Plumbing drawings

Encasement for Drainage Pipe Under ground

Not shown

N/A

Shown without sizing

Pump Data

Flow = 15.77 L/s Head = 1.5 Bar

N/A

Tag. Numbers not matching with plan and calculation (assuming SP1 in plan = typ. to 2 & 3) Flow = 15.77 L/s Head = 1.5 Bar

2 pumps 7.1 L/s each Head 2 Bar IFC pumps accepted

Pump discharge pipe size (Forced Flow)

100 mm The pit shown in the structural is general to be taken actual size from PG drawings

100 mm

Pit Size

1.25 m x 1.25 m Depth is not available

N/A

1.55 x 1.55 x 1.5 m

Shown, but height size was referred to PG (in which not found)

1.8 x 1.8x2.65 m3

DVR 251011/109

P a g e | 138 / 292

Table M.116: SP-2 design data as per mechanical, structural drawings and calculations
Mechanical Drawings Plan Riser Sump pit Service Mechanical Drawings Plan Parking drains Elevator Pit Included Not Included Riser Not Included Not Included Not Included Not Included Calculations Plan N/A N/A Structure Sections N/A N/A Should be included Should be included Should not be included in calculations when using fire sprinkler operation method Should be included Should be included Design Review Output Calculations Plan Structure Sections Design Review Output

Rain water

Not Included

Not Included

Not Included

N/A

N/A

Condensate drain Gray Water Over Flow

Included Included

Not Included Included

Not Included Not Included

N/A N/A

N/A N/A

Calculation was performed based on fire fighting demand Red: Not Acceptable, Orange: Partially, Green: Acceptable

3. Description: a. Pump Flow rate i. In the same discipline there is discrepancy in the Tag numbers miss matching with calculation, and plan, and same mismatching with other disciplines like structural. ii. Reference to plumbing ground floor (P110) the pump discharge flow appears to be free, but referring to site utilities plan (XP1001) the discharge flow is reflected (missing).

DVR 251011/109

P a g e | 139 / 292

4. Pump Head: The following table shows design data calculations and analysis; Table M.117: IFC Design Head Calculations Head Loss According Fluid Residual Safety Total pressure to pipe Velocity Pressure Factor size L/s psi mm psi mm/m m/s m psi m. H2o (Bar) 15.77 16.5 100 6 31* 1.9* 5 15 (1.5) Head loss data & fluid velocity figures with respect to pipe size and flow are as per ASHRAE Fundamentals 2005 chapter 36, Pipe Sizing Refer to Appendix A, Page A.6 Flow Rate Static Head Pipe Size Pipe Friction loss 5. Pit Size: a. b. c. d. Modified calculations based on the above will change pit size. Duplex Pump sizes are not taken into consideration. Effective volume is not properly calculated. Pit depth is less than required (elevator pits are not taken into consideration)

6. Sample of calculation:Below is a sample calculation for SP-2 a. Flow Rate calculations: Based on fire sprinklers operation over the sump pit as per the following assumption v. Sprinkler fire hazard in parking area is ordinary-1 vi. Flow Density for Ordinary-1 hazard is 0.15 gpm/ft2 vii. Area of sprinkler operations is 1500 ft2 viii. The following table shows the calculations

Table M.118: Sump Pump Flow Calculations Flow density (gpm/ft2) 0.15 Area of sprinkler operation (ft2) 1500 Total Pump flow (gpm) [L/s] 225 [14.2 L/s]

DVR 251011/109

P a g e | 140 / 292

b. Pump head calculations: The below table shows pump head calculations for SP-2: Table M.119: Pump Head Calculations Flow Rate L/s Static Head m Pipe Size mm Pipe Equivalent Length m Head Loss According to pipe size mm/m Fluid Velocity m/s Residual Pressure m Safety Factor Total pressure m. H2o (Bar) 20 (2.0)

9 14 100 30 14* 1.2* 4 10% Head loss data & fluid velocity figures with respect to pipe size and flow are as per ASHRAE Fundamentals 2005 chapter 36, Pipe Sizing Refer to Appendix A, Page A.6

c. Pump Selection: The below table shows pump selection and configuration: Table M.120: Pump selection Pump Type No. Total Pump Flow Each Pump Flow Pump Head Submersible waste water pump 2 Pumps (Duplex) L/s (GPM) L/s (GPM) Bar (m H2O) 14.2 (225) 7.1 (112.5) 2.0 (20)

Pump diameter* mm 405 Pump Height* mm 770 Pump Length* mm 795 Configuration Lead-lag *: Reference for pump data from Grundfos Pumps; Refer to Appendix A, Page A.16 IFC Pumps are accepted a. Pit sizing: The below table shows pit sizing calculations: Table M.121: Pit sizing Pump Flow Basin Diameter Draw Down volume Capacity of fluid per ft. Draw Down Height Depth of lowest level incoming piping GPM (L/s) in Gal. Gal/ft. ft. ft. 225 (14.2) 72 891 212 4.2 3

DVR 251011/109

P a g e | 141 / 292

Table M.121: Pit sizing Difference between inlet pipe and high in 6.0 water level Minimum depth at the bottom of the ft. 1.0 basin Sump pit Height ft. (m) 8.7 (2.65) 3 Min. pit size should be 1.8 x 1.8x2.65 (8.6 m ) Procedure for sizing pit is described in Handbook of Mechanical Engineering Calculations; Part 3 Environmental Control; Section 15 Plumbing and Drainage for Buildings and Other Structures. Refer to Appendix A, Pages A.8, A.9, A.10

7. Comparison: The following table shows a comparison between IFC and Design review output Table M.122: Comparison between IFC and design review output IFC Pump flow rate calculations Design review output Fire fighting demand 1: Fire Hazard is ordinary-Type-1 Flow density 0.15 gpm/ft2 Design area 1500ft2 Flow in case of sprinkler operation = 0.15 x 1500 = 225 gpm, this value is divided into 2 pumps 112.5 gpm (7.1 L /s) each

IFC is using fire fighting demand as 500 gpm divided by 2 pits (250 gpm each) 500 gpm fire demand is over estimated.

Pit depth

Forced flow outlet discharge

1.5 m According to ground floor (P110) it is free discharge, and not reflected and coordinated in site utilities plan (XP101) Not considered Not provided

Minimum depth shall not be less than 2.5 m Forced discharge flow shall be connected to the soil net work through brake manhole, in addition to that rain water should be connected to storm water system

Elevator Pit 2 Sand Trap 3

Should be considered in calculations to find the lowest waste incoming pipe connected to SP-2 Should be provided to block sand particles from entering and accumulating inside the pit

1. Refer to Appendix A, Page A.12 2. Refer to Appendix A, Page A.7 3. Refer to Appendix A, Page A.13

DVR 251011/109

P a g e | 142 / 292

III.

GRAY WATER TANK:

Table M.123: Gray water Tank design data as per mechanical, structural drawings and calculations Plan Calculations Riser Structure Design Review Output
3 Basement Master Floor Plumbing Plan (P-101)
rd

Drawing Reference

N/A

3rd Basement Foundation Master Plan (S-101)

N/A

Foundation & Schedule & Details ( S-201)


N/A 22 m3 22 m3

Gray water Tank Size Non-Potable Water Tank Size Location Access Panel Overflow Vent Drain Make up water & backflow preventer Cat ladder Level of incoming waste line

80 m3 No tank is available Basement-3, Under Ground Above Provided Not Provided Provided Provided Not Provided Not considered 1.

N/A Not Provided

N/A Not Provided N/A N/A N/A N/A N/A N/A N/A N/A

Not Provided Basement-3, Above Ground Not Provided Provided N/A N/A N/A Not Provided N/A

N/A N/A N/A N/A N/A N/A Not Provided Not considered

Not matching Should be indicated. Should be provided Matching Should be provided Should be provided Should be provided in calculations and riser Should be provided Should be taken into consideration

Description: a. PG plan drawing shows non potable water tank underground, but PG riser, and structural section shows the tank above ground. b. Gray water tank is over sized and have to be divided into to two tanks, one for Raw water and the other for treated water c. Actual tank size is different than that in calculations and plans ( Level of incoming waste pipe is not taken into considerations) d. Tank is not provided with ladder below tank access panel. Gray water tank sizing: The following table shows gray water tank effective volume as per drainage plans and structural drawings:

2.

Table M.124: Gray Water Tank Effective Volume Given tank area Tank height m2 m 30 2.93

DVR 251011/109

P a g e | 143 / 292

Depth of lowest level incoming piping Difference between inlet pipe and high water level Effective height Effective volume

m m m m3

2.25 0.15 2.1 63

Effective volume is 63 m3 as per IFC and this is below required as per calculations (80m3) 3. Sample calculations:

Table M.125: Gray Water verification Building Floor Area m2 m2 Persons

Total Area: Per person Area requirement--> (as per IPC code) Total no. of users (persons) ----------> OPTION-1 Assuming each person will use the WC a day Quantity of flushed water per flushing Water requirement per day for flushing No. of persons x no. of flushes x 6.1 liters OPTION-2 As per IPC Code Daily water demand for Office application Water requirement = persons x water demand ----->

9522 14 680

2.00 times 6.10 Liters 8,298 8.3 liters m3

45.00 30606

liters/person liters

As per Plumbing Engineering Servicing Design Guide, Water consumption ratio for appliances is as follows: Shower & Bath 5% Toilet flushing 32% Laundry 20% Kitchen 15% Basin 9% So, Flushing water requirement ---> 14,856 liters 14.8 x 3 days = Gray Water System (Collection tank plus treated 44.4m3 tank) Capacity as per calculations ----> Gray water tank capacity = 22 m3 Non-Potable water tank capacity = 22 m3 Gray Water Tank Capacity as per IFC ----> 80 m3

Comparison of IFC Capacities with Calculated Capacities


Tank Capacity (M3) as per Calculation Daily Requirement (m3) No. of Days Holding

DVR 251011/109

P a g e | 144 / 292

Table M.125: Gray Water verification

14.8

5.4

4.

Comparison: The below table shows a comparison between IFC and design review output

Table M.126: Gray Water Tank Comparison IFC Tank size AS per IFC PG plans and calculations, tank size is 85m3 Tank Partition Tank location One partition AS per PG drawings tank is located U/G AS per Structural drawings, tank is located above ground Level of incoming waste pipe Trench location ( serving gray water tank) Not taken into consideration Located above gray water tank footing Design review output AS per structural drawings, effective tank size is 63m3 Tank size needs confirmation from supplier 80 m3 and 63 m3 gray water tank sizes are over-estimated Tank should be split into two tanks, gray water collection tank and treated water tank Tank location must be identified Assumption for tank location above ground has been considered in calculations. Pipe level is 2250 mm measured from tank bottom level Should be taken into consideration and deducted from tank total height Location should be coordinated with structural gray water tank footing.

DVR 251011/109

P a g e | 145 / 292

IV.

RECOMMENDATIONS:

Further to the design review study and analysis, and as per the above sample calculation for sump pits and gray water tanks for IT02 building, the following can be concluded: 1. The discharge pipe from submersible pump is having high pressure loss and fluid velocity, it is recommended to resize the pipe according to the allowable pressure loss and velocity parameters. 2. Pit sizing: The level of lowest invert level incoming waste pipe is not taken into consideration when sizing the pit depth. Also, the size of duplex pumps should be given more attention in sizing the pit to verify if the current size fits for two submersible pumps. 3. The pit size is found to be insufficient with respect to the fixtures and drainage points connected to it. It is recommended to take the level of incoming waste pipes and the size of submersible pumps into consideration when sizing the pit. 4. Gray water tank is oversized. It is recommended to size the gray water tank for no more than 3 days (72 Hours), as per IPC. 5. It is required to provide gray water tank with makeup water line with backflow preventer to avoid pump dry run.

6. It is required to provide the gray water tank with overflow, vent with insect screen, and access panel and cat ladder for maintenance

DVR 251011/109

P a g e | 146 / 292

j. BUILDING ( IT 03)
Underground piping, submersible pumps and pits, gray water concrete tank and related calculations have been reviewed.

I.

