HINDUSTAN PETROLEUM CORPORATION LIMITEDADDL ATF-APT TANKAGE PROJECT- BAHADURGARH TERMINAL (TENDER FOR MISCLLANEOUS WORK)

8- NORMS OF CEMENT CONSUMPTION 1.00.00 1.01.00 GENERAL For calculating the requirements of cement in various items of work the following standards shall be adopted. Over the above theoretical quantity of cement, additional allowance upto plus or minus 3% shall also be allowed as certified by the Engineer. For items not covered in this standard, CPWD standards shall be followed or calculated as per uses/requirement in absence of standard norms. Cement required for enabling work and cement required for testing purposes will be taken into account for consumption purpose. However, in no case such quantity should exceed 5% of the total cement used in the work or as certified by the Engineer based on actual observation whichever is less.

1.02.00

2.00.00 MASONRY WORK


Sl.No. 1. 2. 3. 4. Description of Item Random Rubble Masonry in Random Rubble Masonry in Coursed Rubble Masonry in Brick work in Brick work in Half brick work in Half brick work in CM 1:4 CM 1:6 CM 1:6 CM 1:4 CM 1:6 CM 1:3 CM 1:4 Cement requirement 1.255 quintals per cum 0.825 quintals per cum 0.75 quintals per cum 0.950 quintals per cum of BW 0.625 quintals per cum of BW 1.43 quintals per 10 sqm of area 1.06 quintals per 10 sqm of area

3.00.00 PLAIN/REINFORCED CONCRETE


Sl.No. Description of Item Cement requirement

1.

RCC/PCC of nominal mix 1:4:8 complete (excluding finishing with CP)

1.70

quintals per cum of concrete

2.

RCC/PCC of nominal mix 1:3:6 complete (excluding finishing with CP) RCC/PCC of nominal mix

quintals per cum of concrete

3.

8- Norms Of Cement Consumption

Page 1

HINDUSTAN PETROLEUM CORPORATION LIMITEDADDL ATF-APT TANKAGE PROJECT- BAHADURGARH TERMINAL (TENDER FOR MISCLLANEOUS WORK)

1:2:4 complete (excluding finishing with CP) 4. RCC/PCC of nominal mix 1:1.5:3 complete (excluding finishing with CP)

3.18

quintals per cum of concrete

4.00

quintals per cum of concrete

4.00.00 CONTROLLED CONCRETE PLAIN AND REINFORCED


S.No. Description of Item Cement requirement

5.

Concrete grade

(i) M-7.5 (ii)M-10 (i) M-15 (ii) M-15 (i) M-20 (ii) M-20 To be mutually agreed based on mix design to be prepared by contractor & approved by the engineer plus wastage and all incidentals as descided. To be mutually agreed based on mix design to be prepared by contractor and approved by the engineer plus wastage and all incidentals as decided.

6.

Concrete grade

7.

Concrete grade

8.

Concrete grade

(i) M-25 (ii) M-25 (i) M-30 (ii) M-30

9.

Concrete grade

5.00.00
S.No.

FINISHING
Description of Item Cement requirement

1. 2. 3. 4. 5.

6 mm thick C.P. 1:4 12 mm thick C.P. 1:4 12 mm thick C.P. 1:6 15 mm thick C.P. 1:4 15 mm thick C.P. 1:6

0.280 quintal per 0.547 quintal per 0.360 quintal per 0.655 quintal per 0.440 quintal per

10 sqm area 10 sqm area 10 sqm area 10 sqm area 10 sqm area

8- Norms Of Cement Consumption

Page 2

HINDUSTAN PETROLEUM CORPORATION LIMITEDADDL ATF-APT TANKAGE PROJECT- BAHADURGARH TERMINAL (TENDER FOR MISCLLANEOUS WORK)

6.00.00
S.No.

FLOORING
Description of Item Cement requirement

1.

40mm thick (IPS) cement concrete flooring 1:2:4 with 20mm and down stone chips finished with a floating cement of neat cement 1.500 quintal per 10 sqm area

2.

40mm thick (IPS) flooring with base coat 30mm thick 1:2:4 using stone chips 10mm nominal size and 10mm topping coat 1:1 (1 cement : 1 stone chips 3 to 6mm size) with a floating coat of neat cement 2.320 quintal per 10 sqm area

3.

Extra for each additional thickness of 5 mm granolithic layer of 1:2:4 for flooring 0.016 quintal per 10 sqm area

7.00.00
S.No.

MISCELLANEOUS
Description of Item Cement requirement

1.

Grouting with CM 1:2 CM 1:3 7.18 quintal per cum 5.40 quintal per cum

2.

Fixing steel windows with 1:2:4 concrete blocks Cement-sand mortar :1:1 (1 cement : 1 sand) 1:2 (1 cement : 2 sand) 1:3 (1 cement : 3 sand) 1:4 (1 cement : 4 sand) 1:5 (1 cement : 5 sand) 1:6 (1 cement : 6 sand)

0.40 quintal per

10 sqm of area

3. a) b) c) d) e) f)

10.2 quintal per cum 6.8 quintal per cum 5.1 quintal per cum 3.8 quintal per cum 3.1 quintal per cum 2.5 quintal per cum