DESIGN PARAMETERS:

The followings table shows the design parameters used in the IFC design documents and those extracted through the design review process

Table M.127: Design parameters Item Parking drain Fixtures Units AHU & FCU Fixtures Units Floor Drain Fixtures Units Slope of Drainage piping (100 & 150 mm Diameters) Rainfall intensity WC Flush flow rate Number of persons per m2 IFC Design Value Reference 21 2 2 Not Indicated 75 mm/hr8 Not Indicated Not Indicated Not Indicated UPC UPC UPC UPC Required Parameters Reference UPC2 UPC3 UPC3 IPC4 UPC5 UPC6

Value 8 2 2 1% 50 mm/hr 6.1 liter (1.6 gallon/flush) 14

Water consumption ratio 5% per shower Water consumption ratio Not Plumbing Engineering 32% Indicated per toilet flushing Servicing Design Water consumption ratio Not Guide- The Institute of 20% Indicated Plumbing 20027 per Laundry Water consumption ratio Not 15% Indicated per kitchen Water consumption ratio Not 9% Indicated per basin 1. IFC design indicates parking floor drain to have 2 FU. However, since pipe connection is 4 UPC calls for 8 FU to be used in calculations. 2. Refer to Appendix A, PageA.3 3. Refer to Appendix A, PageA.2 4. Refer to appendix A, Page A.11 5. Refer to Appendix A, Page A.5 6. Refer to Appendix A, Page A.1 7. Refer to Appendix A, Page A.4 8. Rainfall intensity used by the designer varies for different buildings. It is recommended to use 50 mm/hr

DVR 251011/109

P a g e | 147 / 292

II.

SUMP PITS & SUBMERSIBLE PUMPS (SP-2): 1. Submersible pump-2 (SP-2) has been reviewed as an example for others in the same building. Results of this review indicate that same issues are found in other areas within the same building 2. IFC Design plans(Drainage), IFC calculations, IFC risers, IFC structural drawings and sections have been reviewed, the following table shows the results:

Table M.128: SP-1 Design data as per IFC Design Drawings & Calculations Output from design review
Mechanical Drawings Plan 3rd Basement Master Floor Plumbing Plan (P-101) Drawings reference Ground Floor Master Plumbing Plan (P-110) Riser Calculations Plan Structure Sections Design Review Output

N/A

It 03 Calcs -3 (Plumbing Design Calculations)

3rd Basement Foundation Master Plan (S-101)

Foundation & Schedule & Details ( S-201)

Foundation Type Location Encasement for Drainage Pipe Under ground 3 Basement Grids (E,F & 6,7)
RD

Column Base (Footings) 3RD Basement Grids (E,F & 6,7)

N/A

Shown, but height size was referred to PG (in which not found)

N/A

Not shown

N/A

Shown without sizing

Pump Data

Flow = 15.77 L/s Head = 1.5 Bar

Not available

Tag. Numbers not matching with plan and calculation (assuming SP1 in plan = typ. to 2 & 3) Flow = 15.77 L/s Head = 1.5 Bar

2 Pumps 7.1 L/s each Head 2 bar IFC pump flow is accepted

Pump discharge pipe size (Forced Flow)

100 mm

100 mm

Pit Size

1.25 m x 1.25 m Depth is not available

Not available

1.55 x 1.55 x 1.5 m

Shown, but height size was referred to PG (in which not found)

The pit shown in the structural is general to be taken actual size from PG

1.8x1.8x 2.65 m3

DVR 251011/109

P a g e | 148 / 292

Table M.128: SP-1 Design data as per IFC Design Drawings & Calculations Output from design review
Mechanical Drawings Plan Riser Sump Pit Service Design Review Output Sections N/A N/A N/A N/A N/A Should be included Should be included Should be included Should be included Should be included Calculations Plan Structure Sections drawings Design Review Output

Mechanical Drawings Plan Parking drains Elevator Pit Rain water Condensate drain Gray Water Over Flow Included Not Included Not Included Included Included Riser N/A N/A N/A N/A

Calculations

Structure Plan

Not Included Not Included Not Included Not Included

N/A N/A N/A N/A

Not Included N/A N/A Calculation was performed based on fire fighting demand Red: Not Acceptable, Orange: Partially, Green: Acceptable

3. Description of above findings: a. Pump Flow rate i. In the same discipline there is discrepancy in the Tag numbers miss matching with calculation, and plan, and same mismatching with other disciplines like structural. ii. Reference to plumbing ground floor (P110) the pump discharge flow appears to be free, but referring to site utilities plan (XP101) the discharge flow is reflected (missing). 4. Pump Head: The following table shows design data calculations and analysis; Table: M.129: IFC Design Head Calculations Head Loss According Fluid Residual Safety Total pressure to pipe Velocity Pressure Factor size L/s psi mm psi mm/m m/s m psi m. H2o (Bar) 15.77 16.5 100 6 31* 1.9* 5 15 (1.5) Head loss data & fluid velocity figures with respect to pipe size and flow are as per ASHRAE Fundamentals 2005 chapter 36, Pipe Sizing Refer to Appendix A, Page A.6 Flow Rate Static Head Pipe Size Pipe Friction loss

DVR 251011/109

P a g e | 149 / 292

5. Pit Size: a. b. c. d. Modified calculations based on the above will change pit size. Duplex Pump sizes are not taken into consideration. Effective volume is not properly calculated. Pit depth is less than required (elevator pits are not taken into consideration)

6. Sample of calculation:Below is a sample calculation for SP-2 a. Flow Rate calculations: Based on fire sprinklers operation over the sump pit as per the following assumption ix. Sprinkler fire hazard in parking area is ordinary-1 x. Flow Density for Ordinary-1 hazard is 0.15 gpm/ft2 xi. Area of sprinkler operations is 1500 ft2 xii. The following table shows the calculations

Table M.130 Sump Pump Flow Calculations Flow density (gpm/ft2) 0.15 Area of sprinkler operation (ft2) 1500 b. Pump head calculations; The below table shows pump head calculations for SP-1 Total Pump flow (gpm) [L/s] 225 [14.2 L/s]

Table M.131: Pump Head Calculations Flow Rate L/s Static Head m Pipe Size mm Pipe Equivalent Length m Head Loss According to pipe size mm/m Fluid Velocity m/s Residual Pressure m Total Safety pressure Factor m. H2o (Bar) 20 (2.0)

10.68 14 100 30 20* 1.4* 4 10% Head loss data & fluid velocity figures with respect to pipe size and flow are as per ASHRAE Fundamentals 2005 chapter 36, Pipe Sizing Refer to Appendix A, Page A.6

DVR 251011/109

P a g e | 150 / 292

c. Pump Selection: The below table shows pump selection and configuration: Table M.132: Pump selection Pump Type No. Total Pump Flow Each Pump Flow Pump Head Submersible waste water pump 2 Pumps (Duplex) L/s (GPM) L/s (GPM) Bar (m H2O) 14.2 (225) 7.1 (112.5) 2.0 (20)

Pump diameter* mm 405 Pump Height* mm 770 Pump Length* mm 795 Configuration Lead-lag *: Reference for pump data from Grundfos Pumps; Refer to Appendix A, Page A.16 IFC Pumps are accepted d. Pit sizing: The below table shows pit sizing calculations: Table M.133: Pit sizing Pump Flow GPM (L/s) in Gal. Gal/ft. ft. ft. 225 (14.2) 72 891 212 4.2 3

Basin Diameter Draw Down volume Capacity of fluid per ft. Draw Down Height Depth of lowest level incoming piping Difference between inlet pipe and high in 6.0 water level Minimum depth at the bottom of the ft. 1.0 basin Sump pit Height ft. (m) 8.7 (2.65) 3 Min. pit size should be 1.8 x 1.8x2.65 (8.6 m ) Procedure for sizing pit is described in Handbook of Mechanical Engineering Calculations; Part 3 Environmental Control; Section 15 Plumbing and Drainage for Buildings and Other Structures. Refer to Appendix A, Pages A.8, A.9, A.10

DVR 251011/109

P a g e | 151 / 292

7. Comparison: The following table shows a comparison between IFC and Design review output

Table M.134: Comparison between IFC and Design review output IFC Pump flow rate calculations Pit depth Ramp Rain Water IFC is using fire fighting demand as 500 gpm divided by 2 pits (250 gpm each) 500 gpm fire demand is over estimated. 1.5 m Ramp rain water note connected to drainage net work According to ground floor (P110) it is free discharge, and not reflected and coordinated in site utilities plan (XP101) Not considered Not provided Design review output Fire fighting demand 1: Fire Hazard is ordinary-Type-1 Flow density 0.15 gpm/ft2 Design area 1500ft2 Flow in case of sprinkler operation = 0.15 x 1500 = 225 gpm, this value is divided into 2 pumps 112.5 gpm (7.1 L /s) each

Minimum depth shall not be less than 2.5 m Shall be connected Forced discharge flow shall be connected to the soil net work through brake manhole, in addition to that rain water should be connected to storm water system

Forced flow outlet discharge

Elevator Pit 2 Sand Trap 3

Should be considered in calculations to find the lowest waste incoming pipe connected to SP-2 Should be provided to block sand particles from entering and accumulating inside the pit

1: Refer to Appendix A, Page A.12 2: Refer to Appendix A, Page A.7 3: Refer to Appendix A, Page A.13

DVR 251011/109

P a g e | 152 / 292

III.

GRAY WATER TANK:

Table M.135: Gray Water Tank design data as per mechanical, structural drawings and calculations Design Review Plan Calculations Riser Structure Output
3rd Basement Master Floor Plumbing Plan (P-101) 3rd Basement Foundation Master Plan (S-101)

Drawing Reference

N/A

N/A

Foundation & Schedule & Details ( S-201)


N/A 22 m3 22 m3

Gray water Tank Size Non-Potable Water Tank Size Location Access Panel Overflow Vent Drain Make up water & backflow preventer Cat ladder Level of incoming waste line

120 m3 Tank is Not available Basement-3, Under Ground Floor mounted Provided Not Provided Provided

N/A Not Provided

N/A Not Provided N/A N/A N/A N/A N/A

Not shown Basement-3, Above Ground Not Provided Provided N/A N/A

N/A N/A N/A N/A N/A

Not matching shall be indicated. Should be provided matching Should be provided Should be provided in calculation and riser. Should be provided in calculation and riser. Should be provided Should be taken into consideration

Provided Not Provided N/A

N/A Not Provided N/A

N/A N/A N/A

N/A Not Provided N/A

Red: Not Acceptable, Orange: Partially, Green: Acceptable

1.

Description: a. PG plan drawing shows non potable water tank underground, but PG riser, and structural section shows the tank above ground. b. Gray water tank is over sized and have to be divided into to two tanks, one for Raw water and the other for treated water c. Gray water tank system and capacity needs confirmation from supplier d. Actual tank size is different than that in calculations and plans ( Level of incoming waste pipe is not taken into considerations) e. Tank is not provided with ladder below tank access panel.

DVR 251011/109

P a g e | 153 / 292

2.

Gray water tank sizing: The following table shows gray water tank effective volume as per drainage plans and structural drawings:

Table M.136: Gary Water Tank Effective Volume Given tank area Tank height Depth of lowest level incoming piping Difference between inlet pipe and high water level Effective height Effective volume m2 m m m m m3 47.5 2.93 1.68 0.15 1.53 72.6

Effective volume is 72.6 m3 as per IFC and this is below required as per PG plans (120m3) 3. Sample calculations: The below is a sample calculations for sizing of gray water systems

Table M.137: : Gray Water Tank Size Verification Building Floor Area m2 m2 Persons

Total Area: Per person Area requirement--> (as per IPC code) Total no. of users (persons) ----------> OPTION-1 Assuming each person will use the WC a day Quantity of flushed water per flushing Water requirement per day for flushing No. of persons x no. of flushes x 6.1 liters OPTION-2

14025 14 1002

2.00 times 6.10 Liters 12,222 12.22 liters m3

As per IPC Code Daily water demand for Office application 45.00 liters/person Water requirement = persons x water demand -----> 45080 liters As per Plumbing Engineering Servicing Design Guide, Water consumption ratio for appliances is as follows: Shower & Bath 5% Toilet flushing 32% Laundry 20% Kitchen 15% Basin 9% So, Flushing water requirement ---> 14,400 liters

DVR 251011/109

P a g e | 154 / 292

14.4 Gray Water System (Collection tank plus treated tank) Capacity as per calculations ----> 14.4 x 3days = 43.2 Gray water tank capacity = 21.6 m3 Non-Potable water tank capacity =21.6 m3 Gray Water Tank Capacity as per IFC ----> 120

m3

Comparison of IFC Capacities with Calculated Capacities


Tank Capacity (M3) as per Calculation

Daily Requirement (m3) Option-2 14.4

No. of Days Holding 8.32

4.

Comparison: The below table shows a comparison between IFC and Design review output

Table M.138: Gray Water Tank Comparison IFC Tank size AS per IFC PG plans and calculations, tank size is 120m3 Tank Partition Tank location One partition AS per PG drawings tank is located U/G AS per Structural drawings, tank is located above ground Level of incoming waste pipe Not taken into consideration Design review output As per structural drawings, effective tank size is 63m3 Tank size needs confirmation from supplier 120 m3 and 72.31. m3 gray water tank sizes are over-estimated Tank should be split into two tanks, gray water collection tank and treated water tank Tank location must be identified Assumption for tank location above ground has been considered in calculations. Pipe level is 1530 mm measured from tank bottom level Should be taken into consideration and deducted from tank total height Location should be coordinated with structural gray water tank footing.

Trench location ( serving gray water)

Located above gray water tank footing

DVR 251011/109

P a g e | 155 / 292

IV.

RECOMMENDATIONS:

Further to the design review study and analysis, and as per the above sample calculation for sump pits and gray water tanks for IT03 building, the following can be concluded:

1. The discharge pipe from submersible pump is having high pressure loss and fluid velocity, it is recommended to resize the pipe according to the allowable pressure loss and velocity parameters. 2. Pit sizing: The level of lowest invert level incoming waste pipe is not taken into consideration when sizing the pit depth. Also, the size of duplex pumps should be given more attention in sizing the pit to verify if the current size fits for two submersible pumps. 3. The pit size is found to be insufficient with respect to the fixtures and drainage points connected to it. It is recommended to take the level of incoming waste pipes and the size of submersible pumps into consideration when sizing the pit. 4. Gray water tank is oversized. It is recommended to size the gray water tank for 1 day water reserve and no more than 3day (72 Hours), as per IPC. 5. It is required to provide gray water tank with makeup water line with backflow preventer to avoid pump dry run. 6. It is required to provide the gray water tank with overflow, vent with insect screen, and access panel and cat ladder for maintenance

DVR 251011/109

P a g e | 156 / 292

k. BUILDING ( KB04)
Study has been concentrated on underground services at basement . I. DESIGN PARAMETERS:

The followings table shows the design parameters used in the IFC design documents and those extracted through the design review process

Table M.139 : Design parameters Item Parking drain Fixtures Units AHU & FCU Fixtures Units Floor Drain Fixtures Units Slope of Drainage piping (100 & 150 mm Diameters) Rainfall intensity WC Flush flow rate Number of persons per m2 IFC Design Value Reference 21 2 2 Not Indicated 75 mm/hr8 Not Indicated Not Indicated Not Indicated UPC UPC UPC UPC Required Parameters Reference UPC2 UPC3 UPC3 IPC4 UPC5 UPC6

Value 8 2 2 1% 50 mm/hr 6.1 liter (1.6 gallon/flush) 14

Water consumption ratio 5% per shower Water consumption ratio Not Plumbing Engineering Servicing 32% Indicated per toilet flushing Design Water consumption ratio Not Guide- The Institute of 20% Indicated Plumbing 20027 per Laundry Water consumption ratio Not 15% Indicated per kitchen Water consumption ratio Not 9% Indicated per basin 1. IFC design indicates parking floor drain to have 2 FU. However, since pipe connection is 4 UPC calls for 8 FU to be used in calculations. 2. Refer to Appendix A, PageA.3 3. Refer to Appendix A, PageA.2 4. Refer to appendix A, Page A.11 5. Refer to Appendix A, Page A.5 6. Refer to Appendix A, Page A.1 7. Refer to Appendix A, Page A.4 8. Rainfall intensity used by the designer varies for different buildings. It is recommended to use 50 mm/hr

DVR 251011/109

P a g e | 157 / 292

II.

SUMP PITS & SUBMERSIBLE PUMPS (SP-2): 1. Submersible pump-2 (SP-2) has been reviewed as an example for others in the same building. Results of this review indicate that same issues are found in other areas within the same building 2. IFC Design plans(Drainage), IFC calculations, IFC risers, IFC structural drawings and sections have been reviewed, the following table shows the results:

Table M.140: SP-1 Design data as per IFC Design Drawings & Calculations Output from design review
Mechanical Drawings Plan Basement Master Floor Plumbing Plan (P-101) Riser KB04Plumbing Calcs-100pc Calculations Plan Basement Foundation Master Plan (S-101) Structure Sections Basement Foundation & Schedule & Details ( S-201) Design Review Output

Drawings reference

N/A

N/A

Foundation Type Location Encasement for Drainage Pipe Under ground Basement Grids (J,H & 1,2) N/A

Column Base (Footings) Basement Grids (J,H & 1,2) Shown without sizing

N/A

Shown, but height size was referred to PG (in which not found)

N/A Should be indicated on Plumbing drawings

Not shown

N/A

Pump Data

Flow = 6.31 L/s Head = 1.2 Bar

N/A

According to beginning of calculation 2x112.5 gpm it is required , but in end of calculation it is 2 x 100 gpm

2 pumps 7.1 L/s each Head 1.2 Bar IFC pumps are accepted

Pump discharge pipe size (Forced Flow)

100 mm

100 mm

Pit Size

1.1 m x 1.1 m Depth is not available

N/A

1.5 x 1.5 x 1.26 m

1.6 x 1.6, m Depth is not available

The pit shown in the structural is general to be taken actual size from PG drawings

1.8x1.8x2.65 m3

DVR 251011/109

P a g e | 158 / 292

Table M.140: SP-1 Design data as per IFC Design Drawings & Calculations Output from design review
Mechanical Drawings Plan Riser Calculations Plan Structure Sections Design Review Output

Sump pit Service

Mechanical Drawings Plan Parking drains Included Riser N/A

Calculations Plan N/A N/A

Structure Sections N/A

Design Review Output Should be included in plans, riser and calculations Should be included in plans, riser and calculations Should be included in plans, riser and calculations Should be included in plans, riser and calculations

Elevator Pit

Not Included

N/A

N/A

N/A

N/A

Rain water

Included

N/A

N/A

N/A

N/A

Condensate drain

Not Included

N/A

N/A

N/A

N/A

3. Sample of calculation:Below is a sample calculation for SP-2 a. Flow Rate calculations: Based on fire sprinklers operation over the sump pit as per the following assumption i. Sprinkler fire hazard in parking area is ordinary-1 ii. Flow Density for Ordinary-1 hazard is 0.15 gpm/ft2 iii. Area of sprinkler operations is 1500 ft2 iv. The following table shows the calculations

Table M.141: Sump Pump Flow Calculations Flow density (gpm/ft2) 0.15 Area of sprinkler operation (ft2) 1500 Total Pump flow (gpm) [L/s] 225 [14.2 L/s]

b. Pump head calculations; The below table shows pump head calculations for SP-2

DVR 251011/109

P a g e | 159 / 292

Table M.142: Pump Head Calculations Flow Rate L/s 7.2 Static Head m Pipe Size mm Pipe Equivalent Length m Head Loss According to pipe size mm/m Fluid Velocity m/s Residual Pressure m Safety Factor Total pressure

m. H2o (Bar) 9 100 30 10* 1* 4 10% 16 (1.6) *: Head loss data & fluid velocity figures with respect to pipe size and flow are as per ASHRAE Fundamentals 2005 chapter 36, Pipe Sizing . Refer to Appendix A, Page A.6 c. Pump Selection: The below table shows pump selection and configuration:

Table M.143: Pump selection Pump Type No. Total Pump Flow Each Pump Flow Pump Head Submersible waste water pump 2 Pumps (Duplex) L/s (GPM) L/s (GPM) Bar (m H2O) 14.2 (225) 7.1 (112.5) 2.0 (20)

Pump diameter* mm 405 Pump Height* mm 770 Pump Length* mm 795 Configuration Lead-lag *: Reference for pump data from Grundfos Pumps; Refer to Appendix A, Page A.16 IFC Pumps are accepted d. Pit sizing: The below table shows pit sizing calculations: Table M.144: Pit sizing Pump Flow GPM (L/s) in Gal. Gal/ft. ft. ft. 225 (14.2) 72 891 212 4.2 3

Basin Diameter Draw Down volume Capacity of fluid per ft. Draw Down Height Depth of lowest level incoming piping Difference between inlet pipe and high in 6.0 water level Minimum depth at the bottom of the ft. 1.0 basin Sump pit Height ft. (m) 8.7 (2.65) Min. pit size should be 1.8 x 1.8x2.65 (8.6 m3) Procedure for sizing pit is described in Handbook of Mechanical Engineering Calculations; Part 3 Environmental Control; Section 15 Plumbing and Drainage for Buildings and Other Structures. Refer to Appendix A, Pages A.8, A.9, A.10

DVR 251011/109

P a g e | 160 / 292

4. Comparison: The following table shows a comparison between IFC and Design review output Table M.145: Comparison between IFC and Design review output IFC Pump flow rate calculations IFC is using fire fighting demand as 500 gpm divided by 2 pits (250 gpm each) 500 gpm fire demand is over estimated. 1.26 m Ramp rain water note connected to drainage net work According to ground floor (P110) it is free discharge, and not reflected and coordinated in site utilities plan (XP101) Not considered Not provided Design review output Fire fighting demand 1: Fire Hazard is ordinary-Type-1 Flow density 0.15 gpm/ft2 Design area 1500ft2 Flow in case of sprinkler operation = 0.15 x 1500 = 225 gpm, this value is divided into 2 pumps 112.5 gpm (7.1 L /s) each IFC pumps are accepted

Pit depth Ramp Rain Water

Minimum depth shall not be less than 2.5 m Shall be connected Forced discharge flow shall be connected to the soil net work through brake manhole, in addition to that rain water should be connected to storm water system

Forced flow outlet discharge

Elevator Pit 2 Sand Trap 3

Should be considered in calculations to find the lowest waste incoming pipe connected to SP-2 Should be provided to block sand particles from entering and accumulating inside the pit

1:Refer to Appendix A, Page A.12 2:Refer to Appendix A, Page A.7 3:Refer to Appendix A, Page A.13

DVR 251011/109

P a g e | 161 / 292

III.

RECOMMENDATIONS:

Further to the design review study and analysis, and as per the above sample calculation for sump pits and gray water tanks for KB04 building, the following can be concluded: 1. Pit sizing: The level of lowest invert level incoming waste pipe is not taken into consideration when sizing the pit depth. Also, the size of duplex pumps should be given more attention in sizing the pit to verify if the current size fits for two submersible pumps. 2. The pit size is found to be insufficient with respect to the fixtures and drainage points connected to it. It is recommended to take the level of incoming waste pipes and the size of submersible pumps into consideration when sizing the pit.

DVR 251011/109

P a g e | 162 / 292

l. BUILDING ( KB05)
Underground piping, submersible pumps and pits and related calculations have been reviewed.

I.

DESIGN PARAMETERS:

The followings table shows the design parameters used in the IFC design documents and those extracted through the design review process

Table M.146 : Design parameters Item Parking drain Fixtures Units AHU & FCU Fixtures Units Floor Drain Fixtures Units Slope of Drainage piping (100 & 150 mm Diameters) Rainfall intensity WC Flush flow rate Number of persons per m2 IFC Design Value Reference 21 UPC 2 UPC 2 UPC Not Indicated 75 mm/hr8 Not Indicated Not Indicated Not Indicated UPC Required Parameters Reference UPC2 UPC3 UPC3 IPC4 UPC5 UPC6

Value 8 2 2 1%

50 mm/hr 6.1 liter (1.6 gallon/flush) 14

Water consumption ratio per 5% shower Water consumption ratio per Not Plumbing Engineering 32% Indicated toilet flushing Servicing Design Water consumption ratio per Not Guide- The Institute of 20% Indicated Plumbing 20027 Laundry Water consumption ratio per Not 15% Indicated kitchen Water consumption ratio per Not 9% Indicated basin 1. IFC design indicates parking floor drain to have 2 FU. However, since pipe connection is 4 UPC calls for 8 FU to be used in calculations. 2. Refer to Appendix A, PageA.3 3. Refer to Appendix A, PageA.2 4. Refer to appendix A, Page A.11 5. Refer to Appendix A, Page A.5 6. Refer to Appendix A, Page A.1 7. Refer to Appendix A, Page A.4 8. Rainfall intensity used by the designer varies for different buildings. It is recommended to use 50 mm/hr

DVR 251011/109

P a g e | 163 / 292

II.

SUMP PITS & SUBMERSIBLE PUMPS (SP-2): 1. Submersible pump-2 (SP-2) has been reviewed as an example for others in the same building. Results of this review indicate that same issues are found in other areas within the same building 2. IFC Design plans(Drainage), IFC calculations, IFC risers, IFC structural drawings and sections have been reviewed, the following table shows the results:

Table M.147: SP-2 design data as per mechanical, structural drawings and calculations
Mechanical Drawings Plan Basement Master Floor Plumbing Plan (P-101) Riser KB05Plumbing Calcs-100pc Calculations Plan Basement Foundation Master Plan (S-101) Structure Sections Basement Foundation & Schedule & Details ( S-201) Design Review Output

Drawings reference

N/A

N/A

Foundation Type Basement Grids (G,H & 4,3)

Column Base (Footings) Basement Grids (G,H & 4,3)

N/A

Location

N/A

N/A

Encasement for Drainage Pipe Under ground

Not shown

N/A

Shown without sizing

Shown, but height size was referred to PG (in which not found)

Should be indicated on all drawings

Pump Data

Flow = 6.31 L/s Head = 1.2 Bar

N/A

According to beginning of calculation 2x112.5 gpm it is required , but in end of calculation it is 2 x 100 gpm

2 pumps 7.1 L/s each Head 1.6 Bar IFC pumps are accepted

Pump discharge pipe size (Forced Flow)

100 mm

100 mm

Pit Size

1mx1m Depth is not available

N/A

1.5 x 1.5 x 1.26 m

1.6 x 1.6, m Depth is not available

The pit shown in the structural is general to be taken actual size from PG drawings

1.8x1.8x 2.65 m3

DVR 251011/109

P a g e | 164 / 292

Table M.147: SP-2 design data as per mechanical, structural drawings and calculations
Mechanical Drawings Plan Riser Calculations Plan Structure Sections Design Review Output

Sump pit Service

Mechanical Drawings Plan Parking drains Included Riser N/A

Calculations Plan N/A N/A

Structure Sections N/A Should be included in plans, riser and calculations Should be included in plans, riser and calculations Should be included in plans, riser and calculations Should be included in plans, riser and calculations

Elevator Pit

Not Included

N/A

N/A

N/A

N/A

Rain water

Included

N/A

N/A

N/A

N/A

Condensate drain

Not Included

N/A

N/A

N/A

N/A

3. Sample of calculation:Below is a sample calculation for SP-2 a. Flow Rate calculations: Based on fire sprinklers operation over the sump pit as per the following assumption v. Sprinkler fire hazard in parking area is ordinary-1 vi. Flow Density for Ordinary-1 hazard is 0.15 gpm/ft2 vii. Area of sprinkler operations is 1500 ft2 viii. The following table shows the calculations Table M.148: Sump Pump Flow Calculations Flow density (gpm/ft2) 0.15 Area of sprinkler operation (ft2) 1500 Total Pump flow (gpm) [L/s] 225 [14.2 L/s]

DVR 251011/109

P a g e | 165 / 292

b. Pump head calculations; The below table shows pump head calculations for SP-2 Table M.149: Pump Head Calculations Flow Rate L/s Static Head m Pipe Size mm Pipe Equivalent Length m Head Loss According to pipe size mm/m Fluid Velocity m/s Residual Pressure m Total Safety pressure Factor m. H2o (Bar) 16 (1.6)

7.2 9 100 30 10* 1* 4 10% Head loss data & fluid velocity figures with respect to pipe size and flow are as per ASHRAE Fundamentals 2005 chapter 36, Pipe Sizing Refer to Appendix A, Page A.6 c. Pump Selection: The below table shows pump selection and configuration: Table M.150: Pump selection Pump Type No. Total Pump Flow Each Pump Flow Pump Head Submersible waste water pump 2 Pumps (Duplex) L/s (GPM) L/s (GPM) Bar (m H2O) 14.2 (225) 7.1 (112.5) 2.0 (20)

Pump diameter* mm 405 Pump Height* mm 770 Pump Length* mm 795 Configuration Lead-lag *: Reference for pump data from Grundfos Pumps; Refer to Appendix A, Page A.16 IFC Pumps are accepted d. Pit sizing: The below table shows pit sizing calculations: Table M.151: Pit sizing Pump Flow Basin Diameter Draw Down volume Capacity of fluid per ft. Draw Down Height Depth of lowest level incoming piping Difference between inlet pipe and high water level Minimum depth at the bottom of the basin Sump pit Height GPM (L/s) in Gal. Gal/ft. ft. ft. in ft. ft. (m) 225 (14.2) 72 891 212 4.2 3 6.0 1.0 8.7 (2.65)

DVR 251011/109

P a g e | 166 / 292

Table M.151: Pit sizing Min. pit size should be 1.8 x 1.8x2.65 (8.6 m3) Procedure for sizing pit is described in Handbook of Mechanical Engineering Calculations; Part 3 Environmental Control; Section 15 Plumbing and Drainage for Buildings and Other Structures. Refer to Appendix A, Pages A.8, A.9, A.10 4. Comparison: The following table shows a comparison between IFC and Design Review Output Table M.152: Comparison between IFC and Design Review Output IFC IFC is using fire fighting demand in the calculation According to beginning of calculation 2x112.5 gpm it is required , bout in end of calculation it is 2 x 100 gpm 1.26 m Ramp rain water note connected to drainage net work According to ground floor (P110) it is free discharge, and not reflected and coordinated in site utilities plan (XP101) Not considered Not provided Design Review Output

Pump flow rate calculations

Flow in case of sprinkler operation = 0.15 x 1500 = 225 gpm, this value is divided into 2 pumps 112.5 gpm (7.1 L /s) each IFC pumps are accepted

Pit depth Ramp Rain Water

Minimum depth shall not be less than 2.65 m Shall be connected

Forced flow outlet discharge

Forced discharge flow shall be connected to the soil net work through brake manhole, in addition to that rain water should be connected to storm water system

Elevator Pit 2 Sand Trap 3

Should be considered in calculations to find the lowest waste incoming pipe connected to SP-2 Should be provided to block sand particles from entering and accumulating inside the pit

1: Refer to Appendix A, Page A.12 2: Refer to Appendix A, Page A.7 3: Refer to Appendix A, Page A.13

DVR 251011/109

P a g e | 167 / 292

III.

RECOMMENDATIONS:

Further to the design review study and analysis, and as per the above sample calculation for sump pits and gray water tanks for KB05 building, the following can be concluded: 1. Pit sizing: The level of lowest invert level incoming waste pipe is not taken into consideration when sizing the pit depth. Also, the size of duplex pumps should be given more attention in sizing the pit to verify if the current size fits for two submersible pumps. 2. The pit size is found to be insufficient with respect to the fixtures and drainage points connected to it. It is recommended to take the level of incoming waste pipes and the size of submersible pumps into consideration when sizing the pit.

DVR 251011/109

P a g e | 168 / 292

m. BUILDING ( KB06)
Underground piping, submersible pumps and pits and related calculations have been reviewed.

I. DESIGN PARAMETERS: The followings table shows the design parameters used in the IFC design documents and those extracted through the design review process Table M.153 : Design parameters Item Parking drain Fixtures Units AHU & FCU Fixtures Units Floor Drain Fixtures Units Slope of Drainage piping (100 & 150 mm Diameters) Rainfall intensity WC Flush flow rate Number of persons per m2 IFC Design Value Reference 21 UPC 2 UPC 2 UPC Not Indicated 75 mm/hr8 Not Indicated Not Indicated Not Indicated UPC Required Parameters Reference UPC2 UPC3 UPC3 IPC4 UPC5 UPC6

Value 8 2 2 1% 50 mm/hr 6.1 liter (1.6 gallon/flush) 14

Water consumption ratio per 5% shower Water consumption ratio per Not Plumbing Engineering 32% Indicated toilet flushing Servicing Design Water consumption ratio per Not Guide- The Institute of 20% Indicated Plumbing 20027 Laundry Water consumption ratio per Not 15% Indicated kitchen Water consumption ratio per Not 9% Indicated basin 1. IFC design indicates parking floor drain to have 2 FU. However, since pipe connection is 4 UPC calls for 8 FU to be used in calculations. 2. Refer to Appendix A, PageA.3 3. Refer to Appendix A, PageA.2 4. Refer to appendix A, Page A.11 5. Refer to Appendix A, Page A.5 6. Refer to Appendix A, Page A.1 7. Refer to Appendix A, Page A.4 8. Rainfall intensity used by the designer varies for different buildings. It is recommended to use 50 mm/hr

DVR 251011/109

P a g e | 169 / 292

II. SUMP PITS & SUBMERSIBLE PUMPS (SP-2): 1. Submersible pump-2 (SP-2) has been reviewed as an example for others in the same building. Results of this review indicate that same issues are found in other areas within the same building 2. IFC Design plans(Drainage), IFC calculations, IFC risers, IFC structural drawings and sections have been reviewed, the following table shows the results: Table M.154: SP-2 design data as per mechanical, structural IFC drawings and calculations
Mechanical Drawings Plan Riser 2nd Basement Master Floor Plumbing Plan (P-101) Calculations Plan 2nd Basement Foundation Master Plan (S-101) Structure Sections 2nd Basement Foundation & Schedule & Details ( S-201) Design Review Output

Drawings reference

N/A

KB06-Plumbing Calcs-100PC

Foundation Type Location Encasement for Drainage Pipe Under ground Pump Data Pump discharge pipe size (Forced Flow) Basement Grids (F & 4,3) N/A -

Column Base (Footings) Basement Grids (G,F & 4,3) Shown, but height size was referred to PG (in which not found) 2 pumps 7.1 L/s each Head 1.6 Bar

Not shown

N/A

N/A

Shown without sizing

2 Pumps Flow = 6.31 L/s each Head = 1.2 Bar

Not availabl e

2 Pumps Flow = 6.31 L/s each Head = 1.2 Bar

N/A

N/A

100 mm

100 mm

Pit Size

1mx1m Depth is not available

Not availabl e

1.5 x 1.5 x 1.26 m

1.6 x 1.6, m Depth is not available

The pit shown in the structural is general to be taken actual size from PG drawings

1.8 x 1.8x2.65 m3

Sump pit Service Parking drains Elevator Pit Rain water Condensate drain Included Not Included Not Included Included Not Included Not Included Not Included Not Included Not Included N/A Calculations are based on fire fighting demand Red: Not Acceptable, Orange: Partially, Green: Acceptable N/A N/A N/A N/A N/A N/A N/A Should be included in plans and riser Should be included Should be included Should be included in plans and riser

DVR 251011/109

P a g e | 170 / 292

3. Sample of calculation:Below is a sample calculation for SP-2 a. Flow Rate calculations: Based on fire sprinklers operation over the sump pit as per the following assumption i. Sprinkler fire hazard in parking area is ordinary-1 ii. Flow Density for Ordinary-1 hazard is 0.15 gpm/ft2 iii. Area of sprinkler operations is 1500 ft2 iv. The following table shows the calculations Table M.155: Sump Pump Flow Calculations Flow density (gpm/ft2) 0.15 Area of sprinkler operation (ft2) 1500 Total Pump flow (gpm) [L/s] 225 [14.2 L/s]

b. Pump head calculations; The below table shows pump head calculations for SP-2 Table M.156: Pump Head Calculations Flow Rate L/s Static Head m Pipe Size mm Pipe Equivalent Length m Head Loss According to pipe size mm/m Fluid Velocity m/s Residual Pressure m Safety Factor Total pressure m. H2o (Bar) 16 (1.6)

7.2 9 100 30 10* 1* 4 10% Head loss data & fluid velocity figures with respect to pipe size and flow are as per ASHRAE Fundamentals 2005 chapter 36, Pipe Sizing Refer to Appendix A, Page A.6 c. Pump Selection: The below table shows pump selection and configuration: Table M.157: Pump selection Pump Type No. Total Pump Flow Each Pump Flow Pump Head Submersible waste water pump 2 Pumps (Duplex) L/s (GPM) L/s (GPM) Bar (m H2O) 14.2 (225) 7.1 (112.5) 2.0 (20)

Pump diameter* mm 405 Pump Height* mm 770 Pump Length* mm 795 Configuration Lead-lag *: Reference for pump data from Grundfos Pumps; Refer to Appendix A, Page A.16

DVR 251011/109

P a g e | 171 / 292

Table M.157: Pump selection Pump Type IFC Pumps are accepted Submersible waste water pump

d. Pit sizing: The below table shows pit sizing calculations: Table M.158: Pit sizing Pump Flow GPM (L/s) in Gal. Gal/ft. ft. ft. 225 (14.2) 72 891 212 4.2 3

Basin Diameter Draw Down volume Capacity of fluid per ft. Draw Down Height Depth of lowest level incoming piping Difference between inlet pipe and high in 6.0 water level Minimum depth at the bottom of the ft. 1.0 basin Sump pit Height ft. (m) 8.7 (2.65) Min. pit size should be 1.8 x 1.8x2.65 (8.6 m3) Procedure for sizing pit is described in Handbook of Mechanical Engineering Calculations; Part 3 Environmental Control; Section 15 Plumbing and Drainage for Buildings and Other Structures. Refer to Appendix A, Pages A.8, A.9, A.10 4. Comparison: The following table shows a comparison between IFC and design review output

Table M.159: Comparison between IFC and design review output IFC IFC is using fire fighting demand in the calculation
According to beginning of calculation 2x112.5 gpm it is required , bout in end of calculation it is 2 x 100 gpm

Design Review Output

Pump flow rate calculations

Flow in case of sprinkler operation = 0.15 x 1500 = 225 gpm, this value is divided into 2 pumps 112.5 gpm (7.1 L /s) each IFC Pumps are accepted

Pit depth Forced flow outlet discharge

1.26 m According to ground floor (P110) it is free discharge, and not reflected and coordinated in site utilities plan (XP101)

Minimum depth shall not be less than 2.65 m Forced discharge flow shall be connected to the soil net work through brake manhole, in addition to that rain water should be connected to storm water system

DVR 251011/109

P a g e | 172 / 292

Table M.159: Comparison between IFC and design review output IFC Elevator Pit 2 Sand Trap 3 Not considered Not provided Design Review Output Should be considered in calculations to find the lowest waste incoming pipe connected to SP-2 Should be provided to block sand particles from entering and accumulating inside the pit

1. Refer to Appendix A, Page A.12 2. Refer to Appendix A, Page A.7 3. Refer to Appendix A, Page A.13 III. RECOMMENDATIONS:

Further to the design review study and analysis, and as per the above sample calculation for sump pits of KB06 building, the following can be concluded: 1. Pit sizing: The level of lowest invert level incoming waste pipe is not taken into consideration when sizing the pit depth. Also, the size of duplex pumps should be given more attention in sizing the pit to verify if the current size fits for two submersible pumps. 2. The pit size is found to be insufficient with respect to the fixtures and drainage points connected to it. It is recommended to take the level of incoming waste pipes and the size of submersible pumps into consideration when sizing the pit.

DVR 251011/109

P a g e | 173 / 292

2. HVAC (not applicable to this report) 3. Fire fighting (not applicable to this report)

DVR 251011/109

P a g e | 174 / 292

B. ELECTRICAL 1. Grounding & Lightning Protection

Below is the detailed analysis related to the lightning and grounding system considering the methodology specified above: a. For all buildings i. Design criteria and assumptions Calculations related to the lightning and grounding system were not provided to verify the system selection and conductors/cables sizing, Design Reviewer has performed full calculations to check the design. These detailed calculations can be found in Appendix B. In order to perform the detailed calculations we have defined the below design criteria, and made the below mentioned assumptions. 1. Design criteria: Design documents did not contain clear information regarding design criteria. However, specifications list a number of international standards that were used to extract the following criteria: Verified item Air terminal Height Spacing Lightning conductor main Size Spacing Bonding conductor Down conductor Size Size Spacing Size Length Ground ring electrode Lightning resistance Burial Design criteria NFPA 780 Item 4.6.2.1 NFPA 780 Item 4.8.1.2 NFPA 780 Table 4.1.1.1.1 & 2 NFPA 780 Item 4.9.8.1 & 2 NFPA 780 Table 4.1.1.1.1 & 2 NFPA 780 Table 4.1.1.1.1 & 2 NFPA 780 Item 4.9.10 NFPA 780 Item 4.13.2.1 NFPA 780 Item 4.13.2.3.1 NFPA 780 Item 4.13.4.1 BS 7430 BS EN 62305-3 Item 5.4.1 BS 7430 NFPA 780 Item 4.14 Table E.14 Remarks Refer to Appendix B for NFPA cut sheets Refer to Appendix B for NFPA cut sheets Refer to Appendix B for NFPA cut sheets Refer to Appendix B for NFPA cut sheets Refer to Appendix B for NFPA cut sheets Refer to Appendix B for NFPA cut sheets Refer to Appendix B for NFPA cut sheets Refer to Appendix B for NFPA cut sheets Refer to Appendix B for NFPA cut sheets Refer to Appendix B for NFPA cut sheets Refer to Appendix B for BS cut sheets Refer to Appendix B for BS cut sheets Refer to Appendix B for BS cut sheets Refer to Appendix B for NFPA cut sheets

Earth rod

system Calculation Value Size

Grounding conductor Common Grounding

DVR 251011/109

P a g e | 175 / 292

2.

Assumptions: Due to lack of information at this stage, Design Reviewer has assumed below mentioned values in order to finalize the calculations. These calculations shall be revised as per the actual values. Assumed value 100 .m 6% 9% 21kA 1s Remarks Final value is subject to actual site measurement Final value is subject to material selection Final value is subject to material selection As per specifications As per specifications

Item Soil resistivity Transformer per unit impedance Generator per unit reactance MV fault current MV fault duration

Table E.15 ii. Comments on drawings: 1. In detail E (GE-005), the min. burial depth for the bare copper conductor is mentioned as 300mm(see snap shot 1), while in the specifications the ground conductors shall be laid with slack and buried to a min. depth of 600mm below grade. However, as per NFPA 780 Item 4.13.4.1 the ground ring electrode encircling a structure shall be in direct contact with earth at a depth of not less than 460mm. Based on this the ground ring conductor shall be buried 600mm below raft foundation.

2. Down conductors as defined in details drawings are different from the layout, and different between each other as follow:

DVR 251011/109

P a g e | 176 / 292

a. In DWG GE-005 detail E, the down conductor is indicated as 70mm2 bare copper conductors. b. In DWG GE-006 detail E(see snap shot 2), the down conductor is indicated as 120mm2 bare copper conductors inside 38mm RSC conduit.

2.

Location of test links is not specified on the layout, however, detail E in DWG. GE-006 shows the test link coming with the down conductors that terminates to ground test will (earth inspection pit), based on this the layouts were checked for the location of test links.

iii.

Comments on specifications: 1. Earth rods are shown on general drawings to be 3000mm length and 20mm diameter, while it is specified as 3000mm length and 19mm diameter in the specifications. 2. The specifications indicate the size of main and secondary lightning conductors as 12AWG & 14AWG respectively, which doesnt comply with NFPA 780 Table 4.1.1.1.2. 3. As per the specifications conduits larger than 25mm shall not be installed inside structural masonry or slab, while in DWG. GE-006 detail E, a 38mm RSC conduit is embedded in concrete.

DVR 251011/109

P a g e | 177 / 292

b. BUILDING (KB 01-02) i. Comments on drawings 1. General comments a. Drawings show twenty two earth inspection pits and twenty two test links, located in the fourth basement. b. Waterproofing is required for the earth pits through earth rods seals because of the high water table level in the project area. c. Grounding and bonding for telecommunication does not comply with TIA 706 as specified in the specifications. d. All grounding media shall be interconnected to provide a common ground potential, this interconnection shall include lightning protection, electric service, telephone and antenna system grounds, as well as underground metallic piping systems. e. A transient earth clamp shall be used for clamping different grounding systems to prevent transient disturbances; this requirement shall be taken into consideration when providing communication and electrical grounding networks. f. The following table summarize the calculation/design outputs (refer to Appendix B for detailed calculations) As per verification calculations 6.26 32.31 15.17 126.57 mm2 244.19 mm2 244.19 mm2 101.75 mm2 Min. Result Standard/Specification requirements 10 Okay 3 5 126.57 mm2 244.19 mm2 244.19 mm2 101.75 mm2 58 mm2 254 mm 58 mm2 Not Okay Not Okay Okay Okay Okay Okay Okay Not Okay Not Okay Remarks

Item

As per IFC documents N.P N.P N.P N.P 185 mm2 185 mm2 150 mm2 120 mm2 600 mm 25X3 mm 25X3 mm

Lightning system resistance () Telecom. Grounding resistance () RMU grounding resistance () Grounding conductor for RMU Grounding conductor for transformer Grounding conductor for LV switchgear Grounding conductor for generator Grounding ring electrode Air terminal height Lightning main conductor size Down conductor size

58 mm2 Table E.16

2.

DWG. E-346 a. Air terminals spacing does not comply with NFPA 780.

DVR 251011/109

P a g e | 178 / 292

b. The spacing between the lightning main conductors is in compliance with NFPA 780. c. Bonding conductor size is not shown, hence, cannot be verified. d. Spacing between down conductors does not comply with the requirements of NFPA 780. 3. DWG. E306 to DWG. E-336 a. In these drawings it is mentioned that the electrical rooms grounding is connected to a separate grounding for electrical system, while this is not achieved in DWG. E-301.

ii.

Recommendations 1. To have bare copper down conductor exothermally welded with the reinforced bars in order to increase the parallel paths for the current and to reduce the overall resistance of the system. To use the 20mm diameter earth rod as per the drawings in order to have a lower rod resistance. To relocate the earth pits to ground floor level for ease of installation, coordination, reduction of system cost and ease of location coordination, in addition to achieve consistency between the buildings (8 buildings out of 13 do have the earth network at ground floor level). The separation distance between the rods in the triangular configuration is considered to be 2000mm as mentioned in DWG. GE005 detail D. However it is recommended to increase the separation distance in order to reduce the resistance.

2. 3.

4.

DVR 251011/109

P a g e | 179 / 292

c. BUILDING (KB-03) i. Comments on drawings 1. General Comments: a. Drawings show six earth inspection pits and six test links, located in the fourth basement floor, one of them in the mechanical room (if this pit to be kept in the mechanical room, then it shall be coordinated with the mechanical equipments). b. As per NFPA 780 the ground rods shall extend vertically not less than 3m in to the earth, and since the raft foundation depth is 1.2m as per the structural drawings, these earth pits needs to be coordinated with the structural engineer and needs to be reflected on the structural drawings. c. Waterproofing is required for the earth pits through earth rods seals because of the high water table level in the project area. d. Grounding and bonding for telecommunication as per TIA 706 and as specified in the specifications is not provided. e. Grounding bars in electrical and mechanical rooms for the purpose of grounding electrical/mechanical equipments is not provided. f. All grounding media shall be interconnected to provide a common ground potential, this interconnection shall include lightning protection, electric service, telephone and antenna system grounds, as well as underground metallic piping systems. g. A transient earth clamp shall be used for clamping different grounding systems to prevent transient disturbances; this requirement shall be taken into consideration when providing communication and electrical grounding networks. h. The following table summarize the calculation/design outputs (refer to Appendix B for detailed calculations) As per verification calculations 6.26 15.17 Min. Result Standard/Specification requirements 10 Okay 5 Not Okay Remarks

Item

As per IFC documents N.P N.P

Lightning system resistance () RMU, transformer, generator & LV grounding resistance () Grounding conductor for RMU Grounding conductor for transformer Grounding conductor for LV switchgear Grounding conductor for generator Grounding ring electrode Air terminal height Lightning main

N.P 185 mm2 185 mm2 120 mm2 95 mm2 600 mm 25X3 mm

126.57mm2 244.19mm2 244.19mm2 25.43 mm2 -

126.57 mm2 244.19 mm2 244.19 mm2 25.43 mm2 58 mm2 254 mm 58 mm2 Not Okay Not Okay Okay Okay Okay Okay

DVR 251011/109

P a g e | 180 / 292

Item

As per IFC documents

As per verification calculations -

Min. Result Standard/Specification requirements Okay

Remarks

conductor size Down conductor size

25X3 mm

58 mm2 Table E.17

2.

DWG. E-307 & E-310 a. Air terminals are not shown on the layouts; hence, the spacing between them cant be verified. b. The spacing between the lightning main conductors does not comply with NFPA 780. c. Equipments located at roof shall be bonded to the lightning system as required by NFPA 780. d. Spacing between down conductors is in compliance with NFPA 780. DWG. E-301 a. Down conductors locations as shown on roof floor layout, does not match with the down conductors location as shown on the basement layout. b. Not all down conductors shown on roof are terminated to a ground terminal as required by NFPA 780 Item 4.13.1.1.

3.

ii.

Recommendations 1. 2. Same recommendations as for building KB 01-02 To relocate the earth pit located in the mechanical room to be outside, for ease of maintenance and coordination.

DVR 251011/109

P a g e | 181 / 292

d. BUILDING (RD-03) i. Comments on drawings 1. General Comments: a. Drawings show fifteen test links located in the ground floor. Final location of these pits and test links needs to be coordinated with the Architect since the ground floor occupancy is tenancy. b. Grounding and bonding for telecommunication as per TIA 706 and as specified in the specifications is not provided. c. Grounding bars in Generator room, transformer room, LV room, electrical and mechanical rooms for the purpose of grounding electrical/mechanical equipments is not provided. d. A transient earth clamp shall be used for clamping different grounding systems to prevent transient disturbances; this requirement shall be taken into consideration when providing communication and electrical grounding networks. e. The following table summarize the calculation/design outputs (refer to Appendix B for detailed calculations) As per verification calculations 7.44 126.57mm2 244.19mm2 Min. Result Standard/Specification requirements 10 Okay 126.57 mm2 244.19 mm2 244.19 mm2 40.70 mm2 58 mm2 254 mm 58 mm2 Okay Okay Okay Okay Okay Remarks

Item

As per IFC documents N.P N.P N.P

Lightning system resistance () Grounding conductor for RMU Grounding conductor for transformer Grounding conductor for LV switchgear Grounding conductor for generator Grounding ring electrode Air terminal height Lightning main conductor size Down conductor size

2X300mm2 244.19mm2 N.P 120 mm2 600 mm 25X3mm N.P 40.70 mm2 -

58 mm2 Table E.18

2.

DWG. E-300 a. Air terminals are not shown on the layout; hence, the spacing between them cannot be verified. b. The spacing between the lightning main conductors is in compliance with NFPA 780. c. Equipments located at roof shall be bonded to the lightning system as required by NFPA 780. d. Spacing between down conductors is in compliance with NFPA 780.

DVR 251011/109

P a g e | 182 / 292

e.

Drawings show fifteen earth inspection pits located in the ground floor, these earth pits needs to be coordinated with the Architect / landscape to make sure that we have enough space in the plot limit and there is no conflict between the earth pits location and the landscape.

ii.

Recommendations 1. Same recommendations as for building KB 01-02 (item 1and 2)

DVR 251011/109

P a g e | 183 / 292

e. BUILDING (RD-04) i. Comments on drawings 1. General Comments: a. Drawings show thirteen test links located in the ground floor. Final location of these pits and test links needs to be coordinated with the Architect since the ground floor occupancy is tenancy. b. Grounding and bonding for telecommunication as per TIA 706 and as specified in the specifications is not provided. c. Grounding bars in Generator room, transformer room, LV room, electrical and mechanical rooms for the purpose of grounding electrical/mechanical equipments is not provided. d. A transient earth clamp shall be used for clamping different grounding systems to prevent transient disturbances; this requirement shall be taken into consideration when providing communication and electrical grounding networks. e. The following table summarize the calculation/design outputs (refer to Appendix B for detailed calculations) Item As per IFC documents N.P N.P N.P 2X300mm2 N.P 120 mm2 600 mm 25X3 mm N.P As per verification calculations 7.44 126.57mm2 305.24mm2 305.24mm2 45.79 mm2 Min. Result Standard/Specification requirements 10 Okay 126.57 mm2 305.24mm2 305.24mm2 45.79 mm2 58 mm2 254 mm 58 mm2 58 mm2 Table E.19 Okay Okay Okay Okay Okay Remarks

Lightning system resistance () Grounding conductor for RMU Grounding conductor for transformer Grounding conductor for LV switchgear Grounding conductor for generator Grounding ring electrode Air terminal height Lightning main conductor size Down conductor size

2.

DWG. E-300 a. Air terminals are not shown on the layout; hence, the spacing between them cannot be verified. b. The spacing between the lightning main conductors is in compliance with NFPA 780. c. Equipments located at roof shall be bonded to the lightning system as required by NFPA 780. d. Spacing between down conductors is in compliance with the requirements of NFPA 780.

DVR 251011/109

P a g e | 184 / 292

e.

Drawings show earth inspection pits located in the ground floor, these earth pits needs to be coordinated with the Architect / landscape to make sure that we have enough space in the plot limit and there is no conflict between the earth pits location and the landscape.

ii.

Recommendations

1.

Same recommendations as for building KB 01-02 (item 1 and 2)

DVR 251011/109

P a g e | 185 / 292

f. BUILDING (WH 01-04)

i.

Comments on drawings 1. General Comments: a. Drawings show four earth inspection pits and four test links, three of them are located in mechanical rooms and one located in an electrical room. Final location of these pits and test links needs to be coordinated with the mechanical/electrical equipments inside the rooms. b. As per NFPA 780 Item 4.13.2.3.1 the ground rods shall extend vertically not less than 3m in to the earth, and since the raft foundation depth is 1.3m as per the structural drawings, these earth pits needs to be coordinated with the structural engineer and needs to be reflected on the structural drawings. c. Waterproofing is required for the earth pits through earth rods seals because of the high water table level in the project area. d. Grounding and bonding for telecommunication as per TIA 706 and as specified in the specifications is not provided. e. Grounding bars in electrical and mechanical rooms for the purpose of grounding electrical/mechanical equipments is not provided. f. All grounding media shall be interconnected to provide a common ground potential, this interconnection shall include lightning protection, electric service, telephone and antenna system grounds, as well as underground metallic piping systems. g. A transient earth clamp shall be used for clamping different grounding systems to prevent transient disturbances; this requirement shall be taken into consideration when providing communication and electrical grounding networks. h. The following table summarize the calculation/design outputs (refer to Appendix B for detailed calculations) As per verification calculations 6.22 15.17 Min. Result Standard/Specification requirements 10 Okay 5 Not Okay Remarks

Item

As per IFC documents N.P N.P

Lightning system resistance () RMU, transformer, generator & LV grounding resistance () Grounding conductor for RMU Grounding conductor for transformer Grounding conductor for LV switchgear Grounding conductor for generator

N.P 630 mm2 630 mm2 120 mm2

126.57mm2 244.19mm2 244.19mm2 101.75mm2

126.57 mm2 244.19 mm2 244.19 mm2 101.75mm2 Okay Okay Okay

DVR 251011/109

P a g e | 186 / 292

Item

As per IFC documents 120 mm2 600 mm 25X3 mm 25X3 mm 1.5X12.5mm

Grounding ring electrode Air terminal height Lightning main conductor size Down conductor size Bonding conductor size

As per verification calculations -

Min. Standard/Specification requirements 58 mm2 254 mm 58 mm2

Result

Remarks

Okay Okay Okay Okay Okay

58 mm2 1.3X12.7mm Table E.20

2.

DWG. E-316 & E-321 a. Air terminals are not shown on the layouts; hence, the spacing between them cant be verified. b. The spacing between the lightning main conductors is in compliance with NFPA 780. c. Spacing between down conductors is in compliance with the requirements of NFPA 780. DWG. E-301 a. Down conductors locations as shown on roof floor layout, does not match with the down conductors location as shown on the 4th basement layout. b. Not all down conductors shown on roof are terminated to a ground terminal as required by NFPA 780 Item 4.13.1.1.

3.

ii.

Recommendations 1. 2. Same recommendations as for building KB 01-02 To relocate the earth inspection pits and test links to be outside the mechanical/electrical rooms for ease of maintenance, inspection and to avoid miss of coordination with the mechanical/electrical equipments.

DVR 251011/109

P a g e | 187 / 292

g. BUILDING (WH-05)

i.

Comments on drawings 1. General Comments: a. Drawings show two earth inspection pits and two test links, located in the fourth basement. b. As per NFPA 780 Item 4.13.2.3.1 the ground rods shall extend vertically not less than 3m in to the earth, and since the raft foundation depth is 0.9m as per the structural drawings, these earth pits needs to be coordinated with the structural engineer and needs to be reflected on the structural drawings. c. Waterproofing is required for the earth pits through earth rods seals because of the high water table level in the project area. d. Grounding and bonding for telecommunication as per TIA 706 and as specified in the specifications is not provided. e. Grounding bars in electrical and mechanical rooms for the purpose of grounding electrical/mechanical equipments is not provided. f. All grounding media shall be interconnected to provide a common ground potential, this interconnection shall include lightning protection, electric service, telephone and antenna system grounds, as well as underground metallic piping systems. g. A transient earth clamp shall be used for clamping different grounding systems to prevent transient disturbances; this requirement shall be taken into consideration when providing communication and electrical grounding networks. h. The following table summarize the calculation/design outputs (refer to Appendix B for detailed calculations) As per verification calculations 9.17 15.17 Min. Result Standard/Specification requirements 10 Okay 5 Not Okay Remarks

Item

As per IFC documents N.P N.P

Lightning system resistance () RMU, transformer, generator & LV grounding resistance () Grounding conductor for RMU Grounding conductor for transformer Grounding conductor for LV switchgear Grounding conductor for generator Grounding ring electrode Air terminal height Lightning main conductor size

N.P 630 mm2 630 mm2 120 mm2 95mm2 600 mm 25X3 mm

126.57mm2 152.61mm2 152.61mm2 35.61mm2 -

126.57 mm2 152.61 mm2 152.61 mm2 35.61mm2 58 mm2 254 mm 58 mm2 Okay Okay Okay Okay Okay Okay

DVR 251011/109

P a g e | 188 / 292

Item

As per IFC documents

Down conductor size Bonding conductor size

As per Min. Result verification Standard/Specification calculations requirements 25X3 mm 58 mm2 Okay 1.5X12.5mm 1.3X12.7mm Okay Table E.21

Remarks

2.

DWG. E-304 & E-305 a. Air terminals are not shown on the layouts; hence, the spacing between them cant be verified. b. The spacing between the lightning main conductors is in compliance with NFPA 780. c. Spacing between down conductors is in compliance with the requirements of NFPA 780. DWG. E-301: a. Down conductors locations as shown on roof floor layout, does not match with the down conductors location as shown on the 4th basement layout.

3.

ii.

Recommendations 1. Same recommendations as for building KB 01-02

DVR 251011/109

P a g e | 189 / 292

h. BUILDING (WH-06)

i.

Comments on drawings 1. General Comments: a. Drawings show two earth inspection pits and two test links, located in the basement floor. b. As per NFPA 780 Item 4.13.2.3.1 the ground rods shall extend vertically not less than 3m in to the earth, and since the raft foundation depth is 0.7m as per the structural drawings, these earth pits needs to be coordinated with the structural engineer and needs to be reflected on the structural drawings. c. Waterproofing is required for the earth pits through earth rods seals because of the high water table level in the project area. d. Grounding bars in electrical and mechanical rooms for the purpose of grounding electrical/mechanical equipments is not provided. e. All grounding media shall be interconnected to provide a common ground potential, this interconnection shall include lightning protection, electric service, telephone and antenna system grounds, as well as underground metallic piping systems. f. A transient earth clamp shall be used for clamping different grounding systems to prevent transient disturbances; this requirement shall be taken into consideration when providing communication and electrical grounding networks. g. The following table summarize the calculation/design outputs (refer to Appendix B for detailed calculations)

Item

As per IFC documents N.P N.P

Lightning system resistance () RMU, transformer, generator & LV grounding resistance () Telecom. Grounding resistance () Grounding conductor for RMU Grounding conductor for transformer Grounding conductor for LV switchgear Grounding conductor for generator Grounding ring electrode Air terminal height Lightning main conductor

As per verification calculations 9.17 15.17

Min. Result Standard/Specification requirements 10 Okay 5 Not Okay Not Okay Not Okay Okay Okay Okay Okay Okay Okay

Remarks

N.P 120mm2 300 mm2 300 mm2 120 mm2 95mm2 600 mm 25X3 mm

32.31 126.57mm2 244.19mm2 244.19mm2 40.70mm2 -

3 126.57 mm2 244.19mm2 244.19mm2 40.70mm2 58 mm2 254 mm 58 mm2

DVR 251011/109

P a g e | 190 / 292

Item

As per IFC documents

As per verification calculations

Min. Result Standard/Specification requirements Okay Okay

Remarks

size Down conductor size Bonding conductor size

25X3 mm 1.5X12.5mm

58 mm2 1.3X12.7mm Table E.22

2.

DWG. E-302 a. Air terminals are not shown on the layouts; hence, the spacing between them cant be verified. b. The spacing between the lightning main conductors is in compliance with NFPA 780. c. Spacing between down conductors is in compliance with the requirements of NFPA 780. DWG. E-301 a. Down conductors locations as shown on roof floor layout, does not match with the down conductors location as shown on the basement layout. b. Not all down conductors shown on roof are terminated to a ground terminal as required by NFPA 780 Item 4.13.1.1.

3.

ii.

Recommendations 1. Same recommendations as for building KB 01-02

DVR 251011/109

P a g e | 191 / 292

i. BUILDING (IT-01)

i.

Comments on drawings 1. General Comments: a. Drawings show eight test links located in the ground floor. Final location of these pits and test links needs to be coordinated with the Architect since the ground floor occupancy is tenancy. b. Grounding and bonding for telecommunication as per TIA 706 and as specified in the specifications is not provided. c. A transient earth clamp shall be used for clamping different grounding systems to prevent transient disturbances; this requirement shall be taken into consideration when providing communication and electrical grounding networks. As per verification calculations 7.68 126.57mm2 305.24mm2 305.24mm2 76.72mm2 Min. Result Standard/Specification requirements 10 Okay 126.57 mm2 305.24mm2 305.24mm2 76.72mm2 58 mm2 Not Okay Okay Okay Okay Okay Item 4.a below to be considered Remarks

Item

As per IFC documents N.P N.P N.P N.P N.P 120mm2

Lightning system resistance () Grounding conductor for RMU Grounding conductor for transformer Grounding conductor for LV switchgear Grounding conductor for generator Grounding ring electrode

Air terminal height Lightning main conductor size Down conductor size

600 mm 95 mm2 70 mm2

254 mm 58 mm2

Okay Okay Okay

58 mm2 Table E.23

2.

DWG. E-313: a. Air terminals spacing is in compliance with NFPA 780. b. The spacing between the lightning main conductors is in compliance with NFPA 780. c. Equipments located at roof shall be bonded to the lightning system as required by NFPA 780. d. Spacing between down conductors does not comply with the requirements of NFPA 780.

DVR 251011/109

P a g e | 192 / 292

3.

DWG. E-307: a. Down conductors locations as shown on roof floor layout, does not match with the down conductors location as shown on the ground floor layout. b. Not all down conductors shown on roof are terminated to a ground terminal as required by NFPA 780 Item 4.13.1.1. c. Drawings show eight earth inspection pits located in the ground floor, these earth pits needs to be coordinated with the Architect / landscape to make sure that we have enough space in the plot limit and there is no conflict between the earth pits location and the landscape. DWG. E-304: a. Grounding bars in communication rooms, MV room, Transformer, LV, Generator, electrical and mechanical rooms are connected directly to the lightning system grounding network without having their own grounding pits, if this configuration to be kept, then the main ring conductor shall be resized to suit the maximum required grounding conductor which is 305.24 as per BS 7430 (refer to Appendix B for detailed calculations).

4.

ii.

Recommendations 1. Same recommendations as for building KB 01-02 (item 1 and 2)

DVR 251011/109

P a g e | 193 / 292

j. BUILDING (IT-02)

i.

Comments on drawings 1. General Comments: a. Drawings show six test links located in the ground floor. Final location of these pits and test links needs to be coordinated with the Architect since the ground floor occupancy is tenancy. b. Grounding and bonding for telecommunication as per NEC, TIA 706 and as specified in the specifications is not provided. c. A transient earth clamp shall be used for clamping different grounding systems to prevent transient disturbances; this requirement shall be taken into consideration when providing communication and electrical grounding networks. As per verification calculations 7.76 126.57mm2 305.24mm2 305.24mm2 76.72mm2 Min. Result Standard/Specification requirements 10 Okay 126.57 mm2 305.24mm2 305.24mm2 76.72mm2 58 mm2 Not Okay Okay Okay Okay Okay Item 5.a below to be considered Remarks

Item

As per IFC documents N.P N.P N.P N.P N.P 95mm2

Lightning system resistance () Grounding conductor for RMU Grounding conductor for transformer Grounding conductor for LV switchgear Grounding conductor for generator Grounding ring electrode

Air terminal height Lightning main conductor size Down conductor size

600 mm 95 mm2 70 mm2

254 mm 58 mm2

Okay Okay Okay

58 mm2 Table E.24

2.

DWG. E-313: a. Air terminals spacing is in compliance with NFPA 780. b. The spacing between the lightning main conductors is in compliance with NFPA 780. c. Spacing between down conductors does not comply with the requirements of NFPA 780. DWGs. E-310, E-311 & E-312 a. There is no grounding bar in the communications rooms as required by TIA 706 and specified in the specification.

3.

DVR 251011/109

P a g e | 194 / 292

4.

DWG. E-307: a. Down conductors locations as shown on roof floor layout, does not match with the down conductors location as shown on the ground floor layout. b. Not all down conductors shown on roof are terminated to a ground terminal as required by NFPA 780 Item 4.13.1.1. c. Drawings show six earth inspection pits located in the ground floor, these earth pits needs to be coordinated with the Architect / landscape to make sure that we have enough space in the plot limit and there is no conflict between the earth pits location and the landscape. DWG. E-304: a. Grounding bars in communication rooms, MV room, Transformer, LV, Generator, electrical and mechanical rooms are connected directly to the lightning system grounding network without having their own grounding pits, if this configuration to be kept, then the main ring conductor shall be resized to suit the maximum required grounding conductor which is 305.24 as per BS 7430 (Refer to Appendix B for detailed calculations).

5.

ii.

Recommendations 1. Same recommendations as for building KB 01-02 (item 1 and 2)

DVR 251011/109

P a g e | 195 / 292

k. BUILDING (IT-03)

i.

Comments on drawings 1. General Comments: a. Drawings show eight test links located in the ground floor. Final location of these pits and test links needs to be coordinated with the Architect since the ground floor occupancy is tenancy. b. Grounding and bonding for telecommunication as per TIA 706 and as specified in the specifications is not provided. c. A transient earth clamp shall be used for clamping different grounding systems to prevent transient disturbances; this requirement shall be taken into consideration when providing communication and electrical grounding networks. As per verification calculations 6.36 126.57mm2 381.54mm2 381.54mm2 76.72mm2 Min. Result Standard/Specification requirements 10 Okay 126.57 mm2 381.54mm2 381.54mm2 76.72mm2 58 mm2 Not Okay Okay Okay Okay Okay Item 4.a below to be considered Remarks

Item

As per IFC documents N.P N.P N.P N.P N.P 120mm2

Lightning system resistance () Grounding conductor for RMU Grounding conductor for transformer Grounding conductor for LV switchgear Grounding conductor for generator Grounding ring electrode

Air terminal height Lightning main conductor size Down conductor size

600 mm 95 mm2 70 mm2

254 mm 58 mm2

Okay Okay Okay

58 mm2 Table E.25

2.

DWG. E-319: a. Air terminals spacing is in compliance with NFPA 780. b. The spacing between the lightning main conductors is in compliance with NFPA 780. c. Equipments located at roof shall be bonded to the lightning system as required by NFPA 780. d. Spacing between down conductors is in compliance with the requirements of NFPA 780.

DVR 251011/109

P a g e | 196 / 292

3.

DWG. E-307: a. Down conductors locations as shown on roof floor layout, does not match with the down conductors location as shown on the ground floor layout. b. Not all down conductors shown on roof are terminated to a ground terminal as required by NFPA 780 Item 4.13.1.1. c. Drawings show eight earth inspection pits located in the ground floor, these earth pits needs to be coordinated with the Architect / landscape to make sure that we have enough space in the plot limit and there is no conflict between the earth pits location and the landscape. DWG. E-304: a. Grounding bars in communication rooms, MV room, Transformer, LV, Generator, electrical and mechanical rooms are connected directly to the lightning system grounding network without having their own grounding pits, if this configuration to be kept, then the main ring conductor shall be resized to suit the maximum required grounding conductor which is 381.54 as per BS 7430 (refer to Appendix B for detailed calculations).

4.

ii.

Recommendations 1. Same recommendations as for building KB 01-02 (item 1 and 2)

DVR 251011/109

P a g e | 197 / 292

l. BUILDING (KB-04)

i.

Comments on drawings 1. General Comments: a. Drawings show six test links located in the ground floor. Final location of these pits and test links needs to be coordinated with the Architect since the ground floor occupancy is tenancy. b. Provided grounding and bonding for telecommunication is verified, and does not comply with TIA 706 as specified in the specifications. c. All grounding media shall be interconnected to provide a common ground potential, this interconnection shall include lightning protection, electric service, telephone and antenna system grounds, as well as underground metallic piping systems. d. A transient earth clamp shall be used for clamping different grounding systems to prevent transient disturbances; this requirement shall be taken into consideration when providing communication and electrical grounding networks. As per verification calculations 6.42 15.17 Min. Result Standard/Specification requirements 10 Okay 5 Not Okay Not Okay Not Okay Okay Okay Okay Okay Okay Okay Okay Okay Remarks

Item

As per IFC documents N.P N.P

Lightning system resistance () RMU, transformer, generator & LV grounding resistance () Telecom. Grounding resistance () Grounding conductor for RMU Grounding conductor for transformer Grounding conductor for LV switchgear Grounding conductor for generator Grounding ring electrode Air terminal height Lightning main conductor size Down conductor size Bonding conductor size

N.P N.P N.P N.P N.P 120mm2 600 mm 95 mm2 70 mm2 1.5X12.5mm

15.17 126.57mm2 244.19mm2 244.19mm2 50.87mm2 -

3 126.57 mm2 244.19mm2 244.19mm2 50.87mm2 29 mm2 254 mm 29 mm2

29 mm2 1.3X12.7mm Table E.26

2.

DWG. E-310 a. Air terminals spacing is in compliance with NFPA 780. b. The spacing between the lightning main conductors is in compliance with NFPA 780.

DVR 251011/109

P a g e | 198 / 292

c.

Spacing between down conductors does not comply with the requirements of NFPA 780.

3.

DWG. E-304 a. Down conductors locations as shown on roof floor layout, does not match with the down conductors location as shown on the ground floor layout. b. Not all down conductors shown on roof are terminated to a ground terminal as required by NFPA 780 Item 4.13.1.1. c. Drawings show six earth inspection pits located in the ground floor, these earth pits needs to be coordinated with the Architect / landscape to make sure that we have enough space in the plot limit and there is no conflict between the earth pits location and the landscape. DWG. E-301 a. Grounding bars in communication rooms, MV room, Transformer room, LV room and Generator room are connected directly to the lightning system grounding network before being connected to their dedicated grounding pits located at ground floor. However, these grounding bars shall be connected to their own grounding pits, and then equipotentially bonded with the lightning grounding network through an earth transient clamp to achieve the common grounding as per NFPA 780.

4.

ii.

Recommendations 1. Same recommendations as for building KB 01-02 (item 1 and 2)

DVR 251011/109

P a g e | 199 / 292

m. BUILDING (KB-05)

i.

Comments on drawings 1. General Comments: a. Drawings show seven test links located in the ground floor. Final location of these pits and test links needs to be coordinated with the Architect since the ground floor occupancy is tenancy. b. Grounding and bonding for telecommunication as per TIA 706 and as specified in the specifications is not provided. c. A transient earth clamp shall be used for clamping different grounding systems to prevent transient disturbances; this requirement shall be taken into consideration when providing communication and electrical grounding networks. As per verification calculations 6.36 126.57mm2 244.19mm2 244.19mm2 39.68mm2 Min. Result Standard/Specification requirements 10 Okay 126.57 mm2 244.19mm2 244.19mm2 39.68mm2 29 mm2 Not Okay Okay Okay Okay Okay Item 5.a below to be considered Remarks

Item

As per IFC documents N.P N.P N.P N.P N.P 120mm2

Lightning system resistance () Grounding conductor for RMU Grounding conductor for transformer Grounding conductor for LV switchgear Grounding conductor for generator Grounding ring electrode

Air terminal height Lightning main conductor size Down conductor size

600 mm 95 mm2 70 mm2

254 mm 29 mm2

Okay Okay Okay

29 mm2 Table E.27

2.

DWG. E-310: a. Air terminals spacing is in compliance with NFPA 780. b. The spacing between the lightning main conductors does not comply with NFPA 780. c. Equipments located at roof shall be bonded to the lightning system as required by NFPA 780. d. Spacing between down conductors is in compliance with the requirements of NFPA 780.

DVR 251011/109

P a g e | 200 / 292

3. DWG. E-307: a. A grounding bar is provided in the garbage room, while there is no grounding bar in the communication room, the grounding bar shall be relocated in the communication room. 4. DWG. E-304: a. Drawings show seven earth inspection pits located in the ground floor, these earth pits needs to be coordinated with the Architect / landscape to make sure that we have enough space in the plot limit and there is no conflict between the earth pits location and the landscape. 5. DWG. E-301: a. Grounding bars in communication rooms, MV room, Transformer room, LV room, Generator room, electrical and mechanical rooms are connected directly to the lightning system grounding network without having their own grounding pits, if this configuration to be kept, then the main ring conductor shall be resized to suit the maximum required grounding conductor which is 244.19 as per BS 7430 (Refer to Appendix B for detailed calculations).

ii.

Recommendations 1. Same recommendations as for building KB 01-02 (item 1 and 2)

DVR 251011/109

P a g e | 201 / 292

n. BUILDING (KB-06)

i.

Comments on drawings 1. General Comments: a. Drawings show six test links located in the ground floor. Final location of these pits and test links needs to be coordinated with the Architect since the ground floor occupancy is tenancy. b. Grounding and bonding for telecommunication as per TIA 706 and as specified in the specifications is not provided. c. A transient earth clamp shall be used for clamping different grounding systems to prevent transient disturbances; this requirement shall be taken into consideration when providing communication and electrical grounding networks. As per verification calculations 6.36 126.57mm2 305.24mm2 305.24mm2 61.05mm2 Min. Result Standard/Specification requirements 10 Okay 126.57 mm2 305.24mm2 305.24mm2 61.05mm2 29 mm2 Not Okay Okay Okay Okay Okay Item 4.a below to be considered Remarks

Item

As per IFC documents N.P N.P N.P N.P N.P 95mm2

Lightning system resistance () Grounding conductor for RMU Grounding conductor for transformer Grounding conductor for LV switchgear Grounding conductor for generator Grounding ring electrode

Air terminal height Lightning main conductor size Down conductor size

600 mm 95 mm2 70 mm2

254 mm 29 mm2

Okay Okay Okay

29 mm2 Table E.28

2.

DWG. E-310: a. Air terminals spacing is in compliance with NFPA 780. b. The spacing between the lightning main conductors is in compliance with NFPA 780. c. Equipments located at roof shall be bonded to the lightning system as required by NFPA 780. d. Spacing between down conductors is in compliance with the requirements of NFPA 780.

DVR 251011/109

P a g e | 202 / 292

3.

DWG. E-307: a. Down conductors locations as shown on roof floor layout, does not match with the down conductors location as shown on the ground floor layout. b. Not all down conductors shown on roof are terminated to a ground terminal as required by NFPA 780 Item 4.13.1.1. c. Drawings show six earth inspection pits located in the ground floor, these earth pits needs to be coordinated with the Architect / landscape to make sure that we have enough space in the plot limit and there is no conflict between the earth pits location and the landscape. DWG. E-304: a. Grounding bars in communication rooms, MV room, Transformer room, LV room, Generator room, electrical and mechanical rooms are connected directly to the lightning system grounding network without having their own grounding pits, if this configuration to be kept, then the main ring conductor shall be resized to suit the maximum required grounding conductor which is 305.24mm2 as per BS 7430 (refer to Appendix B for detailed calculations).

4.

ii.

Recommendations 1. Same recommendations as for building KB 01-02 (item 1 and 2)

2. 3. 4. 5.

Normal & Emergency Lighting (not applicable to this report) Power & Low Voltage Distribution (not applicable to this report) IT Network (not applicable to this report) fire alarm & detection (not applicable to this report)

DVR 251011/109

P a g e | 203 / 292

V.

REFERENCE STANDARDS
A. Mechanical 1. Drainage System a. UPC: Uniform Plumbing Code b. IPC- International Plumbing Code c. NPC: National Plumbing Code d. PDI: Plumbing & Drainage Institute e. Plumbing Engineering Service Design Guide- The Institute of Plumbing f. Handbook of Mechanical Engineering Calculations; Part 3 Environmental Control; Section 15 Plumbing and Drainage for Buildings and Other Structures. 2. Water System a. UPC- Uniform Plumbing Code. b. ASHRAE Fundamentals, chapter 36, Pipe Sizing. c. NPC-National Plumbing Code. d. PDI: Plumbing & Drainage Institute. e. Plumbing Engineering Service Design Guide- The Institute of Plumbing. 3. HVAC System a. ASHRAE: American Society of Heating, Refrigerating and Airconditioning Engineers. b. SMACNA: Sheet Metal and Air Conditioning Contractors National Association. c. NFPA 92A: Recommended Practice for Smoke-Control Systems. d. NFPA 92 B: Guide for Smoke Management Systems in Malls, Atria, and Large Areas.

4. Fire Fighting System a. NFPA 13- Standard for the Installation of Sprinkler Systems. b. NFPA 14- Standard for the Installation of Standpipe, Private Hydrant, and Hose Systems. c. NFPA 10: Standard for Portable Fire Extinguishers. d. NFPA 20- Standard for the Installation of Stationary Pumps for Fire Protection. e. NFPA 2001: Standard on Clean Agent Fire Extinguishing Systems. 5. Fuel System: a. UPC: Uniform Plumbing Code, Chapter12, Fuel Piping. b. NFPA 30- Flammable and Combustible Liquids Code.

DVR 251011/109

P a g e | 204 / 292

B.

Electrical 1. Grounding & Lightning Protection System a. NFPA 780. Installation of Lightning Protection Systems. b. TIA/EIA 607-A, Commercial building grounding and bonding requirements for telecommunications. c. BS 7430. Code of practice for earthing. d. BS EN 62305-3, Protection against lightning Part3: Physical damage to structures and life hazard. 2. Normal & Emergency Lighting a. SASO (Draft No. 4520), Code for Lighting Of Indoor Work Places b. IESNA-10th Edition, The Lighting Handbook c. BS 5266, Emergency lighting Part 1: Code of practice for the emergency lighting of premises other than cinemas and certain other specified premises used for entertainment d. BS 5266, Emergency lighting Part 7: Lighting applicationsEmergency lighting. e. CIBSE, Code For Lighting f. CIBSE, Lighting Guide 12: Emergency Lighting Design Guide 3. Power & Low Voltage Distribution a. IEC-60364-5-52, Low-voltage electrical installations: Selection and erection of electrical equipment Wiring systems. b. BS 7671. Requirements for electrical installations. The IEE wiring regulations c. NFPA 70- National Electrical Code d. CIBSE, Guide K. Electricity in Buildings. e. BS EN 60439 Low-voltage switchgear and control gear assemblies f. BS EN 60529. Specification for degrees of protection provided by enclosures g. BS EN 62040. Uninterruptible power systems (UPS) 4. Fire Alarm & Detection a. BS 5839. Fire detection and alarm systems for buildings b. NFPA 72-National Fire Alarm Code c. NFPA 101- Life Safety Code 5. IT Network a. TIA/EIA 568 A Commercial building telecommunications standard b. TIA/EIA 568 B Commercial Building Telecommunications Cabling Standard c. TIA/EIA 569 Commercial building standards for telecommunication pathways and spaces.

DVR 251011/109

P a g e | 205 / 292

VI. Appendices
1. APPENDICES

DVR 251011/109

P a g e | 206 / 292

Appendix A ( Mechanical)

DVR 251011/109

P a g e | 207 / 292

Appendix (A): A.1.

DVR 251011/109

P a g e | 208 / 292

Appendix (A): A.2.

DVR 251011/109

P a g e | 209 / 292

Appendix (A): A.3.

DVR 251011/109

P a g e | 210 / 292

Appendix (A): A.4.

DVR 251011/109

P a g e | 211 / 292

Appendix (A): A.5.

DVR 251011/109

P a g e | 212 / 292

Appendix (A): A.6

DVR 251011/109

P a g e | 213 / 292

Appendix (A): A.7.

DVR 251011/109

P a g e | 214 / 292

Appendix (A): A.8.

DVR 251011/109

P a g e | 215 / 292

Appendix (A): A.9.

DVR 251011/109

P a g e | 216 / 292

Appendix (A): A.10.

DVR 251011/109

P a g e | 217 / 292

Appendix (A): A.11.

DVR 251011/109

P a g e | 218 / 292

Appendix (A): A.12.

DVR 251011/109

P a g e | 219 / 292

DVR 251011/109

P a g e | 220 / 292

Appendix (A): A.13.

DVR 251011/109

P a g e | 221 / 292

Appendix (A): A.14.

DVR 251011/109

P a g e | 222 / 292

Appendix (A): A.15.

DVR 251011/109

P a g e | 223 / 292

Appendix (A): A.16.

DVR 251011/109

P a g e | 224 / 292

Appendix (A): A.17.

DVR 251011/109

P a g e | 225 / 292

Appendix (A): A.18.

DVR 251011/109

P a g e | 226 / 292

DVR 251011/109

P a g e | 227 / 292

Appendix (A): A.19.

DVR 251011/109

P a g e | 228 / 292

Appendix (A): A.20.

DVR 251011/109

P a g e | 229 / 292

Appendix (A): A.21

DVR 251011/109

P a g e | 230 / 292

DVR 251011/109

P a g e | 231 / 292

Appendix (A): A.22.

DVR 251011/109

P a g e | 232 / 292

DVR 251011/109

P a g e | 233 / 292

Appendix (A): A.23

DVR 251011/109

P a g e | 234 / 292

DVR 251011/109

P a g e | 235 / 292

DVR 251011/109

P a g e | 236 / 292

Appendix B (Electrical)

DVR 251011/109

P a g e | 237 / 292

B.1 Reference Standards Cut Sheets

DVR 251011/109

P a g e | 238 / 292

DVR 251011/109

P a g e | 239 / 292

DVR 251011/109

P a g e | 240 / 292

DVR 251011/109

P a g e | 241 / 292

DVR 251011/109

P a g e | 242 / 292

DVR 251011/109

P a g e | 243 / 292

DVR 251011/109

P a g e | 244 / 292

DVR 251011/109

P a g e | 245 / 292

DVR 251011/109

P a g e | 246 / 292

DVR 251011/109

P a g e | 247 / 292

DVR 251011/109

P a g e | 248 / 292

DVR 251011/109

P a g e | 249 / 292

DVR 251011/109

P a g e | 250 / 292

DVR 251011/109

P a g e | 251 / 292

DVR 251011/109

P a g e | 252 / 292

B.2 Calculations

DVR 251011/109

P a g e | 253 / 292

DVR 251011/109

P a g e | 254 / 292

DVR 251011/109

P a g e | 255 / 292

DVR 251011/109

P a g e | 256 / 292

DVR 251011/109

P a g e | 257 / 292

DVR 251011/109

P a g e | 258 / 292

DVR 251011/109

P a g e | 259 / 292

DVR 251011/109

P a g e | 260 / 292

DVR 251011/109

P a g e | 261 / 292

DVR 251011/109

P a g e | 262 / 292

DVR 251011/109

P a g e | 263 / 292

DVR 251011/109

P a g e | 264 / 292

DVR 251011/109

P a g e | 265 / 292

DVR 251011/109

P a g e | 266 / 292

DVR 251011/109

P a g e | 267 / 292

DVR 251011/109

P a g e | 268 / 292

DVR 251011/109

P a g e | 269 / 292

DVR 251011/109

P a g e | 270 / 292

DVR 251011/109

P a g e | 271 / 292

DVR 251011/109

P a g e | 272 / 292

DVR 251011/109

P a g e | 273 / 292

DVR 251011/109

P a g e | 274 / 292

DVR 251011/109

P a g e | 275 / 292

DVR 251011/109

P a g e | 276 / 292

DVR 251011/109

P a g e | 277 / 292

DVR 251011/109

P a g e | 278 / 292

DVR 251011/109

P a g e | 279 / 292

DVR 251011/109

P a g e | 280 / 292

DVR 251011/109

P a g e | 281 / 292

DVR 251011/109

P a g e | 282 / 292

DVR 251011/109

P a g e | 283 / 292

DVR 251011/109

P a g e | 284 / 292

DVR 251011/109

P a g e | 285 / 292

DVR 251011/109

P a g e | 286 / 292

DVR 251011/109

P a g e | 287 / 292

DVR 251011/109

P a g e | 288 / 292

DVR 251011/109

P a g e | 289 / 292

DVR 251011/109

P a g e | 290 / 292

DVR 251011/109

P a g e | 291 / 292

DVR 251011/109

P a g e | 292 / 292

You might also like